Date post: | 27-Jan-2023 |
Category: |
Documents |
Upload: | khangminh22 |
View: | 0 times |
Download: | 0 times |
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
EIA/ EMP REPORT FOR
PROPOSED PROJECT OF
POLYESTER RESINS
BY
ASIATIC COMPOSITE LIMITED Survey no. 1963/185/24-B-Paiki, Village: Mankol, Tal: sanand-382110,
Dist: Ahmedabad, Gujarat
2018
B. S. Rana
(MEET ASSOCIATES) 305, Sathi Apartment, Mahalaxmi Lane,
Sarangpur, Ahmedabad-380001 Ph: 9586249761, 9909362746
Email: [email protected]
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
1
Table of Contents
EXECUTIVE SUMMARY .......................................................................................................11 CHAPTER 1. INTRODUCTION AND BACKGROUND .......................................................19
1.1. Project Proponent & Background .......................................................................19 1.2. Proposed Project .................................................................................................19 1.3. Justification of the Project ..................................................................................20 1.4. Site Selection Criteria ..........................................................................................21 1.5. Purpose of the Study ...........................................................................................21 1.6. Objective of EIA Study .........................................................................................21 1.7. Regulatory Frame Work .......................................................................................22 1.8. Scope & Methodology of the study .....................................................................23 1.9. Approved ToR for EIA Study by Gujarat- SEAC .................................................24 1.10. Structure of the Report ........................................................................................42
CHAPTER 2. PROJECT DESCRIPTION............................................................................44 2.1. About the Project .................................................................................................44 2.2. Components of the Project .................................................................................45 2.3. Proposed Schedule of Approval and Implementation .......................................45 2.4. Location of the Project ........................................................................................46 2.5. Layout of the project site .....................................................................................46 2.6. List of Proposed Products ..................................................................................47 2.7. Raw Material & Storage .......................................................................................48 2.8. Manufacturing Process........................................................................................49 2.9. Resource Requirement ........................................................................................51
2.9.1. Land Requirement ..............................................................................................51 2.9.2. Power Requirement ............................................................................................51 2.9.3. Water requirement ..............................................................................................52 2.9.4. Manpower Requirement .....................................................................................53 2.9.5. Fuel Requirement ...............................................................................................53
2.10. Capital Investment ...............................................................................................54 2.11. Pollution Potential and Its Control Measures ....................................................54
2.11.1. Water Environment ...........................................................................................57 2.11.2. Air Environment ................................................................................................59 2.11.3. Solid and Hazardous Waste Management ......................................................59 2.11.4. Noise Pollution .................................................................................................61
2.12. Green Belt Development ......................................................................................61 2.13. Occupational Health & Safety .............................................................................61
CHAPTER 3. DESCRIPTION OF THE ENVIRONMENT .......................................................63 3.1. Background ..........................................................................................................63 3.2. Environmental Setting and Salient Environmental Features of the Project Area
...............................................................................................................................63 3.3. Primary Data Collection: Monitoring Plan and Quality Assurance Procedures
...............................................................................................................................64 3.4. Physical Environment ..........................................................................................66
3.4.1. Topography .........................................................................................................66 3.4.2. Physiography ......................................................................................................66 3.4.3. Geology ...............................................................................................................66
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
2
3.4.4. Geomorphology ..................................................................................................67 3.4.5. Land / Soil Characteristic: ..................................................................................68 3.4.6. Rain Fall: .............................................................................................................68 3.4.7. General Information of Taluka Sanand: ............................................................69 3.4.8. Climate: ...............................................................................................................69 3.4.9. Geohydrology: ....................................................................................................69
3.5. Seismicity of the Study Area ...............................................................................71 3.6. Land use ...............................................................................................................72 3.7. Meteorology ..........................................................................................................74 3.8. Ambient Air Quality ..............................................................................................77
3.3.1. Interpretation of result .......................................................................................82 3.9. Noise Environment ..............................................................................................84
3.4.1. Observation on Ambient Noise Quality: ...........................................................86 3.10. Water Quality ........................................................................................................86 3.11. Soil Quality ...........................................................................................................90
3.11.1. General Characteristics of the Soil in the District ..........................................90 3.11.2. Methodology .....................................................................................................91 3.11.3. Analysis of Soil Samples .................................................................................93 3.11.4. Observation on Soil Quality .............................................................................94
3.12. Traffic Study .........................................................................................................94 3.13. Ecological Environment ......................................................................................96
3.13.1. Flora ..................................................................................................................96 3.13.2. Fauna .................................................................................................................99
3.14. Socio-Economic Environment .......................................................................... 102 3.14.1. Demographic and Socio-Economic Features ............................................... 102 3.9.3. Workers Scenario ............................................................................................. 105
CHAPTER 4. IMPACTS ASSESSMENT AND PREDICTION ............................................. 108 4.1. General ............................................................................................................... 108 4.2. Construction Phase ........................................................................................... 109 4.3. Operation Phase ................................................................................................ 112
4.3.1. Air Environment ................................................................................................ 112 4.3.2. Noise Environment ........................................................................................... 122 4.3.3. Water Environment ........................................................................................... 124 4.3.4. Land/Soil Environment ..................................................................................... 125 4.3.5. Biological Environment .................................................................................... 126 4.3.6. Socio – Economic Environment ...................................................................... 129
CHAPTER 5. ENVIRONMENTAL MANAGEMENT PLAN MONITORING PROGRAM ....... 131 5.1. Introduction ........................................................................................................ 131 5.2. Environment Management Plan ........................................................................ 131 5.3. Objectives of EMP .............................................................................................. 132 5.4. Brief Environmental Management Plan ............................................................ 133
5.4.1 Construction Phase: .......................................................................................... 133 5.4.2. During Operation Phase ................................................................................... 135
5.5. Budget for Environment Protection .................................................................. 140 5.6. Conclusion ......................................................................................................... 141 5.7. Environment Monitoring Program .................................................................... 141
CHAPTER 6: HAZARD EVALUATION AND RISK ASSESSMENT .................................... 144 6.1. Introduction ........................................................................................................ 144 6.2. Risk Assessment ............................................................................................... 144
6.2.1. Risk Screening Approach .............................................................................. 147 6.2.2. Hazardous Materials Storage ........................................................................ 155
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
3
6.2.3. QRA Approach ............................................................................................... 155 6.2.4. Thermal Hazards ............................................................................................ 156 6.2.5. Damage due to Explosion .............................................................................. 158 6.2.6. Hazardous Material’s Release ....................................................................... 159 6.2.7. Data Limitations ............................................................................................. 159 6.2.8. Likely Failure Scenarios ................................................................................ 159
6.3. Quantitively Risk Assessment & Consequence Analysis ............................... 160 6.3.1. Preamble ......................................................................................................... 160 6.3.2. Weather Effect ................................................................................................ 160 6.3.3. Incidents Impacts ........................................................................................... 161 6.3.4. Consequential Impacts .................................................................................. 161 6.3.5. Other Hazards: ............................................................................................... 162 6.3.6. Process hazards and Control ........................................................................ 164 6.3.7. General hazards and controls ....................................................................... 165 6.3.8. Safe Practice for Handling, Storage, Transportation and Unloading of
Hazardous Chemicals .................................................................................... 168 6.3.9. Occupational Health Surveillance Programme ............................................ 169 6.3.10. Treatment of Workers Affected by Accidental Spillage of Chemicals ........ 172 6.3.11. Antidotes ........................................................................................................ 173 6.3.12. Details of fire extinguishers .......................................................................... 177 6.3.13. Minimization of the manual handling of hazardous substance .................. 178 6.3.14. DO’S AND DONT’S ......................................................................................... 178 6.3.15. Hazard Identification and Risk Assessment (HIRA) ..................................... 182
6.4. Conclusion & Recommendations ..................................................................... 184 CHAPTER 7. DISASTER MANAGEMENT PLAN ............................................................... 186
7.1. Disaster Management Plan ................................................................................ 186 7.1.1. Definitions ......................................................................................................... 187 7.1.2. Objective of the Disaster Management Plan ................................................... 187
7.2. Emergency Preparedness and Response System ........................................... 189 7.3. Emergency Organization ................................................................................... 190
7.3.1. Incident Controller ............................................................................................ 190 7.3.2. Site Main Controller .......................................................................................... 191 7.3.3. Other Key Personnel ........................................................................................ 192 7.3.4. Emergency Control Centre .............................................................................. 193 7.3.5. Fire & Toxicity Control Arrangements ............................................................ 194 7.3.6. Medical Arrangements ..................................................................................... 194 7.3.7. Transport & Evacuation, Mutual Aid Arrangements: ..................................... 194
7.4. Communication System .................................................................................... 194 7.4.1. Declaring the Emergency ................................................................................. 194 7.4.2. Internal Communication ................................................................................... 196 7.4.3. Communication to the Authorities .................................................................. 196
7.5. Pre-emergency activities ................................................................................... 197 7.5.1. Evacuation and Transportation ....................................................................... 198 7.5.2. Safe Close Down .............................................................................................. 198 7.5.3. Use of Mutual Aid ............................................................................................. 198 7.5.4. Use of External Authorities .............................................................................. 198 7.5.5. Medical Treatment ............................................................................................ 198 7.5.6. Accounting for Personnel ................................................................................ 198 7.5.7. Access to Records ........................................................................................... 198 7.5.8. Public Relations ................................................................................................ 198 7.5.9. Rehabilitation .................................................................................................... 199
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
4
7.6. Causes of Emergency:....................................................................................... 199 7.6.1. Risk .................................................................................................................... 199
7.7. Off-Site Emergency Plan ................................................................................... 201 7.7.1. Need of the Site Emergency Plan .................................................................... 201 7.7.2. Structure of the Off-Site Emergency Plan ....................................................... 202 7.7.3. Role of the Factory Management ..................................................................... 202 7.7.4. Role of Emergency Co-ordination Office (ECO): ............................................ 202 7.7.5. Role of Local Authority .................................................................................... 202 7.7.6. Role of Fire Authorities: ................................................................................... 202 7.7.7. Role of the Police and Evacuation Authorities: .............................................. 202 7.7.8. Role of Health Authorities ................................................................................ 203 7.7.9. Role of Mutual Aid Agencies ........................................................................... 203 7.7.10. Role of Factory Inspectorate ......................................................................... 203
7.8. Mock Drills and Records ................................................................................... 203 7.8.1. Need of Rehearsal & Training .......................................................................... 203 7.8.2. Some Check Points .......................................................................................... 203 7.8.3. Records and Updating the Plan ....................................................................... 204
CHAPTER 8. PROJECT BENEFITS ................................................................................... 205 8.1 Introduction ................................................................................................................. 205 CHAPTER 9. SUMMARY AND CONCLUSION .................................................................. 206
9.1 Introduction .............................................................................................................. 206 9.2 Conclusion and Recommendations ........................................................................ 208
CHAPTER 9. DISCLOUSER OF CONSULTANT ................................................................ 209
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
5
List of Tables
Table 1.1 ToR Compliance Status ................................................................................................................ 25
Table 2.1 Details of Environmental Setting (10 km Radius) ........................................................................ 44
Table 2.2 List of Proposed Products ............................................................................................................ 48
Table 2.3 Raw Material Consumption ......................................................................................................... 48
Table 2.4 Land Breakup of Proposed Project .............................................................................................. 51
Table 2.5 Power Requirement .................................................................................................................... 52
Table 2.6 Water Consumption .................................................................................................................... 52
Table 2.7 Manpower Requirement ............................................................................................................. 53
Table 2.8 Fuel Requirement ........................................................................................................................ 54
Table 2.9 Identification of Impacts during Operation Phase ...................................................................... 54
Table 2.10 Waste Water Generation .......................................................................................................... 58
Table 2.11 Flue gas emission ...................................................................................................................... 59
Table 2.12 Hazardous Wastes and its Management .................................................................................. 59
Table 3.1 Summary of Methodology for Primary/Secondary Baseline Data Collection ............................. 64
Table 3.2 Land use of the Study Area ......................................................................................................... 72
Table 3.3 Long Term Meteorological Data of Ahmedabad ......................................................................... 75
Table 3.4 Site Specific Meteorological Data ............................................................................................... 76
Table 3.5 Ambient Air Quality Monitoring Locations ................................................................................. 78
Table 3.6 Ambient Air Quality Monitoring Results (24-hour average) ....................................................... 79
Table 3.7 National Ambient Air Quality Standards (CPCB), 2009 ............................................................... 80
Table 3.8 Ambient Noise Quality Monitoring Locations ............................................................................. 84
Table 3.9 Ambient Noise Quality in the Study Area ................................................................................... 86
Table 3.10 Applicable Noise Standards ....................................................................................................... 86
Table 3.11 Ground Water Sampling Locations ........................................................................................... 87
Table 3.12 Ground Water Quality in the Study Area .................................................................................. 88
Table 3.13 Soil Sampling Locations ............................................................................................................. 92
Table 3.14 Physicochemical Characteristics of Soil ..................................................................................... 93
Table 3.15 Traffic survey near the plant site .............................................................................................. 95
Table 3.16 Assessment of Proposed Traffic Load ....................................................................................... 95
Table 3.17 Common Tree species ............................................................................................................... 97
Table 3.18 Wild/Forest Tree species ........................................................................................................... 98
Table 3.19 Agriculture Crop ........................................................................................................................ 98
Table 3.20 Herpetofauna ............................................................................................................................ 99
Table 3.21 Birds ........................................................................................................................................... 99
Table 3.22 Mammals ................................................................................................................................. 101
Table 3.23 Village-wise Population Details ............................................................................................... 102
Table 4.1 Stack Parameters of Proposed Sources..................................................................................... 114
Table 4.2 Summary of Maximum 24-hour GLC due to the Proposed Project .......................................... 115
Table 4.3 Summary of Maximum GLC at Monitoring Locations due to the Proposed Project ................. 115
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
6
Table 5.1 Ecological Criteria & Observations ............................................................................................ 138
Table 5.2 Species suggested for plantation under Greenbelt Development Programmed ...................... 140
Table 5.3 Recurring Cost for Environmental Management ...................................................................... 140
Table 5.4 Environmental Monitoring Program ......................................................................................... 142
Table 6.1 Asiatic Products Details ............................................................................................................. 146
Table 6.2 Raw Material Bulk Storages ...................................................................................................... 147
Table 6.3 Hazards Analysis –Raw materials .............................................................................................. 149
Table 6.4 Risk Classification ...................................................................................................................... 155
Table 6.5 Effects due to Incident Radiation Intensity ............................................................................... 157
Table 6.6 Thermal Radiation Impact to Human ........................................................................................ 157
Table 6.7 Tolerable Intensities for Various Objects .................................................................................. 157
Table 6.8 Damage due to Overpressure ................................................................................................... 158
Table 6.9 Different Failure Scenarios ........................................................................................................ 159
Table 6.10 : Hazards Scenario Impact ....................................................................................................... 161
Table 6.11 Process Hazards and Controls ................................................................................................. 164
Table 6.12 General hazards and controls ................................................................................................. 165
Table 6.13 Plan of Occupational Health & Safety ..................................................................................... 170
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
7
List of Figures
Figure 1.1. Project Location ..................................................................................................................... 20
Figure 1.2. EIA Methodology ................................................................................................................... 24
Figure 2.1 Projection Location Map (Source: Google Earth) ...................................................................... 46
Figure 2.2 Plant Layout ............................................................................................................................... 47
Figure 2.3 Water Balance ............................................................................................................................ 53
Figure 2.4 Schematic Flow Diagram Of ETP ................................................................................................ 58
Figure 3.1 Location Map of 10-km Radius Study Area (Source: google earth) ........................................... 63
Figure 3.2 Road Connectivity Map of Study Area ....................................................................................... 64
Figure 3.3 Seismic Zones Map (Source: Map of India) ................................................................................ 72
Figure 3.4 Graph Showing Land Use of the Study Area (10 km Radius) ..................................................... 73
Figure 3.5 Land use/Land Cover Map of 10 Km Radial Study Zone (Source: Google earth satellite imagery)
.................................................................................................................................................................... 74
Figure 3.6 Wind Rose Diagram .................................................................................................................... 77
Figure 3.7 Air Monitoring Sampling location .............................................................................................. 79
Figure 3.8 Statistical Comparison of PM2.5 Concentration (Winter Season) ............................................. 82
Figure 3.9 Statistical Comparison of PM10 Concentration (Winter Season) .............................................. 83
Figure 3.10 Statistical Comparison of SO2 Concentration (Winter Season) ............................................... 83
Figure 3.11 Statistical Comparison of NOx Concentration (Winter Season) .............................................. 84
Figure 3.12 Noise Monitoring Sampling Location ....................................................................................... 85
Figure 3.13 Ground water Sampling Location ............................................................................................ 88
Figure 3.14 Soil Map of Ahmedabad District .............................................................................................. 91
Figure 3.15 Soil Monitoring Location Map.................................................................................................. 93
Figure 4.1 Isopleth for PM10 GLC due to operation of Proposed Project ................................................ 118
Figure 4.2 Isopleth for PM2.5 GLC due to operation of Proposed Project ............................................... 119
Figure 4.3 Isopleth for NOx GLC due to operation of Proposed Project ................................................... 120
Figure 4.4 Isopleth for SOx GLC due to operation of Proposed Project ................................................... 121
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
8
Abbreviations
AAQM : Ambient Air Quality Monitoring
BOD : Biochemical Oxygen Demand
COD : Chemical Oxygen Demand
DO : Dissolved Oxygen
CPCB : Central Pollution Control Board
GPCB : Gujarat Pollution Control Board
EIA : Environmental Impact Assessment
EMP : Environmental Management Plan
IMD : Indian Meteorological Department
KVA : Kilo Volt Ampere
KLD : Kilo Litres per day
PM : Particulate Matter
PPE : Personal Protective Equipment
TDS : Total Dissolved Solids
ZLD : Zero Liquid Discharge
MTPM : Metric Tonne per Month
PGVCL : Paschim Gujarat Vij Company Limited
NAAQS : National Ambient Air Quality Standards
EPA : Environment Protection Act
SEIAA : State Level Environmental Impact Assessment Authority
SEAC : State Level Expert Appraisal Committee
ToR : Terms of Reference
CHWTSDF : Common Hazardous Waste Treatment, Storage and Disposal Facilities
TSDF : Treatment, Storage and Disposal Facilities
SOP : Standard Operating Procedure
GLC : Ground Level Concentrations
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
9
HSE : Health, Safety & Environment
VOC : Volatile Organic Compounds
QRA : Quantitative Risk Assessment
DMP : Disaster Management Plan
CSR : Corporate Social Responsibility
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
10
List of Annexure
Annexure I: Land Documents
Annexure II: ToR Letter
Annexure III: Toposheet
Annexure IV: Undertaking for use of separate electric meter for waste water treatment
Annexure V: Lab Data
Annexure VI: MSDS of Products & Raw Materials
Annexure VII: Environmental Policy
Annexure VIII: High Court Stay Order
Annexure IX: Undertaking by the project proponent on ownership of EIA Report
Annexure X: Undertaking by the consultant regarding the prescribed ToR have been
complied
Annexure XI: Copy of Consent
Annexure XII: Layout Plan
Annexure XIII: Legal Undertaking for project located outside the notified area
Annexure XIV: Ambient Air quality at work place
Annexure XV: SOPs under Hazardous Waste Rules 2016
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
11
EXECUTIVE SUMMARY
Introduction
Asiatic Composites Ltd. (ACL) is engaged in Manufacture & Supply of composite products for
transportation, sport, chemical, railways and infrastructure sectors meeting global quality levels.
Based on a profound understanding of diverse industrial requirements, the company has
empowered its clients with customized products based on their specific requirements. Owing to
well-equipped R&D and quality laboratories with advanced characterization instruments, ACL
produce composite of highest standard of quality and consistency.
Project Proponent
M/s Asiatic Composite Limited is promoted by Mr. Vibhor M. Agrawal
Type of Project:
M/s Asiatic Composite Limited is planning to manufacture @700 MT/Month of Saturated &
Unsaturated Resins in the existing premises, located at survey no.1963/185/24-B-paiki, village:
Mankol, Tal: Sanand: Ahmedabad, Gujrat-382 110
The project falls under category ‘B’, section 5(f), INDII of EIA notification 2006 and amendment
thereof. The site is well connected with road and railway, nearest city Ahmedabad and there is no
national park, wildlife sanctuary, eco sensitive areas in surrounding 10 km radius. The project
doesn’t fall under CRZ boundaries.
Project cost:
Total Project Cost for proposed project activity is Rs. 1.5 crore.
Location of the Project Site:
Location of the project in survey no.1963/185/24-B-paiki, village: Mankol, tal: Sanand:
Ahmedabad, Gujarat-382110 has been presented in Figure 2.1. The project site is regular in
shape.
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
12
Nature and Size of the project:
M/s Asiatic Composite Limited is planning to manufacture Saturated & Unsaturated Resins in the
existing premises. The proposed production capacity will be 700 MT/Month.
Water Requirement:
The total fresh water requirement during the operation phase for the proposed facility will be 3.4
KLD. The source of water for the proposed project shall Mechanical Evaporator through ground
water (Bore well).
Waste water generation & Management:
Total Effluent generation for proposed facility will be 3.05 KLD [2.1 KLD (Domestic) + 0.95 KLD
(Industrial)], ETP shall provide for treatment of effluent having mostly inorganic salt and
maintained the zero-discharge system by providing mechanical evaporator.
Electricity Requirement:
The Total power requirement will be 100 HP. The main source of power is UGVCL. The back-up
will be provided from DG Sets having capacity of 125 KVA in case of power failure. Therefore, no
additional electricity will be required for proposed project.
Fuel Requirement & Stack details:
LDO is being used as a fuel for Thermic Fluid Heater. Diesel is being used in D.G set. Stack
height of thermic fluid heater is 12 m.
Manpower Requirement:
There will be 64 direct & 30 indirect manpower required for the proposed project. Thus, total
manpower will be 94 workers.
Solid & hazardous waste management:
Hazardous waste like Discarded drum / Container, Used / Spent oil, Distillation residue, discarded
product material (R&D) etc. will be generated and sold or disposed to GPCB authorized vendor /
recycler and / or will be disposed at TSDF.
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
13
Green Belt Development:
Total 65000 sq.m area will be providing in the premises. Suitable local plant of variety of species
are planted with adequate spacing.
Description of the Environment
Study area
The baseline quality of various components of the environment, viz. air, noise, water, land,
biology, meteorological and socio-economic is assessed within the impact zone of about 10 km
around the proposed site. The report presents the data collected during the sampling period of
three months during summer season from December’17 and February’18.
Climate of the study area
The climate of the region is classified as tropical wet and dry climate. The annual maximum
temperature is 43 ˚C in the month of May and minimum temperature is 15 ˚C in the month of
January. The average annual rainfall for the Ahmedabad as a whole is 750 mm. Most of the
rainfall is received from June to September.
Seismicity
According to the seismic-zoning map of India, the project area falls in Zone III-Moderate Risk
zone of seismicity.
Air Environment
AAQM was carried out in 8 locations on 24 hourly average bases as per guidelines of CPCB and
NAAQS within 10 km radius of the study area. PM10 and PM2.5 was found in the range of 48.1
to 54.75 μg /m3 and 33.15 to 38.15 μg /m3 respectively. SO2 found in the range of 13.4 to 17.7
μg /m3 and NOx: 13.55 to 22.65 μg /m3. The PM10, PM2.5, SO2 & NOx parameters are found
within the permissible limit as per NAAQS level.
Noise Environment
Noise can be defined as an unwanted sound. A total of 8 locations were identified for ambient
noise monitoring in the study area. The daytime varied from 47 dB(A) to 61 dB(A) and night time
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
14
noise varied of 40 dB(A) to 56 dB(A). Both daytime noise and night time noise were found within
the limit.
Water Environment
In order to establish the baseline water quality, 7 ground water samples were collected and
analyzed in the study area. The analysis result for ground water samples were within drinking
water limit as per IS 10500: 2012.
Soil Quality
Soil samples were collected from 5 locations in the study area and analyzed for physico-
Chemicals characteristics. Soil quality was found to be normal.
Particle Size: Particle sizes of the different constituents (clay, silt, sand and gravel) control the
porosity and water holding characteristic of the soil. Clay (size < 0,002mm) amount in the soil
samples is 14% to 15% and Sand (size 0.002 to 0.075mm) in the soil sample is 68% to 70%. All
the samples in the study area are free of gravel (size > 4.75mm). Analysis shows it is sandy soil
with less water holding capacity Biological Environment.
Land Use/Land Cover of the Study Area
The basic purpose of land use pattern and classification in an EIA study is to identify the manner
in which different parts of land in an area are being utilized or not utilized. Remote sensing data
provides reliable accurate baseline information for land use mapping, as it is a rapid method of
acquiring up-to-date information of over a large geological area.
Biological Environment
Biological environment includes flora and fauna including aquatic species found in the study area
of 10 km radius.
Flora: Dominant families of plants recorded in the study area are Caesalpiniaceae, Mimosaceae,
Euphorbiaceae, Cucurbitaceae, Papilionaceae.
Fauna: The various animal species in the study area are found, detailed study is given in Baseline
Chapter-3. Field observations of fauna were carried out. The commonly available mammals,
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
15
amphibians, reptiles, butterflies, dragonflies and damselflies within 10 km surroundings were
enumerated.
Socio-economic Environment:
Socio-economic data were collected from within 10 km radius of the Project site. These include
20 villages as per census of India 2011. Total Population of the Study area as per Census of
India, 2011 is 57008.The total number of Household being 11040.Total Male Population of the
Study area is 29415 and total Female Population of the Study Area is 27593. Literacy Rate of the
study area is 52.96% Distribution of male 33.58% and female literacy rate 19.38% in the study
zone is and respectively. Workers Participation Ratio of the worker population is 39.97%, non-
workers 60.03% population.
Anticipated Environmental Impacts & Mitigation Measures
Air Environment
In order to estimate the ground level concentrations due to the emission from the proposed
project, AERMOD View – Lake Environmental Software has been employed.
These predicted ground level concentrations when added to baseline scenario, the overall
scenario levels of PM10, SO2, NOx, are well within the permissible limits specified by CPCB.
VOCs and other NAAQS parameters are observed within below detectable limit, the detail
explanation is mentioned in Baseline chapter-3.
Adequate mitigation measures have been already installed to control air pollution.
Noise Environment
The major noise source includes various machines, pumps, motors, DG sets and vehicular traffic.
The noise levels were below the stipulated standards of CPCB for residential and industrial areas.
Technical and administrative measures are already implemented to minimize the noise levels that
include periodic maintenance of machinery, mandatory use of personal hearing protection
equipment with operable mufflers, oiling and lubrication, noise suppression measures such as
enclosures, buffers, greenbelt development etc.
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
16
Water Environment
The total fresh water requirement during the operation phase for the Proposed facility is 3.4 KLD.
The source of water for the proposed project shall Mechanical Evaporator through ground water
(Bore well). Total Effluent generation for proposed facility will be 3.05 KLD [2.1 KLD (Domestic) +
0.95 KLD (Industrial)], ETP shall provide for treatment of effluent having mostly inorganic salt and
maintained the zero-discharge system by providing mechanical evaporator.
Land Environment
A total of 65000 m2 area has been earmarked for the green area development. There will be little
impact envisaged due to the operation of the plant. There is no discharge of solid as well as liquid
effluent in open land. The green area development and tree plantation will help in enhancing the
aesthetics of the plant. Thus, no adverse impact is envisaged on land environment.
Biological Environment
Analysis of abiotic factors reveals that ambient air and fresh water quality will remain practically
unaffected. Hence no impact on flora and fauna is envisaged. Moreover, there are no reserve
forest, Historic places and protected areas within 10 km radius.
Socio-economic Environment
The proposed project is expected to provide direct and indirect employment opportunity to skilled
and unskilled workers. The project will contribute to the socio-economic development of the area
at the local level in turn reducing migration for employment. Hence, the proposed project will have
positive impact on the socio-economic environment.
Environmental Monitoring Program
Environmental Monitoring Program is designed for operation phase of the project for monitoring
of various environmental parameters like air, water, noise, soil and ecology etc.
Environmental Management Plan
The EMP presents the project specific guidelines on:
Environmental management strategies
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
17
Specialized engineering construction procedures in relation to environmental guidelines
of the country
Spill prevention and control
Management of wastes and hazardous Chemicals
Air, water and soil quality protection
Noise control
Soil erosion control and slope stabilization
Vegetation, wildlife and habitat protection
Socio-economic and welfare considerations
Risk and disaster management plan
To prepare a checklist for statutory compliance
Budget allocation for environment management plan.
Risk Assessment
The Risk assessment study has been conducted for all the operations involved in the project. The
study considers all the hazards associated with all the activities which will be involved. The
hazards leading to possible consequences are summarized in the chapter-6 and the risk
mitigation measures and intended safeguards are specifically mentioned in the chapter 6 in the
EIA report. The risk to personnel, process / operation is considered in the study.
Disaster Management Plan
Disaster Management Plan is prepared for identification of various hazards addressed
qualitatively and included onsite and off-site emergency plan. A Disaster Management Plan is
prepared to meet any grave emergency which can occur due to Natural Disasters such as Floods,
Earthquakes, or due to Man-Made Disasters such as Acts of war and Fires, Power failures. Details
of disaster management plan are given in the EIA report.
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
18
Project Benefits
Growth in the industrial sector creates new opportunities for employment and can also help
diversify the economy.
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
19
CHAPTER 1. INTRODUCTION AND BACKGROUND
1.1. Project Proponent & Background
Asiatic Composites Ltd. (ACL) is engaged in Manufacture & Supply of composite products for
transportation, sport, chemical, railways and infrastructure sectors meeting global quality levels.
Based on a profound understanding of diverse industrial requirements, the company has
empowered its clients with customized products based on their specific requirements. Owing to
well-equipped R&D and quality laboratories with advanced characterization instruments, ACL
produce composite of highest standard of quality and consistency.
M/s Asiatic Composite Limited is promoted by Mr. Vibhor M. Agrawal
1.2. Proposed Project
M/s Asiatic Composite Limited is planning to manufacture @700 MT/Month of Saturated &
Unsaturated Resins in the existing premises, located at survey no.1963/185/24-B-paiki, village:
Mankol, Tal: Sanand: Ahmedabad, Gujrat-382 110
The project falls under category ‘B’, section 5(f), INDII of EIA notification 2006 and amendment
thereof. The site is well connected with road and railway, nearest city Ahmedabad and there is no
national park, wildlife sanctuary, eco sensitive areas in surrounding 10 km radius. The project
doesn’t fall under CRZ boundaries.
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
20
Figure 1.1. Project Location
(Source: Map of india)
1.3. Justification of the Project
This unit M/s. ACL will be able to meet the demand of existing component plant. The unit will use
good faith efforts to employ local people from the nearby villages depending upon the availability
of skilled & un-skilled man-power surrounding the project site. In operation phase, the proposed
project would require significant work force of non-technical and technical persons. Migration of
highly education and skilled experience will result in increase of literacy in the surrounding
villages.
Project Site
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
21
1.4. Site Selection Criteria
Asiatic Composite Limited is planning to establish its manufacturing facilities at the said location
due to the following favorable conditions:
Topographic condition of the land/area.
Availability of suitable and adequate land.
Availability of common infrastructural facilities road, rail for transportation in the area.
Facilities such as power, water, communication etc. are easily available.
Availability of requisite skilled, semi-skilled and unskilled labour from local area.
Availability of good quality of raw materials with adequate quantity and proximity of market.
There is no Wildlife Sanctuary/National Park within 10 km radius of the project site.
1.5. Purpose of the Study
As per the Ministry of Environment, Forest & Climate Change (MoEF & CC), Government of India
EIA Notification 2006 and as amended on December 1, 2009, the proposed Project need to take
environmental clearance prior to commissioning of the plant. The proposed project is covered
under Category “B” as per the Schedule of EIA Notification and hence requires environmental
clearance from State Expert Appraisal Committee (SEAC), Gujarat.
This Environmental Impact Assessment (EIA) study is mainly focused on identification of existing
environmental conditions of the project & its impact on pre and post commissioning. A detailed
prediction of all environmental impacts associated with the various activities during the
construction and operation phases of the proposed project suggesting suitable measures to
navigate the observed adverse environmental impacts. The study also aims at reflecting the
acceptability of the project to different stakeholders and at incorporating the concerns raised by
them into impact assessment and of the subsequent Environmental Management Plan (EMP).
These all mentioned above are part of the Environment Impact Assessment (EIA) project Study.
1.6. Objective of EIA Study
As per provision of the EIA notification, 2006 under the Environmental (Protection) Act, 1986, new
projects can be undertaken only after obtaining an Environmental Clearance (EC). Any project
seeking an environmental clearance requires an EIA report, prepared in accordance with
guidelines of Ministry of Environment, Forests and Climate Change (MoEFCC), Government of
India.
The main objectives of the present EIA study are:
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
22
To have an in-depth know-how of the project and to identify the probable sources of
pollution that may arise due to proposed manufacturing activity of M/s. Asiatic Composite
Limited (ACL).
To assess existing environmental status of air quality, water quality, noise level, land/soil,
ecological and socio-economic components as per suggested TOR.
To identify and quantify the significant impacts of the proposed project on the environment
components.
To prepare Environmental Management Plan (EMP) and suggest preventive and
mitigative measures to minimize adverse impacts and to maximize beneficial impacts.
1.7. Regulatory Frame Work
The plant operation has been subjected to other procedural and compliance monitoring programs
viz. annual consents under Water (Prevention and Control of Pollution) Act, 1974; Air (Prevention
and Control of Pollution) Act, 1981; authorization under Hazardous Waste (Management &
Handling) Rules, 1989/ 2000; Environment (Protection) Act, 1986; requirements and statutory
norms as per Gujarat Pollution Control Board etc. The production level of this plant has been as
per the clearances/consents.
Legislation Areas / Activities Covered
Environment (Protection) Act, 1991 (as
amended) with Rules.
Overall Environment Protection Compliance to
environmental (Air, Water, Noise) Standards
issued under EPR
Air (Prevention and Control of Pollution) Act,
1987 (as amended) with Rules.
Protection of Air Quality, Consent to Establish
(CTE) for establishing and Consent to Operate
(CTO) for activities causing air pollution from
DG sets from GPCB, Compliance to National
Ambient Air Quality Standard
Water (Prevention and Control of Pollution)
Act, 1974 with Rules.
Protection of Water Quality, Discharge of
sewage from proposed project, Obtaining
Consent to Establish (NOC) for establishing
and Consent to Operate (CTE) for activities
causing water pollution from GPCB
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
23
Noise Pollution (Regulation and Control)
Rules, 2006 (as amended)
Compliance with Ambient Noise Standards in
accordance to land use of the area
The Public Liability Insurance Act,1992 (as
amended)
An Act to provide public liability- insurance for
the purpose of providing immediate relief to
the persons affected by accident while
handling any hazardous substance and for
matters connected therewith or incidental
there to
Manufacture, Storage and Import of
Hazardous Chemicals Rules, 2000 (as
amended)
Notifying regulatory authority (in this case, the
State Factories Inspectorate) of storage of
hazardous substances like Waste Oil, etc.
Follow guidance on such storage, maintain
updated MSDS, submit annual Safety Report
to authority Prepare Onsite Emergency Plan.
1.8. Scope & Methodology of the study
This study is aimed at providing a deeper insight into the proposed Expansion Project and its
various environmental components. The present study area for the environmental impact
assessment is within 10 km radius of the location of the project. The methodology used for the
study is given below:
i. Monitoring and collection of baseline data for various environmental components as per
the MoEFCC guidelines.
ii. Identification and quantification of significant environmental impacts due to the project and
associated activities.
iii. Evaluation of impacts due to proposed activities and preparation of an environmental
impact statement.
iv. Preparation of appropriate Environmental Management Plan (EMP) encompassing
strategies for minimizing identified adverse impacts along with budgetary provisions to be
made by the project authorities for implementation of mitigation measures.
v. Delineation of post Environmental Quality Monitoring Program (EQMP) along with
organizational setup required for monitoring the effectiveness of mitigation measures.
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
24
The flow diagram showing methodology adopted for the EIA study has been presented in
Figure 1.2.
Figure 1.2. EIA Methodology
1.9. Approved ToR for EIA Study by Gujarat- SEAC
The application for the scoping of the said project has been submitted to the State Expert
Appraisal Committee (SEAC), Gujarat. Presentation to SEAC for the coping of the project (Terms
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
25
of Reference (ToR) approval for EIA study) was held on 11th January, 2018, in the SEAC Meeting.
The SEAC, Gujarat vide their letter dated 16th February, 2018 had recommended to the SEIAA,
Gujarat, to grant the Terms of Reference for the proposed project. The proposal was considered
by SEIAA, Gujarat in its meeting held on 23rd February, 2018 at Gandhinagar. After careful
consideration, the SEIAA hereby accords Terms of reference to proposed project under the
provisions of EIA Notification dated 14th September, 2006. The copy of Terms of Reference is
attached as Annexure-I. The compliance to the approved TOR has been presented in Table 1.1:
Table 1.1 ToR Compliance Status
Sr.No. Point raised in ToR Compliance Reply
1 A tabular chart with index for point-wise compliance
of below mentioned TORs.
Noted and complied
accordingly.
2 Executive Summary of the project- giving a prima
facie idea of the objectives of the proposal, use of
resources, justification, etc. In addition, it should
provide a compilation of EIA report, including EMP
and the post-project monitoring plan in brief.
Complied in EIA Report
3 Justification for selecting the proposed product and
unit size.
Chapter-1, Section 1.3,
Page No. 20.
4 Land Requirement for the project including its break
up for various purposes, its availability and
optimization.
Chapter-2, Section 2.9,
Sub-section 2.9.1, Page
No. 51.
5 Land possession documents. Copy of NA order
showing permission to use the project land for
industrial purpose. If located in GIDC, copy of plot
holding certificate obtained from GIDC Authority.
Copy of land documents is
attached as Annexure-I
6 Location of the project site and nearest habitats with
distances from the project site to be demarcated on
a topo sheet (1:50000 scale).
Toposheet is given as
Annexure- III
7 Topography details of the project area. Chapter-3, Section 3.4,
Sub-section 3.4.1, Page
No. 66.
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
26
8 Geological features and geo-hydrological status of
the study area.
Chapter-3, Section 3.4,
Sub-section 3.4.3, 3.4.4 &
3.4.9, Page No. 66, 67 &
69.
9 In case of project located outside notified area: Legal
undertaking stating that unit is complying the three
conditions (i.e. water consumption less than 25
m3/day; fuel consumption less than 25 TPDl and not
covered in the category of MAH units as per the
Management, Storage, Import of Hazardous
Chemical Rules (MSIHC Rules, 1989) as per the
amendment to EIA Notification, 2006 vide SO 1599
(E) dated 25/06/2014.
The location of the unit is
outside the notified area. As
per amendment to EIA
Notification, 2006 vide SO
1599 (E) dated 25.06.2014,
small units are categorized
as Category “B” projects.
Small units are defined as
with water consumption less
than 25 m3/day. Fuel
consumption less than 25
TPD, and not covered in the
category of MAH units as per
the Management, Storage,
Import of Hazardous
Chemical Rules, 1989.
The water requirement is 3.4
KLD, fuel requirement is
LDP (<25MT/day) and
chemicals to be used are not
covered in MAH category.
Hence, the proposed
products of Resins fall under
Category B of project activity
5(f) as per the EIA
Notification, 2006.
Legal Undertaking is given
as Annexure- XIII
10 Present land use pattern of the study area shall be
given based on satellite imagery.
Chapter-3, Section 3.6,
Page No. 72.
11 Layout plan of the factory premises clearly
demarcating various units within the plant. Provision
of separate entry & exit and adequate margin all-
round the periphery for unobstructed easy
Chapter-2, Section 2.5,
Page No. 46.
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
27
movement of the emergency vehicle/ fire tenders
without reversing back. Mark the same in the plant
layout.
12 Technical details of the plant/s along with details on
best available technologies (BAT), proposed
technology and reason for selecting the same.
Chapter-2, Section 2.6,
Page No. 48.
The proposed project is
expansion project & we are
using best available
technologies for existing unit
also, hence no proposal for
alternative process or
technology.
13 Product spectrum (proposed products along with
production capacity) and processes.
Chapter-2, Section 2.6 &
2.8, Page No. 48 & 49.
14 Chemical name of each proposed product to be
manufactured. Details on end use of each product.
(Provide CAS number of all the product & raw
materials. In case of Dyes, CI number)
Chapter-2, Section 2.6,
Page No. 48.
15 Details on raw materials, source and storage within
the premises.
Chapter-2, Section 2.7,
Page No. 48.
16 Details of complete manufacturing process/
operations of each product along with chemical
reactions, process flow diagram describing each unit
processes and unit operations along with material
balance, consumption of raw materials etc.
Chapter-2, Section 2.8,
Page No. 49.
17 Details on strategy for implementation of cleaner
production activities.
Proper storage of raw materials, products and fuels
Ensuring close feeding and sampling
Establishing SOPs for startup, shut down & maintenance operational procedures.
Regular work place and
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
28
ambient air quality monitoring will be done.
18 Assessment of source of the water supply with
adequacy of the same to meet with the requirements
for the project. Permission obtained from the
concern authority for supply of raw water.
Chapter-2, Section 2.9,
Sub-section 2.9.3, Page
No. 52.
Source of water supply is
existing bore well.
19 Undertaking stating that no bore well shall be dug
within the premises (if project is located within the
Industrial estate).
Not Applicable
20 Details on water balance including quantity of
effluent generated, recycled & reused. Details of
methods to be adopted for the water conservation.
Chapter-2, Section 2.9,
Sub-section 2.9.3, Page
No. 52.
21 Efforts to minimize effluent discharge and to
maintain quality of receiving water body.
Chapter-2, Section 2.11,
Sub-section 2.11.1, Page
No. 57.
Not Applicable as our
plant will achieve ZLD.
22 Explore the possibilities for Zero Liquid Discharge
(ZLD) option for the proposed project.
Chapter-2, Section 2.11,
Sub-section 2.11.1, Page
No. 57.
23 Segregation of waste streams, characterization and
quality with specific treatment and disposal of each
stream including action plan for maximum recycle of
treated waste water and minimum discharge for
effluent.
Chapter-2, Section 2.11,
Sub-section 2.11.1, Page
No. 57.
There is no generation of
industrial process
effluents. Therefore, no
need of segregation. Only
domestic effluent will be
generated from proposed
activity, which will be
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
29
disposed to septic tank/
soak pit system.
24 Capacity of ETP in Kl/day. Details of ETP including
dimensions of each unit along with schematic flow
diagram. Inlet, transitional and treated effluent
qualities with specific efficiency of each treatment
unit in reduction in respect of all concerned/
regulated environmental parameters. Inlet effluent,
quality should be based on worst case scenario
considering production of most polluting products
that can be manufactured in the plant concurrently.
Chapter-2, Section 2.11,
Sub-section 2.11.1, Page
No. 57.
25 In case of discharge into GIDC drainage/ pipeline:
a. Copy of permission letter with quantity (KL/day)
from the concern authority of drainage network/
pipeline with confirmation for spare capacity
available to take additional effluent.
b. Characteristics of the combined effluent and
treated water to be sent to Common pipeline
with reference to the MoEFCC/CPCB/GPCB
discharge norms.
c. Provision for Continuous Monitoring System for
waste water discharge.
Not Applicable as no
discharge in GIDC
drainage/pipeline
26 In case of waste water sent to Common Facilities
(CF) like CETP, MEE, Spray Dryer etc.
a. Details of Common facilities including (1) Total
capacity of the CF (2) Copy of CC&A of the CF,
(3) Actual load at present (Qualitative and
Quantitative- KL per day) (4) capacity of CF (5)
Copies of XGN generated Inspection reports
with analysis reports of the water/Air/
Hazardous samples collected by GPCB (Last 2
Years). Copies of instructions issued by GPCB
in last 2 years and point wise compliance
Not applicable as
proposed project is ZLD.
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
30
thereof. (6) Copies of Show-cause notices,
closure notices etc. served by the GPCB and its
compliance (7) Recommendations and
suggestions of the last two Environment Audit
reports of CETP and its compliance report. (8)
Common Facility Up gradation scheme, if any.
b. Status of compliance to the 18(1) (b) direction
issued by the CPCB with respect to CETP
compliance & CEPI area action plan along with
relevant supportive documents.
c. Give status of compliance of Environment
norms of existing common infrastructure i.e.
CETP, MEE & Spray Dryer (Whichever is
applicable) in which you are a member.
d. Submit adequacy of Common Infrastructure i.e.
CETP, MEE & Spray Dryer for additional load
(whichever is applicable) along with written
confirmation/ membership certificate
mentioning the same (total consented quantity,
total quantity booked so far, quantity book for
the unit, spare quantity available).
27 In case of Zero Liquid Discharge (ZLD):
a. Action plan for ‘Zero’ discharge of effluent shall
be included. Notarized undertaking for assuring
that underground drainage connection will not
be taken in the unit and there shall be no effluent
discharge outside the plant premises.
b. Economical and technical viability of the effluent
treatment system to achieve Zero Liquid
Discharge (ZLD)
c. Certification of adequacy of proposed ZLD
scheme through credible institutes of National
repute.
Chapter-2, Section 2.11,
Sub-section 2.11.1, Page
No. 57.
Industrial effluent will be
treated in ETP followed by
RO system. RO permeate
will be reused and RO reject
will be evaporated.
Domestic effluent will be
generated from proposed
activity, which will be
disposed to septic tank/
soak pit system.
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
31
d. To estimate & monitor ground water quality & its
contamination status, piezometer wells, one on
up gradient of the groundwater flow and other
three on the down gradient side of the ground
water flow of the proposed project at different
depth based on available ground water depth
shall be established and all the parameters
mentioned in IS 10:500 for potable water
standard shall be monitored.
28 In case of in-house MEE/ Spray dryer for waste
water treatment:
Capacity of MEE/ Spray dryer in KL/hr. Technical
details of MEE including evaporation capacity,
stream required for evaporation, adequacy of the
proposed boiler to supply steam for evaporation in
addition to the steam required for the process etc.
Techno-economical viability of the evaporation
system. Control measures proposed for the
evaporation system in order to avoid/ reduce
gaseous emission/ VOC from evaporation of
industrial effluent containing solvents & other
chemicals.
Not Applicable
29 Technical details of ATFD/ Crystallizer/ Spray dryer,
Ro/NF system etc. (if any)
ATFD/Crystallizer is not
proposed.
Chapter-2, Section 2.11,
Sub-section 2.11.2, Page
No. 59.
Capacity of R.O. – 1 KL/Hr
Capacity of Spray Dryer –
1.5 Ton/Hr
30 Undertaking stating that a separate electric meter
will be provided for the waste water treatment
Undertaking is given as
Annexure- IV
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
32
system viz. ETP, RO, MEE, Spray Dryer etc.
(whichever is applicable).
31 Economical and technical viability of the effluent
treatment system.
Chapter-2, Section 2.11,
Sub-section 2.11.1, Page
No. 57
32 Plans for management, collection and disposal of
waste streams to be generated from spillage,
leakages, vessel washing, used container washing
etc. Measures proposed for preventing effluent
discharge during unforeseen circumstances.
Chapter-5, Section 5.4.2,
Page No. 135.
33 Action plan for reuse of liquid waste streams like
Spent acids, Poly Aluminum Chloride etc. within
premises to convert into valuable products instead
of sending outside to actual end-users.
Not Applicable
34 Adequacy of the proposed EMS with respect to the
pollution load envisaged in terms of Air, Water and
hazardous waste.
Chapter-5, Section 5.4,
Page No. 133.
35 One season Site-specific micro-meteorological data
using temperature, relative humidity, hourly wind
speed and direction and rainfall should be
incorporated.
Chapter-3, Section 3.7,
Page No. 74.
36 Anticipated environmental impacts due to the
proposed project/production may be evaluated for
significance and based on corresponding likely
impacts VECs (Valued Environmental Components)
may be identified baseline studies may be
conducted within the study are for all the concerned/
identified VECs and likely impacts will have to be
assessed for their magnitude in order to identify
mitigation measures.
Chapter-4, Section, 4.2 &
4.3, Page No. 109 & 112.
37 One complete season baseline ambient air quality
data (except monsoon season) to be given along
Chapter- 3, Section 3.8.,
Page No. 77.
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
33
with the dates of monitoring. The parameters to be
covered shall be in accordance with the revised
National Ambient Air Quality Standards (NAAQS) as
well as project specific parameters like NH3, HCl,
Cl2, HBr, VOC etc. Locations of the monitoring
stations should be so decided so as to take into
consideration the pre-dominant downwind direction,
population zone and sensitive receptors. There
should be at lEast one monitoring station in the
upwind direction. There should be at lEast one
monitoring station in the pre-dominant downwind
direction at a location where maximum ground level
concentration is likely to occur.
We have carried out
baseline monitoring from
December, 2017 to
February, 2018.
Monitoring lab reports are
given in Annexure V.
38 Modeling indicating the likely impact on ambient air
quality due to proposed activities. The details of
model used and input parameters used for modeling
should be provided. The air quality contours may be
shown on location map clearly indicating the location
of sensitive receptors. If any, and the habitation. The
wind rose showing pre-dominant wind direction
should also be indicated on the map. Impact due to
vehicular movement shall also be included into the
predication using suitable model. Results of air
dispersion modeling should be superimposed on
satellite image/ geographical area map.
Chapter- 4, Section 4.3,
Sub-section 4.3.1, Page
No. 112.
39 Base line status of the Noise environment, impact of
noise on present environment due to the project and
proposed measures for noise reduction including
engineering controls.
Chapter-3, Section 3.9,
Page No. 84.
40 Specific details of
a) Process gas emission from each unit process
with its quantification.
Chapter-2, Section 2.9,
Sub section 2.9.5 &
2.11.2, Page No. 54 & 59.
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
34
b) Air pollution control measures (APCM)
proposed for process gas emission. Adequacy
of the air pollution control measures (APCM) for
process gas emission measures to achieve the
GPCB norms.
c) Details of the utilities required.
d) Type and quantity (MT/hr & MT/ day) of fuel to
be used for each utility.
e) Flue gas emission rate emission from each
utility.
f) Air Pollution Control Measures (APCM)
proposed to each of the utilities along with its
adequacy.
g) List of project specific sources of fugitive
emission along with its quantification and
proposed measures to control it.
h) Details on tail gas treatment. (if any)
41 Provision of CEMS (Continuous Emission
Monitoring System).
Not Applicable
42 Action Plan for odor control to be submitted. Not Applicable
There would be no odour
generation in the proposed
project.
43 Management plan for hazardous/ solid waste
including storage, handling, utilization and safe
disposal as per the hazardous and other waste
(management and transboundary movement) Rule,
2016. CPCB guidelines in respect of specific
treatment, such as solar evaporation, incineration,
etc., need to be followed.
Chapter-2, Section 2.11,
Subsection 2.11.3, Page
No. 60 & Chapter- 5,
Section 5.4, 133.
44 How the manual handling of the hazardous wastes
will be minimized? Methodology of de-contamination
Chapter- 6, Section 6.3,
Sub-section 6.3.13, Page
No. 178.
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
35
and disposal of discarded containers and its record
keeping.
45 Management of by-product which fall under the
purview of the hazardous and other wastes
(Management and Transboundary Movement) Rule,
2016 as per the said rules and necessary
permissions from the concern authority.
Not Applicable.
There is no by product
generation in
manufacturing process.
46 Membership of Common Environment infrastructure
like TSDF, Common Incineration Facility (CHWIF),
MEE, Spray Dryer etc.
We will take membership
of TSDF site after getting
EC.
47 Name and quantity of each type of solvents to be
used for proposed production. Details of in-house
solvent recovery system including mass balance,
solvent loss, recovery efficiency (%recovery),
feasibility of reusing the recovered solvents etc. for
each type of solvent.
Not Applicable
There is no such use of
solvent during the process
from which spent solvent
is generated and thus
there is no need of any
solvent recovery system.
48 Appropriate monitoring network has to be designed
and proposed, to assess the possible residual
impacts on VECs.
Unit will adopt monitoring
network proposed in
Chapter- 5, Section 5.7,
Page No. 141.
49 A detailed EMP including the protection and
mitigation measures for impact on human health and
environment as well as detailed monitoring plan and
environmental management cell proposed for
implementation and monitoring of EMP. The EMP
should also include the concept of waste-
minimization, recycle/ recover techniques, energy
conservation, and natural resource conservation.
Total capital cost and recurring cost/ annum
earmarked for environment pollution control
measures.
Chapter- 5, Section 5.4 &
5.7, Page No. 133 & 141.
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
36
50 Details of in-house monitoring capabilities and the
recognized agencies if proposed for conducting
monitoring.
Chapter- 5, Section 5.7,
Page No. 141.
51 Permission from PESO, Nagpur for storage of
solvents, other toxic chemicals, if any.
Not Applicable
52 Occupational health impacts on the workers and
mitigation measures proposed to avoid the human
health hazards along with the personal protective
equipment to be provided. Provision of industrial
hygienist and monitoring of the occupational injury to
workers as well as impact on the workers. Plan for
periodic medical check-up of the workers exposed.
Details of work place ambient air quality monitoring
plan as per Gujarat Factories rules.
Chapter- 2, Section 2.13,
Page No. 61 & Chapter- 6,
Section 6.3, Sub-section
6.3.6, 6.3.7, 6.3.9, Page
No. 164, 165 & 169.
Details of work place
ambient air quality
monitoring plan as per
Gujarat Factories rules is
given as Annexure- XIV
53 Details on volatile organic compounds (VOCs) from
the plant operations and occupational safety and
health protection measures. Proposal for Leak
Detection and Repair (LDAR) program as per the
CPCB guidelines.
NA
54 Risk Assessment including prediction of the worst-
case scenario and maximum credible accident
scenarios should be carried out. The worst-case
scenario should take into account the maximum
inventory of storage at site at any point of time. The
risk contours should be plotted on the plant layout
map clearly showing which of the facilities would be
affected in case of an accident taking place. Based
on the same, proposed safeguard measures
including On site/ off site Emergency Plan should be
provided.
Chapter- 6, Section 6.2 &
Section 6.3, Page No. 144
& 160.
Chapter- 7, Section 7.2 to
7.7, Page No. 189 to 201.
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
37
55 MSDS of all the products and raw materials MSDS of all the products
and raw materials is given
as Annexure- VI
56 Details of hazardous characteristics and toxicity of
raw materials and products to be handled and the
control measures proposed to ensure safety and
avoid the human health impacts. This shall include
the details of Antidotes also.
Chapter- 6, Section 6.3,
Subsection 6.3.5, 6.3.6,
6.3.7 & 6.3.11, Page No.
162, 164, 165 & 173.
57 Details of quantity of each hazardous chemical
(including solvent) to be stored, materials of
construction (MoC) of major hazardous chemical
storage tanks, dyke details, threshold storage
quantity as per schedules of the Manufacture,
Storage & Import of Hazardous Chemicals Rules of
major hazardous chemicals, size of the biggest
storage tank to be provided for each raw material &
product etc. How the manual handling of the
hazardous chemicals will be minimized?
Chapter- 6, Section 6.2 &
Section 6.3, Sub section
6.3.8 & 6.3.13, Page No.
168 & 178.
58 Details of the separate isolated storage area for
flammable chemicals. Details of flame proof
electrical fittings, DCP extinguishers and other
safety measures proposed. Detailed fire control plan
for flammable substances and processes showing
hydrant pipeline network, provision of DG sets, fire
pumps, jockey pump, toxic gas detectors etc.
Chapter- 6, Section 6.3,
Sub section 6.3.8, 6.3.12,
Page No. 168 & Chapter-
7, Section 7.3, Sub section
7.3.5, Page No. 194
59 Submit checklist in the form of Do’s & Don’ts of
preventive maintenance, strengthening of HSE,
manufacturing utility staff for safety related
measures.
Chapter- 6, Section 6.3,
Sub section 6.3.14, Page
No. 178.
60 Specify safety precautions to be taken for Chemical
storage, process, handling and transportation
hazards.
Chapter- 6 , Section 6.3,
Sub section 6.3.8, Page No.
168.
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
38
61 Details on workers training before engaging work,
periodical, in-house, outside etc.
Chapter-2, Section 2.13,
Page No. 61.
62 Details on various SOP to be prepared. SOPs will be prepared as
per GPCB guidelines.
Guidelines are given in
Annexure XV.
63 Details on safety audit to be carried and their
compliance status.
After getting EC, safety
audit shall be carry out once
in a year.
64 Specific safety measures to be taken for general
public living in the vicinity.
Chapter-7, Section 7.2,
Page No. 189.
65 Details on hazard identification i.e. HAZOP, HAZAN,
fault tree analysis, event tree analysis, checklist,
audits etc. to be adopted for the safety operation of
the plant.
Chapter-6, Section 6.3,
Sub section 6.3.15, Page
No. 182.
66 Detection and monitoring of VOC’s’ /gases. Chapter – 5, Section 5.7,
Page No. 141.
67 Detailed five-year greenbelt development program
including annual budget, planning schedule,
species, width of plantations, number of trees to be
planted, area under green belt development (with
map), budgetary outlay etc. along with commitment
of the management to carry out the tree plantation
activities outside the premises at appropriate places
in the nearby areas and elsewhere.
Chapter- 5, Section 5.4,
Sub section 5.4.2, Page
No. 135.
68 Action plan for green belt development- species,
width of plantations, planning schedule, etc., in
accordance to CPCB published guidelines.
Chapter- 5, Section 5.4,
Sub section 5.4.2, Page
No. 135.3
69 Detailed socio-economic development measures
including community welfare program most useful in
the project area for the overall improvement of the
environment. Submit a detailed plan for social
corporate responsibilities, with appropriate
Chapter- 5, Section 5.4,
Sub section 5.4.2, Page
No. 135.
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
39
budgetary provisions for the next five years and
activities proposed to be carried out specific to the
current demographic status of the area.
70 (a) Does the company have a well laid down
Environment Policy approved by its Board of
Directors? If so, it may be detailed in the EIA
report.
(b) Does the Environment Policy prescribe for
standard operating process/ procedures to bring
into focus any infringement/ deviation/ violation
of the environmental / forest norms/ conditions?
If so, it may be detailed in the EIA.
Environmental Policy is
given as Annexure VII
71 What is the hierarchical system or administrative
order of the company to deal with the environmental
issues and for ensuring compliance with the EC
conditions? Details of this system may be given.
Environmental Cell of ACL
will take care of all
compliance related
issues.
72 Does the company have a system of reporting of
non-compliances/ violations of environmental norms
Yes. Environmental Cell of
ACL will take care of all
compliance related
issues.
73 Phase wise project implementation schedule with
bar chart and time frame, in terms of site
development infrastructure provision, EMS
Implementation etc.
After obtaining
/Environmental Clearance
for proposed project,
installation will be
completed within 6-8
months.
EMS is given in Chapter-
5, Section 5.4, Page No.
133.
74 Certificate of accreditation issue by the NABET, QCI
to the environmental consultant should be
incorporated in the EIA report.
Hon’ble High Court Stay
Order copy is attached as
Annexure VIII
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
40
75 An undertaking by the project proponent on the
ownership of EIA report as per the MoEFCC OM
dated 05/10/2011 and an undertaking by the
consultant regarding the; prescribed ToRs have
been complied with and the data submitted is
factually corrected as per the MoEFCC, OM dated
04/08/2009
Undertaking by the project
proponent on the
ownership of EIA report is
given as Annexure IX
Undertaking by the
consultant regarding the;
prescribed ToRs have
been complied is given as
Annexure X
76 All documents to be properly referred with index and
continuous page numbering
Noted and complied
accordingly
77. Where data are presented in the Report especially
in Tables, the period in which the data were collected
and the sources should be indicated.
Noted
78 Project proponent shall enclose all the analysis/
testing reports of water, air, soil, noise etc. using the
MoEFCC or NABL accredited laboratories. All the
original analysis/ testing reports should be available
during appraisal of the project.
Lab reports are given as
Annexure V
79 In case of expansion of the project
a. Need for the proposed expansion should be
justified in detail.
b. Adequacy of existing EMS
c. Explore the possibility to achieve zero liquid
discharge for existing as well as proposed
activities.
d. Records of any legal breach of
environmental law
e. Copies of environmental clearance obtained
for the existing plant, its point wise
compliance report.
f. Environmental audit report for last 3 years
Need for the proposed
expansion is given
Chapter- 1, Section 1.3,
Page No. 20.
ZLD details are given in
Chapter- 2, Section 2.11,
Sub-section 2.11.1, Page
No. 57.
There is no legal breach of
environmental law against
ACL.
Copy of Environmental
Clearance is not applicable
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
41
and compliance of its recommendations/
suggestions
g. Copy of consent to operate (CC&A) obtained
along with point wise compliance status of all
the conditions
h. Compliance of MoEFCC circular vide No. J-
11011/618/2010-IAII (I) dated 30/05/2012
and J-11013/41/2006-IAII (I) dated
20/10/2009
i. Copies of XGN generated inspection reports
with analysis reports of the
water/air/hazardous samples collected by
GPCB (2 years). Copies of instruction issued
by GPCB in last 2 year and point wise
compliance thereof.
because manufacturing
process of existing unit did
not fall under EIA
Notification, 2006.
Copy of Consent &
compliance copy is given as
Annexure XI
80 In case of project is located in Ankleshwar- Panoli,
Vatva-narol & Vapi GIDC.
Not Applicable
Additional Information required by SEIAA, Gujarat
1. Adequacy of the proposed area with respect to plant
machineries, EMS, green belt, safety aspect, raw
material & product storage considering worst case
scenario. Submit proper lay out plan clearly
demarcating all activities with scale.
Proper EMS system will be
followed by ACL. Details of
EMS is given in Chapter 5.
Worst case scenario of raw
material and product is given
in Chapter- 6, Section 6.3,
Page No. 160.
Layout of the ACL is given as
Annexure XII
2. Public hearing shall be carried out as per the EIA
Notification 2006. A tabular chart for the issues
raised and addressed during public
hearing/consultation and commitment of the project
proponent on the same should be provided. An
action plan to address the issues raised during
Noted. Point wise Public
hearing compliance will be
incorporated in EIA after
Public hearing proceeding.
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
42
public hearing and the necessary allocation of funds
for the sane should be provided.
3. Action plan for ZLD considering worst case scenario. Chapter 2, section 2.11, sub
section 2.11.1, Page No. 57.
1.10. Structure of the Report
This EIA report has been prepared on the basis of available on-site primary data
(survey/monitoring) and secondary/literature data. The EIA report contains project features,
baseline environmental setup, assessment of environmental impacts, and formulation of
mitigation measures, environmental management and monitoring plan with risk & disaster
management plan.
The report would include 9 Chapters excluding Executive Summary, which is included at the
beginning of the report. The structure of the EIA Report with necessary tables, drawings and
annexure is as follows:
Chapter 1: Introduction & Background
This chapter provides background information on need of project, need of EIA study and brief of
the project. The scope and EIA methodology adopted in preparation of EIA report have also been
described in this Chapter. It also covers the identification of project & project proponent, brief
description of nature, size, and location of the project.
Chapter 2: Project Description
This chapter deals with the project details of the proposed Plant, with type of project, need for the
project, location, size & magnitude of operation including associated activities required by and for
the project, proposed schedule for approval and implementation, technology and process
description including technical details of raw material, quality and quantity etc.
Chapter 3: Description of the Environment
This chapter presents the existing environmental status of the study area around the proposed
project including topography, drainage pattern, water environment, geological, climate, transport
system, land use, flora & fauna, socio-economic aspects, basic amenities etc. Environmental
assessment of the proposed project site in regard to its capability to receive the proposed new
development is also discussed in this Chapter.
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
43
Chapter 4: Impact Assessment and Prediction
This chapter describes the overall impacts of the proposed project activities and underscores the
areas of concern, which need mitigation measures. It predicts the overall impact of the proposed
project on different components of the environment viz. Air, Water, Land, Noise, Biological, and
Socio-Economic.
Chapter 5: Environmental Management Plan and Environmental Monitoring Program
This chapter details the inferences drawn from the environmental impact assessment exercise. It
describes the overall impacts of the proposed activities during construction and operation phases
and underscores the areas of concern, which need mitigation measures. It also provides
mitigation and control measures for environmental management plan (EMP) for minimizing the
negative environmental impacts and to strengthening the positive environmental impacts of the
proposed project. Technical aspects of monitoring the effectiveness of mitigation measures have
been given in this Chapter.
Chapter 6: Hazard Evaluation and Risk Assessment
This chapter details the risks associated with the project activities and storage of hazardous
chemicals.
Chapter 7: Disaster Management Plan
This chapter provides the proposed on-site emergency plan to handle any emergency situation
at the plant site.
Chapter 8: Summary & Conclusion
This chapter provides the summary and conclusions of the EIA study of the proposed project with
overall justification from implementation of the project and also explanation of how, adverse
effects will be mitigated.
Chapter 9: Disclosure of Consultants Engaged
This chapter provides the disclosure of consultants engaged to carry out the EIA study along with
other additional studies.
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
44
CHAPTER 2. PROJECT DESCRIPTION
2.1. About the Project
M/s Asiatic Composite Limited is a proposed project located at is planning to manufacture @700
MT/Month of job work of spraying materials, located at survey no.1963/185/24-B-paiki, village:
Mankol, tal: Sanand: Ahmedabad, Gujarat-382110.
Table 2.1 Details of Environmental Setting (10 km Radius)
Particular Details
Plot No. 1963/185/24-B-paiki
Location village: Mankol, tal: Sanand
District Ahmedabad, Gujarat-382110
Latitude/Longitude 22° 54’ 24.44” N, 72° 14’ 48.48” E
Elevation 38 meters (124 feet)
Defense Installations No Defense installations within 10 km radius
Ecological Sensitive Areas/ Protected Areas as
per Wildlife Protection Act 1972 (National
Parks / Wild life sanctuaries / bio-sphere
reserves / tiger reserves)
Not applicable
Reserved/Protected Forest Not Applicable
Nearest National Highway NH-8 ~ 30.5 Km
Nearest Water Body Gadhiya Lake ~16.67
Nearest Rail Head Mankol: (2 km)
Sanand (6.12 km)
Nearest Airport Ahmedabad (70.90 km)
Nearest Town/ Tourist Place Nearest Town: Sanand (6.12 km) Nearest city:
Ahmedabad (38.62 km, Rly Station)
Nearest Municipal Corporation Local body: Gram Panchayat
Address: Mankol Village, Tal Sanand, Dist
Ahmedabad-382110
Seismic Zone Zone-III (Less Active)
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
45
2.2. Components of the Project
For comprehensive analysis of the proposed expansion project, the components of the project
are summarized hereunder, detailed study of which is necessary for complete Environmental
Impact Assessment study:
Building Construction to accommodate the proposed activities;
Installation and commissioning of the Infrastructure facilities.
Use of Natural resources for operation of the Project (water, fuel)
Use, storage, transport, handling or production of substances or materials, i.e. raw
materials, products and manufacturing processes;
Generation, collection, treatment and discharge of industrial effluent;
Release of pollutants or any hazardous, toxic or noxious substances to air i.e. flue gas
emissions and process emissions;
Production of solid wastes, hazardous waste and non-hazardous waste, during
commissioning, operation or decommissioning;
Risks during commissioning or operation of the proposed project, which may affect human
health or the environment.
Impacts on Ecological and social environment
Employment generation and trade opportunities
Corporate Social Responsibilities of the proponent and proposed welfare activities
2.3. Proposed Schedule of Approval and Implementation
The proposed project will be started after getting Environmental clearance from SEAC, Gujarat &
CTE from GPCB. We shall start construction after getting environmental clearance and consent
to establish.
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
46
2.4. Location of the Project
Location of the project in survey no.1963/185/24-B-paiki, village: Mankol, tal: Sanand:
Ahmedabad, Gujarat-382110 has been presented in Figure 2.1. The project site is regular in
shape.
Figure 2.1 Projection Location Map (Source: Google Earth)
2.5. Layout of the project site
Point Latitudes Longitudes
A 22° 54’ 24.44” N 72° 14’ 48.48” E
Site layout plan of the project site showing demarcation of existing and proposed plant facilities
is presented in Figure 2.2.
The study area of 10 km aerial radius demarcated on google earth imagery is given in chapter3.
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
47
Figure 2.2 Plant Layout
(Source: Asiatic Composite ltd)
2.6. List of Proposed Products
The product details are given below:
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
48
Table 2.2 List of Proposed Products
Sr.
No.
Name of the
Products
CAS
No.
Quantity MT/Month End-use of product
Existing Proposed Total
1 FRP Tank,
Pultrsion Profile,
FR Sheet
-
600 - 600 Furniture
2
Unsaturated
Polyester Resins
9003-
01-4
-
700
700
FRP, Lamination,
Adhesive, Binding
3 Saturated Polyester
Resins
61926-
16-7
FRP, Lamination
2.7. Raw Material & Storage
The raw material details are given below:
Table 2.3 Raw Material Consumption
Name of
Product Name of Raw Material
Quantity
(Existing)
(MT/ MT)
Storage
FRP Tank
Resin (Iso resin/vinyl Easter resin) 0.60 Drum
Mat 0.35
Hardener (Tert-Butyl peroxybenzoate) /
(Methyl ethyl ketone peroxide ) 0.05
Pultrsion
Profile
Resin (General purpose resin/Isopthalic
resin) 0.22
Roving 0.40
Filar 0.20
Hardener (Methyl ethyl ketone peroxide) 0.015
Pigment (Zinc Oxide) 0.015
Mat 0.15
FR Sheet
Resin (Iso resin/vinyl Easter resin) 0.65
Mat 0.30
Hardener (Cobalt octate 3%) 0.035
Pigment (Antimony Oxide/Zinc Oxide) 0.015
Unsaturated
Polyester
Resins
Maleic Anhydride 0.169
Acid anhydride (Phthalic Anhydride)
0.19
Glycol (Propylene Glycol/ Neo Pentyl Glycol) 0.20
PET Flakes 0.13
Styrene Monomer 0.371
Additives 0.0006
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
49
Name of
Product Name of Raw Material
Quantity
(Existing)
(MT/ MT)
Storage
Saturated
Polyester
Resins
Glycol (Di Ethylene glycol/Polyethylene
glycol) 0.197
Glycol (Mono Ethylene glycol/ Neo pentyl
Glycol) 0.197
Iso Phthalic Acid/Poly (Tere Phthelic)acid 0.424
Styrene 0.182
2.8. Manufacturing Process
a) Un Saturated Polyester Resins
Raw materials (e.g. anhydrides and glycols) are charged into the reaction vessel. Then, the
reaction vessel is heated up to first to 160 °C and then up to 220°C under vacuum. During the
reaction, the water and unsaturated polyester are produced. The water is continuously
separated from reactor and collected into the distillate tank. Then water is sent to ETP plant for
further treatment of water.
The produced product in reactor is further cooled down and then whole mass is transferred to
mixing vessel containing styrene monomer which is further cooled down to 40 °C. Then, the
finished product is packed in MS/HDPE drums or HDPE carboys.
Process flow:
Process flow Diagram of Un Saturated Polyester Resins
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
50
Mass balance
Input Quantity (Kg) Output Quantity (Kg)
Malic Anhydride 847 Liquid 311
Acid Anhydride 1279 Solid(Product) 5000
Glycol (MEG,
DEG, PG, NPG)
1327
Styrene
monomer
1855
Additives 3
Total 5311 Total 5311
b) Saturated Polyester Resins
Raw materials (e.g. oil, anhydrides and glycols) are charged into the reaction vessel. Then, the
reaction vessel is heated up to first to 160 °C and then up to 200°C under vacuum. During the
reaction, the water and resin are produced. The water is continuously separated from reactor
and collected into the distillate tank. Then water is sent to ETP plant for further treatment of
water.
The produced product in reactor is further cooled down and then whole mass is transferred to
discharged trays. Afterwards, the product is crushed, pulverized and packed in bags.
Process Flow
Process flow Diagram of Saturated Polyester Resins
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
51
Mass Balance
Input Quantity (Kg)
Output Quantity (Kg)
DEG/PG 394 liquid 120
MEG/PEG 394 Solid(Product) 2000
IPA/PTA 849
Styrene 483
Total 2120 Total 2120
2.9. Resource Requirement
2.9.1. Land Requirement
Land use: Industrial purpose for proposed project of manufacturing of Resins.
Land Ownership: Private land, M/s. Asiatic Composite Limited is promoted by Mr. Vibhor M. Agarwal.
Table 2.4 Land Breakup of Proposed Project
Sr.
No. Details of Land
Area
For Proposed Plant (m2)
1 Net Plot Area Required (Proposed Project) 1249.02
Net Plot Area (Existing and proposed) 2,12,056
Land Use Bifurcation of proposed project
1 Main Plant Building (Production Area) 1107
2 Storage Area 39
3 Utility Area (Boiler & Cooling Tower) 15
4 Plant Office 19.02
5 Laboratory 20
6 ETP 49
Total Area 1249.02
2.9.2. Power Requirement
Electricity shall be obtained from UGVCL. The total power for the proposed project are given
below:
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
52
Table 2.5 Power Requirement
Sr.
No.
Electricity
(HP)
Total
(HP) Source of Supply
1 100 100 UGVCL
Back up: DG Set (125 KVA- existing)
2.9.3. Water requirement
The source of water for the proposed project shall meet through Existing Bore Well Supply.
Table 2.6 Water Consumption
Category Existing (KLD) Proposed
(KLD)
Total (KLD)
A. Domestic 2.5 0.2 2.7
B. Gardening Reuse of STP
treated water
- Reuse of STP
treated water
C. Industrial
Process Nil Nil Nil
Washing Nil Nil Nil
Boiler/ Cooling 0.2 0.5 0.7
Total 2.7 0.7 3.4
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
53
Figure 2.3 Water Balance
(Source: Asiatic composite ltd)
2.9.4. Manpower Requirement
Table 2.7 Manpower Requirement
Particulars Existing Proposed Total
Direct 61 3 64
Indirect 20 10 30
2.9.5. Fuel Requirement
LDO shall be used as a fuel for Boiler. Diesel will be used as a fuel for D.G set. The total fuel
requirement for the proposed project are given below:
Fresh water
consumption
Domestic 2.7 KLD
2.5 KLD (Existing) 0.2 KLD (Proposed)
Industrial
NIL
Process NIL
Washing
NIL
Boiler/Cooling 0.7 KLD
STP 2.1 KLD
Gardening
1.68 KLD Condensat
e
ETP
0.95 KLD
RO Rejected/Evaporation
0.25 KLD
Reject
0.088 KLD
0.7 KLD
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
54
Table 2.8 Fuel Requirement
Sr.
No.
Stack attached to Type of fuel Fuel quantity
1 Thermic Fluid Heater LDO 25 Lit/hr
2 D.G. Set (125 KVA)
(existing)
Diesel 7 Lit/hr
2.10. Capital Investment
Total Project Cost for proposed project activity is Rs. 1.5 crore.
2.11. Pollution Potential and Its Control Measures
Table 2.9 Identification of Impacts during Operation Phase
Activity Environmental
Attribute
Cause Impact characteristic
Nature Duration Reversibility Intensity and
Significance
Vehicle
Movement
and utilities
operation
Air pollution Exhaust
Emissions
i.e. NOx,
SOx and
HC.
Fugitive
emission
Negative Short term Irreversible Low, due to
movement of
vehicle only for
loading and
unloading of raw
material and
finished Goods.
Paving of roads,
reduction in
vehicle speed,
planting of
bushed and trees
along the roads
Noise
pollution
Noise
generation
Negative Short term Irreversible Low due to
limited
activity Power
horns will be
prohibited,
overloading of
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
55
trucks will be
prohibited
Risk &
Hazards
Accidents,
collision of
transport
vehicles
Negative Short term Irreversible Medium due to
loss of property
and injury to
Manpower.
Product and
raw
material
handling,
storage and
processing
Air Pollution Process
emission
Negative No
process
emission
form plant
since all
the
production
process
carried out
in close
vessel.
Noise pollution Noise
generation
from utilities,
processing
machineries
Negative Long term Irreversible Low due to noise
reduction
measures
Work zone air
quality
Process gas
and flue gas
emission
Negative Long term Irreversible Medium, due to
air pollution
control devices
(APC‟s)
Risk & Hazards Catch fire
accidents
Negative Short term Irreversible High, due to
injury to
manpower and
loss of properties
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
56
and fatal
accidents
Leakage
And spillage
from
pipelines or
storage
containers
Negative Short term Irreversible High, due to
corrosion,
leaching, burn
injuries and loss
of properties.
Water quality Vessel
washing,
Floor
washing
due to
spillage of
raw material
or products
Negative Short term Reversible Low, due to
proper storage,
proper loading
and unloading
practice, regular
maintenance of
process
equipment’s and
Machineries.
Adequate well
Designed
Internal
Drainage system
Sewage
and
Effluent
generation
Water quality Generation
Of Waste
water
Noise
Generation
From pumps
and blowers.
Negative Short term Reversible Sewage will be
sent to septic
tank and soak
pits for sewage
treatment.
Effluent will be
treated in ETP
followed by RO
and MEE to
achieve ZLD
Solid/
Hazardous
Waste
Land and soil Generation
of Solid
Waste
generation
Negative Short term Reversible Low, proper
collection and
disposal
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
57
Disposal
Green Belt
Development
Ecology Planting of
Trees
Positive Long term Reversible High, Positive
Impact
Air quality Dust barrier Positive Short term Reversible Low, Positive
Impact
Noise quality Noise barrier Positive Short term Reversible Low, Positive
Impact
LU/LC Conservation
of Land
Positive Short term Irreversible Low, Positive
Impact
Soil Increase in
soil fertility
Positive Short term Reversible Medium, Positive
Impact
Water Water
requirement
Negative Long term Irreversible Low, due to
water
Circulation
Employment
generation
Socio-
Economic
Status
Direct and
Indirect
employment
Positive Long term Irreversible High, the project
will generate
employment
2.11.1. Water Environment
There is no water consumption in manufacturing process. The 0.95 KLD of effluent shall be
generated during the manufacturing process. The effluent is generated as high TDS and low
TDS. The high TDS and low TDS effluent will be collected in separate collection tank. The
effluent will be transferred in to Neutralization Tank. The neutralize effluent will be passed
through the filtered notch. The filtered treated effluent will be collected in to the final collection
tank. The treated effluent from the final collection tank will be passed through the R.O. unit and
permeate of the RO will be reused (0.7 KLD) and RO reject will be evaporated in jacketed
evaporator (0.2 KLD).
The domestic wastewater shall be generated @ of 2.1 KLD which will be treated in STP.
Treated sewage will be reused for gardening.
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
58
Table 2.10 Waste Water Generation
category Existing (KLD) Proposed (KLD) Total after
expansion (KLD)
Domestic 2.0 0.1 2.1
Industrial
Process Nil 0.862 0.862
Boiler/ Cooling 0.05 0.038 0.088
Total Industrial
waste water
0.05 0.9 0.95
s
Figure 2.4 Schematic Flow Diagram Of ETP
The nature of different batch cycle is as follows:
Sr. No.
pH TDS (mg/l)
1 2.32 4894
2 2.89 3526
3 3.14 2112
4 3.97 1416
5 4.10 1364
The condensate composite samples content.
Sr. No.
Parameters Units Before treatment
After treatment
1 pH - 2.6 7.4
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
59
2 Suspended Solids mg/l 62 48
3 TDS mg/l 3368 3212
4 COD mg/l 840 472
5 BOD mg/l 243 132
6 Oil & grease mg/l 6 4
Adequacy Report
The unit shall generate 0.95 KL/ day effluent. The proposed units of ETP are as follows
Name Units No. of
Tank
Compartment
Nos.
Capacity of
Tank cum
Detention
Time In Hr. Remark
Collection Tank 1 2 1.50 48 Adequate
Neutralization
Tank 1 1 0.45 14 Adequate
Filter Notch 1 1 0.60 19 Adequate
Final Collection
Tank 1 2 1.50 48
Adequate
2.11.2. Air Environment
Air emission in form of flue gas along with air pollution control system is discussed in table no.
2.13. PM, SO2, NOx is generally emitted from flue gas stack,
Table 2.11 Flue gas emission
Sr.
No.
Stack Name
Stack
Height from
gl.
Parameter APCM
1 Thermic Fluid Heater 12 PM<150 mg/Nm3
SO2 < 100 ppm
NOx < 50 ppm
--
2 D.G. Set (125 KVA)
(existing)
5 --
Process emission:
There is no process gas emission from manufacturing process
2.11.3. Solid and Hazardous Waste Management
Hazardous waste generated from the process & maintenance. Empty drums and bags is hand
over to authorize vender for further recycle. The Management of Hazardous waste will be done
as per Hazardous Waste Management Rules 2008. The list of hazardous waste generation is
given in below mentioned table.
Table 2.12 Hazardous Wastes and its Management
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
60
Sr.
No.
Types of
Waste
Source of
generation
Category Quantity (MT/annum) Mode of
Disposal
Existing Proposed Total
1.
ETP
Sludge
ETP
33.4
-- 2.4 2.4 Collection,
Storage,
Transportation,
Disposal at
TSDF
site. 2. FRP Board
(FRP
Sheet)
(Trimming
of the
edges)
Process 21.1 0.96 -- 0.96
3. Evaporation
residue
Process -- -- 0.36 0.36
4. Used oil/
spent oil
DG set 5.1
0.01 0.02 0.03 Collection,
Storage,
Transportation, sell to
Registered Pre-processor/
Used as
lubricant in
premises
5. Discarded
Container /
Drum
Raw
material
packing
33.3 100
Nos./
year
200 Nos./
year
300
Nos./year
Sold to
Registered
Re-processor/
Sand back to
supplier
Bags 4700
Nos/
year
5300 Nos/
year
10000
nos/year
Sold to
Registered
Recycler/ Sand
back to supplier
Management and disposal of waste stream to be generated from spillage
Sr.
No.
Scenario Vulnerability
zone
Remarks
1. Spill of LDO Area close to
spill area
Isolate the area immediately and ensure no ignition
source comes nearby. Reclaim the material if possible
or cover the spill with sand/mud/foam.
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
61
2. Liquid
leakage/spillage
in confined
space
Confined area Spillage to be collected in dyke area and transfer to the
separate drum for reuse purpose. Fresh air
inlet/ventilation system to be fully opened. Ventilation
exhaust of vapors
Impervious flooring will be done at manufacturing process and materials storage area.
The preventive maintenance was planned and carried out as per plan to avoid the failure
of valve, pipe lines and other component of transferring line. The spillage will be confined
to the dyke area underneath the vessel. The resultant splash of the above chemicals will
result in exposure of toxic chemicals to employees. The spillage materials will collect and
reuse in process again.
2.11.4. Noise Pollution
Noise generating machines will be provided with appropriate acoustic enclosures to
maintain the noise levels within limits
2.12. Green Belt Development
Existing green belt area: 64000 sq. m.
Proposed green belt area: 1000 sq m.
Total Green belt area: 65000 sq.m
Tree plantation is one of the effective remedial measures to control the Air pollution and
noise pollution. It also causes aesthetics and climatologically improvement of area as well
as sustains and supports the biosphere.
The annual budget for the plantation will be Rs. 2,00,000/ -.
2.13. Occupational Health & Safety
The company is concerned with the health, safety and environment protection. The company will
formulate and develop an “Occupational Health & Safety Policy” to ensure good health and safety
of its employees.
The following key safety measures shall be a part of the Health & Safety policy of the company
and shall be followed after the project implementation:
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
62
Safety Training shall be provided to the employees.
Safety Sirens with Alarm System in case of emergency shall be provided.
Fire Extinguishers shall be provided.
Mock drills shall be periodically conducted and factors like response time shall be
evaluated.
First Aid Facility and training shall be provided.
PPEs and shall be provided to the employees.
Health check-ups shall be organized at regular intervals.
Safety/Health records and MSDS shall be maintained.
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
63
CHAPTER 3. DESCRIPTION OF THE ENVIRONMENT
3.1. Background
Generation of environmental baseline data for a project area is an important phase of any
Environmental Impact Assessment process. Baseline data provide vital information on the
existing environmental quality in which a development is planned. It is also useful for delineating
environmental sensitive areas and for preparing an Environmental Sensitivity Map for contingency
planning. In this study, the environmental characteristics of the project area (10 km study area)
were established through extensive literature search, field sampling/measurements, laboratory
analysis, consultation and data interpretation.
Secondary data from literature search were also obtained from the Govt. sources i.e.
Meteorological Department, CPCB publications; Forest Department and other Govt. Sources. The
study area within a 10 km radius around the proposed plant site has been considered as impact
zone for present EIA study. Primary and secondary data was collected for 10 km radial study of
the project site.
3.2. Environmental Setting and Salient Environmental Features of the Project Area
Figure 3.1 Location Map of 10-km Radius Study Area (Source: google earth)
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
64
Figure 3.2 Road Connectivity Map of Study Area
3.3. Primary Data Collection: Monitoring Plan and Quality Assurance Procedures
Baseline study has been carried out by during winter season (November, 2017 to January, 2018)
as per the standard TOR and prepared/revalidated the baseline data and prepared the EIA report.
The study period and methodology for primary data collection is summarized in Table 3.2.
Table 3.1 Summary of Methodology for Primary/Secondary Baseline Data Collection
Parameters No. of
Sampling
Locations
Frequency/Season Remark
Ambient Air Quality
PM (10), PM(2.5),
SO2, NOx, VOC
8 (Eight) Twice a Week AAQ monitoring was carried
out at eight locations
(representing upwind,
downwind and sensitive
locations). 24 hours sampling
at each location was carried
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
65
out as per CPCB guide lines
(CPCB Gazette notification
dated 18.11.2009 on AAQ).
Meteorology
Temperature,
Humidity, Wind speed,
Direction, Rainfall etc.
One location Hourly Met station was established
close to the site to record the
site-specific hourly met data.
Ground Water Quality
Physical, chemical
and biological
parameters as per
IS:10500
7 (Seven) Once in season Ground water: Sampling was
conducted at seven locations.
Samples were preserved,
transported and analyzed for
different parameters based on
APHA methods. Temp,
conductivity and pH which
were measured intently at site
itself.
Soil
Texture, bulk density,
pH, conductivity,
cation exchange
capacity, organic
matter, Total N,P,K,
and Heavy metals etc
5 (Five) Once in season Soil samples were collected at
five locations within the study
area and analyzed as per IARI
method
Noise
Noise profiling for 24
hrs
8 (Eight) Once in season Noise monitoring was
conducted within the 10-km
area of project site for noise
profiling for 24 hrs using
integrated sound level meter,
as per CPCB guidelines.
Ecology (Flora & Fauna)
Flora & Fauna Study Area Once in season Primary field survey and
secondary sources
Demography & Socio-economic Features
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
66
Demography & Socio-
economic
Study Area Once in season Primary field survey and
secondary sources
Standard methods and procedures have been strictly adhered to in the course of this study.
QA/QC procedures were strictly followed which covers all aspects of the study, and includes
sample collection, handling, laboratory analyses, data coding, statistical analyses, presentation
and communication of results. All analysis was carried out in NABL/MoEF accredited/recognized
laboratory.
3.4. Physical Environment
3.4.1. Topography
Ahmedabad is an Industrial hub for textiles and is popularly known as the “Manchester of India”.
The district headquarter, Ahmedabad was also the State Capital from May 1960 to May 1970,
before it was shifted to the new township at Gandhinagar. Ahmedabad district occupies 8087 sq.
km. area between 21°58‟ and 23°30‟ Northlatitudes and 71°35‟ and 73°02‟ East longitudes in the
central part of Gujarat state. It falls in the survey of India degree sheet numbers 41N, 41M, 46A
and 46B. It is bounded by Mahesana and Gandhinagar in North, Sabarkantha in North East,
Kheda in East Gulf of Cambay (Khambat), Bhavnagar in South and Surendranagar in west.
3.4.2. Physiography
River Sabarmati is the principal river of the district. It originates from Dhebar lake in Aravalli Range
of Udaipur District, Rajasthan and finally debauches into Gulf of Khambat near Vataman village
of Dholka taluka. Sabarmati forms the Eastern boundary of the district flowing from NE to SW
direction in Ahmedabad and Gandhinagar districts. The river Vatrak flows for a smaller length and
joins Sabarmati near village Wauta of Dholka taluka. The Khari river and the Meshwo river drain
Daskroitaluka. The river Bhogavo with its branches Chatori and Omkar drains Dholka and
Dhandhuka talukas. The Bhadar river with its branch Goma, Lilka, Utavali and Ghela drains
Dhandhuka taluka of the district. River Rodh drains Sanand and Dholka talukas. Rivers Shelwa
and Andhli drain Dholka taluka. There is no river or rivulet in Viramgam taluka.
3.4.3. Geology
The project region is located on the banks of the River Sabarmati in the Northern part
of Gujarat and the western part of India. It is located at 23.03°N 72.58°E spanning an area of
205 km². The average elevation is 53 metres.
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
67
There are 2 main lakes located in the city limits – the Kankaria Lake, and the Vastapur Lake.
Kankaria lake, located in Maninagar, is an artificial lake developed by Qutb-ud-din Aybakin 1451.
It also has an aquarium and a zoo. In the middle of the lake is an island palace named Naginawadi,
built during the Mughal era. The city is located in a sandy and dry area. Except for the small hills
of Thaltej-Jodhpur Tekra, the entire city is almost flat. The Sabarmati bifurcates the city into
Eastern and western parts, connected by five bridges, two of which were constructed after
independence. Though the river is perennial, it gets dried up in the summer, leaving only a small
stream of water flowing.
There are typically three main seasons – summer, monsoon and winter. Barring monsoon, the
climate is very dry. The weather is very hot during the months of March to June with the average
summer temperature ranging from maximum 43 °C to minimum 23 °C. The months of November
to February have an average maximum temperature 36 °C and a minimum of 15 °C. The climate
is extremely dry during that period. Cold Northerly winds are responsible for a mild chill during
January. The south-west monsoon winds bring humid climate to Ahmedabad from mid-June to
mid-September. The average rainfall is 932 mm. The highest temperature recorded is 47 °C and
the lowest is 5 °C.
Ahmedabad is divided by the Sabarmati into two physically distinct areas. The Eastern bank of
the river houses the old city which has packed bazaars, a pol system of houses, and many places
of worship like temples and mosques. The old city also houses the main railway station and
the General Post Office. The colonial period saw the expansion of the city to the western side of
Sabarmati falicitated by the construction of Ellis Bridge in 1875. This part of the city houses
educational institutions, modern buildings, well-planned residential areas, shopping
malls, multiplexes and new business districts centred on the C.G. Road, Ashram Road and more
recently the Sarkhej-Gandhinagar Highway.
3.4.4. Geomorphology
Geomorphologically the district can be divided into two zones, the major portion of it forms a flat
planar topography except for a few rocky features in the extreme southern portion.
Flat Alluvial Peneplain
It includes the low-lying land of Dholka and Dhandhuka taluka (falling below 20 m) contour
characterized by marshy land, which is believed to be under sea in the past. Water logging is
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
68
common in these tracts at high tides during monsoon. This barren low land is termed as “The
Bhal” area and characterized by high coastal salinity. The spreading of alluvial bed of Sabarmati
river from end to end of the district is an important natural feature being observed. Below the city,
on the left bank of the river and also midway between it and the Khari river are few small rises.
But everywhere else, the surface of the ground is unbroken on every side, except the North, with
groves of various trees. Along the Right Bank of Sabarmati river, the prominent characteristics of
Daskroipass into Dholka. However, towards west and south-west they pass into fertile but
absolutely flat and monotonous black soil of the Bhal. The area from Dholka to Bavliari creek
along the coast is characterized by salty and marshy land. Along the western border, the land
passes into a reddish form. 10
Low hills
A series of low hills are present few Km west of Rampur in the western Dhandhuka taluka. The
hills around Ninana in the most westerly part of Dhandhuka are covered with fragments of quartz
and limestone. Some hills are located around Vasai and Miroli in the southern section of the
district, also near Thaltej and Gota of Daskroi taluka in the North, and Chandisar in Dholka and
Vastrapur in the City Taluka.
3.4.5. Land / Soil Characteristic:
The sub soil condition below the existing ground level are almost uniform in nature. Sub soil is
composed of Clay mixed with little fine grained silty sand, moram and Kankar with low resistivity
due to clay and soil moisture. The area is covered with recent to sub recent alluvial deposits
comprising of brownish clay mixed with little fine-grained sand, silty sand. The Soil below ground
level consist of top silty low plastic soil layer having no swelling nature. Blackish brown to yellowish
brown clayey silt or sand silt layer extends to the depth of 2 to 3 mts.
3.4.6. Rain Fall:
The average annual rainfall (1980 to 1990) is 558 mm. (10 years) average rain fall of (1990 to
2000) 10 years is 746 mm, average rain falls of (2000-2010) is 889 mm and average rainfall of 30
years is 731 mm contributed mainly by Southwestern monsoon active from June to Mid-
September.
Dependable Rainfall = N X P = 22 X 40 = 8.8
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
69
8th year i.e.=842 mm
Average Rainfall: - 1980-1990 = 558 mm
1990-2000 = 746 mm
2000-2010 = 889 mm
30 years average Rainfall: - = 731 mm
3.4.7. General Information of Taluka Sanand:
Total number of villages = 67
Total area of Taluka in Sq. Kms.= 800
Saline area = 240 Sq. Kms.
Fresh water area = 460 Sq. Kms.
Hard rock area = NIL.
Alluvium area = 800 Sq.Kms
Feasibility =Deep Tubewell
Quality of Groundwater = Potable water & Partly Saline
Ground water Balance – 112.15 MCM/ Year
3.4.8. Climate:
The climate of the area is semi-arid and is characterized by a hot summers and general dryness
except during the South west monsoon between the months June and September. There is a
meteorological observatory at Ahmedabad manned by IMD. May is the hottest month with mean
daily maximum temperature of 41.30C. and the mean daily minimum temperature of 26.30C
3.4.9. Geohydrology:
The litho logical logs of exploratory bore holes, electrical logging results by govt. agencies in and
around Sanand taluka have been studied to understand the subsurface geology and the aquifer
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
70
system. These bore holes have penetrated the thick sequence of post Miocene sediments down
to 300 + m depth.
The hydro geological cross sections have been prepared by CGWB to study the subsurface
geology and aquifer system in the area. It is reveals that the existence of multilayered aquifer
system, within a depth of 300 + m bgl.
I. Ground Water Condition:
In the area under investigation, ground water occurs both under phreatic and confined condition
in aranaceous horizons. The occurrence and movement of ground water is mainly controlled by
primary porosity of inter granular pore spaces. Ground water is being developed extensively by
means of Tube well from deep confined aquifers for water supply both in domestic, industrial and
agricultural sector.
J. Depth of Ground Water Table:
Shallow aquifer (Phreatic) development (up to 30m depth) in the area is limited due to rapid
urbanization inferior quality and low yields. Depth of water level in these tube well ranges from 10
to 20 mts. yield of wells is moderate and quality of ground water is variable and ranges from fresh
to saline.
a. Confined Aquifers:
Deep tube well tapping confined aquifers are the main ground water withdrawal structure. Due to
rapid urban growth, heavy ground water exploitation has resulted in progressive lowering of
potential head and discharges. Depths of tube well have increased from about 150 m in late sixties
to more than 300 m at present. Depth to water level in confined aquifers ranged from 90 to 100mts.
Discharge for tube well ranged from 15 lps to 35 lps for 3 to 10m of drawdowns. The specific
capacity of these wells ranges from 1 to 12 lps/m. Aquifer transmissivity and hydraulic conductivity
varies from about 100 to 2000 m2 /day and 1 to 78 m/day respectively. Ground water quality in
deeper aquifer generally varies from 800 to 2000 TDS.
b. Water level Fluctuation:
Large scale development of Ground Water from deep aquifers has resulted in progressive decline
in water levels. Presently the Pumping water level rest more than 75m bgl. and as a consequence,
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
71
discharge have reduced or pumping costs have increased. The rate of decline varies from 2.06
m/yr to 2.136 m/yr.
K. Drainage Pattern:
The area has a drainage pattern which is of the parallel and trellis type and which is controlled by
the topography and structure and tectonics of the region. All the small streams flow from the
higher grounds and meet ultimately Sabarmati River which flow from North East direction to South
East direction near project area. The area Drainage ultimately meet with Gulf of Khambhat.
Area has diverse landscape made up of small hills, valley, drainage flow, Platue and alluvium
plain. The terrain slope is south in the Northern Western in the South number of major river drains
the area. Due to terrain constraint it is necessary to adopt proper soil conservation and sand water
development and management practice for w/s in sustained basis. Because of short span of
monsoon season and limited storage capacity and rapid cut flow for hard rock aquifers, that is
need to provide ground water recharge facilities to supplement its which drawl at a time of
summer.
As various components of the hydrologic System-Catchment runoff, base flow and ground water
an integrated at the level of river basins, river basin should be the unit of governance and
management of water resource such a system of governance will ensure integration of physical
sustainability consideration and the social economic and environmental consideration in water
resources management planning which ultimately result in good governance
3.5. Seismicity of the Study Area
Based on tectonic features and records of past earthquakes, a seismic zoning map of India has
been prepared by a committee of experts under the auspices of Bureau of Indian Standard (BIS
Code: IS: 1893: Part I 2002. According to the seismic-zoning map of India, the project area falls
in Zone III of seismicity. The seismicity map of study area is shown in Figure 3.3.
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
72
Figure 3.3 Seismic Zones Map (Source: Map of India)
3.6. Land use
Land use analysis was carried out using remote Sensing Data. Interpretation approach based on
systematic digital imaging was used for delineating the land use classes. The demarcation of
boundaries falling under different land use/land cover units is done using different colors assigned
to different land use/land cover units of satellite imagery.
The site is located in the existing industrial area. Most of the land within the 10 km area of the
project site is agricultural land. As per the land use based on satellite image, about 94% of the
land is Agricultural land, 3%% of the land is Open shrub land, about 1% land is water bodies &
1% of the land is covered with vegetation and 1% is comes under settlement.
Table 3.2 Land use of the Study Area
Class Area (Sq km)
Agricultural Land 295.02
Waterbody 3.36
Open Shrub Land 10.20
Settlement 4.58
Vegetation 1.50
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
73
Class Area (Sq km)
Total 314.66
Figure 3.4 Graph Showing Land Use of the Study Area (10 km Radius)
94%
1%
3%
1%
1%
Land Use
Agricultural Land
Waterbody
Open Shrub Land
Settlement
Vegetation
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
74
Figure 3.5 Land use/Land Cover Map of 10 Km Radial Study Zone (Source: Google earth satellite
imagery)
3.7. Meteorology
Observation on Meteorology: The meteorological parameters play a vital role in transport and
dispersion of pollutants in the atmosphere.
Climate: The climate of Gujarat is varied, as it is moist in the southern districts and dry in the
Northern region. The Arabian Sea and the Gulf of Khambhat in the west and the forest-covered
hills in the East soften the rigours of climatic extremes, consequently reducing the temperature
and render the climate more pleasant and healthy. The mean minimum temperature is about 12°C
and means maximum temperature is about 42°C. The normal annual rainfall over the district about
750 mm.
Relative Humidity: The mean monthly average of Relative Humidity values for Ahmedabad
station was recorded & Relative Humidity is generally high during the period from June to
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
75
September. The diurnal variations are lEast during monsoon season. The diurnal variation is
highest during summer period. Relative humidity is maximum 65 % and minimum 18 %.
Cloudiness: The skies are heavily clouded to overcast during the south-west monsoon season.
In May and October, the clouding is moderate. Clear or very lightly clouded skies are common in
the rest of the year.
Regional Meteorology:
Table 3.3 Long Term Meteorological Data of Ahmedabad
Month Mean Daily Maximum
Temperature(0C)
Mean Daily Minimum
Temperature(0C)
Mean Daily Temperature
(0C)
Relative Humidity
(%)
Mean wind
Speed (Km/h)
Average Rainfall
(mm)
January 12.25 29.70 21 20.35 3.7 00
February 23.17 31.48 15.10 15.93 5.7 00
March 29.00 36.87 21.06 11.77 5.9 00
April 32.33 38.83 25.17 12.20 7.6 00
May 35.90 41.39 28.29 15.61 11.4 50
June 34.37 40.50 28.57 26.97 12.1 210
July 29.90 33.68 26.26 54.32 8.9 350
August 28.29 31.35 28.29 65.35 7.4 150
September 29.20 33.73 24.50 51.07 6.2 50
October 29.77 26.45 23.71 40.38 2.5 20
November 23.73 21.27 20.57 17.7 2.4 00
December 22.06 25.03 21.38 18.23 3.3 00
Met Data Generated at Site
Met data for Asiatic Composite Limited was generated at site during November, 2017 to January,
2018. An automatic weather monitoring station was installed at Project site, keeping the sensors
free exposed to the atmosphere and with minimum interference with the nearby structures. The
micro-meteorological data like wind speed, wind direction, temperature, relative humidity and
atmospheric pressure were collected using the weather stationed cloud cover was recorded
manually for the study period.
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
76
Table 3.4 Site Specific Meteorological Data
Month Wind speed
Wind direction
Temperature Relative humidity
Rainfall
December,
2017
2.1 51.1 21.7 52.6 0.0
January,
2018
1.4 44.2 21.7 49.2 0.0
February,
2018
1.3 57.9 24.7 43.7 0.0
Site specific wind rose diagram is presented in Figure 3.6.
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
77
Figure 3.6 Wind Rose Diagram
3.8. Ambient Air Quality
AAQ monitoring was done for winter season (November, 2017 to January, 2018). CPCB
guidelines were applied for selecting the appropriateness of monitoring locations. The location
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
78
and height of the stations were so selected (>5 m from base) to avoid the capture of re-suspended
road dust and fugitive domestic emissions due to burning. All the ambient air analysis with respect
to each parameter were analyzed as per CPCB guidelines. AAQ monitoring was done at eight (8)
locations within the study area considering dominant wind direction, populated area and sensitive
receptors. The data on pollutants concentrations were processed for different statistical
parameters like arithmetic mean, minimum and maximum concentration and 90 percentile values.
Details of monitoring locations are shown in Table 3.5. Monitoring Location map is shown in Figure
3.7. The summary of Ambient Air quality results is presented in Table 3.6.
Table 3.5 Ambient Air Quality Monitoring Locations
Sampling
Station No.
Station Direction with
distance
Coordinates
AAQ1 Project Site 0.0 22°54'11.60"N, 72°14'49.57"E
AAQ2 Mankol WNW, ~2.11 22°53'44.17"N, 72°15'57.43"E
AAQ3 Charal N ~7.25 22°58'6.50"N, 72°14'56.75"E
AAQ4 Kavla S ~8.81 22°49'25.44"N, 72°14'32.23"E
AAQ5 Vinchhiya NE ~4.91 22°55'40.57"N, 72°17'9.24"E
AAQ6 Kundal WSW ~2.65 22°53'53.99"N, 72°13'17.96"E
AAQ7 Rethal WSW ~6.09 22°53'16.54"N, 72°11'14.94"E
AAQ8 Daduka WNW ~7.26 22°54'50.26"N, 72°10'37.80"E
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
79
Figure 3.7 Air Monitoring Sampling location
(Source: google earth)
Table 3.6 Ambient Air Quality Monitoring Results (24-hour average)
Param
eters
AAQ1 AAQ2 AAQ3 AAQ4 AAQ5 AAQ6 AAQ7 AAQ8
PM 10
in
μg/m3
Max. 60.4 52.2 51.8 54.6 55.2 57.4 57.2 55
Min. 49.1 45.6 44.4 46.2 48.6 47.2 47.6 48.5
Mean 54.75 48.9 48.1 50.4 51.9 52.3 52.4 51.75
PM
2.5 in
μg/m3
Max. 40.9 35.6 37.4 36.2 35.2 38.2 39.2 37.6
Min. 35.4 32.4 31.2 33.5 31.1 30.6 33.4 33.4
Mean 38.15 34 34.3 34.85 33.15 34.4 36.3 35.5
Max. 20.3 18.6 16.5 15.6 18.1 16.8 15.9 17.7
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
80
SO2 in
μg/m3
Min. 15.1 13.5 12.4 11.2 14.8 12.6 11.9 12.3
Mean 17.7 16.05 14.45 13.4 16.45 14.7 13.9 15
NOx in
μg/m3
Max. 25.6 17.8 16.6 19.2 21.5 17.5 20.1 15.6
Min. 19.7 12.4 11.5 12.4 14.1 11.8 13.2 11.5
Mean 22.65 15.1 14.05 15.8 17.8 14.65 16.65 13.55
VOC
in
μg/m3
Max. 0.3 BDL BDL BDL BDL BDL BDL BDL
Min. 0.12 BDL BDL BDL BDL BDL BDL BDL
Mean 0.21 BDL BDL BDL BDL BDL BDL BDL
Table 3.7 National Ambient Air Quality Standards (CPCB), 2009
S.N. Pollutant Time
weighted
average
Concentration in Ambient air Methods of
Measurement Industrial,
Residential,
Rural and
Other Area
Ecologically
sensitive area
(notified by
Central Govt.)
1 Sulphur
Dioxide (SO2),
μg/m3
Annual* 50 20 •Improved West and
Geake
•Ultraviolet
fluorescence
24 hours** 80 80
2 Nitrogen
Dioxide
(NO2),μg/m3
Annual* 40 40 •Modified Jacob &
Hochheiser (Na
Arsenite)
•Chemiluminescence
24 hours** 80 80
3 Particulate
Matter (size
less than 10
μm) or
PM10μg/m3
Annual* 60 60 •Gravimetric •TOEM
•Beta attenuation 24 hours** 100 100
4 Particulate
Matter (size
less than 2.5
Annual* 40 40 •Gravimetric •TOEM
•Beta attenuation 24 hours** 60 60
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
81
microns) or
PM2.5μg/m3
5 Ozone (O3)
μg/m3
Annual* 100 100 •UV photometric
•Chemiluminescence
•Chemical method
24 hours** 180 180
6 Lead (Pb)
μg/m3
Annual* 0.5 0.5 •ASS / ICP method
after sampling on
EPM 2000 or
equivalent filter
paper •ED – XRF
using Teflon filter
24 hours** 1.0 1.0
7 Carbon
Monoxide
(CO) mg/m3
8 hours** 2 2 Non Dispersive Infra-
RED (NDIR)
Spectroscopy
1 hour** 4 4
8 Ammonia
(NH3) μg/m3
Annual* 100 100 •Chemiluminescence
•Indophenol blue
method
24 hours** 400 400
9 Benzene
(C6H6) μg/m3
Annual* 5 5 •Gas
chromatography
based continuous
analyser •Adsorption
and desorption
followed by GC
analysis
10 Benzo (a)
Pyrene (BaP) –
particulate
phase only
ng/m3
Annual* 1 1 Solvent extraction
followed by HPLC /
GC analysis
11 Arsenic (As)
ng/m3
Annual* 6 6 AAS / ICP method
after sampling on
EPM 2000 or
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
82
equivalent filter
paper
12 Nickel (Ni)
ng/m3
Annual* 20 20 AAS / ICP method
after sampling on
EPM 2000 or
equivalent filter
paper
* Annual Arithmetic mean of minimum 104 measurements in a year taken twice a week 24 hourly at uniform
interval.
** 24 hourly/ 8 hourly values should be met 98% of the time in a year. However, 2% of the time, it may exceed
but not on two conservative days
3.3.1. Interpretation of result
PM2.5 (Winter Season): The highest PM2.5 level was observed Project Site (38.15 µg/m3), while
the lowest level was observed at Vinchhiya (33.15 µg/m3). The Average PM2.5 levels are within
the NAAQS levels for Industrial, Residential, Rural and Other Areas (60 µg/m3).
Figure 3.8 Statistical Comparison of PM2.5 Concentration (Winter Season)
PM10 (Winter Season): PM10 level was found ranging from 48.1 to 54.75 µg/m3. The highest
PM10 level were found at Project Site (54.75 µg/m3) while the lowest level was found at Charal
(48.1 µg/m3). The PM10 in the study area is contributed mainly by industrial emissions, vehicular
emissions, re-suspended dust from paved / unpaved roads and open areas as well as from
industrial activities. The Average PM10 levels are within the NAAQS levels for Industrial,
Residential, Rural and Other Areas.
0
10
20
30
40
50
60
AAQ1 AAQ2 AAQ3 AAQ4 AAQ5 AAQ6 AAQ7 AAQ8
PM 2.5
Max. Min. Mean
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
83
Figure 3.9 Statistical Comparison of PM10 Concentration (Winter Season)
Sulphur Dioxide (Winter Season): The highest level of SO2 was found at Project Site (17.7
µg/m3) whereas lowest level was found at Kavla (13.4 µg/m3). The SO2 level of the Study area
is well under the NAAQS Standard of 80 µg/m3. The main source of SO2 emission is vehicular.
Figure 3.10 Statistical Comparison of SO2 Concentration (Winter Season)
Oxides of Nitrogen (Winter Season): The highest level of NOx was found at Project Site (22.65
µg/m3) whereas lowest level was found at Daduka (13.55 µg/m3). The NOx level of the Study
area is well under the NAAQS Standard of 80 µg/m3. The main source of NOx emission is
industrial & vehicular.
0
20
40
60
80
100
AAQ1 AAQ2 AAQ3 AAQ4 AAQ5 AAQ6 AAQ7 AAQ8
PM 10
Max. Min. Mean
0
10
20
30
40
50
60
70
80
AAQ1 AAQ2 AAQ3 AAQ4 AAQ5 AAQ6 AAQ7 AAQ8
SO2
Max. Min. Mean
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
84
Figure 3.11 Statistical Comparison of NOx Concentration (Winter Season)
Overall the ambient air quality of the study area during winter season was found to be within the
NAAQS.
3.9. Noise Environment
Noise after a certain level can have a very disturbing effect on the people and animals exposed
to it. Hence, it is important to assess the present noise quality of the area in order to predict the
potential impact of future noise levels due to the proposed project.
Ambient noise measurements were taken at 8 locations during winter season. Noise monitoring
locations are represented in Table 3.8. The Noise level recorded in study area during December,
2017- February, 2018 is represented in Table 3.9.
The monitored levels were compared against the Noise Pollution (Regulation and Control) Rules
2000, as amended through the Noise Pollution (Regulation and Control) Amendment Rules 2010
dated 11th January 2010. The noise levels at all the locations were found within the ambient noise
standards.
Table 3.8 Ambient Noise Quality Monitoring Locations
Sampling
Station No.
Station Direction with
distance
Coordinates
N1 Project Site 0.0 22°54'11.60"N,
72°14'49.57"E
0
10
20
30
40
50
60
70
80
AAQ1 AAQ2 AAQ3 AAQ4 AAQ5 AAQ6 AAQ7 AAQ8
NOx
Max. Min. Mean
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
85
Sampling
Station No.
Station Direction with
distance
Coordinates
N 2 Mankol WNW, ~2.11 22°53'44.17"N,
72°15'57.43"E
N 3 Charal N ~7.25 22°58'6.50"N,
72°14'56.75"E
N 4 Kavla S ~8.81 22°49'25.44"N,
72°14'32.23"E
N 5 Vinchhiya NE ~4.91 22°55'40.57"N,
72°17'9.24"E
N 6 Kundal WSW ~2.65 22°53'53.99"N,
72°13'17.96"E
N 7 Rethal WSW ~6.09 22°53'16.54"N,
72°11'14.94"E
N 8 Daduka WNW ~7.26 22°54'50.26"N,
72°10'37.80"E
Figure 3.12 Noise Monitoring Sampling Location
(Source: Google Earth)
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
86
Table 3.9 Ambient Noise Quality in the Study Area
Location
Name
Day Time
Leq dB(A)
Night Time
Leq dB(A)
N1 50-56 45-50
N 2 51-57 46-49
N 3 49-55 44-48
N 4 52-58 43-49
N 5 47-52 40-46
N 6 50-56 42-48
N 7 57-61 50-56
N 8 52-59 44-50
Table 3.10 Applicable Noise Standards
3.4.1. Observation on Ambient Noise Quality:
The ambient noise quality of the study area is within the prescribed National Ambient Noise
Quality Standards prescribed for industrial (Standards - 75 dBA during day time and 70dBA during
night time) residential area (Standards - 55 dBA during day time and 45 dBA during night time)
and commercial area (Standards - 65 dBA during day time and 55 dBA during night time).
3.10. Water Quality
Water environment of an area is broadly classified into the following categories
Ground water: Water seepage and accumulations in deeper strata of ground.
Surface water: Rivers, drains, canal, ponds etc.
The only source of recharging for both surface and ground water source is from precipitation
(rainfall).
Area Code Category of Area Limit in dB (A) Leq
Day Time Night Time
A Industrial area 75 70
B Commercial area 65 55
C Residential area 55 45
D Silence zone 50 40
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
87
Seven (7) ground water samples were collected from different locations around the site during
winter season (December, 2017- February, 2018). The water samples were examined for
physico-chemical parameters and bacteriological parameters. The samples were collected and
analyzed as per the procedures specified in Standard Methods. Samples for chemical analyses
were collected in polyethylene carboys. Samples for bacteriological analyses were collected in
sterilized bottles. Temperature, pH, conductivity and dissolved oxygen were measured at site
itself.
The name of ground water sampling locations is presented in Table 3.11 respectively. The
analysis results of groundwater for winter season are presented in Table 3.12.
Table 3.11 Ground Water Sampling Locations
Sampling
Station
No.
Station Direction with
distance
Coordinates
GW1 Project Site 0.0 22°54'11.60"N, 72°14'49.57"E
GW2 Mankol WNW, ~2.11 22°53'44.17"N, 72°15'57.43"E
GW3 Charal N ~7.25 22°58'6.50"N, 72°14'56.75"E
GW4 Kavla S ~8.81 22°49'25.44"N, 72°14'32.23"E
GW5 Vinchhiya NE ~4.91 22°55'40.57"N, 72°17'9.24"E
GW6 Kundal WSW ~2.65 22°53'53.99"N, 72°13'17.96"E
GW7 Rethal WSW ~6.09 22°53'16.54"N, 72°11'14.94"E
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
88
Figure 3.13 Ground water Sampling Location
(Source: Google Earth)
Table 3.12 Ground Water Quality in the Study Area
Parameter Unit GW1 GW2 GW3 GW4 GW5 GW6 GW7 Permissible
Limit as
Per
Reference
Method
pH - 7.4 7.3 7.6 7.6 7.7 7.3 7.4 6.5-8.5 APHA
4500 H+
Electric
Conductivity µS/cm 750 650 721 710 690 725 745 -
APHA
2510
TDS mg/l 710 535 585 480 750 547 620 2000 APHA
2540 C
Hardness mg/l 152 150 160 175 165 152 159 600 APHA
2340
Total
Alkalinity mg/l 158 169 153 177 195 185 198 600
APHA
2320
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
89
Parameter Unit GW1 GW2 GW3 GW4 GW5 GW6 GW7 Permissible
Limit as
Per
Reference
Method
Calcium mg/l 45 42 48 51 56 49 55 200 APHA -
3500 Ca
Magnesium mg/l 9.6 10.9 9.76 11.5 6.1 7.1 5.2 100 APHA
3500-Mg
Chloride mg/l 145 136 160 138 140 149 139 1000 APHA
4500 - Cl-
Sulphate mg/l 105 98 85 80 101 79 65 400
APHA
4500-
SO42-
Observation on Ground Water Quality
All the samples meet the desirable standards (pH ranges from 7.3 to 7.7).
TDS in samples ranges from 480 mg/L to 750 mg/L. All the samples meet the permissible
limit of 2000 mg/L.
Total Hardness in the water ranges from 150 mg/L to 175 mg/L. All the samples meet the
permissible limit of 600 mg/L.
Calcium content in the water ranges from 42 mg/L to 56 mg/L all the samples meet the
permissible limit of 200 mg/L.
Magnesium content in the water ranges from 5.2 mg/L to 11.5 mg/L. All the samples meet
the permissible limit of 100 mg/L.
Sulfate content in the water ranges from 65 mg/L to105 mg/L. All the samples meet the
permissible limit of 400 mg/L for drinking water.
Total alkalinity in the water samples ranges from 153 mg/L to 195 mg/L. All the samples are
within the permissible limit of drinking water (600 mg/L).
Chlorides range from 136 mg/L to 160 mg/L, which are below permissible limits (1000 mg/L).
Heavy metals like Copper, Nickel, Cadmium and Zinc are well below the limit in all samples
except Lead, which was slight above the permissible limit.
Hence, it can be observed that ground water qualities in terms of various essential and desirable
characteristics are found within the limits specified by IS 10500:2012.
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
90
3.11. Soil Quality
Soils may be defined as a thin layer of earth's crust that serves as a natural medium for the growth
of plants. It is the unconsolidated mineral matter that has been subjected to and influenced by
genetic and environmental factors. Soils serve as a reservoir of nutrients for plants and crops and
also provide mechanical anchorage and favorable tilts.
Soil is our most important natural resource and a natural resource is anything that comes from
the earth and is used by us. We depend on the soil for food, clothing, shelter, minerals, clay &
water. Soil is the seat of many macro and micro flora like algae, fungi, earthworms, bacteria etc.
These are very beneficial in promoting soil reactions and decomposing the organic matter by
which essential nutrients for plants are liberated. Most of the soils are made-up of two main parts:
Tiny bits of mineral particles which come from larger rocks, and humus, which is dark
brown in colour and consists of decaying remains of plants and animals.
Soil also contains water, air and living organisms, such as fungi, bacteria, earthworms,
roundworms, insects, etc. Actually, more living organisms live in the soil than above it.
For general characterization of soil a few random samples from the study area to the depth of
about 15-cm may sufficient. Deeper soil samples may be needed only for the study of soil Profile.
3.11.1. General Characteristics of the Soil in the District
The soils in the district can broadly be classified as:
Black Soils: Black soils cover the southern part of Dholka and Eastern part of Dhandhuka taluka
popularly known as „Bhal‟ tract, where cotton is grown in the initial stage of monsoon. It is not
very clayey and contains above 20% of clay and about 40 % of sand. Sub-soil invariably contains
horizons of lime nodules. This type of soil is highly suitable for cultivation of rabi wheat, which is
the main crop raised on this soil. If rains are sufficient in the late monsoon, rabi jowar and grams
are sown. Medium Black Soils are found in Viramgam, Sanand and Dholka talukas. This soil is
suitable for growing bajri, jowar and cotton.
Goradu Soils: Goradu soils vary from fertile brown to sandy loam and is found in City, Daskroiand
parts of Sanand, Dholka and Viramgam talukas. This soil is mostly fertile and responds very well
to irrigation and manuring. Practically all kinds of crops can grow on this soil.
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
91
Kyari: Kyari soils are found in several parts of City, DasKroi, Sanand, Dholka and Viramgam
talukas. It is the most fertile soil with very good moisture and retentive capacity. Well known
varieties of paddy such as Pankali, kamod, Jirasar, Sukhvel, Sutarsal and Basumati are grown
on this soil.
Rocky soils: Rocky soils are found in Dhandhuka taluka and is known as Kaner tract. It is
shallow, light in texture and fit for early maturing crops like cotton, Bajri, Jowar and Math.
Soil map of Ahmedabad district is shown as Figure 3.13.
Figure 3.14 Soil Map of Ahmedabad District
3.11.2. Methodology
The soil samples were collected from five selected locations during winter season (December,
2017- February, 2018). The samples collected from all the locations were homogeneous
representative of each location. At random five sub locations were identified at each location and
soil samples were collected from 5 to15-cm below the surface. It was uniformly mixed before
homogenizing the soil samples. The samples about 500-gms were packed in polythene bags
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
92
labeled in the field with location & number and sent to the laboratory for the analysis of
physicochemical parameters. Soil sampling locations were selected based on the local geological
formation and the agricultural practices. Soil sampling locations with their distance & directions
with respect to the proposed expansion project site are presented in Table: 3.13 & shown in
Figure: 3.15.
Table 3.13 Soil Sampling Locations
Sampling
Station
No.
Station Direction with
distance
Coordinates
S1 Project Site 0.0 22°54'11.60"N, 72°14'49.57"E
S2 Mankol WNW, ~2.11 22°53'44.17"N, 72°15'57.43"E
S3 Charal N ~7.25 22°58'6.50"N, 72°14'56.75"E
S4 Kavla S ~8.81 22°49'25.44"N, 72°14'32.23"E
S5 Vinchhiya NE ~4.91 22°55'40.57"N, 72°17'9.24"E
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
93
Figure 3.15 Soil Monitoring Location Map
3.11.3. Analysis of Soil Samples
The soil samples were examined for various physicochemical parameters, to determine the
existing soil characteristics of the study area. Soil samples were collected from the vicinity of
proposed project site during winter season (December, 2017- February, 2018). Physicochemical
characteristics of soil for Asiatic Composite are presented in Table 3.14.
Table 3.14 Physicochemical Characteristics of Soil
Parameter S1 S2 S3 S4 S5
pH 7.7 7.3 7.9 7.4 7.6
Calcium 0.38 0.33 0.31 0.29 0.40
Magnesium 0.21 0.15 0.14 0.17 0.30
Sodium 2.3 0.7 0.59 0.5 2.8
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
94
Potassium 0.22 0.09 0.08 0.15 0.19
Total Alkalinity 1.6 1.5 1.7 1.5 1.7
Sulphate 0.26 0.21 0.18 0.21 0.29
Chloride 3.9 1.7 1.5 1.8 4.0
Organic Matter 0.009 0.14 0.16 0.14 0.15
Available Nitrogen 0.5 0.6 0.7 0.8 0.52
Available
Phosphorus
0.019 0.32 0.5 0.3 0.18
Boron ND ND ND ND ND
Copper ND ND ND ND ND
Cadmium ND ND ND ND ND
Chromium ND ND ND ND ND
SAR in % 4.8 5.0 3.5 4.8 5.1
3.11.4. Observation on Soil Quality
It is observed from the analysis report that;
Particle Size: Particle sizes of the different constituents (clay, silt, sand and gravel) control the
porosity and water holding characteristic of the soil. Clay (size < 0,002mm) amount in the soil
samples is 14% to 15% and Sand (size 0.002 to 0.075mm) in the soil sample is 68% to 70%. All
the samples in the study area are free of gravel (size > 4.75mm). Analysis shows it is sandy soil
with less water holding capacity.
3.12. Traffic Study
Traffic counts are important to calculate the existing and proposed load on the existing Road due
to upcoming Project.
Details regarding the traffic survey are:
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
95
Traffic counts were collected and recorded in 4 hours intervals.
Morning period (pick hours) survey was carried out from 8:00 to 12:00 hrs.
Evening period (pick hours) survey was carried out from 16:00 to 20:00 hrs.
Traffic counts observed during the above survey are tabulated below;
Table 3.15 Traffic survey near the plant site
Type of vehicles Route -1 Route-2
09.00-01.00
(4 hr)
16.00-20.00
(4 hr)
09.00-01.00
(4 hr)
16.00-20.00
(4 hr)
Large Trailer 2 2 8 10
Heavy (Bus, Truck,
etc)
2 4 62 52
Medium (Tractors,
light
commercial vehicles
etc)
11 9 80 83
Light (Car, Jeep,
Pickup
Van etc.)
12 8 69 58
3-Wheeler
(Rickshaw)
10 15 34 25
2-Wheeler (Scooter,
motorcycle, cycle etc)
45 39 47 49
Table 3.16 Assessment of Proposed Traffic Load
Type of vehicles Route -1 Route-2 PCU
Factor
as per
Indian
Road
Code
Average
Vehicles Per
Hour (Worst
Case)
Equivalent
PCU
(Passenger
Car Unit)
per hour
Average
Vehicles Per
Hour
Equivalent
PCU
(Passenger
Car Unit)
per hour
Large Trailer 0 0.0 12 51.8 4.5
Heavy
(Bus, Truck, etc)
2 4.5 82 246.0 3
Medium
(Tractors, light
commercial vehicles
etc)
6 9.0 131 195.8 1.5
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
96
Type of vehicles Route -1 Route-2 PCU
Factor
as per
Indian
Road
Code
Average
Vehicles Per
Hour (Worst
Case)
Equivalent
PCU
(Passenger
Car Unit)
per hour
Average
Vehicles Per
Hour
Equivalent
PCU
(Passenger
Car Unit)
per hour
Light (Car, Jeep,
Pickup
Van etc.)
4 3.5 203 202.5 1
3-Wheeler
(Rickshaw)
7 7.0 53 52.5 1
2-Wheeler (Scooter,
motorcycle, cycle
etc)
32 16.0 151 75.5 0.5
Total PCU/hr 40 824
Width of Road (m) 4 16
Design PCU per hour 900 2900
Existing PCU per hour 40 824
Proposed Load (Trucks/day) 26 26
Proposed PCU per day 78 78
As a Worst Scenario taken
Proposed PCU per day as PCU per
hour
78 78
Total PCU per hour after the
Proposed Project
118 902
3.13. Ecological Environment
The Botanical and wildlife species in an area depend on the availability of suitable habitat for
survival. Habitat loss and increasing habitat fragmentation are the primary causes of species
decline in these environments. This section provides an overview of flora and fauna observed in
study area during site visit.
3.13.1. Flora
Taxonomical Status
Within the sample plots of the study areas, a total of 127 plant species belong to 114 genera and
51 families were recorded. In addition, dicotyledons are dominant plant group and representated
by 114 species (89.47%). In addition, maximum species (76 Nos.) were recorded from agriculture
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
97
& road side habitat and followed by wasteland/habitation/gauchar land habitat (70 species) and
wetland/ riverine areas (51 species).
Status of Life form
Study area reported 127 plant species and they formed 13 sub-categories of lifeforms within five
main categories. Among the life forms, herb was dominated by recording 50 species and
contributed maximum of 39.37% of the total list of plants followed by trees (33 species and
25.98%). Third dominating life form was shrub species (24) and shared 18.90%. The contribution
other life forms were less than 10% of the species list.
Common/Domestic Tree species
A total of 12 common tree species were identified with a total of 34 trees within the sample plots
of the study area. Among the species, Acacia nilotica, Azadirachta indica and Prosopis cineraria
was enumerated maximum times in and around the settlement areas.
Table 3.17 Common Tree species
Sr. No Species Name Local Name Habit Family
1 Acacia nilotica (L.) Del. subsp.
indica(Bth.) Brenan
Deshi Baval,
Bavar
Tree Mimosaceae
2 Albizia lebbeck (L.) Bth. Karo Sirish Tree Mimosaceae
3 Azadirachta indica A. Juss. Limbdo, Neem Tree Meliaceae
4 Cassia siamea Lam. Kasid Tree Caesalpiniaceae
5 Cordia gharaf (Forsk.) E.&.A. Gundi Tree Ehretiaceae
6 Delonix regia (Boj.) Raf. Gulmohor Tree Caesalpiniaceae
7 Derris indica (Lam.) Bennet Karanj Tree Fabaceae
8 Ficus benghalensis L. Vad Tree Moraceae
9 Leucaena latisiliqua (L.) Wt. &
Arn.
Liso Bavar Tree Mimosaceae
10 Mangifera indica L. Keri Tree Anacardiaceae
11 Peltophorum pterocarpum (DC.)
Backer ex Heyne
Tamrafali Tree Caesalpiniaceae
12 Polyalthia longifolia (Sonn.) Thw. Asopalav Tree Annonaceae
Wild/Forest Tree Species
Within the study area only 3 wild/forest tree species have been recorded which were belonging
to 2 families and 3 genera. Since the area are dominant with agriculture habitat, and hence, very
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
98
few trees were recorded under this category and it indicates low density of wild tree species in
and around the study area.
Table 3.18 Wild/Forest Tree species
Sr.No Species Name Local Name Habit Family
1 Acacia leucophloea Harmo Bavar Tree Mimosaceae
2 Salvadora oleoides Mitha Pilu Tree Salvadoraceae
3 Prosopis cineraria Khijado, Hangar Tree Mimosaceae
Status of Agriculture Crops
Based on the intensive field survey in and around the agricultural area and dialogue with the local
farmers a total of more than 10 species have been listed from the study area as crop species.
Fruit and vegetable crops were found cultivated along the agricultural hedges in a small extent of
area. In the study area, Dangar, Bajri (Pennisetum typhoides) and Ghahun (Triticum asetivum)
are the major crops cultivated extensively.
Table 3.19 Agriculture Crop
Sr.No Species Name Local Name Habit Family Season
1 Zizyphus sp Bor Small Tree Rhahmnaceae All
2 Gossypium
herbaceum auct.
Non L. var.
acerifolium (Guill. &
Perr.) Chevalier
Kapas Shrub Malvaceae Monsoon
3 Vegetables mixed Kakadi,
Dudhi,
Gavar, Chori
Climber
and
Herb
Cucurbitaceae
Fabaceae
All
4 Pennisetum
typhoides A. Rich.
Bajri, Bajaro Grass Poaceae Summer
Monsoon
5 -- Ghahun Grass Poaceae Winter
6 -- Tal Herb Pedaliaceae Monsoon
7 -- Makai
Fodder
Herb Poaceae Summer
Monsoon
8 -- Jovar
Fodder
Herb Poaceae Summer
Monsoon
9 -- Dangar Herb Poaceae Summer
10 -- Sherdi Herb Poaceae Monsoon
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
99
3.13.2. Fauna
Herpetofauna
Status of herpetofauna was assessed using Intensive Time Constrained Search Method covering
different micro habitats (Welsh, 1987, Welsh and Lind 1991). This intensive search was made in
different habitat types randomly selected.
Table 3.20 Herpetofauna
Family & Species Name Common and Local Name IUCN Status
Euphlyctis cyanophlyctis Skittering frog (Dedako) LR-nt
Hemidactylus brookii Spotted Indian House Gecko (Garodi) LR-lc
Calotes versicolor Indian Garden Lizard (Kachindo) LR-nt
Sitana ponticeriana Fan-Throated Lizard (Kachindi) LR-lc
Eryx johnii Eastern Red Sand Boa (Dhomalo) LR-lc
Ptyas mucosa Indian Rat Snake (Nag) LR-nt
Lissemys punctata Indian Mud or Flap-shell Turtle
(Kachbo)
--
Birds
Avifaunal status was assessed both in terrestrial and aquatic habitats. Total count or flock count
method was adopted to assess the status of aquatic birds in the existing water bodies (Sridharan
1989 and Bhupathy 1991). Point count method was used to assess the status of terrestrial birds
(Bibby et al., 1992 and Hutto et al., 1986). The second technique adopted was area search
method (Dieni and Jones 2002), a time area constrained survey technique that has been widely
and commonly used in several bird monitoring programs.
Table 3.21 Birds
Species name Common
English name
MS Sch. FG
Pavo cristatus Indian Peafowl R I G
Sarkidiornis
melanotos
Comb Duck R IV A
Upupa epops Common
Hoopoe
RM IV I
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
100
Species name Common
English name
MS Sch. FG
Coracias
benghalensis
Indian Roller R IV I
Alcedo Hercules Common
Kingfisher
R IV P
Halcyon
smyrnensis
White-throated
Kingfisher
R IV P
Ceryle rudis Lesser Pied
Kingfisher
R IV P
Merops orientalis Green Bee-
eater
R IV I
Eudynamys
scolopacea
Asian Koel R IV F
Centropus sinensis Greater Coucal R IV O
Psittacula krameri Rose-ringed
Parakeet
R IV F
Apus affinis House(Little)
Swift
R IV I
Athene brama Spotted Owlet R IV C
Columba livia Rock Pigeon R IV G
Streptopelia
tranquebarica
Red-collared
Dove
R IV G
Gallinula chloropus Common
Moorhen
R IV A
Fulica atra Common Coot R IV A
Actitis hypoleucos Common
Sandpiper
R IV A
Vanellus indicus Red-wattled
Lapwing
R IV I
Accipiter badius Shikra R I C
Circius
melanoleucos
Pied Harrier RM I C
Falco tinnunculus Common
Kestral
RM IV C
Phalacrocorax
niger
Little Cormorant R IV A
Ardea cinerea Grey Heron RM IV A
Bubulcus ibis Cattle Egret R IV AI
Threskiornis
melanocephalus
Black-headed
Ibis
RM IV A
Pseudibis papillosa Black Ibis R IV I
Corvus splendens House Crow R V I
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
101
Species name Common
English name
MS Sch. FG
Dicrurus
macrocercus
Black Drongo R IV I
Saxicoloides
fulicata
Indian Robin R IV I
Acridotheres
ginginianus
Bank Myna R IV I
Acridotheres tristis Common Myna R IV I
Hirundo daurica Red-rump
Swallow
R IV I
Pycnonotus cafer Red-vented
Bulbul
R IV I
Turdoides malcolmi Large Grey
Babbler
R IV G
Galerida cristata Crested Lark R IV GI
Nectarinia asiatica Purple Sunbird R IV N
Passer domesticus House Sparrow R IV G
Mammals
Status and distribution of different mammal species was quantified using Direct count Vehicle
transects (travelling between the sampling location) (Burnham et al. 1980) and indirect evidences
within the survey areas (Rodgers 1988 and Sale and Berkmuller, 1988). Indirect evidences like,
Pellet, dung, tracks (Thommpson et al 1989, Allen et al 1996), scat count (Henke and knowlton
1995) and other signs were enumerated using standered method for nocturnal species (Daniels
1992). Presence of different faunal species was also substantiated by interviewing the local
people and experts with pictorial representation.
Table 3.22 Mammals
Scientific Name Common Name Food Habit
Boselaphus tragocamelus Nilgai Herbivore
Canis aureus Golden Jackal Omnivore
Herpestes edwardsii Grey Mongoose
Omnivore
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
102
Scientific Name Common Name Food Habit
Hyaena hyaena Striped Hyena Scavenger
Hystrix indica Indian Porcupine
Herbivore
Sus scrofa Wild Boar
Herbivore
3.14. Socio-Economic Environment
3.14.1. Demographic and Socio-Economic Features
Demography is one of the important indicators of environmental health of an area. It includes
population, number of households, literacy, population density, etc. In order to assess the
‘Demographic and Socio-economic Features’ of the study area, census data of 2011, for the
concerned District Ahmedabad in Gujarat State was compiled and placed in the form of tabulation
and graphical representation.
Population
Total Population of the Study area as per Census of India, 2011 is 57008.The total number of
Household being 11040.Total Male Population of the Study area is 29415 and total Female
Population of the Study Area is 27593.Village-wise details of population are given in Table 3.23
Table 3.23 Village-wise Population Details
S.N. Name of
Village
No of
Households
Total
Population
Person
Total
Population
Male
Total
Population
Female
1 Zolapur 881 4807 2509 2298
2 Bol 454 2150 1110 1040
3 Kunvar 891 4504 2335 2169
4 Hirapur 395 2026 1030 996
5 Charal 419 1985 997 988
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
103
6 Daduka 440 2360 1222 1138
7 Melasana 339 1912 998 914
8 Makhiyav 757 3887 1997 1890
9 Vinchhiya 480 2427 1261 1166
10 Kodaliya 191 1009 525 484
11 Juda 424 2330 1163 1167
12 Mankol 1120 5862 3042 2820
13 Kundal 419 2016 1032 984
14 Rethal 718 3585 1867 1718
15 Govinda 188 844 442 402
16 Juwal 886 4545 2320 2225
17 Nanodara 622 3329 1691 1638
18 Kavla 403 1958 1045 913
19 Sankod 535 2724 1409 1315
20 Vasna
Dhedhal
478 2748 1420 1328
Total 11040 57008 29415 27593
Gender Ratio
The ‘Sex Ratio’ is a numeric relationship between females and males of an area and bears
paramount importance in the present-day scenario where the un-ethnic predetermination of sex
and killing of female foetus during pregnancy is practiced by unscrupulous medical practitioners
against the rule of the law of the country. It is evident that by contrast the practice of female
foeticide is not prevalent in the study area.
The Sex Ratio of the Study area is 106.6. Tehsil-wise population of the study area is represented
in below figure.
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
104
Scheduled Caste &Scheduled Tribe Population
A considerable 12.5% of the population in the Study Area is constituted by SC/ST, out of which
SC population constitutes 12.46% and rest 0.03 % is constituted by ST Population. Comparative
graphs of SC/ST Population in Study Area are given in below figure
Literacy Rate
Literacy level is quantifiable indicator to assess the development status of an area or region.
Male Population
52%
Female Population
48%
GENDER RATIO
SC12% ST
0%
General88%
POPULATION DISTRIBUTION
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
105
Literacy Rate of the study area is 52.96% Distribution of male 33.58% and female literacy rate
19.38% in the study zone is and respectively. Gender-wise distribution of literacy of Study Area
is given in below figure.
3.9.3. Workers Scenario
Occupational Pattern
Occupational pattern was studied to assess the skills of people in the study area. Occupational
pattern helps in identifying major economic activities of the area. The main and marginal-workers
population with further classification as casual, agricultural, households and other workers.
Worker Scenario
Workers Participation Ratio of the worker population is 39.97%, non-workers 60.03% population.
Literate53%
Illiterate 47%
LITERACY RATE
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
106
Worker40%
Non-Worker60%
WORKER SCENARIO
Main Worker81%
Marginal Worker19%
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
107
Main Cultivator Population Person
48%Main Agricultural
Labourers Population Person
36%
Main Household Industries
Population Person1%
Main Other Workers
Population Person15%
MAIN WORKER DISTRIBUTION
Marginal Worker Population Person
50%
Marginal Cultivator Population Person
9%
Marginal Agriculture Labourers
Population Person37%
Marginal Household Industries
Population Person0%
Marginal Other Workers Population
Person4%
MARGINAL WORKER DISTIBUTION
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
108
CHAPTER 4. IMPACTS ASSESSMENT AND PREDICTION
4.1. General
Impacting activities are defined as elements of organization's activities that can interact with the
environment. These include activities during normal and abnormal actions of Residential,
commercial and education units. Environmental impacts are defined as any change in
environment, whether adverse or beneficial, wholly or partially, resulting from impacting activities.
The environmental indices (or parts of the receiving environment on which impacts are being
predicted) are ambient air, water, noise, land, flora and fauna, infrastructure, and socio-economic
environment. Thus, we predict the environmental impacts of the impacting activities on the
environmental indices. In this chapter we covered the cumulative impact considering approved
TOR.
The possible impact on various components of environment due to the proposed project of Asiatic
Composite Limited can be assessed in terms of:
Beneficial or detrimental
Naturally reversible or irreversible
Repairable via management practices or irreparable
Short term or long term
Temporary or continuous
Occurring during construction phase or operational phase
Local, regional, national or global
Accidental or planned (recognized beforehand)
Direct (primary) or Indirect (secondary)
Cumulative or single
Significant
And on:
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
109
Physical
Biological Environment and
Demographic and Socio-economic Environment.
For proper assessment of significance and magnitude of environmental changes due to
construction and operational phases of the plant, the impacts are analyzed on the 10 km radius
study area around the proposed plant site for each environmental parameter. Impact assessment
study for the Asiatic Composite unit is carried out by predicting net contribution of pollutants
(qualitative as well as quantitative) on overall qualitative assessment of various environmental
indicators. Prediction of impacts is an important component in environmental impact assessment
process. Several techniques and methodologies are in vogue for predicting the impacts due to
existing and proposed industrial development on physico-ecological and socio-economic
components of environment. Such predictions delineate contribution in existing baseline data for
the operational project and superimpose over the baseline (pre-project) status of environmental
quality to derive the ultimate (post-project) scenario of the environmental conditions due to the
proposed project. The quantitative prediction of impacts leads to delineation of suitable
environmental management plan needed for implementation during the construction,
commissioning and operational phases of the proposed project in order to mitigate the adverse
impacts on environmental quality.
4.2. Construction Phase
The activities of proposed expansion program will be confined to the project site within the
boundary of Plant complex. The present project activities will not cause any significant loss of any
important flora.
Emission /Gaseous pollution
Due to different vehicular movement, construction machineries and project construction activities
(Bulk solids handling), the concentration of air pollutants can be increased. These pollutants can
affect the surrounding vegetation and nearby agricultural crops. There will be limited construction
activities at Asiatic Composite Limited.
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
110
Dust / Fumes (from machineries) Generation
Terrestrial flora can be affected by the dusty/ fumes environment to be created due to vehicular
movement/ machineries during construction phase. Increment in the density of the dust particles
(SPM)/ fumes having Sox /NOx /HC in the atmosphere can affect the surrounding plant/
vegetation in following ways:
a) Blockage and damage to stomata
b) Reduction in chlorophyll content
c) Abrasion of leaf surface or cuticle
All these disturbances ultimately affect photosynthesis process and plant metabolism that leads
to reduction in plant growth up to some extent.
Noise Pollution
Noise level of the project area will be increased during construction phase. Although there is no
specific noise-sensitive fauna has been recorded near to project site but limited avifauna and
small animals in the industrial area can be affected by increased noise level. In such cases they
can change their habitat.
Congregation of Labour
Construction activities often require a considerable workforce and associated support services.
The livelihood activities of this increased human population may contribute to local environmental
impacts in terms of collecting firewood and food as well as enhancing recreational activities.
The impacts during construction phase normally are:
Detrimental
Naturally reversible
Short term
Temporary
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
111
Local
Direct
Mitigation Measures:
Gaseous pollution
The pollutants (SPM, SOx, NOx, HC and others) in ambient air of the study area are low.
Development of multi-layer plantation (green belt) around the proposed project area will further
help to mitigate gaseous pollution within and around the project area.
Dust Generation
Dust generation during construction period will be managed through:
Water spraying on rough roads, on powdery construction materials etc.
Land / Soil
As this is an expansion project, there will be construction activities to be carried out. There will
also be installation of new machineries and equipment. But all this would not make a huge
damage to the present condition of land. Further the area of the plant is flat. Much leveling would
not be required. Thus, topography will also remain unchanged after execution of the proposal.
Thus, the impact on the land/soil during the construction will for short terms and insignificant.
Effluent discharge
There will be a negligible discharge of effluent from the proposed plant due to construction
activities, which will be directly sent to Soak pit through septic tank. Safe guard for rainy season
runoff will be taken to prevent any direct discharge from the plant to nearby water body. As such
the water ecology will not be affected, the domestic effluent will be discharged through septic tank
into soak pit.
Congregation of Labour
The impacts will be managed through:
No permanent camping in vegetation rich area and riverside
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
112
A provision of fuel for labourers engaged in construction activities
Restriction on poaching/hunting and removal of any vegetation
Based on the field observations and interaction with local people and forest officials, it was noticed
that the project area is not associated with any National Park/Wildlife Sanctuary/Conservation
Reserve and there are no wildlife migratory routes present in the project area. Improvement in
the green cover under a regular plantation program (Greenbelt Development Program) will not
only increase the plant diversity in the area but also enhance the habitat for wildlife especially for
avifauna.
4.3. Operation Phase
4.3.1. Air Environment
The pre-project (baseline) ambient air quality status in the study area indicates that all the criteria
pollutants are well within the prescribed National Ambient Air Quality Standards (NAAQS) for
industrial, residential, rural and other areas.
The ambient air quality with respect to air pollutants will change during the operation phase of the
proposed project. However, adequate stack height will be provided for better dispersion of flue
gas as per the guidelines of GPCB/CPCB. In addition to that, adequate greenbelt will be
developed for further control of air pollution.
Compliance with the existing ambient air quality standards will be achieved by implementation of
the measures as outlined in EMP. This needs to be coupled with the continuous monitoring of air
pollutants within and around the project site as well as in adjoining areas.
To assess the impact of air emissions from various continuous point sources, air dispersion
modelling study has been conducted with the help of AERMOD Cloud 5 of Envitrans. Detailed
description has been given in the following sub-sections:
Model Details
Air dispersion modelling can be used to predict atmospheric concentrations of pollutants at
specific locations (receptors) over specific averaging times (i.e. annual, daily, and hourly). An
atmospheric dispersion model accounts for the emissions from a source; estimates how high into
the atmosphere they will go, how widely they will spread and how far they will travel based on
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
113
temporal meteorological data; and outputs the pattern of concentrations that will occur for various
exposure periods, thereby providing the exposure risks for different receptors.
In the proposed project, prediction of impacts on air environment has been carried out employing
mathematical model based on a Steady State Gaussian Plume Dispersion Model designed for
multiple point sources for short term. In the present case, AERMOD dispersion model based on
steady state Gaussian Plume Dispersion, designed for multiple point sources for short term and
developed by United States Environmental Protection Agency (USEPA) has been used for
simulations from point sources.
The predictions for air quality during operation phase were carried out for particulate matter less
than 10 microns (PM10), particulate matter less than 2.5 microns (PM2.5), oxides of Nitrogen
(NOx) and oxides of Sulphur (SOx) concentration using AERMOD.
The options used for short-term computations are:
The plume rise is estimated by Briggs formulae, but the final rise is always limited to that
of the mixing layer
Stack tip down-wash is not considered
Buoyancy induced dispersion is used to describe the increase in plume dispersion during
the ascension phase
Calms processing routine is used by default
Wind profile exponents is used by default
Flat terrain is used for computation
Pollutants do not undergo any physico-chemical transformation
No pollutant removal by dry deposition
Universal Transverse Meter (UTM) coordinates have been used for computation
A uniform polar grid was used for the computation and extended to 10 km from the center
of the proposed project. In addition to that, receptors were also placed at the sampling
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
114
locations.
Emissions
The main sources of air pollution due to the operation of the plant are the steam boiler and hot air
generator. The stack parameters of the sources are listed in Table 4.1.
Table 4.1 Stack Parameters of Proposed Sources
S.
No. Stack
Stack
Height
(m)
Stack
Diameter
(m)
Stack Exit
Velocity
(m/s)
Emissions
1 Thermic Fluid
Heater 12.0 0.1 4.11
PM<150 mg/Nm3
SO2 < 100 ppm
NOx < 50 ppm
Meteorological Data
The meteorological data consists of wind speed, direction, temperature, humidity, solar radiation,
cloud cover and rainfall recorded during the months of December, 2017, through February, 2018,
on an hourly basis. Wind speed, wind direction and temperature have been processed to extract
the 24–hour mean meteorological data for application in AERMOD.
Receptor Locations
A total of about 728 receptors – 720 receptors of which were generated with a polar grid from the
center of the proposed project and extended to 10 km. Apart from these receptors, the sampling
locations were also taken into account to assess the incremental load on the baseline
environmental scenario.
Ground level conc. for PM10
The summary of maximum ground level concentrations (GLC) for the proposed project is listed in
Table 4.2.
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
115
Table 4.2 Summary of Maximum 24-hour GLC due to the Proposed Project
Description Concentration ( g/m3)
PM10 PM2.5 NOx SOx
Maximum Rise in GLC 0.04 0.02 0.07 0.18
Distance of occurrence
(km) 1.5 1.5 1.5 1.5
Direction of Occurrence SSW SSW SSW SSW
Maximum Baseline
Concentration reported 60.40 40.90 20.30 25.60
Total Concentration 60.44 40.92 20.37 25.78
Prescribed Standards 100 60 80 80
The above table shows that in the worst-case scenario, the maximum ground level concentration
due to the proposed project will be in the predominant SSW direction. In the post-project scenario,
the 24-hour average concentration for all the criteria pollutants are well within the ambient air
quality standards for industrial, residential, rural and other areas in the worst case. The isopleths
of the pollutant concentration due to the impacts associated with the operation of the Plant are
shown in Figures 4.1 through 4.4 for PM10, PM2.5, NOx and SOx respectively.
Additionally, the cumulative impact of the proposed project at the monitoring locations within 10
km radius is provided in Table 4.3.
Table 4.3 Summary of Maximum GLC at Monitoring Locations due to the Proposed Project
Location Rise in GLC
(µg/m3)
Max.
Background
Concentration
(µg/m3)
Impact from
Project
(µg/m3)
NAAQS
(µg/m3)
Project Site
PM10 0.00E+00 60.4 60.40 100
PM2.5 0.00E+00 40.9 40.90 60
NOx 0.00E+00 20.3 20.30 80
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
116
Location Rise in GLC
(µg/m3)
Max.
Background
Concentration
(µg/m3)
Impact from
Project
(µg/m3)
NAAQS
(µg/m3)
SOx 0.00E+00 25.6 25.60 80
Mankol
PM10 3.15E-03 52.2 52.20 100
PM2.5 1.26E-03 35.6 35.60 60
NOx 5.29E-03 18.6 18.61 80
SOx 1.48E-02 17.8 17.81 80
Charal
PM10 1.00E-03 51.8 51.80 100
PM2.5 4.00E-04 37.4 37.40 60
NOx 1.68E-03 16.5 16.50 80
SOx 4.70E-03 16.6 16.60 80
Kavla
PM10 9.00E-05 54.6 54.60 100
PM2.5 4.00E-05 36.2 36.20 60
NOx 1.60E-04 15.6 15.60 80
SOx 4.30E-04 19.2 19.20 80
Vinchhiya
PM10 6.90E-04 55.2 55.20 100
PM2.5 2.80E-04 35.2 35.20 60
NOx 1.16E-03 18.1 18.10 80
SOx 3.25E-03 21.5 21.50 80
Kundal
PM10 1.55E-02 57.4 57.42 100
PM2.5 6.19E-03 38.2 38.21 60
NOx 2.61E-02 16.8 16.83 80
SOx 7.28E-02 17.5 17.57 80
Rethal PM10 7.05E-03 57.2 57.21 100
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
117
Location Rise in GLC
(µg/m3)
Max.
Background
Concentration
(µg/m3)
Impact from
Project
(µg/m3)
NAAQS
(µg/m3)
PM2.5 2.82E-03 39.2 39.20 60
NOx 1.19E-02 15.9 15.91 80
SOx 3.32E-02 20.1 20.13 80
Daduka
PM10 8.50E-04 55 55.00 100
PM2.5 3.40E-04 37.6 37.60 60
NOx 1.44E-03 17.7 17.70 80
SOx 4.01E-03 15.6 15.60 80
Discussion of the Cumulative Impacts at monitoring locations:
PM10: The total impacts from the project (proposed project and baseline contribution) indicate
maximum PM10 concentration of 60.40 µg/m3 at the Project Site with project impacts of 0.0 µg/m3
and baseline contribution of 60.40 µg/m3. The total impact from the project is well within the
stipulated standard of 100 µg/m3 for industrial as well as residential areas.
PM2.5: The total impacts from the project (proposed project and baseline contribution) indicate
maximum PM2.5 concentration of 40.90 µg/m3 at the Project Site with project impacts of 0.0
µg/m3 and baseline contribution of 40.90 µg/m3. The total impact from the project is well within
the stipulated standard of 60 µg/m3 for industrial as well as residential areas.
NOx: The total impacts from the project (proposed project and baseline contribution) indicate
maximum NOx concentration of 20.30 µg/m3 at the Project Site with project impacts of 0.0 µg/m3
and baseline contribution of 20.30 µg/m3. The total impact from the project is well within the
stipulated standard of 80 µg/m3 for industrial as well as residential areas.
SOx: The total impacts from the project (proposed project and baseline contribution) indicate
maximum SOx concentration of 25.60 µg/m3 at the Project Site with project impacts of 0.0 µg/m3
and baseline contribution of 25.60 µg/m3. The total impact from the project is well within the
stipulated standard of 80 µg/m3 for industrial as well as residential areas.
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
118
As is evident from the table and discussion above, there will be no adverse impacts on the
surrounding area. Highly efficient air pollution control systems will be adopted to mitigate
particulate matter as well as gaseous emissions in the ambient environment.
Figure 4.1 Isopleth for PM10 GLC due to operation of Proposed Project
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
119
Figure 4.2 Isopleth for PM2.5 GLC due to operation of Proposed Project
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
120
Figure 4.3 Isopleth for NOx GLC due to operation of Proposed Project
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
121
Figure 4.4 Isopleth for SOx GLC due to operation of Proposed Project
Mitigation Measures:
The ambient air quality with respect to air pollutants will change during the operation phase of the
proposed project. However, adequate stack height has been provided for better dispersion of flue
gas as per the guidelines of CPCB. In addition, all process stacks have been provided with high
efficiency scrubbing system to control the emission within norms. In addition to that, adequate
greenbelt will be developed for further control of air pollution.
Compliance with the existing ambient air quality standards will be achieved by process system
selection as outlined above, proper system operation and implementation of the measures as
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
122
outlined in EMP. This needs to be coupled with the continuous monitoring of air pollutants within
and around the project site as well as in adjoining areas.
Environmental impacts (AAQ) resulting from proposed project can be grouped into following
Categories:
Beneficial or detrimental --detrimental
Naturally reversible or irreversible---Reversible
Repairable via management practices or irreparable—Repairable to some extent through
Green Belt development
Short term or long term---Short term
Temporary or continuous -- Continuous
Occurring during construction phase or operational phase—Operation Phase
Local, regional, national or global--Local
Accidental or planned (recognized beforehand) --Planned
Direct (primary) or Indirect (secondary)-- Direct
Cumulative or single -- Single
4.3.2. Noise Environment
The sources of noise during the operational phase of the plant are mainly from process
equipment. The other sources of noise are the movement of vehicles along the road. Moving
machineries will be selected with caution as regard to low noise generation as well as low energy
consumption.
Impacts due to Transportation
Noise level contributed from increased movement of light medium and heavy vehicles on the
roads both within and outside the plant can be considerable depending upon the traffic density.
The heavy commercial vehicles traffic is limited depending upon the material receipt and dispatch
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
123
of products through road transport. The major quantity of products will be dispatched through
roads.
Impact of noise on community
Equivalent sound levels are often used to describe community exposures to noise. Noise survey
was also carried out at eight locations outside the plant area but within the study area. Ambient
noise level of the study area is within the prescribed National Ambient Noise Quality Standard for
respective residential, commercial and industrial category at all the monitored locations which is
well within the day and night time standard (commercial).
The operation of proposed project will have the noise level not much exceeding the present noise
level and as such will not have any adverse impact on the human settlement around it. The noise
will not be audible beyond its boundary limit, particularly due to natural green belt and other
attenuators.
Mitigation Measures:
Noise from the plant is to be limited through:
a. High noise machineries (DG sets etc.) should have acoustic enclosures.
b. Proper / regular maintenance of machineries.
Regular noise monitoring in work area. Any abnormal noise level to be investigated and noise
source attended.
Green belt development to arrest noise from going outside the plant.
Environmental impacts (Noise) resulting from proposed project can be grouped into following
Categories:
Beneficial or detrimental --detrimental
Naturally reversible or irreversible---Reversible
Repairable via management practices or irreparable—Repairable to some extent through
Green Belt development
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
124
Short term or long term Short term
Temporary or continuous -- Continuous
Occurring during construction phase or operational phase—Operation Phase
Local, regional, national or global--Local
Accidental or planned (recognized beforehand) -- Planned
Direct (primary) or Indirect (secondary)-- Direct
Cumulative or single—Single
4.3.3. Water Environment
Impact on water environment due to Asiatic Composite Limited proposed project scheme will be
in terms of additional water consumption {water demand} and waste water generation after
treatment will be recycled and reused.
Water Demand
The requirement during construction period will be much less as compared to that during
operation and will be met from Surface water and ground water or both.
Water during operational phase is normally required for:
Industrial: 0.7 KLD
Domestic: 2.7 KLD
Total water requirement will be around limited (3.4 KLD). The total fresh water requirement of the
proposed project will be 2.7 KLD and 0.7 KLD water will recycled and used.
The domestic wastewater generated from the toilets, washrooms and canteen of the plant shall
be sent to STP (Sewage Treatment Plant). No wastewater will be discharged outside the plant
premises during non-monsoon and under normal operating conditions, unit followed the zero
discharge concepts.
Mitigation Measures:
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
125
Water consumption to be controlled though eliminating / reducing any water wastage –leakages/
spillage.
a. Process control
Regular monitoring of effluent sources to ETP will show process conditions and deviation from
optimum water consumption.
ETP – performance for maximum recycle of treated water.
Environmental impacts (Water) resulting from proposed project can be grouped into following
Categories:
Beneficial or detrimental--detrimental
Naturally reversible or irreversible---Reversible
Repairable via management practices or irreparable—Repairable to some extent
Short term or long term Short term
Temporary or continuous --continuous
Occurring during construction phase or operational phase—Operation Phase
Local, regional, national or global--Local
Accidental or planned (recognized beforehand) -- Planned
Direct (primary) or Indirect (secondary)—Direct
Cumulative or single—cumulative
4.3.4. Land/Soil Environment
Essentially, the two major impacts normally faced in impact on land environment due to any
development project are:
Diversion of land from designated use to the Project Use.
Deterioration of land / soil in terms of soil fertility and toxicity.
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
126
Land Diversion
Existing plant land is already for industrial use.
Land Deterioration
The hazardous waste is generated at various stages of the manufacturing activity. The mode of
disposal is mentioned for each category of waste as per hazardous wastes (management,
handling and trans -boundary movement) rules, 2016.
Hazardous wastes will be stored at earmarked area with impervious flooring, shed and spillage/
leakage collection system to eliminate rainwater contamination, chances of overflow / spillages
going on to the land and thus land/ soil contamination.
Solid waste:
Solid/Hazardous Waste
Hazardous/solid waste generation will be the main source of impact on the soil environment.
Entire quantity of hazardous waste will be handled and disposed as per Hazardous Waste
(Management, Handling and Trans boundary movement) Rules 2016, Most of the hazardous
waste will be collected, stored and sent /will be disposed off as per the hazardous waste
management rules.
4.3.5. Biological Environment
Though the concentrations of the emitted pollutants will be kept within permissible levels through
the various engineering controls, it is essential to have eco-management in the Likely Impact
Zone for safeguard and enhanced of ecological environment of the project area. The likely
impacts and mitigation measures associated with different phases due to various project activities
area describes in following Table.
Project
Aspect
Description
Likely Impacts on
Ecology and
Biodiversity (EB)
Impact
Consequence –
Probability
Description/
Justification
Mitigation
measures
Type
Pre-Construction Stage Impacts
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
127
Removal of
site
vegetation
like herbs,
shrubs and
grasses
site specific loss
of common floral
diversity
Site specific loss
of associated
faunal diversity
Site specific loss
of habitat /
habitat diversity
No major
vegetation is
present on site.
Site possesses
common floral
species; This will
be site specific
impact.
Subject to
periodic
monitoring
/surveillance.
However,
greenbelt
/plantation
will be developed
in project site and
in periphery of the
project boundary,
which will improve
floral diversity of
the area.
Short term
Construction Stage Impacts
Dust and
Noise
Generation
due to
movement of
JCBs, other
machinery,
and other
construction
activities
Site specific
disturbance to
faunal species
Dust settlement on
vegetation
No endangered
fauna reported from
the site as well as in
study area.
The species
reported from
project site and
buffer zone are
common / generalist
species and not
very sensitive to the
routine activities, so
there will be no
threat of facing
disturbance.
However, its site
specific and
temporary impact.
Subject to
periodic
monitoring and
surveillance.
Water sprinkling
for Dust
suppression.
Construction
activities shall be
restricted in night
time.
Short term
Operation Stage Impact
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
128
Emission of
PM, NOx,
SOx, due to
operation
(Indirect
impact on
crops, trees
and shrubs of
vicinity due to
contamination
of ambient air,
dust
emission,
vehicular
exhaust)
Noise
Generation
(Disturbance
to sensitive
terrestrial
fauna due to
noise
pollution)
Impact on
surrounding
vegetation and
associated
biodiversity.
Though the
emission levels of
all pollutants will be
kept within
permissible limits.
APCD shall be used
to control dust
emissions from
various sections of
plant.
The incremental air
pollution will not
violate the air quality
standards.
Proposed plant is
zero liquid
discharge basis so
no waste water will
be discharged.
Greenery
development will be
done in and around
the plant site.
Such measures will
be adequate to
protect the noise
and air pollution
impacts.
Operation subject
to management
by operational
controls.
Emission levels of
all pollutants will
be kept within
permissible levels
through various
engineering
control measures.
However, green
belt development
with suitable
species will help
to mitigate likely
cumulative
impacts.
Long term
(insignificant)
Construction Stage Impacts
Excavation and filling up operation may result in fugitive dust emission. The dust deposition on
pubescent leaves of the surrounding vegetation may leads to temporary reduction of
photosynthesis. Such impacts would however be confined mostly to the initial period of the
construction phase and would minimized through paving of roads, surface treatment, regular
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
129
water sprinkling in dust generating areas and greenbelt development. The impact on the ecology
of the surrounding area during the construction stage will be insignificant in nature. Greenbelt
development along the plant boundary, development of gardens and lawns will mitigate the
residual impact on natural resources.
Operation stage Impacts
No national park, wildlife sanctuary, biosphere reserve exists within 10 km area of the project. No
endangered or rare or threatened plant or animal species was observed within 10 km area of the
project site. The impact on the surrounding ecology during the operation of the project will mainly
occur from the deposition of air pollutants. Air pollution affects the biotic and abiotic components
of the ecosystem individually and synergistically with other pollutants. Chronic and acute effects
on plants and animals may be induced when the concentration of air pollutants exceeds threshold
limits. Particulate emission and other gaseous emissions from the proposed plant are the major
pollutant that may affect the ecology of the area. The incremental emission of air pollutants is not
likely to induce any significant changes in the ecology because the national ambient air quality
standards will remain within the limits.
4.3.6. Socio – Economic Environment
Asiatic Composite proposed project will generate employment opportunities some through direct
employment and more so indirectly through services for the plant.
Proposed project will have some impacts also on socio – economic environment of the
study area- some are as given below:
Proposed project will result in handling of product and raw material, which will increase
manpower requirement at various stages directly, or indirectly resulting in more income of
people.
Proposed project would increase requirement from ancillary and auxiliary industries in the
vicinity.
With more load on infrastructure facilities – roads and rails; these facilities would need
improvement.
More income to Government through more taxes on higher amount of production.
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
131
CHAPTER 5. ENVIRONMENTAL MANAGEMENT PLAN MONITORING PROGRAM
5.1. Introduction
Any industrial development is associated with certain positive impacts as well as some negative
impacts on the environment. However, the negative or adverse impacts cannot possibly rule out
scientific development. At the same time, adverse impacts cannot be neglected. An
Environmental Management Plan has been formulated for mitigation of the adverse impacts and
is based on the present environmental conditions and the environmental impact appraisal. This
plan helps in formulating, implementing and in monitoring the environmental parameters during
and after commissioning of the project. The Environmental Management Plan describes, in brief,
the management's plan for proper and adequate implementation of treatment and control system
for air and liquid pollutants and for maintaining the environment. It also includes development of
green belts around the Plant, proper safety of the workers, noise control, fire protection systems
and measures. This chapter provides mitigation and control measures to attenuate or eliminate
environmental impacts, which are likely to be caused by the proposed project. An Environmental
Management Plan (EMP) has been developed to mitigate the potential adverse impacts and to
strengthen the beneficial environmental impacts as well as to create positive environmental
footprints during the construction and operation phases. In addition to that during the operation
phase, the company will have an additional responsibility to comply with the statutory
requirements as per the guidelines of Central/ State Government.
5.2. Environment Management Plan
The Environmental Management Plan (EMP) consists of a set of mitigation, monitoring and
institutional measures to be taken during the design, construction and operation (post
construction) stages of the project. The plan also includes the actions needed for implementation
of these measures.
Overall objective of EMP:
Prevention: Measures aimed at impeding the occurrence of negative environmental impacts
and/or preventing such an occurrence having harmful environmental impacts.
Preservation: Preventing any future actions that might adversely affect an environmental
resource or attribute.
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
132
Minimization: Limiting or reducing the degree, extent, magnitude, or duration of adverse impacts.
The major components of the Environmental Management Plan are:
Mitigation of potentially adverse impacts
Monitoring during project implementation and operation
Implementation schedule and environmental cost estimates
Integration of EMP with project planning, design, construction and operation.
The EMP has been designed keeping in view the regulatory and other requirements to ensure
the following:
Minimum disturbance to the native flora and fauna.
Compliance with the air, water, soil and noise quality norms.
Conservation of water to the extent possible.
Encourage the socio-economic development.
5.3. Objectives of EMP
The main objectives in formulating this environmental management plan are:
To treat all the pollutants viz., liquid and gaseous which contribute to the degradation of
the environment, with appropriate technology.
To comply with all regulations stipulated by the Central / State Pollution Control Boards
related to air emissions and liquid effluents discharges as per air and water pollution
control laws
To handle hazardous wastes as per the Hazardous Waste (Management and Handling
Rules, 1989 of the Environment (Protection) Act, 1986
To encourage support and conduct developmental work for the purpose of achieving
environmental standards and to improve the methods of environmental management.
To promote further afforestation in the surrounding areas of the Plant
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
133
To create good working conditions (devoid of air and noise pollution) for employees
To reduce fire and accident hazards
Perspective budgeting and allocation of funds for environment management expenditure
Dissemination of technological solutions on Commercial basis to interested parties and
Continuous Development and search for innovative technologies for a cleaner and better
environment.
5.4. Brief Environmental Management Plan
5.4.1 Construction Phase:
Adequate and effective environment protection measures will be planned and designed to
minimize the impacts due to activities related to preconstruction (preparatory phase) of the
project, machinery installation and commissioning stages and end with the induction of manpower
and start up. The impacts during the construction phase on the environment will basically be very
insignificant as the project construction area is very small. Only foundation for RCC structure will
be made. Ready mix Concrete will be used and therefore no possibility of fugitive emission due
to material handling. In view of the above, the following measures are recommended to reduce
the impact during this period:
Due provision of necessary infrastructural services like water and power supply etc., for
the construction area.
All possible care will be taken to reduce the noise level due to construction activity. As
planned, no such noise generating machineries will be used. Also, noise prone activities
shall be restricted to the extent possible during night particularly during the period 10 PM
to 6 AM in order to have minimum environmental impact.
Water Environment
Water requirement for the proposed project shall be met from Bore well (ground water). Further,
there will be no housing facilities at site for construction workers and hence a major source of
impact on water environment will be avoided. Proper and sufficient sanitary facilities will be
provided to construction workers to maintain all hygienic conditions at site. Care shall be taken
during undesirable consequences like health and hygiene problems etc.
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
134
Air Environment
Construction phase will be for a short period and hence the impacts will also be for a short and
temporary period. During construction activities, mainly emission of dust and gases from
movement of vehicles and construction activity is expected. However, following measures will be
taken to reduce/contain such emissions:
Possibility of raising green belt along with construction activity will also be explored.
All construction workers will be provided appropriate Personal Protective Equipment
(PPEs) like dust mask, ear plug, helmet, safety belt etc. and made to wear them during
working hours.
Solid Waste
Main solid waste generation during construction phase will be construction debris like rubble, brick
bats, debris, steel scrap, plastic pipes, wooden scrap, sand, gravel etc. However, these materials
are inert in nature and will not result into leaching of any substance or constituent. On completion
of civil work, all debris etc. will be completely removed from site to avoid any incompatibility with
future use.
Noise Environment
Following measures are proposed during construction period to mitigate adverse impacts:
Construction machinery and vehicles will undergo periodic maintenance to keep them in
good working condition.
Feasibility of putting up acoustic enclosure / temporary barrier around areas with high
noise levels will also be explored.
All construction workers working in high noise areas will be provided appropriate PPEs
like ear muffs and made to wear them during working hours.
Possibility of raising green belt along with construction activity will also be explored so as
to serve as a noise barrier.
Land Environment
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
135
Following steps are proposed to take care of impact of construction activity on project land area:
Other materials like diesel etc. will be properly stored and handled to prevent any spillage
on land.
All the wastes will be stored at a designated site within the premises to prevent scattered
discharge on land.
On completion of civil works, all debris etc. will be completely removed from site to avoid
any incompatibility with future use.
Ecological Environment
Proposed project will be within premises in open area, hence no major impact on ecology is
anticipated. However, possibility of rising of green-belt along with construction activity will be
explored so that greening of area can be started at the beginning of project.
Socio-Economic Environment
As there will be no temporary housing colony for construction workers, no socio-economic impact
is envisaged due to the same. Local people from nearby villages of the surroundings of the site
will be employed for construction work to the maximum extent possible.
5.4.2. During Operation Phase
Water Environment
Total water requirement for the proposed project would be 3.4 KLD which will be sourced from
treated water while for domestic purpose 2.7 KLD water will be sourced from ground water using
bore well.
Air Environment
Control measures:
Main sources of the air emission from the existing as well as proposed expansion activities are
emission from flue gas stacks. There is no increase in the source of emission of flue gas only
working hours will be increased resulted to increase overall emission load. At present, flue gas
emission is from common stack attached to Thermic fluid heater, where LDO are used as fuel.
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
136
No new TFH will be installed; only working hours of the utilities will be increased as a result of
which there will be increase in fuel consumption. Multi-cyclone & bag filter will be provided as Air
Pollution Control Measure to the stack attached with TFH.
At present, process gas emission is from the vent attached to reaction vessel. Alkali scrubber is
installed as APCM to absorb the process gases generating from the process reactors and
controlling the emission levels as per GPCB norms.
Adequate stack height to the flue gas stack has been provided for proper dispersion of gaseous
emission. In order to minimize the air pollution, the unit will develop greenbelt on and around its
premises considering the following guidelines,
i) Green cover should be created at all the available open spaces.
ii) Strict surveillance is made to increase the survival rate of the trees.
iii) Plants with higher height, medium and low height should be planted to ensure thick belt for
attenuation of fugitive emission. This activity demands expert advice and guidance.
Control and Monitoring of Fugitive Emissions
Fugitive emissions from the proposed project would be significant as there will be air pollution due
to activities like leakage in pumps, storage container, material transferring and packing. These
operations generate dust. Specific instances of fugitive dust generation may include dust blown
by wind, dust caused by vehicular traffic etc., Good housekeeping, proper maintenance, wetting
of dusty areas, use of enclosures wherever feasible etc., would considerably reduce fugitive dust.
For effective prevention and control of fugitive emissions, following measures shall be taken:
Proper storage of raw material, products and fuels.
Ensuring closed feeding and sampling.
Establishing SOPs for startup, shut down and maintenance operational procedure.
Regular work place and ambient air quality monitoring will be done.
Green belt will be developed around the facility to arrest the fugitive emissions.
Regular training shall be given to the personnel to minimize fugitive dust emissions.
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
137
Noise Environment
During the operational phase, noise generation will be from D. G. sets, machinery, equipment,
pumps, motors, from unloading of materials etc, However, with the implementation of the EMP
for Noise, Noise Levels can be maintained within the SPCB standards.
Following precautionary measures will be adopted to control the noise level.
Noise generating sources and their platforms will be maintained properly to minimize noise
vibrations generated by them.
Personnel working near the noisy machines, will be provided with well-designed ear
muffs/plugs (effective noise reduction 10-15 dBA), use of which will be strictly enforced.
Sophisticated and low noise generating equipment will be selected.
Green belt will be developed to act as a noise barrier.
It would be ensured that there would not be any operator near the noise generating
equipment on continuous basis.
Noise barriers/shields in the form of walls, beams will be provided around the units
wherever found feasible.
Training to personnel will be imparted to generate awareness about effects of noise and
importance of using PPEs.
Land Environment
Accidental spillage of hazardous waste stored at the facility can contaminate the soil. To mitigate
that risk, it will be ensuring that hazardous materials will be stored in proper and designated areas
to minimize the possibility of spillage. Further, ETP sludge shall be generated from the effluent
treatment plant and the same shall be disposed through TSDF site. A very small quantity of used
oil will be generated which will be sold to authorized re-processors.
Ecological Environment
Ecological base line surveys in the core and buffer zones, reveals no exceptional features of
wildlife interest. The survey based on following criteria.
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
138
Table 5.1 Ecological Criteria & Observations
Land use No tree cutting is required. No major vegetation is present within the core
zone hence no wildlife Zone exists within the core zone.
No sensitive ecosystem is present within 10 km area of the project site.
However, one small Forest patches is present but located more than 5 km
away from the project site.
Diversity Species diversity of flora as well as fauna species is restricted to agro
ecosystem.
Rarity There is no endemic, rare or threatened species in site as well as in study
area. There is no endangered or schedule-I faunal species in the study
area
Proximity There are no Biosphere Reserve, National Park, Wildlife Sanctuary,
present within 10 km area of the site
Potential value After developing a wide and dense greenbelt in plant area will increase
habitat condition especially for avifauna.
Green Belt development plan
In order to mitigate and minimize the environmental impacts, arising due to project especially from
air pollution, noise pollution, soil erosion etc. the Greenbelt development in the area delineated
can provide the best mitigation option. The green canopy not only absorbs some of these
pollutants as carbon sink but also improves the aesthetic environment, besides attenuating the
noise levels.
Proposed Plant will develop 5-10 m wide greenbelt (as space available) all around the plant
premises. As per CPCB/MoEF& CC guidelines 33% of the total land area (412 m2) shall be kept
as greenbelt.
Development of Greenbelt
The strategy worked out for development of green belt consists of following:
The species selected should be capable of growing fast,
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
139
The species should be wind firm and long lived.
Broad leaf trees growing above 10 m in height should be planted along the roads, offices
and infrastructure facilities.
The species should form a dense crown cover.
The species should form a litter in abundance on the plantation floor.
Generally local/indigenous fast-growing trees/ shrubs should be planted.
For protection against biotic interference thorn fencing around the plantation, circular
trench around the planting pit and sown with fast growing thorny shrubs on the ridge
should be followed.
Guidelines and Techniques for Green Belt Development
Based on environmental conditions suitable indigenous plants species shall be planted under
green belt development plan. The requirement of plants sapling for development of green belt
shall be made from the nearby forest nursery. The soil characteristics shall also be kept in mind.
As advance work the area to be planted shall be demarcated and pit locations marked. Pits shall
be dug out and semi-filled with good and loose weathered soil before planting with the
commencement of good monsoon rains sometime in month of July. The digging operation of the
pit should be completed before the end of June so as to allow thoroughly weathering of the dugout
soil. Prior to the commencement of the rains, pits shall be refilled with the dugout soil and FYM
added. Planting shall be done when heavy showers causing run-off occurs sometime between
July and August. The saplings should be 9 to 12 months old. Immediately after planting the pits
shall be watered with 20 liters / pit and in case of failure of rainfall it should be watered @ 20 liters
/ pit at fortnight interval. The mortality of plants has been considered @ 20% and re-digging of pit
should be carried out before replacement of the individual plant.
Precautions During Plantation
Some important precautions should be taken during the plantation, which are as under:
Indigenous species recommended should be planted in sufficient numbers to increase
their population size in the area.
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
140
Multipurpose species should be planted in large numbers.
Selection of species for plantation:
The species selected under this plantation will be moderately high, good foliage bearing and are
able to trap dust and noise. The following species along with hedge plant have been proposed for
plantation under green belt.
Table 5.2 Species suggested for plantation under Greenbelt Development Programmed
Common Name of Trees/Plants Scientific Name
Neem / Limbado Azadirachta indica
Gulmohar Delonix regia
Asopalav Polyalthia longifolia (Sonn.) Thw.
Kesudo, Khakharo Butea monosperma (Lam.) Taub.
Pili karan Thevetia peruviana
Lal Karen Nerium indicum
Tulsi Ocimum sanctum
Lawn --
5.5. Budget for Environment Protection
A capital investment towards the environmental protection, control & mitigation measures is about
Rs. 15 Lacs and recurring cost towards the environmental protection measures is 3 lacs per
annum.
The unit keeps provision for adequate funds aside to meet with regular expenses for the
environmental control measures as well as for recurring cost for environmental management for
the proposed project. Unit will regularly and efficiently operate environmental management
systems and keep provision for fund for meeting expenses for the same. Estimated recurring cost
for environmental management is given in Table 5.3.
Table 5.3 Recurring Cost for Environmental Management
Proposed Five Years Program for Greenbelt Development
Plantation
details
1st Year 2nd Year 3rd Year 4th Year 5th Year Total
Yearly % 25% 23% 18% 18% 16% 100%
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
141
Particulars Recurring Cost (Rs. In Lac/ Annum)
Air Pollution Control 0.195
Water Pollution Control 0.99
Noise pollution 0.03
Hazardous / solid waste management 1.2
Green Belt Development 0.12
Occupational Health & Safety 0.3
Statutory Compliance and miscellaneous 0.12
Total 3.0
5.6. Conclusion
Environmental Management plan will be dynamic, flexible and subject to periodic review. For
project where the major environmental impacts are associated, EMP will require regular review.
Senior management responsible for a project should conduct a review of EMP and its
implementation to ensure that the EMP remains effective and appropriate.
5.7. Environment Monitoring Program
Environmental monitoring describes the processes and activities that need to take place to
characterize and monitor the quality of the environment. Environmental monitoring is used in the
preparation of environmental impact assessments, as well as in many circumstances in which
human activities carry a risk of harmful effects on environment. All monitoring strategies and
programs have reasons and justifications which are often designed to establish the current status
of an environment or to establish trends in environmental parameters. In all cases the results of
monitoring will be reviewed and analyzed statistically.
Environmental monitoring program is designed to understand how the environment changes over
time. Therefore, regular monitoring program of the environmental parameters is essential to take
into account the changes in the environment. The objectives of environmental monitoring program
are;
1. To verify the results of the impact assessment study in particular with regard to new
development;
2. To follow the trend of parameters which have been identified as critical;
3. To check or assess the efficiency of the pollution control measures;
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
142
4. To ensure that new parameters, other than those identified in the impact assessment study, do
not become critical through the commissioning of new installations;
5. To check assumption made with regard to the development and to detect deviations in order
to initiate necessary measures; and
6. To establish a database for future Impact Assessment Studies for new projects.
Environmental Monitoring Program
The attributes, which merit regular monitoring, are air quality both at source and ambient
atmosphere, water and wastewater quality, noise levels, ecological preservation, greenbelt
development, socio-economic aspects, etc. Regular monitoring is carried out for the existing plant
and will be continued with additional frequency and parameters as per the need after the proposed
expansion project. Environmental monitoring program after the proposed expansion project is
given in following Table 5.4.
Table 5.4 Environmental Monitoring Program
Sr. No. Particulars Monitoring Frequency Parameters
A Air Pollution
i. Stacks Monitoring (All Stacks) Quarterly SO2, NOx, PM
ii. Ambient Air Quality Monitoring
(2 Locations within premises)
Twice in a year PM10, PM2.5, SO2,
NOx, Volatile Organic
Compound
iii. Work area monitoring (2
Locations in process plant)
Quarterly Volatile Organic
Compounds
B Water and Wastewater Quality
i. Borewell water (Intake source) Twice in a year As per IS: 10500
ii. Industrial effluent (Untreated &
Treated)
Daily pH, COD, BOD, SS,
TDS
Monthly General parameters
iii. Domestic effluents (Untreated
& Treated)
Daily pH
Monthly pH, BOD, SS, TDS
C Ambient Noise Levels
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
143
Sr. No. Particulars Monitoring Frequency Parameters
i. All Prominent places within
premises
Twice in a year --
D Soil (1 within the premises and
1 from vicinity)
Once in a year General parameters
E ETP sludge Twice in a year General parameters
F Safety Audit Once in two years All safety aspects
G Occupation health (medical
checkups)
Pre, post and regular All relevant test
according to working
profile
H Greenbelt development Periodic Survival rate and
growth
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
144
CHAPTER 6: HAZARD EVALUATION AND RISK ASSESSMENT
6.1. Introduction
Industrial plants deal with materials, which are generally hazardous in nature by virtue of their
intrinsic chemical properties or their operating temperatures or pressures or a combination of
these. Fire, explosion, toxic release or combinations of these are the hazards associated with
industrial plants using hazardous chemicals. More comprehensive, systematic and sophisticated
methods of Safety Engineering, such as, Hazard Analysis and Quantitative Risk Assessment
have now been developed to improve upon the integrity, reliability and safety of industrial plants.
The primary emphasis in safety engineering is to reduce risk to human life, property and
environment. Some of the more important methods used to achieve this are:
Quantitative Risk Analysis: Provides a relative measure of the likelihood and severity of various
possible hazardous events by critically examining the plant process and design.
Work Safety Analysis: The technique discerns whether the plant layout and operating
procedures in practice have any inherent infirmities.
Safety Audit: Takes a careful look at plant operating conditions, work practices and work
environments to detect unsafe conditions.
Together, these three broad tools attempt to minimize the chances of accidents occurring. Yet,
there always exists, no matter how remote, probability of occurrence of a major accident. If the
accident involves highly hazardous chemicals in sufficiently large quantities, the consequences
may be serious to the plant, to surrounding areas and the populations residing therein.
6.2. Risk Assessment
A three ‘levels’ risk assessment approach has been adopted for the Asiatic Composite Limited
(Hence forth Asiatic) proposed expansion project to be set up at survey no.1963/185/24-B-Paiki,
village: Mankol, Taluka: Sanand: Ahmedabad, Gujarat-382110.
The risk assessment levels are generally consistent with the practices encountered through
various assignments for medium and large chemical complexes. The brief outline of the three-tier
approach is given below:
Level 1 – Risk Screening
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
145
This is top-down review of worst- case potential hazards/risks, aimed primarily at identifying plant
sites or areas within plant, which pose the highest risk. Various screening factors considered
include:
Inventory of hazardous materials;
Hazardous Materials properties;
Storage conditions (e.g. temperature and pressure);
Location sensitivity (distance to residential areas / populace).
The data / information is obtained from plant. The results provide a relative indication of the extent
of hazards and potential for risk exposure.
Level 2 – Major Risk Survey (Semi - Quantitative)
The survey approach combines the site inspection with established risk assessment techniques
applied both qualitative as well quantitative mode. The primary objective is to identify and select
major risks at a specific location in the plant considering possible soft spots / weak links during
operation / maintenance. Aspects covered in the risk usually include:
Process Hazards;
Process Safety Management Systems;
Fire Protection and Emergency response equipment and programs.
Security Vulnerability;
Impact of hazards consequences (equipment damage, business interruption, injury,
fatalities);
Qualitative risk identification of scenarios involving hazardous materials;
Risk reduction measures.
Selection of critical scenarios and their potential of damage provide means of prioritising mitigative
measures and allocate the resources to the areas with highest risks.
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
146
Level 3 – Quantitative Risk Assessment (Deterministic)
This is the stage of assessment of risks associated with all credible hazards (scenarios) with
potential to cause an undesirable outcome such as human injury, fatality or destruction of
property. The four basic elements include:
Hazards identification utilizing formal approach (Level 2, HAZOP etc.);
Frequency Analysis. Based on past safety data (incidents / accidents); Identifying likely
pathway of failures and quantifying the toxic / inflammable material release;
Hazards analysis to quantify the consequences of various hazards scenarios (fire,
explosion, BLEVE, toxic vapour release etc.). Establish minimum value for damage (e.g.
IDLH, over pressure, radiation flux) to assess the impact on environment.
Risk Quantification: Quantitative techniques are used considering effect / impact due to weather
data, population data, and frequency of occurrences and likely hood of ignition / toxic release.
Data are analyzed considering likely damage (in terms of injury / fatality, property damage) each
scenario is likely to cause.
QRA provides a means to determine the relative significance of a number of undesired events,
allowing analyst and the team to focus their risk reduction efforts where they will be beneficial
most.
M/s Asiatic Chemicals has been incorporated with main object to manufacture Synthetic Organic
Chemicals which have a good export potential. Asiatic has proposed expansion project to
increase the plant capacity by 700 MT/month of Synthetic Organic chemicals (Saturated /
unsaturated Polyester Resins) at the site. Table 6.1 gives the list of products (and their monthly
production capacity) to be manufactured in the proposed Asiatic project. Table 6.2 gives the list
of bulk storages of materials.
Table 6.1 Asiatic Products Details
Sr.
No.
Name of the Products CAS No. Quantity MT/Month
Existing Proposed Total
1 FRP Tank, 600 - 600
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
147
Pultrsion Profile,
FR Sheet
-
2
Unsaturated Polyester
Resins
9003-01-4
-
700
700 3 Saturated Polyester
Resins
61926-16-7
Table 6.2 Raw Material Bulk Storages
S. No
Raw Material Storage (KL/MT)
Storage System
1 Maleic Anhydride 5
Plastic or Steel Drums/ Bags ~ 200/50 litters
2 Phthalic Anhydride 5
3 Glycol(Propylene Glycol/ Neo Pentyl Glycol)
5
4 Iso Phthalic Acid/Poly (terephthelic)acid 8
5 Methyl ethyl ketone peroxide 3
6 Di Ethylene glycol/Polyethylene glycol 5
7 Styrene 5
6.2.1. Risk Screening Approach
Proposed Plant: Risk screening of Asiatic plant was undertaken through data / information
provided by Asiatic. Data of major / bulk storages of raw materials, intermediates and other
chemicals were collected. MSDS of hazardous chemicals were studied vis a vis their inventories
and mode of storage. Asiatic plant will be using number of hazardous chemicals. The chemicals
stored in bulk (Solid/ liquid or gaseous) and defined under MSHIC Rule will be considered for
detailed analysis.
Hazardous materials have been defined under MSIHC Rules (1989) - 2 (e) which means.
(i) Any chemical which satisfies any of the criteria laid down in Part I of Schedule I and is listed in
Column 2 of Part II of this Schedule;
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
148
Toxic Chemicals: Chemicals having the following values of acute toxicity and which owing to
their physical and chemical properties, are capable of producing major accident hazards:
S.
No
Toxicity Oral
Toxicity
LD50
(mg/kg)
Dermal
Toxicity
LD50
(mg/kg)
Inhalation
Toxicity
LC50 (mg/l)
Remarks
1 Extremely Toxic >5 < 40 < 0.5 --
2 Highly Toxic >5 – 50 > 20 – 200 < 0.5 – 2.0 --
3 Toxic >50 - 200 > 200 -
1000
> 2 - 10 --
Flammable chemicals:
Flammable gases; 20 0C and at standard pressure of 101.3 KPa are:
Ignitable when in a mixture of 13% or less by volume with air, or;
Have a flammable range with air of at least 12% points regardless of the lower flammable
limits.
Extremely flammable liquids: chemicals which have a flash point lower than or equal to 230C
and the boiling point less than 350C;
Very Highly flammable liquids: chemicals which have a flash point lower than or equal to 23
0C and the boiling point higher than 35 0C;
Highly Flammable Liquid: Chemicals which have a flash point lower than or equal to 60 0C but
higher than 23 0C.
Flammable liquids: chemicals which have a flash point higher than 60 0C but lower than 90 0C.
Explosives: Explosive means a solid or liquid or pyrotechnics substance (or a mixture of
substances) or an article.
Which is in itself capable by chemical reaction of producing gas at such a temperature
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
149
and pressure and at such a speed as to cause damage to surroundings;
Which is designed to produce an effect by heat, light, sound, gas or smoke or a
combination of these as the result of non-detonative self-sustaining exothermic chemical
reaction.
(ii) any chemical listed in Column 2 of Schedule 2;
(iii) any chemical listed in Column 2 of Schedule 3;
Asiatic will be manufacturing two new products. None of the products are listed under “List of
hazardous and Toxic Chemicals” category under MSIHC Rules, 1989. The raw materials (stored
in bulk) coming under hazardous category as specified by MSIHC Rules is given in Table 6.3
below:
Table 6.3 Hazards Analysis –Raw materials
S. No
Raw material S. No & Threshold Quantity (TQ in MT) as per MSHIC Rules
Chemicals Hazards Potential Remarks
Schedule-1, Part-II
Schedule-2, Part-I
Schedule-3, Part-I
Hazards Toxic DT->---mg/Kg;
OT---- g/Kg;
IT----mg/l;
(Rats)
1. Maleic Anhydride C4H2O3 CAS No:108-31-6 Crystalline solid MP: 52.8 0C
352 --- --- Very hazardous in case of ingestion. Hazardous in case of skin contact (irritant, permeator), of eye contact (irritant), of inhalation. Corrosive to eyes and skin. Inhalation of dust will produce irritation to gastro-intestinal or respiratory tract,
DT->---2620 mg/Kg; (Rabbit)
OT----481mg/Kg (Rat);
IT----mg/l;
(Rats)
2. Phthalic Anhydride C8H4O3 CAS No: 85-44-9
508 --- --- Very hazardous in case of skin contact (irritant), of eye contact (irritant), of ingestion, of inhalation;
DT->---10000 mg/Kg (rabbit);
OT—1530
May be combustible at high temperature
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
150
Crystalline solid with characteristic acrid odour BP:295 0C; MP:131 0C
Repeated inhalation of dust can produce varying degree of respiratory irritation or lung damage.
mg/Kg (Rat);
IT-(Dust)210 mg/m 1 hours [Rat].
3. Glycol (Mono Ethylene glycol/ Neo pentyl Glycol) [2] CAS No: 126-30-7 Colourless Flammable liquid with slight odour
267 --- --- BP:207 0C; FP: 103 0C; Explosive Limit: UEL 11.4 Vol-% LEL 1.1 Vol-% Reacts with inorganic acids and carboxylic acids to form esters. Converts to aldehydes or acids by oxidizing agents Product does not present an acute toxicity hazard based on known or supplied information.
DT->--4000 mg/Kg (Pig);
OT---8400 mg/Kg (Rat);
IT----140mg/M3;
(Rats;8 hrs)
No data available
4. Iso Phthalic Acid/Poly (tere phthelic) acid CAS No:121-91-5 Crystalline white odourless nonflammable powder MP:338-342 0C;
--- --- --- The product is not classified as hazardous to health or the environment, but the product may cause dust explosions and preventive measures must be taken
DT->--2000 mg/Kg;
OT—5000 mg/Kg;
IT---11370 mg/m3;
(Rats)
5. Methyl ethyl ketone peroxide CAS No 13338-23-4 Colourless to light yellow Flammable liquid; BP:68 0C; FP:80 0C
385 --- 5 May be harmful or fatal if swallowed. May cause allergic skin reaction. May be irritating or corrosive to the skin and/or eyes.
DT->--;
OT----1017 mg/Kg (Rat);
IT—17 mg/l;(mouse;4 hrs)
Limited data available Highly reactive material: Store below 38 0C temperature Stability - Conditions to avoid Contamination with ANY foreign substance,
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
151
Exposure to heat Protect from direct sunlight. Incompatible materials Strong acids. Reducing agents
6. Di Ethylene glycol/Polyethylene glycol C4-H10-O3 CAS No:111-46-6 Colorless odorless Syrpy liquid BP:244 0C; FP:154 0C; MP: --6.5—10.5 0C;
197 --- --- Product irritates eyes and skin. High vapour concentrations irritate respiratory system and eyes and may lead to fast coma and death
DT->--;
OT----15600 mg/Kg (Rat);
IT—mg/Kg (mouse;4 hrs)
7. Styrene C8H8 CAS No: 100-42-5 Clear Viscous colorless, Flammable liquid with sweetish aromatic liquid BP:145.2 0C; MP:--30.6 0C; FP:490 0C
583 --- --- Very hazardous in case of eye contact (irritant). Hazardous in case of skin contact (irritant, permeator), of ingestion, of inhalation. Inflammation of the eye is characterized by redness, watering, and itching.
DT->--;
OT----316 mg/Kg (Mouse);
IT—12000 ppm (Rat;4 hrs)
Note:
TQ-I: Threshold quantity (for application of rules 4,5,7 to 9 and 13 to 15)
TQ-II: Threshold quantity (for application of rules 10 to 12)
Note:
Oral Toxicity (OT) in LD50 (mg/kg)
Dermal Toxicity (DT) in LD50 (mg/kg)
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
152
Inhalation Toxicity in LC50 (mg/l) [4 hrs.]
Acute Exposure Guideline Levels (AEGLs)
AEGL-3 is "the airborne concentration of a substance above which it is predicted that the general
population, including susceptible individuals, could experience life-threatening adverse health
effects or death."
AEGL-2 is "the airborne concentration of a substance above which it is predicted that the general
population, including susceptible individuals, could experience irreversible or other serious, long-
lasting adverse health effects or an impaired ability to escape."
AEGL-1 is "the airborne concentration of a substance above which it is predicted that the general
population, including susceptible individuals, could experience notable discomfort, irritation, or
certain asymptomatic no sensory effects.
Emergency Response Planning Guidelines (ERPGs)
The 3 ERPG Emergency Response Planning Guidelines are levels of concern representing the
adverse health effects of a hazardous substance on members of the general public. ERPGs are
developed by the ERPG committee of the American Industrial Hygiene Association
(www.aiha.org). tiers are defined as follows:
ERPG-3 is "the maximum airborne concentration below which it is believed that nearly all
individuals could be exposed for up to 1 hour without experiencing or developing life-threatening
health effects."
ERPG-2 is "the maximum airborne concentration below which it is believed that nearly all
individuals could be exposed for up to 1 hour without experiencing or developing irreversible or
other serious health effects or symptoms which could impair an individual's ability to take protective
action."
ERPG-1 is "the maximum airborne concentration below which it is believed that nearly all
individuals could be exposed for up to 1 hour without experiencing other than mild transient health
effects or perceiving a clearly defined, objectionable odor."
Temporary Emergency Exposure Limits (TEELs)
TEELs Temporary Emergency Exposure Limits are levels of concern representing the adverse
health effects of a hazardous substance on members of the general public. TEELs are defined by
the U.S. Department of Energy for use when ERPGs or AEGLs aren't available (see
www.hss.energy.gov/HealthSafety/WSHP/chem_safety/teel.html). are used in similar situations as
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
153
the 60-minute AEGLs Acute Exposure Guideline Levels are levels of concern representing the
adverse health effects of a hazardous substance on members of the general public. AEGLs are
developed by the National Research Council's National Advisory Committee on AEGLs
(www.epa.gov/oppt/aegl). and ERPGs Emergency Response Planning Guidelines are levels of
concern representing the adverse health effects of a hazardous substance on members of the
general public. ERPGs are developed by the ERPG committee of the American Industrial Hygiene
Association (www.aiha.org).. However, in situations where the concentration The amount of a
chemical present in a given weight or volume of air. Concentration of a gas in air may be expressed
in units such as parts per million (by volume) or milligrams per cubic meter. varies over time, the
TEEL developers recommend using a conservative 15-minute time-weighted average
concentration The amount of a chemical present in a given weight or volume of air. Concentration
of a gas in air may be expressed in units such as parts per million (by volume) or milligrams per
cubic meter. A chemical may have up to 4 TEEL Temporary Emergency Exposure Limits are levels
of concern representing the adverse health effects of a hazardous substance on members of the
general public. TEELs are defined by the U.S. Department of Energy for use when ERPGs or
AEGLs aren't available (see www.hss.energy.gov/HealthSafety/WSHP/chem_safety/teel.html).
values, each of which corresponds to a specific tier of health effects.
The 4 TEEL Temporary Emergency Exposure Limits are levels of concern representing the
adverse health effects of a hazardous substance on members of the general public. TEELs are
defined by the U.S. Department of Energy for use when ERPGs or AEGLs aren't available (see
www.hss.energy.gov/HealthSafety/WSHP/chem_safety/teel.html). tiers are defined as follows:
TEEL-3 is "the maximum concentration The amount of a chemical present in a given weight or
volume of air. Concentration of a gas in air may be expressed in units such as parts per million (by
volume) or milligrams per cubic meter. in air below which it is believed nearly all individuals could
be exposed without experiencing or developing life-threatening health effects."
TEEL-2 is "the maximum concentration The amount of a chemical present in a given weight or
volume of air. Concentration of a gas in air may be expressed in units such as parts per million (by
volume) or milligrams per cubic meter. in air below which it is believed nearly all individuals could
be exposed without experiencing or developing irreversible or other serious health effects or
symptoms that could impair their abilities to take protective action."
TEEL-1 is "the maximum concentration The amount of a chemical present in a given weight or
volume of air. Concentration of a gas in air may be expressed in units such as parts per million (by
volume) or milligrams per cubic meter. in air below which it is believed nearly all individuals could
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
154
be exposed without experiencing other than mild transient health effects or perceiving a clearly
defined objectionable odor."
TEEL-0 is "the threshold concentration The amount of a chemical present in a given weight or
volume of air. Concentration of a gas in air may be expressed in units such as parts per million (by
volume) or milligrams per cubic meter. below which most people will experience no appreciable
risk of health effects."
PACs (Protective Action Criteria)
The National Institute of Occupational Safety and Health (NIOSH National Institute for
Occupational Safety and Health (www.cdc.gov/niosh). The federal agency responsible for
conducting research and making recommendations for the prevention of work-related disease and
injury. NIOSH is part of the Centers for Disease Control and Prevention (CDC).) defines an
immediately dangerous to life or health condition as a situation "that poses a threat of exposure to
airborne contaminants when that exposure is likely to cause death or immediate or delayed
permanent adverse health effects or prevent escape from such an environment."
The IDLH limit Immediately Dangerous to Life and Health limits, levels of concern for adult workers;
estimate of the highest concentration from which escape is possible without permanent injury (if
their respirators fail). IDLHs ae established by the National Institute for Occupational Safety and
Health (www.cdc.gov/niosh). represents the concentration The amount of a chemical present in a
given weight or volume of air. Concentration of a gas in air may be expressed in units such as
parts per million (by volume) or milligrams per cubic meter. of a chemical in the air to which healthy
adult workers could be exposed (if their respirators fail) without suffering permanent or escape-
impairing health effects.
None of Asiatic two new products have been mentioned in MSHIC Rules and as such are not
considered hazardous
Among the seven raw materials stored in bulk only one has not been mentioned in MSIHC Rules.
Three raw materials are solids and four are liquids. None is gas. One of the raw material namely
Methyl ethyl ketone peroxide has been mentioned as “highly reactive substance” in Schedule 3
Part –I of MSIHC Rules. Threshold quantity (for application of Rules 5, 7-9 and 13-15) for Methyl
ethyl ketone peroxide is “5 MT”.
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
155
6.2.2. Hazardous Materials Storage
The solid raw materials will be received in bags or drums and will be stored in chemicals godowns.
The products (liquid or solid) will be packed in drums and stored in product godowns as per market
demand. The bulk storages of hazardous materials are given in the Table 4.2.
The solid materials powder or granules spillage can result in polluting small area only. The damage
to personnel can be through ingress- dermal (if individual come in contact), oral (if individual food
gets infected through fugitive dust) or inhalation (fugitive dust). The main route is fugitive dust
which in covered area will move to short distance only.
The risk is through liquid and gaseous materials which are volatile material. The toxic vapours due
to spillage of such material can travel to some distance (as they are stored in covered godowns)
and cause damage. The liquid products will be packed in drums (50 / 200 litres drums).
6.2.3. QRA Approach
Identification of hazards and likely scenarios (based on Level-1 and Level-2 activities) calls for
detailed analysis of each scenario for potential of damage, impact area (may vary with weather
conditions / wind direction) and safety system in place. Subsequently each incident is classified
according to relative risk classifications provided in Table below as Table 4.4:
Table 6.4 Risk Classification
Stage Description
High
(> 10-2/yr.)
A failure which could reasonably be expected to occur within the expected life
time of the plant.
Examples of high failure likelihood are process leaks or single instrument or valve
failures or a human error which could result in releases of hazardous materials.
Moderate
(10-2 --10-
4/yr.)
A failure or sequence of failures which has a low probability of occurrence within
the expected lifetime of the plant.
Examples of moderate likelihood are dual instrument or valve failures,
combination of instrument failures and human errors, or single failures of small
process lines or fittings.
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
156
Stage Description
Low
(<10-4)
A failure or series of failures which have a very low probability of occurrence
within the expected lifetime of plant.
Examples of ‘low’ likelihood are multiple instruments or valve failures or multiple
human errors, or single spontaneous failures of tanks or process vessels.
Minor
Incidents
Impact limited to the local area of the event with potent for ‘knock – on- events’
Serious
Incident
One that could cause:
Any serious injury or fatality on/off site;
Property damage of $ 1 million offsite or $ 5 million onsite.
Extensive
Incident
One that is five or more times worse than a serious incident.
Assigning a relative risk to each scenario provides a means of prioritising associated risk mitigation
measures and planned actions.
6.2.4. Thermal Hazards
In order to understand the damages produced by various scenarios, it is appropriate to understand
the physiological/physical effects of thermal radiation intensities. The thermal radiation due to tank
fire usually results in burn on the human body. Furthermore, inanimate objects like equipment,
piping, cables, etc. may also be affected and also need to be evaluated for damages. Table 6.5,
Table 6.6Table 6.6 and Table 6.7 (below), respectively give tolerable intensities of various objects
and desirable escape time for thermal radiation.
Thermal hazards could be from fires or explosion. Fire releases energy slowly while explosion
release energy very rapidly (typically in micro seconds). Explosion is rapid expansion of gases
resulting in rapidly moving shock wave. Explosion can be confined (within a vessel or building) or
unconfined (due to release of flammable gases).
BLEVE (boiling liquid expanding vapour explosion) occurs if a vessel containing a liquid at a
temperature above its atmospheric boiling point ruptures. The subsequent BLEVE is the explosive
vaporisation of large fraction of its vapour contents; possibly followed by combustion or explosion
of the vaporised cloud if it is combustible.
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
157
Thermal hazards have been considered for various scenarios including:
Fire in inflammable chemicals storage tanks.
Table 6.5 Effects due to Incident Radiation Intensity
Incident Radiation
kW/m2
Damage Type
0.7 Equivalent to Solar Radiation
1.6 No discomfort on long duration
4.0 Sufficient to cause pain within 20 sec. Blistering of skin
(first degree burn is likely).
9.5 Pain threshold reached after 8 sec. Second degree
burn after 20 sec.
12.5 Minimum energy required for piloted ignition of wood,
melting of plastic tubing etc.
25 Minimum Energy required for piloted ignition of wood,
melting, plastic tubing etc.
37.5 Sufficient to cause damage to process equipment.
62.0 Spontaneous ignition of wood.
Table 6.6 Thermal Radiation Impact to Human
Exposure
Duration
Radiation Energy {1%
lethality; kW/m2}
Radiation Energy
for 2nd degree
burns; kW/m2
Radiation Energy
for 1st degree
burns; kW/m2
10 sec 21.2 16 12.5
30 sec 9.3 7.0 4.0
Table 6.7 Tolerable Intensities for Various Objects
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
158
S.N. Objects Tolerable Intensities (kw/m2)
1 Drenched Tank 38
2 Special Buildings (No window, fire proof
doors)
25
3 Normal Buildings 14
4 Vegetation 10-12
5 Escape Route 6 (up to 30 sec.)
6 Personnel in Emergencies 3 (up to 30 sec.)
7 Plastic Cables 2
8 Stationary Personnel 1.5
6.2.5. Damage due to Explosion
The explosion of a dust or gas (either as a deflagration or detonation) results in a reaction front
moving outwards from the ignition source preceded by a shock wave or pressure front. After the
combustible material is consumed the reaction front terminates but the pressure wave continues
its outward movement. Blast damage is based on the determination of the peak overpressure
resulting from the pressure wave impacting on the object or structure. Damage estimates based
on overpressure are given in Table 6.8 below:
Table 6.8 Damage due to Overpressure
Sl. No Overpressure
(psig / bar)
Damage
1. 0.04 Loud Noise / sonic boom glass failure
2. 0.15 Typical pressure for glass failure
3. 0.5 - 1 Large and small windows usually shattered
4. 0.7 Minor damage to house structure
5. 1 Partial demolition of houses, made
uninhabitable.
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
159
Sl. No Overpressure
(psig / bar)
Damage
6. 2.3 Lower limit of serious structure damage
7. 5 – 7 Nearly complete destruction of houses
8. 9 Loaded train box wagons completely
demolished
9. 10 Probable total destruction of houses
10. 200 Limits of crater lip
In Asiatic case explosion probability is there specific to Methyl ethyl ketone peroxide (Ignition
and/or explosion may occur if Methyl ethyl ketone peroxide mixed with readily oxidizable materials)
6.2.6. Hazardous Material’s Release
Hazardous materials handled and stored in bulk in Asiatic proposed complex two are toxic, three
are both inflammable and toxic and one is highly reactive / flammable/explosive.
Damage criteria: For toxic release the damage criteria considered is IDLH concentration (if data
are available). In the absence of non-availability of IDLH, other data like AEGL, ERPG, TEEL or
PAC will be considered as damage criteria.
For thermal: 1st degree burn (4 Kw/Sq m)
6.2.7. Data Limitations
It is also observed that very little data or information (regarding physical properties required for
modelling) is available for most of the raw materials (stored in bulk as many are not pure chemicals)
and as such failure scenarios cannot be modelled.
6.2.8. Likely Failure Scenarios
The failure scenarios have been selected after critical appraisal of raw materials and storage
inventories. Failure scenarios selected are as given in Table 6.9 below:
Table 6.9 Different Failure Scenarios
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
160
S. No. Scenario Remark
RM-1 Styrene Spillage Inflammable
6.3. Quantitively Risk Assessment & Consequence Analysis
6.3.1. Preamble
In the previous section we have carried out the hazards analysis of the Asiatic existing complex
considering various aspects including bulk storages of hazardous chemicals, plant process
system, plant incidents/accidents records, critical appraisal and discussion at site for soft spots in
the plant etc. Based on the hazards analysis five critical scenarios (liquid and gaseous raw
materials) have been selected for QRA and consequence analysis. QRA quantifies vulnerable
zones for a conceived incident with various levels of severity. Consequence calculations for risk
assessment are invariably in terms of percentage of fatalities but for emergency handling, fatalities
are of no interest saving lives is the main objectives then. The injury criteria have to be agreed in
terms of thermal load or toxic concentration versus exposure duration in the first instance.
In consequence calculation, use is made of a number of calculation models to estimate the physical
effects of an accident (spill of hazardous material) and to predict the damage (lethality, injury,
material destruction, and other property damage). The risk assessment modelling can be roughly
divided into three groups:
Determination of source strength parameters;
Determination of consequential effects;
Determination of damage or damage distances (with specific severity rates)
6.3.2. Weather Effect
The effect of ambient conditions on the impact of fire / thermal radiation and GLC of hazardous /
toxic material can be beneficial as well as harmful. A high wind (turbulence) can dilute the toxic
material impact while stable environment can extend the reach of IDLH or IT (inhalation LC50
rats/mouse for products) concentration to long distance. Any inflammable gas / vapour release in
turbulent weather will soon dilute the hazardous gases below LEL and thus save the disaster.
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
161
6.3.3. Incidents Impacts
The identified failure scenarios (Table 6.9) have been analysed (Using ALOHA and EFFECT
Modules) for the impact zones considering damage due to thermal and toxic impacts. Each incident
will have Impact on the surrounding environment which in extreme case may cross plant boundary.
The impact zones for various scenarios are given in Table 6.10.
Table 6.10 : Hazards Scenario Impact
Scenario
No.
Scenario Impact Zone
(m)
Remarks
Scenario Raw Material
Scenario-1 Styrene Spillage & Fire
<10
1st Degree burn; Template -1
Template 1. Styrene Spillage- Fire- Thermal Impact Zone
6.3.4. Consequential Impacts
The consequential impacts from each incident scenarios can be though thermal, over pressure
wave and toxic route. The damage can be on plant personnel (and neighbouring residents in case
incident crosses boundary), property and also loss in production.
Thermal and Explosion Hazards
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
162
Incidents involving thermal hazards are mainly due to raw material fire (due to spillage). The impact
(1st degree burn) due to Styrene spillage and fire is limited to <10 m only (i.e. within plant
boundary). However, the consequences can go to worse if the incidents lead to domino effect to
other tanks. Many of the raw materials stored are inflammable as well as toxic.
Toxic Hazards
As mentioned above due to data limitation modelling could not be done
6.3.5. Other Hazards:
Hazards due to (Methyl ethyl ketone peroxide -CAS No 13338-23-4)
Health Hazard
Extremely destructive to tissue of the mucous membranes, upper respiratory tract, eyes, and skin.
Symptoms of exposure include burning sensation, coughing, wheezing, laryngitis, shortness of
breath, headache, nausea, and vomiting. (USCG, 1999)
Reactivity Profile
METHYL ETHYL KETONE PEROXIDE is a strong oxidizing agent. May be ignited by heat, sparks
or flame and undergoes self-accelerating decomposition. Explosive decomposition occurs at 230°
F. Sensitive to sunlight. Ignition and/or explosion may occur if mixed with readily oxidizable
materials. Reacts with combustible materials such as wood, cloth or organic materials, with
chlorine, and with metals (iron, copper and their alloys and aluminum and its alloys). Incompatible
with strong oxidizing agents, strong reducing agents, natural rubbers, synthetic rubbers and
chemical accelerators. Incompatible with heavy metals, acids and bases.
Specific Handling Safety Measures
Precautions to be taken in handling and storing: Rotate stock using oldest material first. Avoid
contact with skin, eyes and clothing. Keep containers closed to prevent contamination. Keep
away from sources of heat, sparks, or flame. Do not add to hot solvents or monomers as a violent
decomposition and/or reaction may result. When using spray equipment, never spray raw Methyl
Ethyl Ketone Peroxide onto curing or into raw resin or flues. Keep Methyl Ethyl Ketone Peroxide
in its original container. Do not use near food or drink. Wash thoroughly after handling. The
stability of Methyl Ethyl Ketone Peroxide formulations is directly related to the shipping and storage
temperature history. Cool storage at 80 0F or below is recommended for longer shelf life and
stability. Prolonged storage at elevated temperatures of 100 0F and higher will cause product
degradation, gassing and potential container rupture which can result in a fire and/or explosion.
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
163
Store out of direct sunlight in a well-ventilated area away from combustible and incompatible
materials.
Other Precautions: Unmixed, uncontaminated material, remaining at the end of the day, shall be
returned to a proper organic peroxide storage area. Under no circumstances should material be
returned to original container.
Regulated as an Organic Peroxide, Class 5.2, for storage and handling. Store in original containers
away from incompatible materials, direct sunlight, flames, and all sources of heat. Maximum
Storage Temperature: 38 °C (100 °F). Open them cautiously, in case they may be under slight
pressure. In order to maintain the product's original manufactured assay in long term storage, a
lower storage temperature of below 30 °C (86 °F) is strongly recommended. Shelf Life: (Calculated
from half-life data in benzene solution) Estimate > 48 months at which 95% of the original
manufactured assay remains when stored at or below 30 °C (86 °F).
Hazards due to (Diethylene Glycol—CAS No: 111-46-6)
A colorless liquid. Denser than water. Contact may slightly irritate skin, eyes and mucous
membranes. May be slightly toxic by ingestion. Used to make other chemicals. DIETHYLENE
GLYCOL is incompatible with strong oxidizing agents. It is also incompatible with strong bases. It
can react with sulfuric acid and other dehydrating agents, nitric acid, oxygen, hydrogen peroxide,
perchloric acid and strong acids. Mixtures with sodium hydroxide decompose exothermically when
heated to 446° F. (NTP, 1992)
Hazards due to (Neopentyl Glycol—CAS No: 126-30-7)
White crystalline solid. Melting point 130°C. May be harmful by ingestion or skin absorption.
Causes eye and skin irritation. Material is irritating to mucous membrane and upper respiratory
tract. INHALATION: Call for medical aid. Remove to fresh air. If breathing has stopped, give
artificial respiration. If breathing is difficult, give oxygen. (USCG, 1999)
Reactivity Profile
2,2-DIMETHYLPROPANE-1,3-DIOL may generate toxic gases in combination of with alkali
metals, nitrides, and strong reducing agents. Reacts with inorganic acids and carboxylic acids to
form esters plus water. Converted to aldehydes or acids by oxidizing agents. May initiate the
polymerization of isocyanates and epoxides.
The other hazards in the plant include (but not limited to):
Other toxic hazards due to acids / other toxic spillages (mainly limited to spillage area only.).
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
164
Mechanical hazards due to machines / equipment.
Hazards due to individual soft spots like walking casually and noticing a pit and falling or
colliding/ stumbling or slipping (not noticing a wet place etc.).
Acids Toxic Hazards
Acid spillage-its impact will be limited to spillage area. The spillage if comes in contact with metal
parts will produce hydrogen which is highly flammable gas. Any person moving in area and getting
splash will get the injury. In addition, the spillage will cause pollution problem. The spillage is to be
collected and neutralized for toxic contents before disposal.
6.3.6. Process hazards and Control
Table 6.11 Process Hazards and Controls
Name of
hazardous
process and
operation
Material in
the process
/operation
Type of hazard possible toxic
gas release / fire /explosion /
run away reaction / rupture,
etc.
Control measured
provided
Thermic Fluid
Heater
Oil Fire Hazard:
Causes: Flash point variation of
thermal fluid/oil over a period of
time (Thermal fluids which were
not flammable at the operating
temperature when they were
initially installed but over time
become flammable at the
operating conditions) Mist
Formation around leak points
such as flagged joints, around
valves and connection points in
the pipe line. These may create
explosive atmospheres being
formed outside the pipework
where ignition sources such as
Annual inspections
Safety interlocks to be
provided
Safety and pressure
gauge valves fitted
Properly supported
and protected against
corrosion
Testing of Jackets
and joints of tubes
regularly
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
165
motors pumps and electrical
equipments are present
Lagging Fire – leak and
dispersion of oil within
insultation leads to fire
6.3.7. General hazards and controls
Table 6.12 General hazards and controls
Type of
Emergency
Identification of
Area
Possible Causes Possible
Results
Preventive/control
Measures
Fire Tank farm area Fire due to
Bottom nozzle
failure
Damage of
storage tank
Pump
discharge
nozzle failure
Unloading road
tanker hose
rupture
Major fire in
the tank
farm, it may
spread all
over the
company
and
surrounding
area
May cause
fatalities
Licensed and
isolated storage
tank farm.
Flame proof
fittings.
Earthling while
unloading.
Spark arrestor at
main gate.
Dip pipes on the
tank for unloading.
Provision of dyke.
Earthling of tanks
and pumps.
Get approval from
an explosive
department for
plan approval,
equipment layout
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
166
& emergency
control measures.
No electrical
junction box close
to storage
materials.
Hot work permit
system
followed for hot
working in the
ware house.
Toxic Gas
Release
Tank Farm Area
and Reaction
Vessel area
Cylinder blast
Rupture of
discharge valve
Rupture of gas
cylinder body
Bursting of
pipelines
Major gas
exposure in
the
company
and/or
surrounding
area of the
company
which
resulting in
irritation to
respiratory
track eyes
and
suffocation.
More
inhalation
results in
fatalities.
Storage Tank
stored under shed
and good
ventilated area.
Procured by
license holder
party.
Fitted with valve
protection cap.
Valve opened with
special key.
Loading/unloading
done safely.
Trained persons
for Material
Handling in Tank
Farm and Storage
Tank area.
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
167
Periodic hydraulic
testing through
competent person
by supplier
Painted according
to its color code.
Material
handling
In Plant Flammable,
eye
irritating & body
accident
Fire and
health
Hazards
Trained employee
Required PPE and
Fire
Protective
equipment
Provided Good
engineering
practice
Separate storage
is with dyke
valve system
provided
Storage
and
other
Operation
In Plant Spillage,
Leakage and
overflow,
Fire Hazard Required Fire
Extinguisher
Provided Flame
Proof Electrical
Fitting
Proper Earthling
arrangement
Fire Hydrant
System with
Jockey Pump
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
168
Gas Detector
6.3.8. Safe Practice for Handling, Storage, Transportation and Unloading of
Hazardous Chemicals
For Storage/Handling:
Separate from strong oxidant. & Keep it in well ventilated room.
Dyke wall shall be provided to all above ground storage tank.
Fire hydrant system shall be installed.
Safety shower and eye washer shall be installed near storage area.
Flame proof light fitting shall be provided at flammable storage area.
Proper selection of MOC for chemicals storage tank.
Sprinkler system shall be installed at flammable material storage area
Earthing/bonding shall be provided for static charges.
Flame arrestor shall be provided on flammable material storage tank vent.
Level gauge and level measurement instrument shall be provided on material storage tank.
Lightening arrestor on all chimney and building shall be provided.
Hazardous material should be stored away from the plant and safe distance shall be
maintained.
Safety permit system shall be followed for loading, unloading of hazardous chemical.
Fencing, caution note, hazardous identification board should be provided.
Only authorized person shall be permitted in storage tank area and register will be
maintained.
For Transportation & Unloading:
Solvent shall be received by road tanker and stored in above ground storage tank in
separated bulk storage area.
Loading and unloading procedure shall be prepared for material received through road
tanker.
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
169
Earthing/bonding shall be provided for static charges.
Flexible steel hose shall be used for unloading from the road tanker.
Flame proof electric motor shall be used during loading/unloading.
NRV shall be provided on pump discharge line.
Fixed pipeline with pumps shall be provided for transfer to vessel.
TREM CARD will be provided to all transporters and shall be trained for transportation
Emergency of hazardous chemicals.
Personal Protective Equipment (safety goggles, hand gloves, apron, masks, gum boots
etc.) shall be provided.
6.3.9. Occupational Health Surveillance Programme
Occupational Health Surveillance (also termed as medical surveillance for workers) constitutes an
important component in efforts to protect and improve worker’s health. It is the systematic
collection, analysis, and dissemination of disease data on groups of workers and is designed to
detect early signs of work-related illness. A well-run medical surveillance program can aid in the
early recognition of a relationship between exposure to a hazard and disease, in the assurance of
the safety of new substances, and as an indicator of the effectiveness of existing control measures.
As a vital control measure, medical surveillance employs the use of questionnaires, physical
examinations, ancillary testing, and biologic monitoring. Effective use of biologic monitoring – that
is, the testing of various body specimens for the toxic substance itself, its metabolites, or
physiologic dysfunction. The Factories Act, 1948 and the rules framed thereunder provide for
preemployment and periodical medical examinations of workers employed in industries with
hazardous processes and dangerous operations under section 41-C and section 87 respectively.
Occupational health surveillance programme:
A medical program has been developed for M/s Asiatic Composite Limited., is based on site
specific needs, location, and potential exposures of employees and workers to the various
chemicals handled at the site. The program is designed by an experienced Factory Medical Officer
(MBBS with Associate Fellow of Industrial Health (AFIH) Certification in conjunction with the Site
Safety Officer.
A site medical program consists of the following components:
A. Surveillance:
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
170
Pre-employment screening.
Periodic medical examinations (and follow-up examinations when appropriate).
Termination examination.
B. Treatment:
Emergency
Non-emergency (on a case-by-case basis)
C. Record-keeping
D. Program review
Table 6.13 Plan of Occupational Health & Safety
COMPONENT RECOMMENDED
Pre-Employment Screening Medical history.
Occupational history.
Physical examination.
Determination of fitness to work wearing protective
equipment.
Baseline monitoring for specific exposures.
Periodic Medical Examinations Yearly update of medical and occupational history;
Yearly physical examination; testing based on
(1) examination results,
(2) exposures, and
(3) job class and task.
More frequent testing based on specific exposures.
Emergency Treatment Provide emergency first aid on site.
Develop liaison with local hospital and medical
specialists.
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
171
Arrange for decontamination of victims.
Arrange in advance for transport of victims.
Transfer medical records; give details of incident and
medical history to next care provider
Non-emergency Treatment Development mechanism for nonemergency
health care.
Recordkeeping and Review Maintain and provide access to medical records in
accordance with OSHA and state regulations.
Report and record occupational injuries and
illnesses.
Review Site Safety Plan regularly to determine if
additional testing is needed.
Review program periodically.
Focus on current site hazards, exposures, and
industrial hygiene standards.
General Outline of Occupational Health Programme
Monitoring of occupational hazards like noise, ventilation, chemical exposure etc. is carried
out regularly and its record are maintained.
Good housekeeping, use of PPE, Engineering controls, Enclosure processes, scrubber
system, display of safety boards, SOP of loading / unloading, local exhaust ventilation,
safety shower etc. All necessary safety measures have been taken to keep all chemicals
within TLV.
Appropriate personal protective equipment are provided & ensure the usage of them.
Workers are trained on safe material handling of hazardous chemicals.
Prepare & display the safe operating procedure for hazardous chemicals storage, handling
& transporting or using.
Periodical medical examination of the workers & Liver Function Testes will be done.
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
172
Register (form no.37) for work place air monitoring is done regularly.
Employee training and education is carried out regularly.
Control the noise at source by substitution, isolation, segregation, barriers etc.
Local Exhaust ventilation are installed where it is required to reduce fumes, vapors,
temperature and heat stress.
Chemicals Which Are Exposed to Workers Directly or Indirectly
Pre-employment medical checkup and periodically medical examination is done. SGPT test has
been done for existing workers and if required Liver function test is suggested during pre-
placement and periodical examination. In addition to the above, following safety equipment are
provided;
Fire extinguishers at prominent places in the premises
First aid kit
Portable eye wash station, capable of supplying 15 minutes of water
Emergency shower
Ample supply of potable water for washing and drinking
Emergency communication devices such as mobile phones and two-way radios
Vehicle suitable for emergency transport
6.3.10. Treatment of Workers Affected by Accidental Spillage of Chemicals
Hazards with Acute Exposure
Contact with skin may cause severe burns or systemic poisoning.
Systemic effects may occur from any route of exposure, especially after skin absorption.
Hazards with Chronic Exposure
Repeated or prolonged exposure may harm the respiratory system. Can irritate and inflame
the airways.
Methanol affects the central nervous system, liver, and kidneys.
Special Safety Precautions
Prevent contact with skin by wearing neoprene gloves, lab coat, and resistant apron.
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
173
Wear safety glasses or a face shield if splashing may occur.
Store in a cool, dry, well-ventilated area, away from heated surfaces or ignition sources.
Skin contact requires immediate washing of the affected area with soap and water.
Remove contaminated clothing and launder before wearing again.
Procedure for treating workmen after skin contact.
Skin contact requires immediate flushing of the contaminated area with soap and water at
a sink or emergency shower for a good fifteen minutes. Remove contaminated clothing. In
case of eye contact, promptly flush the eyes with copious amounts of water for 15 minutes
(lifting upper and lower lids occasionally) and obtain medical attention. If methanol is
ingested, obtain medical attention immediately. If large amounts of methanol are inhaled,
move the person to fresh air and seek medical attention at once. It is recommended to
provide the safety shower and eyewash station in plant.
6.3.11. Antidotes
Antidote of Maleic Anhydride
Immediate first aid:
Ensure that adequate decontamination has been carried out.
If patient is not breathing, start artificial respiration, preferably with a demand-valve
resuscitator, bag-valve-mask device, or pocket mask, as trained. Perform CPR as
necessary.
Immediately flush contaminated eyes with gently flowing water.
Do not induce vomiting. If vomiting occurs, lean patient forward or place on left side (head-
down position, if possible) to maintain an open airway and prevent aspiration.
Keep patient quiet and maintain normal body temperature.
Obtain medical attention.
Basic treatment:
Establish a patent airway (oropharyngeal or nasopharyngeal airway, if needed). Suction if
necessary.
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
174
Watch for signs of respiratory insufficiency and assist respirations if necessary. Administer
oxygen by nonrebreather mask at 10 to 15 L/min.
Monitor for pulmonary edema and treat if necessary
Monitor for shock and treat if necessary ... .
For eye contamination, flush eyes immediately with water. Irrigate each eye continuously
with 0.9% saline (NS) during transport, Do not use emetics.
For ingestion, rinse mouth and administer 5 mL/kg up to 200 mL of water for dilution if the
patient can swallow, has a strong gag reflex, and does not drool. Activated charcoal is not
effective. Do not attempt to neutralize because of exothermic reaction.
Cover skin burns with dry, sterile dressings after decontamination
Antidote of Phthalic Anhydride
First aid:
Inhalation - Fresh air, rest. Half-upright position. Refer for medical attention.
Skin - Remove contaminated clothes. Rinse and then wash skin with water and soap. Refer for
medical attention.
Eyes - First rinse with plenty of water for several minutes (remove contact lenses if easily possible),
then take to a doctor.
Ingestion - Rinse mouth. Do NOT induce vomiting. Give plenty of water to drink. Refer for medical
attention.
Immediate first aid:
Ensure that adequate decontamination has been carried out.
If patient is not breathing, start artificial respiration, preferably with a demand-valve resuscitator,
bag-valve-mask device, or pocket mask, as trained. Perform CPR as necessary.
Immediately flush contaminated eyes with gently flowing water.
Do not induce vomiting. If vomiting occurs, lean patient forward or place on left side (head-down
position, if possible) to maintain an open airway and prevent aspiration. Keep patient quiet and
maintain normal body temperature. Obtain medical attention
Basic treatment:
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
175
Establish a patent airway (oropharyngeal or nasopharyngeal airway, if needed). Suction if
necessary. Watch for signs of respiratory insufficiency and assist respirations if necessary.
Administer oxygen by nonrebreather mask at 10 to 15 L/min.
Monitor for pulmonary edema and treat if necessary. Monitor for shock and treat if necessary. For
eye contamination, flush eyes immediately with water. Irrigate each eye continuously with 0.9%
saline (NS) during transport. Do not use emetics.
For ingestion, rinse mouth and administer 5 mL/kg up to 200 mL of water for dilution if the patient
can swallow, has a strong gag reflex, and does not drool. Activated charcoal is not effective. Do
not attempt to neutralize because of exothermic reaction. Cover skin burns with dry, sterile
dressings after decontamination
antidote of Glycol
There are two antidotes used to block ADH-mediated metabolism of EG and methanol: ethanol
and fomepizole.
antidote of Isophthalic Acid
Immediate first aid:
Ensure that adequate decontamination has been carried out.
If patient is not breathing, start artificial respiration, preferably with a demand valve resuscitator,
bag-valve-mask device, or pocket mask, as trained. Perform CPR if necessary.
Immediately flush contaminated eyes with gently flowing water.
Do not induce vomiting. If vomiting occurs, lean patient forward or place on the left side (head-
down position, if possible) to maintain an open airway and prevent aspiration. Keep patient quiet
and maintain normal body temperature. Obtain medical attention.
Basic treatment:
Establish a patent airway (oropharyngeal or nasopharyngeal airway, if needed). Suction if
necessary. Watch for signs of respiratory insufficiency and assist ventilations if needed. Administer
oxygen by nonrebreather mask at 10 to 15 L/min. Monitor for pulmonary edema and treat if
necessary.
Monitor for shock and treat if necessary. Anticipate seizures and treat if necessary.
For eye contamination, flush eyes immediately with water. Irrigate each eye continuously with 0.9%
saline (NS) during transport. Do not use emetics.
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
176
For ingestion, rinse mouth and administer 5 mL/kg up to 200 mL of water for dilution if the patient
can swallow, has a strong gag reflex, and does not drool.
Cover skin burns with dry sterile dressings after decontamination
Antidote of Methyl ethyl ketone peroxide
Eyes: First check the victim for contact lenses and remove if present. Flush victim's eyes with water
or normal saline solution for 20 to 30 minutes while simultaneously calling a hospital or poison
control center. Do not put any ointments, oils, or medication in the victim's eyes without specific
instructions from a physician. Immediately transport the victim after flushing eyes to a hospital even
if no symptoms (such as redness or irritation) develop.
Skin: Immediately flood affected skin with water while removing and isolating all contaminated
clothing. Gently wash all affected skin areas thoroughly with soap and water. If symptoms such as
redness or irritation develop, Immediately call a physician and be prepared to transport the victim
to a hospital for treatment.
Inhalation: Immediately leave the contaminated area; take deep breaths of fresh air. Immediately
call a physician and be prepared to transport the victim to a hospital even if no symptoms (such as
wheezing, coughing, shortness of breath, or burning in the mouth, throat, or chest) develop.
Provide proper respiratory protection to rescuers entering an unknown atmosphere. Whenever
possible, Self-Contained Breathing Apparatus (SCBA) should be used; if not available, use a level
of protection greater than or equal to that advised under Protective Clothing.
Ingestion: DO NOT INDUCE VOMITING. Corrosive chemicals will destroy the membranes of the
mouth, throat, and esophagus and, in addition, have a high risk of being aspirated into the victim's
lungs during vomiting which increases the medical problems. If the victim is conscious and not
convulsing, give 1 or 2 glasses of water to dilute the chemical and immediately call a hospital or
poison control center. Immediately transport the victim to a hospital. If the victim is convulsing or
unconscious, do not give anything by mouth, ensure that the victim's airway is open and lay the
victim on his/her side with the head lower than the body. DO NOT INDUCE VOMITING. Transport
the victim IMMEDIATELY to a hospital.
Antidote of Styrene
Immediate first aid:
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
177
Ensure that adequate decontamination has been carried out. If patient is not breathing, start
artificial respiration, preferably with a demand-valve resuscitator, bag-valve-mask device, or
pocket mask, as trained. Perform CPR as necessary.
Immediately flush contaminated eyes with gently flowing water. Do not induce vomiting. If vomiting
occurs, lean patient forward or place on left side (head-down position, if possible) to maintain an
open airway and prevent aspiration. Keep patient quiet and maintain normal body temperature.
Obtain medical attention.
Basic treatment:
Establish a patent airway (oropharyngeal or nasopharyngeal airway, if needed). Suction if
necessary. Watch for signs of respiratory insufficiency and assist ventilations if necessary.
Administer oxygen by nonrebreather mask at 10 to 15 L/min. Monitor for pulmonary edema and
treat if necessary. Monitor for shock and treat if necessary.
Anticipate seizures and treat if necessary
For eye contamination, flush eyes immediately with water. Irrigate each eye continuously with 0.9%
saline (NS) during transport. Do not use emetics.
For ingestion, rinse mouth and administer 5 mL/kg up to 200 mL of water for dilution if the patient
can swallow, has a strong gag reflex, and does not drool.
6.3.12. Details of fire extinguishers
Details of fire extinguishers and firefighting arrangement provided at prominent places by the
industry is given in table below:
Sr. No. Type Capacity
1 Jockey Pump
2 Sprinkler system with sprinkler heads
3 Dry chemical Powder 2 Kg.
4 Dry Chemical Powder 5 Kg
5 Capacity Dry Chemical Powder 10 Kg.
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
178
6 Capacity Dry Chemical Powder 75 Kg.
6.3.13. Minimization of the manual handling of hazardous substance
Whether moving materials manually or mechanically, employees should know and understand the
potential hazards associated with the task at hand and how to control their work places to minimize
the danger. Employers and employees should examine their workplaces to detect any unsafe or
unhealthful conditions, practices, or equipment and take corrective action. Provide flameproof
electrical motor & transfer chemicals through the pipelines. Use specially designed pallets to hold,
move raw materials, finished products through work areas. Minimize lifting of raw materials, heavy
loads by using appropriate platforms, trolleys etc. Avoid the moving, manual handling of hazardous
material.
6.3.14. DO’S AND DONT’S
A. Handling of Chemicals
Do’s Don’ts
Know the hazards of the chemical
before handling.
Know the antidotes for chemical, which
you are handling.
Do keep material safety data sheet in
locations where chemicals are being
handled and study it.
Use appropriate personal protective
equipment like gloves, aprons, and
respirator; face shield etc. depending
upon nature of the work.
Label every chemical that you use and
tightly close the container.
Do not store the chemicals that are
incompatible with other chemicals.
Do not spill the chemicals.
Do not dispose chemical without
neutralizing.
Do not keep large inventory of
chemicals.
Do not allow empty containers of
hazardous chemicals to be used by
others.
Do not use compressed air for
transferring chemicals.
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
179
Use eye wash fountain / safety shower
in case of splash of chemicals in the eye
or body for at least 15 minutes.
Segregate toxic, flammable chemicals
and keep them under control.
In addition to draining and closing
valves, lines should be blanked before
taking up maintenance work.
Provide proper ventilation at the
chemical handling area to limit their
concentration within prescribed level.
Do not stand near chemical transfer
pump while it is in operation with
temporary hose connection.
Pouring of chemicals by hand or doing
siphoning by mouth should never be
adopted.
Chemicals drums should never be
moved without protection.
Do not attempt to neutralize the acid /
alkali on the skin. Use water only.
Do not use solvent for cleaning hands.
B. Material Handling
Do’s Don’ts
Use proper lifting tool and tackle having
adequate capacity.
Only authorized persons should
operate material handling equipment.
Each tool, tackle or equipment should
have number and safe working load
(SWL) marked on it.
Assess weight of the material, distance
to be carried and hazards etc. before
lifting the load.
Inspect and test all the lifting tools and
tackles regularly as per Factory Rules.
Wear Personal Protective Equipments
while handling of material.
Do not use the equipment for the
purpose other than its design intention.
Do not allow personnel to move
underneath lifted load.
Do not load the equipment above its
safe working load.
Do not use makeshift arrangements for
lifting equipment without inspection and
test.
Do not use defective tool and tackles.
Keep the tools & tackles free from
adverse effect of atmosphere by
applying suitable protective coating.
The angle between the legs of two leg
sling should not exceed 90 degree.
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
180
Wherever possible, mechanized
material handling shall be adopted.
While lifting a load physically, keep the
load as near as possible to the body
with feet properly placed for body
balance.
Bend knees, keep back straight, keep
the load closed to the body and lift the
load.
Do not allow male and female adult to
lift a load manually higher than 55 kgs
and 30 kgs respectively.
Do not hold the load with tip of the
fingers; grasp the load firmly with palm.
C. Fire Prevention
Do’s Don’ts
Follow ‘NO SMOKING’ sign.
Deposit oily rags and waste
combustible material in the identified
containers and dispose them suitably.
Fire Hose used for any other purpose
should be permanently marked and
taken out of fire hydrant system.
Keep minimum inventory of flammable
and combustible substances.
Take permission before breaking or
removal of fire barrier and ensure
subsequent relocation of fire barrier.
Check periodically the operability of
fixed firefighting system.
Attend any abnormality / deficiency with
fire protection system promptly.
Do not leave flammable material like
acetone, kerosene etc. used as
cleaning agent at the work area.
Do not over tighten fire hydrant valves
with F-lever.
Do not allow wild grass growth around
storage of the gas cylinders and
switchyard.
Do not obstruct accessibility to the fire
related equipment.
Do not destroy the inspection tag
provided with the fire equipment.
Do not misuse fire-fighting equipment
other than intended purpose.
Do not store the flammable material in
the open container.
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
181
Provide earthling or bonding to prevent
accumulation of static charges to tanks
where flammable chemicals are
stored/handled.
Use instruments that are intrinsically
safe in explosive atmosphere.
Do not use instruments that are not
intrinsically safe in the explosive
atmosphere.
D. House Keeping
Do’s Don’ts
Assign places for everything and
maintain things at assigned places.
Clean the area after completion of work.
Use aisle space free for personnel and
material movement.
Ensure adequate illumination and
ventilation for the job.
Drop paper, plastic, glass, metal and
biomedical waste in a separate bin kept
for this purpose.
Know the location where emergency
equipment such as first aid box,
firefighting equipment, SCBA,
Stretchers are kept.
Arrest all types of spills such as
chemical, water, oil, air / gas, steam etc.
and clean up the area immediately.
Ensure exits are indicated / painted for
use during emergency.
Do not leave combustible materials in
the work area.
Do not smoke in the area of work.
Do not allow dust bin to overflow.
Do not generate extra waste.
Do not disturb the safety equipment
from assigned location.
Do not block emergency switches and
on/off switches of the equipment by
storming of materials in front of work.
Do not leave cleaning agent like
acetone, isopropyl alcohol, kerosene
etc. at the work area after completion of
work.
Do not block fire exit point by storing
materials or by means.
Do not leave a spillage unattended.
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
182
6.3.15. Hazard Identification and Risk Assessment (HIRA)
The regulations require the employer, in consultation with employees, to identify:
a. All reasonably foreseeable hazards that may cause a major accident; and
b. The kinds of major accidents that may occur, the likelihood of a major accident occurring and
the likely consequences of a major accident.
HIRA must address potentially rare events and situations that ensure the full range of major
accidents and their causes. To achieve this, employers should:
a. Identify and challenge assumptions and existing norms of design and operation to test whether
they may contain weaknesses;
b. Think beyond the immediate experience.
c. Recognize that existing controls and procedures cannot always be guaranteed to work as
expected; and learn lessons from similar organizations and businesses
The HIRA worksheet is presented as below.
Hazard Description Consequences
Unloading of raw materials from
Trucks.
1. Fall of material causing injury to person.
2. Leakage/Spillage of chemical causing fire & explosion in
case of flammable chemicals.
3. Exposure to hazardous chemicals such as carcinogenic
may lead to health hazards.
4. Ergonomic hazards in case of manual handling of materials
Store of Raw Material. 1. Spillage & Leakage
2. Fire & Explosion
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
183
3. Fall of containers if stacked high.
4. Inhalation of chemicals.
Transportation of
solvents/chemicals to production
area
1. Spill & leak
2. Inhalation of vapours.
3. Fire & Explosion
4. Ergonomic hazards to person
5. Chemical/Solvent splash
Charging of Raw Material in to
reactors
1. Fire & Explosion due to static
2. Inhalation of Vapour.
3. Physical Injury
4. Spill & Leak
Boarding & packing of the
Finished product
1. Inhalation of Vapour.
Movement of Trucks 1. Hit & run over by Truck (Facility).
2. Properly Damage due to hitting of moving trucks.
3. Fire inside trucks cabin
4. Traffic Hazardous.
Considering the risk with the activities, company will provide the followings in order to mitigate the
risk:
1. Ventilation system
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
184
2. Fire Extinguishers
3. Summary of MSDS of chemicals will be displayed.
4. Spill control kit
5. Smoke detectors
6. Training to employees
7. Personal Protective Equipment (PPE)
8. Display of cautionary Signboard
9. Dust collection system
10. Speed limit policy within plant area
6.4. Conclusion & Recommendations
The hazard analysis and risk assessment of few possible selected incident scenarios indicates
that such incidents mostly are not limited to plant battery limits and have impact on adjoining plants.
There are possibilities of domino effect and the secondary scenario not predictable can be worse
than the primary one. No scenario (either thermal or toxic hazards scenarios) is crossing the Asiatic
plant boundaries (in normal case). The direction of impact will be in down wind direction (wind
direction and speed vary with season).
Some of the recommendations for Tank farm storage system are as given below:
Provision of flame detectors/ thermal sensors at strategic locations in the storage area.
Water deluge system on each bulk storage area for inflammable liquids. The system should
automatically start taking signal from flame detectors or thermal relay.
Fixed foam system with adequate capacity.
Toxic Hazards are due to Hazardous organic chemicals. Regular ‘Hazard Survey’ ensures the
detection of leakage in the plant.
Hazardous chemicals spillage/ leakage can have adverse impact in large area. In house ‘capability
building’ to attend hazardous scenarios is to be taken up through mock drills.
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
185
Human Factors: Asiatic should have well equipped firefighting system and also safety department
– safety practices (as required for small plants). Human factors role in safety cannot be ignored.
Odd hours working and over / long hours work can drain out individual. It shows in lack of efficiency
and also the lack of apt attention the modern chemical complex demand. They are to be closely
looked into and avoided.
‘Safety’ has unique features:
If no accident has happened so far probability of incident / accident occurring increases.
‘No accident’ / good safety record develops complacency inertia/ over confidence in the
team. This attitude gives rise to gaps / soft spots in the system giving chances to incidents
/ accidents.
Safety requires novelty. Routine training practices get stale with no positive results. Look
for novel scheme of training/ safety practices to build up fresh impetus in safety.
Involvement of employees with refreshed outlook for safety is to be achieved.
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
186
CHAPTER 7. DISASTER MANAGEMENT PLAN
7.1. Disaster Management Plan
Disaster/ Emergency Management Plan is essential for a chemical plant as the processes adopted
for manufacturing are classified under Factory Act as Hazardous due to handling and storage of
toxic, flammable and explosive hazardous materials. Over the years, the chemical process plant
has created adequate infrastructure and adopted risk mitigation measures to tackle any
emergency that may arise during the manufacturing process. The important aspect in emergency
planning is to control an emergency by technical and organizational means, minimize accidents
and consequent losses. Emergency planning also brings to light deficiencies, such as, lack of
resources necessary for effective emergency response. It also demonstrates the organization's
commitment to safety of employees and physical property as well as increases the awareness
among management and employees.
Disaster Management Plan for the plant is necessarily a combination of various actions which are
to be taken in a very short time but in a pre-set sequence to deal effectively and efficiently with any
disaster, emergency or major accident with an aim to keep the loss of men, material,
plant/machinery etc. to the minimum.
A major emergency in a hazardous chemical plant is one, which has the potential to cause serious
injury or loss of life. It may cause extensive damage to property and serious disruption of both
inside and outside the plant. Sometimes, it would require the assistance of outside emergency
services to handle it effectively. Although the emergency at the plant may be caused by a number
of different factors, e.g. leakage of toxic and flammable materials from piping/tanks, total/partial
power failure, earthquake or sabotage, it will normally manifest itself in fire/toxic release.
Primarily, DMP is prepared to furnish details which may require at the time of the emergency, to
delegate responsibility, to estimate the consequences in advance and to prepare ourselves to
control any type of emergency. The plan explains basic requirements as follows:
Definition,
Objectives,
Organization set up,
Communication System,
Action on site,
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
187
Link with Off-site Emergency Plan,
Training rehearsal and record aspect.
7.1.1. Definitions
Various definitions on different analogy used on On-site & Off-site Emergency Plan are as follows:
Accident: An accident may be defined as “an undesirable and unplanned event with or without
or major damage consequence of life and /or property.
Major Accident: It is a sudden, unexpected, unplanned event resulting from uncontrolled
developments during an industrial activity, which causes or has the potential to cause, death or
hospitalization to a number of people, damage to environment, evacuation of local population or
any combination of above effects.
Emergency: This can be defined as any situation, which presents a threat to safety of person's
or/and property. It may require outside help also.
Major Emergency: Occurring at a work is one that may affect several departments within and/or
may cause serious injuries, loss of life, extensive damage to properly or serious disruption outside
the works. It will require the use of outside resources to handle it effectively.
Disaster: Disaster is a sudden calamitous event, bringing great damage, loss or destruction.
Hazards: Hazard may be defined as “the potential of an accident”. Hazard exists in man and the
system of materials and machines.
Chemical Hazards: It is a hazard due to chemical(s) (including its storage, process, handling,
etc.) and it is realized by fire, explosion, toxicity, corrosively, radiation, etc.
Risk: Risk may be defined as the combination of consequence and probability or likelihood of an
accident being caused in a given man-material – machine system.
On-Site Emergency plan: It deals with measures to prevent and control emergencies within the
factory and not affecting outside public or environment.
Off-Site Emergency plan: It deals with measures to prevent and control emergencies affecting
public and the environment outside the premises.
7.1.2. Objective of the Disaster Management Plan
The primary purpose of this Disaster Management Plan is to equip the Plant with required
resources and information for prompt implementation of the set of actions to be undertaken in the
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
188
event of an accident posing hazards to the people and community after commissioning of the
plant.
The objective of Disaster Management Plan (DMP), for the plant is to be in a state of perceptual
readiness through training, development and mock drills, to immediately control and arrest any
emergency situation so as to avert a full fledge disaster and the consequence of human and
property damage and in the event of a disaster still occurring, to manage the same to that the risk
of the damage consequences to life and property are minimized and thereafter, proper
rehabilitation, review and revisions of the DMP to overcome the shortcomings noticed are
undertaken.
The DMP document is prepared keeping in view and to conform the requirements of the provisions
of The Factories Act 1948 under section 41 B (4), Guidelines issued by the Ministry of
Environment and Forests, Govt. of India and Manufacture, Import and Storage of Hazardous
Chemicals Rules, 1989 amended in 2000, Schedule 11 under Environmental Protection Act 1986.
Following are the main objectives of the plan to:
Defined and assess emergencies, including hazards and risk
Control and contain incidents.
Safeguard employees and people in vicinity.
Minimize damage to property and/or the environment.
Minimization of risk and impact of event accident.
Preparation of action plan to handle disasters and to contain damage.
Inform employees, the general public and the authority about the hazards/risk assessed
and to provide safeguard, and the role to be played by them in the event of emergency.
Be ready for 'mutual aid' if need arises to help neighboring unit.
Inform authorities and mutual aid centres to come for help.
Effect rescue and treatment of casualties.
Effective rehabilitation of the affected persons and prevention of damage to the property.
Identify and list any fatalities.
Inform and help relatives.
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
189
Secure the safe rehabilitation of affected areas and to restore normalcy.
Provide authoritative information to the news media.
7.2. Emergency Preparedness and Response System
Section 41-B (4) of the Factories Act, 1948 requires that every occupier of a factory shall prepare
an ON-SITE emergency plan and detailed accident control measures for the factory. Accordingly,
the ON-SITE and OFF-SITE emergency plan with details of accident control measures has been
prepared for the employees and general public living in the vicinity of the factory. This plan gives
the safety measures to be taken in the event of any accident happening at the plant. The
provisions of the proposed draft rules and the following guidelines given by the Factory
Inspectorate office are kept in mind while preparing this plan.
1. Status relating to risk assessment and environment impact in case of Toxic release and the
measures taken for prevention of such accident.
2. Probabilities of possible hazard due to the failure of provided control measures and equipment
such as safety valve, pressure gauge, temperature indicator etc. at different stages of process.
3. Provisions for all facilities and procedures for immediate control to minimize the effect of such
probabilities.
4. Arrangement for informing workers through emergency alarm and public in vicinity and
surrounding factories through telephone and loud speakers in case of emergency at the factory.
5. Arrangement for evacuation of persons likely to be affected due to emergency.
6. Arrangement for transporting affected persons to the hospital and medical center through
Car/Ambulance.
7. Arrangement for necessary treatment and availability of antidotes at hospitals and at medical
center.
8. Organization Chart for fixation of responsibilities of managers, officers, workers at different
stages for handling emergency due to spillage, fire, explosion etc.
9. Details regarding alert system like emergency alarm.
10.Provision for Training, rehearsals, mock drill etc. at regular intervals to the personnel handling
emergency
11.Notification of place of gathering of workers and staff at the time of emergency.
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
190
12.Information in detail, regarding any disaster, which might have occurred in factory.
13.Provisions of main control for 24 hours to use at the time of emergency.
14.Submission of material safety data sheet of chemicals.
15.Arrangement regarding maintenance of different equipment, control measures and safe
procedure of work so that they shall work effectively.
16.A statement of all possible source of accidents involving fire, explosion and plan of showing
the place of above accidents with the facilities to control the emergency near the place and at the
control place
17.A statement of Quality, health and safety policy of factory.
18.OFF-SITE emergency services which a link is between ON-SITE and OFFSITE PLAN. While
preparing this plan, the following documents have been referred and thankful to those for their
contribution.
This plan is prepared covering all hazards like fire, explosion etc. and given steps to prevent and
minimize it.
This plan is very useful to the operatives, employees working in factory, public staying in the
vicinity of the site to take the suitable steps at the time of any emergency.
7.3. Emergency Organization
7.3.1. Incident Controller
Incident Controller’s role will be to control the emergency at the incident site
Duties of Incident Controller
Incident Controller will proceed to the place of emergency after hearing siren/announcement. He
will:
Assess the scale of emergency and decide if a major emergency exists or is likely,
accordingly activate emergency procedure.
Immediately give his feedback to Emergency Control Centre (ECC) regarding emergency.
Direct all operations within the area with following priorities.
o Secure the safety of personnel
o Minimize damage to plant property and environment.
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
191
o Minimize loss of material.
Direct rescue and firefighting operations till the arrival of the outside Fire Brigade; he will
relinquish control to Sr. Officer of Fire Brigade.
Ensure that the affected area is searched for causalities.
Ensure that all non-essential workers in the affected area evacuate to the appropriate
assembly point.
Set up communication point to establish Radio/Telephone/Messenger contact as with
emergency control center.
Pending arrival of works site controller, assume the duties of the post in particular to:
o Direct the shutting down and evacuation of plant and areas likely to be threatened
by emergency.
o Ensure that the outside emergency services have been called in.
Ensure that the key personnel have been called in.
Report all significant development to the Site Main Controller.
Provide advice and information, as required to the Senior Officer of the Fire Brigade.
Preserve evidence that would facilitate any subsequent inquiry into the cause and
circumstances of emergency.
Dy. Incident Controller will carry out above said duties in absence of Incident Controller.
7.3.2. Site Main Controller
Site Main Controller will be overall in-charge of emergency organization:
Duties of Site Main Controller:
Relieve the Incident Controller of responsibility of overall main control.
Co-ordinate ECC or if required, security for raising evacuation siren and also all clear siren,
in case emergency is over.
Declaration of major emergency ensures that outside emergency services will be called
and when required nearby firms will be informed.
Ensure that key personnel will be called in.
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
192
Exercise direct operational control on parts of the works outside the affected area.
Maintain a speculative continuous review of possible development and assess these to
determine most possible cause of events.
Direct the shutting down and evacuation of plants in consultation with key personnel.
Ensure causalities are receiving adequate attention; arrange for additional help if required.
Ensure relatives are advised.
Liaison with Chief Officers of the Fire and Police services for providing assistance in
tackling the emergency.
Ensure the accounting of personnel.
Control traffic movement within the work.
Arrange for a chronological record of the emergency to be maintained.
During prolonged emergency, arrange for the relief of the personnel and provision of
catering facilities.
Contact the local office to receive early notification of impending changes in weather
conditions, in case of prolonged emergency.
Issue authorized statements to the news media and informs H.O.
Ensure that proper consideration is given to the preservation of evidence.
Control rehabilitation of affected areas after control of the emergency.
7.3.3. Other Key Personnel
The key personnel required for taking decision about further action for shutting down the plant,
evacuate the personnel, and carry out emergency engineering works in consultation with Site
Main Controller in light of the information received.
HOD’s /Senior Managers/ Section Heads will be responsible for safety, security, fire, gas and
pollution control, spillage control, communication system including telephone, wireless etc. Also,
medical services, transport, engineering, production, technical services, will form part of advising
team.
Emergency Response Team
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
193
The role of Emergency Response Team members is to actually combat the emergency at the site
and control the emergency situation and carry out rescue operations.
All team members will be thoroughly trained to deal with fires, explosions, chemical spills and
atmospheric releases, first aid. As per priority list during emergency, the activities will be carried
out as per emergency control plan.
Emergency Personnel’s responsibilities Outside Normal Working Hours of the Factory.
The duties of Shift In-charge & team members have been brought out in emergency control plan.
All team members after evacuating the area shall report to ECC/ Incident Place. The non-essential
workers shall be evacuated from the plants if need arises and this will be determined with the
forcible rate with which incident may escalate. Non-essential workers shall assemble at the
earmarked/specified point of assembly.
Assembly Points
At the proposed plan, at least 2 assembly points will be identified and marked properly.
7.3.4. Emergency Control Centre
It will be headed by Site Main Controller, HOD – PD, HOD- P&A and it is sited in Office of Site
Main Controller in Admin Building & New security office (after office hours), which is readily
accessible & with minimum risk, equipped with telephone facilities and other announcements
extra communications facilities needed. It has enough means to receive and transmit information
and directions from site main controller to incident controller and other areas. In emergency
control centre due to its safer location and advantage of easier accessibility, all necessary
personnel protective equipment’s firefighting extinguishers will be stocked in sufficient quantity.
Role of Emergency Control Centre
In case of mishap or accident like fire, toxic gas leakage, explosion in the factory, The Emergency
Control Centre will be Office of Head- Operations
The plot plan indicating all the activities in the factory premises including that of storage’s
utility services, production area, administration, will be kept for ready reference, showing
the location of fire hydrant and firefighting aids.
Normal roll of employees, work permits, gate entries and documents for head count,
employees blood group, other information and addresses will be available and the person,
who will handle this operation will HOD P & A.
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
194
Stationery required is available in the Control Centre (ECC) and HOD (P & A) looks after it
The requirement of personnel protective equipment and other material, like torches, have
been worked out and the quantity required during emergency will be kept in the Control
Room (ECC). The responsible person for maintaining the said requirement/inventory will
be HOD- HSE.
7.3.5. Fire & Toxicity Control Arrangements
The plant will be well equipped with suitable numbers of firefighting and personnel protective
equipment. The staff will be trained regularly to handle the various emergency situations.
7.3.6. Medical Arrangements
Availability of first aid facilities in sufficient quantity will be always ensured. In case of emergency
arrangements will be made to avail outside medical help immediately. Emergency transport facility
will be available.
7.3.7. Transport & Evacuation, Mutual Aid Arrangements:
Transport & Evacuation and Mutual Aid arrangements will be available in the factory.
7.4. Communication System
7.4.1. Declaring the Emergency
In case of any emergency in the plant, speedy and effective communication of the same to all
concerned in lEast possible time is the most important aspect of any emergency-handling plan.
An early communication increases the chances of control of emergency in the bud stage. Blowing
siren will be adopted as method of communication of emergency, to all employees in the plant.
Types of Sirens
Three different types of sirens have been identified for communication of emergency.
Alert Siren: Single Continuous Siren for One Minute. This indicates that there is some accidental
happening in the plant. All have to become alert. Incident controller will be rush to the site of
emergency. Plant area people have to start safe shut down. Rescue team and other emergency
control teams have to reach at the site of emergency.
Siren for evacuation: wailing & waning siren for three minutes. This siren indicates that
emergency is of serious proportion and everybody has to leave his work place. All people having
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
195
their role in emergency control have to assume their assigned role. All non-essential workers have
to proceed immediately to assembly area and wait for further instruction.
All clear siren: Long continuous siren for two minutes. This is a sign of return of normalcy. On
hearing this siren everybody should go back to his or her respective workplace.
Location of Siren
Siren will be located in centre of the plant for wide coverage of the whole campus. Switch for siren
will be provided at security gate. The switch at Security gate should be operated only as a general
rule.
Emergency manual call bell will be installed which will be used in case of total failure of electricity.
It is responsibility of HOD (HSE) to maintain the upkeep of electric call bell and HOD- Security
and administration to maintain manual and Hand operated siren.
Raising Alarm
Any person noticing any emergency situation in the plant should immediately call security gate
with following information:
Identify oneself
State briefly the type of emergency i.e. whether fire, explosion, toxic gas release etc.
Give the location of the incident
Estimated severity of the incident.
Security personnel after ensuring genuineness of the call shall raise the ALERT SIREN. At the
same time he will also contact the incident controller and ECC in order and inform about the
incident. He will keep the gate open and rush his two security personnel at the site of emergency.
ECC will be located at the office of Head- Operations on normal working hours and at Security
gate after normal working hours (during night). ECC shall be immediately manned on hearing
alert siren. If the authorized people to handle ECC are not available, any senior most people out
of the available person nearby shall occupy ECC till authorized person comes.
Incident controller, on hearing alert siren or by any other way of information of the emergency,
will immediately reach at the site of incident and assess the situation. He will immediately give his
feed back to ECC. ECC shall direct security gate to raise evacuation siren, if the need arise.
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
196
SIREN FOR EVACUATION shall be raised on instruction from Site Main Controller or any
Manager of the plant in the ECC.
Security gate person will be authorized to raise ALL CLEAR SIREN on instruction from Site Main
Controller or ECC, after the emergency is over.
Incident controller shall assume the responsibility of site main controller in his absence
7.4.2. Internal Communication
It shall be responsibility of ECC to communicate to all employees in the plant. They may take help
of telephone operator for such communication. However, telephone operator can directly
communicate information about emergency to all internal departments, if such message comes
from incident controller or site main controller. Telephone operator will continue to operate the
switchboard advising the callers that staffs are not available and pass all calls connected with the
incident to ECC.
Availability of Key Personnel Outside Normal Working Hours
The details of key personnel availability after working hours will be made available at Security
Gate, ECC, telephone operator as well as production units. Security personnel shall call required
key personnel from their residence in case emergency occurs outside normal working hours.
Availability of emergency vehicle / Ambulance will be ensured to fetch the key personnel residing
outside. It will be the responsibility of HOD (P & A) to maintain it.
To the Outside Emergency Services
Decision to call outside help to deal with emergency like fire brigade, ambulance, police, etc.,
shall be taken by Site Main Controller. However, in absence of Site Main Controller, if the incident
controller realizes the situation going out of control, he may ask for immediate help from outside.
ECC will be responsible for calling help from outside. A list of emergency services available in the
area with their telephone numbers will be provided at ECC, at Security gate and with telephone
operator. Facilities such as phones, emergency vehicle, and security personnel will be available
to help calling outside emergency services and authorities.
7.4.3. Communication to the Authorities
The emergency will be immediately communicated to the government officers and other
authorities such as SPCB, police, district emergency authority, Factory Inspectorate, hospital etc.
by Emergency Control Centre.
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
197
To Neighbouring Firms & the General Public
In case of emergency having its outside impact, public will be cautioned regarding the same. Co-
ordination of police will be sought for speedy action. This is to be ensured by ECC.
7.5. Pre-emergency activities
Internal Safety survey with regard to identification of hazards, availability of protective
equipment’s, checking for proper installation of safety devices will be carried out periodically.
Periodic pressure testing of equipment
Periodic pressure testing of lines.
Periodic safety/relief valve testing
Periodic fire hydrant system testing.
Mock drill to check up level of confidence, extent of preparedness of personnel to face
emergency is being contemplated.
Regular training is being imparted to all personnel to create awareness.
Adequate safety equipment will be made available.
Periodic check-up of emergency lights.
Safer assembly points will be identified.
Storage of adequate first aid treatment facilities.
Statutory information is imparted to workers.
Post emergency activities:
Following post emergency actions will be carried out to study in detail and preventive measures
to be taken.
Collection of records.
Inquiries
Insurance claims
Preparation of reports comprising suggestion and modification.
Rehabilitation of affected personnel.
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
198
Normalization of plant.
7.5.1. Evacuation and Transportation
In case of emergency, evacuation and transportation of non-essential workers will be carried out
immediately. The affected personnel will be transported for medical aid.
7.5.2. Safe Close Down
During emergency plant shut down will be carried out if situation warrants. This will be as per the
instruction of site main controller under guidance of incident controller.
7.5.3. Use of Mutual Aid
Mutual aid agreement with nearby industries will be ensures to provide help to each other in the
emergency,
7.5.4. Use of External Authorities
As and when necessary, statutory authorities, police, pollution control personnel, medical aid/
center, ambulance etc. will be contacted.
7.5.5. Medical Treatment
The affected personnel will be brought to safer place immediately to give them first aid. Immediate
medical attention will be sought.
7.5.6. Accounting for Personnel
Proper accounting for personnel will be laid down in all the shifts. The number of persons present
inside the plant premises, their duty etc. will be available with the P & A. This record will be
regularly updated and will be made available.
7.5.7. Access to Records
The relatives of affected personnel will be informed. The details regarding all employees will be
made available to Administration building.
7.5.8. Public Relations
In case of emergency, Manager P & A will be available for official release of information pertaining
to the incident.
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
199
7.5.9. Rehabilitation
The affected area will be cleared from emergency activities only after positive ascertaining of the
system in all respects. The entry to affected area will have to be restricted until statutory
authorities visit and inspect the spot of incident. Nothing should be disturbed from the area till
their clearance. The site main controller will be in charge of the activities to be undertaken.
The plan will cover emergencies, which can be brought under control by the works with the help
of emergency team/fire services. The DISASTER CONTROL PLAN for gas leak and fire will be
prepared for entire factory.
7.6. Causes of Emergency:
7.6.1. Risk
Nature
In the plant, the nature of dangerous events could be of the following:
FIRE : Chemical/Electrical
TOXIC RELEASE : From chemicals & Chlorine gas.
LEAKAGES : Equipment, pipe lines, valves, etc.
Release of vapors like chlorine / bromine gas or hexane can result in highly toxic environment or
in fire or explosion.
Improper handling of products (raw materials/finished products)
Large spillage to ground floors resulting in pollution & fire.
Failures of Equipment / Instruments.
Release of safety valves or ruptures of vessels due to excessive pressures.
Various Emergency Actions
a. Onsite
Safe shut down of the plant and utilities.
Emergency control measures.
To attempt with the help of trained crew in firefighting to contain the fire spread up/gas
emission and limit within limited space.
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
200
To cut off source of oxygen by use of firefighting appliances/to cut off source of gas
emission.
Cut off fall sources of ignition like electrical gadgets.
To protect fire prone area from the fire.
To remove material which can catch fire to the extent possible from fire prone area.
Evacuation of non-essential persons.
b. Medical Facilities/Treatment
The Plant will have a Health centre which is manned with trained male nurse on continuous
basis who can render medical first aid. Doctor will visit two times a week for two hour each
time. The Plant is searching for a full time medical officer and will appoint as and when
available.
Depending on seriousness the injured person shall be shifted to any other hospital.
Vehicle will be available round the clock for transportation. Ambulance will be also made
available in the campus on regular basis.
a. In the event of Fatal Accidents
The information shall be given to following authorities:
Inspector of Police
Inspector of Factories
Mamlatdar
Corporate Office
Regd. Office
Insurance the plant
Regional Officer, SPCB
b. Emergency Siren
Emergency siren shall be blown for announcing the emergency which shall have different sound
for identification/differentiation than the normally used for commencement of factory working etc.
Location of Siren : Above Plant.
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
201
Type of Siren : Industrial Siren
Position of siren switch: Located at Main Gate
c. Seeking Help From Neighbouring Industries / Sources For Fire Engine
d. Advise for vacation of other areas
Since the effect of fire/gas emission shall be contained within the area of the plant advice of
vacation of other areas is not necessary.
Response Time-Minutes
Hazard Fire Fighting Police Medical Services
Fire & Explosion Immediate with
whatever facilities
available with the
plant
10 minutes 10 minutes
External Help
within 15 minutes
7.7. Off-Site Emergency Plan
7.7.1. Need of the Site Emergency Plan
Depending upon the wind direction and velocity of the effects of accident in factory may spread
to outside its premises. To avert major disaster, it is essential to seek guidance/assistance of
statutory authorities, police and health department. The movement of traffic may have to be
restricted.
Required information will be given to the authority and consultation will be sought for remedial
measures.
A purpose of the off-site emergency plan is:
o To provide the local/district authorities, police, fire, brigade, doctors, surrounding
industries and public the basic information of risk and environmental impact
assessment and appraise them of the consequences and the protection/prevention
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
202
measures and to seek their help to communicate with public in case of major
emergency.
o To assist district authorities for preparing the off-site emergency plan for district or
particular area and to organize rehearsals from time to time and initiate corrective
actions on experience.
7.7.2. Structure of the Off-Site Emergency Plan
Available with concerned authorities.
7.7.3. Role of the Factory Management
The site main controller will provide a copy of action plan to the statutory authorities in order to
facilitate preparedness of district/area off-site emergency plan.
7.7.4. Role of Emergency Co-ordination Office (ECO):
He will be a senior police or fire officer co-ordination with site main controller. He will utilize
emergency control center.
7.7.5. Role of Local Authority
Preparation of Off Site Plan lies with local authorities. An emergency-planning officer (EPO)
works to obtain relevant information for preparing basis for the plan and ensures that all those
organization involved in offsite emergency and to know their role and responsibilities.
7.7.6. Role of Fire Authorities:
The fire authorities will take over the site responsibility from incident controller after arrival. They
will be familiarized with site of flammable materials, water and foam applies points, firefighting
equipment.
7.7.7. Role of the Police and Evacuation Authorities:
Senior Police Officer designed, as emergency co-ordination officer shall take over all
control of an emergency. The duties include protection of life, property and control of traffic
movement.
Their functions include controlling standards, evacuating public and identifying dead and
dealing with casualties and informing relatives of dead or injured.
There may be separate authorities/agencies to carry out evacuation and transportation
work.
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
203
Evacuation depends upon the nature of accident, in case of fire only neighboring localities
shall be alerted. Whole areas have to be evacuated in case of toxic release.
7.7.8. Role of Health Authorities
After assessing the extent of effect caused to a person the health authorities will treat them.
7.7.9. Role of Mutual Aid Agencies
Various types of mutual aid available from the surrounding factories and other agencies will be
utilized.
7.7.10. Role of Factory Inspectorate
In the event of an accident, the Factory Inspector will assist the District Emergency
Authority for information and helping in getting Neighboring Industries/mutual aid from
surrounding factories.
In the aftermath, Factory Inspector may wish to ensure that the affected areas are
rehabilitated safely.
7.8. Mock Drills and Records
7.8.1. Need of Rehearsal & Training
Regular training and rehearsal program of emergency procedures shall be conducted with
elaborate discussions and testing of action plan with mock drill. If necessary, the co-
operation/guidance of outside agencies will be sought.
7.8.2. Some Check Points
The extent of realistic nature of incidents.
Adequate assessment of consequences of various incidents.
Availability of sufficient resources such as water, firefighting aids, personnel.
The assessment of time scales.
Logical sequences of actions.
The involvement of key personnel in the preparation of plan.
At least 24 hour’s covers to take account of absences due to sickness and holiday,
minimum shift manning.
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
204
Satisfactory co-operation with local emergency services and district or regional emergency
planning offices.
Adequacy of Site.
7.8.3. Records and Updating the Plan
All records of various on-site and off-site emergency plans of the factory will be useful alone with
those of the factors by which statutory authorities draw a detailed plan for the whole area/district.
The records of the activity will be updated regularly.
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
205
CHAPTER 8. PROJECT BENEFITS
8.1 Introduction
Due to the proposed project, 64 nos. of local peoples and outside peoples will get employment
during the construction phase and additional 30 peoples will be employed during the operation
phase. Local people will be given preference for almost all the jobs in the Plant, direct as well as
indirect. Economic status of the local people will be improved due to the increased business
opportunities, thereby, making a positive impact. Educational, medical and housing facilities in
the study area will considerably improve. Therefore, social infrastructure of the study area will be
improved. The company will also do following developmental activities in the area: The proposed
Project does not involve any displacement of villages; however it will lead to development of the
region and increase in infrastructure facility. During the operation phases of the project a work
force will be needed which will include both skilled and unskilled people. Due to the proposed
project direct employment for local employees will be generated. Existing ancillary as well as
auxiliary industries would be benefited by way of getting additional work. In addition to direct
employment, indirect employment will generate ancillary business to some extent for the local
population. Due to the proposed Project, facilities are likely to grow with the development. There
is a positive effect due to improved communication and health services, which have lead to
economic prosperity, better educational opportunities and access to better health and family
welfare facilities. There will be beneficial effect on human settlement due to employment
opportunities from the industry.
Local quality of life will be improved. This factor combined with all other mitigation measures like
proper treatment and disposal of wastewater, hazardous waste and gaseous emission has
minimized the adverse impact on ecology and had a beneficial impact on human settlement and
employment opportunities. There has been a beneficial impact on the local socio-economic
environment. The increasing industrial activity will boost the commercial and economical status
of the locality up to some extent.
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
206
CHAPTER 9. SUMMARY AND CONCLUSION
9.1 Introduction
The environmental impacts of projects or actions generally encompass a broad range of impact
from Air and Noise pollution to affect on employment and neighbourhood as well as on social
structure. All of these impacts vary in magnitude as well as in their beneficial or adverse
classification. As a result, a natural question arises as to what is the “collective” or “overall”
environmental impact of the project or action taken. Is the project beneficial or is it adverse? To
answer such a question requires a comparison of these impacts and to some extent subjective
evaluation of those impacts which are more important than others. Environment Impact
Assessment as detailed in previous chapter can now be concise to impact statement given below.
Air Environment
Meteorological data collected during the study period confirms that climatic Status of the study
area is consistent with the regional meteorology. Average concentration of ambient air quality
parameters such as PM10, PM 2.5, SO2 and NOx in the surrounding study area are well within
the permissible limits as prescribed in the National Ambient Air Quality (NAAQ) Standards for
respective residential rural areas and industrial areas. Evaluated GLCs due to the proposed air
pollution load in proposed stack. When added to the monitored existing ambient air quality,
provides the expected ambient air quality when the proposed stack will be in operation and the
same indicates that expected AAQ are well within the permissible limit of National Ambient Air
Quality Standards for residential rural areas as well as industrial areas. It is concluded from the
above that there will be a minor impact on the AAQ of the surrounding environment due to
operation of the proposed project.
Water Environment
The total fresh water requirement for the proposed project is 2.7.KLD. The water will be met
through the existing bore well. The quality of the water was tested at 7 locations in the study area.
The ground water norms were compared to IS: 10500 (1991) for evaluation. The domestic effluent
(2.1 KLD) is treated through STP.
Wastewater Generation & Disposal:
For the proposed manufacturing activity, the total water consumption will be 2.7.KL /Day.
From that the domestic water consumption will be 2.7 KL/Day • Industrial water consumption will
be Nil.
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
207
The industrial wastewater generation will be 0.95 Kl/Day
From That 2.1 KL/Day Domestic wastewater will goes to STP
Industrial wastewater 0.95KL/Day will go to ETP & finally it will be evaporated in Evaporator to
achieve Zero discharge.
Thus, it can be concluded that negligible impact on surrounding water environment is caused.
Further, it is emphasized that all precautionary measures have to be strictly adhered as mentioned
in the Environmental Management Plan given in Chapter 6, to maintain ground water quality within
norms in the future.
Noise Environment
Base line data indicates that noise levels in the study area are not on higher sides. Noise level in
and around plant site were measured. Measured noise levels within premises indicate that overall
noise levels are within the Damage Risk Criteria. The company will provide ear-protecting
devices/ earplugs for working personnel exposed to high noise level. It can be concluded that
there will be no impact on the noise level of the surrounding environment.
Hazardous Wastes
As per the Hazardous Waste (Management & Handling) Amendment Rules, 2003, all necessary
control steps for each type of Hazardous Wastes generated from the proposed project will be
taken. Therefore, no impact of hazardous wastes generation on surrounding soil environment is
anticipated. Due to the proposed project the, land use pattern; land cover and topography of the
area will be changed only within the premises.
Ecology
The proposed project will be carried out on land within their premises without cutting of any trees.
Also, the project site is expansion project, So it does not alter the crop pattern and natural
vegetation of the surrounding area. Due to the safe control technology of air pollutants, liquid
effluents and solid/hazardous wastes disposal, no impact on the surrounding ecology is
anticipated.
Socio - Economic Environment
The proposed project will generate direct employment for employment persons. The indirect
employment will be generated by way of transportation, shopkeepers and other casual
employment. Implementation of this plant will also reduce production loss due to shortage of
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
208
power. Thus, the proposed project will have significant positive impacts on the employment
pattern of the study area.
9.2 Conclusion and Recommendations
Based on the environmental impact assessment conducted, the following recommendations are
made:
Since regulations are fast changing in India, the project proponent must keep himself or
herself updated with respect to applicable laws and take appropriate actions in case the
provisions in some regulations undergo change.
The impacts envisaged due to construction activities will be for short limited period. Impact
due to operational activities, systems of periodic auditing and reporting shall be adopted
during the operation period to ensure that the system adheres to the EMP.
The project proponent and its team of consultants and contractors are urged to develop a
strategy for effective communication with local people. The construction team/ developer
should effectively follow the suggestions made in the EMP and/ or any other environmental
measures so as not to damage the environment of the project area.
CSR activities should be further strengthened.
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
209
CHAPTER 9. DISCLOUSER OF CONSULTANT
Declaration by Experts Contributing to this Report Declaration by Experts Contributing to the
Environmental impact assessment and Risk assessment for Expansion of manufacture @700
MT/Month of Saturated & Unsaturated Resins at survey no.1963/185/24-B-paiki, village: Mankol,
Tal: Sanand: Ahmedabad, Gujrat-382 110.
I, hereby, certify that I was a part of the EIA team in the following capacity that developed the
above EIA.
EIA Coordinator
Name: Astha Bishnoi
Signature:
Functional Area Experts & Team Members
Functional Areas Name of the
expert
Involvement Signature
Air Pollution
Monitoring &
Control (AP)
Astha Bishnoi Site visit, assistance in selection
of monitoring locations,
checking air quality data,
evaluation of results of Ambient
Air Quality Monitoring (AAQM)
Air Quality
Modelling and
Prediction (AQ)
Rajni Oshan Assistance in air quality
modelling and prediction: met
file generation and model run
Water Pollution
(WP)
Astha Bishnoi
Akruti Patel (Team
member)
Site visit, assistance in selection
of sampling locations for surface
water sampling, water balance
for the project and contribution
to EIA documentation
EIA REPORT OF M/s. ASIATIC COMPOSITES LTD FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS
210
Ecology and
Biodiversity
Conservation (EB)
Astha Bishnoi Site visit, assistance in selection
of sampling locations and
contribution to EIA
documentation
Risk and Hazards
(RH)
Prabhat Kumar
Srivastava
Site visit, Identification of
modeling scenarios,
consequence modeling using
PHAST, finalization of DMP,
contribution to RA / DMP
Documentation and contribution
to EIA documentation
Soil Conservation
(SC)
Astha Bishnoi Site visit, assistance in selection
of sampling locations and
contribution to EIA
documentation
Land use (LU) Akruti Patel Development of land use maps
of study area using GIS / related
tools, site visit for ground truth
survey, finalization of land use
maps.
Declaration by the Head of the accredited consultant organization/ authorized person
I, Bhadresh S. Rana, hereby, confirm that the above-mentioned experts prepared the EIA report
of Expansion of manufacture @700 MT/Month of Saturated & Unsaturated Resins at survey
no.1963/185/24-B-paiki, village: Mankol, Tal: Sanand: Ahmedabad, Gujrat-382 110. I also confirm
that the consultant organization shall be fully accountable for any mis-leading information
mentioned in this statement.
Signature:
Name: Bhadresh S. Rana
Designation: Proprietor