+ All Categories
Home > Documents > CONSTRUCTION METHOD STATEMENT FOR DEMOLITION AND NEW BUILD OF 13 NO. HOUSES AT LIME GROVE SCHOOL...

CONSTRUCTION METHOD STATEMENT FOR DEMOLITION AND NEW BUILD OF 13 NO. HOUSES AT LIME GROVE SCHOOL...

Date post: 27-Nov-2023
Category:
Upload: independent
View: 0 times
Download: 0 times
Share this document with a friend
12
CONSTRUCTION METHOD STATEMENT FOR DEMOLITION AND NEW BUILD OF 13 NO. HOUSES AT LIME GROVE SCHOOL SITE BATH
Transcript

CONSTRUCTION METHOD STATEMENT

FOR DEMOLITION AND NEW BUILD OF

13 NO. HOUSES AT

LIME GROVE SCHOOL SITE

BATH

Lime Grove School, Bath

2

Lime Grove School, Bath

3

Construction Method Statement

INTRODUCTION

The site is currently a disused school with various derelict boarded up buildings on it.

Initial demolition of the school building will need to take place and once planning consents are in place a demolition contractor has been appointed. The demolition contractor will also be the Principal Contractor while demotion works are carried out.

In the interests of being environmentally friendly, all existing concrete and brick rubble will be crushed and reused on site.

SITE SET UP

The extent of the site compound will be as shown in Appendix 1

In the interest of protection for the general public, it will be our intention to have full protective hoarding and screens around the site.

ACCESS AND EGRESS

The existing gate to the school will be kept in place for access and egress purposes.

With regard to members of the public using the adjacent footpath to the south boundary a banksman will be in place to control traffic accessing and leaving the site

TREE PROTECTION

All tree protection measures will be in place to approved drawings prior to any operations taking on site.

Lime Grove School, Bath

4

Construction Method Statement

DELIVERIES

It is our intention to bring all deliveries along the A36 Pulteney Road turning into Pulteney Grove then left into Lime Grove Gardens avoiding Lime Grove due to the narrowness of the road, as shown in Appendix 2.

All deliveries to site will take place on rigid axle lorries only due to residents parking on the road in Lime Grove Gardens. It is also our intention to avoid deliveries during rush hour to alleviate congestion for the local residents.

CONTRACTORS PARKING

All contractors parking will be on-site or in the pay and display car park outside of Bath Cricket Club.

Absolutely no parking will be allowed by sub-contactors on any the adjacent roads.

PILING

None

Lime Grove School, Bath

5

Construction Method Statement

GROUNDWORKS

Groundworks will be carried out by supply and fix contractors, to be appointed, once planning for the development has been received.

The above conditions will be set out in the Terms of Engagement.

It is also envisaged that while the groundworkers are on site the groundworker will be the Principal Contractor and Bloor Homes will be the client.

Once development has reached oversite stage and on-site road and footpaths completed, Bloor Homes will take over as Principal Contractor and our own employed manager will be on site on a permanent basis.

All contractors and sub-contractors will be expected to have passed Bloor Homes’ standard competency checks and where necessary references will be taken and checked.

COMMUNICATION AND LIAISING

Throughout the project Bloor Homes and all their staff and contractors will maintain a high level of liaison and communication with all relevant parties to ensure the programme can be carried out with least amount of disruption to our neighbours, their property and the general public.

The proposed site manager for this development will be Mr John Mumford who has worked in Bath previously on similar projects.

WHEEL WASHING

If required, a wheel wash may be put in place at the entrance to the site.

Lime Grove School, Bath

6

Construction Method Statement

WASTE MANAGEMENT

A full waste management plan will be put in place once planning is granted.

DISC CUTTING

All contractors and sub-contractors are made fully aware of their responsibilities and where necessary, dampening down measures will be put in place.

PROPOSED ORDER OF BUILD

Plots 1, 2, 5, 12, 13, 11, 10, 9, 8, 7, 6, 4 and 3.

ESTIMATE OF CONTRACTORS ON SITE

We estimate no more than 25 contractors on site any one time including:

4 Groundworkers

1 Forklift driver

1 Labourer

3 Carpenters

2 Plumbers

8 Bricklayers

2 Electricians

Lime Grove School, Bath

7

Construction Method Statement

PROGRAMME OF WORKS

It is estimated that the whole project would take no longer than 14 months.

HOURS OF WORKING

Hours of working will be:

8am to 5pm Monday to Friday

8am to 1pm Saturday

No Sunday or Bank Holiday work.

The site will be a Considerate Contractor Site

Construction Director – Mr John Gibbons

Contracts Manager – Mr Phil Lloyd

Head Office Telephone Number – 01793 835600

Lime Grove School, Bath

8

Appendix 1

1

2

3

4

6

P6

P7

P9

P8

EXISTING

RETAINING

WALL

EXISTING

RETAINING

WALL

P5

P10

P11

P12

P13

P11

P10

P12

P12

P13

P13

EXISTING TREES-

TO BE RETAINED

TYPE D

5

P3 P4 P2 P1

Legend:

Lorry Turning Area

Sub-Contract Parking

Compound and Welfare Storage

Turning Area with Banksman

Pedestrian Access

Traffic Route

Cross Over Point

LIME GROVE SCHOOL, BATH

BLOOR HOMES LIMITED

3 STANTON COURT, SOUTH MARSTON PARK

SWINDON, SN3 4YH

TELEPHONE 01793 835600 FACSIMILE 01793 835601

THIS DRAWING AND THE BUILDING WORKS DEPICTED ARE THE COPYRIGHT OF

BLOOR HOMES LIMITED AND MAY NOT BE REPRODUCED OR AMENDED EXCEPT BY

WRITTEN PERMISSION. NO LIABILITY WILL BE ACCEPTED FOR AMENDMENTS MADE

BY OTHER PERSONS

DO NOT SCALE THIS DRAWING, USE FIGURED DIMENSIONS ONLY, IF IN DOUBT ASK.

R

Drawing No.

Scale.

Date.

Drawn.

Checked.

Job.

Title.

Former Lime Grove School

Bath

(13 units)

Traffic Management Plan

1:500@A2

19.01.12

TDO

BHS91.TM01

ACCOMMODATION SCHEDULE

TYPE A (1622 Sq Ft) 4

TYPE B (1960 Sq Ft) 2

TYPE C (1490 Sq Ft) 5

TYPE D (754 Sq Ft) 2

TOTAL 13

Notes:

1. Plot 5 will be used for an office, canteen and toilets.

2. Below plot 5 the garages of plots 1, 2 , 3 and 4 will

be used as storage.

3. Sub-contract parking to the rear garden of plot 3 and

in front of garden 1-4.

4. Turning area for lorries in front of gardens 6, 7 and 8.

5. Banksman with be in attendance at all time to direct

lorry movement

Lime Grove School, Bath

9

Appendix 2


Recommended