Date post: | 09-May-2023 |
Category: |
Documents |
Upload: | khangminh22 |
View: | 1 times |
Download: | 0 times |
Table 1: Comments during TOR Review Meeting on 19 September 2018
No Comment Comment by
Response from Project Proponent / Technology Provider / Environmental Consultant
1. To review and update Dioxin & Furan Control description in the TOR–control temperature, dosing of activated carbon.
DOE Putrajaya
Revision made to Table 15 in the revised ESI and Table 7 in the revised TOR. Continuous operation creating steady state conditions, ensuring complete combustion leading to complete destruction of dioxins and furans (dioxins can completely be eliminated with a residence time of 2 seconds at 1000°C and oxygen level of min 10% is thoroughly distributed). Dosing of Activated Carbon is to catch any remaining dioxin and furan.
2. To confirm the calculation of stack height – 21 m was done by BIC?
DOE Putrajaya
Yes. Stack calculation was done by BIC.
3. Include Data from previous EIA, on-going monitoring and compare with EIA baseline for this Project
DOE Putrajaya
Secondary data will be referred to during EIA preparation.
4. Safety – review records of incidents / spillages, 3rd party audit report
DOSH Review will done and included in the EIA Report.
5. IETS- sludge (SW 204) to be incinerated and the SW code to be included in the SW list in the TOR and EIA
DOE Putrajaya
SW204 has been included in the SW list in the revised TOR.
6. To include good housekeeping – 5S and EMT
DOE Putrajaya
These measures will be included in the EMP section in the EIA Report.
7. To replace’ upgrading’ word in the Project title with ‘New Installation’
DOE Putrajaya
Project title has been revised.
8. Consider co-processing if possible – reutilisation of ash. Co-processing is a new Policy for SW.
DOE Putrajaya
Medivest will consider to co-operate with Amita KUB-Berjaya Kitar Semula Sdn Bhd (AKBK) or other licensed premises, to make bottom ash as an alternative raw material in cement industry. Discussion has been initiated with AKBK. AKBK needs to conduct laboratory testing and analysis on Medivest’s bottom ash sample to determine the level of certain parameters such as chlorine to ensure the bottom ash has acceptable composition as raw material for cement production.
9. To provide incinerator design year not life span
DOE Putrajaya
Design life span of the incinerator is 20 years.
10. Foreign worker control. To apply permit for foreigner construction worker.
MITI Noted. Will be included as mitigation measures in the EIA Report.
11. 18 comments by MOH during TOR meeting on 30 July 2016 for previous submission to be addressed accordingly. A copy of the comments will be forwarded to DOE Putrajaya
MOH Noted. Please refer to feedbacks in Table 2 below.
12. 5 additional waste code proposed should comply with regulation i.e. proposal of method for residue disposal, landfill or co-processing
DOE Putrajaya- BB
Noted by the Project Proponent.
No Comment Comment by
Response from Project Proponent / Technology Provider / Environmental Consultant
13. Competent person for IETS, bag filter, scrubber
DOE Putrajaya-BB
Noted by the Project Proponent.
14. CEMS to follow guideline DOE Putrajaya-BB
Noted by the Project Proponent.
15. To provide details on temporary storage for new scheduled waste
DOE Melaka The new scheduled wastes will be temporary stored at the third compartment at the Scheduled Waste Storage area.
16. IETS- to include biohazard indicator parameters –bacteria / virus
DOE Melaka Disinfectant sanitizer used in the washing activity is anticipated to be able to be effective on a broad range of micro-organisms. Information about this disinfectant sanitizer will be shared with the IETS Consultant in order to determine the requirement to include biohazard parameters.
17. Socio-economic information of the surrounding to be included.
DOE Melaka Socio-economic information will be included in the EIA Report. See revised section 5.3.1 in the revised ESI and revised TOR.
18. Management of bottom ash is not defined in the TOR
DOE Melaka Information on bottom ash management has been included in the revised ESI (section 2.8.2.7) and revised TOR (section 3.7.2.7).
19. Mass balance is not tally. DOE Melaka Revised mass balance is appended as Figure 4 in the revised TOR and Figure 6 in the ESI.
20. Management of fluff (SW501) generated from treatment using the microwaves.
DOE Putrajaya
During incinerator shutdown events, healthcare wastes at the Project site will be treated using the two microwave machines available on-site. SW 501 which consist of fluff will be generated as residues from the activity. Based on Clause No. 5.1 in the Jadual Pematuhan (ref. no. JPBT/KPLT/18/004989) for the microwave operation, these residues (SW 501) shall be sent for disposal at a secured landfill, within 24 hours or may be required to be treated by incineration process. However, since the microwaves machines will only be in operation during incinerator shut down events, SW 501 will not be able to be treated via incineration process at the Project site as the fluff need to be treated within 24 hours. Furthermore, MSB is not able to store the residue for long period i.e., during the incinerator shutdown. MSB will arrange transportation to deliver the residue to a licensed premise, within 24 hours. Management of SW501 will be further discussed in the EIA Report.
21. Report Display for public review to be carried out.
DOE Putrajaya
Noted by all.
Table 2: Comments from NEHAP, MOH during TOR Engagement Meeting on 30 July 2018
No. Comments from NEHAP, MOH Remarks by Medivest / Chemsain during the Meeting
1. Collection of healthcare waste from private sectors must obtain prior approval from Bahagian Perolehan.
Medivest acknowledged the requirement to follow the stipulated procedures and requirement from MOH.
In future planning, after the EIA been approved and the new incinerator is in operation, application for collection of healthcare waste will be done accordingly.
2. Back-up plan in case of incinerator shut down.
Two existing microwave units will be in operation during incinerator shut down. Total capacity is 15 MT.
Storage area (cold room) with capacity of 90 MT.
Sending clinical waste to other licensed premises for treatment, if necessary.
3. To clarify estimated collection of healthcare waste from private sectors out of the total 20 MT
Estimated collection of healthcare waste from private sectors is 5 MT. Priority of collection will be from MOH premises.
4. IETS system is not elaborated in TOR. At the moment the requirement to install IETS is being reviewed.
Based on recent engagement with Director General of Environment, the advice is to install close loop cycle whereby bins and trucks washing waters to be channelled back to the incinerator.
5. Is the Air Pollution Control (APC) adequate? The APC has been used in other incinerator systems and the incinerator of similar design by the same Technology Provider is in operation at Telok Panglima Garang.
Emission data from Radicare’s incinerator plant at Telok Panglima Garang will be gathered for reference to see the efficiency of the APC.
6. To describe the location of existing components.
Details of existing components will be further described in the EIA including the location based on lot numbers.
7. Community engagement should be carried out to gauge communities’ perception towards the project and primary health data.
Since the Project is replacing the old incinerator with a new improved technology, requirement to carry out engagement with the surrounding communities and land users is to be revisited as it may deemed not necessary.
Usual practice is to conduct health survey together with social survey. If health survey is to be carried out independently, it will require additional cost. Expected respondents will be between 100-200 individuals.
No. Comments from NEHAP, MOH Remarks by Medivest / Chemsain during the Meeting
8. To include list of surrounding industries to ensure compatibility. To highlight if there is any food industry nearby.
Kawasan Perindustrian Bukit Rambai mainly consist of light, medium and heavy industries. However, land use survey data will be reassessed to check if there is any food industry nearby.
As included in the TOR, list of surrounding industries within 5 km radius will be included in land use section.
9. Timing of baseline sampling to consider the two monsoon winds seasons, the Southwest Monsoon from April to September, and the Northeast Monsoon from October to March.
Noted. 1st baseline was carried out in June 2018. Attempt for 2nd baseline monitoring during the Northeast Monsoon.
10. To include study on children in the HIA study.
The HIA study will be based on the HIA Guideline, however this study will be considered.
11. PM2.5 to be included in the HIA study. PM2.5 will be included in HIA study.
12. To include other hazard parameters based on Radicare’s emission monitoring.
Will check Radicare’s emission monitoring parameters. Usually the parameters are as listed in the Environmental Quality (Clean Air) Regulations 2014.
13. To include storage hazards management Will be considered in Quantitative Risk Assessment (QRA) study.
14. To include vector free setting. Mitigation measures for vector control will be included in the EIA,
15. To include information on management of storage area.
Description on the management of storage area including the scheduled waste bins arrangement will be provided in the EIA.
The current practice at Medivest facility is to ensure the bins to be managed based on 1st in 1st out order.
16. To include in the EIA the overall process description including from storage area to incinerator plant.
Details will be provided in the EIA report.
17. Any possibility to include health data from private sectors? Or from Statistics Department?
Application can be made but the private sectors usually do not keep disease database, only patient records.
18. To include land uses along Sg Ayer Salak and the river usage.
Study will be carried out and details will be provided.
MEDIVEST SDN BHD
Reference: CK/EV803/8026/18 TOR (Revision 1)
Date: October 2018
Prepared by:
Chemsain Konsultant Sdn Bhd (130904-U) No. 41, 1st Floor, Jalan USJ 10/1D, 47630 UEP Subang Jaya, Selangor, Malaysia Tel: +603-56370163 Fax: +603-56370385
TERMS OF REFERENCE (TOR)
ENVIRONMENTAL IMPACT ASSESSMENT
FOR
PROPOSED NEW INSTALLATION OF THERMAL TREATMENT
FACILITY FOR CENTRE OF HEALTHCARE WASTE TREATMENT
PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33,
JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT RAMBAI,
FASA 4C,MUKIM TANJUNG MINYAK, MELAKA
Second Schedule
DOCUMENT INFORMATION
Project Code: CK/EV803/8026/18 TOR
Client: MEDIVEST SDN BHD
Project Title: PROPOSED NEW INSTALLATION FOR CENTRE OF HEALTHCARE WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT RAMBAI, FASA 4C,MUKIM TANJUNG MINYAK, MELAKA
Document Name: TERMS OF REFERENCE (TOR)
DOCUMENT REVISION HISTORY
Revision No
Revision Date
Description Prepared By Checked By Approved By
0 16/07/18 For issuance Mazura Murat Marina Roland Nawe
TF
1 25/10/18 Revision Mazura Murat Marina Roland Nawe
TF
TERMS OF REFERENCE (TOR)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF HEALTHCARE
WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT RAMBAI, FASA 4C,
MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd TOC i
CK/EV803/8026/18 TOR Revision No.: 1 Revision Date: October 2018
TABLE OF CONTENTS
1 INTRODUCTION .................................................................................................................................. 1
2 PROJECT PROPONENT AND EIA CONSULTANT .......................................................................... 1
3 SCOPE OF PROJECT ......................................................................................................................... 5
3.1 THE PROJECT BACKGROUND ............................................................................................................ 5
3.2 LEGISLATIVE REQUIREMENT ............................................................................................................. 6
3.3 PROJECT LOCATION ......................................................................................................................... 6
3.4 PROJECT CONCEPT ......................................................................................................................... 7
3.5 PROJECT COMPONENTS ................................................................................................................... 8
3.5.1 Former Incinerator Plant ........................................................................................................ 8
3.5.2 Existing Components ............................................................................................................. 8
3.5.2.1 Healthcare Waste Reception Area ............................................................................................... 8
3.5.2.2 Healthcare Waste Storage (Cold Room) ..................................................................................... 8
3.5.2.3 Microwave Machines ................................................................................................................... 8
3.5.2.4 Infrastructures and Utilities .......................................................................................................... 9
3.5.2.4.1 Water Supply ............................................................................................................................................. 9
3.5.2.4.2 Electricity ................................................................................................................................................... 9
3.5.2.4.3 Internet Network......................................................................................................................................... 9
3.5.2.4.4 Storm Water Drainage System ................................................................................................................... 9
3.5.2.4.5 Other Facilities ........................................................................................................................................... 9
3.5.3 Upcoming Components.......................................................................................................... 9
3.5.3.1 Incinerator Plant ........................................................................................................................... 9
3.5.3.2 Truck and Bin Washing Area ..................................................................................................... 11
3.5.3.3 Industrial Effluent Treatment System ......................................................................................... 11
3.6 DESIGN CRITERIA OF THE INCINERATOR ......................................................................................... 11
3.6.1 Key Design Parameters ....................................................................................................... 11
3.7 PROCESS DESCRIPTION ................................................................................................................. 14
3.7.1 Handling of Healthcare Wastes at Source (On-Site Handling) ............................................ 14
3.7.1.1 Transportation of Healthcare Wastes to Project Site ................................................................. 17
3.7.2 Handling of Healthcare Wastes at Project Site (Off-site Handling) ..................................... 18
3.7.2.1 Incineration Process .................................................................................................................. 18
3.7.2.2 Gas Cooling ............................................................................................................................... 19
3.7.2.3 Air Pollution Control System ...................................................................................................... 19
3.7.2.4 Emission Monitoring .................................................................................................................. 19
3.7.2.5 Incinerator Plant Control System ............................................................................................... 20
3.7.2.6 Incinerator Plant Maintenance ................................................................................................... 20
3.7.2.7 Management of Bottom Ash and Fly Ash (SW 406) .................................................................. 20
3.7.2.8 Management of Fluff (SW 501) .................................................................................................. 21
3.7.2.9 Healthcare Waste Storage ......................................................................................................... 21
3.7.2.10 Cleansing and Disinfection of Wheeled Bins and Trucks ........................................................... 21
3.7.2.11 Incinerator Plant Balances ......................................................................................................... 21
3.8 PROJECT DEVELOPMENT SCHEDULE ............................................................................................... 21
3.9 PROJECT ACTIVITIES ...................................................................................................................... 21
3.9.1 Pre-Construction Stage ........................................................................................................ 21
3.9.2 Construction Stage ............................................................................................................... 22
3.9.3 Operation and Maintenance Stage ...................................................................................... 22
4 ALTERNATIVES CONSIDERATION ................................................................................................ 24
4.1 SITE OPTIONS................................................................................................................................ 24
4.1.1 New Site Option ................................................................................................................... 24
4.1.2 Existing Site Option .............................................................................................................. 24
TERMS OF REFERENCE (TOR)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF HEALTHCARE
WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT RAMBAI, FASA 4C,
MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd TOC ii
CK/EV803/8026/18 TOR Revision No.: 1 Revision Date: October 2018
4.2 TECHNOLOGY OPTIONS .................................................................................................................. 24
4.2.1 Counter Current Rotary Kiln ................................................................................................. 25
4.2.2 Co-Current Rotary Kiln ......................................................................................................... 26
4.3 NO PROJECT OPTIONS ................................................................................................................... 28
5 EIA STUDY GUIDELINES AND APPROACHES ............................................................................. 28
5.1 REVIEW OF GUIDELINES AND ENVIRONMENTAL LEGISLATIONS .......................................................... 28
5.2 REVIEW OF PREVIOUSLY APPROVED EIA REPORTS OR STUDIES ...................................................... 29
5.3 ENGAGEMENT WITH RELEVANT AGENCIES AND LOCAL COMMUNITY ................................................. 29
5.3.1 Socio-economic .................................................................................................................... 30
6 SIGNIFICANT ENVIRONMENTAL IMPACTS TO BE STUDIED ..................................................... 30
6.1 WATER QUALITY ............................................................................................................................ 32
6.1.1 Study Boundaries ................................................................................................................. 32
6.1.2 Assessment Standards ........................................................................................................ 33
6.1.3 Description of Modelling Tools and Assessment Methodologies ........................................ 34
6.1.4 Possible Mitigation Measures .............................................................................................. 34
6.2 AIR QUALITY .................................................................................................................................. 34
6.2.1 Study Boundaries ................................................................................................................. 35
6.2.2 Assessment Standards ........................................................................................................ 36
6.2.3 Description of Modelling Tools and Assessment Methodologies ........................................ 36
6.2.4 Possible Mitigation Measures .............................................................................................. 37
6.3 WASTE MANAGEMENT .................................................................................................................... 37
6.3.1 Study Boundaries ................................................................................................................. 38
6.3.2 Assessment Standards ........................................................................................................ 38
6.3.3 Description of modelling tools and assessment methodologies .......................................... 38
6.3.4 Possible Mitigation Measures .............................................................................................. 38
6.4 NOISE ........................................................................................................................................... 38
6.4.1 Study Boundaries ................................................................................................................. 38
6.4.2 Assessment Standards ........................................................................................................ 39
6.4.3 Description of Modelling Tools and Assessment Methodologies ........................................ 39
6.4.4 Possible Mitigation Measures .............................................................................................. 39
6.5 HEALTH IMPACT ASSESSMENT ........................................................................................................ 40
6.5.1 Study Boundaries ................................................................................................................. 40
6.5.2 Assessment Standards ........................................................................................................ 40
6.5.3 Description of Modelling Tools and Assessment Methodologies ........................................ 40
6.5.4 Possible Mitigation Measures .............................................................................................. 41
6.6 QUANTITATIVE RISK ASSESSMENT .................................................................................................. 41
6.6.1 Study Boundaries ................................................................................................................. 41
6.6.2 Assessment Standards ........................................................................................................ 42
6.6.3 Description of Modelling Tools and Assessment Methodologies ........................................ 42
6.6.4 Possible Mitigation Measures .............................................................................................. 43
7 PROJECT TIMETABLE..................................................................................................................... 43
8 PROJECT ASSESSMENT TIMELINE .............................................................................................. 43
9 CONSIDERATION OF CONCURRENT PROJECTS ........................................................................ 43
TERMS OF REFERENCE (TOR)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF HEALTHCARE
WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT RAMBAI, FASA 4C,
MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd TOC iii
CK/EV803/8026/18 TOR Revision No.: 1 Revision Date: October 2018
LIST OF TABLES
Table 1: List of EIA Team Member .................................................................................................................2
Table 2: Approximate Coordinates of the Existing Centre of Healthcare Wastes ..........................................6
Table 3: Components of Incinerator Plant ................................................................................................... 10
Table 4: Incinerator Operating Standards ................................................................................................... 12
Table 5: Emission Standards –European Union and Malaysia ................................................................... 12
Table 6: Typical Medical Waste Chemical Composition ............................................................................. 13
Table 7: Summary of General Technical Characteristic of the Incinerator ................................................. 13
Table 8: Healthcare Wastes Characteristics ............................................................................................... 15
Table 9: Proximate Analysis of Clinical Waste ............................................................................................ 15
Table 10: Ultimate Analysis of Clinical Waste ............................................................................................. 15
Table 11: Healthcare Wastes Collection from Waste Generators ............................................................... 16
Table 12 : Environmental Sensitive Areas (ESA) – Settlement .................................................................. 30
Table 13: Anticipated Significant Environmental Impacts ........................................................................... 31
Table 14: Proposed Baseline Water Quality Locations ............................................................................... 33
Table 15: Proposed Water Quality Parameters ........................................................................................... 33
Table 16: Proposed Baseline Ambient Air Quality Sampling Locations ...................................................... 35
Table 17: Proposed Test Parameters for Ambient Air Quality .................................................................... 36
Table 18: Anticipated Waste from Project ................................................................................................... 37
Table 19: Proposed Baseline Noise Measurement Locations .................................................................... 39
TERMS OF REFERENCE (TOR)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF HEALTHCARE
WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT RAMBAI, FASA 4C,
MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd TOC iv
CK/EV803/8026/18 TOR Revision No.: 1 Revision Date: October 2018
LIST OF FIGURES
Figure 1: Project Location Map
Figure 2: Project Layout
Figure 3: Simplified Schematic Diagram
Figure 4: Mass Balance
Figure 5: Organisation Chart
Figure 6: Counter Current Rotary Kiln
Figure 7: Co-Current Rotary Kiln
Figure 8: Environmental Sensitive Areas
Figure 9: Baseline Sampling Locations
Figure 10: Proposed EIA Study Schedule
APPENDICES
Appendix A Environmental Scoping Information (ESI)
TERMS OF REFERENCE (TOR)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF
HEALTHCARE WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT
RAMBAI, FASA 4C, MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd Page 1
CK/EV803/8026/18 TOR Revision No.: 1 Revision Date: October 2018
1 INTRODUCTION
The purpose of this Terms of Reference (TOR) is to outline the scope of Environmental Impact
Assessment (EIA) study that Chemsain Konsultant Sdn Bhd (Chemsain) will conduct for PROPOSED
NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF HEALTHCARE
WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37,
KAWASAN PERINDUSTRIAN BUKIT RAMBAI, FASA 4C, MUKIM TANJUNG MINYAK, MELAKA
(“the Project”). This is to ensure that the study could fulfil the Department of Environment’s (DOE) Environmental Impact Assessment (EIA) Guidelines 2016.
2 PROJECT PROPONENT AND EIA CONSULTANT
The Project Proponent for this Project is Medivest Sdn Bhd (MSB). MSB has appointed Chemsain
Konsultant Sdn Bhd (Chemsain) to conduct the EIA study for this Project. Corresponding details of MSB
and Chemsain are as follows:
Project Proponent : Medivest Sdn Bhd (224192-H)
Address : Suite 13.01 Penthouse, Wisma E & C
No. 2, Lorong Dungun Kiri
Damansara Heights
50490 Kuala Lumpur
Contact person : Mr Salleh bin Tahir (CEO)
Telephone : +603 209 21000 ext 804
Fax : +603 209 25000
Email : [email protected]
EIA Consultant : Chemsain Konsultant Sdn Bhd (130904-U)
Address : No. 41, 1st Floor, Jalan USJ 10/1D,
UEP Subang Jaya, 47620 Subang Jaya
Selangor
Contact person : Ms Marina Roland Nawe (EIA Team Leader)
Telephone : +603 5637 0163
Fax : +603 5637 0385
Email : [email protected]
The EIA study team members are listed on Table 1.
TERMS OF REFERENCE (TOR)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF HEALTHCARE WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32
& 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT RAMBAI, FASA 4C, MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd Page 2
CK/EV803/8026/18 TOR Revision No.: 1 Revision Date: October 2018
Table 1: List of EIA Team Member
Name Qualification Registration With DOE Experience Proposed Study Area
Signature
Category Area/Field ID. No. Validity Date
A. EIA Study Team Leader
Marina Roland Nawe
M. Environment
B. Sc (Biology)
EIA Consultant
Ecological Studies
Fisheries
General Environmental Management
C 0059 30 April 2021
Marina has over 19 years experience in various EIA, EMP, environmental monitoring, and other environmental studies for various projects all over Malaysia. She is a registered EIA consultant with the Department of Environment (DOE).
EIA Team Leader
EMP
B. EIA Team Member
Ir. Brian Chong Sin Hian
M. Sc (Environment)
B. Sc (Civil Engineering)
EIA Consultant
Wastewater Management
Solid Waste Management
Scheduled Waste Management
Hydrology
C 0089 30 June 2019 Ir Brian has over 25 years of professional environmental consultancy and engineering experience in environmental impact assessment and planning, wastewater and solid waste management and feasibility / masterplan studies.
He is a registered professional engineer as well as a registered EIA consultant with the Department of Environment (DOE). He is the team leader for most the environmental assessment studies conducted by Chemsain with more than twenty (25) detailed environmental impact assessment (DEIA) report.
Hydrology
Waste Management
Wastewater Management
LDP2M2
TERMS OF REFERENCE (TOR)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF HEALTHCARE WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32
& 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT RAMBAI, FASA 4C, MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd Page 3
CK/EV803/8026/18 TOR Revision No.: 1 Revision Date: October 2018
Name Qualification Registration With DOE Experience Proposed Study Area
Signature
Category Area/Field ID. No. Validity Date
Lina Chan B. Sc. (Hons) EIA Consultant
Noise
General Environmental Management
C 0098 31 March 2019
Lina has 21 years of professional consultancy. She is involved in various EIA, EMP and other environmental study for studies all over Malaysia. She is a registered EIA consultant with the Department of Environment (DOE) and Natural Resources and Environmental Board (NREB).
Noise
Lim Sze Fook B. Sc (Hons) Physics
EIA Consultant
Air Quality Meteorology
C 0282 31 July 2019 Lim has more than 24 years of experience in air pollution modelling for EIA studies. He is a registered EIA consultant with the Department of Environment (DOE), Natural Resources and Environmental Board (NREB) and Sabah Environmental Protection Department (EPD).
Air Quality Modelling
Adnan Yusop Ali
B. Eng. (Chemical)
Subject Consultant
Quantitative Risk Assessment
SS 0066 31 May 2020 Adnan has more than 17 years of experience in quantitative risk assessment for EIA studies. He is a registered EIA consultant with the Department of Environment (DOE) and Natural Resources and Environmental Board (NREB). He is also a Chemical Health Risk Assessor registered with DOSH.
Quantitative Risk Assessment
TERMS OF REFERENCE (TOR)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF HEALTHCARE WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32
& 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT RAMBAI, FASA 4C, MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd Page 4
CK/EV803/8026/18 TOR Revision No.: 1 Revision Date: October 2018
Name Qualification Registration With DOE Experience Proposed Study Area
Signature
Category Area/Field ID. No. Validity Date
Prof. Dr. Jamal Hisham Hashim
PhD (Env. Health Science)
MSc (Public Health)
B.A (Biology & Env. Studies)
EIA Consultant and Subject Consultant
Health Impact Assessment
CS 0483 31 January 2021
Prof Dr Jamal has more than 24 years of experience in teaching, research and consultancy in the discipline of environmental health; specializing in environmental chemistry, environmental impact assessment, exposure and risk assessment, and environmental management.. He is a registered EIA consultant with the Department of Environment (DOE). He is also experienced as EIA review panel for DOE.
Health Impact Assessment
Ir. Md Zahar Mohamad
B.Sc (Mechanical Engineering)
EIA Consultant
Air Quality and Odour
Industrial Processes
Solid Waste Management
C0050 31 December 2020
Ir Md Zahar has more than 20 years of professional consultancy experience. He is involved in various EIA, EMP and other environmental study for studies all over Malaysia. He is a registered EIA consultant with the Department of Environment (DOE)
Industrial Processes
Air Pollution Control and Process
TERMS OF REFERENCE (TOR)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF
HEALTHCARE WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT
RAMBAI, FASA 4C, MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd Page 5
CK/EV803/8026/18 TOR Revision No.: 1 Revision Date: October 2018
3 SCOPE OF PROJECT
3.1 THE PROJECT BACKGROUND
Medivest Sdn Bhd (MSB) is one of the concession companies providing Healthcare Waste
Management Services (HWMS) for Ministry of Health Malaysia (“MOH”). The HWMS include storage,
collection, transportation, treatment (microwave system) and disposal of healthcare waste.
MSB intends to install new thermal treatment facility at its existing centre of healthcare waste
treatment plant located at Lot 24, 25, 32 & 33, Jalan PBR 37, Kawasan Perindustrian Bukit Rambai,
Fasa 4C Mukim Tanjung Minyak, Melaka.
The installation works shall include planning, construction, installation and operation of a counter-
current rotary kiln type incinerator with a capacity to treat 20 MT/day of healthcare waste. This
counter-current rotary kiln type incinerator is developed by BIC Systems Asia Pacific Pte Ltd.
The existing plant commenced its operation in 1997 using stepped hearth incineration system and has
ceased the incinerator operation in March 2016. Since the incinerator facility shut down in March 2016,
the incoming clinical wastes is currently treated using microwave system.
To date, the existing centre of healthcare is only treating SW 404 (pathogenic wastes, clinical wastes
or quarantined materials) using two existing microwave machines i.e. Model AMB Ecosteryl
250(licensed since 2016) and Model MDS 2481 (licensed since 2018).
Hence the Project Proponent also plan to treat the following scheduled waste at the upgraded facility:
Scheduled Waste Source
SW 403 – Discarded drugs containing psychotropic
substances or containing substances that are toxic,
harmful, carcinogenic, mutagenic or teratogenic
External (MOH hospitals and laboratory)
SW 409 – Disposed containers, bags or equipment
contaminated with chemicals, pesticides, mineral oil
or scheduled wastes
External (MOH hospitals and laboratory)
Internal
SW 429 – Chemicals that are discarded or off-
specification
MOH hospitals and laboratory
SW 430 – Obsolete laboratory chemicals External (MOH hospitals and laboratory)
Internal
SW 410 – Rags, plastics, paper or filters
contaminated with scheduled wastes
External (MOH hospitals and laboratory)
Internal
TERMS OF REFERENCE (TOR)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF
HEALTHCARE WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT
RAMBAI, FASA 4C, MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd Page 6
CK/EV803/8026/18 TOR Revision No.: 1 Revision Date: October 2018
Scheduled Waste Source
SW 204 – Sludges containing one or several metals
including chromium, copper, nickel, zinc, lead,
cadmium, aluminium, tin, vanadium and berylium
Internal –IETS
When the new incinerator is in operation, the two microwave machines will be on standby mode and
will only be used when the incinerator is shut down.
3.2 LEGISLATIVE REQUIREMENT
Development of the Project which include installation of new thermal treatment facility at the existing
centre of healthcare waste treatment facilities owned by Medivest Sdn Bhd (MSB) has been identified
as a prescribed activity under the Environmental Quality (Prescribed Activities) (Environmental Impact
Assessment) Order 2015 as follows:
Second Schedule – Activity No. 14: Waste Treatment and Disposal
Sub-activity (a): Scheduled waste (i) Construction of thermal treatment plant
In compliance with Section 34A of the Environmental Quality Act, 1974, an EIA report for the Project is
to be prepared for approval from Department of Environment (DOE).
3.3 PROJECT LOCATION
The Project is located at the existing centre of healthcare waste treatment facilities at Lot 24, 25, 32 &
33 within Kawasan Perindustrian Bukit Rambai Fasa 4C, Mukim Tanjung Minyak, Melaka. The total
area of the existing centre is 8, 408 m2 (about 2 acres). Total land area involved for development of
the incinerator plant is 2, 602 m2. The Project location is shown in Figure 1. The Project site is located
about 17 km from the Melaka city centre. The Project site is accessible via Lebuh AMJ/Route 19 –
Lebuh SPA/ Route 33 – Jalan M9 – Jalan PBR 37.
Approximate coordinates of the existing centre of healthcare waste treatment facilities boundaries are
as tabulated in Table 2.
Table 2: Approximate Coordinates of the Existing Centre of Healthcare Wastes
Latitude Longitude Description
2°16’49.17” 102°10’51.27” North Boundary
2°16’44.55” 102°10’54.15” Southeast Boundary
2°16’44.59” 102°10’52.32” South Boundary
2°16’45.83” 102°10’52.22” Middle Boundary
2°16’45.83” 102°10’50.55” West Boundary
THAILAND
KEDAHPulauLangkawi
ALOR SETAR
PERLISKANGAR
PINANGPULAU
TOWN
KELANTAN
KOTA BHARU
TERENGGANU
PERAKTERENGGANU
IPOH
PAHANGKUANTAN
SELANGOR
KUALA LUMPURSHAH ALAM
SEREMBAN
NEGERI
MELAKAJOHOR
JOHORBAHRU
TiomanPulau
SINGAPURA
KUALA
GEORGE
SEMBILAN
CHEMSAIN KONSULTANT SDN. BHD.
LEGEND:
PROJECT
LOCATION
FIGURE 1
TERMS OF REFERENCE (TOR)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF
HEALTHCARE WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT
RAMBAI, FASA 4C, MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd Page 7
CK/EV803/8026/18 TOR Revision No.: 1 Revision Date: October 2018
3.4 PROJECT CONCEPT
As mentioned in Section 3.1, MSB intends to install new thermal treatment facility at its existing centre
of healthcare waste treatment facilities located at Lot 24, 25, 32 & 33, Jalan PBR 37, Kawasan
Perindustrian Bukit Rambai, Fasa 4C Mukim Tanjung Minyak, Melaka.
The upgrading works shall include planning, construction, installation and operation of a counter-
current rotary kiln system type incinerator with a capacity to treat 20 MT/day of healthcare waste. This
counter-current rotary kiln system type incinerator is developed by BIC Systems Asia Pacific Pte Ltd.
The existing plant commenced its operation in 1997 using stepped hearth incineration system and has
ceased the incinerator operation in March 2016. Since the incinerator facility shut down in March 2016,
the incoming clinical wastes is currently treated using microwave system.
To date, the existing centre of healthcare is only treating SW 404 (pathogenic wastes, clinical wastes
or quarantined materials) using two existing microwave machines Model AMB Ecosteryl 250 (licensed
since 2016) and Model MDS 2481 (licensed since 2018).
Hence the Project Proponent also plan to treat the following scheduled waste at the upgraded facility:
Scheduled Waste Source
SW 403 – Discarded drugs containing psychotropic
substances or containing substances that are toxic,
harmful, carcinogenic, mutagenic or teratogenic
External (MOH hospitals and laboratory)
SW 409 – Disposed containers, bags or equipment
contaminated with chemicals, pesticides, mineral oil
or scheduled wastes
External (MOH hospitals and laboratory)
Internal
SW 429 – Chemicals that are discarded or off-
specification
MOH hospitals and laboratory
SW 430 – Obsolete laboratory chemicals External (MOH hospitals and laboratory)
Internal
SW 410 – Rags, plastics, paper or filters
contaminated with scheduled wastes
External (MOH hospitals and laboratory)
Internal
SW 204 – Sludges containing one or several metals
including chromium, copper, nickel, zinc, lead,
cadmium, aluminium, tin, vanadium and berylium
Internal –IETS
TERMS OF REFERENCE (TOR)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF
HEALTHCARE WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT
RAMBAI, FASA 4C, MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd Page 8
CK/EV803/8026/18 TOR Revision No.: 1 Revision Date: October 2018
3.5 PROJECT COMPONENTS
The Project involves planning, construction, installation and operation of an incinerator with a capacity
to treat 20 MT/day of healthcare waste. Generally, the main components of the incinerator plant facility
include waste reception and storage, waste combustion, gas cooling, air pollution control and ash
receiving and storage system, truck and bin washing system and industrial effluent treatment system
(IETS).
Figure 2 shows the layout of the Project components that consist of storage areas (for healthcare
waste, chemicals and ash), plant building (that accommodates the new incinerator area, existing
administration office and existing microwave facilities) and bin washing/ disinfection area. The Project
components are elaborated in the following sub-sections.
3.5.1 Former Incinerator Plant
The existing plant commenced its operation in 1997 using stepped hearth incineration system. During
the operation of the former incinerator plant, there were two incinerator lines equipped with respective
air pollution control systems. Both incinerators, were stepped hearth system, have same exact
specifications and treatment capacity of 7.2 MT/day (300 kg/hr).
MSB has ceased the incinerator operation in March 2016. Abandonment Management Plan was
prepared and submitted to DOE Negeri Melaka in May 2017 and it was approved on 6 June 2017.
Dismantling and removal works were completed on 28 November 2017.
3.5.2 Existing Components
3.5.2.1 Healthcare Waste Reception Area
This area is allocated to house the unloading and weighing of received healthcare waste. It is for temporary
storage before further feeding process in the system.
3.5.2.2 Healthcare Waste Storage (Cold Room)
At the end of the day, untreated healthcare wastes will be stored in the cold storage area before being
processed during the following day. There are six existing cold room stores with a capacity of 15 MT each
(total capacity of 90 MT), temperature of below 6 °C and 8 holding days.
3.5.2.3 Microwave Machines
There are two microwave machines available at the Project site. Details of the machines are
summarised as follows:
i. Model AMB Ecosteryl 250
This microwave machine is from Belgium and has a capacity of 6 MT/day. License for operation
was obtained in 2016.
TERMS OF REFERENCE (TOR)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF
HEALTHCARE WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT
RAMBAI, FASA 4C, MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd Page 9
CK/EV803/8026/18 TOR Revision No.: 1 Revision Date: October 2018
ii. Model MDS 2481
This microwave machine is from the US. It has a capacity of 9 MT/day or 270 MT/month. License
for operation was obtained in May 2018.
3.5.2.4 Infrastructures and Utilities
3.5.2.4.1 Water Supply
Water supply requirement for ancillary facilities is estimated at 250m3/month (average). Since the
Project site is an existing healthcare waste treatment facility, water supply distribution pipe, water
pump house and storm water drainage system are already available at site. Oil sumps, septic tank,
holding tank and sewerline are also already installed at site.
3.5.2.4.2 Electricity
Electricity supply requirement for the incinerator is estimated about 50 kWh. Meanwhile for the
ancillary facilities the electricity requirement is 80 kWh (average)
3.5.2.4.3 Internet Network
The Project site requires internet speed of 4Mbps for computer networking.
3.5.2.4.4 Storm Water Drainage System
There is an existing storm water drainage system around the Project boundary. Storm water within
the Project area will be channelled to existing perimeter drainage system and it will be discharged off-
site to the existing drainage system available within the Kawasan Perindustrian Bukit Rambai, Fasa
4C.
3.5.2.4.5 Other Facilities
Other facilities available at the Project site include main office, workshop, scheduled waste store,
general room and staff room.
3.5.3 Upcoming Components
3.5.3.1 Incinerator Plant
An opened but roofed pad area will accommodate for combustion / incineration process block.
Components of the incinerator plant are summarised in Table 3 below. Component details and
specifications as well as illustration of the components are provided in Section 2.6 of the
Environmental Scoping Information (ESI) (Appendix A).
TERMS OF REFERENCE (TOR)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF
HEALTHCARE WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT
RAMBAI, FASA 4C, MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd Page 10
CK/EV803/8026/18 TOR Revision No.: 1 Revision Date: October 2018
Table 3: Components of Incinerator Plant
Component Description
Waste Feeding System Automated with minimum manual intervention. Skip hoist system comprises of:
a) A hydraulically operated automatic skip hoist mechanism
b) A hydraulically operated automatic skip tilting mechanism
c) A weighing unit
Primary Combustion – Feeding Ram System
The primary combustion comprises of:
a) Feed Hopper
b) Hydraulic Ram
c) A Guillotine Door
Primary Combustion – Incinerator
The incinerator comprises:
a) A Stationary Part
b) A Counter Current Rotary Kiln
c) Kiln rotation CW/CCW
d) A Cylindrical Section With Reduced Diameter For Ash Evacuation
e) A Supporting Frame
f) A Burner
g) A De-Ashing Chamber
Secondary Combustion (Post Combustion)
The post combustion zone comprises of:
h) The Upper Part Of The Stationary Zone
i) Two vertical cylindrical chambers
j) Retractable Burner
Flue Gas Pre-Cooling Consists of a flue gas inlet flange fitted with a butterfly valve operated by a servo motor.
Flue Gas to Thermal Oil Heat Exchanger
Vertical dual pass water (thermal fluid) tube heat exchanger
Thermal Oil Pump Skid Two identical circulation pumps, one main and one back-up with auto switch-over with their respective shut off valves.
Sodium Bicarbonate (NaHCO3) Storing and Injection by Loss-in-Weight
For flue gas treatment. Neutralising reaction time is much (5x) shorter and the reaction itself nearly stoichiometric.
Activated Carbon Storing and Injection by Loss-in-Weight
For dioxin and furan treatment.
Bag House Filter To remove particulates and dust.
Exhaust fan At flue gas system
Emission monitoring equipment
Includes continuous recording and online monitoring system for all the gas elements, as specified by the incinerator emission standards
TERMS OF REFERENCE (TOR)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF
HEALTHCARE WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT
RAMBAI, FASA 4C, MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd Page 11
CK/EV803/8026/18 TOR Revision No.: 1 Revision Date: October 2018
stipulated by NEA
Peripherals a) A hydraulic pack
b) A chimney stack
c) An air compressor assembly
d) Emergency by-pass
e) Fly ash evacuation system
f) Liquids Injection Systems
g) Safety valve (Diluting air inlet)
h) A Plant Automation System - MCC Power Switchboard and PLC Switchboard; Pulpit SCADA PC for User Interfacing
3.5.3.2 Truck and Bin Washing Area
Washing bay will be provided near the weighing area for truck/ bin washing and cleansing upon tipping
of waste and prior to leaving the centre. Waste water from the washing bay will be channelled to a new
Industrial Effluent Treatment System (IETS) for treatment prior discharge.
3.5.3.3 Industrial Effluent Treatment System
The incinerator does not produce any waste water from the incinerator processes. Sources of waste
water are from healthcare waste wheel bins and trucks washing activities. Wheel bins are used for
healthcare wastes collection in healthcare facilities and trucks are used as to transport the collected
healthcare wastes (inside the bins) from healthcare facilities to the Project site. Waste water from the
washing activities are considered to have potential infection risk as the wheel bins and trucks are likely
to be exposed to the healthcare wastes. The amount of waste water is estimated about 1 to 2 m3/day.
The waste water will be channelled to a new Industrial Effluent Treatment System (IETS) that will be
installed within the Project site.
Details of the IETS system will be provided in the EIA report.
3.6 DESIGN CRITERIA OF THE INCINERATOR
3.6.1 Key Design Parameters
The plant is designed according to European Union standards. The key design aims to fulfil typical
regulatory requirements to date, with the key parameters being Destruction Efficiency (DRE %) of
99.9999%, minimum residence time of min. 2 seconds at 1,100 degrees Centigrade in the post
combustion.
TERMS OF REFERENCE (TOR)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF
HEALTHCARE WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT
RAMBAI, FASA 4C, MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd Page 12
CK/EV803/8026/18 TOR Revision No.: 1 Revision Date: October 2018
Table 4: Incinerator Operating Standards
Item Specifications
Destruction efficiency (DRE) 99.9999 %
Primary Combustion Chamber Temperature 850 °C minimum / 1,000 °C maximum
Secondary Combustion Chamber Temperature 1,100 °C minimum / 1,200 °C maximum
Residence Time Minimum 2 seconds
Minimum Oxygen Content 12%-13%
Air / Fuel Ratio 2.5
Source: BIC Systems Asia Pacific Pte Ltd. (2018)
The other key parameter is the conformance to emission standards in Malaysia. The limits are in
Table 5. The EU standard, which is the design standard used by BIC Systems Asia Pacific Pte Ltd is
equally or more stringent than Malaysian standard.
Table 5: Emission Standards –European Union and Malaysia
Parameter EU (Daily)
EU (Hourly)
EU ( 4- Hour)
EU Summary
Malaysia*
mg/m3
Ash / Particulates 5 10 5 100
HF 1
HCl 5 10 5 40
CO 50 100 50 50
NOx 100 200 100 200
SOx 25 50 25 50
Cd 0.05 0.05 0.05
Hg 0.05 0.05 0.05
Pb - -
Heavy Metals 0.5
Dioxin / Furan 0.10 ng/m3 0.10 ng/m3 0.10 ng/m3
Total Organics 5 10 5 10
Note: Environmental Quality (Clean Air) Regulations 2015 (3rd Schedule Regulation 13, Item K: Waste Incinerator in All Sizes.
Source: BIC Systems Asia Pacific Pte Ltd. (2018)
TERMS OF REFERENCE (TOR)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF
HEALTHCARE WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT
RAMBAI, FASA 4C, MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd Page 13
CK/EV803/8026/18 TOR Revision No.: 1 Revision Date: October 2018
The design also takes into account the typical chemical composition of medical waste as shown in
Table 6.
Table 6: Typical Medical Waste Chemical Composition
Element Mass % Mol/kg
C 74.80 0.062
H 7.00 0.070
N 1.00 0.001
S 1.000 0.000
Hg 0.00 0.000
Pb 0.000 0.000
Zn 0.000 0.000
0.000 0.000 0.000
Cl 1.00 0.000
F 0.10 0.000
Br 0.10 0.000
O 5.00 0.003
Ash 10.000 -
Total 100.00 -
Source: BIC Systems Asia Pacific Pte Ltd. (2018)
Summary of design and operational particulars of the incinerator plant are as listed in Table
7. The plant is designed to operate at a capacity of 833 kg/hr where 20 MT/day of healthcare
wastes are expected to be treated.
Table 7: Summary of General Technical Characteristic of the Incinerator
Thermal Capacity 3,750,000 Kcal/hr (15,750 MJ/hr)
Throughput
833 kg/hr (20 MT/day)
(Based on the average calorific value of waste of 4500 kcal/kg (20 MJ/kg)
Life of Plant
10-20 years
(Depends on how well it is maintained)
Process Line 1
Operating Hours 24 hours per day, 7 days per week
Waste storage capacity 90 MT
Incinerator System Counter Current Rotary Kiln
Destruction efficiency (DRE) 99.9999 %
Feeding Loading Skip hoist system
TERMS OF REFERENCE (TOR)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF
HEALTHCARE WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT
RAMBAI, FASA 4C, MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd Page 14
CK/EV803/8026/18 TOR Revision No.: 1 Revision Date: October 2018
Start-up Duration 8 hours to automatically heat up to operating temperature (depending on atmospheric conditions)
Burn period 2-4 hours
Burn Cycle 8 cycles (160 kg per loading)
Residential time 2.3 seconds
Cool Down Period 24 hours
Auxiliary Fuel Diesel - 50 l/hr (for start-up only)
Air Pollution Control System
Heat Removal Heat exchanger: flue gas to thermal oil
Dioxin and Furan Control Continuous operation creating steady state conditions, ensuring complete combustion leading to complete destruction of dioxins and furans (dioxins can completely be eliminated with a residence time of 2 seconds at 1000°C and oxygen level of min 10% is thoroughly distributed)
Dosing of Activated Carbon to catch any remaining dioxin and furan
Dosing of Activated Carbon
Acidic Gas Neutralizer Dosing of Sodium Bicarbonate
Dust Filtration Baghouse: 432 Teflon Felt bags
Parameter of CEMS Conformity with EC and Malaysian emission regulations
Ash Removal Daily
Utilities
Power supply 50 kW/hr (average)
Estimated waste / by product
Fly ash 25 kg/hr
Bottom ash 67 kg/hr
3.7 PROCESS DESCRIPTION
3.7.1 Handling of Healthcare Wastes at Source (On-Site Handling)
SW 404, SW 403, SW 409, SW 429, SW 430 and SW 410 will be collected and transported from the
respective hospitals to the Project site using dedicated trucks. Healthcare wastes characteristics are
listed in Table 8. Clinical wastes analysis are listed in Table 9 and Table 10.
TERMS OF REFERENCE (TOR)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF
HEALTHCARE WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT
RAMBAI, FASA 4C, MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd Page 15
CK/EV803/8026/18 TOR Revision No.: 1 Revision Date: October 2018
Table 8: Healthcare Wastes Characteristics
Material Percentage
P.V.C 3%
Pathological 5%
Plastic other than P.V.C 33%
Paper including waxed paper 30%
Hospital dressing, swab, etc. 10%
Non-combustible including glass, metal, etc. 10%
Obsolete laboratories chemical 5%
Miscellaneous (including flowers, rags, etc.) 5%
Source: Medivest Sdn Bhd. (2018)
Table 9: Proximate Analysis of Clinical Waste
Analysis Range (%) Average (%)
Moisture content 16.9 - 28 21
Ash Content 1.6 - 4.7 3.1
Volatile matter 66.1 - 77.2 72.2
Fixed Carbon 1.2 - 4.3 3.2
Adapted from: Radicare (M) Sdn Bhd. (2012)
Table 10: Ultimate Analysis of Clinical Waste
Component Weight Percentage (%)
Carbon 51.83
Hydrogen 8.63
Oxygen 35.53
Nitrogen 0.17
Sulphur 0.10
Chlorine 0.64
Ash 3.1
Adapted from: Radicare (M) Sdn Bhd. (2012)
Collection and storage of healthcare wastes in CWMS is one of MSB’s responsibilities as the Concession Company. As such, relevant products (i.e. receptacles, plastic bags and on-site
containers) are to be supplied to the hospitals or establishments to contain healthcare wastes.
Segregation of the healthcare wastes is done by MOH’s staff in accordance to Management of Clinical and Related Wastes in Hospital and Health Care Establishments (1993) and Project Operations
Guidelines on Clinical Wastes Management Services (2009) released by the MOH.
TERMS OF REFERENCE (TOR)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF
HEALTHCARE WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT
RAMBAI, FASA 4C, MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd Page 16
CK/EV803/8026/18 TOR Revision No.: 1 Revision Date: October 2018
Healthcare wastes that have been segregated are stored in dedicated containers/ plastic bags before
being sealed and labelled. Once the plastic bags or sharp containers are sealed, it is strictly
prohibited to break the seal. They are handled with care to prevent accidental tears or breaks until the
incineration process, as it may cause health and environmental hazards.
Plastic bags and sharp containers are then transported in wheeled bins to the hospital’s central storage for collection by MSB staff. Collection of healthcare wastes shall be done daily or as
frequently as circumstances demand. Authorised representative of the MOH and MSB staff weights
the healthcare wastes and record the quantities and weights. During the collection of the wheeled
bins containing healthcare wastes, MSB staff shall provide adequate supply of plastic bags, sharp
containers and cleaned receptacles for the collection and on-site storage. Consignment notes are
completed for each collection. Both the MOH’s staff and MSB staff are well-trained and equipped with
personal protective equipment (PPE) during the handling process.
This Project will accommodate healthcare wastes generated from government hospitals and laboratory
in Negeri Sembilan, Melaka and Johor. Estimated quantities of healthcare wastes to be collected and
treated at the Project site are listed in Table 11.
Table 11: Healthcare Wastes Collection from Waste Generators
Source Estimated Load , 2018 (kg/month)
SW 404 SW 403 SW 429 SW 430 SW 409 SW 410
Hospital Tuanku Ja'afar Seremban, Negeri Sembilan
45,731 0 0 0 0 15
Hospital Melaka 63,435 0 0 51,189 0 15
Hospital Sultanah Aminah, Johor Bahru, Johor
52,485 0 0 0 0 20
Hospital Jelebu, Kuala Klawang, Negeri Sembilan
3,552 0 0 6,383 0 0
Hospital Alor Gajah, Melaka 4,983 0 0 0 0 0
Hospital Enche' Besar Hajjah Kalsom, Kluang, Johor
20,444 0 0 0 0 5
Hospital Tuanku Ampuan Najihah, Kuala Pilah, Negeri Sembilan
20,426 0 0 77 0 0
Hospital Sultanah Nora Ismail, Batu Pahat, Johor
24,818 0 0 0 0 5
Hospital Kota Tinggi, Kota Tinggi, Johor
7,033 0 0 0 0 0
Hospital Port Dickson, Negeri Sembilan
5,803 0 0 0 0 0
Hospital Jasin, Melaka 4,044 66 0 3,484 0 0
TERMS OF REFERENCE (TOR)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF
HEALTHCARE WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT
RAMBAI, FASA 4C, MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd Page 17
CK/EV803/8026/18 TOR Revision No.: 1 Revision Date: October 2018
Source Estimated Load , 2018 (kg/month)
SW 404 SW 403 SW 429 SW 430 SW 409 SW 410
Hospital Temenggong Seri Maharaja Tun Ibrahim, Kulai, Johor
4,984 0 0 0 0 0
Hospital Tampin, Negeri Sembilan
3,570 364 0 0 0 0
Hospital Pakar Sultanah Fatimah, Muar, Johor
22,061 0 5,072 0 0 5
Hospital Mersing, Johor 3,001 0 0 0 0 0
Hospital Segamat, Johor 12,915 0 0 0 0 0
Hospital Pontian, Johor 4,530 0 0 0 0 0
Hospital Tangkak, Johor 2,391 0 0 0 0 0
Hospital Permai, Johor Bahru, Johor
7,044 0 0 0 0 0
Makmal Kesihatan Awam Johor Bahru, Tampoi, Johor Bahru
630 0 0 0 20 20
Hospital Sultan Ismail, Johor Bahru, Johor
38,998 0 0 0 0 15
Hospital Jempol, Negeri Sembilan
2,979 31 0 28 0 0
Total 355,857 461 5,702 61,161 20 100
Source: Medivest Sdn Bhd. (2018)
3.7.1.1 Transportation of Healthcare Wastes to Project Site
Six dedicated trucks are allocated for transportation of the healthcare wastes. One of the truck has a
capacity of 16 MT meanwhile the remaining five trucks have a capacity of 18 MT each. It is estimated
that there will be one trip of delivery daily for each truck.
Transportation and collection of the healthcare wastes are daily and divided by five routes as follows:
i. Route 1: Plant – Hospital Pontian – Hospital Sultanah Aminah – Makmal Kesihatan Johor –Hospital Kulai – Plant.
ii. Route 2: Plant – Hospital Kluang – Hospital Kota Tinggi – Hospital Sultan Ismail – Hospital
Permai – Plant.
iii. Route 3: Plant – Hospital Mersing – Hospital Batu Pahat – Hospital Muar- Plant.
TERMS OF REFERENCE (TOR)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF
HEALTHCARE WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT
RAMBAI, FASA 4C, MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd Page 18
CK/EV803/8026/18 TOR Revision No.: 1 Revision Date: October 2018
iv. Route 4: Plant – Hospital Port Dickson – Hospital Tampin – Hospital Alor Gajah – Hospital
Tangkak – Hospital Jasin – Hospital Segamat – Plant.
v. Route 5: Plant – Hospital Seremban – Hospital Jelebu – Hospital Jempol – Hospital Kuala
Pilah –Hospital Melaka – Plant.
3.7.2 Handling of Healthcare Wastes at Project Site (Off-site Handling)
Healthcare wastes received at the Project site will be weighed before further handling and treatment.
3.7.2.1 Incineration Process
Simplified schematic diagram for the overall processes proposed to be undertaken at the incinerator
plant is shown in Figure 3.
Source: BIC Systems Asia Pacific Pte Ltd. (2018)
Figure 3: Simplified Schematic Diagram
The healthcare wastes contained in standard 660 L or 240 L plastic waste bins is fed into the system
with a skip hoist system. The feeding process is automated with minimum manual intervention. Except
placing bins in position, the rest of the process including lifting, tilting, as well as lowering the bins are
fully automated.
The primary combustion train comprises a feeding hopper, a hydraulic ram that pushes the waste and
a guillotine (fire) door that opens only when waste is pushed into combustion chamber. The dumping
of the waste from the feeding hopper to the incinerator is monitored by interlock system, to eliminate
the possibility of overloading or under-loading of waste. The hydraulic ram will be scraped by guillotine
door so that no adhering of waste onto the feeding ram. Meanwhile, cooling air will be aspired through
the feeding area, to cool it down.
TERMS OF REFERENCE (TOR)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF
HEALTHCARE WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT
RAMBAI, FASA 4C, MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd Page 19
CK/EV803/8026/18 TOR Revision No.: 1 Revision Date: October 2018
A stationary part links the feed system to the rotary kiln and serves as a solid hearth bed to start and
to preheat the freshly introduced waste. After being partly burnt, the solid waste enters a counter
current rotary kiln for further complete combustion. The cylindrical rotary kiln rotates clockwise or
counter-clockwise at a controllable speed, to ensure thorough and speedy combustion. A cylindrical
section at the rear end of the kiln serves as an ash evacuation portion. The entire rotary kiln is
supported by four supporting wheels and one trust wheel on self-lubricating bearings.
To raise the temperature at start-up, the incinerator is equipped with a diesel burner. The burner will
start firing automatically when the temperature inside the kiln drops below a pre-set value. There will
be a robust and fool proof ash collection system for the incinerator. The new design can ensure that
no ash nor partially burnt waste shall drops from any part of the incinerator. In addition, replacement of
the bottom ash bin will be manually done for optimum reliability.
The secondary combustion, also known as post combustion chamber, starts at the upper part of the
stationary part, followed by an extension chamber equipped with and retractable burner.
3.7.2.2 Gas Cooling
After combustion, the flue gas will first enter a flue gas cooling system. The flue gas will be directed in
to a Flue Gas Thermal Oil (FGTO) heat exchanger. The vertical thermal heat exchanger enables easy
access and maintenance. The trouble-free design of the vertical FGTO heat exchanger is equipped
with ultrasonic soot blowers, in order to blow off accumulated fly-ash and soot. The newly designed
thermal oil system, fully automatically triggers the stand-by pump in case of low oil flow, where Hi-Hi
temperature will trigger plant trip (emergency by-pass).
3.7.2.3 Air Pollution Control System
Sodium Bicarbonate will be used for acidic gas neutralizer. The advantage of using Sodium
Bicarbonate instead of lime, is that the neutralising reaction time is much (5x) shorter and the reaction
itself nearly stoichiometric. Activated carbon will be used to catch any remaining for Dioxin and Furan
in the flue gases.
Sodium bicarbonate and activated carbon are stored and injected according to loss-in-weight. The
new chemical dosing design is such that it will dose the chemical flow with adjustable feeding rate
according to the quantity and quality of the flue gas. The dosing of chemical flow is by loss-in-weight
feedback. The operators will be notified by the No/Low sensor together with alarms. Moreover, the
dosing system is designed to prevent clogging of bicarbonate powder.
The flue gas then will enter the bag house filter to remove particulates and dust. A pulsating
compressed air system will blow-off the filtered dust from the filter bags and be triggered by differential
pressure across the bags. A large maintenance platform is installed at the top of the bag-house.
Rotary air locks will collect the fly-ash and the collected fly-ash drops by gravity into sealed containers
with automatic lid. The exhaust fan speed is controlled by the negative pressure in the kiln. The flue
gas treatment system is able to treat the flue gas to meet the emission standards.
3.7.2.4 Emission Monitoring
Emission monitoring equipment installed at the incinerator will comprise of in-situ CO, CO2, SO2
analysers which adopt NDIR measurement principle; extractive NOx, O2 analysers which adopt CLD /
Zirconia measurement Principle; in situ HCL/HF analysers and in-situ dust monitoring system. With
TERMS OF REFERENCE (TOR)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF
HEALTHCARE WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT
RAMBAI, FASA 4C, MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd Page 20
CK/EV803/8026/18 TOR Revision No.: 1 Revision Date: October 2018
SCADA, the data of the monitoring system will be connected and integrated with the plant PLC/PC.
The plant supervision PC will show and log all emission monitoring data continuously. The compact
emission monitoring system is enclosed with a weather proof analyser cabinet, equipped with air
condition unit, power distribution panel, lighting, switch and plug C/W rack.
The emission monitoring equipment can continuously record and online monitor all gas components
that are specified by the Malaysian Authorities. Alarms are activated to notify when the present value
are exceeded. If the pre-set values are further exceeded, the incinerator will trip. The emission
monitoring enclosure will be installed on the ground floor level, at the chimney base.
3.7.2.5 Incinerator Plant Control System
The entire incinerator plant is automatically controlled by a PLC (Programmable Logic Controller). All
required instrumentation for the incineration system, the waste feed system, the rotary kiln, the post
combustion chamber, the flue gas treatment and scrubbing system, the fan controls and emergency
by-pass system are included. The incinerator controls include temperature controls, pressure controls,
excess air controls, all burner safeties and the necessary alarms/alert and data logging equipment.
3.7.2.6 Incinerator Plant Maintenance
a) Regular Maintenance
The Regular Maintenance is essential to ensure that the plant continuously operates at optimum level.
This generally involves the following:
Cleaning of the various parts of the plant (pumps, air compressor, pneumatic cylinders, etc.)
Greasing of various components (wheels, ram, guillotine doors, etc.)
Filling up oil for the various pneumatic systems
Various other checks for potential issues
b) Scheduled Maintenance
Every year (even two years depending on how the plant has been maintained), there will be need for a
major shutdown (Scheduled Maintenance). Amongst the key areas are the patching / repairs of
refractory, checks and servicing of the burners and cleaning up the heat exchanger.
3.7.2.7 Management of Bottom Ash and Fly Ash (SW 406)
Bottom ash will be generated 8% from the waste fed into the incinerator which is approximately 67
kg/hr. Bottom ash will be temporary stored inside first and second compartment of Scheduled Waste
Storage Area before being sent to Kualiti Alam for disposal at a secured landfill with frequency of three
times a month.
Meanwhile, it is estimated about 25 kg/hr of fly ash will be generated. Fly ash will be temporary stored
at the Scheduled Waste Storage Area and sent to Kualiti Alam Sdn Bhd for disposal twice a month.
Collection of both type of ashes will done by Kualiti Alam personnel.
TERMS OF REFERENCE (TOR)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF
HEALTHCARE WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT
RAMBAI, FASA 4C, MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd Page 21
CK/EV803/8026/18 TOR Revision No.: 1 Revision Date: October 2018
3.7.2.8 Management of Fluff (SW 501)
During incinerator shutdown events, healthcare wastes at the Project site will be treated using the two
microwave machines available on-site. SW 501 which consist of fluff will be generated as residues
from the activity. Based on Clause No. 5.1 in the Jadual Pematuhan (ref. no. JPBT/KPLT/18/004989)
for the microwave operation, these residues (SW 501) shall be sent for disposal at a secured landfill,
within 24 hours or may be required to be treated by incineration process. However, since the
microwaves machines will only be in operation during incinerator shut down events, SW 501 will not
be able to be treated via incineration process at the Project site as the fluff need to be treated within
24 hours. Furthermore, MSB is not able to store the residue for long period i.e., during the incinerator
shutdown. MSB will arrange transportation to deliver the residue to a licensed premise, within 24
hours. Management of SW501 will be further discussed in the EIA Report.
3.7.2.9 Healthcare Waste Storage
In the event that healthcare wastes could not be incinerated within 24 hours of reception, it will be
stored in a dedicated storage container/ refrigerator at temperature of between below 6˚C (cold storage). There are six storage containers available at the Project site. Total holding capacity is 90
MT.
3.7.2.10 Cleansing and Disinfection of Wheeled Bins and Trucks
Upon unloading of healthcare wastes at the reception area, the emptied wheeled bins will be
transferred to the washing bay area. Wheeled bins will be washed, sprayed with biodegradable
disinfectant solution and rinsed before being transferred to clean bin storage area. Trucks will also be
cleaned and disinfected before the next collection trip or usage. Clean wheeled bins will be returned
to the healthcare wastes generators (hospitals).
3.7.2.11 Incinerator Plant Balances
The incinerator plant’s mass balance is shown in Figure 4.
3.8 PROJECT DEVELOPMENT SCHEDULE
Upon getting EIA approval and other necessary approval, the development of the Project will take
about 12 months including testing and commissioning.
3.9 PROJECT ACTIVITIES
Development of the Project will involve the following activities:
Pre-Construction Stage
Construction Stage
Operation and Maintenance Stage
Details of the activities involve during the stages are described in the following subsections.
3.9.1 Pre-Construction Stage
B I/ Syste s A sia t a ifi t TE Ltd , B ukit B atok / ese t# - W / EDA ToweSi gapoe
pr i mMry combust i on Mi r secundMry combustion Mir dilution Mir HE l eMkge Mi r 1% MCR di l ut i on Mi r dr y scr ubber l eMkge Mi r bMg house l eMkge Mi r 2%ki l n RMst e i nput 3B130 Nm5/h 4BD04 Nm5/h 2B416 Nm5/h 107 0 Nm5/h E63b6E Nm5/h 23D Nm5/h
E 4BD00 kcMl/kg . kJ /kg °C °C °C °C °C °Cm 834 kg/h T/dMy , kJ /s , kJ /s , kJ /s , , kJ /s , kJ /s , kJ /sQ Nm5/h NMHCO3 AC
T 2D °C UR E A 40% in RMter E2 kg/h E kg/h POIIUTANT EMI SSI ON l i mi t UNI T
P 10132D PM 0b00 kg/hCMl kcMl/h % CMpB HCI 10 mg/Nm5BIR type . kJ /s mi xi ng dr y scr ubber bMg house HF 1 mg/Nm5
. kJ /s . kJ /s . kJ /s 3268 kW kJ /s S Ox (S O2) D0 mg/Nm58D0 °C 1100 °C E00 °C 200 °C 200 °C 1E0 °C 180 °C NOx (NO2) 200 mg/Nm5
. kJ /s 10127D PM 10122D PM 10122D PM EE7D0 PM EE2D0 PM EE0D0 PM E80D0 PM TOC (CH4) 10 mg/Nm5CO D0 mg/Nm5
. Nm5/h . Nm5/h . Nm5/h . Nm5/h . PCDD/PCDF (TE Q) 0b1 ng/Nm5
. Am5/h . Am5/h . Am5/h . Am5/h . PMrticulMte 10 mg/Nm5, vol% O2 , vol% O2 , vol% O2 , Cd+Th 0b0D mg/Nm5
Botttom Ash 22Db0E kg/h Hg 0b0D mg/Nm5PM S b+As+Pb+Cr+Co+Cu+Mn+Ni+V 0bD mg/Nm5
kJ /s kJ /s HCI 1428bD7 mg/Nm3 rMdi Mt i on l osses kg/h S MltsHF 14b2E mg/Nm3 kJ /sS ox (S O2) 2631bD8 mg/Nm3
Cuel gas 0 Nm5/h Cuel gas c1 Nm5/h Nox (NO2) 200b00 mg/Nm3 m3/ m2B mi n B ag dia B ag le gth B ag sufa e m2 required # B ags e uiedoil 0 kg/h oil c1 kg/h TOC (CH4) 10b00 mg/Nm3
e e gy 2 kJ /s e e gy c10 kJ /s CO D0b00 mg/Nm3 0b 8 , , ,PCDD/PCDF (TE Q) 0b10 ng/Nm3 0b 8 , , ,
AIIOWED MAXB
I NDI VI DUAI CONCB ( %)
EIEMENT cust omer PlMnt S izing KIIN PlMnt S izing S CC Pl Mnt Si zi ng mi xi ngPMrticulMte 1000b00 mg/Nm3
4b44 D m/s TMrget Velocity 10 m/s TMrget Velocity 13bD m/s TMrget Vel oci t y Cd+Th Db00 mg/Nm311b27 33 % MMx filling grMde , Am3/s GMs F loRrMte , Am3/s GMs Fl oRrMt e Hg 0b20 mg/Nm321b68 , Am3/s GMs F loRrMte , m2 Required surfMce AreM , m2 Requi red sur f Mce AreM S b+As+Pb+Cr+Co+Cu+Mn+Ni+V62bD0 mg/Nm31b00 , m2 Required surfMce AreM , m Required inside diMmeter , m Requi red i nsi de di Mmet er dry scrubber FAN Si zi ng Pl Mnt Si zi ng chi mney
ok 1 , m Required inside diMmeter 2 s TMrget R esidence time (kiln outlet to S CC outlet)0bD s Resi dence t i me 10 m/s TMrget Velocity 6300 PM AV Tot Ml Pressure i ncreMse327D PM NEED Tot Ml Pressure i ncreMse 10 m/s TMrget Vel oci t yok 0b01 , m2 0rqm °ry °qr c ross – sec tqon°l °re°, m Required chMmber lenght , m Iengt h Db30 Am3/s GMs F loRrMte , Am3/s GMs Fl oRrMt e , Am3/s GMs Fl oRrMt eok 1 , m2 Resulting chMmber shell surfMce , m2 The sur f Mce MreM of t he mi xi ng chMmber 0bD3 m2 R equired surfMce AreM 0b7D FMn ef f i ci ency0B71E~0B8 , m2 Requi red sur f Mce AreMok 0b0000 , m2 3ec ond °ry °qr c ross – sec tqon°l °re° 0b8220 m R equired inside diMmeter 0bE8 MechMni cMl ef f i ci ency , m Requi red i nsi de di Mmet er
ok 34b88 , m BIR 37D inside diMmeter , m BIR 37D inside diMmeter , m BIR 37D inside diMmeter 2 s Resi dence t i me , kW Requi red f Mn poRer , m BIR 37D inside diMmeter
ok 0 , m BIR 37D S CC chMmber lenght , m BIR 37D chMmber lenght , m requi red Iengt h , kW BIR 37D fMn poRerok 0 , m BIR 37D inside diMmeterok 24b72 , input from BIR plMnt selction sheet , m BIR 37D chMmber lengthok 0 PCI rMt ki l n/ t ot Ml , mMnuMl inputok 0 , input from pluiming sheetok 0 , fo ula cMlculMtion
, fo ula input from pluiming sheet + cMlculinput from CWI sheet
fo ula input from CWI sheet + cMlculinput from quench cMlc
,
.
. ,
kJ /s
Nm5/hAm5/h
.
. Nm5/hAm5/h
vol% O2
kJ /s
,
Cd+ThHg
S b+As+Pb+Cr+Co+Cu+Mn+Ni+V
MinerMl (loss Mt ignition),,
,PCDD/PCDF (TE Q)
SNOx
TOC (CH4)bA CO
,,,
bA
,F
HO
H2ONCl
,
BIR 37D C ounter C urrent 20 TPD = 834 kg/hr
RMst e i nput
rotMry kiln
kcMl/h
post combustion
rMdiMtion losses rMdiMtion losses
Ai r f Mct or e
COMBB AI R KI IN/ TOTAIH2O %m
Fl ue gMs comp
t her mMl f l ui d HE mi xi ng
vol% O2
Nm5/h
kJ /s°C
M EDIV EST B IR -M &E ala e -
MASS BALANCE
Figure 4
Source: BIC Systems Asia Pacific Pte Ltd. (2018)
TERMS OF REFERENCE (TOR)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF
HEALTHCARE WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT
RAMBAI, FASA 4C, MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd Page 22
CK/EV803/8026/18 TOR Revision No.: 1 Revision Date: October 2018
Pre-construction stage will include the appointment of consultants and surveyors. The activities during
this stage include project planning and environmental assessment.
It is anticipated that the environmental risks range from no impact to low degree of significant impact
during this pre-construction stage.
3.9.2 Construction Stage
Major activities during construction stage include:
Mobilisation of Workforce [Project Manager – 1, Project Supervisor –1, General Worker(local and
foreigner) – 15], Machineries and Construction Materials
Foundation works – soil improvement, piling
Civil and structure works – incinerator plant and IETS
Transportation of construction material and equipment
Mechanical and electrical works – installation of all process equipment, conveying systems and
environmental control systems
Testing and commissioning - No-load, load and performance tests
3.9.3 Operation and Maintenance Stage
During operational stage, the Project will be operated by the existing MSB operational team as follows:
Senior Manager -1 Plant Manager – 1
Engineer – 2 Technical Officer – 3
Technician (Shift Leader) – 3 Operator - 3
The organisation chart is shown as Figure 5.
TERMS OF REFERENCE (TOR)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF
HEALTHCARE WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT
RAMBAI, FASA 4C, MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd Page 23
CK/EV803/8026/18 TOR Revision No.: 1 Revision Date: October 2018
Figure 5: Organisation Chart
Operation of the Project is largely automated and control via process control system. Main processes
in productions are described in Section 2.8.2 of this ESI. Other important activity during the operation
stage is transportation of healthcare wastes. The designated routes of are as listed in Section 2.8.1.
As mentioned in Section 2.8.2.6, regular maintenance which includes cleaning of various parts,
greasing of various components, filling up of pneumatic systems’ oil and various will be carried out according to schedule.
Scheduled maintenance which include patching / repairs of refractory, checks and servicing of the
burners and cleaning up the heat exchanger will be carried out yearly.
TERMS OF REFERENCE (TOR)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF
HEALTHCARE WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT
RAMBAI, FASA 4C, MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd Page 24
CK/EV803/8026/18 TOR Revision No.: 1 Revision Date: October 2018
4 ALTERNATIVES CONSIDERATION
4.1 SITE OPTIONS
4.1.1 New Site Option
Sitting on a new site shall consume substantial cost for new land purchase, feasibility study and
construction of new facilities such as Cold storage, scheduled waste store, administration office and
Control Room.
A new group of workers will have to be trained in the management and operations of the new site.
Public concern on environmental issue which will bring sceptical reaction on the new installation of the
healthcare wastes treatment facility on the new site. However, the public will be more receptive on the
upgrading existing plant on condition that the facility complies with the standard emissions and do not
pose any hazards or environmental issues to the receptors staying area.
4.1.2 Existing Site Option
Other facilities such as the Cold Storage, Control Room, Scheduled Waste Store, Administration
Office and Workshop is already in place and ready for use immediately. Besides that, cost and time
shall be reduced significantly for this upgrading works as the work only focus on the incinerator plant
only.
Data pertaining to the baseline and existing environment in the surrounding area of the existing clinical
wastes incineration plant is well documented to assess any residual impacts of operating of the clinical
waste treatment facility.
The experienced workforce managing and operating the clinical wastes incineration plant can be
further utilized to manage the new plant.
Thus based on the above, the use of the present site is a better option worthy of consideration rather
than the option for locating on a new site.
4.2 TECHNOLOGY OPTIONS
Waste incineration in rotary kiln is considered to be Best Available Technology (BAT) for medical and
hazardous waste treatment, because of continuous operation creating steady state conditions,
ensuring complete combustion leading to complete destruction of dioxins and furans. There are two
types of rotary kilns, named after the sense of solids- compared to gas flow in the kiln.
TERMS OF REFERENCE (TOR)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF HEALTHCARE
WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT RAMBAI, FASA 4C,
MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd Page 25
CK/EV803/8026/18 TOR Revision No.: 1 Revision Date: October 2018
4.2.1 Counter Current Rotary Kiln
Source: BIC Systems Asia Pacific Pte Ltd. (2018)
Figure 6: Counter Current Rotary Kiln
Flue gases flow in the opposite direction of the waste, against the inclination of the kiln. Solids move by
the rotary motion and by gravity from the high end to the low end of the kiln.
Primary Combustion air (cold ambient air) is introduced at the lower end of the kiln (at the de-ashing zone)
by aspiration (the whole system is under negative pressure).While flowing towards the feeding area (front)
of the kiln, the combustion air is preheated by flowing over the hot ash and its oxygen content is gradually
reduced by oxidation of the solids during its passage and – as such - becomes flue gas .At the front of the
kiln the off (flue-) gas contains little oxygen (max.6%) and is hot (1000 °C).By controlling the amount of
inflowing flue gases (simply by adjustment of the inlet damper),it is possible to control the degree of
oxidation of the solids and – as a consequence – to control the remaining oxygen content in the flue gas .It
is thus perfectly possible to operate under controlled starved air conditions (pyrolysis).By correctly
adjusting the primary air, it is thus perfectly possible to:
i. To operate under pyrolysis conditions
ii. To control the combustion temperature in the kiln. This is particularly interesting in the case the solid
waste residues tend to melt at certain temperatures. This feature is particularly interesting for
avoiding clogging (e.g. NaCl melts around 800°C) or for avoiding evaporation of (precious) metals. By
controlling correctly the temperature in the kiln, there is no clogging at all.
iii. To produce more or less rich (pyrolysis) gas, to fuel the post combustion chamber, which provides a
perfect post combustion temperature control without any requirement of external fuel
Incoming solid waste is introduced in the front zone of the kiln and is exposed to the hot (pyrolysis) flue
gas which flows in counter current against the waste. The flue gas being poor in oxygen and high in
temperature, makes all the light fractions - which are present in the solid waste - to evaporate and to be
mixed with the rich gas exiting from the primary combustion (kiln). This highly flammable mixture is mixed
at its origin (right above the feeding zone of the kiln) with incoming post combustion air, where it
immediately starts the post combustion and where the temperature easily reaches 1250 °C (but can be
easily reduced) – without auxiliary fuelling.
TERMS OF REFERENCE (TOR)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF HEALTHCARE
WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT RAMBAI, FASA 4C,
MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd Page 26
CK/EV803/8026/18 TOR Revision No.: 1 Revision Date: October 2018
The bottom ash is evacuated from the primary rotary chamber through a cylindrical section with a reduced
diameter compared to the kiln. As a consequence, the height of the ash in the kiln is permanently
maintained to about 1/3 of the diameter of the kiln.
Only after the combustion of solids is complete (after sufficient residence time), the ash is gradually
scooped out (by refractory lined scoops), from the kiln into the narrowed cylindrical section, in which it is
exposed to incoming primary combustion air to cool it down before dropping directly into the ash
container. As a consequence, the bottom ash is perfectly burnt out (less than 2% residual organic carbon)
and comes out cool and dry. Because combustion air flows in by suction at the exit location of the bottom
ash there is no need for a perfect (water) seal. (Any eventual air leakage will serve as combustion air).
As it is described above, the post combustion being fuelled by a rich gas (which is produced in the primary
chamber) the combustion temperature is equally distributed over the entire area, rather than in one
particular area (as it is the case in any other system, firing a supporting burner) Therefore, the residence
time of the flue gas in the post combustion area can be correctly calculated. This property is most
important for being able to control the destruction of Dioxins. As it is commonly known, dioxins can only be
completely eliminated if a residence time of 2 seconds at 1000 °C and if an oxygen level of minimum 10%
is thoroughly respected everywhere. This is only possible in counter current kiln designed by the
Technology Provider.
Due to the complete destruction of all Dioxins and their components during passage through the post-
combustion, there is absolutely no risk of reformation and as a consequence, there is no need to quench
the flue gas after the post-combustion to prevent reformation. As such, the full heat content of the flue gas
can be recovered to produce steam and/or electric power.
Additional features are that this type of kiln ensures better turbulence and hence the kiln can be kept short
and compact. In order to achieve the same residence time for the solids, the rotation is slower than in a
co-current kiln and by correctly dosing the primary combustion air, the fly ash carry over can be strongly
reduced, compared to a co-current kiln.
4.2.2 Co-Current Rotary Kiln
Source: BIC Systems Asia Pacific Pte Ltd. (2018)
Figure 7: Co-Current Rotary Kiln
Flue gases flow in the same direction of the waste, with the inclination of the kiln. Solids move by the
rotary motion and by gravity from the high end to the low end of the kiln.
Primary combustion air is blown in by a fan. The excess of combustion air is generally 100 % to 150 %.
While flowing to the back of the kiln, the air heats up and becomes poor in oxygen due to the complete
combustion of all the solids basically becoming flue gas so that at the back of the kiln the outflowing flue
TERMS OF REFERENCE (TOR)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF HEALTHCARE
WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT RAMBAI, FASA 4C,
MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd Page 27
CK/EV803/8026/18 TOR Revision No.: 1 Revision Date: October 2018
gases contain less oxygen (6 %) but are hot (900 °C -1000 °C) due to the complete oxidation of all the
waste components (solid and gaseous fraction).
Incoming waste (solids) is cold and follows the same flow direction as the incoming (cold) combustion air.
Depending on the CV of the waste, a make-up burner is required to start the incineration process.
At the back (bottom ash exit) of the kiln, the solids do not contain enough combustible matter anymore,
such that the flue gases flowing to the post combustion zone have to be re-heated from 900 °C -1000 °C
to 1100 °C by a supporting burner.
Bottom ash is hot (1000 °C) and is not cooled down by the incoming combustion air as it is the case with a
counter-current kiln. Also, the oxygen – poor atmosphere cannot help to achieve a good burnout. The high
temperature in the ash evacuation zone (1000 °C) creates a high risk of slagging and makes ash handling
difficult (ash quench is required).
Additional features are that this type of kiln ensures little turbulence and hence the kiln must be longer. To
keep the combustion going, kiln rotation must be faster than in a counter-current kiln, leading to more fly
ash carry over.
Comparison of the operating conditions of a typical example of rotary kiln, counter current versus co-
current.
Counter Current Rotary Kiln Co-Current Rotary Kiln
Size Compact Bigger size
Amount of waste in 1000 kg/h 1000 kg/h
Waste inlet temperature 1000 °C 200 °C
Oxygen % at waste inlet 6 % 21 %
Waste residence time >2-4 h >2h
Bottom ash
Residual organic carbon in Ash <0.5 % >2-8 %
Temperature 200 °C 1000 °C
Mass reduction (%) <85 % >75 %
Post combustion additional support fuel consumption
0 kg/h >100 kg/h
Fly ash 750 mg/Nm3 1500 mg/Nm3
Source: BIC Systems Asia Pacific Pte Ltd. (2018)
TERMS OF REFERENCE (TOR)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF HEALTHCARE
WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT RAMBAI, FASA 4C,
MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd Page 28
CK/EV803/8026/18 TOR Revision No.: 1 Revision Date: October 2018
The Project Proponent has chosen the counter current rotary kiln as their preferred technology based on
the following key benefits:
Low consumption of fuel.
The incinerator will be using counter-flow process which allow very minimum or even non consumption
of fuel during ideal operation. The fuel only consumed during start-up process which takes less than
24 hours.
Better air emission.
The incinerator has been well accepted with 55 units has been operated all around Europe, Africa,
Middle East and Asia. Main factor of this acceptance due to application of modern and highly efficient
air pollutant control system which treats the combustion effectively before being emitted to
environment. The system proven to be able to comply with stringent emission standard worldwide.
Low production of by-product.
No effluent produced from the incinerator. During the incineration process, the ash produced is only
8% from the original load.
4.3 NO PROJECT OPTIONS
Besides the above, “No Project” option will also be discussed in the EIA report.
5 EIA STUDY GUIDELINES AND APPROACHES
5.1 REVIEW OF GUIDELINES AND ENVIRONMENTAL LEGISLATIONS
The EIA study and report shall be undertaken in accordance with the guidelines issued by the DOE and
other agencies. The list of guidelines is not exhaustive and subject to updates and new requirement by the
respective agencies. Nevertheless, the relevant list of guidelines includes:
Environmental Impact Assessment Guidelines for Risk Assessment, December 2004.
Environmental Impact Assessment Guidelines for Toxic and Hazardous Waste Treatment and
Disposal Projects, February 2000.
Environmental Impact Assessment Guidelines in Malaysia (2016) by DOE
Environmental Quality (Amendment) Act, 2012
Environmental Quality (Industrial Effluent) Regulations, 2009
Environmental Quality (Prescribed Activities) (Environmental Impact Assessment) Order 2015
Environmental Quality (Scheduled Wastes) Regulations, 2005
Environmental Quality Act, 1974
TERMS OF REFERENCE (TOR)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF HEALTHCARE
WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT RAMBAI, FASA 4C,
MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd Page 29
CK/EV803/8026/18 TOR Revision No.: 1 Revision Date: October 2018
Factory and Machinery Act (revised 1974)
Guidance Document for Addressing Soil Erosion and Sediment Control Aspects In The
Environmental Impact Assessment (EIA) Report (19 July 2016) by DOE
Guidance Document for the Preparation Of The Document On Land-Disturbing Pollution
Prevention and Mitigation Measures (LD-P2M2) (19 July 2016) by DOE
Guidance Document on Health Impact Assessment (HIA) in Environmental Impact Assessment
(EIA), June 2012
Occupational Safety and Health Act,1994
Environmental Quality (Clean Air) Regulations 2014
The Planning Guidelines for Environmental Noise Limits and Control, (2nd Edition, August 2007)
by DOE
Town and Country Planning Act, 1960
5.2 REVIEW OF PREVIOUSLY APPROVED EIA REPORTS OR STUDIES
Relevant reliable journals, articles, case studies, guidelines and secondary data (i.e. previous EIA Report
of the Project, baseline data, on-going monitoring reports, and safety records); will be reviewed to assist in
the further comprehension of the projected environmental impacts resultant from the Project. Some of the
references include:
Proposed Clinical Waste Incinerator Replacement Project at Radicare (M) Sdn Bhd Plant in Lot 5,
Jalan Waja 16, Teluk Panglima Garang, Daerah Kuala Langat, Selangor (2018) prepared by Tri
Ecoedge Sdn Bhd. (2018).
Detailed Environmental Impact Assessment for the Proposed Clinical Waste Thermal Treatment
Facility in Sabah by Faber Medi-Serve Sdn. Bhd (2009) prepared by Chemsain Konsultant Sdn
Bhd.
5.3 ENGAGEMENT WITH RELEVANT AGENCIES AND LOCAL COMMUNITY
Government policies, legislation and regulations relevant to the proposal will be identified. Local plans
and policies will also be evaluated. Project characteristics will be analysed to ensure compliance with
these policies, legislation and regulations. Appropriate recommendations will be provided to ensure
regulatory compliance. Discussions and meetings may be carried out with various Government Agencies;
with Ministry of Health and Department of Environment being the two key agencies and other agencies
such as:
Department of Environment (DOE)
Ministry of Health (MOH).
Majlis Bandaraya Melaka Bersejarah
Any other relevant Government Agencies as and when necessary
It is intended that this consultation will be in the form of informal and formal discussions
TERMS OF REFERENCE (TOR)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF HEALTHCARE
WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT RAMBAI, FASA 4C,
MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd Page 30
CK/EV803/8026/18 TOR Revision No.: 1 Revision Date: October 2018
5.3.1 Socio-economic
The existing socio-economic information will cover the population of the district and residents living nearby
the zone of influence. An introduction of the socio economic information at the district where the Project is
located is necessary to allow an understanding of:
The strategic importance of having the project at the district and
The socio-economic background of the population in the district.
The source of the data will be collected from secondary demographic data from the Department of
Statistics publication on The 2010 Population and Housing Census of Malaysia.
The information on the socio-economic characteristics of the populations and economic activities
surrounding the project site include demographic characteristics such as on population and household
size, gender, race and age.
6 SIGNIFICANT ENVIRONMENTAL IMPACTS TO BE STUDIED
A scoping exercise was conducted and documented as Environmental Scoping Information (ESI) Report
appended as Appendix A.
Based on initial desktop study, human settlements have been identified as the environmental sensitive
areas (ESA) which are located adjacent to the Project site. The ESAs are listed in Table 12 and shown in
Figure 8.
Table 12 : Environmental Sensitive Areas (ESA) – Settlement
Radius Area
Up to 1 km Radius Taman Tanjung Minyak Perdana (northeast)
Kuli Metto Amman (northwest)
Melaka Chinese Temple (southeast)
Up to 2 km Radius Kg Ayer Salak (southwest) Taman Rambai Indah (southwest)
Taman Tanjung Minyak Utama (southeast)
Bertam Ulu (east)
Taman Bertam Permai (northeast) Kg Bertam Ulu (northeast)
Taman Bertam Impian (north) Taman Bertam Setia (northeast)
Taman Rambai Utama (southeast) SK Bertam Ulu (northeast)
Madrasah Al-Hikmah (northeast) SJK(C) Bertam Ulu (northeast)
Church of St. Mary, Ayer Salak (southwest)
Masjid Bertam Ulu (northeast)
Surau Al-Usrah (northeast)
Up to 3 km Radius Kg Ayer Supai (northeast) Taman Seri Bertam (northwest)
Kg Tangga Batu (southwest) Taman Rambai (southwest)
Tangga Batu (southwest) Kg Seberang Gajah (southwest)
Taman Malim Jaya (southwest) Taman Tanjung Minyak Setia (southeast)
Taman Sri Rambai (southeast) Tanjung Minyak (southeast)
TERMS OF REFERENCE (TOR)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF HEALTHCARE
WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT RAMBAI, FASA 4C,
MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd Page 31
CK/EV803/8026/18 TOR Revision No.: 1 Revision Date: October 2018
Radius Area
Taman Perwira Rumah Awam Cheng (southeast)
Taman Cheng Jaya (southeast)
Taman Cheng Perdana (southeast) Taman Bertam Jaya (east)
Taman Paya Emas (northeast) Taman Cheng Baru (southeast)
SMK Taman Bukit Rambai (southwest)
SJK(C) Cheng (southeast)
SMK Tun Haji Abd Malek (southeast) SK Tanjung Minyak (southeast)
Tangga Batu Fire and Rescue Station (southwest)
Surau Rumah Awam Datin Fatimah Bukit Rambai (southwest)
Up to 5 km Radius Taman Paya Rumput Perdana (northeast)
Taman Raya Rumput Indah (northeast)
Taman Seri Paya Rumput (northeast)
Taman Paya Rumput (northeast)
Taman Permai (northeast) Taman Bukit Cheng (southeast)
Taman Cheng Utama (southeast) Taman Cheng Ria (southeast)
Taman Asean (southeast) Taman Gadong Perdana (southeast)
Kg Bukit Rambai (southeast) Taman Malim Jaya (southeast)
Kg Gaffar Baba (southwest) Kg Rambai Tengah (southeast)
Sg Udang (northwest) Taman Merdeka (southeast)
Kg Gelam (southwest) Kg Tanah Merah Jaya (southwest)
Kg Pantai Kundur (southwest) Kg Sg Udang (west)
Taman Peruna (west) Taman Pahlawan (northwest)
SK Bukit Rambai (southeast) SK Kg Gelam (southwest)
SJK(C) Poh Lan (southwest) SK Sg Udang (west)
SMK Malim (southeast) Kompleks Penjara Melaka (northwest)
Masjid Al-Faizin (south) Turkish Mosque Rombang
Masjid Tangga Batu Pekan, Tanjong Kling (southwest)
Masjid Mohsinin (southwest)
Perpustakaan Desa Paya Rumput (northeast)
Kuil Sannasimalai Andavar Tirukkoril
Potential environmental impacts associated with the development of the Project were identified and
summarised in Table 13.
Table 13: Anticipated Significant Environmental Impacts
No Project Stage Project Activities Environmental Impacts
1. Construction Stage
Mobilisation of Workforce
Foundation works – soil improvement,
piling
Water quality impact
Air quality impact
TERMS OF REFERENCE (TOR)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF HEALTHCARE
WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT RAMBAI, FASA 4C,
MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd Page 32
CK/EV803/8026/18 TOR Revision No.: 1 Revision Date: October 2018
No Project Stage Project Activities Environmental Impacts
Civil and structure works – incinerator
plant and IETS
Transportation of construction material
and equipment
Mechanical and electrical works –
installation of all process equipment,
conveying systems and environmental
control systems
Testing and commissioning - No-load,
load and performance tests
Noise impact
Waste generation and management
2. Operation and Maintenance Stage
Transportation of healthcare wastes to
Project site
Operation of incinerator
Maintenance works
Potential accidental spillage
Waste generation and management
Safety hazard
Air quality
Noise impact
The following sub-sections described the study boundary, assessment standards, assessment
approaches and tools and possible mitigation measures.
6.1 WATER QUALITY
The thermal treatment or incineration of the healthcare wastes is a dry process. The only possible
sources of wastewater are from the truck/ bin cleansing and disinfection activities. The potential scenarios
for water pollution will be assessed based on the evaluation of the projected wastewater discharge from
the washing bay area.
Initial assessment of wastewater management found that the potential impact on water quality is
considered low since the volume of wastewater from the truck/bin cleansing and disinfection activities is
low and shall be channelled to IETS for treatment before being discharged to the industrial area drainage
system.
6.1.1 Study Boundaries
In order to gauge surface water quality within the Project area, baseline for water quality will be
established for in-situ testing and analysis of grab samples taken at the proposed water monitoring
locations as shown in Table 14 and Figure 9.
Water quality monitoring will be carried out twice (except for dioxin and furan) to represent dry and wet
weathers, where possible. Dioxin and furan will be conducted once–off at upstream and downstream of
the site as representative points for future comparison should there be any deposition of such pollutants
upon the operation of the new incinerator.
10
9
8
6
1
2
37
5
4
11
12
14
13
16
19
18
17
20
21
15
22
23
24
25
26
27
28
29
30
31
33
32
34
3539
43
44
45
46
42
47
37 38
36
40
41
48
49
5051
52
53
54
55
56
57 58
6059
61
62
63
64
65
66
67
6869
70
71
CHEMSAIN KONSULTANT SDN. BHD.
ENVIRONMENTAL
SENSITIVE AREA
LEGEND:
500M Radius
1KM Radius
2KM Radius
3KM Radius
5KM Radius
4KM Radius
FIGURE 8
CHEMSAIN KONSULTANT SDN. BHD.
BASELINE SAMPLING
LOCATIONS
LEGEND:
A2/N4
A3
A4
W3
W2
W1
A1
N1
N2
N3
FIGURE 9
TERMS OF REFERENCE (TOR)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF HEALTHCARE
WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT RAMBAI, FASA 4C,
MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd Page 33
CK/EV803/8026/18 TOR Revision No.: 1 Revision Date: October 2018
Table 14: Proposed Baseline Water Quality Locations
Station Approximate Coordinates Justification
W1 2°16'47.6"N 102°10'50.3"E To represent the existing water quality at existing drain next to the storm water drain discharge point at the southeast boundary of Project site
W2 2°16'47.3"N 102°10'50.4"E To represent the existing water quality at existing drain next to the storm water drain discharge point at the west boundary of Project site
W3 2°16'00.9"N 102°10'37.6"E To represent the existing water quality of Sg Ayer Salak located further downstream of the Project site
6.1.2 Assessment Standards
Surface water parameters to be tested are listed in Table 15 and the tests shall be conducted by SAMM
accredited laboratory using appropriate APHA Standard Test Methods. Test results will be discussed in
the EIA report with comparison made with the National Water Quality Standards for Malaysia, where
relevant (Appendix 1 of the ESI).
Table 15: Proposed Water Quality Parameters
Parameters Test Method
Temperature In-situ, APHA 2550 B
pH value In-situ, APHA 4500-H+B
Dissolved Oxygen (DO) In-situ, APHA 2500-O G
Biochemical Oxygen Demand (BOD) APHA 5210B & 4500-O G
Chemical Oxygen Demand (COD) APHA 5220 C
Total Suspended Solids (TSS) APHA 2540 D
Mercury APHA 3112 B
Cadmium, Lead, Copper, Zinc, Iron, Manganese, Nickel
APHA 3111 B
Total Chromium APHA 3125 B
Arsenic APHA 3114 B & C
Tin In-house Method 0502 based on APHA 3111 D
Boron APHA 4500-C B
Cyanide APHA 4500-CN C & D
Phenol APHA 5530 C
Free Chlorine In-situ, In-house Method 0501 base on Palintest Comparator
Sulphide APHA 4500 S2- F
Oil and grease APHA 5520 B
Turbidity (NTU) APHA 2130 B
TERMS OF REFERENCE (TOR)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF HEALTHCARE
WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT RAMBAI, FASA 4C,
MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd Page 34
CK/EV803/8026/18 TOR Revision No.: 1 Revision Date: October 2018
Parameters Test Method
Ammoniacal Nitrogen APHA 4500-NH3 C
Total Coliform Count APHA 9221 B
Faecal Coliform Count APHA 9221 E
Dioxin and furan US EPA Method 1613B
6.1.3 Description of Modelling Tools and Assessment Methodologies
Initial assessment of wastewater management found that the potential impact on water quality is
considered low since the volume of wastewater from the truck/bin cleansing and disinfection activities is
low and shall be channelled to IETS for treatment before being discharged to the industrial area drainage
system.
Nonetheless, the assessment on water quality shall be further detailed out in the EIA. The evaluation of
impacts will be made against established standards and criteria made under the Environmental Quality
Act, 1974 and its subsidiary legislation as well as other international accepted criteria.
6.1.4 Possible Mitigation Measures
Possible mitigation measures or best management practices from similar projects that may be used to
address the water quality of this Project is as follow:
All chemicals, oil and fuels should be stored in a designated and covered area onsite. These
areas should be provided with oil traps and also bunded to prevent spillage.
Trucks and bins washing water to be treated in IETS to comply with Standard B of the
Environmental Quality (Industrial Effluents) Regulations 2009 prior discharge to public drain.
6.2 AIR QUALITY
Prediction of air quality impact during construction stage is due to fugitive dust and gases emissions from
vehicle exhausts and machineries. Potential air quality impact during construction stage is considered
low, temporary and insignificant.
During operation stage, air quality impact is one of the main environmental issues expected from the
operation of the proposed facility. The prediction of impacts due to air pollutants will be made for point
and fugitive dust emissions. Air pollutants are expected from, but not limited to the following sources:
Emissions of flue gases from combustion via the chimney
Handling of ash
Healthcare wastes incineration depending on the capacity, waste feed and combustion conditions of the
incineration plant, can emit the following pollutants into the atmosphere:
Particulate matter
Heavy metals (i.e. lead, cadmium, arsenic, mercury)
TERMS OF REFERENCE (TOR)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF HEALTHCARE
WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT RAMBAI, FASA 4C,
MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd Page 35
CK/EV803/8026/18 TOR Revision No.: 1 Revision Date: October 2018
Acid gases (HCl, SO2)
Oxides of nitrogen
Carbon monoxide
Organics (VOC, dioxin and furan)
Various other materials present in healthcare wastes, such as pathogens and cytotoxins. No radioactive
substances are expected as these are removed before the waste is incinerated.
Particulate matter is emitted as a result of incomplete combustion of organic matter and the entrainment of
non-combustible ash due to the turbulent movement of combustion gases. Particulate matter may contain
heavy metals, acids and trace organics. Acid gases like HCl and (SO2) in the exhaust gas are directly
related to the chlorine and sulphur content of the waste. Most of the chlorine are from polyvinyl chloride
(PVC) waste and other chlorinated compounds wherein during incineration are converted to HCl. Sulphur
is also chemically-bound within the waste materials and is oxidised during combustion to form SO2.
NOx are formed during combustion by i) oxidation of nitrogen chemically bound in waste and ii) reaction
between molecular nitrogen and oxygen in combustion air. As for CO, it is a product of incomplete
combustion.
Similarly failure to achieve complete combustion of organic materials may result in emissions of a variety
of organic compounds such as methane, ethane and other high molecular weight organics (dioxins and
furans).
6.2.1 Study Boundaries
In order to gauge baseline ambient air quality within the Project site and at the identified sensitive
receptors, four sampling locations will be established as listed in Table 16 and shown in Figure 9.
Ambient air monitoring will be carried out twice (except for dioxin and furan) preferably to represent dry
weather and wet weather conditions.
Table 16: Proposed Baseline Ambient Air Quality Sampling Locations
Station Approximate Coordinates Justification
A1 2°16'48.3"N 102° 10' 51.3"E To represent the ambient air quality at the north boundary of Project site.
A2 2°16'53.7"N 102°11'15.9"E To represent the ambient air quality at Taman Tg Minyak Utama (padang permainan facing main road) located northeast of Project site.
A3 2°16'36.6"N 102° 10' 25.5"E To represent the ambient air quality at Kg Ayer Salak located southwest of the Project site.
A4 2°15'47.0"N 102° 11' 3.2"E To represent the ambient air quality at Taman Rambai Jaya located south of Project site.
TERMS OF REFERENCE (TOR)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF HEALTHCARE
WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT RAMBAI, FASA 4C,
MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd Page 36
CK/EV803/8026/18 TOR Revision No.: 1 Revision Date: October 2018
6.2.2 Assessment Standards
The test parameters and respective test methods for ambient air quality baseline are tabulated in Table
17. Test results obtained will be evaluated against the Malaysia Ambient Air Quality Standard and Arizona
Ambient Air Quality Standard (Appendix 2 of the ESI) and discussed in the EIA report.
Table 17: Proposed Test Parameters for Ambient Air Quality
Parameters Test Methods
PM2.5 High Volume Sampler
AS/NZS 3580.9.14.2013
PM10 High Volume Sampler
AS/NZS 3580.9.6.2003
Sulphur Oxides (as SOx) Air Sampling Pump
In House Method based on Methods of air sampling and analysis, 3rd Edition, Method 704 A
Nitrogen Oxides (as NOx) Air Sampling Pump
In House Method based on Methods of air sampling and analysis, 3rd Edition, Method 818A (sampling excluded)
CO In-situ using Dositube
HCl ID 174 SG
HF ID 110
Lead, Mercury, Cadmium, Chromium, Arsenic, Copper
Extracted from particulate matters filter paper
ICPMS
Dioxin and furan US EPA Method TO-9A
6.2.3 Description of Modelling Tools and Assessment Methodologies
Based on assessment study requirements, the type of sources and outputs required, the model selected
for this assessment will be the USEPA AERMOD Model. In this particular assessment, a 10 km X 10 km
(5 km radius) Cartesian grid with 100 m spacing for the nearest 1 km receptors and 200m grid spacing for
receptors further than 1 km from the source is used for impact modelling. The surface weather and upper
air data used in the AERMOD modelling input will be from the nearest meteorological station. One year of
the latest hourly meteorological data consisting of wind speed, wind direction, temperature, stability and
mixing height available data will be used in the analysis.
All raw data used in the modelling will be appended in the EIA report. Pollutants to be modelled and
assessed are:
i. PM10 ii. PM2.5 iii. NO2
iv. SO2 v. HCl vi. arsenic (as As)
vii. cadmium (as Cd) viii. lead (as Pb) ix. mercury (as Hg)
x. dioxin and furan
TERMS OF REFERENCE (TOR)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF HEALTHCARE
WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT RAMBAI, FASA 4C,
MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd Page 37
CK/EV803/8026/18 TOR Revision No.: 1 Revision Date: October 2018
Results of the modelling will be assessed based upon other criteria generally accepted by the DOE for
ground level concentrations of air pollutants and also reputable and relevant international standards. The
type of air pollution control system used will also be addressed. Based on the result, recommendations to
minimise the impact to the surrounding land use or receptor will be formulated.
6.2.4 Possible Mitigation Measures
Possible mitigation measures or best management practices from similar projects that may be used to
address the air quality impacts of this Project is as follow:
Good housekeeping at site.
No open burning of any materials on-site is allowed.
Periodical impact monitoring of air quality at Project boundary and identified sensitive receptor.
Installation of Continuous Emission Monitoring System (CEMS) shall be conducted to monitor the
air emission parameters
More detailed and definite mitigation measures will be discussed in the EIA report.
6.3 WASTE MANAGEMENT
Waste generated during construction and operation stages of the Project will potential deteriorates the
condition of the surrounding environment if they are not properly managed. Anticipated type of wastes to
be generated from the Project is as tabulated in Table 18.
Table 18: Anticipated Waste from Project
Stage Category Type of Waste Possible Source
Construction Stage
Scheduled Waste
Disposed containers, bags or equipment contaminated with chemicals, pesticides, mineral oil or schedule wastes (SW409)
Construction area, workshop
Rags or filters contaminated with scheduled waste (SW410)
Spent lubrication oil (SW 305)
Waste of inks, paints, pigments, lacquer, dye or varnish SW 417
Solid Waste
Metal Scrap/ Construction material Stockpile on site
Operation and Maintenance Stage
Scheduled Waste
Ashes from scheduled waste incinerator (SW 406) Incinerator
Spent lubrication oil (SW 305) Incinerator, workshop
Spent hydraulic oil (SW 306) Incinerator, workshop
Disposed containers, bags or equipment contaminated with chemicals, pesticides, mineral oil or schedule wastes (SW409)
Storage area
TERMS OF REFERENCE (TOR)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF HEALTHCARE
WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT RAMBAI, FASA 4C,
MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd Page 38
CK/EV803/8026/18 TOR Revision No.: 1 Revision Date: October 2018
Stage Category Type of Waste Possible Source
Rags or filters contaminated with scheduled waste (SW410)
Storage area
Sludges containing one or several metals including chromium, copper, nickle, zinc, lead, cadmium, aluminium, tin, vanadium and beryllium (SW204)
IETS
6.3.1 Study Boundaries
The study will cover wastes generated by the Project.
6.3.2 Assessment Standards
Impact assessment on waste management will be based on best management practises as well as latest
Acts and Regulations.
6.3.3 Description of modelling tools and assessment methodologies
Estimation of wastes generation will be attempted using historical data and secondary references.
Proposed waste management plans will be evaluated and documented in the EIA report.
6.3.4 Possible Mitigation Measures
Possible mitigation measures or best management practices from similar projects that may be used to
address the waste management of this Project is as follow:
All workers should be adequately trained in terms of appropriate use, handling and disposal of
chemicals and lubricants involved in the operation of the facility.
To provide appropriate designated and marked storage areas for scheduled wastes.
All scheduled waste during maintenance works should be handled and disposed off according to
the Environmental Quality (Schedule Wastes) Regulations 2005.
More detailed and definite mitigation measures will be discussed in the EIA report
6.4 NOISE
The major source of noise from the Project will arise from the operating machineries such as air
compressors, feed hopper, exhaust fan and other mechanical systems.
6.4.1 Study Boundaries
The existing ambient noise levels will be monitored at four proposed monitoring stations as listed in Table
19 and shown in Figure 9.
TERMS OF REFERENCE (TOR)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF HEALTHCARE
WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT RAMBAI, FASA 4C,
MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd Page 39
CK/EV803/8026/18 TOR Revision No.: 1 Revision Date: October 2018
Table 19: Proposed Baseline Noise Measurement Locations
Station Approximate Coordinates Justification
N1 2°16'48.1"N 102°10'51.9"E To represent the ambient noise level at the northeast boundary of the Project
N2 2°16'46.2"N 102°10'50.7"E To represent the ambient noise level at the west boundary of the Project site.
N3 2°16'44.7"N 102°10'52.9"E To represent the ambient noise level at the south boundary of the Project site.
N4 2°16'53.7"N 102°11'15.9"E To represent the noise level at Taman Tg Minyak Utama located northeast of Project site.
6.4.2 Assessment Standards
Noise measurements will be conducted once at the monitoring station using a calibrated sound level
meter and continuously over 24 hours period to represent 15 hours (7 am to 10 pm) day time and 9 hours
(10 pm to 7 am) night time. Measurement parameters shall include Leq, Lmax, Lmin, L10 and L90. Extraneous
and significant noise contributors observed during the monitoring sessions will be recorded. Measured
results will be evaluated against the Planning Guidelines for Environmental Noise Limits and Control
(Appendix 3 of the ESI) and discussed in the EIA report.
6.4.3 Description of Modelling Tools and Assessment Methodologies
Noise levels at a distance from source can be predicted based on the approach that noise emanating from
a source will attenuate naturally as it propagates over free air. This is due to wave divergence, which
results in dissipation of sound energy. The attenuation of noise can be estimated based on information
related to sound power level of the source and the distance over which the sound travels. Therefore, the
propagation of a noise source measured at 1m away can be shown to behave to the following formula:
(Point source)
(Line source)
Where,
L = Noise Level at d metres away from the source
L0 = Noise Level measured at 1 meter away from the source
d = Distance from the point source in meters
6.4.4 Possible Mitigation Measures
Possible mitigation measures or best management practices from similar projects that may be used to
address the noise level of this Project is as follow:
Establish periodical maintenance schedule for all motorised machineries and equipment as
preventive measure to minimise emission of loud noise. Attention shall be given to efficiency of
mufflers to reduce noise problems.
TERMS OF REFERENCE (TOR)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF HEALTHCARE
WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT RAMBAI, FASA 4C,
MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd Page 40
CK/EV803/8026/18 TOR Revision No.: 1 Revision Date: October 2018
Enclosure or other type of acoustic measures shall be applied on equipment which contribute to
noise levels higher than 85 dB (A).
More detailed and definite mitigation measures will be discussed in the EIA report.
6.5 HEALTH IMPACT ASSESSMENT
The Health impact assessment (HIA) component will investigate potential public health impacts from
primary environmental influences such as air quality and water quality, on the population residing in the
vicinity of the proposed Project especially during the construction and operation stages The HIA
methodology will be based on the Guidance Document on HIA in EIA issued by the Department of
Environment as well as the US EPA’s Human Health Risk Assessment Protocol.
6.5.1 Study Boundaries
The study boundary for EHIA is 5 km radius from the Project.
6.5.2 Assessment Standards
For acute health risk, exposure concentration or dose will be compared with the Malaysia Ambient Air
Quality Standard and Arizona Ambient Air Quality Standard (Appendix 3) and discussed in the EIA report.
For prediction of health impact, the reference concentration (RfC) will be referred to the US EPA
Integrated Risk Information System.
6.5.3 Description of Modelling Tools and Assessment Methodologies
The Health impact assessment (HIA) component will investigate potential public health impacts from
primary environmental influences such as air quality and water quality, on the population residing in the
vicinity of the proposed Project especially during the construction and operation stages The HIA
methodology will be based on the Guidance Document on HIA in EIA issued by the Department of
Environment as well as the US EPA’s Human Health Risk Assessment Protocol.
It is anticipated that main environmental influences from the proposed Project will be the changes to
ambient air quality. The air pollutants that will be modelled for their health effects are:
i. PM10 ii. NO2 iii. SO2
iv. HCl v. arsenic (as As) vi. cadmium (as Cd)
vii. lead (as Pb) viii. mercury (as Hg) ix. dioxins and furans
A description of the existing public health status will be attempted. This will involve describing the
present health status of the population residing in the vicinity of the proposed Project. It will involve both
primary and secondary data collection. Primary data on community health status will be obtained through
a health questionnaire survey of the residents within the proposed project’s zone of impact. Secondary data on disease morbidity will be requested from the nearest government hospital and health clinic to the
proposed project site.
To assess the public health risk of the proposed Project a health risk assessment (HRA) methodology
will be employed. The HRA will describe the public health impacts and risks on the population residing
within the zone of impact of the proposed Project during its construction and operational phases. It will
TERMS OF REFERENCE (TOR)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF HEALTHCARE
WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT RAMBAI, FASA 4C,
MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd Page 41
CK/EV803/8026/18 TOR Revision No.: 1 Revision Date: October 2018
employ the health risk assessment (HRA) approach adopted in the Guidance Document which
comprises the six basic steps of issues identification, hazard identification, dose-response assessment,
exposure assessment, risk characterization and uncertainty analysis. Data input into the HRA process
will be sourced from the health survey, air quality modelling outputs, water quality modelling outputs,
published epidemiological studies on health effects of air and water pollutants, and exposure parameters
database from the US EPA or ATSDR. The specific areas which will be encompassed as part of this HIA
will include, but will not be limited to:
Assessment of public health risks (both acute and chronic) associated with the proposed emission of
air pollutants from the Project during testing and commissioning and full operation. Assessment and
impact projection will be in consideration of any other accumulating sources nearby the proposed
Project site;
Assessment of public health risks (both acute and chronic) associated with any other activities which
at this stage of the assessment are not foreseen.
Based on the outcomes of the HRA process, appropriate mitigation and control measures will be
proposed to minimize the environmental health impacts on the impacted community.
Residual environmental health impacts on the impacted community, if any, will be identified and
adequately described. A proper environmental monitoring and auditing program will be proposed for the
residual impacts identified, if necessary.
6.5.4 Possible Mitigation Measures
Possible mitigation measures or best management practices from similar projects that may be used to
address the air quality impacts of this Project are as follow:
No open burning of any materials on-site is allowed.
Periodical impact monitoring of air quality at Project boundary and identified sensitive receptor.
Installation of proper air pollution control equipment.
Installation of Continuous Emission Monitoring System (CEMS) shall be conducted to monitor the
air emission parameters.
6.6 QUANTITATIVE RISK ASSESSMENT
Quantitative Risk Assessment (QRA) is the application of methodology to produce a numerical
representation of the frequency and extent of a specified level of exposure or harm, to specified people or
the environment, due to the operation of the Project.
6.6.1 Study Boundaries
The study boundary for QRA is 5 km radius from the Project.
TERMS OF REFERENCE (TOR)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF HEALTHCARE
WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT RAMBAI, FASA 4C,
MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd Page 42
CK/EV803/8026/18 TOR Revision No.: 1 Revision Date: October 2018
6.6.2 Assessment Standards
Risk Assessment criteria:
1 x 10-6 fatalities / person per year Individual Risk (IR) contour should not encompass involuntary
recipients of industrial risks such as residential areas, schools, hospitals and places of continuous
occupancy.
1 x 10-5 fatalities / person per year Individual Risk (IR) contour should not extend beyond industrial
developments.
6.6.3 Description of Modelling Tools and Assessment Methodologies
The principal stages of this risk assessment are briefly described as follows:
Data Collection - Information is collected and documented covering the following areas:
Description: the layout of the plant and proposed process.
Surrounding environment: the topography, meteorology, population distribution, possible ignition
sources within or surrounding the proposed Project site.
Safety measures: the measures available to prevent and/or mitigate possible accidents.
Hazard Identification - All potential hazards resulting from the failures of handling and storage of the
hazardous substances are identified. The identification process uses a mixture of experience from
previous QRA’s.
Frequency Analysis - All event outcome frequencies will be calculated based on generic data of
failure rates / leak frequencies applicable for each relevant industry.
Consequence Modelling - The consequences of each event are determined by established
modelling programs such as CIRRUS. The consequences are expressed as distance to levels, which
can cause fatalities.
Risk Presentation - The frequencies and the consequences of each event are combined to produce
overall measures of risk.
Major Risk Contributors - The risk generated by each accident scenario is ranked in terms of
initiating source and consequence type (i.e. explosion, jet fire, pool fire, etc.).
In examining the operations of the Project, all potential hazards arising from the incinerator facility
equipment failure will be identified. For this purpose, information on the incinerator facility layout will be
used for the identification of hazards. The only hazardous substance stored on-site is the fuel for the
incinerator, i.e. diesel. The QRA shall focus on all scenarios relevant to the handling and storage of diesel
within the plant. The possible hazardous scenarios that shall be evaluated are pool fires and its possible
impact towards the surrounding.
The results shall be presented in a risk contour plot representing the overall risk arising from accidents
which could result in fatalities on-site and off-site. The final stage of this assessment is to compare the
TERMS OF REFERENCE (TOR)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF HEALTHCARE
WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT RAMBAI, FASA 4C,
MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd Page 43
CK/EV803/8026/18 TOR Revision No.: 1 Revision Date: October 2018
public risk level arising from the operation of the incinerator plant with commonly acceptable risk levels.
Risk reduction measures and the effects of the mitigating measures will also be discussed to enhance the
safety of the plant.
6.6.4 Possible Mitigation Measures
Possible mitigation measures or best management practices from similar projects that may be used to
address the noise level of this Project is as follow:
Review and update the Emergency Response Plan (ERP) for the operation of the Project.
Enforce safety procedures to ensure authorised access only to the facility and further restrictions
are in place for limiting storage area access to approved persons only.
Perform regular emergency response drills (including desktop exercises), as well as feedback and
review sessions.
Conduct routine inspections of fire safety requirements (fire blankets, fire extinguishers, smoke
detectors, sprinklers, emergency lighting and fire-rated doors etc.
More detailed and definite mitigation measures will be discussed in the EIA report.
7 PROJECT TIMETABLE
Upon getting EIA approval and other necessary approval, the development of the Project will take about
12 months including testing and commissioning.
8 PROJECT ASSESSMENT TIMELINE
The proposed EIA timeline is as shown in Figure 10. This schedule may be revised accordingly as and
when new updates and significant information are received from the Contractor.
9 CONSIDERATION OF CONCURRENT PROJECTS
Based on initial site survey, there is no concurrent project adjacent to the Project site. Therefore no
cumulative impact to the surrounding areas is anticipated.
TERMS OF REFERENCE (TOR)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF HEALTHCARE WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32
& 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT RAMBAI, FASA 4C, MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd Page 44
CK/EV803/8026/18 TOR Revision No.: 1 Revision Date: October 2018
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48
Appointment
Information from Client
Site Survey and Land Use
Engagement with Relevant Government
Agencies on TOR (DOE and Ministry of Health)
Preparation of TOR
TOR to Client and Review
Submission of TOR to DOE
Review and Endorsement of TOR by DOE (TOR
Meeting)#
1st baseline sampling (air, water, noise), land
use survey (5 km)
2nd baseline sampling (air, water), land use
survey (5 km)
Engagement with Relevant Government
Agencies on fact finding / comment on the
Project
Data analyses and interpretation
Impact Assessment
EMP and Monitoring Programme
Public Dialogue
Report Compilation
Preparation and Submission of Draft EIA Report
to Client
Review of Draft DEIA Report by Client
Engagement with Relevant Government
Agencies to Inform of EIA Findings
Printing and Report QA & QC
Submission Final EIA report to DOE
EIA Report Display Public Review
EIA Approval Process (3 months) / EIA Meeting#
Activity
Figure 10: Proposed EIA Study Schedule
TERMS OF REFERENCE (TOR)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF HEALTHCARE
WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT RAMBAI, FASA 4C,
MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd Page 45
CK/EV803/8026/18 TOR Revision No.: 1 Revision Date: October 2018
APPENDIX A
ENVIRONMENTAL SCOPING INFORMATION (ESI)
MEDIVEST SDN BHD
ENVIRONMENTAL SCOPING INFORMATION (ESI)
ENVIRONMENTAL IMPACT ASSESSMENT
FOR
PROPOSED NEW INSTALLATION OF THERMAL TREATMENT
FACILITY FOR CENTRE OF HEALTHCARE WASTE
TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24,
25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN
BUKIT RAMBAI, FASA 4C, MUKIM TANJUNG MINYAK,
MELAKA
Reference: CK/EV803/8026/18 ESI (Revision 1)
Date: October 2018
Prepared by:
Chemsain Konsultant Sdn Bhd (130904-U) No. 41, 1st Floor, Jalan USJ 10/1D, 47630 UEP Subang Jaya, Selangor, Malaysia Tel: +603-56370163 Fax: +603-56370385
Second Schedule
ENVIRONMENTAL SCOPING INFORMATION (ESI)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF HEALTHCARE
WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT RAMBAI, FASA 4C,
MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd TOC iii
CK/EV803/8026/18 ESI Revision No.: 1 Revision Date: October 2018
TABLE OF CONTENTS
1 INTRODUCTION ............................................................................................................................... 1
1.1 ENVIRONMENTAL SCOPING INFORMATION (ESI) PREPARER ............................................................ 1
1.2 LEGISLATIVE REQUIREMENT .......................................................................................................... 1
1.3 PURPOSE OF ENVIRONMENTAL IMPACT ASSESSMENT ..................................................................... 1
1.4 PROCEDURAL STEPS FOR EIA ....................................................................................................... 1
2 BASIC INFORMATION OF PROJECT ............................................................................................ 3
2.1 PROJECT TITLE ............................................................................................................................. 3
2.2 PURPOSE AND NATURE OF PROJECT ............................................................................................. 3
2.3 PROJECT PROPONENT .................................................................................................................. 4
2.4 STATEMENT OF NEED .................................................................................................................... 5
2.5 PROJECT LOCATION ...................................................................................................................... 8
2.6 PROJECT COMPONENTS ................................................................................................................ 8
2.6.1 Former Incinerator Plant ..................................................................................................... 8
2.6.2 Existing Components .......................................................................................................... 9
2.6.2.1 Healthcare Waste Reception Area ............................................................................................ 9
2.6.2.2 Healthcare Waste Storage (Cold Room) ................................................................................... 9
2.6.2.3 Microwave Machines ................................................................................................................ 9
2.6.2.4 Infrastructures and Utilities........................................................................................................ 9
2.6.2.4.1 Water Supply .......................................................................................................................................... 9
2.6.2.4.2 Electricity ................................................................................................................................................ 9
2.6.2.4.3 Internet Network ..................................................................................................................................... 9
2.6.2.4.4 Storm Water Drainage System.............................................................................................................. 10
2.6.2.4.5 Other Facilities ...................................................................................................................................... 10
2.6.3 Upcoming Components..................................................................................................... 10
2.6.3.1 Incinerator Plant ...................................................................................................................... 10
2.6.3.1.1 Waste Feeding System ......................................................................................................................... 10
2.6.3.1.2 Primary Combustion – Feeding Ram System ........................................................................................ 11
2.6.3.1.3 Primary Combustion – Incinerator ......................................................................................................... 13
2.6.3.1.4 Secondary Combustion (Post Combustion) ........................................................................................... 16
2.6.3.1.5 Flue Gas Pre-Cooling ........................................................................................................................... 18
2.6.3.1.6 Sodium Bicarbonate (NaHCO3) Storing and Injection by Loss-in-Weight ............................................... 20
2.6.3.1.7 Activated Carbon Storing and Injection by Loss-in-Weight .................................................................... 21
2.6.3.1.8 Bag House Filter ................................................................................................................................... 21
2.6.3.1.9 Exhaust Fan ......................................................................................................................................... 22
2.6.3.1.10 Emission Monitoring Equipment ............................................................................................................ 23
2.6.3.1.11 Peripherals ........................................................................................................................................... 24
2.6.3.2 Truck and Bin Washing Area .................................................................................................. 29
2.6.3.3 Industrial Effluent Treatment System ...................................................................................... 29
2.7 DESIGN CRITERIA OF THE INCINERATOR ...................................................................................... 29
2.7.1 Key Design Parameters .................................................................................................... 29
2.8 PROCESS DESCRIPTION .............................................................................................................. 32
2.8.1 Handling of Healthcare Wastes at Source (On-Site Handling) ......................................... 32
2.8.1.1 Transportation of Healthcare Wastes to Project Site .............................................................. 36
2.8.2 Handling of Healthcare Wastes at Project Site (Off-site Handling) .................................. 37
2.8.2.1 Incineration Process ............................................................................................................... 37
2.8.2.2 Gas Cooling ............................................................................................................................ 38
2.8.2.3 Air Pollution Control System ................................................................................................... 38
2.8.2.4 Emission Monitoring ................................................................................................................ 38
2.8.2.5 Incinerator Plant Control System ............................................................................................ 39
ENVIRONMENTAL SCOPING INFORMATION (ESI)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF HEALTHCARE
WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT RAMBAI, FASA 4C,
MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd TOC iv
CK/EV803/8026/18 ESI Revision No.: 1 Revision Date: October 2018
2.8.2.6 Incinerator Plant Maintenance ................................................................................................ 39
2.8.2.7 Management of Bottom Ash and Fly Ash (SW 406) ................................................................ 39
2.8.2.8 Management of Fluff (SW 501) ............................................................................................... 39
2.8.2.9 Healthcare Waste Storage ...................................................................................................... 40
2.8.2.10 Cleansing and Disinfection of Wheeled Bins and Trucks ........................................................ 40
2.8.2.11 Incinerator Plant Balances ...................................................................................................... 40
2.9 PROJECT DEVELOPMENT SCHEDULE ............................................................................................ 40
2.10 PROJECT ACTIVITIES ............................................................................................................. 40
2.10.1 Pre-Construction Stage ..................................................................................................... 40
2.10.2 Construction Stage ............................................................................................................ 41
2.10.3 Operation and Maintenance Stage ................................................................................... 41
3 ALTERNATIVE CONSIDERATIONS .............................................................................................. 43
3.1 SITE OPTIONS............................................................................................................................. 43
3.1.1 New Site Option ................................................................................................................ 43
3.1.2 Existing Site Option ........................................................................................................... 43
3.2 TECHNOLOGY OPTIONS ............................................................................................................... 43
3.2.1 Counter Current Rotary Kiln .............................................................................................. 44
3.2.2 Co-Current Rotary Kiln ...................................................................................................... 45
4 MAJOR ELEMENT OF THE ENVIRONMENT IN THE VICINITY OF PROJECT SITE AND STUDY BOUNDARIES ................................................................................................................................ 47
4.1 PHYSICAL ENVIRONMENT ............................................................................................................ 47
4.1.1 Topography ....................................................................................................................... 47
4.1.2 Geology and Soil ............................................................................................................... 47
4.1.3 Hydrology and Drainage ................................................................................................... 48
4.1.4 Meteorology and Climate .................................................................................................. 48
4.1.5 Scope of Environmental Baseline Assessment ................................................................ 48
4.1.5.1 Surface Water Quality ............................................................................................................. 48
4.1.5.2 Ambient Air Quality ................................................................................................................. 50
4.1.5.3 Ambient Noise Level ............................................................................................................... 51
4.2 BIOLOGICAL ENVIRONMENT ......................................................................................................... 51
4.3 HUMAN ENVIRONMENT ................................................................................................................ 51
4.3.1 Land Use ........................................................................................................................... 51
5 OUTLINE OF PLANNING AND IMPLEMENTATION PROGRAMME ............................................ 57
5.1 REVIEW OF GUIDELINES AND ENVIRONMENTAL LEGISLATIONS ....................................................... 57
5.2 REVIEW OF PREVIOUSLY APPROVED EIA REPORTS OR STUDIES ................................................... 58
5.3 ENGAGEMENT WITH RELEVANT AGENCIES AND LOCAL COMMUNITY .............................................. 58
5.3.1 Socio-economic ................................................................................................................. 58
5.4 PROJECT IMPLEMENTATION ......................................................................................................... 59
5.5 PROJECT TIMETABLE................................................................................................................... 59
5.6 PROJECT ASSESSMENT TIMELINE ................................................................................................ 59
5.7 CONSIDERATION OF CONCURRENT PROJECTS .............................................................................. 59
6 ENVIRONMENTAL SENSITIVE AREAS ........................................................................................ 61
7 POSSIBLE SIGNIFICANT ENVIRONMENTAL IMPACTS ............................................................. 62
8 DESCRIPTION OF MODELLING TOOLS, ASSESSMENT METHODOLOGIES .......................... 63
8.1 WATER QUALITY ......................................................................................................................... 63
8.2 AIR QUALITY ............................................................................................................................... 63
8.3 WASTE MANAGEMENT ................................................................................................................. 65
8.4 HEALTH IMPACT ASSESSMENT ..................................................................................................... 66
8.5 QUANTITATIVE RISK ASSESSMENT ............................................................................................... 67
8.6 NOISE ........................................................................................................................................ 68
9 POSSIBLE MITIGATION MEASURES ........................................................................................... 69
ENVIRONMENTAL SCOPING INFORMATION (ESI)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF HEALTHCARE
WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT RAMBAI, FASA 4C,
MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd TOC v
CK/EV803/8026/18 ESI Revision No.: 1 Revision Date: October 2018
10 CONTENTS OF THE EIA REPORT ............................................................................................... 71
11 REFERENCES ................................................................................................................................ 71
LIST OF TABLES
Table 1: Approximate Coordinates of the Existing Centre of Healthcare Waste ...........................................8
Table 2: Counter Current Rotary Kiln Specification ..................................................................................... 14
Table 3: Two Vertical Cylindrical Chambers Specification .......................................................................... 17
Table 4: Retractable Burner Specification ................................................................................................... 17
Table 5: Flue Gas Pre-Cooling System Specification ................................................................................. 18
Table 6: Flue Gas to Thermal Oil Heat Exchanger Specification ................................................................ 19
Table 7: Thermal Oil Pump Skid .................................................................................................................. 19
Table 8: Bag House Filter Specifications .................................................................................................... 22
Table 9: Exhaust Fan Specifications ........................................................................................................... 23
Table 10: Emission Monitoring Equipment .................................................................................................. 24
Table 11: Chimney Stack Details ................................................................................................................ 25
Table 12: Incinerator Operating Standards ................................................................................................. 30
Table 13: Emission Standards –European Union and Malaysia ................................................................. 30
Table 14: Typical Medical Waste Chemical Composition ........................................................................... 31
Table 15: Summary of General Technical Characteristic of the Incinerator ............................................... 31
Table 16: Healthcare Wastes Characteristics ............................................................................................. 33
Table 17: Proximate Analysis of Clinical Waste .......................................................................................... 33
Table 18: Ultimate Analysis of Clinical Waste ............................................................................................. 33
Table 19: Approved Products Used for CWMS ........................................................................................... 34
Table 20: Healthcare Wastes Collection from Waste Generators ............................................................... 35
Table 21: Proposed Baseline Water Quality Locations ............................................................................... 49
Table 22: Proposed Water Quality Parameters ........................................................................................... 49
Table 23: Proposed Baseline Ambient Air Quality Sampling Locations ...................................................... 50
ENVIRONMENTAL SCOPING INFORMATION (ESI)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF HEALTHCARE
WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT RAMBAI, FASA 4C,
MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd TOC vi
CK/EV803/8026/18 ESI Revision No.: 1 Revision Date: October 2018
Table 24: Proposed Test Parameters for Ambient Air Quality .................................................................... 50
Table 25: Proposed Baseline Noise Measurement Locations .................................................................... 51
Table 26: Land Use within 3 km radius ....................................................................................................... 54
Table 27: Environmental Sensitive Areas (ESA) - Settlement .................................................................... 61
Table 28: Anticipated Significant Environmental Impacts ........................................................................... 62
Table 29: Possible Mitigation Measures ...................................................................................................... 69
LIST OF PLATES
Plate 1: Skip Hoist Mechanism .................................................................................................................... 11
Plate 2: Skip Tilting Mechanism .................................................................................................................. 11
Plate 3: Bin Weighing Unit ........................................................................................................................... 11
Plate 4: Feeding Hopper .............................................................................................................................. 13
Plate 5: Guillotine Door ................................................................................................................................ 13
Plate 6: Hydraulic Ram ................................................................................................................................ 13
Plate 7: Stationary Part ................................................................................................................................ 14
Plate 8: Rotary Kiln ...................................................................................................................................... 15
Plate 9: Rotary Motor ................................................................................................................................... 15
Plate 10: Reduced Cylindrical Section for Ash Evacuation ......................................................................... 15
Plate 11: Supporting Frame .......................................................................................................................... 16
Plate 12: Burner ........................................................................................................................................... 16
Plate 13: Post Combustion – Upper Part of Stationary ............................................................................... 17
Plate 14: Post Combustion – Retractable Burner ........................................................................................ 18
Plate 15: Flue Gas Pre-Cooling System ...................................................................................................... 18
Plate 16: Thermal Oil Heat Exchanger ........................................................................................................ 19
Plate 17: Thermal Oil Pump Skid ................................................................................................................ 20
Plate 18: Sodium Bicarbonate Storing and Injection ................................................................................... 21
ENVIRONMENTAL SCOPING INFORMATION (ESI)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF HEALTHCARE
WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT RAMBAI, FASA 4C,
MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd TOC vii
CK/EV803/8026/18 ESI Revision No.: 1 Revision Date: October 2018
Plate 19: Activated Carbon Storing and Injection ........................................................................................ 21
Plate 20: Bag House Filter ........................................................................................................................... 22
Plate 21: Exhaust Fan ................................................................................................................................. 23
Plate 22: Hydraulic Pack ............................................................................................................................. 24
Plate 23: Chimney Stack ............................................................................................................................. 25
Plate 24: Air Compressor Assembly ............................................................................................................ 26
Plate 25: Emergency By-pass ..................................................................................................................... 26
Plate 26: Dust Hopper and Container.......................................................................................................... 27
Plate 27: Liquid Injection System ................................................................................................................ 27
Plate 28: Safety Valve ................................................................................................................................. 28
Plate 29: MCC Power Switch ...................................................................................................................... 28
Plate 30: PLC Switch Board ........................................................................................................................ 28
Plate 31: Control Panel ................................................................................................................................ 29
Plate 32: PC Screen (Sample) .................................................................................................................... 29
Plate 33 Existing Project site condition ....................................................................................................... 52
Plate 34: Location of former incinerator. The new incinerator will be placed here. ..................................... 52
Plate 35: Existing Microwave Facilities ....................................................................................................... 53
LIST OF FIGURES
Figure 1: General Overview of EIA Procedure
Figure 2: Project of Clinical Waste Received Against Treatment Capacity
Figure 3: Project Location Map
Figure 4: Project Layout
Figure 5: Simplified Schematic Diagram
Figure 6: Mass Balance
Figure 7: Organisation Chart
Figure 8: Counter Current Rotary Kiln
ENVIRONMENTAL SCOPING INFORMATION (ESI)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF HEALTHCARE
WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT RAMBAI, FASA 4C,
MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd TOC viii
CK/EV803/8026/18 ESI Revision No.: 1 Revision Date: October 2018
Figure 9: Co-Current Rotary Kiln
Figure 10: Geology Map
Figure 11: Soil Map
Figure 12: Hydrology Map
Figure 13: Baseline Sampling Locations
Figure 14(a): Land Use within 500 m Radius
Figure 14(b): Land Use within 1 km Radius
Figure 14(c): Land Use within 3 km Radius
Figure 14(d): Land Use within 5 km Radius
Figure 15: Future Land Use Map
Figure 16: Proposed EIA Study Schedule
Figure 17: Environmental Sensitive Areas
APPENDICES
Appendix 1 National Water Quality Standards for Malaysia
Appendix 2 Malaysian Ambient Air Quality Guidelines
Appendix 3 The Planning Guidelines for Environmental Noise Limits and Control 2007
ENVIRONMENTAL SCOPING INFORMATION (ESI)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF
HEALTHCARE WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT
RAMBAI, FASA 4C, MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd TOC 1
CK/EV803/8026/18 ESI Revision No.: 1 Revision Date: October 2018
1 INTRODUCTION
This Environmental Scoping Information (ESI) is to outline the scope of Environmental Impact
Assessment (EIA) study that Chemsain Konsultant Sdn Bhd (Chemsain) will conduct for
“PROPOSED NEW INSTALLATION OF THERMAL TREATEMENT FACILITY FOR CENTRE OF
HEALTHCARE WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33,
JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT RAMBAI, FASA 4C, MUKIM TANJUNG
MINYAK, MELAKA” (“the Project”). This is to ensure that the study could fulfil the requirement in the
Department of Environment’s (DOE) Environmental Impact Assessment (EIA) Guidelines 2016.
1.1 ENVIRONMENTAL SCOPING INFORMATION (ESI) PREPARER
This ESI is prepared by Chemsain Konsultant Sdn Bhd, the EIA Consultant appointed by Medivest Sdn.
Bhd. Corresponding details of the company are as follows:
EIA Consultant : Chemsain Konsultant Sdn Bhd (130904-U)
Address : No. 41, 1st Floor, Jalan USJ 10/1D,
UEP Subang Jaya, 47620 Subang Jaya
Selangor
Contact person : Ms Marina Roland Nawe (EIA Team Leader)
Telephone : +603 5637 0163
Fax : +603 5637 0385
Email : [email protected]
1.2 LEGISLATIVE REQUIREMENT
Development of the Project which include installation of new thermal treatment facility at the existing
centre of healthcare waste treatment plant owned by Medivest Sdn Bhd (MSB) has been identified as a
prescribed activity under the Environmental Quality (Prescribed Activities) (Environmental Impact
Assessment) Order 2015 as follows:
Second Schedule – Activity No. 14: Waste Treatment and Disposal
Sub-activity (a): Scheduled waste (i) Construction of thermal treatment plant
In compliance with Section 34A of the Environmental Quality Act, 1974, an EIA report for the Project is
to be prepared for approval from Department of Environment (DOE).
ENVIRONMENTAL SCOPING INFORMATION (ESI)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF
HEALTHCARE WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT
RAMBAI, FASA 4C, MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd TOC 1
CK/EV803/8026/18 ESI Revision No.: 1 Revision Date: October 2018
1.3 PURPOSE OF ENVIRONMENTAL IMPACT ASSESSMENT
The objective of the EIA study is to ensure that all impacts, direct and indirect, especially environmental,
social and economics associated with the proposed development is fully examined and addressed.
Consistent with this objective, the EIA report shall be a self-contained and comprehensive document
which provides:
For the general public, a basis for understanding the proposal, alternatives and preferred
solutions, the existing environment and the potential changes to the environment that may occur
if the proposal is implemented;
For decision maker, information for assessing the proposed development and likely impacts of
all associated development with respect to environment, legislative and policy provisions; and
For the initiator, a comprehensive set of environmental requirements are incorporated in the
project from planning stage to end of project.
1.4 PROCEDURAL STEPS FOR EIA
The EIA and its review process are illustrated in Figure 1. This EIA process is based on the
Environment Impact Assessment Guidelines in Malaysia 2016 recently published by the Department of
Environment (DOE). It provides assessors with a step-by-step guide of EIA process.
ENVIRONMENTAL SCOPING INFORMATION (ESI)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF
HEALTHCARE WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT
RAMBAI, FASA 4C, MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd TOC 2
CK/EV803/8026/18 ESI Revision No.: 1 Revision Date: October 2018
Source: Environment Impact Assessment Guidelines in Malaysia (2016)
Figure 1: General Overview of EIA Procedure
ENVIRONMENTAL SCOPING INFORMATION (ESI)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF
HEALTHCARE WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT
RAMBAI, FASA 4C, MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd TOC 3
CK/EV803/8026/18 ESI Revision No.: 1 Revision Date: October 2018
2 BASIC INFORMATION OF PROJECT
2.1 PROJECT TITLE
The Project’s title is “PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR
CENTRE OF HEALTHCARE WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25,
32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT RAMBAI, FASA 4C, MUKIM
TANJUNG MINYAK, MELAKA”.
2.2 PURPOSE AND NATURE OF PROJECT
Medivest Sdn Bhd (MSB) is one of the concession companies providing Healthcare Waste Management
Services (HWMS) for Ministry of Health Malaysia (“MOH”). The HWMS include storage, collection,
transportation, treatment and disposal of healthcare waste.
MSB intends to install new thermal treatment facility at its existing centre of healthcare waste treatment
plant located at Lot 24, 25, 32 & 33, Jalan PBR 37, Kawasan Perindustrian Bukit Rambai, Fasa 4C
Mukim Tanjung Minyak, Melaka.
The installation works shall include planning, construction, installation and operation of a counter-current
rotary kiln type incinerator with a capacity to treat 20 MT/day of healthcare waste. This counter-current
rotary kiln type incinerator is developed by BIC Systems Asia Pacific Pte Ltd.
The existing plant commenced its operation in 1997 using stepped hearth incineration system and has
ceased the incinerator operation in March 2016. Since the incinerator facility shut down in March 2016,
the incoming clinical wastes is currently treated using microwave system.
To date, the existing centre of healthcare is only treating SW 404 (pathogenic wastes, clinical wastes or
quarantined materials) using two existing microwave machines Model AMB Ecosteryl 250 (licensed since
2016) and Model MDS 2481 (licensed since 2018).
With the proposed installation of a counter-current rotary kiln incinerator, the Project Proponent also plan
to treat scheduled wastes under the following scheduled wastes codes at the upgraded facility:
Scheduled Waste Source
SW 403 – Discarded drugs containing psychotropic
substances or containing substances that are toxic,
harmful, carcinogenic, mutagenic or teratogenic
External (MOH hospitals and laboratory)
SW 409 – Disposed containers, bags or equipment
contaminated with chemicals, pesticides, mineral oil
or scheduled wastes
External (MOH hospitals and laboratory)
Internal
SW 429 – Chemicals that are discarded or off-
specification
MOH hospitals and laboratory
ENVIRONMENTAL SCOPING INFORMATION (ESI)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF
HEALTHCARE WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT
RAMBAI, FASA 4C, MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd TOC 4
CK/EV803/8026/18 ESI Revision No.: 1 Revision Date: October 2018
Scheduled Waste Source
SW 430 – Obsolete laboratory chemicals External (MOH hospitals and laboratory)
Internal
SW 410 – Rags, plastics, paper or filters
contaminated with scheduled wastes
External (MOH hospitals and laboratory)
Internal
SW 204 – Sludges containing one or several metals
including chromium, copper, nickel, zinc, lead,
cadmium, aluminium, tin, vanadium and berylium
Internal – IETS
When the new incinerator is in operation, the two microwave machines will be on standby mode and will
only be used when the incinerator is shut down.
2.3 PROJECT PROPONENT
Medivest Sdn Bhd is the Project Proponent of this Project. Corresponding details of MSB are as follows:
Project Proponent : MEDIVEST SDN BHD (224192-H)
Address : Suite 13.01 Penthouse, Wisma E & C
No. 2, Lorong Dungun Kiri
Damansara Heights
50490 Kuala Lumpur
Telephone : +603 209 21000 ext 804
Fax : +603 209 25000
Contact person : Mr Salleh bin Tahir (CEO)
Email : [email protected]
ENVIRONMENTAL SCOPING INFORMATION (ESI)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF
HEALTHCARE WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT
RAMBAI, FASA 4C, MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd TOC 5
CK/EV803/8026/18 ESI Revision No.: 1 Revision Date: October 2018
2.4 STATEMENT OF NEED
Since 1996, MSB has operated two units of incinerators, for clinical waste treatment. However the
treatment of clinical wastes using incinerators have been replaced with a microwave machine (Microwave
AMB Ecosteryl 250) in 2016. A second microwave machine (Microwave MDS 2481) has been installed
and licensed in May 2018.
MSB planned to upgrade its centre of healthcare waste treatment facilities based on the following
considerations:
i. Increase of Clinical Waste Volume
Projection of future clinical waste volume against current capacity of the existing centre of healthcare
facilities is shown in Figure 2. Volume of clinical wastes is anticipated to increase approximately 5%
annually. MSB currently receives 11.0 MT/day (on average). By operating two units of the microwave
machines, MSB treatment capacity is 15.0 MT/day. By year 2025, MSB is expecting to receive 14.4
MT/day which is 96% of the total treatment capacity. Due to this projection on clinical waste load
annual increment, MSB shall prepare the facility earlier, to ensure treatment capacity is always more
than volume of the waste being generated. This is significant as to avoid the clinical waste backlog
incident which occurred around 2014-2015. Replacing the old incinerator with this new incinerator,
with 20.0 MT/ day treatment capacity, MSB will secure treatment capacity which ensure backlog
incident not repeating in future.
ENVIRONMENTAL SCOPING INFORMATION (ESI)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF HEALTHCARE WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32
& 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT RAMBAI, FASA 4C, MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd TOC 6
CK/EV803/8026/18 ESI Revision No.: 1 Revision Date: October 2018
Figure 2: Projection of Healthcare Wastes Received Against Treatment Capacity
ENVIRONMENTAL SCOPING INFORMATION (ESI)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF
HEALTHCARE WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT
RAMBAI, FASA 4C, MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd TOC 7
CK/EV803/8026/18 ESI Revision No.: 1 Revision Date: October 2018
ii. Best treatment for Clinical Waste
Incineration process is the best treatment for clinical waste. Treating clinical waste through
incineration process is also recommended by Department of Environments (DOE) Malaysia whereby
it ensures almost complete destruction of the clinical waste and volume of the by-product produced
from this process is significantly small, less than 10% volume of the waste treated.
iii. Treatment Centre for Healthcare Waste
New concessionaire agreement with Ministry of Health (MOH), Malaysia in 2016 requires MSB not to
manage clinical waste only but also other scheduled wastes arise from healthcare practices. The
other scheduled wastes are SW 403 (discarded drugs containing psychotropic substances or
containing substances that are toxic, harmful, carcinogenic, mutagenic or teratogenic); SW 409
(disposed containers, bags or equipment contaminated with chemicals, pesticides, mineral oil or
scheduled wastes); SW 429 (chemicals that are discarded or off-specification), SW 430 (obsolete
laboratory chemicals) and SW 410 (rags, plastics, paper or filters contaminated with scheduled
wastes). By replacing with new, modern and advance technology incinerator, it is capable to treat
various type of healthcare wastes, not only treating clinical waste.
iv. Environmental-friendly Technology
Previous incinerator used by MSB is stepped hearth-type incinerator which technology origin from
Australia. MSB has conducted technical and commercial evaluation on which technology suit the best
with the company’s requirement. Based on the evaluations, technology offered by BIC Systems Asia
Pacific Pte Ltd (BIC) is chosen as the best technology. BIC offers rotary kiln-type incinerator with
counter-current design.
Advantages of the technology to the environmental basis are:
Low consumption of fuel.
The incinerator will be using counter-flow process which allow very minimum or even non-
consumption of fuel during ideal operation. The fuel only consumed during start-up process which
takes less than 24 hours.
Better air emission.
The incinerator system is well accepted with 55 units has been operated all around Europe, Africa,
Middle East and Asia. Main factor of this acceptance due to application of modern and highly efficient
air pollutant control system which treats the combustion effectively before being emitted to
environment. The system proven to be able to comply with stringent emission standard worldwide.
Low production of by-product.
No effluent produced from the incinerator. During the incineration process, the ash produced is only
8% from the original load.
ENVIRONMENTAL SCOPING INFORMATION (ESI)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF
HEALTHCARE WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT
RAMBAI, FASA 4C, MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd TOC 8
CK/EV803/8026/18 ESI Revision No.: 1 Revision Date: October 2018
v. Collection of Clinical Waste from Private Sectors
MSB intends to collect and treat clinical waste from private sectors. The private sectors include
private hospitals, haemodialysis centres and clinics.
2.5 PROJECT LOCATION
The Project is located at the existing centre of healthcare waste treatment facilities at Lot 24, 25, 32 & 33
within Kawasan Perindustrian Bukit Rambai Fasa 4C, Mukim Tanjung Minyak, Melaka. The total area of
the existing centre is 8, 408 m2 (about 2 acres). Total land area involved for development of the
incinerator plant is only about 2, 602 m2. The Project location map is shown as Figure 3. The Project site
is located about 17 km from the Melaka town. The Project site is accessible via Lebuh AMJ/Route 19 –
Lebuh SPA/ Route 33 – Jalan M9 – Jalan PBR 37.
Approximate coordinates of the existing centre of healthcare waste treatment plant boundaries are as
tabulation in Table 1.
Table 1: Approximate Coordinates of the Existing Centre of Healthcare Waste
Latitude Longitude Description
2°16’49.17” 102°10’51.27” North Boundary
2°16’44.55” 102°10’54.15” Southeast Boundary
2°16’44.59” 102°10’52.32” South Boundary
2°16’45.83” 102°10’52.22” Middle Boundary
2°16’45.83” 102°10’50.55” West Boundary
2.6 PROJECT COMPONENTS
The Project involves planning, construction, installation and operation of an incinerator with a capacity to
treat 20 MT/day of healthcare waste. Generally, the main components of the incinerator plant facility
include waste reception and storage, waste combustion, gas cooling, air pollution control and ash
receiving and storage system, truck and bin washing system and industrial effluent treatment system
(IETS).
Figure 4 shows the layout of the Project components that consist of storage areas (for healthcare waste,
chemicals and ash), plant building (that accommodates the new incinerator area, existing administration
office and existing microwave facilities) and bin washing/ disinfection area. The Project components are
elaborated in the following sub-sections.
2.6.1 Former Incinerator Plant
The existing plant commenced its operation in 1997 using stepped hearth incineration system. During the
operation of the former incinerator plant, there were two incinerator lines equipped with respective air
pollution control systems. Both incinerators, were stepped hearth system, have same exact specifications
and treatment capacity of 7.2 MT/day (300 kg/hr).
THAILAND
KEDAHPulauLangkawi
ALOR SETAR
PERLISKANGAR
PINANGPULAU
TOWN
KELANTAN
KOTA BHARU
TERENGGANU
PERAKTERENGGANU
IPOH
PAHANGKUANTAN
SELANGOR
KUALA LUMPURSHAH ALAM
SEREMBAN
NEGERI
MELAKAJOHOR
JOHORBAHRU
TiomanPulau
SINGAPURA
KUALA
GEORGE
SEMBILAN
CHEMSAIN KONSULTANT SDN. BHD.
LEGEND:
PROJECT
LOCATION
FIGURE 3
ENVIRONMENTAL SCOPING INFORMATION (ESI)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF
HEALTHCARE WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT
RAMBAI, FASA 4C, MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd TOC 9
CK/EV803/8026/18 ESI Revision No.: 1 Revision Date: October 2018
MSB has ceased the incinerator operation in March 2016. Abandonment Management Plan was prepared
and submitted to DOE Negeri Melaka in May 2017 and it was approved on 6 June 2017. Dismantling and
removal works were completed on 28 November 2017.
2.6.2 Existing Components
2.6.2.1 Healthcare Waste Reception Area
This area is allocated to house the unloading and weighing of received healthcare waste. It is for temporary
storage before further feeding process in the system.
2.6.2.2 Healthcare Waste Storage (Cold Room)
At the end of the day, untreated healthcare wastes will be stored in the cold storage area before being
processed during the following day. There are six existing cold room stores with a capacity of 15 MT each
(total capacity of 90 MT), temperature of below 6 °C and 8 holding days.
2.6.2.3 Microwave Machines
There are two microwave machines available at the Project site. Details of the machines are summarised
as follows:
i. Model AMB Ecosteryl 250
This microwave machine is from Belgium and has a capacity of 6 MT/day. License for operation was
obtained in 2016. This microwave machine is currently operating as the main clinical waste treatment
facility at the Project site.
ii. Model MDS 2481
This microwave machine is from the US. It has a capacity of 9 MT/day or 270 MT/month. License for
operation was obtained in May 2018.
2.6.2.4 Infrastructures and Utilities
2.6.2.4.1 Water Supply
Water supply requirement for ancillary facilities is estimated at 250m3/month (average). Since the Project
site is an existing healthcare waste treatment facility, water supply distribution pipe, water pump house
and storm water drainage system are already available at site. Oil sumps, septic tank, holding tank and
sewerline are also already installed at site.
2.6.2.4.2 Electricity
Electricity supply requirement for the incinerator is estimated about 50 kWh. Meanwhile for the ancillary
facilities the electricity requirement is 80 kWh (average).
2.6.2.4.3 Internet Network
The Project site requires internet speed of 4Mbps for computer networking.
ENVIRONMENTAL SCOPING INFORMATION (ESI)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF
HEALTHCARE WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT
RAMBAI, FASA 4C, MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd TOC 10
CK/EV803/8026/18 ESI Revision No.: 1 Revision Date: October 2018
2.6.2.4.4 Storm Water Drainage System
There is an existing storm water drainage system around the Project boundary. Storm water within the
Project area will be channelled to existing perimeter drainage system and it will be discharged off-site to
the existing drainage system available within the Kawasan Perindustrian Bukit Rambai, Fasa 4C.
2.6.2.4.5 Other Facilities
Other facilities available at the Project site include main office, workshop, scheduled waste store, general
room and staff room.
2.6.3 Upcoming Components
2.6.3.1 Incinerator Plant
An opened but roofed pad area will accommodate for combustion / incineration process block.
Components of the incinerator plant are summarised below:
2.6.3.1.1 Waste Feeding System
Automated with minimum manual intervention. Skip hoist system comprises of:
a) A hydraulically operated automatic skip hoist mechanism
Working pressure hydraulics: 100 barG
Hydraulic oil: ARO ISO 46
Max lifting weight (net): 250 Kg
b) A hydraulically operated automatic skip tilting mechanism
Working pressure hydraulics: 100 barG
Hydraulic oil: ARO ISO 46
Max tilting weight (net): 250 kg
A bin holding structure: For standard 850 l or 240 l Euro bins
c) A weighing unit
Maximum load: 1000 kg
Precision: 1 kg
ENVIRONMENTAL SCOPING INFORMATION (ESI)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF
HEALTHCARE WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT
RAMBAI, FASA 4C, MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd TOC 11
CK/EV803/8026/18 ESI Revision No.: 1 Revision Date: October 2018
Plate 1: Skip Hoist Mechanism
Plate 2: Skip Tilting Mechanism
Plate 3: Bin Weighing Unit
2.6.3.1.2 Primary Combustion – Feeding Ram System
Features of the feeding ram system:
Feed hopper height is 5 meters, from where the waste is introduced.
Suitable level indication/switches are incorporated.
Suitable weight monitoring system is incorporated.
The bottom of the hopper that feeds to the incinerator has interlocks to protect the hopper from the
high temperature in the incinerator.
The bottom of the hopper is designed sufficiently strong to receive impact from the waste dropping
and not bend over time.
Dumping the waste from the feed hopper to the incinerator is monitored by the interlock system, so
that the incinerator is not overloaded or running without feed.
ENVIRONMENTAL SCOPING INFORMATION (ESI)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF
HEALTHCARE WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT
RAMBAI, FASA 4C, MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd TOC 12
CK/EV803/8026/18 ESI Revision No.: 1 Revision Date: October 2018
Feeding ram design is trouble free and very versatile.
A scraper will be installed to prevent waste from adhering onto the ram.
The ram has improved stiffeners to prevent it from bending over time.
Cooling water injection is foreseen in the feeding area.
The primary combustion comprises of:
a) A Feed Hopper
Pneumatic cylinder working pressure: 8 barG
Power supply: 24VDC
Length: 1500 mm
Width: 1500 mm
Height: 2000 mm
Mild steel thickness: 10 mm
b) A Hydraulic Ram
Working pressure: 100 barG
Length: 1250 mm
Width: 1000 mm
Height: 500 mm
Mild steel thickness: 16 mm
c) A Guillotine Door
Working pressure pneumatic cylinder: 8 barG
Grease type door tracks: graphite or copper powder based
Insulation: refractory lined with concrete
Mild steel: 6 - 10 mm
Length: 250 mm
Width: 1500 mm
Height: 2100 mm
Refractory steel back plate: Included
ENVIRONMENTAL SCOPING INFORMATION (ESI)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF
HEALTHCARE WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT
RAMBAI, FASA 4C, MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd TOC 13
CK/EV803/8026/18 ESI Revision No.: 1 Revision Date: October 2018
Plate 4: Feeding Hopper
Plate 5: Guillotine Door
Plate 6: Hydraulic Ram
2.6.3.1.3 Primary Combustion – Incinerator
Features of the incinerator:
The incinerator is equipped with a diesel oil burner, which will start automatically when the
temperature in the kiln drops below a preset value.
There is a robust and foolproof ash collection system for the incinerator. No ash/ partially burned
waste shall be dropping from any part of the incinerator.
A liquid injection system for the liquid waste is included.
The incinerator comprises:
a) A Stationary Part
A stationary part that links the feed system to the rotary kiln and serving as a flue gas collector
between the kiln and the post combustion chamber (mild steel sheet of 6 - 8 mm and is lined with an
85 % alumina containing refractory concrete). The improved version includes the modification of the
voute above the feeding mouth and the addition of a liquid waste injection system.
ENVIRONMENTAL SCOPING INFORMATION (ESI)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF
HEALTHCARE WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT
RAMBAI, FASA 4C, MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd TOC 14
CK/EV803/8026/18 ESI Revision No.: 1 Revision Date: October 2018
Plate 7: Stationary Part
b) A Counter Current Rotary Kiln
The rotary kiln, which is a cylindrical combustion chamber in 10 mm mild steel sheet lined with 200
mm of refractory concrete containing 85 % alumina. The refractory lined ash extraction flights at the
rear of the kiln have been redesigned. Refractory lining made of high alumina (85%) high density
castable materials. The kiln now has a VSD motor control with integrated management of motor
parameters. This way, automatic action can be taken in case of increased kiln friction.
Table 2: Counter Current Rotary Kiln Specification
Type BIR 375
External diameter 2000 mm
Internal diameter 1600 mm
Length 4650 mm
Volume 12 m3
Thermal capacity 3,75 Gcal/Hr
Design CV of waste 2000 - 10.000 kcal/kg (8372 - 41860 kJ/kg)
Residual organic carbon content of bottom ash
2 % maximum
Operating temperature 900 °C to 1000 °C
Rotary speed 1.5 rev/min (max.)
Source: BIC Systems Asia Pacific Pte Ltd. (2018)
ENVIRONMENTAL SCOPING INFORMATION (ESI)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF
HEALTHCARE WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT
RAMBAI, FASA 4C, MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd TOC 15
CK/EV803/8026/18 ESI Revision No.: 1 Revision Date: October 2018
Plate 8: Rotary Kiln
Plate 9: Rotary Motor
c) Kiln rotation CW/CCW
Power: 2x2.2 Kw
Tension: 3 x 400/50Hz + N
Rotational speed outgoing shaft: 1.5 rpm
Control: by VSD
d) A Cylindrical Section With Reduced Diameter For Ash Evacuation
Refractory lining made of high alumina (85%) high density castable materials. Refractory steel (AISI
310) flame deflector for the burner flame will be installed.
External diameter: 1100 mm
Internal diameter: 900 mm
Length: 850 mm
Volume: 0.7 m3
Plate 10: Reduced Cylindrical Section for Ash Evacuation
e) A Supporting Frame
Comprises of four supporting wheels and one trust wheel on self-lubricating bearing and a motor
redactor.
ENVIRONMENTAL SCOPING INFORMATION (ESI)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF
HEALTHCARE WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT
RAMBAI, FASA 4C, MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd TOC 16
CK/EV803/8026/18 ESI Revision No.: 1 Revision Date: October 2018
Plate 11: Supporting Frame
f) A Burner
Burner with thermal power rating of 90 kW and requires 3 x 400/50Hz + N power supply.
Plate 12: Burner
g) A De-Ashing Chamber
Features of the de-ashing system:
The bottom ash bin replacement system is manually done for optimum reliability. The bins for ash
collection cannot be equipped with level sensors because of the presence of the burner flame. A
timer system is also not reliable to monitor the levels. These principles also apply to the de-
ashing system for the fly ash.
2.6.3.1.4 Secondary Combustion (Post Combustion)
Features of post combustion chamber:
Fuel/Air ratio is on auto-control
Fuel flow is measured and recorded
Lo, Lo-Lo, Hi and Hi-Hi temperature alarms are included
High temperature and low temperature trips are incorporated.
For the post combustion chamber, burner flame failure signal will trip the incinerator
ENVIRONMENTAL SCOPING INFORMATION (ESI)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF
HEALTHCARE WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT
RAMBAI, FASA 4C, MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd TOC 17
CK/EV803/8026/18 ESI Revision No.: 1 Revision Date: October 2018
The post combustion zone comprises of:
a) The upper part of the Stationary Zone
Plate 13: Post Combustion – Upper Part of Stationary
b) Two vertical cylindrical chambers
Table 3: Two Vertical Cylindrical Chambers Specification
Type BIR 375
Length 6000 mm
Width 1500 mm
Height -
Steel mild steel sheet 6 mm
Insulation lined with 150 mm refractory concrete 85 % alumina content
Inspection Inspection doors at bottom and top
Source: BIC Systems Asia Pacific Pte Ltd. (2018)
c) A Retractable Burner
The retracting mechanism is actuated by one single horizontal compressed air cylinder, protected
from radiant heat.
Table 4: Retractable Burner Specification
Type BIR 375
Thermal power rating 90 Kw
Power supply 3 x 400/50Hz + N
Working pressure pneumatic cylinder
8 barG
Source: BIC Systems Asia Pacific Pte Ltd. (2018)
ENVIRONMENTAL SCOPING INFORMATION (ESI)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF
HEALTHCARE WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT
RAMBAI, FASA 4C, MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd TOC 18
CK/EV803/8026/18 ESI Revision No.: 1 Revision Date: October 2018
Plate 14: Post Combustion – Retractable Burner
2.6.3.1.5 Flue Gas Pre-Cooling
A flue gas pre-cooling system consists of a flue gas inlet flange fitted with a butterfly valve operated by a
servo motor. Purpose is to reduce the temperature at the heat exchanger inlet below fusion point of the
particulates to avoid slagging. This system is to prevent any risk of corrosion.
Table 5: Flue Gas Pre-Cooling System Specification
Type BIR 375
Maximum inlet temperature 1200 °C
Exit temperature 800 °C
Maximum flow rate 8000 Nm3/h
Source: BIC Systems Asia Pacific Pte Ltd. (2018)
Plate 15: Flue Gas Pre-Cooling System
2.6.3.1.5.1 A Flue Gas to Thermal Oil Heat Exchanger
Features of the Flue gas heat exchanger:
The heat exchanger is designed to be trouble-free
Online back blowing facility by ultrasonic soot blowers are foreseen to blow off accumulated soot and
dust
ENVIRONMENTAL SCOPING INFORMATION (ESI)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF
HEALTHCARE WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT
RAMBAI, FASA 4C, MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd TOC 19
CK/EV803/8026/18 ESI Revision No.: 1 Revision Date: October 2018
Vertical dual pass water (thermal fluid) tube heat exchanger has been designed for easy access and
maintenance. Large inspection doors at the inlet, as well as at the outlet of the exchanger allow easy
and quick access to the pipe bundles and allow quick cleaning by means of a vacuum cleaner
Automatic evacuation of fly ash by rotary valve into a removable steel bin with quick couplings
Table 6: Flue Gas to Thermal Oil Heat Exchanger Specification
Type BIR 375
Design inlet temperature 850 °C
Exit temperature 200 °C
Maximum flue gas flow rate 11000 Nm3/h
Source: BIC Systems Asia Pacific Pte Ltd. (2018)
Plate 16: Thermal Oil Heat Exchanger
2.6.3.1.5.2 A Thermal Oil Pump Skid
Highlighted features of new thermal oil system
The Thermal Oil system is designed for the full automation
Low oil flow will trigger the stand by pump
Oil return Hi-Hi temperature will trigger incinerator trip
The system mainly features two identical circulation pumps, one main and one back-up with auto switch-
over with their respective shut off valves.
Table 7: Thermal Oil Pump Skid
Type BIR 375
Electrical supply 3 x 400 V/ 50Hz + N
Pressure 2.0 bar
Flow rate 80 m3/h
Source: BIC Systems Asia Pacific Pte Ltd. (2018)
ENVIRONMENTAL SCOPING INFORMATION (ESI)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF
HEALTHCARE WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT
RAMBAI, FASA 4C, MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd TOC 20
CK/EV803/8026/18 ESI Revision No.: 1 Revision Date: October 2018
The system features a thermal filling pump and filling shut-off valves. Each pump can be separately
drained into a closed-loop drain system for spill-free and safe maintenance. The system also includes a
3-way control valve for temperature control and a safety by-pass valve.
Plate 17: Thermal Oil Pump Skid
2.6.3.1.6 Sodium Bicarbonate (NaHCO3) Storing and Injection by Loss-in-Weight
Features of chemical dosing system:
Dosing chemical flow with feed rate adjustable according to the quantity and quality of flue gas
Dosing chemical flow indication by loss-in-weight feed back
No/Low sensors give alarm to warn operators
The dosing system is designed to prevent clogging of bicarbonate powder
Replacement of bags is done at floor level
FIBC’s are attached to an easy to handle and easy to install solid steel frame
The system has maximum mass flowrate of 25 kg/h and requires 3 x 400 V/ 50Hz + N of electricity
supply.
The advantage of using Bicarbonate instead of lime, is that the neutralising reaction time is much (5x)
shorter and the reaction itself nearly stoichiometric. This results in using less reactant and a more
complete reaction and a nearly null emission of acids to the atmosphere. Further, using less reactant,
means less fly ashes to be evacuated.
ENVIRONMENTAL SCOPING INFORMATION (ESI)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF
HEALTHCARE WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT
RAMBAI, FASA 4C, MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd TOC 21
CK/EV803/8026/18 ESI Revision No.: 1 Revision Date: October 2018
Plate 18: Sodium Bicarbonate Storing and Injection
Plate 19: Activated Carbon Storing and Injection
2.6.3.1.7 Activated Carbon Storing and Injection by Loss-in-Weight
Features of chemical dosing system (similar to the above):
Dosing chemical flow with feed rate adjustable according to the quantity and quality of flue gas
Dosing chemical flow indication by loss-in-weight feed back
No/Low sensors give alarm to warn operators
The dosing system shall be designed to prevent clogging of bicarbonate powder
The system has maximum mass flowrate of 25 kg/h and requires 3 x 400 V/ 50Hz + N of electricity supply.
2.6.3.1.8 Bag House Filter
Features of bag filter house/system:
Auto back blow system on timer basis and on differential pressure basis, whichever triggers first
Manual back blow facility, which will override the auto settings
Bag filter, comes along with maintenance platform
Fly ash is collected at the bottom of the hoppers and is evacuated automatically by rotary air locks
into sealed container with automatic lid
ENVIRONMENTAL SCOPING INFORMATION (ESI)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF
HEALTHCARE WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT
RAMBAI, FASA 4C, MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd TOC 22
CK/EV803/8026/18 ESI Revision No.: 1 Revision Date: October 2018
Table 8: Bag House Filter Specifications
Type BIR 375
Tension electrical supply 3 x 400 V/ 50Hz + N
Maximum air pressure 6 barG
Flow rate 30,000 m3/h
Design inlet temperature 200 °C
No. of sleeves 432
Material for sleeves Teflon needle felt
Removal of fly-ash By Rotary air locks
Source: BIC Systems Asia Pacific Pte Ltd. (2018)
Plate 20: Bag House Filter
2.6.3.1.9 Exhaust Fan
Features of flue gas treatment system, in terms of emissions:
The flue gas treatment system is able to treat the flue gas to meet the emission standards
The exhaust fan speed is controlled by the negative pressure in the kiln.
ENVIRONMENTAL SCOPING INFORMATION (ESI)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF
HEALTHCARE WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT
RAMBAI, FASA 4C, MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd TOC 23
CK/EV803/8026/18 ESI Revision No.: 1 Revision Date: October 2018
Table 9: Exhaust Fan Specifications
Type BIR 375
Tension electrical supply 3 x 400 V/ 50Hz + N
Power rating 110 kW
Maximum inlet temperature 250 °C
Maximum gas flow rate 600 m3/min
Maximum rotation speed 1500 rpm
Source: BIC Systems Asia Pacific Pte Ltd. (2018)
Plate 21: Exhaust Fan
2.6.3.1.10 Emission Monitoring Equipment
Highlighted features of emission monitoring equipment
The emission monitoring equipment includes continuous recording and online monitoring system
for all the gas elements, as specified by the incinerator emission standards stipulated by National
of Environment (NEA) Singapore
Alarms are activated to notify the plant operator when the pre-set values are exceeded. If the
emission further crosses the limits, then incinerator will be tripped
The emission monitoring enclosure is installed on the ground floor level, at the chimney base
ENVIRONMENTAL SCOPING INFORMATION (ESI)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF
HEALTHCARE WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT
RAMBAI, FASA 4C, MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd TOC 24
CK/EV803/8026/18 ESI Revision No.: 1 Revision Date: October 2018
Table 10: Emission Monitoring Equipment
Equipment Principle / Manufacturer
Extractive CO, CO2, SO2 analyser Principle of measurement: NDIR
Extractive NOx, O2 analyser Principle of measurement: CLD / Zirconia
HCL / HF analyser In-situ
Dust monitoring In-situ
SCADA The data of the monitoring system will be connected to and integrated with the plant PLC/PC. Process interlocks will not be implemented from the start but can be added easily at a later stage if required. The plant supervision PC will show and log all emission monitoring data continuously.
CAL gases The system has provisions for connection of the necessary CAL gas bottles.
Enclosure Weather-proof analyser system, cabinet construction based on 2.0 mm thickness galvanised plate with powder coated equipped with air condition unit and heating. Equipped with power distribution panel, lighting, switch and plug C/W cylinder rack.
Source: BIC Systems Asia Pacific Pte Ltd. (2018)
2.6.3.1.11 Peripherals
a) A hydraulic pack
Working pressure: 100 barG
Volume of oil tank: 250 l
Hydraulic oil: ARO ISO 46
Power electric motor: 11 kW
Tension electrical supply: 3 x 400 VAC/50Hz + N
Plate 22: Hydraulic Pack
b) A chimney stack
The chimney is equipped with the necessary sampling ports and access platform. The
chimney is self-supporting and of mild steel.
ENVIRONMENTAL SCOPING INFORMATION (ESI)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF
HEALTHCARE WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT
RAMBAI, FASA 4C, MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd TOC 25
CK/EV803/8026/18 ESI Revision No.: 1 Revision Date: October 2018
Table 11: Chimney Stack Details
Type BIR 375
External diameter 1500/1350 mm
Height 21 m
Flow volume of flue gas 12000 Nm3/hr
Exit velocity of flue gas 9 m/s
Temperature of flue gas at inlet 160 °C
Source: BIC Systems Asia Pacific Pte Ltd. (2018)
Plate 23: Chimney Stack
c) An air compressor assembly
Features of air compressor assembly:
Careful location of the unit (dust-free) and preventive, regular maintenance will render it
trouble-free
Maximum working pressure: 8 barG
Flow rate: 2.85 m3/min
ENVIRONMENTAL SCOPING INFORMATION (ESI)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF
HEALTHCARE WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT
RAMBAI, FASA 4C, MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd TOC 26
CK/EV803/8026/18 ESI Revision No.: 1 Revision Date: October 2018
Plate 24: Air Compressor Assembly
d) Emergency by-pass
Features of emergency by-pass:
Emergency bypass system for the bag house filter is fully automated
The bypass is a failsafe design (gravity opened) and is interlocked with the process
When the bypass valve is open, the incinerator is tripped
The bypass valve manual control is not allowed by law
The emergency by-pass consists of an automatic lid on top of the emergency dump stack at
the top of the post combustion. A guillotine-type shut-off valve to isolate the process
downstream.
Plate 25: Emergency By-pass
e) Fly ash evacuation system
A fly ash evacuation system comprises two dust hoppers, two rotary air locks and two easily
replaceable dust containers with semi-automatic lid.
ENVIRONMENTAL SCOPING INFORMATION (ESI)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF
HEALTHCARE WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT
RAMBAI, FASA 4C, MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd TOC 27
CK/EV803/8026/18 ESI Revision No.: 1 Revision Date: October 2018
Plate 26: Dust Hopper and Container
f) Liquids Injection Systems
The system consists of a volumetric injection pump (temperature controlled) and a
compressed air assisted injection nozzle. The flow rate is 500 l/h meanwhile the maximum
pressure is 8 barG.
Plate 27: Liquid Injection System
g) Safety valve (Diluting air inlet)
The safety valve consists of an automatic control valve for controlled air ingress after the heat
exchanger (set point 200 °C).
ENVIRONMENTAL SCOPING INFORMATION (ESI)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF
HEALTHCARE WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT
RAMBAI, FASA 4C, MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd TOC 28
CK/EV803/8026/18 ESI Revision No.: 1 Revision Date: October 2018
Plate 28: Safety Valve
h) A Plant Automation System
Highlighted features of plant automation system
The plant is fully automatic, safe and user-friendly in all circumstances
Motor Control Center (MCC) and Programmable Logic Controls (PLC) are housed in a
control room
All components are designed for the fail-safe conditions.
The plant automation system comprises of:
i. An MCC Power Switchboard - The switchboard houses all motor starters, variable speed drives
(VSD) and thermal overloads.
ii. A PLC Switchboard - The switchboard houses PLC and Ethernet modules.
Plate 29: MCC Power Switch
Plate 30: PLC Switch Board
ENVIRONMENTAL SCOPING INFORMATION (ESI)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF
HEALTHCARE WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT
RAMBAI, FASA 4C, MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd TOC 29
CK/EV803/8026/18 ESI Revision No.: 1 Revision Date: October 2018
iii. A Pulpit Supervisory Control and Data Acquisition (SCADA) PC for User Interfacing - The pulpit
is equipped with a desktop PC with the LCD screen behind a protective window. A back-up PC
runs in parallel in a control room/rack room to render the system fail safe.
Plate 31: Control Panel
Plate 32: PC Screen (Sample)
2.6.3.2 Truck and Bin Washing Area
Washing bay will be provided near the weighing area for truck/ bin washing and cleansing upon tipping of
waste and prior to leaving the centre. Waste water from the washing bay will be channelled to a new Industrial
Effluent Treatment System (IETS) for treatment prior discharge.
2.6.3.3 Industrial Effluent Treatment System
The incinerator does not produce any waste water from the incinerator processes. Sources of waste
water are from healthcare waste wheel bins and trucks washing activities. Wheel bins are used for
healthcare wastes collection in healthcare facilities and trucks are used as to transport the collected
healthcare wastes (inside the bins) from healthcare facilities to the Project site. Waste water from the
washing activities are considered to have potential infection risk as the wheel bins and trucks are likely to
be exposed to the healthcare wastes. The amount of waste water is estimated about 1 to 2 m3/day. The
waste water will be channelled to a new Industrial Effluent Treatment System (IETS) that will be installed
within the Project site.
Details of the IETS system will be provided in the EIA report.
2.7 DESIGN CRITERIA OF THE INCINERATOR
2.7.1 Key Design Parameters
The plant is designed according to European Union standards. The key design aims to fulfil typical
regulatory requirements to date, with the key parameters being Destruction Efficiency (DRE%) of
99.9999%, minimum residence time of min. 2 seconds at 1,100 degrees Centigrade in the post
combustion. The Operating Standards are listed in Table 12.
ENVIRONMENTAL SCOPING INFORMATION (ESI)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF
HEALTHCARE WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT
RAMBAI, FASA 4C, MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd TOC 30
CK/EV803/8026/18 ESI Revision No.: 1 Revision Date: October 2018
Table 12: Incinerator Operating Standards
Item Specifications
Destruction efficiency (DRE) 99.9999 %
Primary Combustion Chamber Temperature 850 °C minimum / 1,000 °C maximum
Secondary Combustion Chamber Temperature 1,100 °C minimum / 1,200 °C maximum
Residence Time Minimum 2 seconds
Minimum Oxygen Content 12%-13%
Air / Fuel Ratio 2.5
Source: BIC Systems Asia Pacific Pte Ltd. (2018)
The other key parameter is the conformance to emission standards in Malaysia. The limits are in Table
13. The EU standard, which is the design standard used by BIC Systems Asia Pacific Pte Ltd is equally or
more stringent than Malaysian standard.
Table 13: Emission Standards –European Union and Malaysia
Parameter EU (Daily) EU (Hourly) EU ( 4- Hour) EU Summary
Malaysia*
mg/m3
Ash / Particulates 5 10 5 100
HF 1
HCl 5 10 5 40
CO 50 100 50 50
NOx 100 200 100 200
SOx 25 50 25 50
Cd 0.05 0.05 0.05
Hg 0.05 0.05 0.05
Pb - -
Heavy Metals 0.5
Dioxin / Furan 0.10 ng/m3 0.10 ng/m3 0.10 ng/m3
Total Organics 5 10 5 10
Note: Environmental Quality (Clean Air) Regulations 2015 (3rd Schedule Regulation 13, Item K: Waste Incinerator in All Sizes.
Source: BIC Systems Asia Pacific Pte Ltd. (2018)
The design also considers the typical chemical composition of medical waste as shown in Table 14.
ENVIRONMENTAL SCOPING INFORMATION (ESI)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF
HEALTHCARE WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT
RAMBAI, FASA 4C, MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd TOC 31
CK/EV803/8026/18 ESI Revision No.: 1 Revision Date: October 2018
Table 14: Typical Medical Waste Chemical Composition
Element Mass % Mol/kg
C 74.80 0.062
H 7.00 0.070
N 1.00 0.001
S 1.000 0.000
Hg 0.00 0.000
Pb 0.000 0.000
Zn 0.000 0.000
0.000 0.000 0.000
Cl 1.00 0.000
F 0.10 0.000
Br 0.10 0.000
O 5.00 0.003
Ash 10.000 -
Total 100.00 -
Source: BIC Systems Asia Pacific Pte Ltd. (2018)
Summary of design and operational particulars of the incinerator plant are as listed in Table
15. The plant is designed to operate at a capacity of 833 kg/hr where 20 MT/day of
healthcare wastes are expected to be treated.
Table 15: Summary of General Technical Characteristic of the Incinerator
Thermal Capacity 3,750,000 Kcal/hr (15,750 MJ/hr)
Throughput
833 kg/hr (20 MT/day)
(Based on the average calorific value of waste of 4500 kcal/kg (20 MJ/kg)
Design Life Span 20 years
Process Line 1
Operating Hours 24 hours per day, 7 days per week
Waste storage capacity 90 MT
Incinerator System Counter Current Rotary Kiln
Destruction efficiency (DRE) 99.9999 %
Feeding Loading Skip hoist system
Start-up Duration 8 hours to automatically heat up to operating temperature (depending on atmospheric conditions)
Burn period 8 hours
Burn Cycle 8 cycles (160 kg per loading)
ENVIRONMENTAL SCOPING INFORMATION (ESI)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF
HEALTHCARE WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT
RAMBAI, FASA 4C, MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd TOC 32
CK/EV803/8026/18 ESI Revision No.: 1 Revision Date: October 2018
Residential time 2 – 3 seconds
Cool Down Period 24 hours
Auxiliary Fuel Diesel - 50 l/hr (for start-up only)
Air Pollution Control System
Heat Removal Heat exchanger: flue gas to thermal oil
Dioxin and Furan Control Continuous operation creating steady state conditions, ensuring complete combustion leading to complete destruction of dioxins and furans (dioxins can completely be eliminated with a residence time of 2 seconds at 1000°C and oxygen level of min 10% is thoroughly distributed)
Dosing of Activated Carbon to catch any remaining dioxin and furan
Acidic Gas Neutralizer Dosing of Sodium Bicarbonate
Dust Filtration Baghouse: 432 Teflon Felt bags
Parameter of CEMS Conformity with EC and Malaysian emission regulations
Ash Removal Daily
Utilities
Power supply 50 kW/hr (average)
Estimated waste / by product
Fly ash 25 kg/hr
Bottom ash 67 kg/hr
2.8 PROCESS DESCRIPTION
2.8.1 Handling of Healthcare Wastes at Source (On-Site Handling)
SW 403, SW 404, SW 409, SW410, SW 429 and SW 430 will be collected and transported from the
respective hospitals and laboratory to the Project site using dedicated trucks. Healthcare wastes
characteristics are listed in Table 16. Clinical wastes analysis are listed in Table 17 and Table 18.
ENVIRONMENTAL SCOPING INFORMATION (ESI)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF
HEALTHCARE WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT
RAMBAI, FASA 4C, MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd TOC 33
CK/EV803/8026/18 ESI Revision No.: 1 Revision Date: October 2018
Table 16: Healthcare Wastes Characteristics
Material Percentage
P.V.C 3%
Pathological 5%
Plastic other than P.V.C 33%
Paper including waxed paper 30%
Hospital dressing, swab, etc. 10%
Non-combustible including glass, metal, etc. 10%
Obsolete laboratories chemical 5%
Miscellaneous (including flowers, rags, etc.) 5%
Source: Medivest Sdn Bhd. (2018)
Table 17: Proximate Analysis of Clinical Waste
Analysis Range (%) Average (%)
Moisture content 16.9 - 28 21
Ash Content 1.6 - 4.7 3.1
Volatile matter 66.1 - 77.2 72.2
Fixed Carbon 1.2 - 4.3 3.2
Adapted from: Radicare (M) Sdn Bhd. (2012)
Table 18: Ultimate Analysis of Clinical Waste
Component Weight Percentage (%)
Carbon 51.83
Hydrogen 8.63
Oxygen 35.53
Nitrogen 0.17
Sulphur 0.10
Chlorine 0.64
Ash 3.1
Adapted from: Radicare (M) Sdn Bhd. (2012)
Collection and storage of healthcare wastes in CWMS is one of MSB’s responsibilities as the Concession Company. As such, relevant products (i.e. receptacles, plastic bags and on-site
containers) are to be supplied to the hospitals or establishments to contain healthcare wastes.
Segregation of the healthcare wastes is done by MOH’s staff in accordance to Management of Clinical and Related Wastes in Hospital and Health Care Establishments (1993) and Project Operations
Guidelines on Clinical Wastes Management Services (2009) released by the MOH.
ENVIRONMENTAL SCOPING INFORMATION (ESI)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF
HEALTHCARE WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT
RAMBAI, FASA 4C, MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd TOC 34
CK/EV803/8026/18 ESI Revision No.: 1 Revision Date: October 2018
Healthcare wastes that have been segregated are stored in dedicated containers/ plastic bags before
being sealed and labelled. Once the plastic bags or sharp containers are sealed, it is strictly
prohibited to break the seal. They are handled with care to prevent accidental tears or breaks until the
incineration process, as it may cause health and environmental hazards.
Table 19 presents types of products approved by the MOH to be used for containment of CW
generated at source.
Table 19: Approved Products Used for CWMS
Purpose Products Used
Segregation of sharps and syringes
Yellow-coloured triple-lock container (20L, 10L, 5L and 2.5L)
Segregation of non-sharps clinical wastes
Yellow-coloured plastic bags
Holding of non-sharps clinical wastes
Yellow-coloured flip top storage bin (30L and 45L)
Sealing and tagging of plastic bags during collection
Bag lock seal
For collection and transportation of clinical waste
Yellow-coloured wheeled bin (240L)
Plastic bags and sharp containers are then transported in wheeled bins to the hospital’s central storage for collection by MSB staff. Collection of healthcare wastes shall be done daily or as
frequently as circumstances demand. Authorised representative of the MOH and MSB staff weight the
ENVIRONMENTAL SCOPING INFORMATION (ESI)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF
HEALTHCARE WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT
RAMBAI, FASA 4C, MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd TOC 35
CK/EV803/8026/18 ESI Revision No.: 1 Revision Date: October 2018
healthcare wastes and record the quantities and weights. During the collection of the wheeled bins
containing healthcare wastes, MSB staff shall provide adequate supply of plastic bags, sharp
containers and cleaned receptacles for the collection and on-site storage. Consignment notes are
completed for each collection. Both the MOH’s staff and MSB staff are well-trained and equipped with
personal protective equipment (PPE) during the handling process.
This Project will accommodate healthcare wastes generated from government hospitals and laboratory
in Negeri Sembilan, Melaka and Johor. Estimated quantities of healthcare wastes to be collected and
treated at the Project site are listed in Table 20.
Table 20: Healthcare Wastes Collection from Waste Generators
Source Estimated Load, 2018 (kg/month)
SW 404 SW 403 SW 429 SW 430 SW 409 SW 410
Hospital Tuanku Ja'afar Seremban, Negeri Sembilan
45,731 0 0 0 0 15
Hospital Melaka 63,435 0 0 51,189 0 15
Hospital Sultanah Aminah, Johor Bahru, Johor
52,485 0 0 0 0 20
Hospital Jelebu, Kuala Klawang, Negeri Sembilan
3,552 0 0 6,383 0 0
Hospital Alor Gajah, Melaka 4,983 0 0 0 0 0
Hospital Enche' Besar Hajjah Kalsom, Kluang, Johor
20,444 0 0 0 0 5
Hospital Tuanku Ampuan Najihah, Kuala Pilah, Negeri Sembilan
20,426 0 0 77 0 0
Hospital Sultanah Nora Ismail, Batu Pahat, Johor
24,818 0 0 0 0 5
Hospital Kota Tinggi, Kota Tinggi, Johor
7,033 0 0 0 0 0
Hospital Port Dickson, Negeri Sembilan
5,803 0 0 0 0 0
Hospital Jasin, Melaka 4,044 66 0 3,484 0 0
Hospital Temenggong Seri Maharaja Tun Ibrahim, Kulai, Johor
4,984 0 0 0 0 0
Hospital Tampin, Negeri Sembilan
3,570 364 0 0 0 0
Hospital Pakar Sultanah Fatimah, Muar, Johor
22,061 0 5,072 0 0 5
ENVIRONMENTAL SCOPING INFORMATION (ESI)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF
HEALTHCARE WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT
RAMBAI, FASA 4C, MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd TOC 36
CK/EV803/8026/18 ESI Revision No.: 1 Revision Date: October 2018
Source Estimated Load, 2018 (kg/month)
SW 404 SW 403 SW 429 SW 430 SW 409 SW 410
Hospital Mersing, Johor 3,001 0 0 0 0 0
Hospital Segamat, Johor 12,915 0 0 0 0 0
Hospital Pontian, Johor 4,530 0 0 0 0 0
Hospital Tangkak, Johor 2,391 0 0 0 0 0
Hospital Permai, Johor Bahru, Johor
7,044 0 0 0 0 0
Makmal Kesihatan Awam Johor Bahru, Tampoi, Johor Bahru
630 0 0 0 20 20
Hospital Sultan Ismail, Johor Bahru, Johor
38,998 0 0 0 0 15
Hospital Jempol, Negeri Sembilan
2,979 31 0 28 0 0
Total 355,857 461 5,702 61,161 20 100
Source: Medivest Sdn Bhd. (2018)
2.8.1.1 Transportation of Healthcare Wastes to Project Site
Six dedicated trucks are allocated for transportation of the healthcare wastes. One of the truck has a
capacity of 16 MT meanwhile the remaining five trucks have a capacity of 18 MT each. It is estimated
that there will be one trip of delivery daily for each truck.
Transportation and collection of the healthcare wastes are daily and divided by 5 routes as follows:
i. Route 1: Plant – Hospital Pontian – Hospital Sultanah Aminah – Makmal Kesihatan Johor –Hospital Kulai – Plant.
ii. Route 2: Plant – Hospital Kluang – Hospital Kota Tinggi – Hospital Sultan Ismail – Hospital
Permai – Plant.
iii. Route 3: Plant – Hospital Mersing – Hospital Batu Pahat – Hospital Muar- Plant.
iv. Route 4: Plant – Hospital Port Dickson – Hospital Tampin – Hospital Alor Gajah – Hospital
Tangkak – Hospital Jasin – Hospital Segamat – Plant.
v. Route 5: Plant – Hospital Seremban – Hospital Jelebu – Hospital Jempol – Hospital Kuala
Pilah –Hospital Melaka – Plant.
ENVIRONMENTAL SCOPING INFORMATION (ESI)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF
HEALTHCARE WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT
RAMBAI, FASA 4C, MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd TOC 37
CK/EV803/8026/18 ESI Revision No.: 1 Revision Date: October 2018
2.8.2 Handling of Healthcare Wastes at Project Site (Off-site Handling)
Healthcare wastes received at the Project site will be weighed before further handling and treatment.
2.8.2.1 Incineration Process
Simplified schematic diagram for the overall processes proposed to be undertaken at the incinerator
plant is shown in Figure 5.
Source: BIC Systems Asia Pacific Pte Ltd. (2018)
Figure 5: Simplified Schematic Diagram
The healthcare wastes contained in standard 660 L or 240 L plastic waste bins is fed into the system
with a skip hoist system. The feeding process is automated with minimum manual intervention. In
exception of placing bins in position, the rest of the process including lifting, tilting, as well as lowering
the bins are fully automated.
The primary combustion train comprises a feeding hopper, a hydraulic ram that pushes the waste and
a guillotine (fire) door that opens only when waste is pushed into combustion chamber. The dumping
of the waste from the feeding hopper to the incinerator is monitored by interlock system, to eliminate
the possibility of overloading or under-loading of waste. The hydraulic ram will be scraped by guillotine
door so that no adhering of waste onto the feeding ram. Meanwhile, cooling air will be aspired through
the feeding area, to cool it down.
A stationary part links the feed system to the rotary kiln and serves as a solid hearth bed to start and
to preheat the freshly introduced waste. After being partly burnt, the solid waste enters a counter
current rotary kiln for further complete combustion. The cylindrical rotary kiln rotates clockwise or
counter-clockwise at a controllable speed, to ensure thorough and speedy combustion. A cylindrical
section at the rear end of the kiln serves as an ash evacuation portion. The entire rotary kiln is
supported by four supporting wheels and one trust wheel on self-lubricating bearings.
To raise the temperature at start-up, the incinerator is equipped with a diesel burner. The burner will
start firing automatically when the temperature inside the kiln drops below a pre-set value. There will
be a robust and fool proof ash collection system for the incinerator. The new design can ensure that
ENVIRONMENTAL SCOPING INFORMATION (ESI)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF
HEALTHCARE WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT
RAMBAI, FASA 4C, MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd TOC 38
CK/EV803/8026/18 ESI Revision No.: 1 Revision Date: October 2018
no ash nor partially burnt waste shall drops from any part of the incinerator. . In addition, replacement
of the bottom ash bin will be manually done for optimum reliability.
The secondary combustion, also known as post combustion chamber, starts at the upper part of the
stationary part, followed by an extension chamber equipped with and retractable burner.
2.8.2.2 Gas Cooling
After combustion, the flue gas will first enter a flue gas cooling system. The flue gas will be directed in
to a Flue Gas Thermal Oil (FGTO) heat exchanger. The vertical thermal heat exchanger enables easy
access and maintenance. The trouble-free design of the vertical FGTO heat exchanger is equipped
with ultrasonic soot blowers, in order to blow off accumulated fly-ash and soot. The newly designed
thermal oil system, fully automatically triggers the stand-by pump in case of low oil flow, where Hi-Hi
temperature will trigger plant trip (emergency by-pass).
2.8.2.3 Air Pollution Control System
Sodium Bicarbonate will be used for acidic gas neutralizer. The advantage of using Sodium
Bicarbonate instead of lime, is that the neutralising reaction time is much (5x) shorter and the reaction
itself nearly stoichiometric. Activated carbon will be used to catch any remaining for Dioxin and Furan
in the flue gases.
Sodium bicarbonate and activated carbon are stored and injected according to loss-in-weight. The
new chemical dosing design is such that it will dose the chemical flow with adjustable feeding rate
according to the quantity and quality of the flue gas. The dosing of chemical flow is by loss-in-weight
feedback. The operators will be notified by the No/Low sensor together with alarms. Moreover, the
dosing system is designed to prevent clogging of bicarbonate powder.
The flue gas then will enter the bag house filter to remove particulates and dust. A pulsating
compressed air system will blow-off the filtered dust from the filter bags and be triggered by differential
pressure across the bags. A large maintenance platform is installed at the top of the bag-house.
Rotary air locks will collect the fly-ash and the collected fly-ash drops by gravity into sealed containers
with automatic lid. The exhaust fan speed is controlled by the negative pressure in the kiln. The flue
gas treatment system is able to treat the flue gas to meet the emission standards.
2.8.2.4 Emission Monitoring
Emission monitoring equipment installed at the incinerator will comprise of in-situ CO, CO2, SO2
analysers which adopt NDIR measurement principle; extractive NOx, O2 analysers which adopt CLD /
Zirconia measurement Principle; in situ HCL/HF analysers and in-situ dust monitoring system. With
SCADA, the data of the monitoring system will be connected and integrated with the plant PLC/PC.
The plant supervision PC will show and log all emission monitoring data continuously. The compact
emission monitoring system is enclosed with a weather proof analyser cabinet, equipped with air
condition unit, power distribution panel, lighting, switch and plug C/W rack.
The emission monitoring equipment can continuously record and online monitor all gas components
that are specified by the Malaysian Authorities. Alarms are activated to notify when the present value
are exceeded. If the pre-set values are further exceeded, the incinerator will trip. The emission
monitoring enclosure will be installed on the ground floor level, at the chimney base.
ENVIRONMENTAL SCOPING INFORMATION (ESI)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF
HEALTHCARE WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT
RAMBAI, FASA 4C, MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd TOC 39
CK/EV803/8026/18 ESI Revision No.: 1 Revision Date: October 2018
2.8.2.5 Incinerator Plant Control System
The entire incinerator plant is automatically controlled by a PLC (Programmable Logic Controller). All
required instrumentation for the incineration system, the waste feed system, the rotary kiln, the post
combustion chamber, the flue gas treatment and scrubbing system, the fan controls and emergency
by-pass system are included. The incinerator controls include temperature controls, pressure controls,
excess air controls, all burner safeties and the necessary alarms/alert and data logging equipment.
2.8.2.6 Incinerator Plant Maintenance
a) Regular Maintenance
The Regular Maintenance is essential to ensure that the plant continuously operates at optimum level.
This generally involves the following:
Cleaning of the various parts of the plant (pumps, air compressor, pneumatic cylinders, etc.)
Greasing of various components (wheels, ram, guillotine doors, etc.)
Filling up oil for the various pneumatic systems
Various other checks for potential issues
b) Scheduled Maintenance
Every year (even two years depending on how the plant has been maintained), there will be need for a
major shutdown (Scheduled Maintenance). Amongst the key areas are the patching / repairs of
refractory, checks and servicing of the burners and cleaning up the heat exchanger.
2.8.2.7 Management of Bottom Ash and Fly Ash (SW 406)
Bottom ash will be generated 8% from the waste fed into the incinerator which is approximately 67
kg/hr. Bottom ash will be temporary stored inside first and second compartment of Scheduled Waste
Storage Area before being sent to Kualiti Alam for disposal at a secured landfill with frequency of three
times a month.
Meanwhile, it is estimated about 25 kg/hr of fly ash will be generated. Fly ash will be temporary stored
at the Scheduled Waste Storage Area and sent to Kualiti Alam Sdn Bhd for disposal twice a month.
Collection of both type of ashes will done by Kualiti Alam personnel.
2.8.2.8 Management of Fluff (SW 501)
During incinerator shutdown events, healthcare wastes at the Project site will be treated using the two
microwave machines available on-site. SW 501 which consist of fluff will be generated as residues
from the activity. Based on Clause No. 5.1 in the Jadual Pematuhan (ref. no. JPBT/KPLT/18/004989)
for the microwave operation, these residues (SW 501) shall be sent for disposal at a secured landfill,
within 24 hours or may be required to be treated by incineration process. However, since the
microwaves machines will only be in operation during incinerator shut down events, SW 501 will not
be able to be treated via incineration process at the Project site as the fluff need to be treated within
24 hours. Furthermore, MSB is not able to store the residue for long period i.e., during the incinerator
ENVIRONMENTAL SCOPING INFORMATION (ESI)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF
HEALTHCARE WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT
RAMBAI, FASA 4C, MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd TOC 40
CK/EV803/8026/18 ESI Revision No.: 1 Revision Date: October 2018
shutdown. MSB will arrange transportation to deliver the residue to a licensed premise, within 24
hours.
2.8.2.9 Healthcare Waste Storage
In the event that healthcare wastes could not be incinerated within 24 hours of reception, it will be
stored in a dedicated storage container/ refrigerator at temperature of between below 6˚C (cold storage). There are six storage containers available at the Project site. Total holding capacity is 90
MT.
2.8.2.10 Cleansing and Disinfection of Wheeled Bins and Trucks
Upon unloading of healthcare wastes at the reception area, the emptied wheeled bins will be
transferred to the washing bay area. Wheeled bins will be washed, sprayed with biodegradable
disinfectant solution and rinsed before being transferred to clean bin storage area. Trucks will also be
cleaned and disinfected before the next collection trip or usage. Clean wheeled bins will be returned
to the healthcare wastes generators (hospitals).
2.8.2.11 Incinerator Plant Balances
The incinerator plant’s mass balance is shown in Figure 6.
2.9 PROJECT DEVELOPMENT SCHEDULE
Upon getting EIA approval and other necessary approval, the development of the Project will take
about 12 months including testing and commissioning.
2.10 PROJECT ACTIVITIES
Development of the Project will involve the following activities:
Pre-Construction Stage
Construction Stage
Operation and Maintenance Stage
Details of the activities involve during the stages are described in the following subsections.
2.10.1 Pre-Construction Stage
Pre-construction stage will include the appointment of consultants and surveyors. The activities during
this stage include project planning y and environmental assessment.
It is anticipated that the environmental risks range from no impact to low degree of significant impact
during this pre-construction stage.
B I/ Syste s A sia t a ifi t TE Ltd , B ukit B atok / ese t# - W / EDA ToweSi gapoe
pr i mMry combust i on Mi r secundMry combustion Mir dilution Mir HE l eMkge Mi r 1% MCR di l ut i on Mi r dr y scr ubber l eMkge Mi r bMg house l eMkge Mi r 2%ki l n RMst e i nput 3B130 Nm5/h 4BD04 Nm5/h 2B416 Nm5/h 107 0 Nm5/h E63b6E Nm5/h 23D Nm5/h
E 4BD00 kcMl/kg . kJ /kg °C °C °C °C °C °Cm 834 kg/h T/dMy , kJ /s , kJ /s , kJ /s , , kJ /s , kJ /s , kJ /sQ Nm5/h NMHCO3 AC
T 2D °C UR E A 40% in RMter E2 kg/h E kg/h POIIUTANT EMI SSI ON l i mi t UNI T
P 10132D PM 0b00 kg/hCMl kcMl/h % CMpB HCI 10 mg/Nm5BIR type . kJ /s mi xi ng dr y scr ubber bMg house HF 1 mg/Nm5
. kJ /s . kJ /s . kJ /s 3268 kW kJ /s S Ox (S O2) D0 mg/Nm58D0 °C 1100 °C E00 °C 200 °C 200 °C 1E0 °C 180 °C NOx (NO2) 200 mg/Nm5
. kJ /s 10127D PM 10122D PM 10122D PM EE7D0 PM EE2D0 PM EE0D0 PM E80D0 PM TOC (CH4) 10 mg/Nm5CO D0 mg/Nm5
. Nm5/h . Nm5/h . Nm5/h . Nm5/h . PCDD/PCDF (TE Q) 0b1 ng/Nm5
. Am5/h . Am5/h . Am5/h . Am5/h . PMrticulMte 10 mg/Nm5, vol% O2 , vol% O2 , vol% O2 , Cd+Th 0b0D mg/Nm5
Botttom Ash 22Db0E kg/h Hg 0b0D mg/Nm5PM S b+As+Pb+Cr+Co+Cu+Mn+Ni+V 0bD mg/Nm5
kJ /s kJ /s HCI 1428bD7 mg/Nm3 rMdi Mt i on l osses kg/h S MltsHF 14b2E mg/Nm3 kJ /sS ox (S O2) 2631bD8 mg/Nm3
Cuel gas 0 Nm5/h Cuel gas c1 Nm5/h Nox (NO2) 200b00 mg/Nm3 m3/ m2B mi n B ag dia B ag le gth B ag sufa e m2 required # B ags e uiedoil 0 kg/h oil c1 kg/h TOC (CH4) 10b00 mg/Nm3
e e gy 2 kJ /s e e gy c10 kJ /s CO D0b00 mg/Nm3 0b 8 , , ,PCDD/PCDF (TE Q) 0b10 ng/Nm3 0b 8 , , ,
AIIOWED MAXB
I NDI VI DUAI CONCB ( %)
EIEMENT cust omer PlMnt S izing KIIN PlMnt S izing S CC Pl Mnt Si zi ng mi xi ngPMrticulMte 1000b00 mg/Nm3
4b44 D m/s TMrget Velocity 10 m/s TMrget Velocity 13bD m/s TMrget Vel oci t y Cd+Th Db00 mg/Nm311b27 33 % MMx filling grMde , Am3/s GMs F loRrMte , Am3/s GMs Fl oRrMt e Hg 0b20 mg/Nm321b68 , Am3/s GMs F loRrMte , m2 Required surfMce AreM , m2 Requi red sur f Mce AreM S b+As+Pb+Cr+Co+Cu+Mn+Ni+V62bD0 mg/Nm31b00 , m2 Required surfMce AreM , m Required inside diMmeter , m Requi red i nsi de di Mmet er dry scrubber FAN Si zi ng Pl Mnt Si zi ng chi mney
ok 1 , m Required inside diMmeter 2 s TMrget R esidence time (kiln outlet to S CC outlet)0bD s Resi dence t i me 10 m/s TMrget Velocity 6300 PM AV Tot Ml Pressure i ncreMse327D PM NEED Tot Ml Pressure i ncreMse 10 m/s TMrget Vel oci t yok 0b01 , m2 0rqm °ry °qr c ross – sec tqon°l °re°, m Required chMmber lenght , m Iengt h Db30 Am3/s GMs F loRrMte , Am3/s GMs Fl oRrMt e , Am3/s GMs Fl oRrMt eok 1 , m2 Resulting chMmber shell surfMce , m2 The sur f Mce MreM of t he mi xi ng chMmber 0bD3 m2 R equired surfMce AreM 0b7D FMn ef f i ci ency0B71E~0B8 , m2 Requi red sur f Mce AreMok 0b0000 , m2 3ec ond °ry °qr c ross – sec tqon°l °re° 0b8220 m R equired inside diMmeter 0bE8 MechMni cMl ef f i ci ency , m Requi red i nsi de di Mmet er
ok 34b88 , m BIR 37D inside diMmeter , m BIR 37D inside diMmeter , m BIR 37D inside diMmeter 2 s Resi dence t i me , kW Requi red f Mn poRer , m BIR 37D inside diMmeter
ok 0 , m BIR 37D S CC chMmber lenght , m BIR 37D chMmber lenght , m requi red Iengt h , kW BIR 37D fMn poRerok 0 , m BIR 37D inside diMmeterok 24b72 , input from BIR plMnt selction sheet , m BIR 37D chMmber lengthok 0 PCI rMt ki l n/ t ot Ml , mMnuMl inputok 0 , input from pluiming sheetok 0 , fo ula cMlculMtion
, fo ula input from pluiming sheet + cMlculinput from CWI sheet
fo ula input from CWI sheet + cMlculinput from quench cMlc
,
.
. ,
kJ /s
Nm5/hAm5/h
.
. Nm5/hAm5/h
vol% O2
kJ /s
,
Cd+ThHg
S b+As+Pb+Cr+Co+Cu+Mn+Ni+V
MinerMl (loss Mt ignition),,
,PCDD/PCDF (TE Q)
SNOx
TOC (CH4)bA CO
,,,
bA
,F
HO
H2ONCl
,
BIR 37D C ounter C urrent 20 TPD = 834 kg/hr
RMst e i nput
rotMry kiln
kcMl/h
post combustion
rMdiMtion losses rMdiMtion losses
Ai r f Mct or e
COMBB AI R KI IN/ TOTAIH2O %m
Fl ue gMs comp
t her mMl f l ui d HE mi xi ng
vol% O2
Nm5/h
kJ /s°C
M EDIV EST B IR -M &E ala e -
MASS BALANCE
Figure 6
Source: BIC Systems Asia Pacific Pte Ltd. (2018)
ENVIRONMENTAL SCOPING INFORMATION (ESI)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF
HEALTHCARE WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT
RAMBAI, FASA 4C, MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd TOC 41
CK/EV803/8026/18 ESI Revision No.: 1 Revision Date: October 2018
2.10.2 Construction Stage
Major activities during construction stage include:
Mobilisation of Workforce [Project Manager – 1, Project Supervisor –1, General Worker(local and
foreigner) – 15], Machineries and Construction Materials
Foundation works – soil improvement, piling
Civil and structure works – incinerator plant and IETS
Transportation of construction material and equipment
Mechanical and electrical works – installation of all process equipment, conveying systems and
environmental control systems
Testing and commissioning - No-load, load and performance tests
2.10.3 Operation and Maintenance Stage
During operational stage, the Project will be operated by the existing MSB operational team as follows:
Senior Manager -1
Plant Manager – 1
Engineer – 2
Technical Officer – 3
Technician (Shift Leader) – 3
Operator - 3
The organisation chart is shown as Figure 7.
ENVIRONMENTAL SCOPING INFORMATION (ESI)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF
HEALTHCARE WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT
RAMBAI, FASA 4C, MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd TOC 42
CK/EV803/8026/18 ESI Revision No.: 1 Revision Date: October 2018
Figure 7: Organisation Chart
Operation of the Project is largely automated and control via process control system. Main processes
in productions are described in Section 2.8.2 of this ESI. Other important activity during the operation
stage is transportation of healthcare wastes. The designated routes of are as listed in Section 2.8.1.
As mentioned in Section 2.8.2.6, regular maintenance which includes cleaning of various parts,
greasing of various components, filling up of pneumatic systems’ oil and various will be carried out according to schedule.
Scheduled maintenance which include patching / repairs of refractory, checks and servicing of the
burners and cleaning up the heat exchanger will be carried out yearly.
ENVIRONMENTAL SCOPING INFORMATION (ESI)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF
HEALTHCARE WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT
RAMBAI, FASA 4C, MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd TOC 43
CK/EV803/8026/18 ESI Revision No.: 1 Revision Date: October 2018
3 ALTERNATIVE CONSIDERATIONS
3.1 SITE OPTIONS
3.1.1 New Site Option
Sitting on a new site shall consume substantial cost for new land purchase, feasibility study and
construction of new facilities such as Cold storage, scheduled waste store, administration office and
Control Room.
A new group of workers will have to be trained in the management and operations of the new site.
Public concern on environmental issue which will bring sceptical reaction on the new installation of the
healthcare wastes treatment facility on the new site. However, the public will be more receptive on the
upgrading existing plant on condition that the facility complies with the standard emissions and do not
pose any hazards or environmental issues to the receptors staying area.
3.1.2 Existing Site Option
Other facilities such as the Cold Storage, Control Room, Scheduled Waste Store, Administration
Office and Workshop is already in place and ready for use immediately. Besides that, cost and time
shall be reduced significantly for this upgrading works as the work only focus on the incinerator plant
only.
Data pertaining to the baseline and existing environment in the surrounding area of the existing clinical
wastes incineration plant is well documented to assess any residual impacts of operating of the clinical
waste treatment facility.
The experienced workforce managing and operating the clinical wastes incineration plant can be
further utilized to manage the new plant.
Thus, based on the above, the use of the present site is a better option worthy of consideration rather
than the option for locating on a new site.
3.2 TECHNOLOGY OPTIONS
Waste incineration in rotary kiln is considered to be Best Available Technology (BAT) for medical and
hazardous waste treatment, because of continuous operation creating steady state conditions,
ensuring complete combustion leading to complete destruction of dioxins and furans. There are two
types of rotary kilns, named after the sense of solids- compared to gas flow in the kiln.
ENVIRONMENTAL SCOPING INFORMATION (ESI)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF
HEALTHCARE WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT
RAMBAI, FASA 4C, MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd TOC 44
CK/EV803/8026/18 ESI Revision No.: 1 Revision Date: October 2018
3.2.1 Counter Current Rotary Kiln
Source: BIC Systems Asia Pacific Pte Ltd. (2018)
Figure 8: Counter Current Rotary Kiln
Flue gases flow in the opposite direction of the waste, against the inclination of the kiln. Solids move
by the rotary motion and by gravity from the high end to the low end of the kiln.
Primary Combustion air (cold ambient air) is introduced at the lower end of the kiln (at the de-ashing
zone) by aspiration (the whole system is under negative pressure). While flowing towards the feeding
area (front) of the kiln, the combustion air is preheated by flowing over the hot ash and its oxygen
content is gradually reduced by oxidation of the solids during its passage and as such becomes flue
gas. At the front of the kiln the off-flue gas contains little oxygen (max.6%) and is hot (1000 °C). By
controlling the amount of inflowing flue gases (simply by adjustment of the inlet damper), it is possible
to control the degree of oxidation of the solids and as a consequence to control the remaining oxygen
content in the flue gas. It is thus perfectly possible to operate under controlled starved air conditions
(pyrolysis). By correctly adjusting the primary air, it is thus perfectly possible to:
i. To operate under pyrolysis conditions
ii. To control the combustion temperature in the kiln. This is particularly interesting in the case the
solid waste residues tend to melt at certain temperatures. This feature is particularly interesting
for avoiding clogging (e.g. NaCl melts around 800°C) or for avoiding evaporation of (precious)
metals. By controlling correctly, the temperature in the kiln, there is no clogging at all.
iii. To produce more or less rich (pyrolysis) gas, to fuel the post combustion chamber, which
provides a perfect post combustion temperature control without any requirement of external fuel
Incoming solid waste is introduced in the front zone of the kiln and is exposed to the hot (pyrolysis)
flue gas which flows in counter current against the waste. The flue gas being poor in oxygen and high
in temperature, makes all the light fractions - which are present in the solid waste - to evaporate and to
be mixed with the rich gas exiting from the primary combustion (kiln). This highly flammable mixture is
mixed at its origin (right above the feeding zone of the kiln) with incoming post combustion air, where it
immediately starts the post combustion and where the temperature easily reaches 1250 °C (but can
be easily reduced) – without auxiliary fuelling.
ENVIRONMENTAL SCOPING INFORMATION (ESI)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF
HEALTHCARE WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT
RAMBAI, FASA 4C, MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd TOC 45
CK/EV803/8026/18 ESI Revision No.: 1 Revision Date: October 2018
The bottom ash is evacuated from the primary rotary chamber through a cylindrical section with a
reduced diameter compared to the kiln. As a consequence, the height of the ash in the kiln is
permanently maintained to about 1/3 of the diameter of the kiln.
Only after the combustion of solids is complete (after sufficient residence time), the ash is gradually
scooped out (by refractory lined scoops), from the kiln into the narrowed cylindrical section, in which it
is exposed to incoming primary combustion air to cool it down before dropping directly into the ash
container. As a consequence, the bottom ash is perfectly burnt out (less than 2% residual organic
carbon) and comes out cool and dry. Because combustion air flows in by suction at the exit location of
the bottom ash there is no need for a perfect (water) seal. (Any eventual air leakage will serve as
combustion air).
As it is described above, the post combustion being fuelled by a rich gas (which is produced in the
primary chamber) the combustion temperature is equally distributed over the entire area, rather than in
one particular area (as it is the case in any other system, firing a supporting burner) Therefore, the
residence time of the flue gas in the post combustion area can be correctly calculated. This property is
most important for being able to control the destruction of Dioxins. Generally, dioxins can only be
completely eliminated if a residence time of 2 seconds at 1000 °C and if an oxygen level of minimum
10% is thoroughly respected everywhere. This is only possible in counter current kiln designed by the
Technology Provider.
Due to the complete destruction of all Dioxins and their components during passage through the post-
combustion, there is absolutely no risk of reformation and as a consequence, there is no need to
quench the flue gas after the post-combustion to prevent reformation. As such, the full heat content of
the flue gas can be recovered to produce steam and/or electric power.
Additional features are that this type of kiln ensures better turbulence and hence the kiln can be kept
short and compact. In order to achieve the same residence time for the solids, the rotation is slower
than in a co-current kiln and by correctly dosing the primary combustion air, the fly ash carry over can
be strongly reduced, compared to a co-current kiln.
3.2.2 Co-Current Rotary Kiln
Source: BIC Systems Asia Pacific Pte Ltd. (2018)
Figure 9: Co-Current Rotary Kiln
Flue gases flow in the same direction of the waste, with the inclination of the kiln. Solids move by the
rotary motion and by gravity from the high end to the low end of the kiln.
ENVIRONMENTAL SCOPING INFORMATION (ESI)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF
HEALTHCARE WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT
RAMBAI, FASA 4C, MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd TOC 46
CK/EV803/8026/18 ESI Revision No.: 1 Revision Date: October 2018
Primary combustion air is blown in by a fan. The excess of combustion air is generally 100 % to 150
%. While flowing to the back of the kiln, the air heats up and becomes poor in oxygen due to the
complete combustion of all the solids – basically becoming flue gas - so that at the back of the kiln the
outflowing flue gases contain less oxygen (6 %) but are hot (900 °C -1000 °C) due to the complete
oxidation of all the waste components (solid and gaseous fraction).
Incoming waste (solids) is cold and follows the same flow direction as the incoming (cold) combustion
air. Depending on the CV of the waste, a make-up burner is required to start the incineration process.
At the back (bottom ash exit) of the kiln, the solids do not contain enough combustible matter
anymore, such that the flue gases flowing to the post combustion zone have to be re-heated from 900
°C -1000 °C to 1100 °C by a supporting burner.
Bottom ash is hot (1000 °C) and is not cooled down by the incoming combustion air as it is the case
with a counter-current kiln. Also, the oxygen – poor atmosphere cannot help to achieve a good
burnout. The high temperature in the ash evacuation zone (1000 °C) creates a high risk of slagging
and makes ash handling difficult (ash quench is required).
Additional features are that this type of kiln ensures little turbulence and hence the kiln must be longer.
To keep the combustion going, kiln rotation must be faster than in a counter-current kiln, leading to
more fly ash carry over.
Comparison of the operating conditions of a typical example of rotary kiln, counter current versus co-
current.
Counter Current Rotary Kiln Co-Current Rotary Kiln
Size Compact Bigger size
Amount of waste in 1000 kg/h 1000 kg/h
Waste inlet temperature 1000 °C 200 °C
Oxygen % at waste inlet 6 % 21 %
Waste residence time >2-4 h >2h
Bottom ash
Residual organic carbon in Ash <0.5 % >2-8 %
Temperature 200 °C 1000 °C
Mass reduction (%) <85 % >75 %
Post combustion additional support fuel consumption
0 kg/h >100 kg/h
Fly ash 750 mg/Nm3 1500 mg/Nm3
Source: BIC Systems Asia Pacific Pte Ltd. (2018)
ENVIRONMENTAL SCOPING INFORMATION (ESI)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF HEALTHCARE
WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT RAMBAI, FASA 4C,
MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd TOC 47
CK/EV803/8026/18 ESI Revision No.: 1 Revision Date: October 2018
The Project Proponent has chosen the counter current rotary kiln as their preferred technology based on
the following key benefits:
Low consumption of fuel.
The incinerator will be using counter-flow process which allow very minimum or even non consumption
of fuel during ideal operation. The fuel only consumed during start-up process which o takes less than
24 hours.
Better air emission.
The incinerator has been well accepted with 55 units operating all around Europe, Africa, Middle East
and Asia. Main factor of this acceptance due to application of modern and highly efficient air pollutant
control system which treats the combustion effectively before being emitted to environment. The
system proven to be able to comply with stringent emission standard worldwide.
Low production of by-product.
No effluent produced from the incinerator. During the incineration process, the ash produced is only
8% from the original load.
4 MAJOR ELEMENT OF THE ENVIRONMENT IN THE VICINITY OF
PROJECT SITE AND STUDY BOUNDARIES
Details on major elements of the environment which consist of physical, biological and human
environment will be compiled based on baseline information to be collected from field investigations,
secondary sources and from the Project Proponent and/or his engineers, Technology Provider and other
consultants on the Project as well as consultation with relevant Government departments. Descriptions of
the major elements are required to provide the necessary baseline data for subsequent evaluation in the
impact assessments and for the formulation of environmental management measures and monitoring
programme.
Study zone for this Proposed Project is within 5 km radius from the Project facility.
4.1 PHYSICAL ENVIRONMENT
4.1.1 Topography
The Project is located within an existing healthcare wastes centre which has been established since 1996.
The area is a ready site located within Kawasan Perindustrian Bukit Rambai, Phase 4C.
4.1.2 Geology and Soil
Geology and soil features at the Project site will be described based on secondary data and published
geology and soil maps. Based on initial reference made to Peta Geologi Semenanjung Malaysia Cetakan
ke-8, 1985, the geology condition of the Project site and its surrounding is Devonian geology which consist
of phyllite, schist and slate whereby there are limestone and sandstone are locally prominent, some
interbeds of conglomerate, chert and rare volcanic. Meanwhile based on the Generalised Soil Map of
ENVIRONMENTAL SCOPING INFORMATION (ESI)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF HEALTHCARE
WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT RAMBAI, FASA 4C,
MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd TOC 48
CK/EV803/8026/18 ESI Revision No.: 1 Revision Date: October 2018
Peninsular Malaysia 1970, the Project site is located on gley soils on marine clays (saline gley soils and
acid sulphate soils). (See Figure 10 and Figure 11).
4.1.3 Hydrology and Drainage
Based on reference made to the topography survey plan and site observation, there is no stream or river
on the Project site, however there is a river called Sg Ayer Salak that traverses further northwest to south
(about 1.4 km) from the project site before joining Sg Melaka and entering the Selat Melaka (see Figure
12).
There is an existing drainage system surrounding the Project site within the industrial area.
4.1.4 Meteorology and Climate
The meteorology of an area can be described by the wind pattern, rainfall amount, surface temperature
and relatively humidity measured at the area. The Project area experiences an equatorial type of climate
characterised by warm and humid weather all year round with intermittent rainfall. There are two distinct
monsoon seasons, the Northeast Monsoon (from November to March) and the Southwest Monsoon (from
May to September).
The Malaysian Meteorological Services (MMS) maintains a principal meteorological station at Melaka
(Latitude: 02° 16' N Longitude: 102° 15' E; Elevation: 8.5 m). Since this principal station is the nearest
meteorological station to the Project site, data from this station is used to describe and represent the
climatological conditions of the Project site.
4.1.5 Scope of Environmental Baseline Assessment
Environmental baseline data obtained prior to the implementation of the Project provides a benchmark for
formulating future environmental compliance limits or standards for the Project, during the construction
and operation stages respectively.
The following environmental assessment areas will be investigated as part of the environmental baseline
assessment for the EIA. Proposed baseline sampling locations are provided in Figure 13. Secondary data
will be sourced to complement baseline data collected where available.
4.1.5.1 Surface Water Quality
In order to gauge surface water quality within the Project area, baseline for water quality will be
established for in-situ testing and analysis of grab samples taken at the proposed water monitoring
locations as shown in Table 21 and Figure 13.
Surface water quality monitoring will be carried out twice (except for dioxin and furan) to represent dry and
wet weathers, where possible. Dioxin and furan will be conducted once–off at upstream and downstream
of the site as representative points for future comparison should there be any deposition of such pollutants
upon the operation of the new incinerator.
THAILAND
KEDAHPulauLangkawi
ALOR SETAR
PERLISKANGAR
PINANGPULAU
TOWN
KELANTAN
KOTA BHARU
TERENGGANU
PERAKTERENGGANU
IPOH
PAHANGKUANTAN
SELANGOR
KUALA LUMPURSHAH ALAM
SEREMBAN
NEGERI
MELAKAJOHOR
JOHORBAHRU
TiomanPulau
SINGAPURA
KUALA
GEORGE
SEMBILAN
CHEMSAIN KONSULTANT SDN. BHD.
LEGEND:
GEOLOGY
MAP
FIGURE 10
THAILAND
KEDAHPulauLangkawi
ALOR SETAR
PERLISKANGAR
PINANGPULAU
TOWN
KELANTAN
KOTA BHARU
TERENGGANU
PERAKTERENGGANU
IPOH
PAHANGKUANTAN
SELANGOR
KUALA LUMPURSHAH ALAM
SEREMBAN
NEGERI
MELAKAJOHOR
JOHORBAHRU
TiomanPulau
SINGAPURA
KUALA
GEORGE
SEMBILAN
CHEMSAIN KONSULTANT SDN. BHD.
LEGEND:
SOIL MAP
FIGURE 11
Sg
. Lere
h
Sg
. Ayer S
ala
k
Sg. M
ela
ka
Sg
. Mela
ka
CHEMSAIN KONSULTANT SDN. BHD.
HYDROLOGY MAP
LEGEND:
FIGURE 12
CHEMSAIN KONSULTANT SDN. BHD.
BASELINE SAMPLING
LOCATIONS
LEGEND:
A2/N4
A3
A4
W3
W2
W1
A1
N1
N2
N3
FIGURE 13
ENVIRONMENTAL SCOPING INFORMATION (ESI)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF HEALTHCARE
WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT RAMBAI, FASA 4C,
MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd TOC 49
CK/EV803/8026/18 ESI Revision No.: 1 Revision Date: October 2018
Table 21: Proposed Baseline Water Quality Locations
Station Approximate Coordinates Justification
W1 2°16'47.6"N 102°10'50.3"E To represent the existing water quality at existing drain next to the storm water drain discharge point at the southeast boundary of Project site
W2 2°16'47.3"N 102°10'50.4"E To represent the existing water quality at existing drain next to the storm water drain discharge point at the west boundary of Project site
W3 2°16'00.9"N 102°10'37.6"E To represent the existing water quality of Sg Ayer Salak located further downstream of the Project site
Surface water parameters to be tested are listed in Table 22 and the tests shall be conducted by SAMM
accredited laboratory using appropriate APHA Standard Test Methods. Test results will be discussed in
the EIA report with comparison made with the National Water Quality Standards for Malaysia, where
relevant (Appendix 1).
Table 22: Proposed Water Quality Parameters
Parameters Test Method
Temperature In-situ, APHA 2550 B
pH value In-situ, APHA 4500-H+B
Dissolved Oxygen (DO) In-situ, APHA 2500-O G
Biochemical Oxygen Demand (BOD) APHA 5210B & 4500-O G
Chemical Oxygen Demand (COD) APHA 5220 C
Total Suspended Solids (TSS) APHA 2540 D
Mercury APHA 3112 B
Cadmium, Lead, Copper, Zinc, Iron, Manganese, Nickel
APHA 3111 B
Total Chromium APHA 3125 B
Arsenic APHA 3114 B & C
Tin In-house Method 0502 based on APHA 3111 D
Boron APHA 4500-C B
Cyanide APHA 4500-CN C & D
Phenol APHA 5530 C
Free Chlorine In-situ, In-house Method 0501 base on Palintest Comparator
Sulphide APHA 4500 S2- F
Oil and grease APHA 5520 B
Turbidity (NTU) APHA 2130 B
Ammoniacal Nitrogen APHA 4500-NH3 C
Total Coliform Count APHA 9221 B
ENVIRONMENTAL SCOPING INFORMATION (ESI)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF HEALTHCARE
WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT RAMBAI, FASA 4C,
MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd TOC 50
CK/EV803/8026/18 ESI Revision No.: 1 Revision Date: October 2018
Parameters Test Method
Faecal Coliform Count APHA 9221 E
Dioxin and furan US EPA Method 1613B
4.1.5.2 Ambient Air Quality
In order to gauge baseline ambient air quality within the Project site and at the identified sensitive
receptors, four sampling locations will be established as listed in Table 23 and shown in Figure 13.
Ambient air monitoring will be carried out twice (except for dioxin and furan) preferably to represent dry
weather and wet weather conditions.
Table 23: Proposed Baseline Ambient Air Quality Sampling Locations
Station Approximate Coordinates Justification
A1 2°16'48.3"N 102° 10' 51.3"E To represent the ambient air quality at the north boundary of Project site.
A2 2°16'53.7"N 102°11'15.9"E To represent the ambient air quality at Taman Tg Minyak Utama (padang permainan facing main road) located northeast of Project site.
A3 2°16'36.6"N 102° 10' 25.5"E To represent the ambient air quality at Kg Ayer Salak located southwest of the Project site.
A4 2°15'47.0"N 102° 11' 3.2"E To represent the ambient air quality at Taman Rambai Jaya located south of Project site.
The test parameters and respective test methods for ambient air quality baseline are tabulated in Table
24. Test results obtained will be evaluated against the Malaysia Ambient Air Quality Standard and Arizona
Ambient Air Quality Standard (Appendix 3) and discussed in the EIA report.
Table 24: Proposed Test Parameters for Ambient Air Quality
Parameters Test Methods
PM2.5 High Volume Sampler
AS/NZS 3580.9.14.2013
PM10 High Volume Sampler
AS/NZS 3580.9.6.2003
Sulphur Oxides (as SOx) Air Sampling Pump
In House Method based on Methods of air sampling and analysis, 3rd Edition, Method 704 A
Nitrogen Oxides (as NOx) Air Sampling Pump
In House Method based on Methods of air sampling and analysis, 3rd Edition, Method 818A (sampling excluded)
CO In-situ using Dositube
HCl ID 174 SG
HF ID 110
ENVIRONMENTAL SCOPING INFORMATION (ESI)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF HEALTHCARE
WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT RAMBAI, FASA 4C,
MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd TOC 51
CK/EV803/8026/18 ESI Revision No.: 1 Revision Date: October 2018
Parameters Test Methods
Lead, Mercury, Cadmium, Chromium, Arsenic, Copper
Extracted from particulate matters filter paper
ICPMS
Dioxin and furan US EPA Method TO-9A
4.1.5.3 Ambient Noise Level
Existing ambient noise levels at the boundary of the Project site and identified sensitive receptor will be
described in terms of tenth and ninetieth percentiles (L10 and L90), equivalent continuous sound pressure
level (Leq), and minimum and maximum instantaneous levels (Lmin and Lmax). The existing ambient noise
levels will be monitored over 24 hours to represent 15 hours day time (7am to 10pm) and 9 hours night
time (10pm to 7am) conditions at the baseline locations shown in Figure 13.
A calibrated sound level meter will be used for the noise measurement. Baseline for ambient noise level
will be established at four proposed monitoring stations as listed in Table 25.
Table 25: Proposed Baseline Noise Measurement Locations
Station Approximate Coordinates Justification
N1 2°16'48.1"N 102°10'51.9"E To represent the ambient noise level at the northeast boundary of the Project
N2 2°16'46.2"N 102°10'50.7"E To represent the ambient noise level at the west boundary of the Project site.
N3 2°16'44.7"N 102°10'52.9"E To represent the ambient noise level at the south boundary of the Project site.
N4 2°16'53.7"N 102°11'15.9"E To represent the noise level at Taman Tg Minyak Utama located northeast of Project site.
Measured results will be evaluated against the Planning Guidelines for Environmental Noise Limits and
Control (Appendix 4) and discussed in the EIA report.
4.2 BIOLOGICAL ENVIRONMENT
The Project is located within an existing centre of healthcare waste treatment facility. The area is a ready
site with concrete pavement. The immediate surroundings of the Project site also have been cleared and
developed into industrial lots within the Kawasan Perindustrian Bukit Rambai, Fasa 4C. Therefore, there is
no flora and fauna of significant values are present at the area and its surroundings.
4.3 HUMAN ENVIRONMENT
4.3.1 Land Use
The land use component of the existing environment shall involve collation, review and analyses of both
primary and secondary data. An initial site visit was carried out to familiarize with the existing use of the
land of the Project site and its surrounding areas. The zone of study is 5 km radius from the Project site.
ENVIRONMENTAL SCOPING INFORMATION (ESI)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF HEALTHCARE
WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT RAMBAI, FASA 4C,
MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd TOC 52
CK/EV803/8026/18 ESI Revision No.: 1 Revision Date: October 2018
Existing Land Use within the Project Site
The Project is located within an existing centre of healthcare waste treatment facility owned by MSB. The
facility is located within Kawasan Perindustrian Bukit Rambai, Fasa 4C.
Plates 35 – 37 show some of existing on-site conditions.
Plate 33 Existing Project site condition
Plate 34: Location of former incinerator. The new incinerator will be placed here.
ENVIRONMENTAL SCOPING INFORMATION (ESI)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF HEALTHCARE
WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT RAMBAI, FASA 4C,
MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd TOC 53
CK/EV803/8026/18 ESI Revision No.: 1 Revision Date: October 2018
Plate 35: Existing Microwave Facilities
Existing Land Use within 5 km radius from Project Site
Existing land use within 5 km radius from the Project site is shown in Figure 14(a-d). The prominent land
uses within 5 km radius from the Project site are listed in Table 26. Additional site surveys will be
conducted to locate and map land uses and features within 5 km radius of the Project site and the land
use maps will be updated where necessary in the EIA report.
Based on reference made to Rancangan Tempatan Daerah Melaka Tengah 2003-2015, the Project site is
located in Blok 3.3.i – Blok Perancangan Kecil 3.3: Tanjung Minyak within Blok Perancangan (BP) 3:
Tangga Batu. BP 3 covers an area of 12,348.84 ha with BPK 3.3 covers an area of 3,516.70 ha. The
major land uses within BPK 3.3i are commercial, housing and Tanjung Minyak Indutsrial Area. Figure 15
illustrates the future land use of the Project site.
ENVIRONMENTAL SCOPING INFORMATION (ESI)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF HEALTHCARE
WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT RAMBAI, FASA 4C,
MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd TOC 54
CK/EV803/8026/18 ESI Revision No.: 1 Revision Date: October 2018
Table 26: Land Use within 3 km radius
Land Use Type
Distance from Project Site
Description
Industry
Up to 250 m Radius
Easy Power Sdn Bhd (south) STS Steven Trading Sdn Bhd (southeast)
HASRO Furniture Gallery Sdn Bhd (southwest)
Teras Puncak Sdn Bhd (southwest)
AZY (factory)(southwest) RONAS Niaga Enterprise (southwest)
FOMTEC Industries Sdn Bhd (southwest)
DRPTS Manufacturing Sdn Bhd (west)
Elegant Success Sdn Bhd (northwest)
MASRO Group of Companies (northwest)
Up to 500 m Radius
Kawasan Perindustrian Tanjung Minyak Perdana (northeast)
Fimmex Trading Sdn Bhd (southwest)
WINCO Precision Engineering (Melaka) Sdn Bhd (southwest)
Daiyan Marketing Sdn Bhd (southwest)
Grand Fortune Corporation Sdn Bhd (southwest)
Green Aim Oil Refinery (west)
Up to 1 km Radius
DIALOG (southwest) MASBRO Paya Rumput Sdn Bhd (south)
Shen Yong Design and Fabrication Sdn Bhd (southwest)
Protection Technology Sdn Bhd (southeast)
Jati Beringin Sdn Bhd (south)
MCTI Scientex Solar Sdn Bhd (southeast)
FETTA Auto Part Industries (M) Sdn Bhd (southeast)
Teng Long Industries (M) Sdn Bhd (southeast)
Industry
Up to 2 km Radius
Leong Hup Feedmill Sdn Bhd (southwest)
Fazlie Trading and Construction (southeast)
SunMetal Industries (M) Sdn Bhd (south)
Up to 3 km Radius
Pine & Hill Wood Products
Up to 5 km Radius
Imperial Steal Drum Manufactures Sdn Bhd (southwest)
TKR Manufacturing (M) Sdn Bhd (southwest)
Panasonic Appliances Foundry Malaysia Sdn Bhd (southwest)
Petronas Melaka Lube Blending Plant (southwest)
Depoh Petronas (southwest) Melaka Fuel and LPG Terminal (southwest)
Petronas Penapisan Kontra Pharma (M) Sdn Bhd
ENVIRONMENTAL SCOPING INFORMATION (ESI)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF HEALTHCARE
WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT RAMBAI, FASA 4C,
MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd TOC 55
CK/EV803/8026/18 ESI Revision No.: 1 Revision Date: October 2018
Land Use Type
Distance from Project Site
Description
(Melaka) Sdn Bhd (southwest)
(southeast)
SWM Environment Sdn Bhd (southeast)
Likom Caseworks Sdn Bhd (southeast)
Settlement
Up to 1 km Radius
Taman Tanjung Minyak Perdana (northeast)
Up to 2 km Radius
Kg Ayer Salak (southwest) Taman Rambai Indah (southwest)
Taman Tanjung Minyak Utama (southeast)
Bertam Ulu (east)
Taman Bertam Permai (northeast)
Kg Bertam Ulu (northeast)
Taman Bertam Impian (north)
Taman Bertam Setia (northeast)
Taman Rambai Utama (southeast)
Up to 3 km Radius
Kg Ayer Supai (northeast) Taman Seri Bertam (northwest)
Kg Tangga Batu (southwest) Taman Rambai (southwest)
Tangga Batu (southwest) Kg Seberang Gajah (southwest)
Taman Malim Jaya (southwest)
Taman Tanjung Minyak Setia (southeast)
Taman Sri Rambai (southeast)
Tanjung Minyak (southeast)
Taman Perwira Rumah Awam Cheng (southeast)
Taman Cheng Jaya (southeast)
Taman Cheng Perdana (southeast)
Taman Bertam Jaya (east)
Taman Paya Emas (northeast)
Taman Cheng Baru (southeast)
Up to 5 km Radius
Taman Paya Rumput Perdana (northeast)
Taman Raya Rumput Indah (northeast)
Taman Seri Paya Rumput (northeast)
Taman Paya Rumput (northeast)
Taman Permai (northeast) Taman Bukit Cheng (southeast)
Taman Cheng Utama (southeast)
Taman Cheng Ria (southeast)
Taman Asean (southeast) Taman Gadong Perdana (southeast)
Kg Bukit Rambai (southeast) Taman Malim Jaya (southeast)
Kg Gaffar Baba (southwest) Kg Rambai Tengah (southeast)
Sg Udang (northwest) Taman Merdeka (southeast)
Kg Gelam (southwest) Kg Tanah Merah Jaya (southwest)
ENVIRONMENTAL SCOPING INFORMATION (ESI)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF HEALTHCARE
WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT RAMBAI, FASA 4C,
MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd TOC 56
CK/EV803/8026/18 ESI Revision No.: 1 Revision Date: October 2018
Land Use Type
Distance from Project Site
Description
Kg Pantai Kundur (southwest)
Kg Sg Udang (west)
Taman Peruna (west) Taman Pahlawan (northwest)
Institution
Up to 2 km Radius
SK Bertam Hulu (northeast) St Mary Chinese Primary School (southwest)
Madrasah Al-Hikmah (northeast)
SJK(C) Bertam Ulu (northeast)
Up to 3 km Radius
SMK Taman Bukit Rambai (southwest)
SJK(C) Cheng (southeast)
SMK Tun Haji Abd Malek (southeast)
SK Tanjung Minyak (southeast)
Up to 5 km Radius
SK Bukit Rambai (southeast) SK Kg Gelam (southwest)
SJK(C) Poh Lan (southwest) SK Sg Udang (west)
SMK Malim (southeast) Kompleks Penjara Melaka (northwest)
Public Amenities / Utilities
Up to 1 km Radius
Kuil Metto Amman (northwest)
Melaka Chinese Temple (southeast)
PMU Bukit Rambai (southeast)
Up to 2 km Radius
Church of St. Mary, Ayer Salak (southwest)
Surau Al-Usrah (northeast)
Masjid Bertam Ulu (northeast)
Up to 3 km Radius
Tangga Batu Fire and Rescue Station (southwest)
Surau Rumah Awam Datin Fatimah Bukit Rambai (southwest)
Up to 5 km Radius
Masjid Al-Faizin (south) Turkish Mosque Rombang
Masjid Tangga Batu Pekan, Tanjong Kling (southwest)
Masjid Mohsinin (southwest)
Perpustakaan Desa Paya Rumput (northeast)
Kuil Sannasimalai Andavar Tirukkoril
10
1
2
4
5
6
7
3
8
9
11
12
13
14
15
16
17
18
21
19
20
22
23
24
25
2627
28
2930
31
CHEMSAIN KONSULTANT SDN. BHD.
LEGEND:
LAND USE WITHIN
500M RADIUS
500M Radius
250M Radius
FIGURE 14a
1
2
3
4
5
6
7
8
9
10
11
12
13
14
CHEMSAIN KONSULTANT SDN. BHD.
LAND USE WITHIN
1KM RADIUS
500M Radius
1KM Radius
250M Radius
LEGEND:
FIGURE 14b
1
2
3
4
5
6
7
8
9
10
11
12 13
14
15
1617
18
19
20
21
22
23
24
25
26
27
28
2930
31
33
32
35
34
36
37
38
39
40
41
42
43
CHEMSAIN KONSULTANT SDN. BHD.
LAND USE WITHIN
3KM RADIUS
500M Radius
1KM Radius
2KM Radius
3KM Radius
LEGEND:
FIGURE 14c
1
2
34
5
67
8
9
10
11
12
13
14
15
16
17
1819
2120
22
23
24
25
26
27
28
29
3031
32
33
34
35
36 37
38
39 40
41
42
43
44
45
46
47
CHEMSAIN KONSULTANT SDN. BHD.
LAND USE WITHIN
5KM RADIUS
500M Radius
1KM Radius
2KM Radius
3KM Radius
4KM Radius
5KM Radius
LEGEND:
FIGURE 14d
ENVIRONMENTAL SCOPING INFORMATION (ESI)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF HEALTHCARE
WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT RAMBAI, FASA 4C,
MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd TOC 57
CK/EV803/8026/18 ESI Revision No.: 1 Revision Date: October 2018
5 OUTLINE OF PLANNING AND IMPLEMENTATION PROGRAMME
5.1 REVIEW OF GUIDELINES AND ENVIRONMENTAL LEGISLATIONS
The EIA study and report shall be undertaken in accordance with the guidelines issued by the DOE and
other agencies. The list of guidelines is not exhaustive and subject to updates and new requirement by the
respective agencies. Nevertheless, the relevant list of guidelines includes:
Environmental Impact Assessment Guidelines for Risk Assessment, December 2004.
Environmental Impact Assessment Guidelines for Toxic and Hazardous Waste Treatment and
Disposal Projects, February 2000
Environmental Impact Assessment Guidelines in Malaysia (2016) by DOE
Environmental Quality (Amendment) Act, 2012
Environmental Quality (Industrial Effluent) Regulations, 2009
Environmental Quality (Prescribed Activities) (Environmental Impact Assessment) Order 2015
Environmental Quality (Scheduled Wastes) Regulations, 2005
Environmental Quality Act, 1974
Factory and Machinery Act (revised 1974)
Guidance Document for Addressing Soil Erosion and Sediment Control Aspects In The
Environmental Impact Assessment (EIA) Report (19 July 2016) by DOE
Guidance Document for the Preparation Of The Document On Land-Disturbing Pollution
Prevention and Mitigation Measures (LD-P2M2) (19 July 2016) by DOE
Guidance Document on Health Impact Assessment (HIA) in Environmental Impact Assessment
(EIA), June 2012
Occupational Safety and Health Act,1994
Environmental Quality (Clean Air) Regulations 2014
The Planning Guidelines for Environmental Noise Limits and Control, (2nd Edition, August 2007)
by DOE
Town and Country Planning Act, 1960
ENVIRONMENTAL SCOPING INFORMATION (ESI)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF HEALTHCARE
WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT RAMBAI, FASA 4C,
MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd TOC 58
CK/EV803/8026/18 ESI Revision No.: 1 Revision Date: October 2018
5.2 REVIEW OF PREVIOUSLY APPROVED EIA REPORTS OR STUDIES
Relevant reliable journals, articles, case studies, guidelines and secondary data (i.e. previous EIA Report
of the Project, baseline data, on-going monitoring reports, and safety records); will be reviewed to assist in
the further comprehension of the projected environmental impacts resultant from the Project. Some of the
references include:
Detailed Environmental Impact Assessment for Proposed Clinical Waste Incinerator Replacement
Project at Radicare (M) Sdn Bhd Plant in Lot 5, Jalan Waja 16, Teluk Panglima Garang, Daerah
Kuala Langat, Selangor (2018) prepared by Tri Ecoedge Sdn Bhd.
Detailed Environmental Impact Assessment for the Proposed Clinical Waste Thermal Treatment
Facility in Sabah by Faber Medi-Serve Sdn. Bhd (2009) prepared by Chemsain Konsultant Sdn
Bhd.
5.3 ENGAGEMENT WITH RELEVANT AGENCIES AND LOCAL COMMUNITY
Government policies, legislation and regulations relevant to the proposal will be identified. Local plans
and policies will also be evaluated. Project characteristics will be analysed to ensure compliance with
these policies, legislation and regulations. Appropriate recommendations will be provided to ensure
regulatory compliance. Discussions and meetings may be carried out with various Government Agencies;
with Ministry of Health and Department of Environment being the two key agencies and other agencies
such as:
Department of Environment (DOE)
Ministry of Health (MOH)
Majlis Bandaraya Melaka Bersejarah
Any other relevant Government Agencies as and when necessary
It is intended that this consultation will be in the form of informal and formal discussions.
5.3.1 Socio-economic
The existing socio-economic information will cover the population of the district and residents living nearby
the zone of influence. An introduction of the socio economic information at the district where the Project is
located is necessary to allow an understanding of:
The strategic importance of having the project at the district and
The socio-economic background of the population in the district.
The source of the data will be collected from secondary demographic data from the Department of
Statistics publication on The 2010 Population and Housing Census of Malaysia.
The information on the socio-economic characteristics of the populations and economic activities
surrounding the project site include demographic characteristics such as on population and household
size, gender, race and age.
ENVIRONMENTAL SCOPING INFORMATION (ESI)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF HEALTHCARE
WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT RAMBAI, FASA 4C,
MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd TOC 59
CK/EV803/8026/18 ESI Revision No.: 1 Revision Date: October 2018
5.4 PROJECT IMPLEMENTATION
As mentioned in section 2.3, Medivest is the Project Proponent that will undertake the Project
development. Chemsain Konsultant Sdn Bhd, the preparer of this ESI has been appointed by Medivest
Sdn Bhd to undertake the EIA study. Contact details of the company is as provided in section 1.1.
5.5 PROJECT TIMETABLE
As mentioned in section 2.9, upon getting EIA approval and other necessary approval, the development of
the Project will take about 12 months including testing and commissioning.
5.6 PROJECT ASSESSMENT TIMELINE
The proposed EIA timeline is as shown in Figure 16. This schedule may be revised accordingly as and
when new updates and significant information are received from the Contractor.
5.7 CONSIDERATION OF CONCURRENT PROJECTS
Based on initial site survey, there is no concurrent projects adjacent to the Project site. Therefore, no
cumulative impacts to the surrounding areas is anticipated.
ENVIRONMENTAL SCOPING INFORMATION (ESI)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF HEALTHCARE WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32
& 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT RAMBAI, FASA 4C, MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd Page 60
CK/EV803/8026/18 ESI Revision No.: 0 Revision Date: July 2018
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48
Appointment
Information from Client
Site Survey and Land Use
Engagement with Relevant Government
Agencies on TOR (DOE and Ministry of Health)
Preparation of TOR
TOR to Client and Review
Submission of TOR to DOE
Review and Endorsement of TOR by DOE (TOR
Meeting)#
1st baseline sampling (air, water, noise), land
use survey (5 km)
2nd baseline sampling (air, water), land use
survey (5 km)
Engagement with Relevant Government
Agencies on fact finding / comment on the
Project
Data analyses and interpretation
Impact Assessment
EMP and Monitoring Programme
Public Dialogue
Report Compilation
Preparation and Submission of Draft EIA Report
to Client
Review of Draft DEIA Report by Client
Engagement with Relevant Government
Agencies to Inform of EIA Findings
Printing and Report QA & QC
Submission Final EIA report to DOE
EIA Report Display Public Review
EIA Approval Process (3 months) / EIA Meeting#
Activity
Figure 16: Proposed EIA Study Schedule
ENVIRONMENTAL SCOPING INFORMATION (ESI)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF HEALTHCARE
WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT RAMBAI, FASA 4C,
MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd Page 61
CK/EV803/8026/18 ESI Revision No.: 0 Revision Date: July 2018
6 ENVIRONMENTAL SENSITIVE AREAS
Based on initial desktop study, human settlements, schools and places of worship have been identified as
the environmental sensitive areas (ESA) which are located adjacent to the Project site. The ESAs are
listed in Table 27 below and shown in Figure 17.
Table 27: Environmental Sensitive Areas (ESA) - Settlement
Radius Area
Up to 1 km Radius Taman Tanjung Minyak Perdana (northeast)
Kuli Metto Amman (northwest)
Melaka Chinese Temple (southeast)
Up to 2 km Radius Kg Ayer Salak (southwest) Taman Rambai Indah (southwest)
Taman Tanjung Minyak Utama (southeast)
Bertam Ulu (east)
Taman Bertam Permai (northeast) Kg Bertam Ulu (northeast)
Taman Bertam Impian (north) Taman Bertam Setia (northeast)
Taman Rambai Utama (southeast) SK Bertam Ulu (northeast)
Madrasah Al-Hikmah (northeast) SJK(C) Bertam Ulu (northeast)
Church of St. Mary, Ayer Salak (southwest)
Masjid Bertam Ulu (northeast)
Surau Al-Usrah (northeast)
Up to 3 km Radius Kg Ayer Supai (northeast) Taman Seri Bertam (northwest)
Kg Tangga Batu (southwest) Taman Rambai (southwest)
Tangga Batu (southwest) Kg Seberang Gajah (southwest)
Taman Malim Jaya (southwest) Taman Tanjung Minyak Setia (southeast)
Taman Sri Rambai (southeast) Tanjung Minyak (southeast)
Taman Perwira Rumah Awam Cheng (southeast)
Taman Cheng Jaya (southeast)
Taman Cheng Perdana (southeast) Taman Bertam Jaya (east)
Taman Paya Emas (northeast) Taman Cheng Baru (southeast)
SMK Taman Bukit Rambai (southwest)
SJK(C) Cheng (southeast)
SMK Tun Haji Abd Malek (southeast) SK Tanjung Minyak (southeast)
Tangga Batu Fire and Rescue Station (southwest)
Surau Rumah Awam Datin Fatimah Bukit Rambai (southwest)
Up to 5 km Radius Taman Paya Rumput Perdana (northeast)
Taman Raya Rumput Indah (northeast)
Taman Seri Paya Rumput (northeast)
Taman Paya Rumput (northeast)
Taman Permai (northeast) Taman Bukit Cheng (southeast)
ENVIRONMENTAL SCOPING INFORMATION (ESI)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF HEALTHCARE
WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT RAMBAI, FASA 4C,
MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd Page 62
CK/EV803/8026/18 ESI Revision No.: 0 Revision Date: July 2018
Radius Area
Taman Cheng Utama (southeast) Taman Cheng Ria (southeast)
Taman Asean (southeast) Taman Gadong Perdana (southeast)
Kg Bukit Rambai (southeast) Taman Malim Jaya (southeast)
Kg Gaffar Baba (southwest) Kg Rambai Tengah (southeast)
Sg Udang (northwest) Taman Merdeka (southeast)
Kg Gelam (southwest) Kg Tanah Merah Jaya (southwest)
Kg Pantai Kundur (southwest) Kg Sg Udang (west)
Taman Peruna (west) Taman Pahlawan (northwest)
SK Bukit Rambai (southeast) SK Kg Gelam (southwest)
SJK(C) Poh Lan (southwest) SK Sg Udang (west)
SMK Malim (southeast) Kompleks Penjara Melaka (northwest)
Masjid Al-Faizin (south) Turkish Mosque Rombang
Masjid Tangga Batu Pekan, Tanjong Kling (southwest)
Masjid Mohsinin (southwest)
Perpustakaan Desa Paya Rumput (northeast)
Kuil Sannasimalai Andavar Tirukkoril
7 POSSIBLE SIGNIFICANT ENVIRONMENTAL IMPACTS
A comprehensive assessment as to the potential environmental impacts which may be presented as a
result of the Project during construction and operation stages will be undertaken in relation to various
contexts, including that of natural environmental impact, human health impact, socio-economic and other
associated impacts. The significant environmental impacts which are anticipated due to the development
of the Project are as listed in Table 28.
Table 28: Anticipated Significant Environmental Impacts
No Project Stage Project Activities Environmental Impacts
1. Construction Stage
Mobilisation of Workforce
Foundation works – soil improvement,
piling
Civil and structure works – incinerator
plant and IETS
Transportation of construction material
and equipment
Mechanical and electrical works –
installation of all process equipment,
conveying systems and environmental
control systems
Water quality impact
Air quality impact
Noise impact
Waste generation and management
10
9
8
6
1
2
37
5
4
11
12
14
13
16
19
18
17
20
21
15
22
23
24
25
26
27
28
29
30
31
33
32
34
3539
43
44
45
46
42
47
37 38
36
40
41
48
49
5051
52
53
54
55
56
57 58
6059
61
62
63
64
65
66
67
6869
70
71
CHEMSAIN KONSULTANT SDN. BHD.
ENVIRONMENTAL
SENSITIVE AREA
LEGEND:
500M Radius
1KM Radius
2KM Radius
3KM Radius
5KM Radius
4KM Radius
FIGURE 17
ENVIRONMENTAL SCOPING INFORMATION (ESI)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF HEALTHCARE
WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT RAMBAI, FASA 4C,
MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd Page 63
CK/EV803/8026/18 ESI Revision No.: 0 Revision Date: July 2018
No Project Stage Project Activities Environmental Impacts
Testing and commissioning - No-load,
load and performance tests
2. Operation and Maintenance Stage
Transportation of healthcare wastes to
Project site
Operation of incinerator
Maintenance works
Trucks and bins washing
Potential accidental spillage
Waste generation and management
Safety hazard
Air quality
Noise impact
Health impact
Water quality
8 DESCRIPTION OF MODELLING TOOLS, ASSESSMENT
METHODOLOGIES
8.1 WATER QUALITY
The thermal treatment or incineration of the healthcare wastes is a dry process. The only possible
sources of wastewater are from the truck/ bin cleansing and disinfection activities. The potential scenarios
for water pollution will be assessed based on the evaluation of the projected wastewater discharge from
the washing bay area.
Initial assessment of wastewater management found that the potential impact on water quality is
considered low since the volume of wastewater from the truck/bin cleansing and disinfection activities is
low and shall be channelled to IETS for treatment before being discharged to the industrial area drainage
system.
Nonetheless, the assessment on water quality shall be further detailed out in the EIA. The evaluation of
impacts will be made against established standards and criteria made under the Environmental Quality
Act, 1974 and its subsidiary legislation as well as other international accepted criteria. Appropriate
mitigation measures shall be recommended to minimise the impact on water quality.
8.2 AIR QUALITY
Prediction of air quality impact during construction stage is due to fugitive dust and gases emissions from
vehicle exhausts and machineries. Potential air quality impact during construction stage is considered
low, temporary and insignificant.
During operation stage, air quality impact is one of the main environmental issues expected from the
operation of the proposed facility. The prediction of impacts due to air pollutants will be made for point
and fugitive dust emissions. Air pollutants are expected from, but not limited to the following sources:
Emissions of flue gases from combustion via the chimney
Handling of ash
ENVIRONMENTAL SCOPING INFORMATION (ESI)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF HEALTHCARE
WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT RAMBAI, FASA 4C,
MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd Page 64
CK/EV803/8026/18 ESI Revision No.: 0 Revision Date: July 2018
Healthcare wastes incineration depending on the capacity, waste feed and combustion conditions of the
incineration facility, can emit the following pollutants into the atmosphere:
Particulate matter
Heavy metals (i.e. lead, cadmium, arsenic, mercury)
Acid gases (HCl, SO2)
Oxides of nitrogen
Carbon monoxide
Organics (VOC, dioxin and furan)
Various other materials present in healthcare wastes, such as pathogens and cytotoxins. No radioactive
substances are expected as these are removed before the waste is incinerated.
Particulate matter is emitted as a result of incomplete combustion of organic matter and the entrainment of
non-combustible ash due to the turbulent movement of combustion gases. Particulate matter may contain
heavy metals, acids and trace organics. Acid gases like HCl and (SO2) in the exhaust gas are directly
related to the chlorine and sulphur content of the waste. Most of the chlorine are from polyvinyl chloride
(PVC) waste and other chlorinated compounds wherein during incineration are converted to HCl. Sulphur
is also chemically-bound within the waste materials and is oxidised during combustion to form SO2.
NOx is formed during combustion by i) oxidation of nitrogen chemically bound in waste and ii) reaction
between molecular nitrogen and oxygen in combustion air. As for CO, it is a product of incomplete
combustion.
Similarly, failure to achieve complete combustion of organic materials may result in emissions of a variety
of organic compounds such as methane, ethane and other high molecular weight organics (dioxins and
furans).
Based on assessment study requirements, the type of sources and outputs required, the model selected
for this assessment will be the USEPA AERMOD Model. In this particular assessment, a 10 km X 10 km
(5 km radius) Cartesian grid with 100 m spacing for the nearest 1 km receptors and 200m grid spacing for
receptors further than 1 km from the source is used for impact modelling. The surface weather and upper
air data used in the AERMOD modelling input will be from the nearest meteorological station. One year of
the latest hourly meteorological data consisting of wind speed, wind direction, temperature, stability and
mixing height available data will be used in the analysis.
All raw data used in the modelling will be appended in the EIA report.
Pollutants to be modelled and assessed are
i. PM10 ii. PM2.5 iii. NO2
iv. SO2 v. HCl vi. arsenic (as As)
vii. cadmium (as Cd) viii. lead (as Pb) ix. mercury (as Hg)
x. dioxin and furan
ENVIRONMENTAL SCOPING INFORMATION (ESI)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF HEALTHCARE
WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT RAMBAI, FASA 4C,
MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd Page 65
CK/EV803/8026/18 ESI Revision No.: 0 Revision Date: July 2018
Results of the modelling will be assessed based upon other criteria generally accepted by the DOE for
ground level concentrations of air pollutants and also reputable and relevant international standards. The
type of air pollution control system used will also be addressed. Based on the result, recommendations to
minimise the impact to the surrounding land use or receptor will be formulated.
8.3 WASTE MANAGEMENT
Ash will be generated as waste from the proposed facility, namely bottom ash and fly ash. These ashes
are generated as result of combustion processes in the primary chamber, secondary chamber, dry
scrubber and bag filter. Proper handling of these ashes is fundamental to minimise any environmental
impact from the overall operation of the proposed facility.
Evaluation of the impacts from wastes generated will be made based on existing information on the
characteristics of the ash from other similar plant. Furthermore, this evaluation will involve the
consideration of proposed disposal methods and capacities of receiving licensed premises.
The other anticipated type of wastes includes the following:
Stage Category Type of Waste Possible Source
Construction Stage
Scheduled Waste Disposed containers, bags or equipment contaminated with chemicals, pesticides, mineral oil or schedule wastes (SW409)
Construction area, workshop
Rags or filters contaminated with scheduled waste (SW410)
Spent lubrication oil (SW 305)
Waste of inks, paints, pigments, lacquer, dye or varnish SW 417
Solid Waste Metal Scrap/ Construction material Stockpile on site
Operation and Maintenance Stage
Scheduled Waste Ashes from scheduled waste incinerator (SW 406)
Incinerator
Spent lubrication oil (SW 305) Incinerator, workshop
Spent hydraulic oil (SW 306) Incinerator, workshop
Disposed containers, bags or equipment contaminated with chemicals, pesticides, mineral oil or schedule wastes (SW409)
Storage area
Rags or filters contaminated with scheduled waste (SW410)
Storage area
Sludges containing one or several metals including chromium, copper, nickle, zinc, lead, cadmium, aluminium, tin, vanadium and beryllium (SW204)
IETS
Proposed management of wastes will be evaluated and documented in the EIA report.
ENVIRONMENTAL SCOPING INFORMATION (ESI)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF HEALTHCARE
WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT RAMBAI, FASA 4C,
MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd Page 66
CK/EV803/8026/18 ESI Revision No.: 0 Revision Date: July 2018
8.4 HEALTH IMPACT ASSESSMENT
The Health impact assessment (HIA) component will investigate potential public health impacts from
primary environmental influences such as air quality and water quality, on the population residing in the
vicinity of the proposed Project especially during the construction and operation stages The HIA
methodology will be based on the Guidance Document on HIA in EIA issued by the Department of
Environment as well as the US EPA’s Human Health Risk Assessment Protocol.
It is anticipated that main environmental influences from the proposed Project will be the changes to
ambient air quality. The air pollutants that will be modelled for their health effects are:
i. PM10 ii. NO2 iii. SO2
iv. HCl v. arsenic (as As) vi. cadmium (as Cd)
vii. lead (as Pb) viii. mercury (as Hg) ix. dioxins and furans
A description of the existing public health status will be attempted. This will involve describing the present
health status of the population residing in the vicinity of the proposed Project. It will involve both primary
and secondary data collection. Primary data on community health status will be obtained through a health
questionnaire survey of the residents within the proposed project’s zone of impact. Secondary data on
disease morbidity will be requested from the nearest government hospital and health clinic to the
proposed project site.
To assess the public health risk of the proposed Project a health risk assessment (HRA) methodology will
be employed. The HRA will describe the public health impacts and risks on the population residing within
the zone of impact of the proposed Project during its construction and operational phases. It will employ
the health risk assessment (HRA) approach adopted in the Guidance Document which comprises the six
basic steps of issues identification, hazard identification, dose-response assessment, exposure
assessment, risk characterization and uncertainty analysis. Data input into the HRA process will be
sourced from the health survey, air quality modeling outputs, water quality modeling outputs, published
epidemiological studies on health effects of air and water pollutants, and exposure parameters database
from the US EPA or ATSDR. The specific areas which will be encompassed as part of this HIA will
include, but will not be limited to:
Assessment of public health risks (both acute and chronic) associated with the proposed emission of
air pollutants from the Project during testing and commissioning and full operation. Assessment and
impact projection will be in consideration of any other accumulating sources nearby the proposed
Project site;
Assessment of public health risks (both acute and chronic) associated with any other activities which
at this stage of the assessment are not foreseen.
Based on the outcomes of the HRA process, appropriate mitigation and control measures will be proposed
to minimize the environmental health impacts on the impacted community.
Residual environmental health impacts on the impacted community, if any, will be identified and
adequately described. A proper environmental monitoring and auditing program will be proposed for the
residual impacts identified, if necessary.
ENVIRONMENTAL SCOPING INFORMATION (ESI)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF HEALTHCARE
WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT RAMBAI, FASA 4C,
MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd Page 67
CK/EV803/8026/18 ESI Revision No.: 0 Revision Date: July 2018
8.5 QUANTITATIVE RISK ASSESSMENT
Quantitative Risk Assessment (QRA) is the application of methodology to produce a numerical
representation of the frequency and extent of a specified level of exposure or harm, to specified people or
the environment, due to the operation of the Project. The objectives of such assessment are:
To identify the major risk associated with the handling / storage of the hazardous substances at the
incinerator plant.
To determine hazards / risks due to possible accident scenarios which will lead to fire, explosion or
toxic release at the incinerator plant.
To recommend mitigating measures in order to reduce / minimise the risks / hazards to a level which
is as low as reasonably practicable.
The principal stages of this risk assessment are briefly described as follows:
Data Collection - Information is collected and documented covering the following areas:
Description: the layout of the plant and proposed process.
Surrounding environment: the topography, meteorology, population distribution, possible ignition
sources within or surrounding the proposed Project site.
Safety measures: the measures available to prevent and/or mitigate possible accidents.
Hazard Identification - All potential hazards resulting from the failures of handling and storage of the
hazardous substances are identified. The identification process uses a mixture of experience from
previous QRA’s.
Frequency Analysis - All event outcome frequencies will be calculated based on generic data of
failure rates / leak frequencies applicable for each relevant industry.
Consequence Modelling - The consequences of each event are determined by established
modelling programs such as CIRRUS. The consequences are expressed as distance to levels, which
can cause fatalities.
Risk Presentation - The frequencies and the consequences of each event are combined to produce
overall measures of risk.
Major Risk Contributors - The risk generated by each accident scenario is ranked in terms of
initiating source and consequence type (i.e. explosion, jet fire, pool fire, etc.).
In examining the operations of the Project, all potential hazards arising from the incinerator facility
equipment failure will be identified. For this purpose, information on the incinerator facility layout will be
used for the identification of hazards. The only hazardous substance stored on-site is the fuel for the
incinerator, i.e. diesel. The QRA shall focus on all scenarios relevant to the handling and storage of diesel
within the plant. The possible hazardous scenarios that shall be evaluated are pool fires and its possible
impact towards the surrounding.
ENVIRONMENTAL SCOPING INFORMATION (ESI)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF HEALTHCARE
WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT RAMBAI, FASA 4C,
MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd Page 68
CK/EV803/8026/18 ESI Revision No.: 0 Revision Date: July 2018
The results shall be presented in a risk contour plot representing the overall risk arising from accidents
which could result in fatalities on-site and off-site. The final stage of this assessment is to compare the
public risk level arising from the operation of the incinerator plant with commonly acceptable risk levels.
Risk reduction measures and the effects of the mitigating measures will also be discussed to enhance the
safety of the plant.
8.6 NOISE
The major source of noise from the Project will arise from the operating machineries such as air
compressors, feed hopper, exhaust fan and other mechanical systems.
Noise impacts will be predicted based on the information of noise sources during the construction and
operation of the Project.
Noise levels at a distance from source will be predicted based on the approach that noise emanating from
a source will attenuate naturally as it propagates over free air. This is due to wave divergence, which
results in dissipation of sound energy. The attenuation of noise can be estimated based on information
related to sound power level of the source and the distance over which the sound travels.
Therefore, the propagation of a noise source measured at 1m away can be shown to behave to the
following formula:
(Point source)
(Line source)
Where,
L = Noise Level at d metres away from the source
L0 = Noise Level measured at 1 meter away from the source
d = Distance from the point source in meters
Mitigating measures and compliance noise limits will be proposed to minimise the predicted impacts.
ENVIRONMENTAL SCOPING INFORMATION (ESI)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF HEALTHCARE
WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT RAMBAI, FASA 4C,
MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd Page 69
CK/EV803/8026/18 ESI Revision No.: 0 Revision Date: July 2018
9 POSSIBLE MITIGATION MEASURES
Possible mitigation measures or best management practices from similar projects that may be used to
address the environmental impacts of this Project are listed in Table 29.
Table 29: Possible Mitigation Measures
No Project Stage Environmental Impacts Possible Mitigation Measures
1. Construction Stage
Water quality impact
Air quality impact
Noise impact
Waste generation and
management
Construction materials, oil storage area, etc.
should be stockpiled and located away from the
nearest waterway to minimize risk of water
pollution.
All chemicals, oil and fuels should be stored in a
designated and covered area onsite. These
areas should be provided with oil traps and also
bunded to prevent spillage.
No open burning of any materials on-site is
allowed.
Fuel burning equipment to be regularly
maintained and serviced to prevent the
emergence of dark smoke.
Piling works should be done in a proper manner
that will not cause black smoke, noise and
vibration problems using hydraulic piling or bore
piling methods or any other more
environmentally friendly methods. Piling works
are limited only from 8.00 am to 7.00 pm only.
All scheduled waste must be handled and
disposed off according to the Environmental
Quality (Scheduled Wastes) Regulations 2005.
2. Operation and Maintenance Stage
Potential accidental
spillage
Waste generation and
management
Safety hazard
Air quality
Noise impact
Health impact
Water quality impact
Periodical impact monitoring of water quality, air
quality and noise level.
All workers should be adequately trained in
terms of appropriate use, handling and disposal
of chemicals and lubricants involved in the
operation of the facility.
Emergency response plan should be
implemented in case there is any chemical or oil
spillage.
Good housekeeping at site.
Prohibit discharge of untreated sewage.
No open burning of any materials on-site is
allowed.
Periodical impact monitoring of air quality at
Project boundary and identified sensitive
receptor.
ENVIRONMENTAL SCOPING INFORMATION (ESI)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF HEALTHCARE
WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT RAMBAI, FASA 4C,
MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd Page 70
CK/EV803/8026/18 ESI Revision No.: 0 Revision Date: July 2018
No Project Stage Environmental Impacts Possible Mitigation Measures
Review and update the Emergency Response
Plan (ERP) for the operation of the Project.
Enforce safety procedures to ensure authorised
access only to the facility and further restrictions
are in place for limiting storage area access to
approved persons only.
Perform regular emergency response drills
(including desktop exercises), as well as
feedback and review sessions.
Conduct routine inspections of fire safety
requirements (fire blankets, fire extinguishers,
smoke detectors, sprinklers, emergency lighting
and fire-rated doors etc.
Installation of Continuous Emission Monitoring
System (CEMS) shall be conducted to monitor
the air emission parameters.
Installation of proper air pollution control
equipment.
All scheduled waste during maintenance works
must be handled and disposed off according to
the Environmental Quality (Scheduled Wastes)
Regulations 2005.
To provide appropriate designated and marked
storage areas for scheduled wastes.
For personnel stationed in identified high
temperature areas, rest periods away from high
temperature areas are to be scheduled when
high temperatures are encountered for
extended periods.
Establish periodical maintenance schedule for
all motorised machineries and equipment as
preventive measure to minimise emission of
loud noise. Attention shall be given to efficiency
of mufflers to reduce noise problems.
Enclosure or other type of acoustic measures
shall be applied on equipment which contribute
to noise levels higher than 85 dB (A).
Trucks and bins washing water to be treated in
IETS to comply with Standard B of the
Environmental Quality (Industrial Effluents)
Regulations 2009 prior discharge to public
drain.
ENVIRONMENTAL SCOPING INFORMATION (ESI)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF HEALTHCARE
WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT RAMBAI, FASA 4C,
MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd Page 71
CK/EV803/8026/18 ESI Revision No.: 0 Revision Date: July 2018
10 CONTENTS OF THE EIA REPORT
The EIA report will contain the following:
A non-technical executive summary (In English and Bahasa Malaysia);
An introduction to the proposed Project;
Description of the proposed Project components and activities;
Description and details of the existing environment indicated in Section 3 of this ESI;
Documentations of impact assessments as indicated in Section 6 of this ESI and their significance
during construction and operational stages of the Project. Mitigation measures and environmental
management to enhance the environmental performance during construction and operational
stages of the Project;
Residual impacts and monitoring requirements (three types of monitoring, namely: Performance
monitoring (PM), compliance (CM), and impact monitoring (IM). Each type shall be detailed out in
the EIA report); and
Conclusion of the EIA study.
11 REFERENCES
Tri Ecoedge Sdn Bhd. (2018). Proposed Clinical Waste Incinerator Replacement Project at Radicare (M)
Sdn Bhd Plant in Lot 5, Jalan Waja 16, Teluk Panglima Garang, Daerah Kuala Langat, Selangor.
Chemsain Konsultant Sdn Bhd. (2009). Detailed Environmental Impact Assessment for the Proposed
Clinical Waste Thermal Treatment Facility in Sabah by Faber Medi-Serve Sdn. Bhd.
Department of Environment. (2016) Environmental Impact Assessment Guidelines in Malaysia.
Department of Environment. (July 2016). Guidance Document for Preparing Terms of Reference (TOR).
Department of Environment. (June 2012). Guidance Document on Health Impact Assessment (HIA) in
Environmental Impact Assessment (EIA).
ENVIRONMENTAL SCOPING INFORMATION (ESI)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF HEALTHCARE
WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT RAMBAI, FASA 4C,
MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd App 1-1
CK/EV803/8026/18 ESI Revision No.: 0 Revision Date: July 2018
APPENDIX 1
NATIONAL WATER QUALITY STANDARDS FOR
MALAYSIA
ENVIRONMENTAL SCOPING INFORMATION (ESI)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF HEALTHCARE
WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT RAMBAI, FASA 4C,
MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd App 1-2
CK/EV803/8026/18 ESI Revision No.: 0 Revision Date: May 2018
NATIONAL WATER QUALITY STANDARDS FOR MALAYSIA
Classes
Parameters Unit I IIA IIB III IV V
Ammoniacal-N mg/l 0.1 0.3 0.3 0.9 2.7 >2.7
BOD mg/l 1 3 3 6 12 >12
COD mg/l 10 25 25 50 100 >100
DO mg/l 7 5-7 5-7 3-5 <3 <1
pH - 6.5-8.5 6-9 6-9 5-9 5-9 -
Colour TCU 15 150 150 - - -
Elec. Cond* S/cm 1000 1000 - - 6000 -
Floatables - N N N - - -
Odour - N N N - - -
Salinity % 0.5 1 - - 2 -
Taste - N N N - - -
Tot. Diss. Sol. mg/l 500 1000 - - 4000 -
Tot. Susp. Sol. mg/l 25 50 50 150 300 >300
Temperature °C - Normal + 2 °C
- Normal + 2 °C
- -
Turbidity NTU 5 50 50 - - -
F. Coliform** counts/ 100ml
10 100 400 5000 (20000)a
5000 (20000)a
-
Total Coliform counts/ 100ml
100 5000 5000 50000 50000 >50000
N = No visible floatable material / debris,
or No objectionable odour,
or No objectionable taste.
* = Related parameters, only one recommended for use
** = Geometric mean
a = Maximum not to be exceeded
ENVIRONMENTAL SCOPING INFORMATION (ESI)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF HEALTHCARE
WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT RAMBAI, FASA 4C,
MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd App 1-4
CK/EV803/8026/18 ESI Revision No.: 0 Revision Date: July 2018
Class
Parameter Unit I IIA / IIB III# IV V
Al mg/l
N
A
T
U
R
A
L
L
E
V
E
L
- (0.06) 0.5
L
E
V
E
L
S
A
B
O
V
E
IV
As mg/l 0.05 0.4 (0.05) 0.1
Ba mg/l 1 - -
Cd mg/l 0.01 0.01* (0.001) 0.01
Cr (IV) mg/l 0.05 1.4 (0.05) 0.1
Cr (III) mg/l - 2.5 -
Cu mg/l 0.02 - 0.2
Hardness mg/l 250 - -
Ca mg/l - - -
Mg mg/l - - -
Na mg/l - - 3 SAR
K mg/l - - -
Fe mg/l 1 1 1 (leaf) 5 (others)
Pb mg/l 0.05 0.02* (0.01) 5
Mn mg/l 0.1 0.1 0.2
Hg mg/l 0.001 0.004(0.0001) 0.002
Ni mg/l 0.05 0.9* 0.2
Se mg/l 0.01 0.25 (0.04) 0.02
Ag mg/l 0.05 0.0002 -
Sn mg/l - 0.004 -
U mg/l - - -
Zn mg/l 5 0.4* 2
B mg/l 1 (3.4) 0.8
Cl mg/l 200 - 80
Cl2 mg/l - (0.02) -
CN mg/l 0.02 0.06 (0.02) -
F mg/l 1.5 10 1
NO2 mg/l 0.4 0.4 (0.03) -
NO3 mg/l 7 - 5
P mg/l 0.2 0.1 -
Silica mg/l 50 - -
SO4 mg/l 250 - -
S mg/l 0.05 (0.001) -
CO2 mg/l - - -
Gross- Bq/l 0.1 - -
Gross- Bq/l 1 - -
Ra-226 Bq/l <0.1 - -
Sr-90 Bq/l <1 - -
ENVIRONMENTAL SCOPING INFORMATION (ESI)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF HEALTHCARE
WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT RAMBAI, FASA 4C,
MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd App 1-4
CK/EV803/8026/18 ESI Revision No.: 0 Revision Date: July 2018
Classes
Parameters Unit I IIA / IIB III@ IV V
CCE g/l N
A
T
L
E
V
O
R
A
B
S
E
N
T
500 - - -
MBAS/BAS g/l 500 5000 (200) - -
O & G (Mineral) g/l 40;N N - -
O & G (Emulsified Edible)
g/l 7000;N N - -
PCB g/l 0.1 6 (0.05) - -
Phenol g/l 10 - - -
Aldrin / Dieldrin g/l 0.02 0.2 (0.01) - -
BHC g/l 2 9 (0.1) - -
Chlordane g/l 0.08 2 (0.02) - -
t-DDT g/l 0.1 1 (0.01) - -
Endosulfan g/l 10 - - -
Heptachlor / Epoxide
g/l 0.05 0.9 (0.06) - -
Lindane g/l 2 3 (0.4) - -
2,4-D g/l 70 450 - -
2,4,5-T g/l 10 160 - -
2,4,5-TP g/l 4 850 - -
Paraquat g/l 10 1800 - -
Notes:
* = At hardness 50 mg/l CaCO3
# = Maximum (un-bracketed) and 24-hr average (bracketed) concentrations
N = Free from visible film sheen, discolouration and deposits
CLASS USES
I represent water body of excellent quality. Standards are set for the conservation of natural environment in its undisturbed state. Water bodies such as those in the national park areas, fountainheads, and in high land and undisturbed areas come under this category where strictly no discharge of any kind is permitted. Water bodies in this category meet the most stringent requirements for human health and aquatic life protection.
IIA/IIB represents water bodies of good quality. Most existing raw water supply sources come under this category. In practice, no body contact activity is allowed in this water for prevention of probable human pathogens. There is a need to introduce another class for water bodies not used for water supply but of similar quality which may be referred to as Class IIB. The determination of Class IIB standard is based on criteria for recreational use and protection of sensitive aquatic species.
III is defined with the primary objective of protecting common and moderately tolerant aquatic species of economic value. Water under this classification may be used for water supply with extensive / advance treatment. This class of water is also defined to suit livestock drinking needs.
IV defines water quality required for major agricultural irrigation activities which may not cover minor applications to sensitive crops.
V represents other waters which do not meet any of the above uses.
ENVIRONMENTAL SCOPING INFORMATION (ESI)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF HEALTHCARE
WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT RAMBAI, FASA 4C,
MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd App 2-1
CK/EV803/8026/18 ESI Revision No.: 0 Revision Date: July 2018
APPENDIX 2
MALAYSIA AMBIENT AIR QUALITY STANDARD
(MAAQS) AND ARIZONA AMBIENT AIR QUALITY
STANDARD (AAAQS)
ENVIRONMENTAL SCOPING INFORMATION (ESI)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF HEALTHCARE
WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT RAMBAI, FASA 4C,
MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd App 2-2
CK/EV803/8026/18 ESI Revision No.: 0 Revision Date: July 2018
AMBIENT AIR QUALITY STANDARD CONCENTRATION LIMIT
Table 1: Concentration Limit for Suspended Particulate 10 micrometre or less (PM10)
AVERAGE TIME UNIT EXISTING
GUIDELINES IT – 1 (2015) IT – 2 (2018) STANDARD
(2020)
1 YEAR μg/m3 50 50 45 40
24 HOURS μg/m3 150 150 120 100
Table 2: Concentration Limit for Suspended Particulate 2.5 micrometre or less (PM2.5)
AVERAGE TIME UNIT EXISTING
GUIDELINES IT – 1 (2015) IT – 2 (2018) STANDARD
(2020)
1 YEAR μg/m3 - 35 25 15
24 HOURS μg/m3 - 75 50 35
Table 3: Concentration Limit for Sulphur dioxide (SO2)
AVERAGE TIME UNIT EXISTING
GUIDELINES IT – 1 (2015) IT – 2 (2018) STANDARD
(2020)
1 HOUR μg/m3 350 350 300 250
24 HOURS μg/m3 105 105 90 80
Table 4: Concentration Limit for Nitrogen dioxide (NO2)
AVERAGE TIME UNIT EXISTING
GUIDELINES IT – 1 (2015) IT – 2 (2018) STANDARD
(2020)
1 HOUR μg/m3 320 320 300 280
24 HOURS μg/m3 75 75 75 70
Table 5: Concentration Limit for Ground Level Ozone (O3)
AVERAGE TIME UNIT EXISTING
GUIDELINES IT – 1 (2015) IT – 2 (2018) STANDARD
(2020)
1 HOUR μg/m3 200 200 200 180
8 HOURS μg/m3 120 120 120 100
Table 6: Concentration Limit for Carbon monoxide (CO)
AVERAGE TIME UNIT EXISTING
GUIDELINES IT – 1 (2015) IT – 2 (2018) STANDARD
(2020)
1 HOUR mg/m3 35 35 35 30
8 HOURS mg/m3 10 10 10 10
Note : IT – Interim Target
Source: Translated from “Had Kepekatan Standard Kualiti Udara Ambien” issued by Department of Environment Malaysia
ENVIRONMENTAL SCOPING INFORMATION (ESI)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF HEALTHCARE
WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT RAMBAI, FASA 4C,
MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd App 3-1
CK/EV803/8026/18 ESI Revision No.: 0 Revision Date: July 2018
APPENDIX 3
PLANNING GUIDELINES FOR ENVIRONMENTAL NOISE
LIMITS AND CONTROL
ENVIRONMENTAL SCOPING INFORMATION (ESI)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF HEALTHCARE
WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT RAMBAI, FASA 4C,
MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd App 3-2
CK/EV803/8026/18 ESI Revision No.: 0 Revision Date: July 2018
EXTRACTED FROM THE PLANNING GUIDELINES FOR ENVIRONMENTAL NOISE LIMITS AND CONTROL 2007, PUBLISHED BY THE DOE
ENVIRONMENTAL SCOPING INFORMATION (ESI)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF HEALTHCARE
WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT RAMBAI, FASA 4C,
MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd App 3-3
CK/EV803/8026/18 ESI Revision No.: 0 Revision Date: July 2018
ENVIRONMENTAL SCOPING INFORMATION (ESI)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF HEALTHCARE
WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT RAMBAI, FASA 4C,
MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd App 3-4
CK/EV803/8026/18 ESI Revision No.: 0 Revision Date: July 2018
ENVIRONMENTAL SCOPING INFORMATION (ESI)
ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED NEW INSTALLATION OF THERMAL TREATMENT FACILITY FOR CENTRE OF HEALTHCARE
WASTE TREATMENT PLANT FOR MEDIVEST SDN BHD AT LOT 24, 25, 32 & 33, JALAN PBR 37, KAWASAN PERINDUSTRIAN BUKIT RAMBAI, FASA 4C,
MUKIM TANJUNG MINYAK, MELAKA
Chemsain Konsultant Sdn Bhd App 3-5
CK/EV803/8026/18 ESI Revision No.: 0 Revision Date: July 2018