Date post: | 09-Apr-2023 |
Category: |
Documents |
Upload: | khangminh22 |
View: | 0 times |
Download: | 0 times |
Contractor Coaching and Mentorship ConceptDevelopmentandOverview
MkC@ILO10-Sept-2015
Cont
ract
or C
oach
ing
And
Men
tors
hip
Contents 1
Contractor Mentorship1 ConceptDevelopmentandProgrammeoverview
1ThesymbolistheJapanesecharacterforKaizen–whichdescribeshowweintendtodevelopthe small scale contractors – constant change. Kaizen is the practice of continuousimprovement. Today Kaizen is recognized worldwide as an important pillar of anorganization'slong-termcompetitivestrategy.
Contents 2
1. Contents 1. Contents...............................................................................................2
2. Background..........................................................................................6
3. Rationaleformentorshipandproposednewapproach......................7
4. MentorshipObjectives.........................................................................9
5. TargetAudience.................................................................................10
5.1 AudiencewithintheCompanies........................................................10
5.2 Otherstakeholders–outsidecompany.............................................10
6. InstructionPlan..................................................................................11
6.1 Background........................................................................................11
6.2 MainActivities,CoachingandMentorship........................................12
7. RolesofPersonsinthenewmentorshipapproach...........................17
7.1 Background........................................................................................17
7.2 RoleofCompanyDirector..................................................................17
7.3 RoleofContractor’sEngineer............................................................17
7.4 RoleofContractorSupervisors..........................................................18
7.5 RoleofMentor...................................................................................18
8. WorkMethod-businessmentorship/problemresolution..............20
9. BusinessandTechnicalCoaching–anoverview...............................22
9.1 TechnicalCoaching............................................................................22
9.2 Objectives–TechnicalCoaching........................................................24
9.3 Expectedoutcomes–TechnicalCoaching.........................................24
9.4 BusinessCoaching..............................................................................25
9.5 Objectives–BusinessCoaching.........................................................26
9.6 Expectedoutcomes–BusinessCoaching..........................................26
10. TechnicalCoaching............................................................................29
10.1 Mobilisation&SiteSetup..................................................................29
ContractsSigned................................................................................29
SiteHandover....................................................................................29
SiteCamp...........................................................................................30
Buildings/FacilitiesatCampSite.....................................................30
ToolsstorageatCampSite...............................................................31
Equipment.........................................................................................31
10.2 LabourRecruitment...........................................................................32
SocialSafeguardsandrecruitmentprocess.....................................32
Contents 3
LabourManagementSystems..........................................................33
PaymentSystems..............................................................................34
ContractingFramework....................................................................35
10.3 Works.................................................................................................35
Planning,SpecificsforTasks,QualityControl,Measurement.........35
10.4 AdHocAdjustmentstoResourcesandSchedule..............................37
BalancingResources(Finance,Staff,Equipment)............................37
AdjustmentofWorkProgramme.....................................................38
FlexibilityinSchedule.......................................................................39
Payments.................................................................................................................39
11. ContractorMentorship......................................................................42
11.1 BackgroundandOverview.................................................................42
12. EquipmentManagement(sample)....................................................44
12.1 Objectives..........................................................................................44
12.2 TargetAudience.................................................................................44
12.3 Providers............................................................................................44
12.4 Influenced..........................................................................................44
12.5 Objectivessetby................................................................................44
12.6 Pre-requisites.....................................................................................44
12.7 Trainingmaterial................................................................................45
12.8 Referencematerial............................................................................45
12.9 MeasurementofEffectivenessof“module”.....................................45
13. CompanyTechnicalStaffManagement(sample)..............................46
13.1 Objectives..........................................................................................46
13.2 TargetAudience.................................................................................46
13.3 Providers............................................................................................46
13.4 Influenced..........................................................................................46
13.5 Objectivessetby................................................................................46
13.6 Pre-requisites.....................................................................................47
13.7 Trainingmaterial................................................................................47
13.8 Referencematerial............................................................................47
13.9 MeasurementofEffectivenessof“module”.....................................47
14. CompanyHealthandSafetyStandards.............................................48
14.1 Objectives..........................................................................................48
14.2 TargetAudience.................................................................................48
14.3 Providers............................................................................................48
Contents 4
14.4 Influenced..........................................................................................48
14.5 Objectivessetby................................................................................48
14.6 Pre-requisites.....................................................................................48
14.7 Trainingmaterial................................................................................49
14.8 Referencematerial............................................................................49
14.9 MeasurementofEffectivenessof“module”.....................................49
15. CompanyFuture................................................................................50
15.1 Objectives..........................................................................................50
15.2 TargetAudience.................................................................................50
15.3 Providers............................................................................................50
15.4 Influenced..........................................................................................50
15.5 Objectivessetby................................................................................50
15.6 Pre-requisites.....................................................................................50
15.7 Trainingmaterial................................................................................50
15.8 Referencematerial............................................................................50
15.9 MeasurementofEffectivenessof“module”.....................................51
16. SolutionSheet....................................................................................53
17. Effecting Change “Implementing the Project” (Mentor ANDContractor) 56
17.1 ProjectSetuporInitiation..................................................................56
17.2 ActionsatProjectSetup.....................................................................57
17.3 Deliverables(stages)..........................................................................57
17.4 RegularMonitoring,FinalEvaluationandTerminatingProjects.......58
18. EstimatedResourceRequirements....................................................60
18.1 Background........................................................................................60
18.2 ResourceEstimates............................................................................60
18.3 EstimatedPersondays.......................................................................61
Background 6
2. Background TheR4Dprogrammehasprovidesformalclassroomandpracticalsitebasedtrainingto contracting companies prior to engagement on rural road maintenance and/orrehabilitationcontracts.TheformaltrainingisprovidedincollaborationwiththeILOERAprogramme.
Inadditiontotheformaltrainingprogrammeduringtheexecutionoftheworks,theR4D regional engineers have provide day-to-day guidance and support to both thecompanydirectorsand technical staff to facilitate completionof theworkson site.Thissupport, thoughvaluable,hasbeenprovidedonanad-hocbasisrespondingtotheimmediaterequirementsofthetaskathand.
Further, provision of this support carries a risk of conflict of interest. The R4Dregional engineers primarily act as the client’s representative on site, managingworks to ensure compliance with standards and contract. Provision of advice tocontractors and contractor staff thus places an onerous burden on the R4Dengineers. It is noted that the R4D engineers are able to provide support to thecontractorsduetoeither;
1. Technicalweaknessofthecontractorcompanies2. Respect the contractorshave forR4Dengineers– i.e. theyareviewedasa
neutralcontractadministrator3. Thecontractorsoftensimplyneedanyhelptheycanget.
Rationaleformentorshipandproposednewapproach 7
3. Rationale for mentorship and proposed new approach Basedontheobjectivesof theR4Dprogramme–whichcanbesuccinctlystatedasdevelopment of a functional rural road sector in Timor Leste, the programme hasidentified a need to support the development of contractors working in the ruralroadsector.
Themainproblemsobservedonsite(butnotlimitedto)include;
i. Sub-standardphysicaloutputleadingtoabortiveworkii. Poorstaffretentioniii. Cashflowmanagementissuesiv. Non-optimal(poor)equipmentownershiparrangementsv. Poorworkschedulingvi. Inappropriatematerialhandlingvii. Poormaterialprocurement
Adhocsitesupportwillprimarilyhelpalleviateproblemssuchasi)above.However,theotherproblemsareclearlycomplexproblemsprobablyamanifestationofotherproblems including limitedmanagementcapability,poorcompanysystemsand lackofmanagementvision.Itisquitepossiblethatbyaddressingonlyitemi)above(e.g.ad-hoc support provided by R4D regional engineers using the current supportmodel), the financial position of the company may get worse – because thetighteningofworkmethodsandprocessestogethighqualityoutputfromacompanygearedtogeneratepoorworkplacesanadditionalfinancialburdenonthecompany.Thus while the client gets a better product, the company further reduces itsprofitabilitytopleasetheclientfornoadditionalfinancialbenefittothecompany.Asmentioned above, sub-standardwork is often a consequenceof deeper underlyingmaladieswithinacompanyorcompanysystemsasopposedtoasimpleproblemofsupervisionorskills.
It isalsoenvisaged thatwith thedevelopmentofa functional rural roadsector,anincreasingamountofthefunctionsundertakenbytheR4DregionalengineerswillbetakenoverbytheDRBFCstaff.Itisdifficulttoenvisageasituationwheregovernmentemployees who are charged with managing contractors also have a role to guidecontractorsintheexecutionofworks.Thisrole(mentorship),isthusoneoftherolesthatcannotbe“transferred”totheDRBFCfromtheR4Dinthecurrentsetup.
Itmaybethatinthelongtermthereisnoneedforcontractormentorshipbecausethere may be a self-sustaining number of competent rural roads contractors withcompetentstaffwhoareabletopassontheirknowledgetonewentrants–eitherviarecruitment or observation. It is also possible that the role ofmentorship is takenover by the private sector or a training institute as has happened in other place(institutionofengineers,contractorsassociationsorprivatesectortrainingprovidersetc.).
Acomprehensivementorshipprogrammehasbeendeveloped–thisisarrivedatbyworking backwards through the “system.” A successful contracting company is notmerelyacompanythatisabletoexecuteworkstotheclients’satisfactionbutratheracompanythatisabletomeetbothitsobjectivesaswellastheclients’objectivesin
Rationaleformentorshipandproposednewapproach 8
the longterm. Ironically– intheshorttermasuccessfulcompanymaybeonethatonlymeets its’ objectives (usually profit and growth). Thementorship programmetakes congisance of this fact and is heavily geared towards creating effectivecompaniesasaprimaryobjectiveasopposedtocreatingcompanies thataresolelyclientfocused.Invariably,foracompanytosurvive,itmusthaveclientsandsatisfiedclients, and thus there is also a focus on ability to deliver high quality work. Thetechnicaltrainingduringthementorship(supporttodeliveringhighqualitywork),isheavilybiasedtowardsoptimizingthedeliveryprocessandjustgettingtheprocessescorrectratherthansimplyprovidingthebesti.e.theyareaimedatsatisficingratherthanmaximizing. The underlyingmotive here is there is a contract documentwithspecificationsandoncethespecificationsaremet,thecontractorhasnothingtogainbygrosslyexceedingthestandards–excepttoloosepotentialprofit.
Further, the new approach distinguishes between coaching and mentoring.Coachinginthiscontextreferstoatrainingwheretheparticipantsareleadthroughapredefinedcurriculathatshouldstrengthentheircapabilitiesinareasthathavebeendefined.Mentorship on the other hand refers to a structured approach to solvingspecificproblemsthatarisewithinacompany.
Thus coaching canbe seen as an extensionof the classroom training in a practicalcontext. Coaching if a follow-up of the material taught in the ERA RehabilitationContractor Training Course, while mentorship is primarily aimed at helpingcontractors resolve specific problems or overcome hurdles to growing theircompanies.
MentorshipObjectives 9
4. Mentorship Objectives Mentorshipisintendedtoformalizethemateriallearntinthepre-contractclassroomtraining,usingaformalizedcurriculaandmethodologythathasbeentailoredtotherequirementsofeachcontractor.Thereareanumberofobjectivestothementorshipprogramme.Theseare;
1. SupportnascentcontractingcompaniesworkingintheRuralRoadsectorfortheDRBFCtodevelop, function independently,becommerciallysustainablefirms2. It is envisaged that the development of the contracting companiesshallaimtoimprovethefollowingareas:
a. Coretechnicalcompetencyofthecompanystaffb. Businessskillsofthecompanydirectorsandmanagingstaff
2. Improvethequalityofruralroadsinthecountrybyminimizingsub-standardwork.
3. Improve contractor profitability (and hence commercial viability) byminimizingabortivework.
4. Support the growth of small construction companies – by creating anenvironment within the companies that maximizes their chance of profitmakingandhencethesustainabilityofthecompanies.
5. Developasingleconsistentmentorshipregimethatisappliedthroughouttheprogramme to replace the ad-hoc support currently provided and thusensuring high quality and uniform coaching which in turn should lead toimprovedworksontheR4Dprogamme.
6. To support the project objectives – the development of a functional ruralroad contracting sector (a functional private sector is needed tomeet thisobjective)
7. InthelongtermminimizethecostofruralroadconstructionbyensuringthatthecontractorsmakeprofitsANDareefficientintheiroperationsi.e.thereisacompetitiveandeffectiveconstructionsector.
2Note:thismaynotalwaysresultinbehaviorconducivetothedesiresoftheclient
ThePRIMARYobjectiveof thementorship is todevelopCommercially Viable construction companies – thatwillturnoveraPROFITSandGROW.
This is ultimately in the interest of the Directorate ofRoads Bridges and Flood Control because a robust,reliable and vibrant private sector is needed to deliverthe infrastructure the Directorate is charged withdelivering.
TargetAudience 10
5. Target Audience
5.1 Audience within the Companies
Targetaudienceforthementorshipprogrammeare:
• Companydirectors• Seniorcompanytechnicalstaff(engineers)• Sitetechnicalstaff(technicians)
Thementorshiphasbeenorganizedtoensurethatallpersonswithresponsibilityinacompanyare“trainedormentored”intheappropriateareaswhichwillachievethedesiredculturalchangewithinthecompany.
Essentially the mentorship is designed as a change process within the companiesaccompanied by the development of company systems that will ensure long termintegration of the changesmade. Layered on top of the development of companysystems, there isaneedtodevelopthe technicalcapacityof thestaffwhoactuallyimplementtheworktoensuretheyarecompetentANDareawareofthecommercialimplicationsoftheiractions.
Thementorshipisthusessentiallydevelopmentofskillsattheoperationallevelanddevelopmentofmanagementproceduresatthehigherlevelwithinthecompany.
It is envisaged that some training will also be required for the R4D staff and theDistrictstaff.ThetrainingforR4Dstaffwillbeprovidedtoenablethemto
• provideday-to-daysupporttothecontractors• providefeedbackoncontractorperformance• make suggestions on areaswhere the contractors need additional support
andtraining
5.2 Other stakeholders – outside company
FortheDRBFCDistrictstaff,itisexpectedthatsupport/engagementwillprimarilybeinformation sharing. This is aimed to sensitize the DRBFC staff on the hurdlescontractors face, make them aware of the mentorship programme. It may benecessary to hold training courses to improve the supervision capability of theministrybythisisaseparateactivitytotheproposedmentorship.
InstructionPlan 11
6. Instruction Plan
6.1 Background
Thesectionprovidesanoverviewof theproposedworkshopschedule. It shouldberegardednotasacurriculabutasoverviewofthemaincomponentsofaprogamme.It also lists who the primary target audience of each module shall be. It isacknowledged thatwhilst ideallymentorship shouldbea responsive–withactionsprimarilyinitiatedbythecontractor,itisalsorecognizedthatinitially,thecontractormaynotbeableto3initiatementorshipdialogue.
However, beyond the initial phase where the mentor may take leadership inprocesses, it iscriticalthatforallchanges/training/coachingactivities,thecompanymanagement are involved. Even for simple site activities, the underlying principleshould be to coach/train the supervisors only if the management is involved,understands themotiveof the training input andwillmonitor andensure that thenewproceduresarecarriedoutwhenevernecessaryi.e.embeddedinthecompanyculture.
Technical Coaching
Business Coaching
Mentorship
Type
of S
uppo
rt
Time (years) [or dev contractor progression]
1. figureaboveshowsthelevelandtypeofsupportrequiredbythecontractorsovertime2. thelevelofsupportisrepresentedbythewidthofthearrow3. initially,thecontractorswouldprimarilyrequiretechnicalsupporttodeliveranacceptableproducteconomically
(thisstartsatthemobilisationstage)4. thistechnicalsupportispurelycoaching–theproviderscanfollowasetcurricula(withallowancefordifferent
levelsofskills5. soonafterworksbegin,businesscoachingisrequired–thisisalsobasicbusinesscoachingandcanfollowaset
curriculawithallowancefordifferentskillsrequirements6. oncethecompanyhasreachedacertainlevelofbothbasic*technicalandbusinessskillsmentorshipcanbegin6. initiallyallthreeruntogether,butitisexpectedthatthedemandforbothtechnicalandbusinesscoachingdrops
(ascompanybecomeproficientinbasicskills),whilethedemandformentorshipshouldincreaseovertime.Also,thementorshipapproachwillbeusedtoresolvebothtechnicalandbusinessproblemsascompanymatures
Figure6-1:Supportrequirementascontractorcapacityevolves
3Eitherduetotechnicalorgeneralcompetencelimitations(unawareofpossibleavenuesandavailablesupportmechanismstoimplementchangewithintheiroperations).
InstructionPlan 12
Figure6.1showstheexpected inputprofile tosupporta typicalcontractorworkingon rural roads. The standard activities (i.e. the basic knowledge that a reasonablecontractingcompanymustprocess)isdeliveredvia“coaching.”Thisbasicknowledgehasbeendivided into two– technical knowledge to complete theassignment to adecentlevelANDbusinessknowledgerequiredtorunacompanyandbreakeven.
It is assumed that management knowledge is encapsulated within the businessknowledge. Hence management coaching is subsumed in business coaching. Formentorship all solutions (technical and business) are developed within a robustmanagement (companymanagement) framework. The width of the arrows reflecttheintensityoftheinput,whilethelocationontheX-axiswouldgiveanindicationofthedurationandthestart-endpointsofthesupport.
Further, the Coaching can be provided using experience technical staff who areconversant with all the workings of a typical labour based site. The ERA projectalreadyhasaCoachingGuidelinewhichbroadlycoversthemainmaterialthatwouldbe required in the coaching programme. It is noted that the coaching programmeenvisaged in this document would require strengthening and expansion of thecurrent ERA coaching guidelines. It is also noted that the current guidelines are asufficient starting point and can be used whilst being upgraded. Further, theupgradingoftheguidelineswouldprobablyrequireandbenefitfrominputfroma1styearcoachingexercise.
TheMentorshipwouldrequireahigherlevelofinput.Itwouldrequireapersonwhois able to mentor the contractors based on a deep understanding of contracting,privatesectoroperations,profitmaximization,riskmonitoring,workinginuncertainenvironments, growing companies, monitoring costs, optimizing costs and alsogrowingcompanies.Simplystated–thementorwouldideallybesomeonewhohasworkedatthecoalfaceintheconstructionindustry.
6.2 Main Activities, Coaching and Mentorship
Theproposedstructureofthecoachingandmentorshipisasfollows:
Induction: this is a session in Dili at the beginning of the contract where theprinciples and concept behind the provision of mentorship is explained to thecompanymanagement. During the session thementorship process is explained tothecontracts(andtheengineers),issuessuchasultimateresponsibility(remainswiththe contractor), buy-in into the proposed changes, access to the mentor etc. areexplainedtotheparticipants.
Theparticipantsinthementorshipinductionareboththedirectorandengineer.Therationalearethatthesetwocomprisethe“management”withinthecompanieswearedealingwith.Thedirectorastheownerandtheengineerasthehighesttechnicalpersonwithinthecompanyandwhowillsupportthedirectorindecisionmaking.
ItisproposedthattheinductionisdeliveredbyR4DstaffandERA–bothofwhowillprovidethementorshipsupport.
ItwouldbeusefultohavesomeR4Dengineerstoattendtheinduction.
InstructionPlan 13
Technicalcoaching:Thisistheinitialphaseatthebeginningofthementorshipwherethe contractors have first begun on a contract and some coaching (rather thanmentorship) is requiredtobringthecompanyoperationsandmanagementskills toan acceptable level. This will primarily involve coaching in works planning, basicrecord keeping on site, meeting basic standards on works etc. As this coaching issimpleandgeneric (i.e.applies toall companies), thementor (coach), can take theinitiative and develop a “curricula” to guide the contractors through the basicrequirementstooperateacompanyandthesitestaffthroughthebasicoperations.
Theparticipantsforthetechnicalcoachingareprimarilythecompanyengineersandsitesupervisors.Therationalisthattheyaretheonesinvolvedinthedailyoperationsof the company and need to understand the technical requirements and basicmanagementprocessesofacompany.Thetechnicalcoachingcanberegardedasanextensionof thebrief trainingonsitewhere theR4DandERAstaff strengthenandinstillitemstaughtduringthepre-contracttraining.
Dailyfollow-upontechnicalcoaching:self-explanatory,seeabove.
Business coaching: Soon after the start of the contract, the contractors will needsome basic business support. This is primarily related to the “normal” businessproceduresandprocesses required to runa typical labour-based road constructionsite. The elements taught will include the basic procedures and reinforcing thesubjectmatter taughtduring thepre-contract training. Thiswould includematerialsuchas staffmanagement,basic record keeping (muster roll, expenses, equipmentmonitoringetc).Therealreadyexistsagoodbodyofknowledge,referencematerialandexperienceinthisareaintheERAProject,asaresultofsupporttoERAtrainedcontractors.
Mentorship-Companyidentity:Thispartofthetrainingisinitiatedbythementors.This isacriticalpartof thenewapproachtomentorship. It isat thispoint that thecompany director with the support of the engineer do an audit of the type ofcompanytheycurrentlyhave(profilealonganumberofkeyitems),andthementoralsogets to know the company indetail. It forms thebasisofdecidewhat typeofcompanytheywanttheircompanytobe.
The rational is that this will provide both the contractor company management(directorandengineers)andopportunitytohaveadetailedlookattheoperationsofthe company and also prepare themselves for defining realistic targets during thementorship.Intheprocess,thementorwillalsogettodevelopanaccuratepictureofthecompanies.
Thesessionshouldideallytakeplaceafewweeksafterthebeginningofthecontract,tominimize the tendencyof companiesover-estimating their capacity (they shouldhaveonesomephysicalworkbeforethisstage).ThephysicalworkwillalsohelptheR4D engineers help the mentor develop a more accurate picture of the companybasedontheworksdonebeforethesession.
ThissessioncantakeplaceeitherclosetothesiteorinDili.Itisnotsuitabletoholdthesessiononsiteasitmaybeconducivetodiscussion.
InstructionPlan 14
Mentorship-DevelopmentofCompanyObjectives:Thisisasessionthattriggersthementorshipleadbythecompanydirector.Followingthediscussiononthecompanyidentity,thedirector(perhapstogetherwiththehelpofengineerifrequired)shoulddecidewhattypeofcompanytheywanttodevelop.Thementorcouldhelpthemsettypicalobjectives(minimizeexpenditure,growthecompany,improvestaffretention,movefromone-man-showmanshiptoarealcompanyetc.).
Theformulationofcompanyobjectivesearlyoninthementorshipwillhelpdecidethegeneral framework for which specific decisions are made in the future. This is thefundamentaldifferencesinpriorcoachingwiththeproposedapproach.Thiselementwillactuallydevelopcompaniesratherthanaddressspecificproblemsindependently.
The development of company objectives is expected to take a few sessions, andinitialsessionwheretheconceptofcompanyobjectivesaredecided.Theobjectivesshould also include the standard obligatory or legally required objectives such asdiscrimination, compliancewith H&S etc. Ideally this session should be a director-onlysessionbecauseastheownerofthefirm,thedirectorshouldsetthehigh-levelobjectivesforthefirm.
The objectives must be achievable i.e. should match the size, capacity andopportunitiesthecompanyhasratherthanbeawish-list.Thelistshouldbedrawnupbythedirectornotthementor,becausecommitmenttoachievingtheobjectiveswillprobablyonlybepossibleforthearduoustaskofchangemanagementifthedriverofchangeisthedirector.
Company Strategy: Following the development of company objectives, the nextphaseof thementorship is thedevelopmentof solutions todailyproblemsusingastrategic approach. Two types of Company Strategy will be developed. Thedevelopmentofstrategyfor;
1. longtermobjectives(proactive)and2. specificproblems(reactive)
Someofthecompanyobjectivescanbemetbylongtermpolicye.g.genderequality– develop systems that do not favour any specific gender at recruitment,managecompany in appropriate manner etc. Some company objectives will need specificaudits and then development of policy/procedures e.g. reduce equipment costswouldberesolvedbyanauditthatwillidentifycompanyspecificproblemsrelatedtoequipment costs, rank theseas to identify themostprofitable to “attack”,developsolutions,implementthesolutionsandmonitorprogress.
Daily Monitoring: One of the key functions of management is monitoring. Infacteffectivemanagement cannot take placewithoutmonitoring. There is thus a needfor developing effective monitoring systems (that meet the requirements of thecompany as opposed to reporting that meets the requirements of the client orreporting based on historical systems from force-account legacy), using the formsand inculcatinga cultureofmonitoringwithin thecompanies. The results from themonitoringwillalsoguidethementorisprovidingsupporttothecompany,checkingtheeffectivenessofmeasuresimplementedetc.
InstructionPlan 15
The main recipients of mentorship in the areas of monitoring are the companyengineersandsupervisors.Thecompanysupervisorswillgeneratetheprimarydatafromthemonitoringandimplementingcompanysystems.Thecompanyengineerasthefirstlineofmanagementwillassessandactontheresultsofthemonitoringandalsoprovidefeedbacktothecompanydirectoronaregularbasis.
It is assumed that there isnoneed for thedirector inawell-managedcompany toregularlyponderoverdetaileddailyperformance figuresexpectwhendealingwithspecificproblems.
TargetMonitoring:Onaregularbasis, theDirectorandEngineertogetherwiththementorifnecessaryshallmeettoreviewprogressonvariousfrontsfromacompanyperspective.When thesemeetings take place in the presence of thementor, theyshallprimarilybetoassessprogressoncompanyinitiativesortoidentifyareasthatrequireattention.
InstructionPlan 16
Table6-1:OverviewofCoachingandMentorshipActivities
Activity Target Location Resources Duration Type1 Induction Directors
EngineersDili ( atcontractaward)
ERA andR4D
HalfDay Instant
2 TechnicalCoaching
EngineersSupervisors
Site ERA andR4D
ContractDuration
Routine
3 Daily follow-up ontechnicalcoaching
SupervisorsEngineers
Site R4DRegionalEngineers
ContractDuration
Routine
4 BusinessCoaching DirectorsEngineersSupervisors
Site ERAR4DRegionalEngineers
ContractDuration
Routine
5 MentorshipCompanyIdentity
Directors Dili orSite
R4D andMentor
1hour? Instant
6 CompanyObjectives
Directors R4DDiliERAOthers
ContractDuration
Routine
7 Company Strategyformulation
Directors R4DDiliERA
ContractDuration
Routine
8 StrategyImplementation
DirectorsEngineersSupervisors
ERAR4DRegional
ContractDuration
Regular
9 DailyMonitoringSupport toCoaching
EngineersSupervisors
R4DRegional
ContractDuration
Regular
10 TargetMonitoring DirectorsEngineers
ERAR4DRegional
ContractDuration
Periodic
tba=convenientlocationtobeagreedbyallparties
RolesofPersonsinthenewmentorshipapproach 17
7. Roles of Persons in the new mentorship approach
7.1 Background
The mentorships is primarily driven by the company director, who first of allidentifies a specific problem, then together with the mentor’s help develops anunderstanding of the primary causes of the problem, before developing a solutionthatbothdealsfirstwiththeunderlyingcauseoftheproblemandthentheproblemitself. The solution is then communicated to the relevant company staff in thecontextofthecompanyobjectives(orpolicy).Themonitoringoftheeffectivenessofthechangeprocessisthentheresponsibilityofthecompanydirector.
7.2 Role of Company Director
Thechangestheresponsibilityforallthefollowingitemstothecompany(effectivelycompanydirector);
1. Identifychange2. Buy-inintotherequiredchange3. Designtherequiredchangesinthecompany4. Ensurethatstaffareinformedaboutthechanges5. Ensurethatstaffareprovidedwithsufficienttools,resourcesandincentive
toimplementthechanges6. Monitortheimplementationofthechanges
It is recognized that the companydirector are not able to effectively “initiate” theprocess(i.e.articulateproblems)andalsotofindoptimalsolutionstotheproblems.Inthisregard–thementorshipwillintheinitialstagesbeledbyR4D(andERAasthetrainingpartners)withincreasingresponsibilitytoguidethementorshipbeingledbythe contractor (Director) as the mentorship progresses. Thus in Table 6-1, allactivitieslistedwouldbeinitiatedbythementor.However,astheworksprogress,itis expected that the contractor will initiate technical coaching, company strategyformulation, daily monitoring, strategy implementation and monitoring WITH thehelpofthementor.
A further advantage of this approach is that companies will be able to “choose adevelopment trajectory” that is aligned to the desires of the company and thecapabilitiesofthecompany.
7.3 Role of Contractor’s Engineer
Theengineer isanemployeeof thecompany.ASsuchtheengineerprimarilyhasaroletoimplementcompanypolicyusingcompanysystems.However,acknowledgingthat most small contracting firms are run by directors with limited technical andcommercial knowledge it is necessary to utilize the knowledge of the engineer tosupport thedirectors.Theengineer thusservesadual role–somemanagement inadditiontothetechnicalmanagementandcontrolrole.
RolesofPersonsinthenewmentorshipapproach 18
Theprimaryroleoftheengineerisimplementationofcompanypolicyandstrategy.Itisimportantthatthecompanydirectorcommunicatesthesestrategiesandpoliciesto the engineer AND that he (company director) gets buy-in on the policies. Theengineer will have day-to-day responsibility in ensuring implementation of theactions developed by the mentor and director. HOWEVER, the engineer isresponsible to the director not the mentor and as such the mentor should workthroughthedirector.
Thementormayissueadvicedirectlytotheengineer,howevertheseshouldalsobemade known to the director and it is the director who will monitor theimplementation of the advice. It is expected that apart from roles where theengineer supports the director in business related decisions/discussions (as part ofmentorship)– theprimary contactbetween theengineerand thementor4 shallbeduringprovisionoftechnicalcoaching.
7.4 Role of Contractor Supervisors
The supervisors are the final link in the mentorship chain. They will often be theimplementers. The main contact between the supervisors and mentors/coach willprobablybeintheareaoftechnicalsupportandtechnicalcoaching.
Thesupervisorsliketheengineerswillultimatelyreporttothecompanydirector.Asimplementers they are expected to have. However, for a successful mentorshipprogrammeitisexpectedthatthesupervisorshallunderstandthebasictenetsofthecompany policy and hence the reason why changes are being made. It is theresponsibilityof theengineer (anddirector) toexplain these to the supervisor, buttheremaybeinstanceswherethementorhastohelpgetbuy-in.
7.5 Role of Mentor
Thementorshallprimarilyguide thecompanydirectoror thecompanyengineer inhis/herroleasarepresentativeofthecompanydirector.Sincementorshipprimarilyinvolves implementing long term cultural and operational changes in a company,these require participation at the highest level in the company i.e. at the directorlevel.Itisatthislevel(director)thatthementorshallinteractwiththecompany.
If it isnecessaryforthementorto interactwithother levelswithinthecompany, itshall onlybe as a representativeof thedirector– i.e. thementor shall be advisingonly based on agreement with the company director and to achieve a previouslyagreedcompanyobjective.
Itmaybenecessaryforthementortodelegatesomefunctionse.g.dailysupporttofieldstaffmaybedelegatedtotheprojectengineerorsomeofthesupportfunctionsmay require specialized input e.g. equipment management etc. In cases wherespecialized input is required or delegation of daily responsibility, thementor shallmaintain overall responsibility and shall brief andmonitor the person carrying outtheworkonbehalfofthementor.
4MentorherecouldmeR4Dengineer,ERArepresentativeorspecialistmentor
RolesofPersonsinthenewmentorshipapproach 19
Thementorshallonlymakechangestooperationsonceagreedwiththedirectorandthe intendedchangeshavebeenagreedwithdirector i.e. thementor isadriverofchangethatisdesiredbythedirector.
WorkMethod-businessmentorship/problemresolution 20
8. Work Method - business mentorship / problem resolution
Whenresolvingproblemswiththehelpof thementor, thesolutiontotheproblemhas tobedeveloped togetherwith thecompanymanagement (usuallydirectorbutmay include support from the engineer). The reasons for this approach have beenpreviouslyexplained.
The diagram below shows an overview of the approach to identifying, developing,implementingandmonitoringsolutionstoproblems.Thisapproachshouldget longlastingsolutionstocompanyproblemswithbuy-infrommanagement.
Company DirectorSupervisor(or Engineer)
IdentifyProblemArea
Setcompanyobjectivesintheproblem
area
Developsolutionsforproblems(systemic)
Communicatesolutions Implement Monitor
Company Director (with support of Mentor)
Explanationoftheprocessesandproceduresshownabove
1. MentorhelpsDirectoridentifyunderlyingcausesofproblemandhelpsdirectorformulatestrategicsolutiontoproblem2. Togetherwithmentor(andengineerattimes),directordevelopsfirstpolicyandthensolutionstoproblem3. DirectorcommunicatesboththePOLICYANDSOLUTIONtothetechnicalstaff4. TechnicalStaffimplementthesolutionstotheproblem–andadheretothesolutionsbecauseitisnowcompanypolicy5. TechnicalstaffreporttoDirectoronthesolutionsimplemented6. DirectormonitorstheimpactofthePOLICYandprocedures.
1 6
5
4
3
2
BusinessandTechnicalCoaching–anoverview 22
9. Business and Technical Coaching – an overview
9.1 Technical Coaching
Thefollowing isa listoftopicsexpectedtobecovered inthecoachingprogramme.However,ascoachingprovidedisspecifictoeachcompany,noteverycompanywillneed training in all the areas listed below. Further, some companies will haveworked on R4D contracts for longer than others or have better qualified staff etc.Additionally,uponembarkingonthecoaching,itisexpectedthattheprogrammewillreveal additional areas of “weaknesses” in the contracting companies that needcoaching.Thelistshouldbeseenasacomprehensivebutprobablynotcompletelist.
Furtherthedurationofthementorshipisexpectedtolastbeyondasinglecontract.Itwillprobablyrequireatleast3contractstoachievewhatonewouldconsiderafullyfunctional company that has functional policies, procedures and systems thatgenerallyleadtogoodroadsandprofitability.
The ILO ERA programme has developed an LBT Coaching Guideline and a set ofmanualswhichdoprovideacrediblestartingpointfor
TechnicalArea ImprovementTarget
1 Toolsandequipment(basic)Inc:
1. toolstouseonsite2. Efficiencyoftoolsforvariousoperations3. Toolsformonitoringworks(templatesetc)4. Measuringaids5. Innovativeuse,maintenanceoftools
Operations
2 Labourregulationsandstandards1. Coreprinciples2. Maximizingoutputandmotivation3. Proactivesafetymanagement
Compliance
3 Settingupandmanagingasitecamp1. Officespace2. Storage3. Equipment4. Security5. Facilities
Operations
4 Equipment1. Optimalselection2. Characteristics3. Management4. Optimisationofutilization5. Rental6. Operatortraining7. Operatormanagement
Operations
BusinessandTechnicalCoaching–anoverview 23
TechnicalArea ImprovementTarget
5 Technicalrefresher1. Planningworks2. General works optimization and site
management3. Settingout4. Clearing5. Formation6. Drainage7. Gravelling/AsphaltWorks/ConcreteWorks8. Quarryworks9. Materialoptimization10. Materialhandlingandmanagement11. Erosioncontrolstructure12. Environmentalissues
Operations
6 Technicalrefresher(materials)1. Gravel2. Aggregate3. Cement4. Bitumen5. Sand6. Steelrebar
Operations
7 Technicalrefresher(compositematerials)1. Concrete2. Asphalt3. (anyotherexpensivecompositematerial)
Operations
8 Technicalrefresher(standardsandcompliance)1. Understandingthetechnicalstandards2. Understanding how work will be measured –
both volume of work and standards of finalproduct
3. Awareness of common mistakes in processeswhichleadtofailedproducts
4. Being able to optimse processes withoutaffectingthestandardofthefinalproduct
5. Investment in instruments / construction aidsthatwill help contractor check standards at alllevels(camberboards,spiritlevel,DCPetc)
6. Developing quality control procedures in theprocesses to ensure that mistakes are quicklyidentified and rectified hence minimizingabortivework
Operations
9 Smallstructures1. Culverts2. Gabions3. Drifts4. VentedDrifts5. Retainingwalls
Operations
BusinessandTechnicalCoaching–anoverview 24
9.2 Objectives – Technical Coaching
AttheendofthedevelopmentoftheTechnicalSkillscomponentofthecoaching,thecompanywillbeableto:
• Independentlyundertakeallactivitiesrequiredinruralroadconstruction• Efficientlyutilizeresources(materialandlabour)inruralroadconstruction• Develop the technical competence of “freshly recruited technical staff” to
allowthemtocontributeeffectivelytocompanyeffortsonsite• Demonstrateimprovedprofitabilityresultingfrombettertechnicalskills• Demonstrate reduced abortive non-compliant work (unless deliberately
implemented)• Demonstrateanunderstandingoftheprocessinroadbuildingandshowthat
effort is beingmade tooptimiseoperations i.e. achieve required standardswithminimalcostbyprocessimprovement
9.3 Expected outcomes – Technical Coaching
AttheendoftheTechnicalCoaching,thecompanyshould:
• Buildroadsthatmeetthestandardsspecifiedinthecontract• Buildroadsinanefficientmanner(technicalprocess)• Haveworkmethodsthatareconsistentwithacompanythathavesufficient
technicalskillstomanagethework• Demonstrateanunderstandingofeachoftheprocessesinlabour-basedroad
buildingandbeabletoaddressproblemsinanappropriatemanner• Manageresources(labour,equipmentandfinances) inamannerconsistent
withacompanythatunderstandstheroadbuildingprocess
BusinessandTechnicalCoaching–anoverview 25
9.4 Business Coaching
The business coaching is primarily aimed at the company management i.e thedirector and in some cases the engineer as well. The list below is the minimumrequisite material that the company management need to be fully conversant inadditiontodevelopingspecificmentorshipsolutionswhichwillbeaddressed in theparallel
Areaofcoaching ImprovementTarget
1. Understandingcompanycosts1. Recordkeepingasaprerequisite2. Developingacultureofanalyzingcosts3. Understandingcompanycosts4. Conceptofresourceleveling5. Conceptofmaximizationofresourceutilization6. Understanding concept of value-for-money vs
cheapestandlinktoinefficiency7. Conceptofcashflow8. Cashflowmanagement9. Importanceofinvoicingontime10. Tailoring work rate to payment schedules and
clientresponsiveness11. Loansandloanmanagement12. Types of company costs (capital, recurrent,
outputrelatedcostsetc.)13. Managingcosts
Management
2. Contractsandunderstandingcontract1. Understandingthemeaningofacontract2. Understandingcontractorobligationsoncurrent
contract3. Understanding contractor rights on current
contract4. Awareness of source contract documents in
casesof“short-formofcontract”5. Assertingcontractorrightswherefavorable
Management
3. Companystrategy1. Understandingthevalueofastrategy2. Makingastrategyforthecompany3. Implementingthestrategy4. Monitoring progress in implementing the
strategy5. Communicating the company strategy to key
companystaff6. Getting buy-in from staff on the company
strategy7. Fine-tuningthecompanystrategyasnecessary
Management
BusinessandTechnicalCoaching–anoverview 26
Areaofcoaching ImprovementTarget
4. PersonnelManagement1. Identifycompanyhumanresourcerequirements2. Assessingexistinghumanresourcecapacity3. Matching human resource requirements to
companycapabilities4. Developingastaffpolicy5. Recruitingnewstaff6. Managingcompanystaff7. Developingcompanystaff8. Payingandrewardingcompanystaff9. Staffretention10. Maintainingrelationshipwithcompanyalumni11. Compliance with national labour laws, norms
etc
Management
5. Externalcompanyrelations1. Clientrelationsmanagement2. Communityrelationsmanagement
Management
9.5 Objectives – Business Coaching
AttheendoftheBusinessSkillsmentorship,thecompanywillbeableto:
• Develop a company-wide ethos that reflects good management in theplanning,organizing,leadingandcoordinatingacrossalllevels
• Demonstrate a deep understanding of the financial implications of eachactivityundertaken
• Demonstrate optimized operational systems (operational planning andorganization)thatmaximizethefinancialreturns
• Demonstrate ability by companymanagement to set company-wide goals,effectivelycommunicatethegoalsandfinallytoimplementthegoals
• Demonstrate ability of management to set up systems that will result incompanyachievingitsgoals
• Demonstrableabilityofthecompany(bothmanagementandtechnicalstaff)toworkinanorganizedwaywithinsystemstheyhavedevelopedtofacilitatetheiroperations
• Effectiveleadershipbythecompanymanagementandtechnicalstaff• Effective coordination of utilization of company resources to achieve the
companyobjectives
9.6 Expected outcomes – Business Coaching
AttheendoftheBusinessCoaching,thecompanyshould:
• Makeprofits(orunderstandwhytheyarenotmakingprofits,ifproblemsarebeyondtheircontrole.g.badbidpricesetc)
• Qualitysystemstocaptureandmanagecosts• Haveanunderstandingoftheoperationalcoststructure• Worktowardsoptimizingtheircoststructure
BusinessandTechnicalCoaching–anoverview 27
• Have a consistent and rational business ethos that pervades the upperechelonofthecompany
• Ageneralbehavioramongsnrstaffthatreflectsthebusinessethos
• Buildroadsthatareacceptedbytheclient• Clearlydefinedcompanyobjectiveswhichareknowntostaff• Companystrategiestheguidedecisionmaking• Ongoingprogrammestoachievelongtermcompanystrategies
AttheendoftheBusinessSkillsmentorship,thecompanydirectorsshould:
• havedefinedcompanyobjectivesthatarerealistandachievable• abilityregularlyarticulatecompanyobjectivesespeciallytoemployees• managecompanyinamannerconsistentwithcompanyobjectives• havedefinedindicatorsthatwillmonitorprogresstowardsobjectives• monitortheindicators• beabletoamendcompanypoliciesandprocedurestomatchtheobjectives
ofcompanyandcurrentrequirements
AttheendoftheMentorship(Technicalandbusinesswhererelevant),thecompanyengineershall;
• demonstrate an understanding of the commercial implications of companyoperations
• understandthecompanyobjectives• actinamannerconsistentwithcompanyobjectives• implement and monitor activities to optimize operations in line with
companyobjectives• beabletocommunicatecompanyobjectivestootherstaff
Attheendofthementorship,thecompanysitesupervisors
• areabletounderstandcommercialimplicationsoftheirwork• understandthecompanypolicies• work in a manner consistent with company policy (hopefully these are
alignedwithdeliveringgoodqualityworkatcost)
BusinessandTechnicalCoaching–anoverview 28
Part III Key Subjects – Coaching AGuideforCoaches,withkeypoints
TechnicalCoaching 29
10. Technical Coaching
10.1 Mobilisation & Site Setup
i. Contractssignedii. Sitehandoveriii. Sitecamplocationiv. Sitecampbuildingsv. Toolsvi. Equipmentvii. Office
Thefollowingarekeypointsthatneedtobearrangedatthisstage:
Contracts Signed • Havethecontractsbeensigned• Doesthecontractorhavehiscopiesofallrelevantdocuments• Doesthecontractorunderstandthemeaningofthecontract• Hasadatebeensetforthesitehandover• Has thecontractorvisited thesiteprior to thehandover,notingdownany
significant changes that have occurred in the period between his/her bidsubmissionandnow
• Has time been made available for BOTH the contractor and the client’srepresentativetovisitthesiteTOGETHERaspartofthehandover
• Arethereanydocumentsrequiredtobesignedatthesitehandover• Dophotosneedtobetakenofthechangesintheroadconditioninaddition
todocumentingthese• Have copies of the relevant portions of the contract beenmade ready for
easyaccessby relevant company staffe.g.BOQ,ConditionsofContractetcforsiteengineeretc
Site Handover • Hasadatebeenagreedforsitehandover• Is it necessary to make the client’s representative aware of any issues
regardingchangesontheroadpriortothesitevisit• Is thereanyformaldocumentationtobecompletedduringorafterthesite
handover• Areallrelevantpersonsfrombothsides(ClientandContractor)informedand
present• Is there need to invite civil leaders to the site handover too (Xefi Succo,
Aldeia,Parish,DA’sofficeetc)• Ifcivilleadersarerequired,havetheybeeninvited• Havearrangementsbeenmadetodocumentanyissuesnotedduringthesite
handover• If contractor is responsible for access during the construction phase, have
arrangements been made to maintain access immediately followinghandover
TechnicalCoaching 30
• Onthedayofthehandover,hasthemeetinglocationbeenagreed(usuallyattheproposedsiteofficeorstartoftheroad
• Istheresufficienttransportforeverybodyattending
Site Camp • Hascontractoridentifiedasuitablelocationforthesite.Thisisusuallyclose
totheroadworks,closetoshopsorothersocialfacilitiesetc• Isthesitecamplocationsuitableforasitecampregardingsafety• Is the location reasonably flat (considerequipmentwillbeparkedand light
maintenancecarriedout)• Thesitecampisnotatriskfromflooding,landslidesorfallingrocks• Theproposedcampsiteiseasilyaccessiblefromthemainroad• Istheresufficientspaceforthenumberofequipment• Isthereanadequatesupplyofcleanwater• Ifthereisaccesstopublicutilities–electricitythenbetter• Isthereaphonesignal–criticalforanysitecampotherwisecommunication
isnotpossible• Has contractor investigated if there are any issues with the land e.g.
community sacred ground or other activities that may not be compatiblewith construction camp site activities in the area e.g. school, religiousservices,hospitalmaybedisturbedbyconstructionequipmentnoise
• Does the location of the proposed site camp expose pre-existing users /residents to a particular risk e.g. young children are at risk of constructionequipment(notsomuchforhighschooletc)
Buildings / Faci l it ies at Camp Site Thespecificsofbuildingsatcampsiteswillvaryforeachcontractor,thefollowinglistareitemstoconsider
• Howmuchofficespaceisrequired• Whatfacilitiesarerequiredtostoreconstructionmaterialintermsofspace,
protection, accessibility etc. e.g. aggregates can be stockpiles outside,cementhastobestoredindoors,toolsarevaluableandeasytomove,needsafestoragebutstillaccessible
• Is there need to build a vehicle loading and unloading ramp – critical forprecastculverts
• If a vehicle loading ramp is built, is it safe –with a FLAT loading area, andgentlyslopingapproachesandbarriersorsmalledgestostoponefallingoff
• Isthereneedtobuildavehicleservicepitorwheelraisers• Ifthereisaservicepitorwheelraisers,aretheSAFE• Isthereneedtoimprovein-campplumbingorwatersupply• Whichbuildingsinthecampneedelectricityandcanthisbedoneinacheap
andsafemanner• Arethereanadequatenumberoftoiletfacilitiesatthecampsite• Are toilet facilitieswell designedand suitably located– foruseboth in the
daytimeandatnight(securityguardsorstaffwholiveinthecampwillneedtousethese24hours)
TechnicalCoaching 31
• Haveprovisionsbeenmadetodisposeofrubbishgeneratedinthecampinasafemanner
• Isthereneedforshowersatthesitecamp?• Ifthereisneedforshowers,arethewelldesignedandsuitablylocated• Arethereanadequatenumberofshowers?• Has the layout of the site been thought through – in terms of vehicle
movement,officelocation,peoplemovementetc.tominimizeconflict• Ensurethatnochildrenliveinthecamporwalkunsupervisedatthecamp• If it is necessary that staff live with their families at the camp – then
adequateprovisionhastobemadetosegregatechildrenfromdanger
Tools storage at Camp Site Thefollowinglisthighlightssomeissuestoconsiderwhenmakingprovisionsfortoolsstorageatthesitecamp
• What is thepeaknumberofworkersexpectedduring constructionandwhatwillbethetoolrequirementatpeak
• Whatisthenumberofworkersexpectedatthebeginningoftheproject– if this ismuch lower than the peak number then provision for toolsneedonlytakecareoftheinitialdemand
• Howmanyofeachtypeoftoolwillberequired• How will the tools be stored at the site office – is there adequate
provisione.g. some toolsarebetter storedon racks,whileothersmustbestoredonthefloor
• Isthetoolsstoragesafe?• Isthetoolstoragewell lit?(provisionfornatural lightmaybeall that is
required)• Haveprovisionsbeenmadeformanagingtoolse.g.adeskforthestore-
personinthetoolsstorageandsuitablestationery• Has provision beenmade for toolmaintenance – files, grindingwheel,
smallwelder,extrahandlesetc• Is there sufficient space formaintaining the tools e.g. aplace to locate
thegrindingwheel,filesetc.• Has theuserof theequipmente.g.grinderetcbeen trainedonhowto
use the equipment safely and has he/she been provided with suitablesafeguardse.g.eyeshields
• Hasthepersonbeentrainedonhowtoproperlymaintaintools• Is therea facility /procedure towrite-offused toolsor recycleuseable
partsofthetools
Equipment This list is broadly divided into two – the first part considers smaller pieces ofequipmentthatmaybeneededintheofficeortosupporttheoperationsofthecompanywhilethesecondpartfocusesonthemainconstructionequipment
• Has consideration been given to requirements needed in the office tofunction–files,stationary,miscofficeequipment(punchetc)
• Arethesufficientdesksandchairs
TechnicalCoaching 32
• Istheresufficientlighttowork• If a computer is needed or required in office, is there one, is there
suitablesupplyofelectricity• What additional equipment is needed to support the site operations
fromthesiteoffice–weldingmachines,tools,vehicleliftingjack• Aretheequipmentsupporttoolssafe• Aretheoperatorsoftheequipmentwelltrainedtousetheequipment• Is thereaplacetostoretheequipmentandtherequesttheequipment
foruse• Isthereasinglepersonresponsiblefortheequipment• Has the equipment requirement of the project been developed – i.e.
whatwillbeneededandhowmany• Hasthoughtbeengiventohowequipmentusagecanbeoptimized• Hasthoughtbeengiventohowequipmentcostscanbeminimized• Isthereanequipmentmaintenanceregime• Isthereanequipmentusagetrackingsystem• Havesufficientnumberofstaffbeentrainedtousetheequipment(e.g.
there shouldalwaysbemore staff able tooperateequipment than thenumberofequipmentandstaff should ideallybeable tooperatemorethan a single piece of equipment – to minimize low utilization due tostaffabsence)
• Have staff been trained on simple equipment preventive maintenanceandservice
• Hasthoughtbeengiventowhatsparesshouldbekeptatthesiteofficeandwhowillusethese–e.g.brakefluid,oil,grease,assortedboltsandwashers,insulationtape,somewire,bulbsetc
10.2 Labour Recruitment
i. SocialSafeguardsii. LabourManagementSystemsiii. PaymentSystemsiv. ContractingFramework
Social Safeguards and recruitment process Thefollowinglisthighlightssomeissuestoconsiderwhenrecruitinglabour.
• Hasthecontractordeterminedthenumberoflabourersrequiredbeforetheannouncement
• Hasthecontractorplannedworktobalanceoutthe labourdemandforthenextfewweeks(atleastfourweeks)
• Hasthecontractorcheckedthattherearesufficienttoolsandresourcesneedtoworkforthelabourbeingrecruited
• Isthecontractorawareofthelegalobligationstolabour• Canthecontractormeettheirlegalobligationstothelabour• Isthecontractorfamiliarwiththerecruitementprocess
TechnicalCoaching 33
• Does the contractor know that recruitement has to impartial with nogender bias, political opinion differentiation, ethnic bias or any othercriteriaotherthanabilitytodothejob
• Thejobsalsohavetobeopenlyadvertisedorannounced• Therearecertainthingsthatmustbeincludedintheannouncemente.g.
the location and time of recruitment, the approximate number ofcandidateswhowillbeacceptedandalsostatewhoiseligible(allgender,all above certain age etc) – there may be more items needed in theannouncement
• The contractor may need to contact the local civil administration tofacilitateintherecruitmentprocess
• Wheremoreapplicantsthanthenumberofvacanciesavailableapply,afairandtransparentselectionprocesshastobeusede.g.ballotetc
• Thecontractorhastobepreparedwellbeforethefinalrecruitmentdate• Beforetherecruitmentbegins,theproceduresforthecontractorshould
beconversantwiththeprocess• On recruitmentday, all applicantsmustbe informedof theprocedures
beforetheprocessbegins• Conditionsofemploymentshouldideallybemadecleartoanypotential
candidate before the selection process AND if not possible MUST bemade clear to all successful candidates BEFORE and legally bindingagreementisenteredintowiththecandidates
• Among “employment conditions” include typical employment duration,typeofwork, pay rates, frequencyof payment, howpayment ismade,documents needed at contract signing (e.g. identification documents)etc.
• The contractor must be aware that one of the benefits of rural roadsconstruction is local employment and skill development – thus unlessthereisacompellingreason,locallabourshouldbeengaged
• Oncethelabourisengaged,thecontractorshouldbeawareofandmeettheir obligations to the labour e.g. provision of safe workingenvironment, an environment free from bullying, decent tools, non-exploitative practices e.g. excessive task rates, safety equipment whenneeded,trainingtocompletetaskswhenneededetc.
Labour Management Systems Followingtherecruitmentoflabour,thecontractorwillneedtohavesystemstofacilitate administration, monitoring and assignment of tasks to the labourers.Thefollowinglisthighlightssomeofthekey itemscontractorwillhavetomakeprovisionsfor.
• DoesthecontractorhaveacontractorCasualEmploymentform,whichwill have to be signed by each labourer and the contractor (orrepresentative). This forms the actual contract between the labourerandfirm.
• Sample of the above mentioned Casual Employment form can beobtainedfrompreviousprojects–howeverifanewformisdesigneditmustcontainallthecriticalelements.
TechnicalCoaching 34
• Does thecontractorhavea safeplace to store theCasualEmploymentFormforeachlabourer,andinanaccessiblelocation.
• DoesthecontractorhaveaMusterRoll• HavestaffbeentrainedinfillingtheMusterRoll• Do thestaffUNDERSTANDthevalueof thedata in theMusterRolland
its’importanceinthefinancialcontrolprocessofthecompany• Dothestaffunderstandthevalueofthedown-timeandtheimportance
ofplanningthetaskforthelabourersthedaybeforetheworkisdue• Does the contractor have systems in place to plan for work for the
labourers• Are the sufficient measurement guides or tools on site to facilitate
measurementoftheworkinatransparent,fairandsimplemannere.g.templates for ditching and camber formation. Strings and pegs forexcavationetc.
• Doesthecontractorhavesystemstocheckthequalityofworkdonebythelabourerschecklistsetc.Havesupervisorystaffbeentrainedinusingthese?
• Does the contractor have systems to check that the company iscomplyingwithhealthandsafetyonsite
• AretheH&Ssystemsaudited• Arethereenoughsupervisorstoeffectivelymanagetheworkforce• Do the supervisors have sufficient site management aids they –
clipboards, forms, stationery, tape measures, ranging rods, hammers,pegsetc.
Payment Systems Labour isoneofthekey inputs intoruralroadworks.Thecostof labourtothecontractorvariesfrom12%toupto40%dependingonhowlabourintensivetheoperationsareandtheactivitiesbeingundertaken.Itisimportanttoensurethatworkersarepaidinatimelymannerandthecorrectamounts.Tofacilitatethis,thefollowingwillhavetobeconsideredbythecontractor.
• DoesthecontractorhaveaMusterRoll• IstheMusterRollcompletedeveryday• Does the company have systems in place to audit the Muster Roll
occasionally• Is the data from the Muster Roll regularly collated (e.g. weekly) to
estimatethelabourcostandaccruedlabourcosts• Is there a payment processing system – that effectively computes the
moneyowedtoeachlabourer inatimelymannerforpayments(onceamonth?)accordingtothescheduledagreedatrecruitment
• Isthereasystemtocollectthemoneyfromthebankandensurethatitiscollected in the correct denominations to facilitate exact payment toeachlabourer
• Does the company have a system to record each payment to eachlabourernotingdownthemoneypaid,date,andalsoacknowledgementfromtherecipient(signatureandID?)
TechnicalCoaching 35
• Does the company follow standards regarding payment e.g. ensuringonlythepersonwhoworkedcollectsthemoneynothusbandsforwifeorbrotherscollectingtheirsisters’pay
Contracting Framework Theframework/agreementsgoverningtherelationshipbetweenthelabourersandthe contractor are critical to the success of the contract. Further, how thework isissuedtotheindividuallabourerandhowtheoutputismeasuredisalsoimportanttothesuccessofthejob.Thefollowingisalistofitemsthecontractorshouldconsider.
• The contractor should be aware of the concepts how work is issued ontypicalruralroadsprojects–taskwork,grouptaskwork,dailyrate
• The contractor should be aware that different jobs are better suited todifferentpaymentsysteme.g. treeandstumpremovalmaybebetterdonebyagroupof2or3ratherthanalonelabourer
• Thecontractorshouldbeawareoftypicaltaskratesforlabourbasedworksandadjustthesedependingonthespecificconditions
• Thecontractorshouldhavesystemsinplacetoallowthesupervisorstoplanworkforeachdaypriortotheworkbeginning(thepreviousday)
• The contractor must have systems to record the work issued out to eachlabour(orgroupoflabourerseachday)
• The contractor must have systems to recordWHO is on site and workingeachday–MusterRoll
• ThecontractormusthavesystemswhereEACHlabourerclearlyknowwhatisexpectedofthemeachdayi.e.ataskmustbeassignedtoeachworkereachday
• The contractor must have systems to enable BOTH the labourer and thesupervisorstochecktheworkdonebeforethelaboureris“signedoff”
• In a task based system, each labourer must be able to leave soon aftercompletingtheirassignedtask(i.e.theremustbecapacityinthecontractingcompanytocheckworkdoneasitiscompleted)
• ThecontractorstaffmustbeawarethattheyareresponsiblefortheH&Sofeverybodyonsiteincludingvisitors
• The company should have systems that allow a labourer to undertake asmallertaskoccasionallyifnecessary(withreducedpay)
• The company should planworkwith resilience – i.e. if some labourers areabsentonaday,theworkshouldbeabletocontinueonsite
10.3 Works
i. Planning(Project,Daily,Structuresetc)ii. Specificsrelatedtoeachmajortaskiii. QualityControliv. MeasurementofWorks
Planning, Specif ics for Tasks, Quality Control, Measurement Roads construction is a series of different activities. Coordination and balance ofproduction rate for the various activities is critical for optimal construction,avoidanceofabortiveworkandefficientutilizationofresources. Thefollowing isa
TechnicalCoaching 36
list of items thatmay need to be brought to the contractors attention to improvetheircompletionofvarioustasks.
• Does the contractor understand the value of developing an accurate(obviouslysubjecttochangeasprojectprogresses)WHOLEprojectplan
• Hasthecontractordevelopedaprojectplan(GanttChart)• Is the chart realistic considering the resource base of the contractor, the
clientpaymentproceduresandlabouravailability• Doestheplanhavebuiltinresilience?• Hasthisplanbeensharedwiththeclients’representative?Hastheplanbeen
accepted• Has the contractor shared the plan with his/her site management team
(engineers,supervisorsetc)• Do the site management team know the critical path (or at least critical
activitiesontheplan)• Iftheplanhasbeenmadebytheengineer,doesthedirectorofthecompany
understand theplan, thecriticalpathandresource requirement toexecutetheplan
• Has a resource requirement been developed based on the REALIST andapprovedplan
• Is the resource requirement profile within the envelope that the companycanmeet
• If the company cannot meet the resource, requirement, as though beengiventore-designingthePLANorobtainingadditionalresources
• Are all company supervisory staff aware of the conditions of contract, thequalitystandardsandpaymentmethods?
• Doallcompanysupervisorystaffknowtheoptimalwaytoexecutethetaskstheyaresupervising?Aretheyexecutingworksinanoptimalmanner?
• Does the company structure allow for flexibility between tasks to achieveefficientoutput?
• Does thecompanyhavesystems inplace to recordoutput foreachactivityeachday
• Istheoutputrecordedeachdaycollated?• Aretheretoolstofacilitatemeasurementofworkforeveryonewhoneedsto
measure – labourers (templates, tape etc), supervisors (templates, levels,tapemeasures,DCPetc)andengineer
• Is the daily outputmeasured and recorded in a system that facilitates theproductionofinvoicesattheendofthemonth
• Isthereaqualitycontrolsystemforeachtask• Does the company have clearly defined systems and responsibilities
regardingqualitycontrol–i.e.whochecks,howoften,howcheckingisdone,howaretheresultsofthecheckingrecorded,whodidthework(ifpossiblee.g.forcompactionetc)
• Does the company have systems to record abortivework – and if abortivework is frequent, who is responsible to develop structural solutions afteridentifythecause
• Isthecompanyawareofthemaincostsassociatedwitheachtask
TechnicalCoaching 37
• Doesthecompanytrytolimitthemajorcostsincurredineachtaski.e.effortisnotwastedonmarginalcostsorsavingcostswithmarginalgains
• Is there need to develop a culture of constant improvement within thecompany
• Istheequipmentusedfortasksoptimal?(type,capacity,age,servicestate)• Aretheequipmentoperatorsusingtheequipmentinanoptimalmanner?• Are thenumber, typeandqualityof tools issued to labourersadequate for
eachtask?
10.4 Ad Hoc Adjustments to Resources and Schedule
i. Balancingresources(finance,staff,equipment)ii. Adjustmentofworkprogrammeiii. Flexibilityinschedule
Balancing Resources (Finance, Staff, Equipment) Roadsconstruction isa seriesofdifferentactivities.For success thecompanymustensurethateachofthemajorinputs(finance,staffandequipment)areutilizedinanoptimalmanner. The following is a listof key items to consider regarding resourcebalancing.
• Hasaprojectplanbeendrawnup• Istheprojectplanrealistic• Hasaresourceprofilebeendrawnupbasedontheprojectplan• Hasacomparisonbeenmadebetweencompanyresources(finance,staffand
equipment)andtheresourceprofilerequirement• Isthereanissuewiththereliabilityofanyofthekeyresources(finance,staff
orequipment)• If there is a problemwith cash flow (supply of funds) havemeasuresbeen
taken to solve these– e.g. bank loan, improvedpaymentprocesson clientside,regularsubmissionofinvoicesbythecontractoretc.
• Further, if there isaproblemwithcashflow,hasthecontractorconsideredchanging the work plan to balance work done and payments takingcognizanceofthepaymenttime
• Is the company able to proceed with the assignment given its’ financialposition(belowacertainlevelofresourcesnothingcanbedone)
• Is thereanadequatesupplyof labourwhencomparedto therequirementsshownintheresourceprofile
• Has the resource profile been levelled to minimize peaks in labourrequirements
• Ifthereisinsufficientlabour,hasaninvestigationintothecauseofthelaboursupply issues been undertaken (often caused by irregular payments, PRissuesetc,non-compliancewithlegislationandsafeguards)
• Canthecontractoraddressinternalproblemsthatcauselabourshortages• Iflabourshortageorreliabilitycausedbyexternalfactorsbeyondthecontrol
oftheproject–hasconsiderationbeenmadetousealternativemethods
TechnicalCoaching 38
• If labour shortages caused by external problems, has the client beeninformedandcan theclient take remedialaction (usuallypossible ifgovt istheclient)
• Are equipment requirements balanced i.e. no excessive peaks (based onassessmentofcompanyplan)
• Is the equipment resource profile based on the actual equipmentproductivityofthecompanyi.e.notwishfulthinking
• IFthereisashortfallofequipment–waystoovercomethiscouldbe–revisittheworkplan,rentequipment,buyorsharewithanothercontractor
• Has the possibility of using alternative, readily available and economicalequipmentthatisreadilyavailablebeenconsidered?
• Iftheequipmentproductivity isthecauseoftheshortfall,canthecompanyimproveproductivity
• Equipmentproductivitycanbeincreasebyseveralwaysincluding–ensuringthat the temporary roadsarebettermaintained forhaulage, improving theavailability via improved maintenance, better training for equipmentoperators, improving work methods and procedures, better equipmentmanagementetc.
• Havelongtermsolutionstoequipmentshortfallsbeenconsidered• Hasthecompanydeterminedtheminimumlevelofeachclassofequipment
itneedstocompletetheprojectwhilemeetingtheschedule• Isthereanequipmentusagemonitoringsystem?• Istheequipmentusagemonitoringsystemmanagedi.e.isthedatacollected
assessedbycompanymanagement• Does thecompanybenchmark itsequipmentproductivityandcostsagainst
othersimilarcompaniesandstellarcompaniesoperatinginthesamearea• Doesthecompanyhavearesilientequipmentfleete.g.moreoperatorsthan
numberofequipment,readilyavailablesimplespareparts,quickaccesstoagoodworkshopetc
Adjustment of Work Programme This prompts in this section are best read in conjunction with the prompts in thesection“BalancingResources(Finance,StaffandEquipment).”Asonecanexpecttheconstructionofaroaddoesnotoftenfollowthetrajectoryoftheinitialprojectplandeveloped.Infacttheprojectplanrequiresfrequentupdating,andoftenevenmorechanges are required in resource allocation from day-to-day tomeet the plan. Allitemsinthislistassumethereisalreadyawell-consideredprojectplantowhichthecontractorisworking.
• Isthereregularmonitoringofprogressvsplan• Are there good company records that allow management or pinpoint the
causeofdelays• Hasaneffortbeenmadetoidentifythecausesofdelay• Ifdelaysaredueto inefficiencieshavethesebeenaddressedasopposedto
addingmore resources to the activity i.e. continuing inefficient operationsbutguisingthembyaddingmoreresource
• If delays in someactivities are due to lack of resources can rebalancingbedonebeforeconsideringadditionalexternalresources
TechnicalCoaching 39
• If there are delays in some activities and excessive over-production onothers,istherescopetorebalanceresourceinitiallyonlytemporarilymovingresources but if the situation redevelops then permanently redeployingresources
• Aredelayscausedbycashproblems?• If delays are caused by cash problems – are these due to contractor
(insufficientfunds,poorinvoicingcycles,errorsininvoiceetc)ORcausedbyclientnotpayingontime
• Develop a solution to cash problems based on the cause – if client, thenreduceproductivityuntilprevious invoicespaidAND invoice frequentlyandcorrectly
• Ifproblemscausebyclientconsiderdrasticactionsuchasbeginningworkonnon-capitalintensiveworkswhichareALSOhighlyprofitable
Flexibi l ity in Schedule Foracompanytobeabletomeettheprogrammeitmustbuildsomeresilienceinitswork methods. This has to be built throughout the resource chain. The companyneedstohavesomeresilienceinthesupervisorystaff, labour,equipment,suppliersetc.
• Hasananalysisoftheresiliencebeenundertaken• Aredelayscausedtolargeportionsofworksimplybecauseasingleelement
ofinputismissinge.g.ifasupervisoradriver/equipmentoperatorill,thereisnobodytotakeovertheirworkimmediatelyandhugeswathsofworkstall
• Ifasinglesupplierdoesnothavegoodsdoesthecompanysupplychainbreakdown
• If a simple commonpieceonequipment fails, does themachine stop for afewdayse.g.oilfilter,punctureetc
Payments
i. Processesforproducinginteriminvoicesii. Processesofpayingcreditors/purchasesiii. Proceduresformonitoringcostsiv. Proceduresformanagingcosts
ContractorMentorship 42
11. Contractor Mentorship
11.1 Background and Overview
Thefollowingsectioncoverstypicaltopicsthatareexpectedtobecoveredduringthementorship. As previous mentioned, there cannot be a curricula during thementorshipphase.Thisisbecausethesupportprovidedbythementorwillvaryfromcompany-to-company depending on the specific requirements or challenges thecompany is facing. Thus the following section instead of providing a list of topicsthrough which the trainer can work, present a number of sample topics that thecontractors are expected to face and that would constitute typical areas in whichmentorshipsittobeprovided.
Simply because the specific topic areas in which a contractor would requirementorshiparenotpossibletopre-determine,doesnotmeanthattheapproachtoeachspecifictopiccannotbestructured.Onthecontraryastructuredmethodologyhas been adopted that shouldbe applicable tomost topics inwhichmentorship isprovided.
Thegeneraltrajectoryindevelopmentofeachareaofsupportisasfollows:
1. Problemidentification: this is thestageatwhichthecontractordecidesthefirm has a problem that needs mentorship support. The problems isdiscussedwiththementorandifagreedthatitrequiresmentorshipsupportaprocessofmentorshipisformallyinitiated.
2. Definition of objectives: At this stage both the contractor and thementordefinewhat the intendedoutcomesof the interventionsundertaken in thespecific area. It is important that the list generally only includes high-levelobjectives that are expected outcomes as opposed to intermediateobjectives.Itisagainsttheseobjectivesthatthesuccessoftheinterventionsintroducedunderthementorshipregime.Itisalsoimportanttoensurethatthe objectives are achievable – achievability can be assessed against theinitial benchmarking exercisewhere the contract did an assessment of thecapabilitiesofthecompany.
3. Identificationoftargetaudience:Oftenstructuralchangeswithinacompanyare aimed at certain persons – usually those in a position of responsibility(for either finances, resource allocation or processes undertaken). Thesepersonhavetobeidentifiedasspecificactionswillthenbedefinedforeachgroup.Itisexpectedthatoftentherewillbeseverallevelswithinacompanythatwillbethe“targetaudience”oftheinterventions.Atthisstageitisalsoexpected that the target audience will generally fall within the circle ofinfluenceof thecompany i.e.personsandpeopleoverwhomthecompanyhascontrol–thisisgenerallyexpectedtobetheemployeesorownersofthecompany. Rarely will there be a target audience outside the company –thoughitisnotimpossiblethatthisisthecase.
4. Identification of Mentorship providers: The mentor is not expected toprovide all support. The mentor will lead in the provision of support,however to be truly effective, the mentorship process should be able to
ContractorMentorship 43
enlist thehelpof specialists toprovide specific support in areaswhere thementor may not be the ideal person to provide guidance. Typical areaswhere specialist support may be required could include development ofequipment maintenance regimes (fleet manager), training equipmentoperators (fleet manager), community engagement (CommunityDevelopmentOfficer),buildabilityissues(CDMexperiencedperson)etc.Theidentificationofproviderswill be the responsibilityof thementor.Anotherresource optimization approach is to maximize the involvement of thoseproviding coaching. Thementorwould then direct coach to provide inputsintothementorshipprocess.
5. Identification of persons who will be influenced: This stage identifies thepersonswhosemodusoperandiwill experience a long-term changedue tothemodified process. Both thementor AND the “Target Audience”will beresponsible for identifying the group of personswhowill be influenced bythe intervention. Generally these are expected to be persons within thecompany. It is possible that the “TargetAudience” and “InfluencedGroup”havesomepersons.Moreoftenthe“InfluencedGroup”shallincludesomeoftheTargetAudienceANDsomecompanystaff.Thementorthusworkswiththemanagementthroughthe“TargetAudience”tochangethe“Influenced”group.
6. Determine Operational Objectives: The “Target Audience” will thendetermine Operational Objectives for the “Influenced Group.” Theoperationalobjectivesareeffectively intermediateobjectives. It isassumedthat the high level objective is attained by implementation of process orchangesinthemanagementsystemsthatwillultimatelyleadtothedesiredoutcomes. Verification of the assumption that fulfilling the operationalobjectiveswill result in fulfilment of the high level objectives is somethingthat both the mentor and the director must have done at the problemanalysisstage.
7. DesignandCommunicatethesolutionsorchangesneededtotheInfluencedGroup:The“TargetAudience”willthedesigntherequiredchanges(couldbechangestotheprocess,procedures,companyrulesetc.), thesewill thenbecommunicatedtotherelevantpersonsandtheywillimplementthem.Partofthe design should include sufficient (resource, forms, time) for reportingprogressbythe“TargetAudience.”
8. Monitoring
EquipmentManagement(sample) 44
12. Equipment Management (sample)
12.1 Objectives
PossiblehighlevelObjectives:
i. Tominimizethetotalequipmentownershipcostii. Tomaximizeequipmentavailabilityiii. Tooptimizetheequipmentfleetiv. Tooptimizeequipmentutilizationv. Toimprovefleetreliabilityandavailability
12.2 Target Audience
i. CompanyDirectorsii. CompanyEngineersiii. CompanyTechniciansiv. (EquipmentOperatorsandcompanymechanics)
12.3 Providers
i. Experiencedengineer(resourcepool:R4D,ERA,DRBFC)ii. Experiencedequipmentfleetmanager(IGE,consultant,ERA)iii. Experiencedequipmentoperator(ERA,othercontractor)
12.4 Influenced
i. Companysupervisorsii. Equipmentoperatorsiii. Othercompanystaff
12.5 Objectives set by
i. Directorwith help of Engineerwith INFO from Supervisors and EquipmentOperators
12.6 Pre-requisites
i. Effectiveandconsistentequipmentcostmonitoringii. Improvedmanagementconsistentwithobjectivessetaboveiii. Effectivecommunicationofobjectivestocompanystaffiv. “rewards” for staff in line with achieving objectives i.e. there must be a
motiveandalsomotivationfortheirparticipationv. Computationofinitialequipmentoperatingcosts
EquipmentManagement(sample) 45
12.7 Training material
i. Sampleequipmentmonitoringformsii. Sampleequipmentmonitoringregimeiii. Typicalequipmentproductivityratesiv. Specificmaterialdevelopedbymentore.g.costmonitoringschedule
12.8 Reference material
i. CATHandbook(orsimilar)ii. Manufacturerequipmentmaintenancescheduleiii. Typicalequipmentoperatingcosts
12.9 Measurement of Effectiveness of “module”
Method:BaseLineDatacomparedtoprovidecontinuouscomparison.Parameterstobemonitored.
• Equipmentutilization• Totalcostofequipmentownership• Equipmentcost/unitofproduction• Equipmentcost/unitofprofit• Equipmentmonitoringsystem(L)• Trainingforequipmentoperators(L)• Effectivenessofcommunicationofobjectives(L)
CompanyTechnicalStaffManagement(sample) 46
13. Company Technical Staff Management (sample)
13.1 Objectives
PossiblehighlevelObjectives:
i. Toimprovetechnicalskillsofstaffii. Toimprovemanagementskillsofstaffiii. Todevelopeffectivecommunicationwithstaffiv. Toeffectatransparentandmotivatingpaystructurev. Toimprovecompliancewithlabourlegislationvi. Todevelopandimprovecompanylabourmanagementsystemsvii. Improvingdiversityviii. Preventingdiscriminationix. Eliminatingbullingorharassmentx. Improvingsenseofownershipxi. Expensesandbenefitsxii. Workingtimeandconditionsxiii. HealthandSafetyxiv. Trainingxv. DrugsandAlcoholpolicy
13.2 Target Audience
i. CompanyDirectorsii. CompanyEngineers(onlyiftheymanagestaff)iii. CompanyTechnicians(onlyiftheymanagestaff)
13.3 Providers
i. Experiencedengineer(resourcepool:R4D,ERA)ii. Suitable“social”staff(R4Dsocialsafeguards)iii. ExperiencedHRmanageriv. Experiencedlabourlawyerormanager
13.4 Influenced
i. CompanyDirectorsii. CompanyEngineers(iftheymanagestaff)iii. CompanyTechnicians(iftheymanagestaff)
13.5 Objectives set by
i. DirectorOnly
CompanyTechnicalStaffManagement(sample) 47
13.6 Pre-requisites
i. Basiccompliancewithlabourlawsii. Longtermvisionforcompanystaffandstaffmanagementpolicyiii. Basicstaffrecordsiv. UnderstandingofthebenefitsofgoodHR
13.7 Training material
i. Simplifiedlabourlegislationdocumentsii. SamplegoodcompanyHRpolicyiii. Typicaltrainingschedulesiv. Typicaljobdescriptionsv. Typicalengineering(technicalcrafts-person)skillsdevelopmentvi. TVETskillsdevelopmentmatricesvii. Keepingstaffrecords(content,storagemethod,access,privacy)viii. Bestpracticeinrecruitmentandemploymentstandards–NIGovtwebsite
13.8 Reference material
i. LabourLegislationii. HRmanualsfromsuccessfulcompaniesiii. ILOpapersonlabourandstandardsiv. ConstructionIndustryEmploymentscheme(UK&NI)v. ILOpapersonshorttermemploymentandalsoconstructionindustry
13.9 Measurement of Effectiveness of “module”
Method:BaseLineDatacomparedtoprovidecontinuouscomparison.Parameterstobemonitored.
• Implementationofagreedmeasures• BeforeandAfterquestionnairesurveysofstaff• Staffretention(longtermmeasures)• Improvementinmoral• Improvementintechnicaloutputquality
CompanyHealthandSafetyStandards 48
14. Company Health and Safety Standards
14.1 Objectives
PossiblehighlevelObjectives:
i. Toreducenumberofaccidentsii. Toeliminateavoidableaccidentsiii. Tocomplywithlegislationiv. Toreduceinsurancepremiumsv. TodealwithanAlcohol/Drugsproblem
14.2 Target Audience
i. CompanyDirectorsii. CompanyEngineersiii. CompanyTechnicians
14.3 Providers
i. ExperiencedengineerWITHCOMPETENCEINH&S(note:thisisasubjectareawhichrequiresspecializedknowledge–akintotheCDMRole)–onecannot“wing”throughthisarea
ii. Socialsafeguardstosupportcompetentpersonaboveiii. ExperienceClerkofWorkswithknowledgeofGOODPRACTICE
14.4 Influenced
i. CompanyDirectorsii. CompanyEngineers(iftheymanagestaff)iii. CompanyTechnicians(iftheymanagestaff)
14.5 Objectives set by
ii. DirectorOnly
14.6 Pre-requisites
i. Basiccompliancewithlabourlawsii. AcompanywideH&SAuditundertakentogoodstandardsiii. Understanding the need for a company system to record accidents, near
missesANDobservedrisksiv. Understanding that siteH&S is responsibility of everyone– employer, staff
andevenclientincasesofacompetentclientv. Longtermvisionforcompanystaffandstaffmanagementpolicyvi. BasicunderstandingofH&S,H&Spolicy,benefitsofH&Svii. BasicknowledgeCOSHH
CompanyHealthandSafetyStandards 49
viii. Basicawarenessofthecosts/benefitofaneffectivesafetyregimeix. Basicawarenessoftherisksassociatedwithconstructionactivities
14.7 Training material
i. Socialsafeguardsmaterialsrelatedtosafetyii. Safetyonconstructionsites–H&Ematerialiii. Documents that list roles and responsibilities of key persons on site w.r.t.
safetyiv. Typicaljobdescriptionsv. Typicalengineering(technicalcrafts-person)skillsdevelopmentvi. TVETskillsdevelopmentmatricesvii. Keepingstaffrecords(content,storagemethod,access,privacy)
14.8 Reference material
i. LabourLegislationii. H&Smanualsfromsuccessfulcompaniesiii. DocumentsdescribingtheCDMrolesinsuccessfulcompaniesiv. HSEwebsite(GB)v. HSAwebsite(IRL)vi. AssociationofProjectSafetywebsite(APS)
14.9 Measurement of Effectiveness of “module”
Method:BaseLineDatacomparedtoprovidecontinuouscomparison.Parameterstobemonitored.
• Implementationofagreedmeasures• H&Ssystems(beforeandafter)• AwarenesswithinthecompanyofthevalueofH&Sprocedures• AwrittenH&Spolicywhichisknown(recall:anycompanywithmorethan5
people needs awrittenH&S policy inmany countries – can be adopted asgoodpracticehere)
• WrittenH&Spolicyisclearlyexhibitedoncompanysiteoroffice.Alsosharedwithemployeesinpositionofmanagement(engineersandsupervisors)
• Accidentstatistics(longtermmeasures–itisexpectedthattoofewincidentstomakestatisticaldifferenceintimeframe)
CompanyFuture 50
15. Company Future
15.1 Objectives
PossiblehighlevelObjectives:
i. Tosetalongtermvisionforthecompany
15.2 Target Audience
i. CompanyDirectors
15.3 Providers
i. Experiencedengineerwithbusinessexperience
15.4 Influenced
i. CompanyDirectors
15.5 Objectives set by
iii. DirectorOnly
15.6 Pre-requisites
i. Understanding of company status (financial, technical, work load pipeline,majorhurdles,resourcebaseetc)
ii. Awarenessandsomebasicunderstandingofmarketconstraintsiii. Basicunderstandingofachievabletargets
15.7 Training material
i. Growthmodels (It is strongly recommended that theBalancedScorecard isused, however the Director is the leader of the change process and candetermineasuitablemodel)
ii. Businessmanagementdocuments
15.8 Reference material
i. BalancedScoreCard(balancescorecardrecommendedbecauseitaddressesfundamental objectives across a broad areas relevant to nascentconstruction companies ð "learning and growth", "internal businessprocesses","customerperception"and"financialhealth"
ii. Othersuitablebusinessmodelsasrequirediii. B2B review material (to help develop understanding of perception of
company)
CompanyFuture 51
iv. Performancefiguresandoperationsofappropriatecompanythatcaninformdirectionsetting
15.9 Measurement of Effectiveness of “module”
Method:Measureattheendofthementorshipphaseprogressthathasbeenmadetochangethecompanyinto.
• Implementationofagreedmeasures• BeforeandAfterquestionnairesurveysofstaff• Staffretention(longtermmeasures)• Improvementinmoral• Improvementintechnicaloutputquality
CompanyFuture 52
Part VII Record Keeping & Monitoring, Mentorship Formstorecordadvicegivenandmonitorprogressduringmentorship
SolutionSheet 53
16. Solution Sheet
Item/Issue:Initiatedby:High LevelObjective(s)
ActionPlans
Notes – discussionpoints
Parameters tomonitor
Alignment withcompanyvision
VeryGood Good NotAligned
TargetAudience
Director Engineer Supervisor
AdviseProviders InfluenceTarget
Director Engineer Supervisor Other Other Other
ProgressMonitoringL1
Who What When
ProgressMonitoringL2
Who What When
ReviewofProgress When ReviewofOutcome Unintended +ve
outcomes
Unintended –veoutcomes
AdditionalComments
SolutionSheet 54
InitialProblemAnalysisbyContractor
ContractCompany Companyname
Director CompanyDirector Date:
Problemasidentifiedbythecontractor:Here the contractor specifies theproblem that requiresmentorship support. It is best if theproblem isa singleproblemi.e.therootproblem,notproblemsthatariseasaconsequenceofarootproblem.
Consequencesofproblemasperceivedbycontractor:(qualitative)Thecontractorliststheeffectsoftheproblem.Thissectionshouldhelpfocusthecontractors’attentiontotheimplicationsofthe“do-nothing”option.Itwillalsoallowthementortobetterunderstandthelevelofthecontractors’understandoftheirbusinessoperations.
Consequencesofproblemasestimatedbycontractor:(quantitative)Thequantificationofthecostsoftheproblemwillhelpdeterminethepotentialbenefitsvsthecostsoftheexerciseandalsoprobablyprioritizeincasethereareseveralcompanyproblemstobesolved.
Solutionasinitiallyidentifiedbycontractor:Herethecontractor(companydirector)willnotedowntheirproposedsolutiontotheproblem.This is importantbecauseit:
1. Gives the director an opportunity to analyze the problem themselves and hence improves theirmanagementskills
2. Providesthementorattheinceptionmeetingthesomeinsightintowhatmaybenon-obviouscausesoftheproblem.Causesonlyevidenttoacompanyinsider.
Intendedoutcomeofsolutionsabove:Fillingthissection,willallowthecontractorto
Risksassociatedwithproposedsolutions:
SolutionSheet 55
ProblemAnalysis(MentorANDContractor)
ContractCompanyandDirector
Mentor Date:
ProblemasidentifiedbybothContractorandMentor:Boththecontractorandthementorshouldmaketimetodiscusstheproblem.Itmaybenecessarytoinviteseniorstaffinthecompanyforthisinitialdiscussionorforsomepartofthediscussion.Itisimportantthattheproblemidentificationisobjectiveanddoesnotbecomeaninternal“witch-hunt.”TheproblemshouldthenberewordedaProjecte.g.ifPoorEquipmentAvailabilityistheproblem.ItwilllaterberewordedasaprojecttoImproveEquipmentAvailability.MostimportantConsequencesofproblem:(qualitative)TheMentorandthecontractorhavetoevaluatetheconsequencesoftheproblemabovei.e.theconsequencesoftheproblemontheoperationsofthecompany.Further, it would be useful to determine the alignment of the consequences with the company’s long termobjectives–thecloserthesearealignedtothelongtermobjectivesthebetter.Estimatedconsequencesofproblem:(quantitative)Thementor togetherwith thecompanydirector (helpmayberequired fromsenior technicalstaff)estimatetheadditionalcostsofthecompanyincursduetotheproblem.Itisimportanttothinkbroadlyatthisstageandincludeawiderangeofcostsincludingfinancial,reputation,risks,depreciationandpotentialfutureincomecosts.
Underlyingcausesofproblem:Inthisstageboththecontractorandthementordeterminetheunderlyingcausesoftheproblem.Thisstepiscriticalbecauseitwillinformthedevelopmentofsolutions.
Solutionasinitiallyidentifiedbycontractorandmentor:The contractor and thementor together arrive at a solution. It is ideal if thementor guides the contractor inarrivingatthesolutioni.e.mentorsthecontractorthroughthedecisionmakingprocessasopposedtounilaterallyprovidingasolutiontothecontractor.Some problemsmay requiremore than a single sitting – e.g. collection of additional data,monitoring variousparameters(e.g.fuelconsumption,staffutilization,materialprices,companypracticesetc.)toinformthedecisionmakingprocess.Thementor shoulddelegateasmuchof thedatacollectionprocess tocontractor. Further, thisshould also be usedas part of the development of the contractor to instill a culture ofmonitoring in companyoperations.
Intendedoutcomeofsolutionsabove:Following development of the solution(s) to the problem, BOTH the contractor andmentor should also list theexpectedoutcomesofthesolutions.Reasonable time frames should be assigned to each outcome and if interim solutions can be identified theseshouldalsobenoted.
Risksassociatedwithproposedsolutions:Changestocompanyculturecomewithrisks.Theyareatleastdisruptiveandoftenstressfultotheemployeesifnot well implemented. It is possible to loose staff, make things worse and disrupt company operations.Identificationandmanagementofriskisthusoneofthekeyactivitieswhichmustbeundertaken.BOTH the contractor and the mentor have to develop a risk register. The contractor MUST maintain the riskregisterandtheremustbetriggerpointsdeterminedforcriticalrisksatwhichpointthecontractorwouldrequestadditionalhelpfromthementor.ItisimportantthatthecontractorUNDERSTANDStherisksassociatedwitheachproposedchangeANDagreestoundertakethechangesinspiteoftherisks.Asortofbenefit-costanalysismustbeundertakenforeachchangei.e.arethechangesworththerisks(andcosts)associatedwiththechange?
EffectingChange“ImplementingtheProject”(MentorANDContractor) 56
17. Effecting Change “Implementing the Project” (Mentor AND Contractor)
17.1 Project Setup or Initiation
ThepreviousprocessiseffectiveaProjectStartup.Itispossibletohaveastartupmeetingwiththecontractorandagreeafterthestartupmeetingthatthe“problem”asidentifiedbythecontractorisnotreallyaproblem.Otherpossiblereasonswhyresolutionofaproblemasidentifiedbythecontractormaynotbeworthwhilecouldinclude:
1. therisksassociatedwiththetryingtosolvetheproblemaretoobigcomparedtothepossiblegains
2. thesolutionstotheproblemmayliebeyondtheresourcesofthecompany(technicalcapability,financialresourcesetc)
3. thesolutionmaylieoutsidethecompanyandinareasitcannotinfluencee.g.legislation,governmentpolicyetc.
4. theremaybemorepressingproblemstodealwith5. theproblemcanbedealtwithmoreeffectivelyunderthecoachingregime
ratherthanunderamentorshipprogramme6. otherproblemsmayneedresolutionbeforetheproblemidentifiedcanbe
addressede.g.implementationofbasicmonitoringsystems,companyHRpolicy,trainingetc.
Asimplifiedwaytolookattheinitialstart-upmeetingandthesubsequentactivities–iftheyaretobefollowedthroughareillustratedbelow.Thestartupisnotpartoftheproject.Thestartup-meetingdoesnotnecessarilyleadtoaproject.Andaprojectcanhaveseveraldeliverablesorstages.
Astart-upisoftenbriefandfocused.However,itisalsopossibletohaveastartupphasethatislongerwhentimeisneededtodecideiftheproblem(whichwillleadtoaproject)canandshouldbetackledunderthementorshippregijme.
The Project
Initiation
Delivery 3
Delivery 2
Delivery 1
Start up
Adapted from Passing the Prince2 Exams, Nick Graham
EffectingChange“ImplementingtheProject”(MentorANDContractor) 57
17.2 Actions at Project Setup
OncetheProjectisagreedwiththecontractor,thefollowingneedtobeidentifiedandmadeclear.
1. Whoisresponsibleforexecutingthe“project”2. Whoisresponsibleformanagingthe“project”3. Whoaretheotherstakeholdersandwhataretheirroles4. Monitoring–progressandrisks,whowillberesponsible,howitwillbedone,
reportingetc.5. Doesthe“project”needtobedividedintodiscretechunkswithdeliverables
whichcaneitherberunindependentlyorconcurrently(seeDelivery1,2,…,n)6. Ariskregisterwillneedtobedevelopedandupdatingproceduresagreed7. Formostmentorshipinterventionsitisexpectedthatmonitoringofimpact
orvariousmetricswillbeanimportantandlargecomponentthatwillguidesubsequentdecisions
Itisimportantthatforallprojects–(expectedtobeall),thecompanydirectorshouldbetheresponsiblefortheimplementationoftheproject.Insomeinstances,theresponsibilitymaybedelegatedtosomeoneinthecompanywithreportingstillhappeningtothecompanydirector.Theroleofthementorissimplytoprovidesupportandsteertothechangeprocess.Thementorshouldneverberesponsibleforanyoftheprojects.
17.3 Deliverables (stages)
Oncethe“Project”hasbeensetup,theprojectmayneedtobedividedintoworkpackagesorstagesthataremanageable.Thestagesneedtobeindependenti.e.theydonotdependonoutputfromanother.Iftheydependonoutputfromanotherstage,thenitisbettertohavethestagesoccurconcurrently.
Thesettingupofeachofthestageshastobedonetogetherwiththementor.Eachstagemust;
1. Haveacleardeliverable,thatcontributestothehighlevelobjective,thisshouldbeguidedbyafundamentalunderstandingoftherelationshipbetweencauses,effects,targetareasandwhatcanbechanged.
2. Haveaclearsetofactivitiesthatwillresultinthedeliverables(set1above)3. Haveacleardelegationofactivitiesandmanageroftheactivities4. Haveariskregisterwithacompetentpersonchargedwithmaintainingthe
riskregister5. Makeallowancefortheriskregistertobereviewedregularlybyboththe
directorandthementor6. makeallowanceforregularmonitoringmeetingswiththementor
Thereader is remindedto reviewthesheetspresented inPart IVof thisdocumentthat includes some sample sheetshighlighting typical areas tobe consideredwhendealingwithtypicalareasinacompanythatmayneedimprovement.
EffectingChange“ImplementingtheProject”(MentorANDContractor) 58
17.4 Regular Monitoring, Final Evaluation and Terminating Projects
Theaimofmostprojectswillbetoachievelonglastingeffectswithinthecompany.Itisexpectedthattheywillessentiallyleadaculturalchangewithinthecompanywithlongtermpositiveeffects.
Monitoring has to be built into each stage of the change projects, it has to beeffectivelycarriedoutandifnecessaryfeedbackfromthemonitoringhasto informcurrentandsubsequentchanges.
Infactsimplymonitoringkeyparameterswithinacompanyandgettingcompaniestoregularly assess thedata comingoutofmonitoring is a big improvement formanycompanies.
Monitoringhastobespecificfortheintendedresults–butatthesametime,abroadoversight has to be maintained to ensure that unintended consequences of theinterventionsarealsospottedandeitherencouragedorminimizeddependingontheconsequences5.
5Unintendedconsequencescaneitherbefavorableorunfavorable
EffectingChange“ImplementingtheProject”(MentorANDContractor) 59
Part VIII Estimated Resource Requirements F
EstimatedResourceRequirements 60
18. Estimated Resource Requirements
18.1 Background
Thissectionprovidesanestimateof resourcerequirements to implementCoaching(Technical and Business) andMentorship as developed within the document. ThissectionismainlyrelevanttotheR4Dprogrammeforthe2015/2016contracts6.Theassumptionsforthebudgetarefollowedbythenumberofpersonsrequiredforthementorship.
18.2 Resource Estimates
Theestimateisbasedonthefollowingassumptions:
• Acoachwouldneedtoseethecontractorsonceamonth• Contact time with contractors during the coaching time is about 2hours
(henceabout4contractorscanbecoachedinaday)• Adequate time has to be allocated to discuss the contractors during the
coachingprocess–currentlyassumed2hours/contractor• Thecoachwill alsoneed tobedebriefedby theR4Dregionalengineerand
theclient’srepresentativepriortothecoach-contractormeeting• The coach will need to brief the R4D regional engineer and the cient’s
representative after the coaching visists – these are to update the R4Dengineer but also to delegate backstopping tasks required of the R4Dengineerbetweencoachingvisits.
• Thecoachshallprovidetraining(coaching)inputasanimpulse.TheRegionalEngineersshallthenprovidetheday-to-daysupporttothecontractorbasedonthebriefingandde-briefingprovidedbythecoach
• Thementorwould on average be required tomeet a contractor once in 6weeks
• Thementorwouldspendabouthalfadaywitheachcontractoron thesitevisits
• Unlessthecontractorshaveacommonproblem,itisgenerallyexpectedthatthementorshallmeetthecontractorsprivately
• Noteverycontractorwillrequirementorshiponallvisitsbythementor
Additionalpoints
Thecoach,mentorandregionalengineershallcloselyco-ordinatetheiractivities
It isexpectedthattherequirementforad-hocsupportfromtheRegionalEngineersshallbegreatlyreducedbythestructuredcoaching.
6 The rest of thedocumenthasbeendesigned tohave a longer lifespan that 2015/16R4Dcontracts
EstimatedResourceRequirements 61
Both the coaching programme and thementorship progamme are specific to eachcontractor. Though it is expected that the coachingprogrammes for contractors atthesamelevelofdevelopmentwillbebroadlysimilar.
The Regional Engineers shall continue to provide daily support to the contractors,howeverthisshallnowbemorestructured,followingfeedbackfromthecoach.
TheRegionalEngineershallinputwhichwillsteerboththementorshipandcoachingprograms. The input shall be based on their sizeable experience working with thecontractorsonadailybasis.
ThementoroperatesatavisibledistancefromtheRegionalEngineerandtheclientorganization i.e. it has to be visible to the contractor that the mentor is on thecontractors’side
Districts NumberofRoadRehabContractors(contracts)
CoachingPerson-days/
month
CoachingManangment
/month
ContractorContact
MentorshipPersondays/1.5months
MentorshipManangement/1.5months
1. BobonaroCovalima
20
4 2 4 2
2. LautemBaucauViqueque*
041
6 2 6 2
3. ManufahiAinaro
10
3 1 3 1.5
4. AileuLiquiçáErmera
200
3 1 3 1.5
5. Oecusse 1 3 1 3 1.5 Total 11 19 7 19 8.5
18.3 Estimated Person days
Mentor~27.5persondaysper1.5monthsabout0.75utilisation
Coach~26persondayspermonth.About2coachesabout60%utilisation
Effectively, thiswould translate to2personsworkingascoachesand1personasamentor.