+ All Categories
Home > Documents > WP9 Presentation

WP9 Presentation

Date post: 03-Jun-2018
Category:
Upload: stephendavis
View: 220 times
Download: 0 times
Share this document with a friend

of 34

Transcript
  • 8/12/2019 WP9 Presentation

    1/34

    Quality assurance of PV plants

    connected to the grid

  • 8/12/2019 WP9 Presentation

    2/34

    Today widely extended technical quality assurance practises

    STEP PROCEDURE OBJECTION

    Design:

    Energy yield forecast

    Commercial software Based on non-guaranteed

    information

  • 8/12/2019 WP9 Presentation

    3/34

    ..for definitive simulations, the user is advised to carefully verify the library data

    with the last manufacturers specificationsWe drop out any responsibility about

    the integrity and the exactness of the data and performance including in the

    library..

    Disclaimer at PVSYS Users Guide

    The PVsyst is based on the full I-V curve one-diode model. Required information

    (series and shunt resistance, photo current, saturation current and diode quality

    factor) is mainly obtained from I-V curves database from TISO (Centrale di prova

    peer componente PV, Ticino, Switzarland) and Photon (German PV journal)

    ..These data are key parameters of the model, and should be part of the modules

    specifications in the future..

    A. Mermoud el al, 25thEuropean PVSEC (2010)

    The database was compiled to the best of our knowledge and with the greatest

    possible accuracy. At the same time, PHOTON cannot be held responsible from

    any damage that results from the use of this database.

    Disclaimer at Photon database

  • 8/12/2019 WP9 Presentation

    4/34

    Risk of relying on default settings that prescribe irradiance behaviour in PV*SOL

    and Pvsyst module models

    K. Sauer et al, from Yingly

    PV Performance Modelling Workshop, Sandia Labs (2013)

  • 8/12/2019 WP9 Presentation

    5/34

    Today widely extended technical quality assurance practises

    STEP PROCEDURE OBJECTION

    Design:

    Energy yield forecast

    Commercial software Based on non-guaranteed

    informationProcurement:

    PV module sample

    peak power testing

    Prior to the

    installation, at

    qualified laboratories

    Neither Light Induced

    Degradation nor

    Irradiance and temperature

    behaviour are addressed

  • 8/12/2019 WP9 Presentation

    6/34

    Today widely extended technical quality assurance practises

    STEP PROCEDURE OBJECTION

    Design:

    Energy yield forecast

    Commercial software Based on non-guaranteed

    informationProcurement:

    PV module sample

    testing

    Prior to the

    installation, al

    qualified laboratories

    Light Induced Degradation

    not addressed

    Commissioning:

    PV plant production

    testing

    PRduring a week

    (Often pass criteriaPR 80%)

    -Time-dependence disturbs

    technical qualityqualification

  • 8/12/2019 WP9 Presentation

    7/34

    Weekly PR evolution along the year

    0,850

    0,900

    0,950

    1,000

    1,050

    1,100

    1,150

    0 10 20 30 40 50 60

    PRDC

    PR

    The weekly PR varies up to 10% along the year, and up to 5 % along a

    same month.

    c-Si PV array, Navarra (Spain), 2011

  • 8/12/2019 WP9 Presentation

    8/34

    Today widely extended technical quality assurance practises

    STEP PROCEDURE OBJECTION

    Design:

    Energy yield forecast

    Commercial software Based on non-guaranteed

    informationProcurement:

    PV module sample

    testing

    Prior to the

    installation, al

    qualified laboratories

    Light Induced Degradation

    not addressed

    Commissioning:

    PV plant production

    testing

    PRduring a week -Time-dependence disturb

    technical qualityqualification

    - Detailed characterization of

    real PV plant behaviour not

    addressed

    Infrared inspection Hot-spot detection - Acceptance criteria scarcely

    addressed

    Operation

    PV plant production

    PRduring full years - Ageing measurement not

    addressed

  • 8/12/2019 WP9 Presentation

    9/34

    IEC 62446:

    Grid connected PV systemsMinimum requirements for system

    documentation, commissioning tests and inspection

    7.2.2.2 IR test resultsModule hot spots

    Module temperature should be relatively uniform, with non areas of significant

    temperature difference. However, it is to be expected than the module will be hotter

    around the junction box compared to the rest as the heat is not conducted as well tothe surrounding environment. It is also normal for the PV modules to see a

    temperature gradient at the edges and supports.

    A hot spot elsewhere in a module usually indicates an electric problem, possibly series

    resistance, shunt resistance or cell mismatch. In any case investigate the performance

    of all modules that show significant hot spot(s). Visual inspection may show signs ofoverheating, for example a brown or discoloured area.

  • 8/12/2019 WP9 Presentation

    10/34

    Today widely extended technical quality assurance practises

    STEP PROCEDURE OBJECTION

    Design:

    Energy yield forecast

    Commercial software Based on non-guaranteed

    informationProcurement:

    PV module sample

    testing

    Prior to the

    installation, al

    qualified laboratories

    Light Induced Degradation

    not addressed

    Commissioning:

    PV plant production

    testing

    PRduring a week -Time-dependence disturb

    technical qualityqualification

    - Detailed characterization of

    real PV plant behaviour not

    addressed

    Infrared inspection Hot-spot detection - Acceptance criteria scarcely

    addressed

    Operation

    PV plant production

    PRduring full years - Ageing measurement not

    addressed

  • 8/12/2019 WP9 Presentation

    11/34

    SUMMARY:

    Energy production of current large PV plants seems to satisfy investors

    expectation

    Nevertheless, Technical Quality Assurance procedures can be improved in

    order to:

    Clarify the rules for endorsement of responsibilities in the event of

    problems (real production below expectation, hot-spots appearance, etc.)

    Improve the technical soundness and the usefulness of in-field

    commissioning testing

  • 8/12/2019 WP9 Presentation

    12/34

    QA Objective: Tightening real and predicted productions

    Expectation in terms of , both, yearly energy production and degradation rate

    Assumptions:

    Phenomena Procedure Responsible

    Weather evolution (G(0) and TA) Solar database Nobody

    Operation conditions (G(in-plane)

    and TC) evolution

    Transposition models Nobody

    PV plant response P*, INV, loses

    PR, PRSTC

    EPC; PV modules and

    inverter manufacturers

    Commissioning:

    Testing the PV plant response during a few weeks period

    Operation:

    Monthly and yearly verification of PV plant response and

    maintenance procedures

  • 8/12/2019 WP9 Presentation

    13/34

    Modelling the PV plant response

    *

    GPACP

    G

    TC

    =

    , , . .

    - Dealing with the PV plant response requires modelling of= , ,

    - Because associated responsibilities, involved specifications (P*, thermal

    response, etc.) must be agreed with PV manufactures.

    - Current specification practises:

    - Guaranteed: P*, degradation rate in %/year

    - Standard information: NOCT, Thermal coefficients

    - Additional information: I-V graphics

  • 8/12/2019 WP9 Presentation

    14/34

    = , , modelling alternatives

    1- Considering just the MPP

    =

    1

    + .

    + .

    standard data sheet information (IEC 61215 and IEC 61646)

    (a, b,c) a=1, b=0, c=0

    200

    /1000

    (IEC 61215 and IEC 61646)

    granting generality to published values (1)

    Commissioning tests

    2- Considering the full I-V curve

    Adjusting 5 parameters (ISC, VOC, RS, RP and m) to a given I-V curve is not straightforward

    Module to module parameters variation is typically larger than MPP variation

    3Specific energy rating attempts

    Kings model from Sandia Lab

    Power matrix as defined at IEC 618532

    (1) R. Kenny et al, Prog. Photovolt: Rs.Appl. (DOI: 10,1002/pip.2365 (2013)

  • 8/12/2019 WP9 Presentation

    15/34

    Available literature warns about scarce benefits from complexity

    Surprisingly, there doesnt seem to be a need for overly complicated modelling to

    achieve this accuracy for most technologies

    PERFORMANCE final brochure (EPIA, 2009)

    A simplified version of the Kings model, using a single expression for the maximum,

    power point and requiring just 6 empirical coefficients performs as well as the original

    (Huld, T. 2011)

    The authors feeling is that the complexity of the standard [ IEC 618532] is actually not

    beneficial for an accurate energy prediction, as it requires data which is actually

    normally not know and the generation of this.. seems to affect the overall agreement

    more than it would be without this complicated step

    (Jyotirmoy Roy, 2008)

  • 8/12/2019 WP9 Presentation

    16/34

    Experimental comparison of different practical possibilities

    - 6 PV arrays of different technologies (1.9 < P*(kW)

  • 8/12/2019 WP9 Presentation

    17/34

    Weekly energy errors [(ModelledExperimental)/Experimental ], for the c-Si

    PV array, weighted by the daily irradiation and expressed in %.

    DATA SHEET ADDITIONAL EXPERIMENTS

    Full I-V MPP

    MPP

    , 200

    Full I-V MPP

    , ref (1)

    MPP

    , meas.

    W1 0.4 1.85 2.67 -0.08 2.15 1.41W2 -1.69 0.84 1.81 -0.79 1.12 0.28

    W3 -1.78 0.97 2.03 -0.8 1.26 0.32

    W4 3.95 1.89 3.79 -0.64 2.93 1.17

    Year 2.11 1.50 2.64 -0,83 1.86 0.85

    1.42 1.27 1.29 1.07 0.9 0.97

    - PREAL* 1% larger than PNOMINAL*

    - Selected weeks are centred on the equinox (W1 and W3), on the summer solstice

    (W2) and on the winter solstice (W4)

    An MPP model considering just the power temperature coefficient given at

    the data sheet explains up to 97% of the observed variability.

    Considering also the efficiency variation with irradiance reduces uncertainty

    by about 1%

  • 8/12/2019 WP9 Presentation

    18/34

    Yearly energy errors at 12 different commercial Spanish PV plants

    - G and TC given by reference PV modules, MPP model with and 200/1000

    - P* and INVERTERvalues obtained at Commissioning tests

    Nominal power(MW)

    Real yearly Yield(kWh/kW)

    Modelled yearlyyield (kWh/kW)

    Error (%)

    2 2038 2067 1.4

    2.16 2056 2095 1.9

    2.95 2050 2096 2.2

    2 2194 2163 -1.4

    1.5 2074 2032 -2.1

    1.4 1561 1597 2.3

    2.03 2142 2140 -0.1

    11.2 2016 2038 1.1

    2.1 2204 2198 -0.3

    1.9 2320 2279 -1.8

    9.7 2108 2111 0.1

    25.3 1594 1616 1.4

  • 8/12/2019 WP9 Presentation

    19/34

    Daily energy errors at 45.6 kW Amaraleja PV plant

    0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8-5

    0

    5

    10

    15

    20

    KTd

    heoretical-

    easured(

    -6 -4.5 -3 -1.5 0 1.5 3 4.5 6 7.5 90

    5

    10

    15

    20

    25

    Theoretical-Measured (%)

    requency

    Mean: 1.3 %

    STD: 1.9 %

    - G and TC given by 9 reference PV modules, MPP model with

    - P* and INVERTERvalues first obtained at Commissioning tests andperiodically reviewed

  • 8/12/2019 WP9 Presentation

    20/34

    Commissioning testing: Current state of art - 1

    - The simplest possibility rely on the Performance Ratio concept

    - Acceptation , .

    .PRGUARANTEED. (or PR PRGUARANTEED)

    Given by the energy meter Specified at the contract (80%)

    Nominal power Given by the in-plane solar radiation meter

    - PRcalculation requires only Grecords

    - Because it includes time-dependent unavoidable losses, the mere PRis generally

    not adequate for sub-year periods (days, weeks, months ).

  • 8/12/2019 WP9 Presentation

    21/34

    Weekly PR evolution along the year

    0,850

    0,900

    0,950

    1,000

    1,050

    1,100

    1,150

    0 10 20 30 40 50 60

    PRDC

    PR

    The weekly PR varies up to 10% along the year, and up to 5 % along a

    same month.

    c-Si PV array, Navarra (Spain), 2011

  • 8/12/2019 WP9 Presentation

    22/34

    Commissioning testing: Current state of art - 2

    - Time-dependent unavoidable energy loses are removed at the Performance Ratio at

    Standard Test Conditions concept:

    =

    (1)

    - E means energy loses and I extends to all unavoidable phenomena:

    - Thermal (due to TC TC* )- Efficiency variation with irradiance

    - Anomalies: Shading, inverter saturation, PV plant disconnections, etc.

    - PRSTCcalculation requires (additional to G) TC records .and modelling.

    - PV reference modules are recommended to minimize uncertainty

    - Acceptation PRSTC along T PRSTC, GUARANTEED

  • 8/12/2019 WP9 Presentation

    23/34

    Weekly PR and PRSTCevolution along the year - 1

    0,850

    0,900

    0,950

    1,000

    1,050

    1,100

    1,150

    0 10 20 30 40 50 60

    PR

    PRSTC

    PR

    PRSTC

  • 8/12/2019 WP9 Presentation

    24/34

    Commissioning testing: Advances procedures

    - Not only energy production but also PV plant characterization is addressed

    G

    TCPDC PAC

    PREAL* =PNOMINAL* . (1-FG); INV, REAL= INV, NOMINAL.(1-FINV

    - Highly desirable for further careful operation surveillance

    - PV plant in-field characterization requires G, TC, PDCand PACrecordsand modelling

    - PV reference modules and accurate wattmeters are recommended to minimizeuncertainty

  • 8/12/2019 WP9 Presentation

    25/34

    PV reference modules and accurate wattmeters

    I fi ld t ti AC

  • 8/12/2019 WP9 Presentation

    26/34

    In-field testing: AC power response

    21

    PAC,EXPPDC,EXPG, TC

    I fi ld t ti STC f th PV t

  • 8/12/2019 WP9 Presentation

    27/34

    0

    20

    40

    60

    80

    100

    120

    140

    0 200 400 600 800 1.000 1.200

    Gef(W/m2

    )

    PDC

    Gef,

    25C

    W

    PDC= 0,1087 Gef

    R2= 1

    In-field testing: STC power of the PV generator

    *

    CC

    DCefDC

    1

    C25,

    TT

    PGP

    PAC,EXPPDC,EXPG, TC

    ,EXP

  • 8/12/2019 WP9 Presentation

    28/34

    Mean

    ISC*[A] 1240.0 6.4

    VOC*[V] 862.3 5.1

    IM*

    [A] 1114.6 4.2VM

    *[V] 703.4 10.6

    PM, IEC-60891*[W] 784044 11067

    FF* 0.733 0.003

    PM,*[W] 742728 4894

  • 8/12/2019 WP9 Presentation

    29/34

    In-field testing: efficiency of inverters

    0

    10

    20

    30

    40

    50

    60

    70

    80

    90

    100

    0,0 0,1 0,2 0,3 0,4 0,5 0,6 0,7 0,8 0,9 1,0

    pac

    (%)

    Inversor A

    Inversor B

    Inversor C

    Modelo

    Fabricante

    h

    P

    PAC,EXPPDC,EXPG, TC

  • 8/12/2019 WP9 Presentation

    30/34

    Dealing with hot-spots - 1

    Hot-spots threaten PV module lifetime and reduce operation voltage

    THS 5oC

    VOP= 29.5 V

    THS 17.4oC

    VOP= 26.3 V THS 14.3oC; THS 11.8

    oC

    VOP= 22.6 V

  • 8/12/2019 WP9 Presentation

    31/34

    Dealing with hot-spots - 2

    Proposal for contracts:

    - THS 20oC PV module rejection

    - 10oC THS< 20oC and V > 20%

  • 8/12/2019 WP9 Presentation

    32/34

    CONCLUSIONS

    - c-SI PV array response is properly described by a simple model considering

    just the maximum power point and the power temperature coefficient

    - The power temperature coefficient must be included at the guarantees

    provided by the PV module manufacturers

    - In-field commissioning testing must preferably deal with PRSTC(over the

    mere PR). That requires measuring Gand TC and modelling unavoidable

    loses

    - Commissioning testing can also include the characterization of the

    effective behaviour of the PV plant. That requires measuring G,TC , PDCand

    PAC.

    - Reference PV modules are preferred for measuring, both, Gand TC

    - Proposed rejection criteria for PV module with hot-spots:

    - Temperature differences larger than 20oC

    - Temperature differences between 10oC and 20oC, and voltage

    operation loses larger than 20%

  • 8/12/2019 WP9 Presentation

    33/34

  • 8/12/2019 WP9 Presentation

    34/34


Recommended