    Project DefinitionProject Name:Blue Zuma project for greatest X-Games scooter of this generation.

    Project Scope Statement

    Project Objective:creation of one of the greatest scooters of this generation to construct a cutting -edge Xgames razor scooter to make products for the benefit of children everywhere within 250days by 2/1/2008 at cost for the project is only $ 1,265,556.20 and it is also estimated thatthe project will increase revenue for the company by 10-12%.

    Deliverables: Razor Scooter Patent on Razor Scooter design Production facility and equipment Develop a project Plan. in agreement on the Scope of the project. Requires assembly and materials must meet current safety standards and

    technical plans to provide for specified X-Games equipment .

    Milestones: discussing that finalized the design we cannot move forward by 1 December 2007

    Technical Requirements: Assembly and materials must meet current safety standards Technical plans to provide for specified X-Games equipment (For example, gyro

    bars to allow for full rotation of the handle bars without brake line interference.) Adjustable shocks to handle different heights and load restrictions Provide optional performance upgrade kits for the engine

    Limits and Exclusions: Budget only $ 1,265,556.20 Project team works eight hour days (Monday through Friday) Holiday scheduled with customer. The project will only take duration of 250 days. That the project will increase revenue for the company by 10-12%. Materials must meet current safety standards and technical plans.

    Customer Reviews:

    Project manager(me) review with customer(Robin Lane).

  • 7/30/2019 zuma-part1-^solutions+(1).docx

    2/12

    Priority Matrix:

    Time Performance Cost

    constrain

    Enhance

    Accept

    ZUMA PROJECT COMPUTER EXERCISE

    Part 1:

    STEP 1:

    STEP 2:

    STEP 3:

  • 7/30/2019 zuma-part1-^solutions+(1).docx

    3/12

  • 7/30/2019 zuma-part1-^solutions+(1).docx

    4/12

    STEP 4:

    Q1:When is the project estimated to be completed? How long wil l the proj ect take?The project esimated to be completed at 22/12/08.The project take 250 days

    Q2:What is the cri tical path for the project?The critical path for the project is:

    2,3,5,8,9,10,12,13,14Market Analysis + Product Design + Product Design Selection + Detailed ProductDesign + Test Prototype + Finalize Product Design + Order Production Equipment +Install Production Equipment + Celebration

  • 7/30/2019 zuma-part1-^solutions+(1).docx

    5/12

    STEP 5:

    STEP 6:

  • 7/30/2019 zuma-part1-^solutions+(1).docx

    6/12

    Q3 : What activi ty has the greatest amount of slack?

    Detailed Marketing Plan has 159 days of free slack

    Q4: How sensitive is thi s network?

    When project have sensitive its mean project has more than one critical path. Thenetwork is not very sensitive, there is only one critical path.

    Q5: I dentif y 2 sensible milestones and explain your choices?

    Milestones are appropriate checkpoints that provide an indication of progress on theproject. About Zuma's project the milestones are:Marketing analysisits the firstactivity the project have to start with it before do any other activity , and Product designselection most of the project activates depend on it.

    Q6: What are advantages of displaying the schedule as a network versus a Gantt

    chart?

    Network schedules more clearly exemplify the relationship between different activitiesand the critical path. Gantt chartsare easy to understand and provide a clear overview ofthe project schedule according to calendar dates.

  • 7/30/2019 zuma-part1-^solutions+(1).docx

    7/12

    A Gantt chart :

  • 7/30/2019 zuma-part1-^solutions+(1).docx

    8/12

  • 7/30/2019 zuma-part1-^solutions+(1).docx

    9/12

    A network digram :

  • 7/30/2019 zuma-part1-^solutions+(1).docx

    10/12

  • 7/30/2019 zuma-part1-^solutions+(1).docx

    11/12

  • 7/30/2019 zuma-part1-^solutions+(1).docx

    12/12

    Schedule table reporting ES,LS,EF,LF, and Slack for

    each activity?

    Acti

    vities

    Early

    start

    Late start Early

    finish

    Late

    finish

    Free slack

    1

    2 0 25 0 25 0

    3 25 65 25 65 0

    4 25 45 45 65 20

    5 65 75 65 75 0

    6 75 90 234 249 159

    7 75 105 105 135 30

    8 75 125 75 125 0

    9 125 135 125 135 0

    10 135 160 135 160 0

    11 160 167 187 194 27

    12 160 174 160 174 0

    13 214 249 214 249 0

    14 249 250 249 250 0