Date post: | 27-Mar-2023 |
Category: |
Documents |
Upload: | khangminh22 |
View: | 0 times |
Download: | 0 times |
Consideration Paper – HRE09001 Modified Reassessment of LPG, Propane and Butane Page 1 of 62
HRE09001
Hazardous Substances Consideration Committee
TOPIC: Consideration of Application for the Modified Reassessment of
LPG, Propane and Butanes
Introduction
1 The LPG Association of New Zealand Inc (LPGA) is seeking the modified reassessment
of the substance identified as Liquid Petroleum Gas (LPG). As the definition of LPG
may include 100% propane, 100% butane or 100% isobutane1, these substances are also
included in the reassessment. Please note that the term LPG as used in this document
also refers to propane, butane and isobutane.
2 The substances were approved under the Hazardous Substances and New Organisms Act
1996 (―the Act‖) via the Hazardous Substances (Dangerous Goods and Scheduled Toxic
Substances) Transfer Notice 2004 (as amended) and have the following HSNO Approval
Numbers:
Liquefied Petroleum Gas (LPG) Approval No: HSR001009
Propane Approval No: HSR001010
Butane Approval No: HSR000989
Isobutane Approval No: HSR001003
3 The application document proposed the following modifications to the approvals for the
identified substances:
2.1 An increase in the threshold for the requirement for location test certificates from
100 kg to 300 kg;
2.2 The replacement of the default requirement for spray cages over tank wagons
carrying LPG which are parked for longer than one hour, with a risk assessment
using section 12 of AS/NZS 1596 for each storage premises;
2.3 The replacement of the separation distances for cylinder and tank storage of LPG
as specified in the Hazardous Substances (Dangerous Goods and Scheduled
Toxic Substances) Transfer Notice 2004 with those specified in AS/NZS 1596;
2.4 The removal of the fire extinguisher requirements for storage of > 50 kg of LPG
in domestic property;
2.5 The removal of the aggregation requirement for separation distances for
vaporisers; and
2.6 The removal of the stationary container system certification requirements for
LPG and transfer of any requirements not covered by Pressure Equipment,
Cranes, and Passenger Ropeways (PECPR) Regulations 1999 to the location
certification requirements.
1 Please note that isobutane was unintentionally omitted from the application to determine grounds for
reassessment, but is considered to be covered by the definition of LPG and therefore has been included in this
application for reassessment.
Consideration Paper – HRE09001 Modified Reassessment of LPG, Propane and Butane Page 2 of 62
Legislative Criteria for the Application
4 Unless otherwise stated, references to section numbers in this report refer to sections of
the Act and clauses to clauses of the Hazardous Substances and New Organisms
(Methodology) Order 1998 (―the Methodology‖).
5 In its decision dated 5 December 2008 (Application Number: RES07007), the Authority
determined that there was significant new information relating to the effects of the
substances and that this information constituted grounds for their reassessment (section
62(2)(a)). Consequently, the applicant was able to make an application for the modified
reassessment of the substance.
6 The application was Formally Received on 25 September 2009 in accordance with
section 63A on the basis that─
(a) a reassessment of the hazardous substances under section 63 is not appropriate
because the reassessment will involve only specific aspects of the approvals; and
(b) the amendments are not minor or technical amendments to which section 67A
applies (i.e. a change is use is not considered a minor or technical amendment).
7 The Authority may approve or decline an application for reassessment under this section,
as it considers appropriate, after taking into account (see section 63A(6)):
(a) all the effects associated with the reassessment; and
(b) the best international practices and standards for the safe management of
hazardous substances.
8 When making their decision, the Authority must follow the decision path outlined in
Appendix 1.
Notification and Consultation
9 The Minister for the Environment was advised of the application2 and given the
opportunity to ―call-in‖ the application3. This action was not initiated.
10 The Department of Labour (Workplace Group) was identified as having a specific
interest in the application and was provided with a copy of the application.
11 Other Government departments, Crown agencies and other interested parties, as listed in
Appendix 2, were provided with a copy of the application summary and given the
opportunity to comment or to make a submission.
12 The application was publicly notified on the ERMA New Zealand website on 8 October
2009 and subsequently advertised in The Dominion Post, the New Zealand Herald, the
Christchurch Press and the Otago Daily Times4.
2 section 53(4)(a)
3 section 68
4 section 53
Consideration Paper – HRE09001 Modified Reassessment of LPG, Propane and Butane Page 3 of 62
Submissions
13 Thirteen submissions were received. A summary of submissions is attached as
Appendix 3. The summary of submissions includes the applicant‘s response to the
submissions.
14 Three parties initially requested to be heard in support of their submissions, but all three
withdrew their requests after additional discussions with the Agency.
EVALUATION
15 To enable the Agency to consider all the effects associated with the proposed
reassessment, the Agency has undertaken an assessment of the risks, costs and benefits
associated with the proposed modifications to the approval of the substances. The
Agency has taken into consideration the information provided by the applicant in its
application, submissions received on the proposed amendments and the applicant‘s
responses to those submissions.
Increasing the Threshold for Location Test Certification
Applicant‘s Proposal
16 In the application document, the applicant proposed that the location certificate trigger
limit (threshold) be increased from 100 kg to 300 kg. The applicant provided a report
which it considers provides new information about the risks associated with the storage
of LPG and considers that this information supports an increase in the threshold for
location test certification requirements. The report concludes that the risks associated
with LPG cylinder operations in New Zealand are extremely low and in fact the largest
area of risk is the delivery of the cylinders rather than the location of the cylinders.
17 The applicant indicated that the risks of increasing the threshold are that those issues
covered by the location certificate will not be adhered to for installations between 100 kg
and 300 kg of LPG storage. The applicant identified that these requirements are that the
cylinders have to be 2 metres away from an area of high intensity land use (such as a
house/building) or have the walls of the building behind the cylinders and to 2 metres
either side of the cylinder be fire resistant or have a fire resistant covering and that there
is no opening into the building below the top of the cylinder and within 2 metres of any
cylinder.
18 The applicant proposed that these risks can be addressed via two proposals: 1) a multi-
cylinder code of practice for cylinder installations of more than 2 X 45kg cylinders, for
use by Gas Fitters and the LPG Industry and 2) a compliance/check sheet for
installations up to 300kg. The applicant has not indicated when these documents will be
available.
19 The applicant considers that increasing the threshold to 300 kg would result in savings
for over 3,700 consumers. At an annual cost for a location certificate of between $100
and $400 it will save consumers around $925,000 using an average cost of $250 per
certificate.
Consideration Paper – HRE09001 Modified Reassessment of LPG, Propane and Butane Page 4 of 62
Submitter Response
20 A number of submitters indicated that they had concerns about the level of compliance
of existing LPG storage sites and expressed concerns about the ability of the LPG
Industry to self regulate. The submitters indicated that they believed the removal of the
requirement for independent checks by Test Certifiers (carried out before the issuing of a
location test certificate) for facilities storing less than 300 kg of LPG would result an
increase in unsafe facilities and result in an increased risk to human health (including
that of firefighters who may need to visit these facilities) and to the environment.
21 The Department of Labour (DoL) indicated they did not support the proposal as written.
They suggested that as an alternative, the 100 kg threshold should be retained, but with a
test certificate renewal period for installations up to 300 kg of three to five years.
Applicants Response to Submitters
22 In response to the submissions, the applicant indicated a wish revise the proposal. The
revised proposal would retain an initial check by a test certifier for installations greater
than 100 kg, but subsequent independent test certification would only be required where
storage quantities were in excess of 300 kg. The applicant advised that it believes that
leaving compliance checking to the industry is a valid option because:
Industry are aware of all installations, rather than only those that have been
issued with a location test certificate;
It is in the interest of the industry to ensure ongoing safety of consumer
installations; and
Once the responsibility for checking compliance has been passed to the
industry this will remove the confusion of responsibility under the current
system where the industry has no legal, or agreed responsibility to ensure
compliance.
Agency‘s Evaluation
23 The Agency notes that the MWH report submitted by the applicant discusses the
international requirements for LPG storage in comparison with the current requirements
in New Zealand, but does not provide an analysis of the relative incident rates in the
different jurisdictions. The Agency considers that the provision of information that
indicated that jurisdictions with higher thresholds demonstrated a no greater rate of
incidents would have supported the applicant‘s proposal.
24 The Agency considers that the recently enacted Gas (Safety and Measurement)
Regulations 2010, which now require a Gas Fitter to have a gas installation approved up
to the cylinder valve outlet, will address a number of the non compliance issues raised by
the submitters. All gasfitting is required to be certified by a qualified and licensed
certifier. Certification is carried out by a craftsman gasfitter or a person holding a
certificate of exemption to certify particular gasfitting, as authorised by the Plumbers
Gasfitters and Drainlayers Board. This Board has a statutory function to ensure that all
certifiers maintain an adequate level of competence either as a craftsman gasfitter or
exemption holder.
Consideration Paper – HRE09001 Modified Reassessment of LPG, Propane and Butane Page 5 of 62
25 The Agency considers that any proposal to allow an element of industry self-regulation
must be balanced with increased accountability. An example of increasing the level of
accountability is the addition of a legal requirement which makes it an offence for a
supplier to deliver the substances to a non compliant site.
Agency Recommendation
26 The Agency recommends:
The location test certificate threshold for LPG, propane and butanes remain
at 100 kg;
For installations containing < 300 kg of the substances subsequent
compliance checking may be conducted as set out in an approved code of
practice or by a test certifier; and
The addition of a requirement that it is an offence to deliver LPG, propane
or butanes to a location that does not have a valid location test certificate.
Tank Wagon Parking Requirements
Applicant‘s Proposal
27 In the application document, the applicant proposed that the default requirement of spray
cages over all tank wagons carrying LPG which are parked for longer than 1 hour be
removed and replaced by a risk assessment using section 12 of AS/NZS 1596 for each
storage premises.
28 The applicant considers that the removal of the blanket requirements and replacement
with a risk assessment at each site would mean that spray cages would only be required
where the risks assessment indicated that this was necessary. Moving to a risk
assessment for all sites could result in potential savings on those sites that have no need
for a spray cage.
Submitter Response
29 Submitters indicated that they had concerns about the content of any risk assessment and
suggested a number of factors that should be considered, including adjoining land use.
The DoL indicated that they did not believe that the existing HSNO requirements were
onerous to comply with and questioned the suitability of the risk assessment processes in
AS/NZS 1596 as identified by the applicant.
Applicants Response to Submitters
30 The applicant‘s response to the submissions indicated that they would seek agreement
with ERMA New Zealand regarding the content of any risk assessment.
Agency‘s Evaluation
31 The Agency considers that providing alternatives to the default requirements for spray
cages is appropriate, as long as the alternative methods address and control the risks
associated with parked tank wagons that contain LPG, propane or butanes.
Consideration Paper – HRE09001 Modified Reassessment of LPG, Propane and Butane Page 6 of 62
Agency Recommendation
32 The Agency recommends that the variation to Regulation 42 of the Hazardous
Substances (Tank Wagons and Transportable Containers) Regulations 2004 as stated in
the Hazardous Substances (Dangerous Goods and Scheduled Toxic Substances) Transfer
Notice 2004 is not applied to the approvals for LPG, propane and butanes and that the
following variation be added:
“Regulation 42 of the Hazardous Substances (Tank Wagons and Transportable
Containers) Regulations 2004 applies to road tank wagons containing liquified
petroleum gas, propane or butane as if the following subclauses were inserted after
subclause (5):
(6) When a liquefied petroleum gas tank wagon with a capacity of 12,000 litres or
greater is parked for a period of time greater than one hour, fire fighting facilities
must be provided, such facilities must include a spray system capable of
delivering water to the exposed surfaces of the tank at a rate of 600 litres per
square metre per hour, and equipped with an automatic spray system that—
(a) detects fire; and
(b) starts delivering water to the tank; and
(c) can be manually controlled from a safe location,
provided that the tank wagon is parked whilst containing liquefied petroleum gas
in gaseous form only, a hydrant system equipped with a monitor or equivalent
means to direct water to all sides of the tank need only be provided.
(7) the Authority may vary the requirements of subclause (6)─
(a) by approving a code of practice under section 79 of the Act that specifies
requirements equivalent to those specified by subclause (6); or
(b) upon application by the person in charge of a location at which a tank
wagon containing liquefied petroleum gas is parked.
(8) when considering whether to grant an application made under (7)(b), the
Authority must have regard to─
(a) the separation distance between the tank wagon and an area of high
intensity land use or an area of low intensity land use (as the case may be);
and
(b) any hazards located within the site where the tank wagon is parked; and
(c) the exposure of the tank wagon to or from any other property; and
(d) the available water supply; and
(e) the likely response time and available resources of the local units of the
New Zealand Fire Service; and
(f) any other matter the Authority thinks fit.”
Consideration Paper – HRE09001 Modified Reassessment of LPG, Propane and Butane Page 7 of 62
Separation distances for cylinder and tank storage
Applicant‘s Proposal
33 In the application document, the applicant proposed that the separation distances for
cylinder and tank storage of LPG from AS/NZS 1596 replace those stated in the
Hazardous Substances (Dangerous Goods and Scheduled Toxic Substances) Transfer
Notice.
34 The applicant considers that AS/NZS 1596 represents international best practice and
therefore the adoption of the separation distances in this standard would result in no
increase in risk. As AS/NZ 1596 is already used by industry for many issues, the
applicant considers that changing to the separation distances in AS/NZS 1596 would add
simplicity to the regime.
Submitter Response
35 One submitter noted that AS/NZS 1596 is called up in some District Plans or conditions
of Resource Consents which causes conflict with the existing HSNO requirements.
Other submissions suggested that the impact of the change in the separation distances on
the other parts of the transfer notice must be considered before approving the adoption of
the separation distances in AS/NZS 1596.
Agency‘s Evaluation
36 The Agency has undertaken an analysis of the impact of adopting the separation
distances for cylinder and tank storage of LPG from AS/NZS 1596. This analysis can be
found in Appendix 4.
37 The Agency notes that the requirements specified in Table 4.1 of AS/NZS 1596 for
separation distances from cylinders appear to be stricter than those required by Table (2)
of clause 30 of Schedule 10 of the Hazardous Substances (Dangerous Goods and
Scheduled Toxic Substances) Transfer Notice 2004. Therefore, adoption of the values in
Table 4.1 of AS/NZS 1596 would mean that a number of existing installations would
become non-compliant and result in compliance costs. As the increased compliance cost
is not deemed to be balanced by a clear benefit, the Agency considers that Table 4.1
AS/NZS 1596 should not be adopted. Industry are, however, welcome to use the stricter
separation distances in Table 4.1 of AS/NZS 1596 should they wish to do so.
Agency Recommendation
38 Based on its analysis, the Agency recommends that the separation distances from tanks
identified in Table (3) of clause 30 of Schedule 10 of the Hazardous Substances
(Dangerous Goods and Scheduled Toxic Substances) Transfer Notice 2004 are not
applied to the approvals for LPG, propane and butanes. These values will be replaced
with the separation distances as specified in Table 6.1 of AS/NZS 1596. This
amendment does not include the adoption of the values for tanks with vapour draw-off,
as specified in Table 6.1 of AS/NZS 1596, as HSNO does not allow for this eventuality.
Consideration Paper – HRE09001 Modified Reassessment of LPG, Propane and Butane Page 8 of 62
Fire extinguisher requirements for domestic properties
Applicant‘s Proposal
39 In the application document, the applicant proposed that the requirement for a fire
extinguisher at locations where more than 50 kg of LPG should not be applied to
domestic properties, rather it should be limited to places of work. This was the case
prior to 2004 and the applicant believes that the original concept was adequate.
40 The applicant considers that there has been a large increase in domestic LPG facilities
over the last 10 years and that there is no evidence of incidents involving fire on or
around such installations and therefore there is no incident information to support the
requirement. Furthermore, should such an incident occur, householders are not trained
in the use of fire extinguishers on LPG fires and therefore any attempt by an untrained
householder to fight such a fire would result in an increased risk of harm to the
householder.
41 In addition, the applicant considers that the requirement is unenforceable as the vast
majority of domestic LPG installations have a capacity under the current 100 kg trigger
for a location test certificate and are therefore not checked for compliance with the fire
extinguisher requirement, the existence of which is completely unknown to the domestic
consumer. The domestic consumer may only be aware of their legal liability in the case
of something going wrong, when they may be faced with an insurance issue.
42 The applicant considers that limiting the requirement to workplaces would result in
significant cost savings for domestic consumers. The removal of this unnecessary
requirement would mean a reduction in the compliance costs associated with the use of
LPG.
Submitter Response
43 While the majority of submitters supported limiting the requirement to workplaces, the
New Zealand Fire Service submitted that it considered that fire extinguishers are useful
tools to control a fire and in their view they should be present. The Fire Service also
considers that the costs associated with the purchase of a fire extinguisher are not
significant. However, the Fire Service noted that fire extinguishers should only be used
to fight a fire in certain circumstances.
Agency‘s Evaluation
44 The Agency considers that the amendment to Regulation 21 of the Hazardous
Substances (Emergency Management) Regulations 2001 that was enacted in 2004 was
not intended to remove the limitation of the fire extinguisher requirements to places of
work. The Agency considers that this was an unintended consequence of the
amendment. Furthermore, the Agency considers that while the presence of a fire
extinguisher at locations were greater than 50 kg of LPG is advisable, making this a legal
requirement for domestic properties cannot be justified on a cost/benefit basis.
Agency Recommendation
45 The Agency recommends that the approvals for LPG, propane and butanes be amended
so that the requirements of Regulation 21 of the Hazardous Substances (Emergency
Management) Regulations 2001 are limited to a place of work where more than 50 kg of
the substances are present.
Consideration Paper – HRE09001 Modified Reassessment of LPG, Propane and Butane Page 9 of 62
Aggregation of Separation Distances for Vaporisers
Applicant‘s Proposal
46 In the application document, the applicant proposed that the requirement in clause 55(4)
of Schedule 8 of the Hazardous Substances (Dangerous Goods and Scheduled Toxic
Substances) Transfer Notice 2004, that separation distances for vaporisers be based on
the aggregate capacity of vaporisers, should be removed. The applicant advises that
AS/NZS 1596 states that aggregation is not required and each vaporiser has to comply
with the relevant separation distances based on their individual capacity.
47 The applicant indicated that there are a number of existing installations that do not
comply with the current HSNO requirement for aggregation. The applicant considers
that alignment with AS/NZS 1596 in this matter will avoid significant costs associated
with alterations to those installations, without any measurable decrease in safety.
Submitter Response
48 With the exception of the submission from the New Zealand Fire Service, the
submissions indicated support for the proposal. The New Zealand Fire Service
submission provided no specific reasons for their opposition to the proposal.
Agency‘s Evaluation
49 The Agency considers that separation distances based on the individual capacity of each
of the vaporisers are sufficient to manage the risks and that alignment with AS/NZS
1596 in this matter will result in reduced compliance costs for existing installations.
Agency Recommendation
50 The Agency recommends that the approvals for LPG, propane and butane be modified so
that clause 55(4) of Schedule 8 of the Hazardous Substances (Dangerous Goods and
Scheduled Toxic Substances) Transfer Notice 2004 does not apply to these substances.
Stationary Container System Certification Requirements
Applicant‘s Proposal
51 In the application document, the applicant proposed that the requirement for stationary
container system certification, as specified in Regulation 91 of Schedule 8 of the
Hazardous Substances (Dangerous Goods and Scheduled Toxic Substances) Transfer
Notice 2004, is not applied to LPG, propane and butane. The applicant proposed that
any requirements not already covered by the Pressure Equipment, Cranes and Passenger
Ropeways (PECPR) Regulations 1999 be transferred to the location certification
requirements.
52 The applicant considers that many of the requirements captured by stationary container
system certification are already adequately addressed by the PECPR Regulations and that
those requirements that are not captured, may be addressed by addition to the location
certification requirements.
53 The applicant considers that removing the stationary container system requirements for
the substances will not result in an increase in risk and will result in a reduction in
significant costs to industry.
Consideration Paper – HRE09001 Modified Reassessment of LPG, Propane and Butane Page 10 of 62
Submitter Response
54 The DoL submitted that since Test Certifiers who issue stationary container system
certificates can also issue location test certificates and that certification for a site may be
combined and efficiencies to be gained would be minimal. The DoL also suggested that
providing an exemption for LPG would be inconsistent with how other substances stored
in tanks were managed under Schedule 8 of the Hazardous Substances (Dangerous
Goods and Scheduled Toxic Substances) Transfer Notice 2004 and that this would create
additional complexities inside the HSNO control framework.
Agency‘s Evaluation
55 The Agency has undertaken an analysis of those requirements of the stationary container
system certification that have equivalent requirements under the PECPR Regulations and
identified those that do not. This analysis can be found in Appendix 5. Based on this
analysis, the requirements of stationary container system certification (as specified in
Regulation 92 of Schedule 8 of the Hazardous Substances (Dangerous Goods and
Scheduled Toxic Substances) Transfer Notice 2004) that will require transfer to the
location test certificate are as follows:
92(2)(b)(viii) the separation requirements specified in Part 5;
92(2)(b)(ix) fire fighting systems;
92(2)(b)(xi) plans specified in clause 81;
92(2)(e) if the stationary container system includes a vaporiser, the vaporiser
complies with clause 55; and
92(2)(j) records specified in clause 81.
56 The Agency considers that the removal of the requirement for a stationary container
system certificate for LPG, propane and butane will provide significant cost savings to
industry. Those provisions not already covered by the PECPR Regulations may be
transferred to the location test certification requirements without compromising the
safety of the installations.
Agency Recommendation
57 The Agency recommends that the approvals for LPG, propane and butane be amended to
remove the requirement for stationary container system certification and that those
requirements not covered by the PECPR Regulations be transferred to the location test
certification requirements for the substances.
Best international practices and standards for the safe management of hazardous
substances
58 Before the Authority can approve amendments to the approval of a substance, they must
take into account─
―The best international practices and standards for the safe management of the hazardous
substances.‖
Consideration Paper – HRE09001 Modified Reassessment of LPG, Propane and Butane Page 11 of 62
59 The grounds provided by the applicant included a review of international LPG controls,
notably:
(a) In the United Kingdom, storage locations and equipment must be installed by a
certified Gas Fitter. Appliances must be approved under the EU Gas Appliances
Directive. No licensing requirements were identified other than small retail and
commercial sites being subject to inspection by fire service officers. Facilities
greater than 25 tonnes are subject to the Control of Major Accident Hazards
(COMAH) regulations.
(b) In Australia, individual States provide their own legislation although substantively
based on AS/NZS 1596. In Queensland the legislation deals with the workplace
and not domestic installations. There is no obligation for the occupier to hold a
licence if the quantity is below the minor storage limit of 250 kg.
In New South Wales compliance with the legislation is required where there is 300
kg connected for use, and 150 kg when not in use. In Southern Australia and
Tasmania, a licence is required where the quantity exceeds 250 kg. In Victoria
holders of LPG in excess of 2,500 kg are required to notify the authorities.
(c) In the USA, LPG is managed under national fire legislation (NFPA 58) although
individual States may require notification, typically where the quantity exceeds
3,500 kgs. There is no requirement for licensing.
(d) The review included Japan and Singapore. The former has a high use of LPG.
LPG cylinders are not allowed indoors and most households have are fitted with
automatic monitoring systems. The latter seems to be based on the US system.
60 The proposed amendment to the location test certification requirements for the
substances will mean that the New Zealand requirements are not inconsistent with other
jurisdictions.
61 The applicant advises that no other jurisdiction requires a blanket requirement for spray
cages over parked tank wagons. All require a risk assessment approach. Therefore, the
proposed amendment will more closely align with international best practice.
62 The separation distance requirements in AS/NZS 1596 for cylinder and tank storage and
vaporisers are used throughout Australia and are based on international standards for the
management of LPG.
63 The applicant indicated that they were not aware of any other jurisdiction that regulates
fire extinguisher requirements for domestic installations. Therefore the removal of this
requirement would be in line with international best practice.
64 The stationary container system certification requirements that will be amended, so they
are either covered by the PECPR Regulations or transferred to the location test
certificate. This will maintain the existing standard.
65 The Agency considers that all the proposed amendments are consistent with best
international practice and standards for the safe management of hazardous substances.
Consideration Paper – HRE09001 Modified Reassessment of LPG, Propane and Butane Page 12 of 62
Transitional period for implementation of new controls
66 The Agency considers that it will not be practical for the proposed new controls to be
introduced immediately. Hence the Agency proposes a transitional period to avoid
unnecessary compliance costs.
67 The Agency proposes that a six month ‗transitional‘ period should apply before the
proposed control variations come into effect (this period commencing on the date of the
Authority‘s decision on any variations to the controls)
CONCLUSION
68 The Agency recommends the following regarding the approvals for LPG, propane and
butane:
1. Location test certification:
(a) The location test certificate threshold for LPG, propane and butane remain at
100 kg;
(b) For installations containing < 300 kg of the substances subsequent
compliance checking may be conducted as set out in an approved code of
practice or by a test certifier; and
(c) The addition of a requirement that it is an offence to deliver the substances
to a location that does not have a valid location test certificate.
2. Tank wagon requirements:
The variation to Regulation 42 of the Hazardous Substances (Tank Wagons and
Transportable Containers) Regulations 2004 as stated in the Hazardous Substances
(Dangerous Goods and Scheduled Toxic Substances) Transfer Notice 2004 is not
applied to the approvals for LPG, propane and butane and a revised requirement
which allows alternatives to spray cage requirements is added.
3. Separation distances for cylinder and tank storage:
The separation distances identified in Table (3) of clause 30 of Schedule 10 of the
Hazardous Substances (Dangerous Goods and Scheduled Toxic Substances)
Transfer Notice 2004 are not applied to the approvals for LPG, propane and
butane. These values are replaced with the separation distances as specified in
Table 6.1 of AS/NZS 1596. This amendment does not include the adoption of the
values for tanks with vapour draw-off as specified in Table 6.1.
4. Fire extinguisher requirements for domestic properties:
The approvals for LPG, propane and butane are amended so that the requirements
of Regulation 21 of the Hazardous Substances (Emergency Management)
Regulations 2001 are limited to a place of work where more than 50 kg of the
substances are present.
5. Separation distances for vaporisers:
The approvals for LPG, propane and butane are modified so that clause 55(4) of
Schedule 8 of the Hazardous Substances (Dangerous Goods and Scheduled Toxic
Substances) Transfer Notice 2004 does not apply to these substances.
Consideration Paper – HRE09001 Modified Reassessment of LPG, Propane and Butane Page 13 of 62
6. Stationary Container System Certification
The approvals for LPG, propane and butane are amended to remove the
requirement for stationary container system certification and those requirements
not covered by the PECPR Regulations are transferred to the location test
certification requirements for the substances.
69 The Agency recommends that a six month transition period be applied for
implementation of the changes to the approvals of the substances.
Consideration Paper – HRE09001 Modified Reassessment of LPG, Propane and Butane Page 14 of 62
APPENDIX 1 DECISION PATH
Consideration Paper – HRE09001 Modified Reassessment of LPG, Propane and Butane Page 15 of 62
APPENDIX 2 - Parties Notified A G (Andy) Miller & Co Limited
A to Z Diving
AA Solutions Limited
AberGas Ltd
Accreditation Limited
Adventure Dive (Rotorua) Limited
Adventure Dive Gisborne
Adventure Education Hawkes Bay (Dive Centre)
Adventure Watersports
A-Gas Australia P/L
Agribusiness Training Ltd
Agriculture New Zealand
Agriculture New Zealand, PPG Wrightsons Ltd
Air and Power Centre-1997 Limited t/a Air and Power Toolshed
Air Liquide New Zealand Limited
Air Matters Limited
Air Products and Chemicals Inc
Air Technology Limited
Airfabrico Ltd
Airflowe Ltd
Airtech International Inc
Allan Autogas Limited
Allgas Products
ANZIGA
AsureQuality Limited - Head Office
Australia New Zealand Industrial Gas Association
B and B Plumbing
B.O.C. Gases
Barrier Gas Limited
Bay Dive and Fishing Tackle
Benchmark Building Supplies
Blenheim Dive Centre
BOC Gases New Zealand Limited
BP Oil New Zealand Limited
Bunnings Limited T/A Benchmark Building Supplies
Can Train Limited
Canterbury Cylinder Testing
Capital Dive Services Ltd
Cascades Dive
Cathedral Cove Dive Ltd
Certified Limited
Chemsafety Limited
Christchurch City Council
Chubb NZ Limited
Coastal Cylinder Testing
Collievale Enterprises
Contract Air Ltd
Contract Environmental Limited
Cook 'N' With Gas
Cornerstone Industry Training Limited
Coromandel Fish & Dive
CSL Technical and Training Services
C-Test Limited/Imtest Laboratory Ltd
Cylinder Test Laboratory Gisborne
Consideration Paper – HRE09001 Modified Reassessment of LPG, Propane and Butane Page 16 of 62
Cylinder Testing Services
Dangerous Goods Compliance Ltd
Department of Conservation
Department of Labour
Dive and Ski HQ
Dive Centre Ltd
Dive Connection
Dive HQ
Dive Kaikoura
Dive Otago Limited
Dive Picton
Dive Supplies 2002 Limited
Dräger Safety Pacific Pty Ltd
Earth2Ocean
Eastern Bay Cylinders
Eastern Institute of Technology
Educhem Limited
Elgas Limited
Emery Holding 2002 Limited t/a Rockgas Greymouth
En Gaston
Envirocom (NZ) Limited
Enviroservices (2002) Limited
Evatech
Evonik Degussa Peroxide Ltd
Fire Corp Industries NZ Ltd
Fire Extinguishers Limited
Fire Protection Southland
Firewise
Firework Professionals Limited
Furmanite New Zealand Limited
G.B Invercargill LTD
Gage Services Limited
Gas & Petrochemical ITO
Gas & Pipeline Services
Gas & Tool Direct
Gas & Tyre Centre Limited T/A Greerton Service Station
Gas & Tyre Services
Gas Appliance Suppliers Association
Gas Association of New Zealand Incorporated
Gas Company Wanaka Ltd T/A Rockgas Wanaka
Gas Eketahuna Limited
Gas 'n' Gear
Gas New Brighton
Gas Pro
Gas, Fire & Cylinder Services
GasCo
Gasoline Alley Services Limited
Gasworkz Limited
GBI Gas Company Limited
Geils Gas Cylinder Test Station
Global Dive
Go Deep Scuba Ltd
Greater Wellington - The Regional Council
Grow and Spray Ways Limited
Grow Protech Limited
Hamilton Plumbing Co Ltd
Consideration Paper – HRE09001 Modified Reassessment of LPG, Propane and Butane Page 17 of 62
Hawkes Bay Gas Supply
Haz Subs Certifications Limited
Haz Subs Services Limited
Haz-Answers New Zealand Limited
Hazardous Substances Inspection Services
Hazbar Certification Ltd
HazEnviro Solutions Ltd
HazKnow Limited
HAZSUB Systems
Haz-Subs Solutions Limited
Hope International
Hulmegas
Independent Consultancy Services Limited
Inferno Consultants
International Accreditation New Zealand
John Bennett & Dale Garrick T/A Eastern Gas & Hire
JohnsonDiversey Australia Pty Ltd
JohnsonDiversey New Zealand Limited
Kajes Petroleum Waiheke Ltd T/A Rockgas Waiheke
Kelly Tarltons Underwater World
Kwikill Limited
Land Based Training
Liquigas Limited
LPG & Safety Consultants
LPG Association of NZ (Inc.)
Luxfer Gas Cylinders
M J Nankivell HazTec Ltd
Mander Plumbing Limited
Marlborough Cylinder Testing
Marua Road GAS
Massey University
Master Drive Services Ltd
Master Plumbers & Gasfitters ITO
Mico Plumbing & Pipelines
Mincorp Agencies (Tergo Industries)
Ministry of Economic Development – Energy Safety Division
Ministry for the Environment
Ministry of Health
Mitre 10 (NZ) Ltd
Mount Dive Shop
National Gas Limited
Natural Gas Corporation
Nelson Fire Protection Limited
New Plymouth Underwater Limited
New Zealand Army
New Zealand Defence Force
New Zealand Fire Service
New Zealand Gaskets Limited
New Zealand Police
New Zealand Retailers Association Inc.
New Zealand Underwater
NGC Kapuni Gas Treatment Plant
North Canterbury Gas Ltd
Nova Fire Safety Services Ltd
Nova Gas Limited T/A Hulmegas
NZ Sea Adventures Mana/Dive Spot
Consideration Paper – HRE09001 Modified Reassessment of LPG, Propane and Butane Page 18 of 62
OH & S Services Limited
On Gas Limited
Orakei Dive Shop
Peak Risk Management Limited
Peebles Owen Westburn Limited T/A BP Gas City
Peggemma Properties
PK Gas Services
Placemakers
Plant and Platform Consultants Ltd
Plumbing World
Porirua Cylinder Testing Laboratory
Port Fitzroy Dive Station
Pro Cylinder Testing Ltd
Prowin Company Limited t/a Gas Mt Roskill
QEC Quality Environmental Consulting Ltd
Quality and Safety Management Limited
R.K. Service Station Limited T/A Gas Swanson
Ray lambert Plumbing Ltd
Richmond Sports Power
Rockgas
Ron Richdale Fire Equipment Services Limited
Royal New Zealand Airforce
RSM Consultants
Safety Solutions Ltd
Snells Beach Dive and Fish
Southern Aqua Adventures
Southern Gas Services Limited
Southern Monitoring Services Limited
Southland District Council
Splash Gordon Limited
Sportsworld Whakatane Ltd
Stirlings Dive Shack
T and L Testers
Tairua Dive and Fishinn
Tank Inspection and Certification Limited
Tank Test Laboratories Limited
Taranaki Regional Council
Tauranga Cylinder Testing
Technical Strategy Group Limited
The Australian Gas Association
The Dive Connection (2003) Limited
The Dive Doctor
The Dive Inn
The Gasman NZ Limited
Timaru Plumbing and Gas Centre
TMR Limited
Total Automation Ltd
Twizel Plumbing Supplies
Underwater Sports
Underwater World/ Performance Diver NZ Ltd
Vector - Wellington Office
Vector Gas
VT Fitzroy Limited
Wanganui Gas
Watco Plumbing Limited
Westland Diver Services
Consideration Paper – HRE09001 Modified Reassessment of LPG, Propane and Butane Page 19 of 62
Whangamata Plumbing & Drainage
Whitianga Sports Centre Ltd
Wilson & Choat Plumbing Limited
Work Injury Care Limited
Wormald
Wormald Cylinder Test Station
Worthington Cylinders GmbH
Zip Plumbing Supplies
Consideration Paper – HRE09001 Modified Reassessment of LPG, Propane and Butane Page 20 of 62
APPENDIX 3
Summary of Submissions
Modified Reassessment of LPG, Propane and Butane (Application Number HRE09001)
Index of Submitters
Submission # Submitter Organisation Requesting to be
heard
1 Debbie Fielder Institute of Refrigeration, Heating and Air Conditioning
Engineers of New Zealand (IRHACE)
No
2 Harry Flannigan Test Certifier No
3 Jack Travis Tauranga City Council No
4 Dick Thornton-Grimes New Zealand Fire Service No
5 Kevin Bailey LPG & Safety Consultants Ltd No
6 Gayle Smith BOC Ltd No
7 Jim Mackness Test Certifier No
8 Michael Farrier ─ No
9 Rex Alexander Envirocom (NZ) Ltd Yes
10 Rob Milner Roma 25 Ltd No
11 Kim Comben Department of Labour No
12 Kevin Daly Contact Energy Ltd Yes
13 Peter Hallett New Zealand Professional Firefighters Union (NZPFU) Yes
Consideration Paper – HRE09001 Modified Reassessment of LPG, Propane and Butane Page 21 of 62
Submissions
Submitter Support/
Opposed
Submission LPGA Response
Location Test Certification Threshold
IRHACE Support No specific comment
Harry
Flannigan
Opposed I think the LPGA request to exclude up to 300 kgs of LPG from controls is
ridiculous, considering the recent fires and explosion fatalities with this
product. There would not have been more than this amount involved in the
cool store explosion considering the ratio of 270/1 and vol/air ration of
28/30 to 1. If anything I would recommend the controls be stricter and
require controls at 45 kgs.
The only recent significant fire and explosion relating to
LPG was the Hamilton cool store fire, which did not
involve the storage of LPG, but the use of LPG in a
system, which is completely outside the matters
considered for this application.
Tauranga
City Council
Opposed I think that the trigger for a Location cert should remain at 100 kg.
New
Zealand Fire
Service
Opposed The document advises on page 29 that the data records (2001 - 2003)
appear to be comprehensive and the accuracy of incident rates is relatively
good. We content the data is inaccurate and for a third of data period used
owing to industrial action by fire fighters throughout 2001.
We note the UK HSE's publication "Reducing Risks, Protecting People"
advises on the risk values in the document "We must also stress that these
criteria are merely guidelines to be interpreted with commonsense and are
not intended to be rigid benchmarks to be complied with". The risk
frequencies used from this document are for workplaces that impact
society, not for societal risk per se, i.e. a residential rate in isolation.
LPG hazards indicate cylinders don't normally BLEVE. This is incorrect;
our experience is that cylinders do BLEVE. Fire fighters do report such
instances but this may not form part of a fire report for cause and origin
We do not believe industrial action by the Fire Service
in 2001 would have reduced information of 45kg LPG
cylinder incidents. Either the Industry would have
known or OSH would have been informed.
There is no single universally accepted definition of
societal risk. The planning method alluded to by
submitters is design for use in assessing safety risk at
major hazardous installation affecting the adjacent
populations. This method is not appropriate for
assessing risks at numerous sites involving relatively
small quantities of LPG.
The MWH report is very clear on how risks were
calculated in the report.
Consideration Paper – HRE09001 Modified Reassessment of LPG, Propane and Butane Page 22 of 62
purposes when conducting a fire investigation.
In the main LPGA application para (d) makes the implicit connection
between a control being unenforceable and thus a contributory factor for
the removal of that control in this case a fire extinguisher at a residential
address. This stance undermines the argument put forward to removing test
certification and increasing training competent person who effectively
becomes the only oversight upon installation. If a safety control that by
implication is not enforced becomes even more unenforceable how does
this provide greater safety?
The hazard exposure and risk assessment of what is at risk completely
omits emergency responders. This is essential against an already low level
of test certification compliance. No thought is given on what further
deregulation and oversight may mean for to the very people who will have
to end up tackling the problem we see the LPGA submission creating.
There is no information in the document on what the effect is of putting
larger stores of LPG as NZ moves towards a medium and high density
housing context. Such storage can take place now but frequently a home
will have 90kg. With the LPGA encouraging the move to ever higher
quantities (up to 300kg) of LPG a risk and cost benefit should be included.
In this way the risk assessment is neither systematic nor complete as per
ERMA publication ER-TG-05-02 03/09.
Appendix 1 is out of date and out of step with international thinking in a
number of areas, for example "LPG compared to reticulated natural gas...
the intrinsic hazard....is more flammable and explosive than LPG". The
more recent ICL report finds "Because of its greater density and its
flammability in air at lower concentrations, LPG presents a greater hazard
than natural gas."
The document ―Reducing Risks, Protecting People‖
gives some UK examples of risks expressed with respect
to the entire (UK) population, see Table 2 on page 78,
which includes ―Gas incident (fire, explosion or carbon
monoxide poisoning)‖ quoted as having a risk of 1
(death) in 1,350,000 people. Note this risk is not limited
to small installations of LPG only, so cannot be directly
compared to the figures quoted in the MWH report for
New Zealand, but illustrates the presentation of risk to
society as whole in the form of odds, which can be
translated directly into an annual average risk figure
(Response from MWH).
We have no information regarding bleves of LPG
cylinders. We do not believe either DOL or ERMA have
this information either, so must question this statement.
Our argument is not only that the current requirements
are poorly complied with, but that this level of non
compliance has clearly not resulted in incidents.
Therefore a no cost system implemented by the Industry
to replace an expensive system which is not being
complied with will not reduce safety. Also having the
Industry take responsibility for this checking would
provide complete coverage of all sites rather than just
those which have applied for a location certificate and
therefore increase safety for these currently non
certified sites.
After speaking to the Fire Service I believe their real
concern is one of having knowledge of whether there are
hazardous substances used on a site that they have been
Consideration Paper – HRE09001 Modified Reassessment of LPG, Propane and Butane Page 23 of 62
In effect the LPGA is requesting deregulation of the LPG installations with
a trust us approach and the use of competent persons. The Fire Service
accepts the ICL inquiry is for a larger fixed installation but unequivocal
about the need for oversight "A verification scheme would, I think, have
averted this disaster". NZ already has just such a scheme it is called a test
certificate.
Since 2006 the Hazardous Substance Advisor (HSA) for the Auckland Fire
Region has been conducting inspections of hazardous substance locations
under Section 29 of the Fire Service Act 1995. In this time there have been
505 documented inspections. The 2nd most frequent reason for
recommending a test certificate is because a location has over the trigger
threshold for LPG. ERMANZ itself has previously acknowledged the low
level of test certification compliance (30 - 40%) against what was predicted
out of the transition from the old Dangerous Goods regime to HSNO. The
LPGA does not address how deregulation against an already low base of
compliance will lead to increased compliance. The Fire Service is
concerned that the removal of independent verification for the storage of
significant quantities of LPG where the market becomes the sole regulator
(unless an incident occurs in which it is too late) and can only lead to a
"race for the bottom" in which the lowest common denominator prevails.
called to. Whether the installation is certified or not, the
Fire service will not have this information. This could
be covered by the Industry providing the Fire Service
with this information.
Also there will not be an automatic move to more
cylinders on sites, as cylinders cost money both for the
Industry and the customer. An increase to storage will
only occur if needed.
This is a reference to an incident involving degraded
LPG piping running through a factory and has no
relevance to the storage of LPG in 45kg cylinders other
than the heavier than air nature of LPG.
Again the inquiry relates to LPG in piping and as we
understand it is the UKLPGA which is undertaking a
survey of LPG Installations, not the HSE. The storage of
LPG cylinders in the UK does not require certification
by a Test certifier and still does not following this
inquiry.
This illustrates that customers are not complying with
the requirements of HSNO compared to the old DG
license requirements which we believe is a result of the
increased cost of a location certificate which is required
every 12 months.
We believe our proposal for the Industry to run the
compliance checking in future is an entirely valid
option. Firstly the Industry knows about all installations
rather than just what has been issued with a location
certificate, secondly it is in the interests of the Industry
to ensure the ongoing safety of consumer installations
Consideration Paper – HRE09001 Modified Reassessment of LPG, Propane and Butane Page 24 of 62
and thirdly once the responsibility for checking
compliance has been passed to the Industry this removes
the confusion of responsibility under the current system
where the Industry has no legal, or agreed responsibility
to ensure compliance.
The Industry has made attempts to check whether
installations they supply have location certificates , but
ERMA were unable to supply this information to the
Industry because of privacy issues.
LPG &
Safety
Consultants
Ltd
Opposed The LPG industry has a long history of using 45 kg cylinders for fuel
supply to a wide range of users. Twin packs (2 x 45 kg) have been very
common and rely on the gas fitter to ensure compliance with NZS 5261 Gas
Installations. We are still finding installations today that do not comply
with this standard. As recently as 13 November 2009 we were requested to
carry out an inspection of a large country resort in Martinborough. There
are 16 twin pack installations on site and 9 of those installations were built
on top of drains and all installations have been signed off by the gas fitter
as being correct. Even though the site has 1,440 kg of LPG present they are
all twin pack installations on separate buildings and therefore the site does
not require a location test certificate. We have been to a similar site in
Franz Joseph where the gas supplier and gas fitter have established 20
separate and independent twin pack installations on the site just so they
would not have to take out a location test certificate. If the gas suppliers
and gas fitters are able to do this with twin pack installations they will find
a way to install multiple 300 kg installations and no one will know they
exist.
We have a rest home client in Auckland with 23 LPG installations on site
ranging from 3 to 6 cylinders at each location. The gas supplier had given a
draft copy of the proposed LPGA checklist to the cylinder delivery driver
so they could inspect all of the installations. Each installation was signed
off as being correct and fully compliant with the requirements of the
Hazardous Substances Transfer Notice 2004. They even placed little
Using multiple twin pack installations is acceptable
under the ERMA guidelines for commercial premises.
Each twin pack is isolated from the others and
consequently can be treated as separate installations.
The suggestion that these multiple twin packs will
suddenly all become multiple 300kg, is not logical
because of the increased costs for the supplier and
customer. If any change resulted it is more likely to be
an amalgamation of the existing twin packs. Also this
could easily be remedied by an ERMA guideline
limiting the total amount of LPG on a site before a
location certificate is required.
We very much doubt/dispute the proposition that the 20
twin pack installations were decided on just to avoid a
the need for a location certificate. It is far more likely
that the individual cabins on the site are more cost
effectively served by having 20 cylinder locations rather
than one large one and then being faced with
reticulating the LPG. Again cylinders will not
proliferate for no logical reason
The check sheet is still being developed and driver
training has not commenced on the new system, so
Consideration Paper – HRE09001 Modified Reassessment of LPG, Propane and Butane Page 25 of 62
stickers on each installation saying it had been audited and was fully
compliant. When we inspected the site to issue a location test certificate,
16 of the installations did not comply, the installations were within 2
metres of doorway openings into the various buildings, some were on top of
drains, some in front of windows, there was no fire resistant material
behind and 2 metres either side of the cylinders and there were electrical
fittings within the hazardous area zones.
The level of compliance varies between the LPG suppliers: some are
proactive and will not deliver any cylinders without the customers holding
a location test certificate. At the other extreme is a gas supplier that does
not care about compliance, they are only interested in the cylinder rental
fees. They do not actively tell the customer to obtain a location test
certificate and leave it up to a test certifier to try and find the installation. I
am currently training a new test certifier in Auckland and even he has given
up trying to get compliance on this suppliers sites, so far we have had 100%
non compliance on their sites, the majority of these are between 4-6
cylinders, the ones that will fall outside the requirements if the threshold is
raised. This gas supplier frequently delivers the cylinder to the customer‘s
front gate and tells them to connect up the cylinders without giving them
any guidance. At periods when they have staff away they will double up
the cylinders at each location and tell the customer to connect the cylinders
themselves. This occurs at Christmas time, we found one of our customers
having 40 cylinders on site in addition to the 20 on the location test
certificate all because the gas supplier did not want to make deliveries over
the Christmas period. Another gas supplier boasts that they estimate at
least 90% of their sites are non compliant and very few have location test
certificates, they do not tell their customers to get the certificates.
I do not think that the drivers will report any non compliant installations.
The majority of cylinder delivery drivers are self employed contractors who
must deliver a certain quantity of cylinders each day or be penalized. After
speaking to a number of drivers, both company and self employed, they say
they will not have time to fill out check sheets and when they have reported
judging the proposal on this one early attempt is unfair.
The majority of drivers are employed by the LPG
suppliers, for those that are contracted this requirement
will be added to the contract requirements.
Consideration Paper – HRE09001 Modified Reassessment of LPG, Propane and Butane Page 26 of 62
substandard installations in the past nothing gets done to fix them.
The LPGA has proposed the training of gas fitters to do the inspection
work, most of the gas fitters are on loyalty payments to gas suppliers, so
there is no way they will report substandard work to the gas supplier that
pays them.
On Monday this week (16 November) we had a site referred to use by an
opposition gas supplier, the site had 4 x 45 kg cylinders in a cage against a
car wash lean-to. The cylinders were used to decant fill smaller cylinders
for camper vans. On investigation the installation did not meet the cylinder
filling station requirements, there were no scales on site to weigh the
cylinders, the staff did not have any training, there were no approved fillers,
no approved handler and the gas supplier was annoyed we had found the
site and now has a lot of remedial work to do.
Some of our customers do not want to see the threshold increased, they do
not place any reliance on the gas supplier to check the installation, and are
more than happy with an independent third party inspection such as that
undertaken by a test certifier. Problems have arisen were test certifiers
have given very poor and very expensive service which has put a lot of
people off obtaining a location test certificate. An example is a school in
Auckland we have recently certified. There are 10 x 45 kg cylinders on
site; our quote for the work was $281.25; Auckland certifier‘s charges were
$750.00 (mileage extra), $1,000 and $1,200.
I do not believe the LPG threshold should be raised to 300 kg. The LPG
industry has demonstrated by its own actions it is not ready to put any
credible inspection or auditing system in place. There are still a large
number of installations that are non compliant, one company estimates this
to be as high as 30,000 sites, and the gas suppliers do not care, they see
compliance with HSNO as a hindrance to their business. If the threshold is
raised to 300 kg there should still be some form of third party inspection to
ensure there is full compliance with the HSNO requirements. They are not
We do not agree with the logic of this argument. The
gasfitter is a qualified competent person. If properly
informed of HSNO requirements they will follow agreed
procedures. We have been in contact with the Master
Plumbers Gasfitters and Drainlayers NZ and they have
agreed to make their members aware of the LPGA multi
cylinder code of practice and will include it in their
upskilling courses. We will also be talking to the ITO to
include it in the core gasfitter training.
Our proposal to increase the location certificate
quantity does not include filling sites.
Agree high fees are putting customers off obtaining a
location test certificate. Our proposal will mean that at
least the below 300kg installations will be at least
checked for compliance by the Industry.
The Industry does care and systems to check customer
compliance have been tried. The advantage of an
Association agreement is that all the suppliers will be
agreeing to carry out the same checking process which
means it is far more likely to be followed through.
At the meeting we have all the industry represented and
we disagree with this estimate.
Consideration Paper – HRE09001 Modified Reassessment of LPG, Propane and Butane Page 27 of 62
that difficult to comply with. Over the past 5 years at items we have found
it frustrating dealing with this industry and may times have seriously
looked at giving up due to the lack of co-operation from the gas suppliers to
ensure installations are compliant and certified. If the threshold is raised
this situation will only get worse due to the current large number of non-
compliant installations.
I am prepared to give photographic evidence of these sites should you
require this.
BOC Ltd Support No specific comment
Jim
Mackness
Opposed My issue is with Item 1 - "To increase location test threshold from 100kg to
300kg".
I refer first to the Building Industry and leaky homes where pressure on the
Building Industry in the past I suggest resulted in a reduction of basic
standards and rules which ultimately lead to many "leaky building"
problems. The costs and heart ache involved in this must be considerable.
I also refer to the recent "Hamilton Icepack" incident and loss of life. This
horrendous accident I understand involved only 400kg of LPG with such
devastating effect.
There is no doubt that LPG as well as being a commonly used substance, is
also a highly hazardous substance having the potential to be extremely
dangerous even in small quantities.
Test Certifiers are currently employed by Owners / Companies who have
quantities of on-site LPG in excess of the threshold level of 100kg. They
advise on the safe storage, use, and general requirements of the Hazardous
Substance and New Organism Act and Regulations (HSNO). When
satisfied with compliance the Test Certifier issues a "Site Certificate".
This is not relevant to this discussion as it did not
involve any LPG storage systems or certification of such
systems. It involved the use of LPG in an installation
and would not have been certified under the current
regime. It would also not be included in our proposed
increase to the trigger limit.
This will all be covered by the Gasfitter and the LPG
Supplier.
Consideration Paper – HRE09001 Modified Reassessment of LPG, Propane and Butane Page 28 of 62
Reasons for opposing change to the threshold level:
1. Raising the level to 300kg of LPG would mean a site with less than that
quantity would not require the services and expertise of a Test Certifier
or require a Site Certificate.
2. A site of only LPG below the proposed threshold level of 300kg (i.e. no
other hazardous substances on-site), would never receive Test Certifier
safety checks or advice.
This I suggest must put staff and public safety at risk. Persons on-site
safety is of paramount importance.
3. Raising the threshold level must be a lowering of standards in a similar
manner to that of the Building Industry and "leaky buildings". Not a road I
suggest ERMA should consider going down.
4. 100kg of LPG has been the trigger level for years in both current and
past legislation. This has worked well, is recognized throughout the
country, and is to my knowledge a level that is satisfactory to industry.
Recommendations
1. That the LPG threshold level of 100kg remain as is:
2. That "Test Certifier's" qualified by ERMA for Class 2 products be
the only persons able to issue "Site Certificates" for LPG.
Michael
Farrier
Opposed Insufficient information has been provided to justify the proposed increase
of the test certification thresholds. Current storage and use practices have
not been considered and the current level of governance of users by the
suppliers has not been evaluated. Any review of threshold requirements
should be based on a review of current New Zealand practice rather than a
review of incidents involving LPG. If international practices and
regulations are to be considered as justification, the current outcomes of
their application of them and the associated enforcement also needs to be
reviewed.
From information received in other submissions it is
clear that the current system is not working. The
industry is offering to check on all installations whether
certified or not.
Consideration Paper – HRE09001 Modified Reassessment of LPG, Propane and Butane Page 29 of 62
No data has been provided to indicate the current situation in New Zealand
regarding use and storage.
Based on my experience of current LPG cylinder storage practices on
operating sites, practices are generally poor on sites with little appreciation
of the properties of LPG and no guidance has been provided to the
customer by the supplier. Until all LPG suppliers make an effort to ensure
that clients are complying with current HSNO requirements for LPG no
change should be made.
The LPG Association MWH report is based on a limited period of incident
data up until December 2005. There has been at least one significant
explosion incident involving a small quantity of LPG since 2005. It is also
unfortunate that no reference has been made to the original hazard
assessment work conducted in New Zealand by the Liquid Fuels Trust
Board. This was subject to a number of peer reviews and public
consultation. One report No. LF 5006 Liquids Fuels Trust Board Project
650/02/1 ―Risk Assessment of Future LPG Facilities in New Zealand, Sept
1984, provides a sound background on which to consider present day risks.
I would also like to refer ERMA a paper that reviewed domestic explosions
from small LPG containers in the United Kingdom (Domestic Explosion
Hazards from Small LPG Containers, S Ames and D Crowhurst, J. of
Hazardous Materials 19 1988) that is worthy of consideration in regard
general domestic use of LPG and also aerosol cans. I have not referred to
the Wakelin report (2004) – it may have been considered in that report.
In respect to reference in the paper to Societal Risk, I believe that this has
been used out of context of its normal use. The term ―Societal Risk‖ has
been developed as a land use planning tool and the assessment of the risk to
the surrounding population from a single event (accident). In my opinion
the assessment of societal risk based on a number of events over time is not
appropriate. It would be more appropriate in my opinion to refer to it as the
annual risk of death of risk of death in New Zealand population from LPG
use.
Not sure what is being asked for here.
Suppliers provide MSD‘s to their customers and will
explain any issues if asked.
Cool store incident not relevant.
The LFTB covered the major LPG storage facilities in
NZ such as the Liquigas Depots and not relevant to 45kg
installations.
There is no single universally accepted definition of
societal risk. The planning method alluded to by
submitters is design for use in assessing safety risk at
major hazardous installation affecting the adjacent
populations. This method is not appropriate for
assessing risks at numerous sites involving relatively
small quantities of LPG.
Consideration Paper – HRE09001 Modified Reassessment of LPG, Propane and Butane Page 30 of 62
Before a decision is made to increase the threshold of LPG the gas industry
needs to demonstrate that they can support LPG users in ensuring that LPG
cylinders are stored and used in an appropriate manner. In my visits to well
over 50 sites in recent times I have seen few examples that this is occurring.
Just to use one specific issue as an example, the storage of LPG cylinders is
often in a location that drains to an adjacent storm water drain.
The MWH report is very clear on how risks were
calculated in the report.
The document ―Reducing Risks, Protecting People‖
gives some UK examples of risks expressed with respect
to the entire (UK) population, see Table 2 on page 78,
which includes ―Gas incident (fire, explosion or carbon
monoxide poisoning)‖ quoted as having a risk of 1
(death) in 1,350,000 people. Note this risk is not limited
to small installations of LPG only, so cannot be directly
compared to the figures quoted in the MWH report for
New Zealand, but illustrates the presentation of risk to
society as whole in the form of odds, which can be
translated directly into an annual average risk figure
(Response from MWH).
This is because there is currently no legal requirement
on the LPG supplier and no Industry agreed process. .
Envirocom
(NZ) Ltd
Opposed We are strongly opposed to any increase in test certification limits until:
The level of compliance with the HSNO controls on LPG cylinder
installations in excess of 100 kg improves dramatically – non
compliance on first inspection has remained about 30% nationally;
and
NZS 5261 is re-written to reference the Controls in Gazette Notice
Number 25; it currently applies to and gives examples of two
cylinder installations (90 kg) only; and
Gas Fitters receive sufficient training in the Controls for
installations over 100 kg; we continually find 1 meter separations
to building operations ― because it is in NZS 5261‖; and
There is a greater level of self compliance in the industry; and
Poor compliance because of cost of certificates.
The Industry through the LPGA is producing multi
cylinder COP to cover this issues.
Multi cylinder COP will cover this.
Consideration Paper – HRE09001 Modified Reassessment of LPG, Propane and Butane Page 31 of 62
That the increased level of compliance is reflected in dramatic
reductions in callouts for the NZ Fire Service. LPG is still by far
the single most responded to hazardous substance facility incident
category.
The LPGA has in addition to submitting to ERMA to raise the Test
Certification trigger limit to 300 kg, also circularized every Territorial
Local Authority in the country requesting a similar increase for District
Plan Resource Consent triggers. In other words they would intend there be
no control at all for LPG cylinder locations below 300 kg other than an
acceptance of Standards, and the knowledge (or lack of) of gas fitters. As
we indicated in our submission that knowledge is dangerously substandard
for anything over 100kg and often also for 2 x 45 kg installations for which
there is no excuse, the information being extensively detailed in the gas
fitters‘ own Standard NZS5261. We believe this action by the LPGA
compounds the problem of achieving compliance with HSNO and adds
further weight to the importance of our submission.
These are related to 9kg cylinders with very few 45kg
related incidents.
Correct LA‘s should not be getting involved in HSNO
issue for such small quantities .This is not relevant to
increasing the HSNO trigger limit.
Roma 25 Ltd Opposed It is my opinion that the submission by the applicant LPGA would not
provide a continuance of basic safety standards which over the years has
proved to be successful.
As a HSNO advisor working with a ERMA appointed Test Certifier, and
we are an active company involved in daily audit processes of LPG
installations, I have concern that any eroding of proven safety standards and
processes will not provide the continuance of compliant/safe/acceptable
installations for residential –commercial – industrial clients.
I can say this as I have over 38 active years workforce experience within
this LPG industry and other HSNO workplaces and would have concern if
the existing legislation was to be altered to appease the LPG Association
and their members.
I do not support the application by LPGA or their submission for change to
the HSNO legislation currently in place
The proposal is not asking for a reduction in safety
standards rather the Industry is asking for reduction in
compliance cost which is itself a barrier to compliance.
The industry will then provide compliance checking for
its customers at no cost.
Consideration Paper – HRE09001 Modified Reassessment of LPG, Propane and Butane Page 32 of 62
Please refer to the information relating to the failure of the Aquaknect
flexible connections and the non disclosure of these matters by the LPGA
and industry to the ERMA and appointed Test certifiers/advisors of this
faulty equipment.
This example is an indication of what will occur when there is no checking
authority or on site audit of LPG installations.
Also refer to email discussions between myself –Mr Tony Smith Senior
Tech officer-Min of EE and Mr Travis Team Leader HSNO E Officer.
It is imperative that a robust on site audit process be maintained for LPG
installations >100kg and in this respect the ERMA must not allow any
reduction of the safety standards which are currently in place to occur.
Refer to photos for examples of serious non compliance.
We liaised with Energy Safety on the recall and liaised
with ERMA. The Industry contacted all potentially
affected customers to ensure all were informed and a
0800 number was arranged to organize replacement.
This is irrelevant to our proposal.
Department
of Labour
Opposed It is somewhat disconcerting to see the MWH report attached the
application being somewhat dated, furthermore some of the accident data
was based on the period between 2001 – 2003 with no real explanation as
to why this particular period was chosen given that report was drafted in
late 2005/early 2006. It is considered that the findings and
recommendations do not really provide an up to date snapshot of the
industry. Currently the LPG industry in New Zealand has and is undergoing
large changes since the MWH report was written. There have been two new
recent entrants into the New Zealand market one of which specialises in the
insitu filling of LPG cylinders utilising LPG Bobtail tankers, cylinder
exchange and the other which is focusing a cylinder swap scheme for 9 kg
cylinders. Whilst there has been insitu filling of cylinders in New Zealand
previously there now appears to be a more vigorous approach being taken
in respect of this system of supply.
It is noted from the MWH report that the incident rate in respect of the
storage in LPG cylinders connected to supply systems is very low, (part of
which they attribute to the robust approval processes for cylinders and
The original report was prepared in 2007 and access to
meaningful safety data was not available past 2005.
However the report fundamentals would not have
changed as incidents involving 45kg cylinders have
remained extremely low.
You rightly point out that we restricted evaluation
to periods over which adequate data reporting was
available. However, contrary to your response, our
original study was commissioned in 2005 and
reported in Feb 2006, which further explains why
there is no more recent data used in our study.
(response from MWH)
Drivers filling insitu cylinders are trained fillers and
Consideration Paper – HRE09001 Modified Reassessment of LPG, Propane and Butane Page 33 of 62
valves) however, it was pointed out that that there have been leaks at
cylinder storage sites which have been attributable to failing flexible
connections between the cylinder and the changeover valve/regulator. One
of the critical aspects in managing such events at the storage location is to
ensure that the cylinders are appropriately located in the first instance thus
minimising the potential for a greater consequence event to occur. With the
rising probability that a greater number of locations will be filled ―in situ ―
and there will be a vapour discharging as result there is a greater incentive
to ensure that the supply containers in the system are in fact appropriately
located especially as the storage quantities increase.
What is predictable if the trigger quantity that requires a hazardous
substance location is increased is that there will be a corresponding
increase in the storage of cylinders at locations from two to in all likelihood
six or larger capacity cylinders will be introduced that will ultimately
replace the existing 45kg fleet over time. The increase in cylinders or the
introduction of greater capacity cylinders may provide for a greater source
of potential leakage points and a greater volume of gas that can be
discharged at the storage point if a leak should occur.
From discussing this proposal with Test Certifiers there is concern in that
for installations over 100kg that do currently require a Location Test
Certificate there have been a number of installations that did not comply
with the HSNO requirements in respect of their location. It has to be noted
that the HSNO Gazette Notice No 35 requirements are more generous in
respect of location distances than what the previous Dangerous Goods
(Class 2- Gases) Regulations permitted. Whilst the LPA Association
proposal is to ensure that installers and suppliers will be provided with
Codes of Practice and a Checklist to ensure the installations are compliant
(industry self regulation) it will remove the independent third party
checking that occurs at present with appropriately ERMA accredited Test
Certifiers.
A direct shift of the trigger quantity to 300 kg will ultimately mean a large
approved handlers and are therefore better qualified to
check compliance for these installations than normal
cylinder delivery drivers.
It will be arguably safer to have a single 250kg cylinder
than 6 x 45kg cylinders as there is only a single
connection and valve. These are very common in
Australia and have proved as safe if not safer than 45kg
cylinders.
There will be no wholesale move to more cylinders as
discussed earlier and will depend on operational
requirements
Consideration Paper – HRE09001 Modified Reassessment of LPG, Propane and Butane Page 34 of 62
number of installations will not be given an independent check prior to
their commissioning. It is considered critical that the installation be located
correctly in the first instance.
Comparisons have been made in the MHW report with the controls
required in other countries namely Australia, Japan, Singapore, United
Kingdom and the USA. Whilst it is considered making comparisons with
other nations on occasion can be helpful; it may also be detrimental if the
environment/systems are different to New Zealand conditions. Taking the
United Kingdom as an example there does not appear to be a large LPG
45kg cylinder market for static supply cylinders as they have a developed
supply infrastructure with natural gas reticulation and hence the reason for
the lack of controls regarding licensing therefore is it considered
inappropriate to make such a comparison.
The country New Zealand would align to most in respect of the storage and
distribution of LPG would be Australia. The MWH report infers that there
is no checking/licensing of LPG cylinders below 250 kg in New South
Wales, South Australia and Tasmania. It should be noted that at least in
New South Wales, fixed installations do have compliance plates attached
which would indicate that that some form of checking has occurred on the
installation incidentally this also applies to installations of less than 100 kg.
It is accepted that the usage rate of LPG in gas burning systems has
increased in recent times particularly with the introduction of continuous
flow hot water systems, raising the trigger quantities before a Location
Certificate is required does not alter the hazards associated with the use of
LPG in such circumstances. The industry does make the point that there
will be a resulting saving in compliance costs by increasing the trigger
level, however this must offset as to what is happening in the currently
evolving market in New Zealand.
The proposal to increase the trigger level to 300kg before a test certificate
is required is not accepted. As an alternative, what would be acceptable
UK has approx over 1 million 45 kg cylinders. Also Aus
has more than 1 million and Japan has countless 45kg
cylinders.
There is no lack of control on compliance in the UK
there is simply another way of achieving it through
Industry. Comparing our systems with other is valid and
we are not looking to reduce standards simply another
means of checking compliance.
These are for gasfitting compliance and not HSNO
compliance.
Given the submissions on our application, the
Association recognises the logic in having an initial
Consideration Paper – HRE09001 Modified Reassessment of LPG, Propane and Butane Page 35 of 62
would be to retain the current level at 100kg and then vary the renewal
period for installations up to 300 kg with a three or five yearly renewal
period. This would significantly reduce compliance costs yet a level of
auditing to ensure that installations had been installed in accordance with
regulatory standards.
check of the installation by an independent Test
Certifier to reassure the Fire Service, Test Certifiers
and the DoL of initial compliance. However
following this initial certification there is very little
reason to insist on further certification unless
storage quantities are increased over 300kg or if the
physical surroundings are changed such that
separation distances can no longer be achieved. The
trigger for this can come from the industry checking
ongoing compliance of all installations. We believe
this is a sensible outcome which retains initial
certification but reduces ongoing consumer costs
while not compromising safety.
Contact
Energy Ltd
Support There is considerable expense for Location certificates for domestic or
commercial cylinder users and this can be prohibitive and force a user to
use another energy source or to operate with inadequate cylinder storage
leading to vaporisation, pressure drop or gas supply problems in the winter.
Other countries do not have this requirement and the checks carried out by
the Test Certifiers add little value given that the installation is installed by a
gasfitter in the first instance and the gas supplier will alert the owner to any
observed deficiencies.
New
Zealand
Professional
Firefighters
Union
Opposed No specific comment. We believe the concerns of the Fire service centre
around whether they know if LPG cylinders are going to
be encountered on site. As mentioned previously a
location certificate does not of itself inform the Fire
Service if LPG is present on a site. It should also be
remembered that all that is checked for a location
certificate for an installation between 100 and 300kg is
the distance from a drain, distance from an opening into
a building and whether the building material behind the
cylinders is fire resistant. None of these issues would be
critical to fire fighters fighting a house fire. From the
statistics LPG cylinders may be involved in fires but do
not cause fires. Also we believe our plan B proposal
Consideration Paper – HRE09001 Modified Reassessment of LPG, Propane and Butane Page 36 of 62
should take care of the concerns as the initial
installation will be checked for compliance by a Test
Certifier.
Tank Wagon Parking Requirements
IRHACE Support No specific comment.
Tauranga
City Council
Support No specific comment.
New
Zealand Fire
Service
Opposed No specific comment.
BOC Ltd Support No specific comment.
Michael
Farrier
Opposed The report No. LF 5006 Liquids Fuels Trust Board Project 650/02/1 ―Risk
Assessment of Future LPG Facilities in New Zealand, Sept 1984 has been
referenced in this submission however details of how the new (current)
assessment of the risk compares with that presented in the report is not
included. There is substantial NZ literature related town planning and LPG
storage in regard to societal risk assessment and acceptance in the 1980‘s.
These include reports and papers by the Ministry of Works and
Development Town and Country Planning Division by Professor Roger
Keey.
If the spray cage requirement is to be removed for parked tank wagons
containing LPG, a land use planning framework needs to be established in
regard to societal risk and its acceptance (this is issue is currently being
reviewed by the HSE in the UK). Additional issues that need to be
considered in regard to parked tankers are security, availability of fire
fighting response (and water supply), seismic stability, wind direction in
respect to the exposed population and the tank wagon maintenance and
certification regime. Sensors are often provided at fixed installations to
provide an early indication of a leak of an LPG vessel. This is unlikely to
be the case in regard to a parked road tanker.
The risk assessment criteria can be agreed with
ERMA/DoL based on AS/NZS 1596.
Our request is to remove the blanket requirement and
introduce risk assessment for each site. The content of
assessment could be agreed with ERMA.
Australia removed the blanket requirement over 15
years ago as the systems were never used and
maintenance costs were very high for no sensible safety
outcome.
Envirocom Support We conditionally support the LPG Association suggestion to remove the
Consideration Paper – HRE09001 Modified Reassessment of LPG, Propane and Butane Page 37 of 62
(NZ) Ltd requirement for spray cages over all tank wagons where they are parked for
longer than 1 hour. Our support is conditional on:
Recognition of (risks posed to) the adjoining land use; to be
determined by the territorial local authority with regard to land use
zoning under s31 of the RMA, they being cognizant of and
understand the risks associated with those hazards.
The deletion of spray cages shall have the support in writing of the
Location test Certifier and ERMA.
The default position should be that spray cages are required.
Department
of Labour
Opposed This proposal is not supported as it is considered that the current HSNO
controls are not onerous to comply with. Spray cages are only required by
for tank wagons in excess of 12,000 litres water capacity and specifically
for those that contain product otherwise a hydrant system equipped with a
monitor would suffice.
As detailed in the supporting information on this issue it is recommended
that Section 11 and appendix O of AS/NZS 1596 be followed. Section 11.1
requires that Section 11 is read in conjunction with the forward to the
standard. The forward states that the installation has to be addressed as
whole; sound engineering design also reduces the probability for leaks and
greater isolation distances help to minimise the impact on the tank of an
adjacent fire which in turn may reduce the need for water protection.
Appendix O in respect of its application applies to installations of more
than 50 kL capacity. It is not clear how from the information provided in
appendix 2 of the Application how many of the parking areas would be in
the category with onsite storage of over 50kl. Therefore its actual relevance
in applying it as model to tank wagon parking areas would indeed require
extra consideration regarding its suitability.
Reference is made in the application that Tankwagon would present less of
a risk than a stationary container system due to transfer points being
connected to the system such as cylinder filling and automotive fill points
All road tankers are over 12,000 litres. Spray cages
about $20,000 each park.
AS/NZS 1596 Section 11 does apply to lesser quantities
and multi parking facilities.
Consideration Paper – HRE09001 Modified Reassessment of LPG, Propane and Butane Page 38 of 62
and when the tank wagon is parked valves would be in a closed condition.
What was overlooked is that there is a greater presence of combustible
material on a Lpg Tank wagon e.g. Tyres, wiring, flexible hoses all of
which will add to the thermal loading on the tank in the event of a fire
occurring whereas with a stationary container system the presence of
combustible material at the tank is negligible.
The LPG Road Tank Wagon Parking Risk Assessment (appendix 3) to the
application in section 4.3 makes reference the Chief Inspector of
Dangerous Goods issuing guide lines for the parking of LPG tank wagons.
The statement at the end of the Guideline transcript; ―There were no
requirements for a spray cages to be installed at road tankwagon parking
facilities.” is incorrect as the guidance note in subparagraph (k) does in
fact refer to regulation 78 of the Dangerous Goods (Class 2 Gases)
Regulations 1980 which requires a fixed water spray system over tanks
with a water capacity greater than 12.000 litres. Regulation 78 was
amended in 1987 to include a water spray. It has to be noted that at the
time there was also an allowance made for tank wagons that are nominally
empty to be afforded protection by the installation of a hydrant and
monitors this approach would have only been applied to fixed tanks in rare
situations. These requirements have been place for nearly twenty years it
surprising that the industry expresses some dismay that the were not
consulted with the amendment to the Gazette Notice in 2007. This
amendment merely corrected an omission from the controls that should
been occurring in the first place.
The data provided in respect of the time it would take for a tank to BLEVE
is consistent with actual events that have occurred overseas. When it is
considered that such a catastrophic failure can occur within 10- 20 minutes
of a fire occurring at a tank then surely any additional protection that may
be provided by a water spray on larger Stationary Containers has to be
beneficial in assisting the Emergency services in responding to and
controlling such an event.
Parts of the Industry were not aware of the requirements
and obviously parts of the DG regime ware also not
aware as DG license were issued for sites without spray
cages.
Engineering controls separation distances many other
ways to control risks.
Spray cages are not required as of right in NFPA 58 or
AS/NZS 1596.
We have many sites were tankers are parked without
spray cages and have had no incidents.
Consideration Paper – HRE09001 Modified Reassessment of LPG, Propane and Butane Page 39 of 62
New Zealand has been very fortunate to date with the management of LPG
in that there has never been a BLEVE, this in all likelihood has been due to
ensuring the relevant regulatory standards are adhered to and maintained.
The recent Tamahere Icepak explosion and fire demonstrated what a
relatively small release (when compared to what could escape from a
tankwagon) of LPG can do.
The requirements of Section 11 and appendix 0 of AS/NZS 1596 appear to
be designed to take a preventative approach in respect of minimising the
consequences of a fire near an LPG storage facility and if a fire event does
occur rely on a response from the fire service to control the situation when
they arrive, given the relatively short time they have for a response before a
major event could occur it is surely preferable on larger tanks to take the
additional precaution of providing tank cooling. Furthermore in it is stated
in appendix O that if there are additional storage tanks on the site or other
Flammable materials these would require a separate evaluation over and
above than what is detailed in the procedure for evaluation in Appendix O.
It is considered that is this application for a variation was to succeed it
would decrease the current standard that applies and therefore is
considered not to be acceptable.
All aspects of each parking facility will be taken
account of in the risk assessment for which the content
can be agreed with ERMA.
Contact
Energy Ltd
Support The requirement for spray cages over LPG road tankers should be risk
based. There is a need on occasions to be able to park tankers overnight on
sites which are not dedicated tanker parks when driving hours or weather
dictate. In these cases it is not always possible to provide water sprays as
the land is owned by other parties who do not want a cage permanently
erected on their site.
New
Zealand
Professional
Firefighters
Union
Opposed No specific comment.
Separation Distances for Cylinder and Tank Storage
IRHACE Support No specific comment.
Consideration Paper – HRE09001 Modified Reassessment of LPG, Propane and Butane Page 40 of 62
Tauranga
City Council
Support No specific comment.
New
Zealand Fire
Service
Opposed No specific comment.
BOC Ltd Support No specific comment.
Michael
Farrier
Support Separation distance requirements should be considered in regard to
applicable management systems and controls under the HSNO regime. It
would be appropriate to ensure that AS/NZS 1596 requirements integrate
with all other HSNO requirements so that there is a level playing field
when managing LPG and controlling the associated hazards.
The Dunedin City Council made a land use planning decision in regard to
the LPG depot adjacent to the new stadium which has already compromised
some of the earlier planning advice in regard to separation distances and
societal risk of LPG storage and distribution. Is it appropriate for an LPG
depot to be 200 meters distant from a location where up to 30,000 people
may gather? I doubt whether planning permission would be granted for a
LPG Distribution Depot within 200 meters of an existing sporting stadium
because of the societal risk.
This situation should not be allowed to occur again; separation distances
should not be considered in isolation of land use planning requirements,
societal risk and essential services.
The original Liquigas LPG Depots in New Plymouth, Auckland,
Christchurch and Dunedin were established in accordance with world best
practice – engineering design and planning requirements should not be
compromised so as to increase societal risk.
Envirocom
(NZ) Ltd
Opposed The adoption of the separation distances in AS/NZS 1596 for tanks
suggested by the LPGA is not supported. The adoption of the separation
distances in AS/NZS 1596 for LPG cylinders suggested by the LPGA is not
supported.
Department Opposed The immediate concern regarding this is why was not an alignment sought It was 2008 and our application just covered the
Consideration Paper – HRE09001 Modified Reassessment of LPG, Propane and Butane Page 41 of 62
of Labour in respect of AS/NZS 1596 2008 rather than the 2002 as detailed in the
application. Furthermore appendix 3 appears to go further in certain areas
and appears to be over and over above what being asked for in the original
application in that the application appeared to be seeking to amend the
storage distances for cylinders as required by table (2) Clause 30 in
Schedule 10 and table (3) Clause 30 Schedule 10 for tanks. Assuming that
that the LPG Association application is intending to cover all the aspects of
isolation distances associated with cylinder and tank storage then this
would present a substantial conflict with what is currently required by the
gazette notice and a more detailed analysis would be required as to the
acceptability of the proposal.
Furthermore it is stated in the application that the AS 1596 2002 contains
significant new information, what the significance of this new information
is does not appear to have been detailed in the application. As previously
stated AS/NZS 1596 has been revised and new version was published in
2008. If the Application request is considered in its entirety it may already
be out of date due a newer version of the standard superseding what has
been presented to date.
If Tables 4.1 and 6.1 are to be considered in isolation then consideration
should be given the proposal the only area of concern would be in respect
of lower first two line lower quantities in the respective tables and this may
impact on the other parts in the Gazette Notices.
In summary the given the current information provided the Proposal could
only be accepted in part.
differing separation distances covered in tables 4.1 and
6.1.
HSNO regs are so complicated that most people other
than test certifiers cannot use them AS/NZS 1596 is a
far more useable document.
Contact
Energy Ltd
Support AS/NZS 1596, The Storage and Handling of LP Gas, defines the isolation
distances for LPG and there is a need to align the gazette version to line up
without NZ standard to avoid conflict. AS/NZS 1596 is called up in some
District Plans or conditions of Resource Consents so this conflict is
difficult to resolve. The differences appear minor, therefore adopting the
requirements of AS/NZS 1596 would not appear onerous.
New Opposed No specific comment.
Consideration Paper – HRE09001 Modified Reassessment of LPG, Propane and Butane Page 42 of 62
Zealand
Professional
Firefighters
Union
Fire Extinguisher Requirements
IRHACE Support No specific comment.
Tauranga
City Council
Support No specific comment.
New
Zealand Fire
Service
Opposed Fire extinguishers are useful tools to control a fire and the fire service view
is that they should be present. This may be more so for rural locations
where LPG installation may be more prevalent and a volunteer brigade may
take longer to attend. Having such equipment may mitigate a fire in the
following circumstances.
When everyone has been evacuated and accounted for at a safe
meeting place.
When the fire service has been called.
When it is safe to do so considering the size and location of the
fire.
Access to the fire is unrestricted and a safe retreat is possible at all
times.
Remember life is more important than property, don't put yourself
or others at risk.
If the cost of a fire extinguisher (LPGA quote $30) by the LPGA's assertion
is such a significant barrier to entry for the installation of LPG or moving to
higher storage quantities than 50kg, we believe the cost of upgrading from a
9kg cylinder to a 45kg cylinder or the installation cost would be more than
$30? This undermines the benefit and safety case of the LPGA.
It might be a good idea but to make customers legally
liable if they don‘t have one is just not sensible. It is
unenforceable and consumers would only be aware of
their liability in the case of something going wrong
when they may well be faced with an insurance issue.
BOC Ltd Support No specific comment.
Envirocom Support We agree with the suggestion of the LPGA to remove the requirement for
Consideration Paper – HRE09001 Modified Reassessment of LPG, Propane and Butane Page 43 of 62
(NZ) Ltd fire extinguishers for LPG (in any quantity) in domestic settings.
Department
of Labour
Support No specific comment
Contact
Energy Ltd
Support Whilst we support the idea of home owners having a fire extinguisher in
their home this is not a legal requirement. We do not support making this
a condition when storing more than 50 kg of LPG as this adds cost and
infers it should be used for LPG emergencies. We would not encourage
domestic users to attempt to fight an LPG related fire. Instructions in an
emergency are to call the Fire Brigade and evacuate. Attempting to use the
fire extinguisher could be dangerous unless home owners are specifically
trained to deal with LPG fire fighting. This is where the Fire Brigade is
required.
New
Zealand
Professional
Firefighters
Union
Opposed No specific comment.
Separation Distances for Vaporisers
IRHACE Support No specific comment.
Tauranga
City Council
Support No specific comment.
New
Zealand Fire
Service
Opposed No specific comment.
BOC Ltd Support No specific comment.
Envirocom
(NZ) Ltd
Support We agree with the suggestion of the LPGA to remove the aggregation
requirements for separation distances for vaporisers.
Department
of Labour
Support No specific comment
Contact
Energy Ltd
Support Adopt the wording of AS/NZS 1596 which uses the isolation distance of
each individual vaporiser rather than the aggregated total.
Stationary Container Certification
IRHACE Support No specific comment.
Tauranga Support No specific comment.
Consideration Paper – HRE09001 Modified Reassessment of LPG, Propane and Butane Page 44 of 62
City Council
New
Zealand Fire
Service
Opposed No specific comment.
BOC Ltd Support No specific comment.
Envirocom
(NZ) Ltd
Opposed We do not support the suggestion of the LPGA to remove the need for
SCSC and transfer the requirements to the Location Test Certificate.
Department
of Labour
Opposed It is considered that the parts of Schedule 8 that require Stationary Tank
certification are in fact intrinsic matters that relate to the tank system as
whole and thus the installation should be appraised under the Stationary
Container process. The augment that the regime imposes additional costs
on the industry does not have merit. Test Certifiers who can issue
stationary certification can also issue Location Test Certificates. ERMA
has accepted that the certification for a site may be combined, thus
providing efficiencies in the Test Certification process. The PECPR
regulations address the requirements for the pressure integrity of the
Stationary Container System not the overall installation layout and safety
systems incorporated into the Container design.
Furthermore it is stated in the application that in addition to reducing costs
it will also reduce complexity. Again it is difficult to see how the
complexity will be reduced as the requirements will remain the same. It
could be considered that the requirements in schedule 10 for tank isolation
distances be transferred into schedule 8 and thus be made part of the
Stationary Container Certification process. However it is considered the
efficiencies to be gained would be minimal.
Finally making changes as proposed would then not be consistent in respect
of how other substances stored in tanks managed inside schedule 8 and
therefore this would create additional complexities inside the HSNO
control framework. On this basis the proposal is not supported.
There is no need for a separate stationary container
certificate should be a combined process.
What we are suggesting is that the location and fire
fighting sections of the stationary container certificate
be moved into the location certificate. The Stationary
Container certificate will become the PECPR certificate.
So before the location certificate is issued a current
PECPR certificate will be required.
The LPG Industry can only focus on LPG issues and
there should be enough flexibility in the Regulations to
allow substance specific options.
Contact
Energy Ltd
Support All LPG tanks are pressure vessels under PECPR regulations and are
inspected annually or bi-annually by specialised pressure vessel engineers
under Regulations enforced by OSH. The current requirement for tanks to
Consideration Paper – HRE09001 Modified Reassessment of LPG, Propane and Butane Page 45 of 62
also be inspected by a Test Certifier under the HSNO regulations provides
little or no value, but comes at a significant cost to industry. It is also
unworkable in practice as the Test Certifiers will not issue their Test
Certificates until they sight the PEPCR certificate. As the PEPCR
certificate is not available for approx one month from the date of the
inspection and the Test Certifier requires a similar time to inspect and issue
the certificate, the site will operate with an expired Stationary Container
Certificate for up to two months. Also because the Test Certifier will only
issue the Stationary Container Certificate for the period of the PEPCR
certificate typically this only runs for ten months from date of receipt. The
current requirement for LPG tanks is clumsy and unworkable and provides
no use outcome, therefore we support moving the few checks not already
covered by PEPCR inspection across to the Location Certificate inspection
and dropping the requirement for Stationary Container certification for
LPG tanks.
New
Zealand
Professional
Firefighters
Union
Opposed No specific comment.
Other/General
IRHACE Support The LPGA submission, while not focusing on LPG as a refrigerant, has
obviously been thoroughly researched by the LPG Association and we
therefore expect that any additional risks have been thoroughly assessed as
well.
New
Zealand Fire
Service
Opposed The Fire Service opposes the LPGA application on the grounds that the
submission does not reflect current thinking. The LPGA submission has
completely omitted the risk to emergency responders. The recent ICL
inquiry by Lord Gill (UK) contradicts the LPGA submission.
The removal of test certification and basic fire safety measures (fire
extinguishers) is counterproductive to addressing already low levels of
compliance and providing some basic fire response and this application will
not reduce the incidence or consequence of fire or provide communities
Consideration Paper – HRE09001 Modified Reassessment of LPG, Propane and Butane Page 46 of 62
with any greater protection.
The Fire Service requests that ERMA New Zealand retains all current
HSNO test certification and controls relating to LPG, butane and propane
and rejects the LPGA submission in its entirety.
BOC Ltd Support BOC supports this modified reassessment. It brings NZ into line with
international standards and codes.
Michael
Farrier
N/A I request that ERMA New Zealand:
Require additional information to be collated on existing LPG cylinder
management practices and ask that LPG suppliers set and example by
enforcing a Code of Practice under the current requirements before
increasing the threshold storage level.
Look at establishing societal risk criteria requirements in New Zealand by
which land use planning requirements can be considered in a consistent
manner. These should take into account site security, emergency
evacuation, and fire protection response, etc.
Consider the requirement of LPG tank wagon parking in regard to all
applicable factors; not only stand-alone separation distances.
Ask that the applicant demonstrates that a fair comparison has been made
in their submissions in regard to overseas practice and the management
system and controls that apply in the jurisdiction.
Envirocom
(NZ) Ltd
N/A It is our considered opinion from many years of undertaking site
inspections, training of personnel, attendance at incidents, and our
collective very close association with this industry from our previous
disparate and very related backgrounds that the LPG Association‘s risk
assessment is flawed or at best paints a picture of the industry that bears
little relationship to the reality out there on the ground.
We wish the submission hearing panel to take note of the photographs
attached to our submission. The level of non compliance with not only the
Consideration Paper – HRE09001 Modified Reassessment of LPG, Propane and Butane Page 47 of 62
HSNO controls but the previous and now repealed Dangerous Goods
legislative Controls should be immediately obvious. Most of those
illustrated have now been resolved, but such mistakes continue.
New
Zealand
Professional
Firefighter
Union
(NZPFU)
We request that ERMA New Zealand:
Leave intact or strengthen all safety regulations/issues related to LPG and
not to relax or lessen the existing regulations as sought by the LPG
Association. Already there is anecdotal evidence that
compliance/enforcement of existing regulations is well below what ought to
be expected, the NZPFU don‘t see how relaxing of LPG regulations further
will better protect the public and Firefighters.
Consideration Paper – HRE09001 Modified Reassessment of LPG, Propane and Butane Page 48 of 62
APPENDIX 4 - Impact of adopting the separation distances for cylinder and tank storage of LPG
from AS/NZS 1596
Separation of Tanks Boundary of Controlled Zone
LPG Density 0.537 g/ml
Water
capacity of
tank (kL)
Area of high
intensity land use
(metres)
Protected Works Area of low
intensity land
use (metres)
Public Place
Column 1 Column 2 AS/NZS 1596 AS/NZS 1596
– vapour
draw-off
Column 3 AS/NZS 1596 AS/NZS 1596
– vapour
draw-off
0.5 2.00 1.50 1.50 2.00 1.50 1.50
1 3.00 3.00 3.00 3.00 2.00 2.00
2 4.25 6.00 4.50 3.50 4.00 3.00
5 8.00 8.00 5.00 5.00 5.00 3.50
8 9.80 10.00 6.00 6.20 6.00 4.00
10 11.00 11.00 11.00 7.00 7.00 7.00
20 15.00 15.00 15.00 9.00 9.00 9.00
50 17.00 17.00 17.00 10.00 10.00 10.00
100 21.00 20.00 20.00 12.00 11.00 11.00
200 28.00 25.00 25.00 14.00 12.00 12.00
500 28.00 42.00 42.00 14.00 22.00 22.00
Consideration Paper – HRE09001 Modified Reassessment of LPG, Propane and Butane Page 49 of 62
Issues Definitions
High intensity land use
Low intensity land use
area of high intensity land use— (a) includes— (i) an area of regular habitation; and (ii) a structure made of or containing combustible materials that would sustain a significant fire; and (iii) a high density traffic route; but (b) does not include a small office constructed of non-combustible materials associated with a hazardous substance location that is used by persons authorised to be at the location by the person in charge of that location
area of low intensity land use— (a) includes— (i) an area where any person may be legally present occasionally; and (ii) a public park or reserve; and (iii) a traffic route of low or medium traffic density; but (b) does not include an area of regular habitation
Protected place
Public place
Any of the following: (a) A dwelling, place of worship, public building, school or college, hospital, theatre or any building or open area in which persons are accustomed to assemble in large numbers, whether within or outside the property boundary of the installation. (b) A factory, office, workshop, store, warehouse, shop or building where people are employed, except a building used for the storage and handling of LP Gas. (c) A vessel (e.g. a ship) lying at permanent berthing facilities. (d) Any storage facility for dangerous goods outside the property boundary of the installation, except those defined as minor storages in other Standards or regulations.
Any place, other than private property, open to the public and including a street or road. Parking areas for commercial and public buildings are not considered public places.
Consideration Paper – HRE09001 Modified Reassessment of LPG, Propane and Butane Page 52 of 62
For high intensity land use, above 270,000 L the separation distances required by AS/NZS 1596 are greater than those set by HSNO, although it must be recognised that these are large tanks. Between 15,000 L and 270,000 the distances required by AS/NZS 1596 are less than HSNO, varying by between 0% and 10% (25m v 28m). In the range 0 to 10,000 L there is a agreement for tanks between 1,000 L and 10,000 L, however, for tanks less than 500 L HSNO requires an additional 0.5 m separation (2m cf 1.5 m). In this range, AS/NZS 1596 also allows a significant reduction in separation distance where there is a single tank used only for vapour withdrawal. HSNO does not allow for this eventuality.
Minimum distance to an adjacent tank AS/NZS 1596 requires the separation to be the diameter of the largest tank, however, it also says that a tank that has no other tank within 8 m of it may be considered
a single tank. If tanks are located end to end the larger of 3m or twice the diameter of the largest tank. Clause 6.2.2(c) of AS/NZS 1596. HSNO specifies the diameter of the largest tank, or at least 1 m if the largest tank is less than 10,000 L or 2 m if of a greater capacity.
Consideration Paper – HRE09001 Modified Reassessment of LPG, Propane and Butane Page 54 of 62
For low intensity land use, above 250,000 L the separation distances required by AS/NZS 1596 are greater than those set by HSNO, although it must be recognised that these are large tanks. Between 50,000 L and 250,000 the distances required by AS/NZS 1596 are less than HSNO, varying by between 0% and 16% (12m v 14m). In the range 0 to 10,000 L there is a reasonable agreement for tanks between 1,500 L and 10,000 L, however, for tanks less than 1,500 L HSNO requires up to an additional 1 m separation (3m cf 2 m at 2,000 L). In this range, AS/NZS 1596 also allows a significant reduction in separation distance where there is a single tank used only for vapour withdrawal. HSNO does not allow for this eventuality.
Consideration Paper – HRE09001 Modified Reassessment of LPG, Propane and Butane Page 55 of 62
Separation of Cylinders from Boundary of Controlled Zone
LPG Density 0.537 g/ml
Aggregate
quantity of
liquefiable gas
in cylinders
only (kg)
Area of high intensity
land use (metres)
Protected
Works
Area of low
intensity land
use (metres)
Public Place
Column 1 Column 2 AS/NZS
1596
Column 3 AS/NZS 1596
100 0.00 0.00 0.00 0.00
300 2.00 0.00 0.00 0.00
500 2.00 0.00 2.00 0.00
537 2.02 3.00 2.00 1.50
1000 2.33 3.00 2.00 2.43
1342 2.56 4.50 2.00 3.00
2,000 3.00 5.03 2.00 3.00
3222 3.81 6.00 2.41 3.00
5,000 5.00 7.10 3.00 3.83
6444 5.58 8.00 3.29 4.50
10,000 7.00 8.43 4.00 4.71
50,000 8.00 12.83 5.00 7.13
64440 15.00 15.00 8.00 8.00
Consideration Paper – HRE09001 Modified Reassessment of LPG, Propane and Butane Page 59 of 62
Distances Distances required by AS/NZS 1596 are greater than those in the legislation. As a consequence locations that currently compliant may not conform in the future. These facilities will have to be subject to transitional conditions.
Controls where quantities are less than 1,000 kg
There is no suggestion that controls on fire resistance and fire resistance rating of walls behind the cylinders specified in HSNO be changed.
Consideration Paper – HRE09001 Modified Reassessment of LPG, Propane and Butane Page 60 of 62
APPENDIX 5
LPG Facility Test Certificate for Stationary Container System Schedule 8 – Elements Requiring Transfer
The facility must have a tank that has a water capacity of greater than 500 litres.
92 (2) Requirements for test certificate
(a) the stationary container system is—
(i) suitable for service with a specified hazardous substance, or specified substances, without leakage
of the substance, for all reasonably foreseeable operating pressures, temperatures, stresses and
loadings;
Pressure Equipment, Cranes and
Passenger Ropeways (PECPR)
Regulations 1999.
Clause 92 (5) (a)
(ii) constructed of materials that are compatible with any hazardous substance that the system is
likely to contain;
PECPR Clause 92 (5) (a)
(b) if the stationary container system includes a stationary tank, the stationary tank complies with the requirements specified in this Schedule relating to
(i) tank design; PECPR Clause 92 (5) (b)
(ii) tank construction; PECPR Clause 92 (5) (b)
(iii) tank installation; PECPR Clause 92 (5) (b)
(iv) pressure management; PECPR Clause 92 (5) (b)
(v) emergency pressure management; PECPR Clause 92 (5) (b)
(vi) the level indicator requirements specified in clauses 13 and 36 Clauses 13 and 36 are not relevant
(vii) lightning and stray current protection; Not applicable as far as Part 4 is
concerned, but is referenced in
AS/NZS 1940
(viii) the separation requirements specified in Part 5; Yes
Consideration Paper – HRE09001 Modified Reassessment of LPG, Propane and Butane Page 61 of 62
92 (2) Requirements for test certificate
(ix) fire fighting systems; Yes, if >12,000 L
(x) the marking requirements under clause 77; Not applicable. Clause 77 (a)
(xi) the requirements relating to plans under clause 81; Covered by the location test
certificate
(c) if the stationary container system includes a stationary tank with integral secondary containment,
the stationary container system complies with regulation 39 or 40 as applicable of the Hazardous
Substance (Emergency Management Regulations) 2001;
Not applicable, no secondary
containment for class 2.1.1A
(d) if the stationary container system includes a stationary tank that contains a [class 3.1D, or] class
6, or class 8, or class 9 hazardous substance that is not also a class 2, or class 3 [other than class
3.1D], or class 4, or class 5 hazardous substance, the stationary container system complies with
the requirements of Part 4 of the Hazardous Substances Emergency Management) Regulations
2001
Not applicable.
(e) if the stationary container system includes a vaporiser, the vaporiser complies with clause 55; Yes, but very few vaporisers.
These are to be checked as
approved by ERMA New Zealand,
and that separation distance criteria
is met.
(f) if the stationary container system complies with Part 13; Not applicable
(g) if the stationary container system includes a burner, the burner is—
(i) approved in accordance with clause 68; and
(ii) installed in accordance with clause 71; and
Not applicable. An approval for a
burner is confined to class 3.1
substances.
(h) pipework complies with requirements for—
(i) design, construction, and installation; and PECPR Clause 96 (6) (a)
(ii) operation, inspection, testing, and maintenance; and PECPR Clause 96 (6) (a)
(iii) installation of transfer point pipework in accordance with clause 75; and Questionable, although very few
ship to shore pipelines. In Gazette
Consideration Paper – HRE09001 Modified Reassessment of LPG, Propane and Butane Page 62 of 62
92 (2) Requirements for test certificate
Notice 35 clause 75 did not apply
where equipment was subject to
PECPR. A subsequent amendment
continued the requirement for
pipework including transfer lines.
The amendment did not address
Clause 75 which is specific to a
ship to shore transfer line.
However, this clause does not
specify any design criteria for LPG
pipework
(i) the requirements for valves in clause 75 are complied with; and Yes, very few. Valves are covered
by clause 76, not 75. See also
comment above (h) (iii)
(j) the records specified in clause 81 are available; and Already asked in (b) (xi) above.
May mean clause 82. Essentially
covered by the location test
certificate
(k) any repairs or alterations carried out comply with the requirements of Part 18. PECPR Clause 92 (5) (c)
Clause 96 (6) (9)