Quarterly Progress Report No. 1
Project Number : 43251 – 025
February 2018
Indonesia : Metropolitan Sanitation Management
Investment Project (MSMIP)
Asian Development Bank
ADB Loan 3123-INO: Metropolitan Sanitation Management Investment Project
Quarterly Report No. 1, February 2018 i
Table of Contents 1 Executive Summary ......................................................................................................................... 1
1.1 The Contract ............................................................................................................................ 1
1.2 Detailed Design ....................................................................................................................... 2
1.3 Key Issues ................................................................................................................................ 2
1.4 Progress ................................................................................................................................... 3
1.5 Look Ahead ............................................................................................................................. 4
2 Acronyms and Abbreviations .......................................................................................................... 5
3 Introduction and Basic Data ............................................................................................................ 7
3.1 Purpose of the Report ............................................................................................................. 7
3.2 Brief Description of Project ..................................................................................................... 7
3.2.1 Rationale ............................................................................................................................. 7
3.2.2 Design Status ...................................................................................................................... 8
3.2.3 Impact and Outcome ........................................................................................................ 10
3.2.4 Outputs ............................................................................................................................. 10
3.2.5 Coverage ........................................................................................................................... 10
3.3 Basic Data .............................................................................................................................. 15
3.3.1 Loan Amount .................................................................................................................... 15
3.3.2 Project Cost ...................................................................................................................... 15
3.3.3 Executing Agency .............................................................................................................. 17
Directorate General of Human Settlement, MPWH ..................................................................... 20
3.4 Key Dates .............................................................................................................................. 20
3.5 Other Relevant Information .................................................................................................. 21
3.5.1 Project Proposed Changes ................................................................................................ 21
4 Utilization of Funds ....................................................................................................................... 22
4.1 Contract Awards (actuals this quarter, annual and overall project) ..................................... 22
4.2 Loan Withdrawal and Disbursement .................................................................................... 23
4.3 Projection vs Actual Achievement ........................................................................................ 24
5 Implementation Progress ............................................................................................................. 25
5.1 General .................................................................................................................................. 25
5.2 Coordination at central and regional levels (CPMU, LCO’s) ................................................. 28
5.2.1 Pekanbaru ......................................................................................................................... 28
5.2.2 Jambi................................................................................................................................. 29
ADB Loan 3123-INO: Metropolitan Sanitation Management Investment Project
Quarterly Report No. 1, February 2018 ii
5.2.3 Makassar .......................................................................................................................... 30
5.2.4 Site Visits .......................................................................................................................... 31
5.3 Liaison with ADB ................................................................................................................... 32
5.4 Consultant Procurement and Contract Management .......................................................... 33
5.4.1 Project Office Establishment ............................................................................................ 33
5.4.2 Staff Mobilisation ............................................................................................................. 35
5.4.3 Communication Plan ........................................................................................................ 37
5.4.4 Document Control ............................................................................................................ 39
5.5 Management of Contractors and Consultants ...................................................................... 39
5.5.1 Management of Contractors ............................................................................................ 39
5.5.2 Management of Consultants ............................................................................................ 40
5.6 Project Coordination Meetings ............................................................................................. 40
5.7 Training/ Workshops ............................................................................................................. 40
5.8 Progress of Project Component ............................................................................................ 41
5.9 Project Performance and Monitoring System ...................................................................... 41
5.10 Safeguard Monitoring ........................................................................................................... 41
5.11 Gender Action Plan ............................................................................................................... 41
5.11.1 Gender Classification ........................................................................................................ 41
5.11.2 Purpose and Strategy ....................................................................................................... 42
5.11.3 Implementation and Monitoring Arrangements. ............................................................. 43
5.11.4 GAP Budget. ...................................................................................................................... 43
5.12 Financial Management.......................................................................................................... 44
5.13 Arrangement for O&M of Project Facilities .......................................................................... 44
5.14 Project Targets ...................................................................................................................... 44
6 Compliance with Loan Covenants ................................................................................................. 46
7 Major Issues/Problems and Proposed/Recommended Remedial Actions ................................... 49
7.1 Problems and Rectification ................................................................................................... 49
7.2 Delays in consultant recruitment/ issuance of DIPA ............................................................ 59
7.2.1 PISC Mobilization. ............................................................................................................. 59
7.3 Potential covenant compliance issues .................................................................................. 59
7.4 Project Audit Issues ............................................................................................................... 60
8 Expected Activities in the next Quarter ........................................................................................ 61
App A – Project Organisation ................................................................................................................ 62
App B – Design Phase Project Schedule ................................................................................................ 63
ADB Loan 3123-INO: Metropolitan Sanitation Management Investment Project
Quarterly Report No. 1, February 2018 iii
App C – Staffing Schedule ..................................................................................................................... 67
App D – Progress Meetings ................................................................................................................... 71
List of Tables
Table 1-1 Projects Description – Loan ADB ............................................................................................. 1
Table 3-1 The MSMIP Project Coverage to be Implemented ............................................................... 11
Table 3 - 2. Detailed Cost Estimate – Revised ....................................................................................... 16
Table 3 - 3 Projects Description - Loan ADB .......................................................................................... 20
Table 3-4 Summary of Changes in Treatment Plant Capacity and Property Connections ................... 21
Table 4-1 Description of MSMIP of Estimated Contract ...................................................................... 22
Table 5-1 Summary of Changes in Treatment Plant Capacity .............................................................. 26
Table 5-2 Summary of Revised Property Connections to the Central Sewerage Systems .................. 26
Table 5-3 Contract Procurement Schedule ......................................................................................... 27
Table 5-4, Illustrates the recruitment so far ........................................................................................ 34
Table 5-5 MSMIP’s Gender Action Plan ............................................................................................... 41
Table 5-6 PISC’s Project Targets ........................................................................................................... 44
Table 7-1 Project Risk Register ............................................................................................................. 54
List of Figures
Figure 3.1 Project Locations of MSMIP ................................................................................................... 9
Figure 3.2 Service Areas and Catchment of Jambi Wastewater Offsite System ................................... 12
Figure 3.3 Service Areas and Catchment of Pekanbaru Wastewater Offsite System ........................... 13
Figure 3.4 Service Areas and Catchment of Makassar Wastewater Offsite System ............................. 14
Figure 3.5 Project Organization Structure of MSMIP ........................................................................... 18
Figure 5.1 Staffing levels for Jakarta during the project term based on the original Contract and
Addendum No 1 .................................................................................................................................... 33
Figure 5.2 Communication Flow Diagram ............................................................................................ 37
Figure 7.1 Earthworks for WWTP Site in Pekanbaru ............................................................................ 50
ADB Loan 3123-INO: Metropolitan Sanitation Management Investment Project
Quarterly Report No. 1, February 2018 iv
Figure 7.2 Location for Pumping Station .............................................................................................. 50
Figure 7.3 Earthwork at WWTP Site ...................................................................................................... 51
Figure 7.4 Current Situation at PS Site .................................................................................................. 52
Figure 7.5 Plan of Canal Accross The WWTP Site ................................................................................. 53
ADB Loan 3123-INO: Metropolitan Sanitation Management Investment Project
Quarterly Report No. 1, February 2018 1
1 Executive Summary The first Quarterly Report has been developed to update DGHS and ADB of the project progress in the
first three months of the project, between the dates of 2nd October 2017 and 2nd January 2018. The
information contained in the report details the project status including outputs and the key issues that
surround the project. A summary of the main points within the document are given in this section.
1.1 The Contract
On October 2nd 2017, the Project Implementation Support Consultant (PISC) for the project - Loan
No. 3123-INO. Metropolitan Sanitation Management Investment Project – were appointed by
Directorate of General Housing Settlement (DGHS) to undertake tasks listed under Contract
HK.02.03/MSMIP-KONS/X/11/2017. The PISC consists of lead Consultant SMEC International Pty Ltd
in joint venture with Stantec Australia Pty Ltd (ex-MWH) and in association with the following firms
as sub-consultants: PT. Infra Tama Yakti (ITY), PT. SMEC Denka Indonesia, PT. Amurwa International
and PT. Widya Graha Asana (WGA).
The Contract will run from October 2nd 2017 to January 2nd 2021 which is a 40 month period which
is a reduction to the 48 month period defined in the RFP. The loan agreements were signed on 13 May
2014, declared effective on 9 July 2014, and scheduled for closing on 31 December 2020. A table of
Project key dates are provided in Table 1-1.
(Table 1-1 Projects Description – Loan ADB)
No Description ADB – OCR Loan ADB – AIF Loan
1 Loan Number ADB L 3123- INO ADB L 8280 - INO
2 Project Number 43251 – 025 43251 - 025
3 Total Loan $ 80 million $ 40 million
4 Signed Loan 13-May-14 13-May-14
5 Effective loan 09-Jul-14 09-Jul-14
6 Closing date 31-Dec-20 31-Dec-20
7 Method of Payment Special Account Special Account
8 No Special Account N/A N/A
9 Amount of Initial Deposit N/A N/A
10 Project Location
Implemented
3 ( three )
Local Government
2 ( two )
Local Government
a. Jambi City a. Jambi City
b.Makasar City b.Pekanbaru City
c. Pekanbaru City
14 Executing Agency The Directorate General of Human Settlements , Ministry of
Public Works
14 Institutions Involved
a. Central Goverment DGHS,CPMU,CPIU
b. Provincial Goverment PPMU,PPIU
c. Local Govenment LPMU,LPIU
ADB Loan 3123-INO: Metropolitan Sanitation Management Investment Project
Quarterly Report No. 1, February 2018 2
1.2 Detailed Design
The Detailed Design of the wastewater treatment plants and sewerage networks have been prepared
by other consultants, namely MWH, Perancang Adhinusa and Dwikarsa Envacotama, for the three
cities, which currently is further being reviewed by the PISC. Following review, the PISC will make
changes where necessary and provide a robust design that can be tendered either by using
International Competitive Bidding (ICB) or National Competitive Bidding (NCB) processes. The
tendering process has been defined based on the contracts for the Wastewater Treament plant/WTP,
Wastewater sewer system/WSS which will be budgeted for through an ADB loan , and funds from
Central Government and local Government . Once the design and tender documents are prepared
accordingly, they can be tendered and the Construction phase can commence. The PISC will provide
construction supervision of the development of the sewerage systems for Jambi, Makasar and
Pekanbaru.
1.3 Key Issues
There are key concerns around the level of quality of the current designs for all cities that will require
a longer period of design detailing and in some cases re-planning before they are deemed fit for
purpose. These include;
Reduction to the areas that forms the WWTP site at Jambi and Makassar meaning
reconfiguration of the site;
New regulations regarding Discharge Standards that were made since the design was
undertaken, mean that the WWTPs in their current form do not meet the desired standards
and therefore a new plant design must be considered;
Limited Geotechnical information in Pekanbaru and no available information in Jambi means
that a Geotechnical Site Survey must be carried out;
Topographical Survey information in Jambi is incorrect and therefore a new survey is required.
Verification of surveys in Pekanbaru and Makassar is also required;
Jambi network design is of a very poor standard and a re-design must be undertaken;
The drawing details associated with Pekanbaru and Jambi are very limited and a lot of work is
required to deem them a fit for purpose detailed design set of drawings;
ADB major change document that reduced the number of connections in December 2016 was
not accounted for in the designs. This may have major impact on plant sizing and network
capacities.
In general the Contracts for each City are broken into three main contracts dependant on the loan
provider. These are
Contract A – Earthworks
Contract B – WWTP and partial network
Contract C – Networks
Based on contract value, Contract C will be split up further. As this will be written under NCB terms
and local contractors are invited to bid, it has been recognised that the value of the works exceeds the
value that could be undertaken by a single contractor in Indonesia, hence the need to contract C in a
number of packages.
ADB Loan 3123-INO: Metropolitan Sanitation Management Investment Project
Quarterly Report No. 1, February 2018 3
The Earthworks package is to be funded by Local Government however minimal progress has been
made in Jambi and Pekanbaru due to insufficient funds and although assurances have been given that
Makassar Earthworks will be started in early 2018, there are no signs ofthat happening. DGHS will
discuss the matter further with ADB in the second quarter of the project.
Issues around land acquisition are apparent at the Jambi and Maksaar WWTP and Pump Station
locataions. LG have offered the Pump Station A site in Makassar for a Multi Stiorey Car Park and Jambi
Pump Station has some resettlement concerns and access and egress restrictions.
1.4 Progress
PISC have made progress in the first quarter of the project on many fronts and whilst the current
programme issued with the Inception Report in November 2017 is to be updated to incorporate
changes and construction timeframes, the project has started well. PISC have been able to;
Review the current design status delivered by others
Provide recomendations of requirements through Addendum 1
Provide monthly reports 1 and 2 and the Inception Report
Undertake design reviews for Jambi and Pekanbaru
Provide a Project Schedule
Develop a Risk Register
Hold regular meetings with the Client
Make progress with the development of Makassar Contract C Documents that include
o Preparation of the Standard Specifications in Indonesian
o Preparation of the Contract Documents in Bahasa
o Separation of Drawings for the Tender Package
o Prepare a cost estimnate
Whilst the deployment of International Staff has been hampered for issues that are described below,
an International Water and Wastewater Expert, Brian Hayden, has taken on as Temporary Team
Leader Role to ensure that the project mobilisation is smooth and to ensure that the Natioanl Key and
Non Key Experts are mobilised as necessary. The challenges PISC have realised at this stage of the
project, in mobilising the necessary key International staff exist for a number of reasons listed below;
1. The project was tendered in June 2016 and finally awarded in October 2017 following a long
period of negotiation during which key experts signed CVs to accept the positions, the period
between signing and commencing tasks proved too long for the named Team Leader, Andrew
Mclernon, who accepted another position. Andrew will be replaced by Malcolm Ehrlich.
2. On intial review of all available data, PISC realised that the number of key personnel actually
required to deliver the design would be greater than that proposed in the RFP. Whilst
preparing a comprehensive Addendum, PISC needed to identify all positions and attain signed
cvs and payment proof which is requirement by CPMU in order to sign off the Addendum.
3. Based on previous projects, the PISC have experience in mobilising International Experts to
Indonesia and the minimum time normally allowed for HR to process visas can be two months.
There are a mixture of key personnel on the project from UK, Phillippines and Australia. Staff
from Phillippines have an additional requirement to receive an Overseas Employment
ADB Loan 3123-INO: Metropolitan Sanitation Management Investment Project
Quarterly Report No. 1, February 2018 4
Certificate (EOC), from Phillippines as well as going through the necessary process’s in
Indonesia. Process’s in Phillippines these International Countries were also affected by the
Christmas holidays.
The project mobilisation is beginning to show signs of improvement with Social Safeguard and Genders
and Social Development Experts expected in January. This should also coincide with agreement of the
Addendum.
1.5 Look Ahead
The following activities are expected to be implemented as deailed under the Project Schedule in the
next quarter between 2nd January 2018 and 2nd April 2018.
Topographical Surveys for sites where required
Geotechnical Investigations for sites where required
Continuation and finalization of cost estimates for Makassar Contracts C to allow Satker
Makassar to launch prequalification
Continuation of detailed design for Makassar Contract C
Preparation of General Specifications associated with all National Contracts related to the
project
Preparation of the Tender Documents for Makassar Contract C
Preparation of Drawing Packages associated with Makassar Contract C
Detailed Design for the networks associated with Pekanbaru
Initial review on Social Safeguards and Resettlement
Initial review on Gender and Social Development
Initial review of the Environmental Status of the project
Continue recruitment of staff in accordance with the Contract and with he Addendum 1 when
approved
ADB Loan 3123-INO: Metropolitan Sanitation Management Investment Project
Quarterly Report No. 1, February 2018 5
2 Acronyms and Abbreviations
ADB Asian Development Bank
ADF
APBD
Asian Development Fund
Anggaran Pendapatan dan Belanja Daerah/Regional Government
Budget
APBN Anggaran Pendapatan dan Belanja Negara/ National
Government Budget
AusAid Australian Agency for International Development
BLH Biro/Badan Lingkungan Hidup/Environmental Agency
BLUD Badan Layanan Umum Daerah/Regional Public Service Agency
CBD Central Business District
CDTA Capacity Development Technical Assistance
CEMP
CPMU
Contractor’s Environmental Management Plan
Central Project Management Unit
CSS City Sanitation Strategy
DAK Dana Alokasi Khusus/Special Allocation Fund
DAU Dana Alokasi Umum/General Allocation Fund
DD
DED
Due Diligence
Detailed Engineering Design
DESD
DFAT
Directorate of Environmental and Sanitation Development
Department of Foreign Affairs and Trade (Australia), formerly
AusAid
DGHS Directorate General of Human Settlements (Cipta Karya)
DKK Dinas Kebersihan Kota/City Sanitation Agency
DMF Design and Monitoring Framework
EA
EIA
EMP
FOPIP
GIS
Executing Agency
Environmental Impact Assessment
Environmental Management Plan
Financial and Operating Performance Improvement
Geographic Information System
GoI Government of Indonesia
HH
IMB
Household
Ijin Mendirikan Bangunan/Building Permit
IndII Indonesia Infrastructure Initiative
ICB
IEE
INDII
WWTP
International Competitive Bidding
Initial Environmetal Examintation
Indonesian Infrastructure Initiative
Instalasi Pengolahan Air Limbah/Wastewater Treatment Plant
IPLT Instalasi Pengolahan Lumpur Tinja/Septage Treatment Plant
IUWASH Indonesia Urban Water, Sanitation and Hygiene Project (United
States International Agency for Development)
LARAP
LIBOR
Land Acquisition and Resettlement Action Plan
London Interbank Offered Rate
ADB Loan 3123-INO: Metropolitan Sanitation Management Investment Project
Quarterly Report No. 1, February 2018 6
LPMU Local Project Management Unit
MIS Management Information System
MLD
MOF
MOHA
Megalitres per Day
Ministry of Finance
Minster of Home Affairs
MPWH Ministry of Public Works and Housing
MSMHP Metropolitan Sanitation Management and Health Project
MSMIP Metropolitan Sanitation Management Investment Project
NCB
NGOs
O&M
National Competitive Bidding
Non Government Organization
Operation and Maintenance
PAM Project Administration Manual
PIU Program Implementation Unit
PISC Project Implementation Support Consultant
PPMU Provincial Project Management Unit
POKJA Kelompok Kerja/Working Group PPLP
PPLP Direktorat) Pengembangan Penyehatan Lingkungan Pemukiman/
Directorate of Environmental Sanitation Development,
Directorate General of Human Settlements, Ministry of Public
Works and Housing
PPP Public Private Partnership
PPSP Program Percepatan Sanitasi Permukiman/Acceleration of Urban
Sanitation Development Program
PPTA Project Preparation Technical Assistance
PROLEGDA Program Legislasi Daerah/Local Legislation Procedure
PUPR Ministry of Public Works and Housing (Kementerian Pekerjaan
Umum dan Perumahan Rakyat)
PSC
sAIIG
Project Support Consultants
Australia Indonesia Infrastructure Grants for Sanitation
SANIMAS Program Sanitasi Berbasis Masyarakat/Community Based
Sanitation Program
SATKER Satuan Kerja/Work Unit
SDO Service Delivery Organization
SPS
SOP
Safeguards Policy Statement
Standard Operational Procedure
SSK Strategi Sanitasi Kota/City Sanitation Strategy
UPTD Unit Pelaksana Teknis Daerah/Local Government Technical
Implementation Unit
USRI Urban Sanitation and Rural Infrastructure Support to PNPM
Mandiri Project (ADB funded)
WA
WWTP or WWTW
Withdrawal Application
Wastewater Treatment Plant or Works
ADB Loan 3123-INO: Metropolitan Sanitation Management Investment Project
Quarterly Report No. 1, February 2018 7
3 Introduction and Basic Data
3.1 Purpose of the Report
The Quarterly Report is a statement of work carried out during the progress phase of the MSMIP PISC.
The report covers the period from October 2nd up to the 31st December 2017. This Report describes
the progress of the PISC who are contracted to provide design and construction services to the project
that focus on sewerage systems in the business districts in Jambi, Makassar and Pekanbaru. The design
and construction includes Environmental, Social and Safeguards, Gender Planning and Resettlement
aspects of the works during its implementation. The report also provides the Directorate General of
Human Settlements (DGHS), with an insight into how the Project Implementation Support Consultant
(PISC) plans to implement the works under the Contract based on their progress and findings. The
Quarterly report has been developed following reviews of current information available from the
Makassar, Jambi and Pekanbaru, meetings with the Client and other stakeholders, site visits, research
and actual progress.
3.2 Brief Description of Project
3.2.1 Rationale
Indonesia has one of the lowest coverage rates of conventional off-site urban sewerage in Asia. Only
11 out of its 330 cities have partial sewerage systems, and only 2% of the national urban population
is connected to central WWTPs; the remaining urban population depends on poorly constructed and
maintained septic tanks and unlined pit latrines, which result in leachates penetrating the aquifers.
Some 80% of grey water drains directly to surface waters. The MSMIP project will provide urban
wastewater services in the cities of Jambi, Makassar and Pekanbaru. These cities currently lack any
piped sewerage or wastewater treatment facilities and current arrangements to provide such services
are not suitable, due to inadequate and poorly enforced regulations. This results in limited desludging
of septic tanks, inadequate septage treatment facilities, and fragmented operational responsibility.
The project will respond to the needs of urban communities (including low-income households) by
constructing new separate sewerage systems and wastewater treatment plants (WWTPs), setting up
local wastewater infrastructure management institutions, and strengthening the relevant regional
government departments. The project will respond the needs of urban communities that are
inadequate and un-integrated, due to inadequate and poorly enforced regulations. This results in
limited de-sludging of septic tanks, inadequate septage treatment facilities, and fragmented
operational responsibility. Improved access to safe water and basic sanitation is part of the
Government of Indonesia’s effort to achieve its 2015 Millennium Development Goal (MDG) targets.
While the government’s MDG reports suggest that good progress has been achieved with respect to
sanitation, in practice the available facilities are substandard, and rely on unsustainable septage
removal and treatment facilities. As a result, there is significant environmental pollution, widespread
contamination of surface and groundwater with the associated spread of water-related diseases and
high infant mortality. The inadequate sanitation systems and their resulting environmental and health
impacts produce economic opportunity losses of about USD 5.6 billion annually, equivalent to 2.3% of
the country’s gross domestic product. These issues can be solved by the development of the public
sewerage and wastewater treatment facilities, arise of the awareness of the public sanitation practice,
establishing an organization for wastewater management in which its management and maintenance
should be operated effectively. The MSMIP will support the Government of Indonesia in the
ADB Loan 3123-INO: Metropolitan Sanitation Management Investment Project
Quarterly Report No. 1, February 2018 8
improvement of urban wastewater services in the cities of Jambi, Makassar, and Pekanbaru, which
currently lack any pipes sewerage and wastewater treatment facilities for the needs of urban
communities (including low-income households) by constructing new separate sewerage systems and
wastewater treatment plants (WWTPs).
3.2.2 Design Status
The Detailed Design of the wastewater treatment plants and sewerage networks have been prepared
by other consultants, namely MWH, Perancang Adhinusa and Dwikarsa Envacotama for the three
cities, which currently is further being reviewed by the PISC. Following review, the PISC will make
changes where necessary and provide a robust design that can be tendered either by using
International Competitive Bidding (ICB) or National Competitive Bidding (NCB) processes. The
tendering process has been defined based on the contracts for the Wastewater Treament plant/WTP,
Wastewater sewer system/WSS which will be budgeted for through an ADB loan , and funds from
Central Government and local Government . Once the design and tender documents are prepared
accordingly, they can be tendered and the Construction phase can commence. The PISC will provide
construction supervision of the development of the sewerage systems for Jambi, Makasar and
Pekanbaru.
ADB Loan 3123-INO: Metropolitan Sanitation Management Investment Project
Quarterly Report No. 1, February 2018 9
Figure 3.1 Project Locations of MSMIP
Makassar
Pekanbaru
Jambi
Jakarta
ADB Loan 3123-INO: Metropolitan Sanitation Management Investment Project
Quarterly Report No. 1, February 2018 10
3.2.3 Impact and Outcome
There are many positive impacts and outcomes to the implementation of the MSIMP project that will
provide environmental, sustainable, social and economic improvements over the current
arrangements. These include
reduced pollutant discharges to water courses and ground
reduced health risks
reduced odours and visual impact
employment propspects at the plant and on the netwroks for the Operation and
Maintenance period
removal of open sewers
It is important to note that the positive outcomes will only be realised through education and social
integration. Without programmes to encourage the local communities of the positive impact of the
new sewerage syatem, some actual outcomes may be negative. Such as failure to make the necessary
connections required for the sewerage system to function adequately and failure of operate and
maintain the system as necessary.
3.2.4 Outputs
The MSMIP has the following two outputs:
Output 1: Infrastructure development for off-site wastewater systems completed.
Construction of approximately 470 kilometres (km) of trunk and main sewers, secondary,
lateral and tertiary sewers. About 44,300 sewer connections and four WWTPs with a total
installed capacity of 51,700 cubic meters per day (m3/d), and with provision for future
expansion 10 will also be constructed. At least 10% of the connections (and associated service
charges)—for poor households, households headed by women, and other vulnerable groups
will be subsidized, and 64 community-based sanitation systems will be installed in non
sewered areas serving low-income families. These systems will be directly funded by local
government budgets.
Output 2: Project implementation support institutionalized.
The capacity of the executing and implementing agencies will be strengthened through
provision of management support and training in (i) procurement and construction
supervision; and (ii) design and commissioning of sewerage systems. TA for institutional
development and management and capacity building support for sustainability will be
implemented separately. This will include development by the government of public
sanitation awareness campaigns that seek to build appreciation and understanding of the
benefits of sewerage systems and the need for adequate charges to ensure that they remain
fully operational and correctly maintained.
3.2.5 Coverage
The MSMIP responds to the needs of these urban communities, including low-income households, by,
developing new systems, improving governance and building local institutional capacity for
community-based and government-owned wastewater service providers and the regional
governments. The MSMIP subprojects in Jambi, Makassar and Pekanbaru will be funded by ADB. These
tree cities will be covered by the PISC. The MSMIP will support the Government of Indonesia in the
ADB Loan 3123-INO: Metropolitan Sanitation Management Investment Project
Quarterly Report No. 1, February 2018 11
improvement of urban wastewater services in the cities of Jambi, Makassar and Pekanbaru, which
currently lack any pipes sewerage and wastewater treatment facilities. The MSMIP subprojects are to
provide public sewerage systems and wastewater treatment to serve the Central Business Districts
(CBD) in the Cities of Jambi, Makassar, Palembang and Pekanbaru. In each city, the housing areas
adjacent to the CBD and along the routes of the trunk sewers to the WWTPs will be connected to the
sewerage system.
Table 3-1 The MSMIPP Project Coverage to be Implemented
No Description Units Pekanbaru Jambi Makassar
1 Connections
Domestic unit 9,900 8,900 6,900
Commercial unit 1,100 1,400 4,100
2 Sewer Km 130 103 115
3 WWTP
Capacity MLD 8.1 7.6 16.1
Area Ha 8.0 6.0 6.0
Technical Assistance for institutional development and management and capacity building support for
sustainability will be implemented separately. This will include development by the government of
public sanitation awareness campaigns that seek to build appreciation and understanding of the
benefits of sewerage systems and the need for adequate charges to ensure that how the sewerage
system that will have been built can run in accordance with its function and managed properly and
correctly so that this system can operate continuously.
ADB Loan 3123-INO: Metropolitan Sanitation Management Investment Project
Quarterly Report No. 1, February 2018 12
Figure 3.2 Service Areas and Catchment of Jambi Wastewater Offsite System
ADB Loan 3123-INO: Metropolitan Sanitation Management Investment Project
Quarterly Report No. 1, February 2018 13
Figure 3.3 Service Areas and Catchment of Pekanbaru Wastewater Offsite System
ADB Loan 3123-INO: Metropolitan Sanitation Management Investment Project
Quarterly Report No. 1, February 2018 14
Figure 3.4 Service Areas and Catchment of Makassar Wastewater Offsite System
3
8. All work financed by the government-owned funding will also be supervised by the project implementation support consultant, which as of May 2016 was being recruited. Work in service areas financed by the government will be implemented in the same time with those financed under the loan proceeds, as part of the project scope.
Figure 1: Service Area and Catchment (Jambi)
Figure 2: Service Area and Catchment (Makassar)
ADB Loan 3123-INO: Metropolitan Sanitation Management Investment Project
Quarterly Report No. 1, February 2018 15
3.3 Basic Data
3.3.1 Loan Amount
The government of Indonesia has received a Loan that was approved on 31 March 2014 with funding
through ADB amounting to USD 120.00 million, in which;
USD 80.00 million is from The Ordinary Capital Resources /OCR – No.3123 INO
USD 40.00 million is from ASEAN Infrastructure Fund /AIF – No.8280 INO.
The ADB Loan will have a 17 – year term, including a grace period of 7 (seven) years , an annual
interest rate determined in accordance with ADB’s rate LIBOR with commitment charge of 0.15 % per
year and such other terms and condition set forth in the loan agreements. The loan agreements were
signed on 13 May 2014, declared effective on 9 July 2014, and scheduled for closing on 31 December
2020. Project MSIMP will be implemented in three cities: Makassar, Pekanbaru, Jambi, whereas
Cimahi City, originally a part of the scheme, had been deleted due to land issues.
The Government of Australia had also allocated USD 48.83 million to develop the urban wastewater
of Palembang City only. The ADB loan (Loan A) OCR and the ADB loan (Loan B) AIF will have the same
term, grace period and repayment schedule. The Loan A proceeds will finance civil works of the
wastewater treatment plant and equipment of Jambi, Makassar, and Pekanbaru. The Loan B will fund
the civil works and equipment of the wastewater sewer collection and transfer system of Pekanbaru
and Jambi. The Central Government of Indonesia will provide USD 98.15 Million, including Palembang
City (USD 25.63 million) and the remaining fund to finance the project, including property connections
and consultant services for Jambi, Pekanbaru, Makassar city. In this case, the central government also
have budgeted funds for financial Charges during implementation estimated at USD 8.76 million. The
local Government will provide USD 55.60 million, including Palembang City (USD 24.20) to finance land
acquisition and preparation (earthworks at WWTP and pump station location), house connections and
also involuntary resettlement. The local governments /City have been and each is undertaking the
obligation to carry out land acquisition. The contribution of local government to finance the project
all will be applied the terms of Taxes and Duties.
3.3.2 Project Cost
The original total project budgets were prepared based on the results of the PPTA that the originally
estimated at USD 310.09 million for 4 cities Jambi, Makassar, Pekanbaru and Palembang. The
government of Australia has also allocated USD 48.33 million for the construction works only
associated with the city of Palembang.
The updated totals of the project cost amounted to USD 223.84 million, which consisted of ADB OCR
funds amounting to USD 80.00 million (35,74%), ADB AIF funds to USD 40.00 million (17,87%) , the
central government funds USD 72.52 million (32,40%) and the remaining funds will be financed from
the city government own revenue of USD 31.23 million (14,00 %)
The detailed project cost of MSIMP that will be financed from various sources—ADB Ordinary Capital
Resources (OCR), ADB ASEAN Infrastructure Fund (AIF), Central Government and City Governments of
Jambi, Makassar, and Pekanbaru by expenditure category are provided in Table 3-2.
ADB Loan 3123-INO: Metropolitan Sanitation Management Investment Project
Quarterly Report No. 1, February 2018 16
Table 3 - 2. Detailed Cost Estimate – Revised in USD Million
Description ADB Government
Total OCR AIF Central Local
A. Investment Cost
1. Land Acquisition and Site Preparation
-
-
-
11.55
11.55
Sub Total 11.55 11.55
2. Civil Works
A. Jambi
- Waste Water Treatment Plant/ WWTP
- Wastewater Sewer System/ WSS –West
- Wastewater Sewer System/ WSS –East
- Property Connection
- Community - based System
14.75
-
-
-
-
-
19.30
-
-
-
-
-
14.36
0.50
-
-
-
-
4.95
0.88
14.75
19.30
14.36
5.45
0.88
Sub Total 14.75 19.30 14.86 5.83 54.74
B. Makassar
- Waste Water Treatment Plant/ WWTP
- Wastewater Sewer System/ WSS –C
- Wastewater Sewer System/ WSS –NW
- Property Connection
- Community - based System
27.20
13.40
-
-
-
-
-
-
-
-
-
-
24.31
0.50
-
-
-
-
5.06
1.10
27.20
13.40
24.31
5.56
1.10
Sub Total 40.60 - 24.81 6.16 71.57
C. Pekanbaru
- Waste Water Treatment Plant/ WWTP
- Wastewater Sewer System/ WSS –N
- Wastewater Sewer System/ WSS –S
- Property Connection
- Community - based System
12.90
-
-
-
-
-
20.70
-
-
-
-
-
22.44
0.44
-
-
-
-
4.95
1.10
12.90
20.70
22.44
5.39
1.10
Sub Total 12.90 20.70 22.88 6.05 62.53
3. Consulting Services
- PISC – ADB
- Central Government
- Local Government
11.75
-
-
-
-
-
-
0.44
-
-
-
0.19
11.75
0.44
0.19
Sub Total 11.75 - 0.44 0.19 12.38
4. Recurrent Cost
- Project Management by Government
- Project Management by Local Government
-
-
-
-
0.77
-
-
1.54
0.77
1.54
Sub Total - - 0.77 1.54 2.31
5. Financial Charge During Construction
- Interest during Construction
- Commitment fee
-
-
-
-
8.44
0.32
-
-
8.44
0.32
Sub Total - - 8.76 - 8.76
Grand Total 80.00 40.00 72.52 31.32 223.84
Based on PAM –Revised -Nov-2016 ( PN 43251-025 )
ADB Loan 3123-INO: Metropolitan Sanitation Management Investment Project
Quarterly Report No. 1, February 2018 17
3.3.3 Executing Agency
The Directorate General of Human Settlement (DGHS) in the Ministry of Public and Housing/PUPR are
the Executing Agency (EA). The EA / DGHS task is to coordinate various project tasks as a focal unit for
coordination with ADB, as well as external Government offices whose endorsement or approval and
monitoring activities are mandated by existing policies or Law. The EA has appointed the Central
Project Management Unit (CPMU) as a Unit to;
(i) be responsible for the overall project implementation, including project supervision,
monitoring, accounting, and consolidated report;
(ii) submit withdrawal application to ADB , including retention of any supporting documents.
The central Satker/CPIU is a Work Unit which is part of an organizational unit at the
Ministry/Institution performing one or several activities of a program, including selection, contracting
and supervision of implementation consultant. At the province level a Provincial Project Management
Unit (PPMU) has been established, appointed by Governor. At City level a Local Project Management
Unit (LPMU) has been established, appointed by the Mayor of city. Each institution involved sas full-
time counterpart staff to coordinate implementation activities at provincial and City level. For the
management of the ADB loan fund, it has been determined by the decision of the PUPR minister of an
official / Satker and the organizational personnel of the Provincial Public Works Office (PPIU) are to to
be responsible for the management of the MSIMP project in the cities of Jambi, Makassar and
Pekanbaru. The duties of Satker include;
(i) taking full responsibility for the planning and implementation of all aspects and
components under the project MSIMP in each Cities;
(ii) closely monitoring construction progress;
(iii) provide signing contract and supervision of the contract implementation.
For the control and responsibilities of the project activities, PPIU (under Satker) are responsible for
the issuance of payment to the Third parties by using direct payment mechanism. The PICS’s services
are required to support the central project management Unit (CPMU), Provincial and City Project
management Unit (PPMU and LPMU) and Project Implementation Unit (PPIU/LPIU).
ADB Loan 3123-INO: Metropolitan Sanitation Management Investment Project
Quarterly Report No. 1, February 2018 18
Figure 3.5 Project Organization Structure of MSMIP
The Ministry of Public Works and Housing, Directorate General of Human Settlements (DGHS) is the
Executing Agency (EA) for the MSMIP. DGHS will establish a Central Project Management Unit (CPMU)
composed of technical and administrative staff from Directorate of Environmental and Sanitation
Development (DESD). A Senior Officer of the DESD heads the CPMU.
ADB Loan 3123-INO: Metropolitan Sanitation Management Investment Project
Quarterly Report No. 1, February 2018 19
Agency Key Persons
Executing Agency :
Directorate General of Human
Settlements
Ministry of Public Works and Housing
Officer's Name : Dwityo A. Soeranto Position : Director of the Integration of Settlement Infrastructure Telephone : +62-21 72796588 Email address : [email protected] Office Address : Jl. Pattimura 20, Kebayoran Baru Jakarta Selatan 12110 Indonesia Officer’s Name Designation : Doddi Krispratmadi Position : Director of Environmental Sanitation Development Telephone: +62-21 72797175 Office address : Jl. Pattimura No. 20 Jakarta Email address : [email protected]
CPMU :
Directorate of Environmental and
Sanitation Development
Directorate General of Human
Settlement, MPWH
Officer’s Name : Asri Indiyani Position : Head of CPMU Telephone : +62-21 72797175 Email address : [email protected]
PPK PISC MSMIP:
Directorate of Environmental and
Sanitation Development
Directorate General of Human Settlement, MPWH
Officer’s Name : Larap K. Estu Position : PPK Wastewater Telephone : Email address :
Satker PS-PLP Province of Riau
(PPIU)
Directorate of Environmental and
Sanitation Development
Directorate General of Human Settlement, MPWH
Officer’s Name : Afrizal K Position : Head of Satker Address :Jl. SM Amin no 9A, Simpang Buru, Tampan Pekanbaru Telephone :
Satker PS-PLP Province of Jambi
(PPIU)
Directorate of Environmental and
Sanitation Development
Directorate General of Human Settlement, MPWH
Officer’s Name : Eka Prasetiyawaty Position : Head of Satker Address : Jl. H. Agus Salim No.2 Kota Baru, Jambi Telephone :
ADB Loan 3123-INO: Metropolitan Sanitation Management Investment Project
Quarterly Report No. 1, February 2018 20
Satker PS-PLP Province of Sulawesi
Lelatan (PPIU)
Directorate of Environmental and
Sanitation Development
Directorate General of Human Settlement, MPWH
Officer’s Name : Antonius Pongsilurang Position : Head of Satker Address : Jl. Jenderal Urip Sumohardjo, Panaikang, Makassar Telephone : 0411 - 441797
3.4 Key Dates
The loan agreements were signed on 13 May 2014, declared effective on 9 July 2014, and scheduled
for closing on 31 December 2020. A table of Project key dates are provided in Table 3-3.
Table 3-3 Projects Description - Loan ADB
No Description ADB – OCR Loan ADB – AIF Loan
1 Loan Number ADB L 3123- INO ADB L 8280 - INO
2 Project Number 43251 – 025 43251 - 025
3 Total Loan $ 80 million $ 40 million
4 Signed Loan 13-May-14 13-May-14
5 Effective loan 09-Jul-14 09-Jul-14
6 Closing date 31-Dec-20 31-Dec-20
7 Method of Payment Special Account Special Account
8 No Special Account N/A N/A
9 Amount of Initial Deposit N/A N/A
10 Project Location
Implemented
3 ( three )
Local Government
2 ( two )
Local Government
a. Jambi City a. Jambi City
b.Makasar City b.Pekanbaru City
c. Pekanbaru City
14 Executing Agency The Directorate General of Human Settlements , Ministry of
Public Works
14 Institutions Involved
a. Central Goverment DGHS,CPMU,CPIU
b. Provincial Goverment PPMU,PPIU
c. Local Govenment LPMU,LPIU
ADB Loan 3123-INO: Metropolitan Sanitation Management Investment Project
Quarterly Report No. 1, February 2018 21
3.5 Other Relevant Information
3.5.1 Project Proposed Changes
During appraisal by ADB and EA in 2013, the costs for wastewater collection and treatment
infrastructure (civil works, including property works) were estimated at $203.0 million. In 2015, the
preparation and reviews of DEDs for the project cities were completed. Cost estimates in the DEDs
increased to $267.2 million, 32% higher than appraisal costs, because:
a. the DEDs measured the length of tertiary and lateral sewers more accurately,
b. the WWTPs required more structural engineering content to meet the constraint of the sites
selected and the higher quality of effluent discharge requested by the participating cities,
c. greater site preparation and stabilization costs at the WWTP sites are required, and
d. greater depths for the sewers are required. Consequently, the available loan proceeds of $120
million will no longer be sufficient to meet the project scope agreed during appraisal.
To address the issues, the government requested to increase its share and reduce the project scope
by lowering:
a. The number of cities covered under the project, The ADB and EA considered removing Cimahi
City from the proposed plan, in mid-2015 because of issues related to acquiring the land for
the current WWTP location. The mission statement read that keeping Cimahi will further delay
project implementation because it would take at least 1 year to acquire the land and revise
the DED since topography and geotechnical data will need to be collected
b. The capacity of the WWTPs, Capacities of the other WWTPs will also be adjusted. As a result,
the overall WWTP capacity proposed will decrease from 83.0 megaliters per day to 51.7
megaliters per day
c. the number of connections. The service areas was reducing (number of connections) and
finance only the areas that are considered having strong service demand. This change will
reduce the number of property connections to the central sewerage systems by about 46%,
from 82,900 to 44,300.
Table 3 – 4 Summary of Changes in Treatment Plant Capacity and Property Connections1
Item Wastewater Treatment Plant Capacity (megaliter per day)
Cimahi Makassar Jambi Pekanbaru Palembang Total
Current 11.1 19.1 15.0 14.7 23.1 83.0
Proposed Change 0.0 16.0 7.6 8.1 20.0 51.7
Property Connections by City
Cimahi Makassar Jambi Pekanbaru Palembang Total
Current 9,800 14.400 20,200 17,200 21,300 82,900
Proposed Change 0 11,000 10,300 11,000 12,000 44,300
1 Major Change in Project : Project Number: 43251-025Loan Numbers: 3123-INO and 8280-INO December 2016, Metropolitan
Sanitation Management Investment Project
ADB Loan 3123-INO: Metropolitan Sanitation Management Investment Project
Quarterly Report No. 1, February 2018 22
4 Utilization of Funds
4.1 Contract Awards (actuals this quarter, annual and overall project)
The procurement of goods, works and consulting services shall be subject to and governed by the
procurement guidelines and consulting Guidelines, respectively. The methods procurement of MSIMP
will use the following methods;
(i) International Competitive Bidding
(ii) National Competitive Bidding
The Packages of Civil Works will be procured through International Competitive Bidding (ICB)
procedures exceeding USD 25.0 million and for goods will be procured by ICB exceeding USD 5.0
million. In relation to National Competitive Bidding (NCB) procedures, these must be acceptable to
ADB’s provisions for procurement of physical works and goods within their respective limits.
Procurement of goods amounting to equivalent of USD 100 thousand or less may be procured through
shopping.
If packages are to be split into smaller packages , the split should be solely on geographical or practical
basis .The conditions for award of contract , where the Government as borrower shall award any works
contract until obtaining the clearance from ADB of the relevant IEE (Initial Environmental Examination
). Before the commencement of any procurement, ADB and the Government will review the public
procurement laws to ensure consistency with ADB procurement Guide lines (in 2015, as amended
time to time). The PCA (procurement capacity Assessment) undertaken by PPTA consultant
identifying related to the Satker’s procurement capacity in terms of;
(i.) Organization and staff capacity
(ii.) Information management
(iii.) Procurement practices
(iv.) Performance effectiveness
(v.) Accountability measures.
(vi.) Accountability measures.
Table 4-1 describes the types and packages of procurement distinguished by project investment of
the estimated goods and works contracts for which procurement is either on going or expected to
commence in 2017 and the next fiscal year 2018 :
Table 4-1 Description of MSMIP of Estimated Contract
City
Location
Name of Contract &
Source of Loan
Value
(million
USD)
Proc
Method Description
Pekanbaru 1. Contract A
APBD Kota Pekanbaru
NCB Site Preparation (land clearing,
land maturation and fences)
2. Contract B
ADB Loan 3123 – INO -
12.90 NCB The construction of WWTP
3. Contract C-1
ADB Loan 8280 – INO -S
20.70 NCB The construction of sewage and
wastewater collection system -N
4. Contract C-2
APBN FY. 2017–2020
22.88 NCB The construction of sewage and
wastewater collection system
ADB Loan 3123-INO: Metropolitan Sanitation Management Investment Project
Quarterly Report No. 1, February 2018 23
City
Location
Name of Contract &
Source of Loan
Value
(million
USD)
Proc
Method Description
(North catchment) – S and
property connection
5.Contract APBD Kota
Pekanbaru – FY 2017-2020
6.05 NCB Property Connection and
Community –based System
Jambi 1.Contract A
APBD Kota Jambi
NCB Site Preparation (land clearing,
land maturation and fences)
2.Contract B
ADB Loan 3123 – INO
14.75 NCB The construction of WWTP
3.Contract C – 1
ADB Loan 8280 – INO
19.30 NCB The construction of sewage and
wastewater collection system
(West catchment)
4. Contract C- 2
APBN FY. 2017–2020
14.86 NCB The construction of sewage and
wastewater collection system
(East catchment) and property
connection
5.Contract APBD Kota Jambi FY
2017-2020
5.83 NCB Property Connection and
Community –based System
Makassar
1.Contract A
APBD Kota Makassar
NCB
Site Preparation (land clearing,
land maturation and fences)
2.Contract B
ADB Loan 3123 – INO
40.60
ICB
The construction of WWP and
sewerage collection system - C
3.Contract C
APBN FY. 2017–2020
24.81
NCB
North–West Waste Water
Collection System, Transfer
System A, and Pressure Main
4.Contract APBD Kota Jambi FY
2017-2020
6.16 NCB Property Connection and
Community –based System
Consulting
Services
1. PISC
2. Central Government
3. Local/City Government
11.75
0.44
0.19
NCB
NCB
NCB
It Has been Contracted in 2017
N/A
N/A
Source : MSMIP PAM (Revised), November 2016
4.2 Loan Withdrawal and Disbursement
The Loan proceeds will be disbursed in accordance with ADB’s disbursement regulation and detailed
arrangements agreed upon by the Government and ADB. The ADB funds may not be applied to the
prohibited activities. The disbursement of Loan ADB for Consulting services and Civil Works
implemented by under international and national bidding will be directly payment through direct
payment procedures. The utilization and payment of the ADB loan is to finance eligible expenditures,
which mainly consist of civil works contracts by constructing new separate sewerage systems and
wastewater treatment plants (WWTPs). These works have not yet shown any significant progress in
year 2017. In addition, the contract for civil works in cities of Jambi, Makasar, and Pekanbaru in 2017
have not been realised yet. The utilisation of funds in fiscal year of 2017 was only for the consultant
PISC Contract. Of the USD 11.75 million allocation of ADB –OCR Loan to consultant, a total of USD
4.60 million and in IDR 60.billion has been contracted and USD 976.2 thousand and in IDR 9.10 billion
disbursed. The contracts begin effective from 11 September 2017 until 31 October 2020 with issuing
ADB Loan 3123-INO: Metropolitan Sanitation Management Investment Project
Quarterly Report No. 1, February 2018 24
withdrawal application for 39 stages. In connection with the construction work that will be done in
2018 the civil work in the city of Makassar which is most likely, while for Jambi and Pekanbaru is still
in the process stage which is constrained by land ownership. The use of funds from the loan is still low.
From the total loan ADB USD 120.00 million absorbed only as much as USD 9.21 billion or 7.67% has
been used. Related to this, the absorption of funds for construction work is important. There are
number factors needed to be prepared and solved immediately that will impact the breakup of
contracts under the project. At the time of proposal it was understood that the contracts were split in
the following manner and this applied to each city ;
(i) Contract A – earth works
(ii) Contract B – WWTP and part of the networks
(iii) Contract C – part of the network only.
However following PISC review, it is understood that these contracts should be better prepared in
accelerating the implementation of construction work immediately.
4.3 Projection vs Actual Achievement
Regarding the land acquisition required for WWTP site and the access road to WWTP in Jambi,
Makasar, and Pekanbaru it was reported that completion would be by the end of 2016. The city
confirmed that the land acquisition has been conducted in accordance with the resettlement plan
prepared in 2013. The Budget for purchasing of the land had been included in the each city annual
Budget. ADB will be carry out due diligence of land acquisition implementation. The PISC consultants
need to obtain documents of proof of payment for land ownership to be used on MSMIP projects that
have been issued by their respective municWWTP governments. In preparing a budget plan, local
government are waiting for the completion of the pland from PISC to show the WWTP footprint. The
plans are being prepared by the PISC consultant but the actual WWTP processe are in question due to
new discharge standards that were released in 2016 after the design completion and the poor quality
of the exisiting plant drawings.
A Bidding Committee in accordance with the regulation is not yet established, Implementation of the
Bidding becomes longer so the project will delay and costs will overrun. The number of eligible
committees at provincial level cannot be fulfilled. Some committees have reasonable procurement
capacity but no experience with ADB. This problem may lead to the project having additional costs,
schedule delays, poor quality delivery and a final result that is not acceptable. The consequences in
this case, the request for payment to the ADB shall be deemed ineligible expenditure in the event of
procurement process and procurement documents are not feasible to be financed by ADB Loan.
ADB Loan 3123-INO: Metropolitan Sanitation Management Investment Project
Quarterly Report No. 1, February 2018 25
5 Implementation Progress
5.1 General
On October 2nd 2017, the Project Implementation Support Consultant (PISC) for the project - Loan
No. 3123-INO. Metropolitan Sanitation Management Investment Project – were appointed by
Directorate of General Housing Settlement (DGHS) to undertake tasks listed under Contract
HK.02.03/MSMIP-KONS/X/11/2017. The PISC consists of lead Consultant SMEC International Pty Ltd
in joint venture with Stantec Australia Pty Ltd (ex-MWH) and in association with the following firms
as sub-consultants: PT. Infra Tama Yakti (ITY), PT. SMEC Denka Indonesia, PT. Amurwa International
and PT. Widya Graha Asana (WGA).
The Contract will run from October 2nd 2017 to January 2nd 2021 which is a 40 month period which
is a reduction to the 48 month period defined in the RFP. The Contract end date coincides with the
ADB Loan Agreement expiry date of 31st December 2020.
The progress during the first three months of the project has been a mixture of mobilising, planning
and implementation. At the end of November the PISC Consultant prepared an Inception Report that
outlined a stage of data gathering, initial analysis and planning. The Consultant will continue the
project based on the Schedules issued with the Inception Report.
The PISC identified that the design inputs required by the project were greater than that described in
the RFP based on a number of issues some of which are defined below;
1. Earthwork Contracts associated with the three cities has not progressed as expected. The
release of Contract B associated with the WWTP, is reliant on the Earthworks Contracts being
completed;
2. Discharge standards of wastewater to water courses were changed in mid 2016 following the
completion of the designs. The new discharge standards mean that Pekanbaru and Jambi will
require re-design. This is coupled with poor drawing sets for the WWTP on both these schemes
which will require additional effort to provide adequate information for construction;
3. Jambi network drawings are very poor and PISC will provide an observation report in January
that is expected to recomend a re-design is required;
4. Makassar is the only city where contract documents are complete, yet all contract documents
are in English. Only Contract B is to be written as an International Contract. Contract C which
are the network contracts, are to be developed based on National requirements and will
therefore be prepared in Indonesian Bahasa based on local standards;
5. There are unresolved land issues at a number of sites including :
o pump station site in Jambi which has been designed in a middle of a housing
settlement with limited access/egress where extensive land requirements and
resettlement will be required;
o half WWTP site at Makassar is under dispute with locals this remains unresolved;
o permit has been given for a car park on the location of pump station A in Makassar;
o the pump station at Pekanbaru could be located in a better position on the opposite
side of the river than is currently planned.
ADB Loan 3123-INO: Metropolitan Sanitation Management Investment Project
Quarterly Report No. 1, February 2018 26
6. Ground conditions at WWTP sites are very poor. Geotechnical Information at Makassar can
be used to understand the necessary works required to develop the site earthworks.
Information from Pekanbaru and Jambi is insufficiuent and hence extra studies are required;
7. Topographical information for sewer lines in Jambi is inaccurate and a physical survey will
be required to resolve the issue. Although Pekanbaru survey is better, a topographical survey
is recomended to eliminate any incorrect levels;
PISC are currently reviewing designs based on populations/house connections. It is noted that the ADB
produced a ‘Major Change in Project’ report in December 2016. The report highlighted a reduction to
the capacity of the WWTP and the number of house connections. Designs have not been changed
since the report was issued hence the PISC review will include;
1. Assessment of the extent of the network and if it is necessary to install the length of pipe
designed;
2. Assessment of pipe sizing/hydraulics to understand if the capacity of the pipe and depth of
installation could be reduced.
The summary of changes highlighted in the document are given in Tables 5-1 and 5-2 below.
Table 5-1 Summary of Changes in Treatment Plant Capacity
Item Wastewater Treatment Plant Capacity (MLD)
Makassar Jambi Pekanbaru
Current 19.1 15.0 14.7
Proposed 16.0 7.6 8.1
Table 5-2 Summary of Revised Property Connections to the Central Sewerage Systems
Item Property Connections by City
Makassar Jambi Pekanbaru
Current 14,400 20,200 17,200
Proposed 11,000 10,300 11,000
The design effort is larger than that envisaged but still must be complete in a reasonable timeframe
to allow suitable time for construction within the project programme. So the challenge is to ensure
sufficient resources are sourced to complete the designs accordingly. The PISC has identified the key
experts required to deliver the project and currently trying to identify the personnel in order to
provide a comprehensive addendum for the project that will be suitable to complete the works. The
reduction in the project timeframe from 48 to 40 months makes this task even more critical.
The quick wins can be associated with preparation of Tender Documents for the networks. The PISC
has rapidly mobilised a team to develop specifications and tender documents for a National Contract
that can be associated with the development on Contract C for all cities. Whilst designs will need to
be developed, the tender documents can be prepared as a draft ready for updating prior to contract
release. PISC has completed a cost estimation excercise in Makassar which will allow Satker Makassar
to issue a Pre-Qualification for Network Contract in early 2018. The same exercise will continue in
Pekanbaru and Jambi.
ADB Loan 3123-INO: Metropolitan Sanitation Management Investment Project
Quarterly Report No. 1, February 2018 27
Table 5-3 Contract Procurement Schedule
City
Contract Source of
Loan
Value (million
USD)
Procurement
Method Description
Pekanbaru Contract A APBD Kota Pekanbaru
Site Preparation (land clearing and fences)
Contract B ADB Loan 3123 – INO
12.90 NCB The constructtion of WWTP
Contract C1 ADB Loan 8280 – INO
20.70* NCB The construction of sewage and wastewater collection system
Contract C2 APBN FY. 2017–2020
17.00 NCB The construction of sewage and wastewater collection system (North catchment)
Jambi Contract A APBD Kota Jambi
Site Preparation (land clearing and fences)
Contract B ADB Loan 3123 – INO
14.75 NCB The construction of WWTP
Comntract C1 ADB Loan 8280 – INO
19.30** NCB The construction of sewage and wastewater collection system (East catchment)
Contract C2 APBN FY. 2017–2020
13.70** NCB The construction of sewage and wastewater collection system (West catchment)
Makassar Contract A APBD Kota Makasar
8.20
NCB Site Preparation (land clearing and fences)
Contract B ADB Loan 3123 – INO
40.60
ICB The construction of WWP and part sewerage collection system
Comntract C1 APBN FY. 2017–2020
21.80 (part of budget)
NCB North – West Waste Water
Collection System, Transfer
System A, and Pressure Main
(Split to be defined)
Contract C2 APBN FY. 2017–2020
21.80 (part of budget)
NCB North – West Waste Water Collection System, Transfer System A, and Pressure Main (Split to be defined)
* Pekanbaru Contract C1 is greater than the maximum value of works that can be undertaken by a Main Contractor in Indonesia
Consideration may need to be given to splitting up the contract further.
** Contract C1 is greater than the maximum value of works that can be undertaken by a Main Contractor in Indonesia. C2 is less.
Consideration may need to be given to adding the works from these two contracts together and splitting up the contract further.
Earthworks for Makassar has developed the furthest of the three with approximately half the site (2.5
Ha), being prepared for Construction. However, the half of the site that was originally considered to
be Contract A Phase 1 works has not been developed and yet phase 2 has. PISC have not been able to
gather records of supervision during the work and there is no sign of Settlement Monitoring as
specified in the original Earthworks Contract designed by MWH.
PISC did collect two different Tenders for the Earthworks Contract from 2016 and 2017 referenced.
Neither of the Tenders contained a Particular Specifications as outlined in the Contract Documents
developed by MWH that describe the layer compaction and settlement monitoring process. The 2016
Contract shows drawings reflecting works to be carried out on Phase 1 works as described by the
MWH Tender Documents but no drawings were issued to PISC with regards to the works for the 2017.
ADB Loan 3123-INO: Metropolitan Sanitation Management Investment Project
Quarterly Report No. 1, February 2018 28
Contract A Earthworks for Pekanbaru has concentrated on the road that splits the site in two phases.
There has been no earthworks carried out on the land associated with the WWTP itself. PISC have
been requested by LG to provide a plan of the site so that they can progress with the Earthworks
associated with Phase A. PISC have to review the current process based on new discharge standards
hence this may impact the site layout. Although the impact to the site requirement is likely to be
minimal, the LG are reluctant to start the tender like Makassar. Furthermore, there is no exisiting
Geotechnical Investigation for the site. PISC have received quotations for an investigation at
Pekanbaru and propose that this commences in January in order to receive the necessary data for the
earthworks contract to commence as well as the detailed design to be completed.
Contract A Earthworks for Jambi has also concentrated on the road that splits the site in two. The
progress is similar to Pekanbaru and there is much work to be done. Jambi has land issues associated
with the site which means that the site area is reduced. A review of the new site area along with the
discharge standards will be carried out by PISC in order to understand if the current process is valid or
further inputs are required. Like Pekanbaru, LG require PISC to provide new layouts in order to finalise
the Earthworks Contract. There is a Geotechnical Report for Jambi with information at the WWTP site
but further investigation is required.
5.2 Coordination at central and regional levels (CPMU, LCO’s)
5.2.1 Pekanbaru
5.2.1.1 Institutional
The municWWTP government has established a UPTD Air Limbah that will be responsible for
operations and maintenamce of the system and managing assets built through the MSMIP project. A
ADB Loan 3123-INO: Metropolitan Sanitation Management Investment Project
Quarterly Report No. 1, February 2018 29
UPTD for wastewater management was established through Peraturan Walikota Pekanbaru Nomor
64 Tahun 2014 tentang Susunan Organisasi, Tugas dan Fungsi Unit Pelaksana Teknis Dinas (UPTD) pada
Dinas Perumahan, Permukiman dan Cipta Karya Kota Pekanbaru dated July 14, 2014. However there
is a change of regulation from MoHA where the establishment of UPTD must receive approval from
Provincial Government. Currently the municWWTP government has submitted a letter of approval
request to the Governor for the establishment of UPTD Air Limbah. Upon approval, the UPTD will be
activated again and start to be involved in the preparation of the MSMIP project.
In accordance with the provisions in the PAM, the management of MSMIP projects at the provincial
and municWWTP levels and should be undertaken by authorized institutions namely PPMU, PPIU and
LPIU. Until now only PPIU exist and are working to prepare the MSMIP project. PPMU is the task of
Pemprov and LPIU, the duty of City Government has not been formed. Satker PSPLP is continuing to
coordinate with Provincial Public Works Office of Riau and Bappeda Kota Pekanbaru to accelerate the
establishment of this institution.
Pekanbaru municWWTP government does not yet have a special law to regulate the management of
domestic wastewater. The CDTA Team Leader has prepared and submitted a previous example of the
required Script as an addition to the ordinance template prepared by the team. The deliberations and
approval of Perda by DPRD will be conducted by the DPRD during 2018.
5.2.1.2 Procurement
In 2017, Satker PS-PLP Riau Province budgeted for Contract C for the construction of sewerage and
wastewater collection system (South catchment) and the construction of sewage and wastewater
collection system (North catchment). However since land and DED issues are not fully completed,
Contract C procurement activities are planned to be implemented in 2018. The entire Contract B and
C both financed by ADB loans and through a multi-year state budget will be implemented through
Bidding conducted by the NCB and PS-PLP Satker Riau Province.
5.2.2 Jambi
5.2.2.1 Institutional
UPTD IPLT was established in 2009 under the Cleanliness, Parks and Cemetery Agency (Dinas
Kebersihan, Pertamanan dan Pemakaman, DKPP). It was responsible for the operation of the Septage
Treatment Installation and vacuum trucks. As a result of the implementation of Government
Regulation No. 18 of 2016 Concerning Regional Government Structures (Peraturan Pemerintah
Republik lndonesia Nomor 18 Tahun 2016 tentang Perangkat Daerah), Dinas Kebersihan, Pertamanan
dan Pemakaman has been eliminated as of 1 January 2017 and responsibility for operation of the IPLT
and vacuum trucks including related assets has been transferred to Dinas Pekerjaan Umum dan
Penataan Ruang. The municWWTP government plans asset management built through the MSMIP
project will be managed by the existing UPTD IPLT.
As with Pekanbaru City, only PPIU exists and work to prepare the MSMIP project, while PPMU which
is the task of Pemprov and LPIU, a duty of City Government has not been formed. Satker PS-PLP is
continuing to coordinate with the Provincial Public Works Office of Jambi and Bappeda Kota Jambi to
accelerate the establishment of this institution.
ADB Loan 3123-INO: Metropolitan Sanitation Management Investment Project
Quarterly Report No. 1, February 2018 30
The DPRD approved Perda Kota Jambi Nomor 13 Tahun 2015 (Local Government Decree) concerning
Domestic and Settlement Wastewater Management. The regulation contains a number of stipulations
about on-site sanitation. Fees for desludging of septic tanks were established in 2012 (Perda Kota
Jambi Nomor 2 Tahun 2012 concerning General Service Retribution. This decree will have to be
replaced by a regulation establishing the legal base for collecting regular payments from users for
wastewater services, which will allow the government to implement a scheduled desludging scheme
(Layanan Lumpur Tinja Terjadwal, L2T2).
5.2.2.2 Procurement
Satker PS-PLP Jambi Province has budgeted Contract C for the construction of the sewage and
wastewater collection system, but since the bidding documents for Contract C1 and C2 are not ready
to be tendered in 2017, so PPK decided to reallocate these two packages by 2018. The budget already
allocated for both packages C is USD 4.615 million (or IDR. 60 billion)
5.2.3 Makassar
5.2.3.1 Institutional
A UPTD Pengelolaan Air Limbah was established in 2011 under Dinas PU through a decree by the
Mayor. Detailed responsibilities and job descriptions followed in 2012. Later Perwali issued in early
2014 basically related to changes of the responsibilities of Dinas PU. Formally cancelled the Perwali of
2011 but did not affect the operations of the UPTD. This issue needs to be resolved through Provincial
Government.
The DPRD approved a domestic wastewater ordinance, signed in July 2016 (PERDA Kota Makassar
Nomor 1 tahun 2016 tentang Domestic Wastewater Management). The regulation contains a number
of stipulations about on-site sanitation. The government and the local assembly have been long
discussing a local regulation to establish a wastewater tariff or tax. This would form the legal base to
collect regular payments from users for wastewater services, which would allow the government to
implement a city-wide scheduled desludging scheme (Layanan Lumpur Tinja Terjadwal, L2T2). There
is no certainty about when this regulation is likely to be approved.
In accordance with the provisions in the PAM, the management of MSMIP projects at the provincial
and municWWTP levels should be undertaken by authorized institutions namely PPMU, PPIU and LPIU.
Until now only PPIU that already exist and work effectively prepare the MSMIP project, while PPMU
which is the task of Pemprov and LPIU which is the duty of City Government has not been formed.
Satker PS-PLP is continuing to coordinate with Provincial Public Works Office of South Sulawesi and
Bappeda Kota Makassasr to accelerate the establishment of this institution.
5.2.3.2 Procurement
In contrast to Kota Pekanbaru and Jambi, the number of packages in Makassar City is only two, namely
Contract B, financed by the ADB loan and being tendered under ICB that includes the construction of
the WWTP and sewerage collection system and Contract C North – West Waste Water Collection
System, Transfer System A, and Pressure Main.
Meanwhile, due to the limited number of potential domestic bidders who can participate under
Contract C due to its value, CPMU and Satker PS-PLP decided to split Contract C into two parts namely
C1 and C2. How the contract is split will be defined during design development under PISC. In principle
ADB Loan 3123-INO: Metropolitan Sanitation Management Investment Project
Quarterly Report No. 1, February 2018 31
the value of the project can still be fulfilled by a number of potential domestic participants (based on
work experience requirements)
5.2.4 Site Visits
The PISC Consultant made initial Site Visits to Makassar, Pekanbaru and Jambi between 26th October
and 3rd November 2017 and is documented in the Inception Report. General details from the report
is given in this section.
5.2.4.1 25th to 27th October - Makassar.
The PISC meeting in Makassar started with technical coordination with the Satker PS-PLP of South
Sulawesi Province and its staff to discuss the status of the latest activities under the Contract, the
availability of planning documents and Satkers plan to accelerate the preparation of tender in 2017
and 2018. An important finding of this meeting is the delay in Contract C bidding process caused by
the lack of preparation of the bidding documents, both technical drawings and OE (Owner Estimate).
It was revealed that there was still an inconsistency between the Drawings and the measure prepared
for the OE by MWH. Also, the OE format and bidding document (technical specifications) must be
adjusted to the standard bidding documents in the MoPWH.
The PISC also held meetings with the Dinas PU of Makassar City to discuss the status of Contract A ~
Land Works (Land clearing & maturation, and fencing) for WWTP, as well as the readiness of the
pumping station location which is the responsibility of the LG including the current land ownership
status. There are two key land issues. Part of the land for the WWTP is under dispute with a local group
which means the earthworks contract has stopped and only half the site is complete. The second issue
is at the site of Pump Station A where LG has given approval for a car park to be constructed in the
same location.
CPMU, PISC together with the Public Works Office later held a meeting with the Mayor and received
were requested to ensure that the construction works related to thr pipeline network should not
impact on the new pedestrian facilities built by the LG
5.2.4.2 30th October to 1st November – Pekanbaru
The PISC site visit and meeting in Pekanbaru began by coordinating with Satker PS-PLP Riau Province
and its staff to discuss the current status of the MSMIP project, the constraints faced and the future
plans. The meeting focused on the land for WWTP and DED documents (note design, drawings and
OE) that are still need updated by PISC. The main problem on WWTP’s site is the volume of Earthwork
in 2017 is inadequate. Only the earthworks associated with an access road. It was the intention that
all earthworks associated with the site would be completed as soon in 2018 FY before before starting
the construction of WWTP. At a meeting with the LG (Dinas PU and Bappeda) it was revealed that the
budget for Earthwork on WWTP land has not been adequate for necessary works in 2018. PISC was
asked by Bappeda to prepare the final drawings of WWTP layout as the basis for the LG to propose
additional Earthwork budget in APBD 2018. PISC maintained that this could only be done after the
process was assessed and this would be mid February 2018.
5.2.4.3 1st November to 3rd November - Jambi,
At the meeting with PPK Satker PS-PLP of Jambi Province, it was explained that a key issue affecting
project preparation in Jambi is the insufficient land for the WWTP and that the progress of Earthworks
associated with the site is very late. There is a plot of land that cannot be purchase by LG until the end
ADB Loan 3123-INO: Metropolitan Sanitation Management Investment Project
Quarterly Report No. 1, February 2018 32
of 2017 and only Earthworks associated with the access road can be completed. We were informed
that Earthwork for the new WWTP footprint will be implemented in 2018, but the funds would appear
insufficient to do so. DEDs for Contract B and C need to be reviewed in its entirety but it would appear
that the design of the network is of a very poor standard.
5.2.5 Palembang
5.2.5.1 Institutional
A UPTD Pengelolaan Air Limbah was established under Dinas PU through a decree by the Mayor. The
UPTD is in the process of being re-established under Dinas PUPR after all UPTD’s were abolished by a
Home Affairs regulation. The UPTD manages the operation and maintenance of communal systems .
The DPRD approved a domestic wastewater ordinance, signed in August 2016 (PERDA Kota Makassar
Nomor 7 tahun 2016 tentang Domestic Wastewater Management). The regulation contains a number
of stipulations about on-site, communal and off-sitesanitation, including the provision that connection
to the sysem, once available, is a requirement.
The subjects of the Service Delivery Organization and tariffs have not been set in the PERDA and are
subject to further decision making through a Peraturan Walikota.
In accordance with the provisions in the PAM, the management of PCSP should be undertaken by
authorized institutions namely CPMU, PPMU, PPIU, LPMU and LPIU. Of these, CPMU and LPMU have
been formally established. The function of PPMU AND PPIU are effectively being undertaken by the
Satker PS-PLP South Sumetera, while the function of LPIU is being undertaken by Dinas PUPR.
With the PPH (On-Grant Agreement) signed per January 24, 2018, formalization of the LPIU, PPIU
and PPMU needs to be undertaken.
5.2.5.2 Procurement
The planned procurement in Kota Palembang concerns 7 construction packages and is as follows:
A National Competitive Bidding package for site works of the WWTP, financed by APBD and
DFAT. The package includes the payment of ompensations as specified in the approved LARP.
The works have been contracted on the 13th of September 2017.
An ICB for the WWTP and main pumping station, financed by DFAT through APBD.
A National Competitive Bidding for the transmission main, financed by APBN. The works have
been contracted on the 11th of December 2017 and have an implementation period of 2 years.
A National Competitive Bidding for a part of the gravity system, financed by APBN. Given the
limited number of contractors that would be able to participate in the tender for this package,
it is likely that the package needs to be split into 2 or more packages.
A National Competitive Bidding for a pilot of a 1,000 house connections, financed by APBN.
2 National Competitive Bidding packages for a part of the gravity system, financed by APPD.
In addition, additional packages will be managed and financed by Kota Palembang for the construction
of an additional 11,000 house connections.
ADB Loan 3123-INO: Metropolitan Sanitation Management Investment Project
Quarterly Report No. 1, February 2018 33
5.3 Liaison with ADB
PISC have liased with ADB during the first three months of the project at the start of the ADB mission
on 23rd November. This coincided with PISCs presentation to DGHS of the Inception Report, so ADB
representatives sat in the presentation and PISC were able to listen to ADBs presentation for the
Mission. PISC are expected to be invited to following meetings in January when the mission results
will be published. PISC also hope to mobilise personnel associated with the softer side of the project
in January / February 2018 which will include Environmental, Social Safeguards, Gender, Resettlement
expertise and would like to extend invitations to ADB to meet the experts when they arrive and be
involved in the planning phase of these works.
5.4 Consultant Procurement and Contract Management
During the mobilisation period for the project, the PISC has appointed a Temporary Team Leader in
Brian Hayden to guide the project through the early months. He is responsible to ensure project
progress whilst recruiting the necessary personnel for the future. He is being used to carry out the
duties for a four month period in which time the necessary team will show signs of completion and
continuous advancement in the programme can progress under the management of the Team Leader.
The following Contract Management general tasks have been carried out in accordance with the
Project Plan;
Project office establishment
Communication Plan
Document Control System
Project Organisation; Appendix A
Design Phase Project Schedule; Appendix B
Staffing Schedule; Appendix C
Risk Register; Appendix D
Progress Meetings; Appendix E
5.4.1 Project Office Establishment
The PISC will be located in a new office address for the purpose of the Contract as of January 1st 2018.
The Jakarta Central office will be located at the following address for the project duration.
KMO Building 2nd Floor Unit 201, Jalan Kyai Maja No. 1, Kebayoran Baru, RT.3/RW.8, Gunung,
Jakarta, Kota Jakarta Selatan, Daerah Khusus Ibukota, Jakarta 12120
The Central Office will be the main office during the project and will be home to the Team Leader,
design and administrative staff for the duration of the project. Based on the original Contract the peak
period in the office would be during the first 6 months where staff levels would range between 12 and
30. Based on the addendum, the peak period, although provides a greater number of staff, projects a
similar pattern and the staff number ranges between 20 and 44. The peak period itself is also
stretching over a 10 month period, which aligns with the design and tender phase under the current
programme. After a 12 month period, both options illustrate a levelling off of the staff number.
Between month 12 and 40 for the Contract illustrates an average number of 9 staff are required whilst
a9 staff are the average number under the Addendum.
ADB Loan 3123-INO: Metropolitan Sanitation Management Investment Project
Quarterly Report No. 1, February 2018 34
Figure 5.1 Staffing levels for Jakarta during the project term based on the original Contract and
Addendum No 1
Month Number of Personnel Addendum/Contract
Capacity Increase (x) Original Contract Addendum 1
1 13 3 0.18
2 17 21 1.23
3 30 31 1.03
4 27 43 1.59
5 18 42 2.33
6 15 43 2.86
7 14 38 2.71
8 14 37 2.64
9 12 30 2.50
10 10 27 1.70
11 9 21 2.33
12 9 20 2.22
13 11 20 1.81
14 10 20 2.00
15 11 22 2.00
16 10 20 2.00
17 11 19 1.73
18 9 20 2.22
19 9 17 1.89
20 8 17 2.12
21 8 17 2.12
22 9 18 2.00
02468
10121416182022242628303234363840424446
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40
Original Contract Addendum No. 1Month
Addendum 1Peak Staff Level = 44
Contract Peak Staff Level = 30
Addendum 1
Av. Staff Level = 19 (after 12 months)
Contract Av. Staff Level = 9 (After 12 months)
ADB Loan 3123-INO: Metropolitan Sanitation Management Investment Project
Quarterly Report No. 1, February 2018 35
Month Number of Personnel Addendum/Contract
Capacity Increase (x) Original Contract Addendum 1
23 9 19 2.11
24 9 21 2.33
5.4.2 Staff Mobilisation
The PISC recruitment is continuous and a number of key positions are filled based on the original
contract. We are seeing some of the issues regarding Key International Staff being resolved and Key
National Staff are performing the duties required to ensure that the programme is delivered
accordingly. Some issues regarding the recruitment of International Staff is recognised under Section
5.10, Project Performance and Monitoring, but many named Key Internationals recruitment issues are
gradually being resolved. Addendum 1 is expected to be approved in January and a mobilisation
programme that suits the project can be defined.
Table 5-4, Illustrates the recruitment so far.
October 2nd to January
2nd Status Name Notes
Senior Infrastructure
Specialist
International Brian Hayden Not named under the Contract, but
deemed necessary to accelerate the
programme during mobilisation as a
stand in Team Leader.
Deputy Team Leader Key National Benny Sihaloho Described under the Contract
Office Manager Non Key
National
Utami Kusumaningrum
Described under the Contract
Financial Management Specialist
Key National Thariq Marzuki Described under the Contract
Benefit Monitoring
Specialist
Key National Treesnowati Described under the Contract
Engineering Support / Drafting
Non Key National
Darning Described under the Contract
Civil Engineer National Wildan Not named under the Contract but
deemed essential. Initial works to re-
write Specificationsto National
Standard
Mechanical Engineer National Henry Pranajaya Not named under the Contract but deemed essential. Initial works to re-write Specificationsto National Standard
Cost Estimator National Sulikha Not named under the Contract but deemed essential. Initial works to prepare a cost estimate for works associated for Contract C for each city so that the Prequalification excercise
ADB Loan 3123-INO: Metropolitan Sanitation Management Investment Project
Quarterly Report No. 1, February 2018 36
October 2nd to January
2nd Status Name Notes
can take place and Billis of Quantitie can be prepared.
Surveyor National Supiyanto Not named under the Contract but deemed essential. Initial works to assist the cost estimator in each city and check the measure of quantities for works associated for Contract C for each city so that the Prequalification excercise can take place and Billis of Quantitie can be prepared.
Accounting Specialist Non Key National
Ermien Fatma Julia Described under the Contract
Bilingual Secretary Non Key National
Devi Satriani Described under the Contract
Office Boy Non Key National
Safrizal Atmawjaya Described under the Contract
During January 2018, the following staff will be mobilised onto the project
January 2018 Status Name Notes
Team Leader Key International
Malcolm Ehrlich Described under the Contract
Wastewater Process
Engineer
Key International
Anthony Gunadi Described under the Contract
Gender and Social
Development Specialist
Key International
Rosemary
Faletese
Described under the Contract
Environmental Specialist Key International
Joselito Losario Described under the Contract
Social Safeguards / Resettlement Specialist
Key International
Victoria Pineda Described under the Contract
MIS Specialist Key National Achyar Lubis Described under the Contract
Electrical Engineer Key National - Described under the Contract
Geotechnical Engineer Key National Widaryanto Described under the Contract
Structural Engineer Key National Yan Haryadi Described under the Contract
Sewerage Engineer Key National Luthfi Basit Described under the Contract
Procurement and
Contract Specialist
Key National Wiryawan Djati Described under the Contract
ADB Loan 3123-INO: Metropolitan Sanitation Management Investment Project
Quarterly Report No. 1, February 2018 37
January 2018 Status Name Notes
GIS-IT Support Non Key National
- Described under the Contract
An MIS Specialist will be deployed to the project in January and they will be responsible to develop
the Project Website where information will be made available to stakeholders through the project
period.
5.4.3 Communication Plan
The communication strategy has been developed to ensure that the access of information can be
issued accordingly and professionally and make sure that the right individuals whom require the
information have access. For MSMIP there are a number of stakeholders who will require information
of different types and it is imperative that procedures are implemented to ensure data is transferred
efficiently. A strategy is oultlined in PAM (Project Administration Manual) of MSMIP that helps ensure
a regular flow of reliable project information and allows for a two-way exchange between the project
implementers and stakeholders.
The PISC Consultant’s Project Team hold regular progress meetings with CPMU/PPIU, to ensure that
the agreed tasks as identified in the Inception Report are achieved in a timely manner and to
communicate key issues and proposed solutions arising during the process.
Figure 5.2 Communication Flow Diagram
Notes :
command
coordination
contractual & administration
reporting
CPMU (Central Project Management Unit)
PISC (Project SuupportImplementation Consultant)
PPK PISC MSMIP
PPMU (Provincial Project Management Unit)
City Team of PISC
DGHS/DESD(Executing Egency)
COMMUNICATON FLOW DIAGRAM
ADB Loan 3123-INO: Metropolitan Sanitation Management Investment Project
Quarterly Report No. 1, February 2018 38
The Ministry of Public Works and Housing, Directorate General for Human Settlements (DGHS) is the
Executing Agency (EA) for the MSMIP. DGHS have established a Central Project Management Unit
(CPMU) composed of technical and administrative staff from Directorate of Environmental and
Sanitation Development (DESD). The CPMU is headed by a Senior Officer of the DESD.
Agency Key Person
Executing Agency : Directorate General of Human Settlements in the Ministry of Public Works and Housing
Officer's Name : Dwityo A. Soeranto Position : Director of the Integration of Settlement Infrastructure Telephone : +62-21 72796588 Email address : [email protected] Office Address : Jl. Pattimura 20, Kebayoran Baru Jakarta Selatan 12110 Indonesia Officer’s Name Designation : Dodi Krispratmadi Position : Director of Environmental Sanitation Development Telephone: +62-21 72797175 Office address : Jl. Pattimura No. 20 Jakarta Email address : [email protected]
CPMU : Directorate of Development Sanitation Environment Housing in the Ministry of Public Works and Housing
Officer's Name : Asri Indiyani Position : Head of CPMU Telephone : +62-21 72797175 Email address : [email protected]
The city government (PEMKOT) is the Implementing Agency (IA) in Palembang. For Jambi, Makassar
and Pekanbaru, several units will work jointly to manage and implement the subprojects.
At the provincial level,
1) the PPIU or the SATKER comprises full time staff detailed from DGHS to the provinces to implement specific projects of DGHS, and
2) the Provincial Project Management Unit (PPMU) will provide coordination with the other offices (dinas) in the provincial level.
At the city level, the LPMU will work with the Satuan Kerja Perangkat Daerah (SKPD) to provide
coordination and support for project implementation. The PPIU will comprise full time staff
transferred from the DGHS. The PPIU will take full responsibility for the project implementation at the
city level including progress monitoring and contracts management. The shadow LPMU will support
the PPIU in the implementation and monitoring of the project activities, including setting of special
policies that will satisfy the conditions of the loan agreement. For Palembang, the LPMU will solely be
responsible for management and implementation of the subproject.
The CPMU will appoint an Environment Officer for the Project, to oversee the implementation and
monitoring of environmental safeguards requirements under ADB's Safeguards Policy Statement (SPS)
2009. Environmental Officers will also be designated in the PPIUs and LPMUs to effectively manage
the environmental aspects at the subprojects level.
5.4.3.1 Authorized Representatives
The Authorized Representatives are:
ADB Loan 3123-INO: Metropolitan Sanitation Management Investment Project
Quarterly Report No. 1, February 2018 39
For the CPMU:
The Management Director
William S. Sinclair
Regional Manager - SMEC Indonesia
NHB Building Lt. 2 - 4,
Jalan Melawai Raya No.14, RT.3/RW.1, Melawai, Kby. Baru,
Kota Jakarta Selatan, Daerah Khusus Ibukota Jakarta 12160
Phone: 0821-2445-7999
For the PISC Consultant:
The Team Leader
(To be appointed) Standing in during the mobilisation phase is Brian Hayden
SMEC International Pty
NHB Building Lt. 2 - 4,
Jalan Melawai Raya No.14, RT.3/RW.1, Melawai, Kby. Baru,
Kota Jakarta Selatan, Daerah Khusus Ibukota Jakarta 12160
Phone: 0821-2445-7999
5.4.4 Document Control
PISC are utilising an internal Document Control System to effectively manage all documentation
associated with the project. All Project information is stored on the a server located at SMEC Denkas
head office. The filing structure complied with SMECs standard QA/QC procedures for project control.
000 Internal Administration and Personnel Management
010 Internal Management and Finance
020 SMEC Contracts
030 Correspondence, Meetings and Reports
040 Design Input Data
050 Construction Management
5.5 Management of Contractors and Consultants
5.5.1 Management of Contractors
PISC expect to engage Contractors in January and February associated with Geotechnical and
Topographical surveys. These works will be carried out and funded through the Provisional Sum. In
this instance, it is our intention to;
1. Receive a minimum of three quotations
2. Do a factory/office inspection of the preferred bidder
3. Submit a letter to CPMU describing the works and recomending the contractor
4. On approval by CPMU, place an order with the contractor
5. Manage the site works
6. Place a number of enquiries with trusted contractors
ADB Loan 3123-INO: Metropolitan Sanitation Management Investment Project
Quarterly Report No. 1, February 2018 40
5.5.2 Management of Consultants
The PISC consists of lead Consultant SMEC International Pty Ltd in joint venture with Stantec Australia
Pty Ltd (ex-MWH) and in association with the following local sub-consultants: PT. Infra Tama Yakti
(ITY), PT. SMEC Denka Indonesia, PT. Amurwa International and PT. Widya Graha Asana (WGA). All
Consultants are fully engaged in the project and providing the necessary national key and non key
staff in accordance with the contract.
The Project managers for each of the Sub Consultants have attended SMECs Bribery and Anti
Corruption workshops and weekly progress meetings are held with all involved Consultant PMs on
Tuesdays at 9am.
5.6 Project Coordination Meetings
CPMU and PISC have met regularly during the first three months of the project. These meetings have
not been regular, but key staff have met as and when required. In a progress meeting on December
29th December it was agreed to meet on a bi weekly basis every second Friday.
The initial kick off meeting attended by PISC for MSMIP project following contract signing (dated
October 2, 2017) was held on Monday, October 9th, 2017. Representatives from CPMU, PPK, PISC,
and Satkers/ PPKs responsible for Pekanbaru, Makassar and Jambi attended the meeting.
In the meeting each party introduced themself along with their project roie. PISC presented an
understanding of the project and work plan and requested all parties provided the information
available on the designs for each city, especially the Satker/PPK in relation to the current condition
both from technical and non-technical aspects.
In order to obtain accurate information related to the status of each city, PISC accompanied by CPMU
arranged to conduct field visits the following week including early communication / coordination with
local government (Dinas PU and Bappeda).
5.7 Training/ Workshops
There have been no training provided in the first three months of the project and there is no training
planned in the three months look ahead programme.
In Q1 period, the Consultant has conducted two training and workshop activities:
A. Socialization Workshop of MSMIP Development Program of Makassar City. The event that
took place on Thursday December 14, 2017 was held at Sheraton Hotel Makassar (Four
Points), Jl. New Landak of Makassar City by Satker PS-PLP of South Sulawesi Province. Related
parties were invited especially representatives from PKK and NGO of sanitation in Makasar
city including some SKPD in Pemkot Makassar. The participants enthusiastically supported the
MSMIP program, to be implemented as soon as possible with the real support of the
beneficiaries, the PISC proposed to have a series of Advanced Socialization events that are
limited, and focus on the people who will connect.
B. Workshop on Finalization of EE (engineering estimate) and Document Preparation of PQ for
Contract C-1 and C2 of Kota Makasar. This workshop was attended by staff from Satker PSPLP
of South Sulawesi Province and PISC Consultant. This workshop was held on Friday, December
ADB Loan 3123-INO: Metropolitan Sanitation Management Investment Project
Quarterly Report No. 1, February 2018 41
15, 2017. The result of this Workshop is Draft Engineering Estimate for Contract C1 and C2
Wastewater Water Piping Network of Makassar City along with Draft Document of PQ
5.8 Progress of Project Component
Under the Contract there are two project components which are described further in Section 3.2.4; 1. Output 1: Infrastructure development for off-site wastewater systems completed.
2. Output 2: Project implementation support institutionalized.
The progress associated with output 2 is provided within the monthly and quarterly reports whilst
Project Progress will be reported through the Project Management systems assigned to the
Construction phase for progress associated with Output 1.e progress reporting will be discussed pre-
construcion phase to ensure that it provides DSHG and ADB with the information required and follows
the progress reporting Quality Management Systems that are commonly adopted by the PISC Lead
Consultant on similar projects.
A Project Baseline Schedule for the design phase was issued in the Inception Report and is issued
under Appendix F and illustrates shows the progress to date.
5.9 Project Performance and Monitoring System
The objective of project performance monitoring Services is to ensure that the project is implemented and managed effectively and that benefits of the project are optimised. The project management and coordination is to monitor performance against progress, identifying problem areas and working with CPMU, PPMU/PPIU, LPMU /LPIU to solving the problem. The consultant PISC regarding reporting services of the MSIMP Loan, shall include monitoring progress of the activities including problem solving and reporting to the CPMU. Whereas for the periodic reports, such as physical progress and audited financial reports that are prepared for ADB is a provision that has been arranged in the loan agreement.
5.10 Safeguard Monitoring
Apart from the Socialization Workshop of MSMIP Development Program of Makassar City held on 14th
December 2017, there have been no further activities.An International Social Safeguard /
Resettlement Specialist is due to mobilise in February 2018.
5.11 Gender Action Plan
5.11.1 Gender Classification
The purpose of the MSMIP is to improve urban wastewater systems in three major cities namely,
Jambi, Makassar, and Pekanbaru. The Project is in response to the inadequacy of the current sanitation
systems and the resulting health and environmental problems. The subprojects include the
construction of separate wastewater systems and wastewater treatment plants (WWTPs) to serve the
urban communities, including low income and poor House Connections. Women will benefit through
special measures for subsidized connections and tariffs, employment enhancement, increased
participation in decision making process, training, institutional and capacity building, and targets for
women in project management. The Project is classified as effective gender mainstreaming (EGM) one
in design.
ADB Loan 3123-INO: Metropolitan Sanitation Management Investment Project
Quarterly Report No. 1, February 2018 42
5.11.2 Purpose and Strategy
The Project gender analysis shows that many of the poor live in deprived areas which lack sanitation
facilities and services. The significant social and economic burden of illness, health care for the family
and other associated domestic responsibilities as a result of not having proper access to adequate
sanitation, falls primarily on women. Women in these areas earn low incomes as a result of limited
access to employment and livelihood opportunities. There are a significant percentage of female-
headed households (FHHs) in most project cities who are generally poor. Women are in a
disadvantaged position to equally and meaningfully share in the Project’s benefits and management
despite their central role in water, hygiene and sanitation management. The MSMIP gender strategy
will facilitate women’s participation and benefits through GAP implementation (see Table 5-5). These
include enhanced sanitation awareness, connections to proper sanitation and off-site wastewater
treatment systems, and improved gender sensitive management and operational capacity. Social
inclusion and pro-poor measures include provision of on-site sanitation with livelihood options, as
needed, near WWTPs. Desludging points in the city will reduce haulage distances from septage
collection within non-sewered areas and hence reduce the associated tipping costs and charges.
Table 5-5 MSMIP’s Gender Action Plan
Project Outputs Gender Actions and Targets
Output 1
Infrastructure
development for
off-site
wastewater
systems
completed
At least 30% of participants in public consultation and sewerage
connection campaign activities are women and vulnerable groups
(such as FHHs – at least 10% overall), who will get full information
about subsidized sewage connection fees and criteria for subsidized
monthly tariffs.
At least 30% participation of women at public hearings concerning
future sanitation tariff increases, which shall take into consideration
gender issues and affordability.
Information bulletin on risks of HIV/AIDS relayed through
appropriate media with civil works contractors providing
information/preparing code of conduct for workers and providing
information on HIV/AIDS through expert NGO as stipulated in
bidding documents.
Of the 70,270 households with domestic house connections to
central sewer systems, at least 10% will be provided to poor and
vulnerable groups (including FHHs).
All of the above 10% poor and vulnerable households (including
FHHs) connected under the project will receive subsidized
connections and monthly fees.
Of onsite sanitation managed by CBOs established in non-sewered
hot spots near the WWTP sites connecting at least 90% of
households disposing wastewater into waterways, at least 30% of
households will be from poor, female-headed household or
vulnerable groups (if population will otherwise not have access to
ADB Loan 3123-INO: Metropolitan Sanitation Management Investment Project
Quarterly Report No. 1, February 2018 43
Project Outputs Gender Actions and Targets
sanitation infrastructure) implemented in coordination with the
eligible NGOs.
At least 50 women, either as individuals or as part of women’s
organizations near the WWTPs will be provided with livelihood and
enterprise development training from the Sanitation/Livelihood
Development Assistance in coordination with relevant NGO and
government agencies for livelihood support.
Output 2:
Project
Implementation
Support
Institutionalized
EA/IAs/SDOs will ensure additional 10% female staff with 10%
increase of females in management positions by 2018.
Specific gender sensitization and sanitation investment and
operation/maintenance training modules and
technical/management capacity development training are open to
managers and staff at all levels (i.e. national, districts).
To promote professional advancement of female staff, ensure that
at least 30%female participants in training on gender, community
facilitation, utility management, technical and project/sector
management- related skills.
Public awareness campaigns aimed at creating an appreciation and
understanding of the benefits of sewerage systems and the need to
pay for adequate charges to cover O&M will ensure 30% women
participation.
At least 30% of all capacity building participants on hygiene and
sanitation education, promotion, planning and participatory
monitoring (e.g. WWTP impacts) are women.
Source : Project Administration Manual of MSMIP (Revised November 2016)
So far, no project references regarding women participating in public consultations regarding project
impact and house connections and sanitation for the 3 cities has been identified. The same situation
is apparent with reference to vulnerable households served by this project.
5.11.3 Implementation and Monitoring Arrangements.
The GAP is integrated into the overall cost estimates and project implementation arrangements. A
national Gender and Social Development Specialist will support the central and local PMU and Service
Delivery Organizations (SDOs) to ensure that the GAP and social strategy agreed between the
Government and ADB is fully implemented. The PMUs and the SDOs will be responsible for
implementing, updating and monitoring the GAP. Sex-disaggregated baseline data and monitoring
indicators will be used in quarterly reports to provide GAP progress updates. Gender issues and
impacts will be discussed in mid-term reviews and regular progress reports submitted to ADB.
5.11.4 GAP Budget.
The GOI will provide sufficient resources to implement the GAP within the PMU and across all
responsible agencies and sewerage development organizations as they are established. The budget
for the GAP is integrated within the overall Project budget. In addition, sanitation/livelihood
development assistance will be provided set up where Social Development and Sanitation Advocacy
ADB Loan 3123-INO: Metropolitan Sanitation Management Investment Project
Quarterly Report No. 1, February 2018 44
(SDSA) assessment confirms the need for livelihood opportunities and onsite sanitation near WWTP
sites.
5.12 Financial Management
A transparent and accountable financial management practice is necessary to ensure that projects are
properly utilized for the purpose and that every Satker/Work unit in managing the funds would be
able to fulfil their obligation in reporting the disbursement and use of the funds. The loan is disbursed
for the implementation of works and consultants services managed and supervised by four
Satker/PPIU’s, three provincial Satkers (Jambi, Makassar, and Pekanbaru) and one handling the
consultant services in Central Government /CPIU.
The financial administration project conducted in accordance with MSMIP and other prevailing rules
in financial of accounting policy are as follows;
(i) Minister of Finance decree regarding implementation guidelines of ADB Loan for MSIMP
project;
(ii) Director General of Treasury regulation payment for implementation of fund MSIMP;
(iii) Revenue and expenditures are recorded on the cash basis Method;
(iv) Accounting period for fiscal year is conducted in accordance with the government Budget
period, starting from 1 January to 31 December;
(v) The ADB’s fund consolidated financial statement regarding the MSIMP Project. (v) The
currency is in Indonesian Rupiah with currency exchange fixed rate in USD 1 equals IDR
13.000;
(vi) Funding of the loan ADB with direct payment procedure is realized base on the value fixed
at withdrawal date;
(vii) The administration of the loan ADB is not allocated through DIPA Mechanism, but paid
directly by ADB to the Consultant, Contractor, and supplier through Direct Payment.
The Executing Agency/EA will maintain the applicable financial reporting standard and separate
Books and records for all expenditure incurred based on public standard cash based accounting
system. At the provincial level, these three provincial agencies/PPIU’s, Jambi, Makasar, and
Pekanbaru should understand to implement the practice of ADB’s Procedure including financial
management requirements and maintain separate projects record and accounts that are
adequate to identify works and services financed from ADB loan Proceeds.
5.13 Arrangement for O&M of Project Facilities
No current actions have been undertaken regarding O+M of Project Facilities.
5.14 Project Targets
The current Programme is given under Appendix G and defines key tasks throughout the design and
tender process. The key dates are given in the table below.
ADB Loan 3123-INO: Metropolitan Sanitation Management Investment Project
Quarterly Report No. 1, February 2018 45
Table 5-6 PISC’s Project Targets
City Task Item Key Date of Delivery
Makassar 23 Commence Phase 1 Earthworks under Contract A
16th March 2018
Makassar 28 Issue Prequalification for Contract C1 and C2
8th January 2018
Makassar 42 Tender Announcement for Contract C1 and C2
13th March 2018
Makassar 62 Tender Announcement for Contract B1
7th August 2018
Makassar 81 Tender Announcement for Contract B2
9th May 2018
Pekanbaru 48 Commence Phase 1 Earthworks under Contract A
18th May 2018
Pekanbaru 24 Issue Prequalification for Contract C1 and C2
26th February 2018
Pekanbaru 39 Tender Announcement for Contract C1 and C2
27th June 2018
Pekanbaru 65 Tender Announcement for Contract B
24th July 2018
Jambi 48 Commence Phase 1 Earthworks under Contract A
7th May 2018
Jambi 24 Issue Prequalification for Contract C1 and C2
27th February 2018
Jambi 39 Tender Announcement for Contract C1 and C2
28th June 2018
Jambi 65 Tender Announcement for Contract B
18th July2018
ADB Loan 3123-INO: Metropolitan Sanitation Management Investment Project
Quarterly Report No. 1, February 2018 46
6 Compliance with Loan Covenants Loan covenants are considered necessary to ensure efficient implementation of and full realisation of
the benefit from, projects financed by ADB. These include the development of covenants that deal
with the objectives and implementation of an ADB-financed project including MSMIP, taking into
account ADB's role as a development financing institution and its objective to contribute to the
economic growth of the region. These covenants include covenants entered into by ADB with its equity
investments.
Loan covenants are primarily the obligations to be performed by the Government of Indonesia/DGHS
for ADB-financed projects. ADB is under an obligation to monitor and follow up these obligations
contained in loan covenants. ADB's general approach on noncompliance with loan covenants is to seek
corrective measures in order to attain the original development objectives of the ADB-financed
project. ADB's legal remedies on noncompliance with loan covenants include suspension, cancellation,
or acceleration of maturity, which are available under the loan agreement and the loan regulations
made applicable thereto. Resorting to legal remedies in the event of noncompliance is not automatic
or mandatory. Before resorting to such measures,
MSMIP’s particular covenants will include matters such as institutional and staffing arrangements for
project execution; acquisition of required land; allocation or provision of water, fuel or power
resources; distribution and marketing arrangements or supporting services; conduct of surveys and
studies; institutional development and training; review of tariffs, rates, charges and prices; sector or
regional policy matters; operational and management matters; and co-financing arrangements and
other financial measures. Here below is the particular covenants for MSMIP
Section 1
a) The Borrower shall ensure the Project is carried out with due diligence and efficiency and
in conformity with sound applicable technical, financial, business, and development
practices.
b) In the carrying out of the Project and operation of the Project facilities, the Borrower
shall perform, or cause to be performed, all obligations set forth in Schedule 5 to the
Loan Agreement.
Section 2
The Borrower shall make available, promptly as needed and on terms and conditions
acceptable to ADB, the funds, facilities, services, land and other resources, as required, in
addition to the proceeds of the Loan, for the carrying out of the Project and for the operation
and maintenance of the Project facilities.
Section 3
a) Whenever applicable, in the carrying out of the Project, the Borrower through the Project
Executing Agency shall cause competent and qualified consultants and contractors,
acceptable to ADB to be employed to an extent and upon terms and conditions
satisfactory to the Borrower and ADB.
b) The Borrower through the Project Executing Agency shall cause the Project to be carried
ADB Loan 3123-INO: Metropolitan Sanitation Management Investment Project
Quarterly Report No. 1, February 2018 47
out in accordance with plans, design standards, specifications, work schedules and
construction methods acceptable to the Borrower and ADB, as applicable. The Borrower
shall furnish, or cause to be furnished, to ADB, promptly after their preparation, such
plans, design standards, specifications and work schedules, and any material
modifications subsequently made therein, in such detail as ADB shall reasonably request.
Section 4
The Borrower shall ensure that the activities of its departments and agencies with respect to
the carrying out of the Project and operation of the Project facilities are conducted and
coordinated in accordance with sound administrative policies and procedures.
Section 5
a) The Borrower through the Project Executing Agency shall
(i) maintain separate accounts and records for the Project;
(ii) prepare annual financial statements for the Project in accordance with
accounting principles acceptable to ADB;
(iii) have such financial statements audited annually by independent auditors whose
qualifications, experience and terms of reference are acceptable to ADB, in
accordance with international standards for auditing or the national equivalent
acceptable to ADB;
(iv) as part of each such audit, have the auditors prepare a report (which includes the
auditors’ opinion on the financial statements, use of the Loan proceeds and
compliance with the financial covenants of this Loan Agreement) and a
management letter (which sets out the deficiencies in the internal control of the
Project that were identified in the course of the audit, if any); and
(v) furnish to ADB, no later than 6 months after the end of each related fiscal year,
copies of such audited financial statements, audit report and management letter,
all in the English language, and such other information concerning these
documents and the audit thereof as ADB shall from time to time reasonably
request.
b) ADB shall disclose the annual audited financial statements for the Project and the
opinion of the auditors on the financial statements within 30 days of the date of their
receipt by posting them on ADB’s website.
c) The Borrower through the Project Executing Agency shall enable ADB, upon ADB's
request, to discuss the financial statements for the Project and the Borrower's financial
affairs where they relate to the Project with the auditors appointed pursuant to
subsection (a)(iii) hereinabove, and shall authorize and require any representative of
such auditors to participate in any such discussions requested by ADB. This is provided
that such discussions shall be conducted only in the presence of an authorized officer of
the through the Project Executing Agency, unless the Borrower through the Project
Executing Agency shall otherwise agree.
ADB Loan 3123-INO: Metropolitan Sanitation Management Investment Project
Quarterly Report No. 1, February 2018 48
Section 6
The Borrower shall enable ADB's representatives to review the Project, inspect the Goods and
Works, and obtain any relevant records and documents.
Section 7
The Borrower shall ensure that any facilities relevant to the Project are operated, maintained
and repaired in accordance with sound applicable technical, financial, business, development,
operational and maintenance practices.
ADB Loan 3123-INO: Metropolitan Sanitation Management Investment Project
Quarterly Report No. 1, February 2018 49
7 Major Issues/Problems and Proposed/Recommended Remedial Actions
7.1 Problems and Rectification
The key problems that we have at this stage, focusing on immediate issues and rectifications are
highlighted the Project Risk Register in table xx. The table highlights some of the main Project related
risks that will need to be managed throughout the project term. The document is fluid and will
therefore be regularly updated, illustrating risk mitigation and conclusion when the risk no longer
exists. Below are a summary of some of the key points are;
For Pekanbaru
In 2017 Pekanbaru’s Government has started the Earthwork Contract for the access and
operational road only at/to WWTP site only. The budget provided in 2017 through the APBD
was USD 230,769 (IDR 3 billion, assumption 1 USD = IDR 13,000) and in 2018 with budget of
USD 230.769 (IDR 3 billion) will be available. The PISC considers this budget extremely
insufficient.
Adjustment of unit price is required as orginal budget based on price of 2013.
The design and methodology of the sewer installation is based on the design field conditions
and views of the design Consultant and must be adjusted to the current conditions. Whilst
budgets have been prepared associated with the works cost, at this stage it is not understood
if the cost estimator appreciated the most suitable construction practice associated with the
pipeline Installation. There is also a request from LG not to use open trench construction
methods in the main carriageways. Open cut methods will result in traffic management issues
and in some cases road closure where diversionary works will be necessary. Trenchless
construction will be considered where practical however such method of construction may
have practical and cost restraints associated with them.
The geotechnical survey work undertaken by the Consultant for the construction of WWTP is
poor and not informative particularly in relation to the depth of the hardsoil (bedrocks). The
soil investigation carried is limited to a depth of approximately 5 metres. A geotechnical
survey of the area is essential to provide the most appropriate analysis and basis for design.
Pekanbaru City Government already has EIA Document (Andal and RKL / RPL) for MSMIP
project and will be the basis for the issuance of the sewer installation permit and construction
of WWTP.
The pump station for Pekanbaru is located on the most impractical side of the river for
engineering purposes
There is a new regulation related to the domestic wastewater quality discharge standard that
is Permen LHK 68/1026 which is not the current reference of the WWTP Design.
ADB Loan 3123-INO: Metropolitan Sanitation Management Investment Project
Quarterly Report No. 1, February 2018 50
Figure 7.1 Earthworks for WWTP Site in Pekanbaru
Figure 7.2 Location for Pumping Station
For Jambi
In 2017, Jambi’s Government conducted earthworks for a part of WWTP site. It is an access
road covered by a budget of USD 76,923 (IDR 1 billion). In 2018, Jambi’s Government has plan
to continue the Earthworks for the WWTP but it will not cover the complete WWTP site that
is already purchased.
ADB Loan 3123-INO: Metropolitan Sanitation Management Investment Project
Quarterly Report No. 1, February 2018 51
There is no Geotechnical information available for Jambi
There is a reduction to the site area for the WWTP at Jambi
Jambi’s Government has purchased the Land for WWTP, and now the National Land Agency
(BPN) of Jambi is conducting an areas measurement before being issued with a land ownership
certificate (SHM).
The land areas for the Pumping Station is sufficient, however, it should be noted that the width
of access to site is very challenging and will require resettlement of certain prperties
The rising main between the pump station and the WWTP will be challenging. There is limited
space at the pump station site for the downstream pipeline..
The ground conditions are poor at Jambi again and the current design illustrates a major
structure to be housed in these poor conditions with no geotechnical information for the site.
In 2016 Jambi’s Government has allocated the budget for purchase of the access road but it
could not be implemented due to the rejection of owners to sell their house. Finally the budget
is idle and reallocated to 2018 financial year.
Figure 7.3 Earthwork at WWTP Site
ADB Loan 3123-INO: Metropolitan Sanitation Management Investment Project
Quarterly Report No. 1, February 2018 52
Figure 7.4 Current Situation at PS Site
For Makassar
The PISC were informed during a site visit that the dispute over land causing security issues at
the site were resolved on 26th October 2017 however this has not been the case to date.
The land that was given to PISC for the detailed design purposes for Pump Station A has since
been issued for a carpark. PISC have raised concerns about this issue and have requested the
plans for the car park so to understand the impact if the development. If it is matter not
resolved PISC will recommend that a new site is found
The Earthwork Contract A for the area of the site that is to contain sludge beds has been
implemented yet works was meant to commence on the main part of the site in order to
implement the construction process accordingly.
ADB Loan 3123-INO: Metropolitan Sanitation Management Investment Project
Quarterly Report No. 1, February 2018 53
Figure 7.5 Plan of Canal Accross The WWTP Site
ADB Loan 3123-INO: Metropolitan Sanitation Management Investment Project
Quarterly Report No. 1, February 2018 54
Table 7-1 Project Risk Register
Risk ID Risk Areas Description Impact
Likelihood Consequences Risk Rating
Responsible Party
Mitigation
Rar
e
Un
like
ly
Po
ssib
le
Like
ly
Alm
ost
Ce
rtai
n
Mar
gin
al
Min
or
Mo
de
rate
Maj
or
Seve
re
Low
Me
diu
m
Hig
h
Cri
tica
l
I PLANNING AND DESIGN
A-10 General – Budget for works
Budget that have been developed for the different Cobtracts are insufficient
Budget is unavailable for the complete works
DGHS PISC to provide a cost estinmate against the contract and provide a basis for the new budget
A-20 Makassar – WWTP Site
Land Not Available No wastewater treatment plant to satisfy discharge standards
LG Ensure the ownership papers are acquired and approved
A-21 Works Completed but not as per the contract
Ground Settlement issues on roadways and pipe corridors
PISC Provide suitable Geotechnical Design to ensure the future design works account for any inefficiency in the earthworks design
A-22 Dinas PU of South Sulawesi Province will build new big drainage canal right on the IPAL’s building site impacting on the current design,
The current General Arrangment of the tanks and process equipment will be affected
PISC Consultant will coordinate with LG Makassar and Dinas PU of SS Province to receive canal drawings and re-design works
A-23 WWTP Design does not meet the Discharge Standards
New plant will not mee the local legislation on discharge standards and fines may be incurred
PISC PISC to design the plantto meet the necessary disscharge standards
A-31 Makassar – Pump Station sites
In 2018 LG Makasar will build a Parking area at Pumping Station A and have requested that PISC design a pump station beneath the site of the new car park
Pump Station re-design efforts required or new site required
DGHS – new
location PISC Design
Issues
Opt for a new location
Provide a safe robust design
Identify with the carpark designer and coordinate effectively
A-32 Pump Station Land is unavailable
No pump stations hence a requirement to identify new land, re-design.
LG Ensure the ownership papers are acquired and approved
A-41 Makassar - Networks
Inadequate Design Increased time on the Design programme
PISC Design review to include hydraulic performance. Re-design where necessary
A-42 Inadequate Topograhical Survey
Increased time on the Design programme
PISC Design review to include hydraulic performance. Re-design where necessary
A-43 WWTP Design does not meet the Discharge Standards
New plant will not mee the local legislation on discharge standards and fines may be incurred
PISC PISC to design the plantto meet the necessary disscharge standards
A-51 Pekanbaru – WWTP Site
Land Not Available Search for a new site LG Ensure the ownership papers are acquired and approved
A-52 The LG’s budget associated with Earthworks inadequate.
Earthworks Contract A is not completed on time that will impact the Contract B programme timeframe
DGHS Early discussions required on methods of financing the earthworks contracts for example through LG, DGHS or ADB. Assist LG with completion of earthworks.
Establish a
suitabl
Extremely Poor Ground Conditions
Higher cost of construction and longer timeframes to deliver the works
PISC
ADB Loan 3123-INO: Metropolitan Sanitation Management Investment Project
Quarterly Report No. 1, February 2018 55
Risk ID Risk Areas Description Impact
Likelihood Consequences Risk Rating
Responsible Party
Mitigation
Rar
e
Un
like
ly
Po
ssib
le
Like
ly
Alm
ost
Ce
rtai
n
Mar
gin
al
Min
or
Mo
de
rate
Maj
or
Seve
re
Low
Me
diu
m
Hig
h
Cri
tica
l
e Geotechnical
Investigation
and re-establis
h a budget estimat
e.
A-54 Pekanbaru – Pump Station
Pump Station Land is unavailable
No pump stations hence a requirement to identify new land, re-design.
LG Ensure the ownership papers are acquired and approved
A-55 Extremely Poor Ground Conditions
Higher cost of construction and longer timeframes to deliver the works
PISC Establish a suitable Geotechnical Investigation and re-establish a budget estimate.
A-60 Pekanbaru - Networks
Inadequate Design Increased time on the programme PISC Design review to include hydraulic performance. Re-design where necessary
A-61 Inadequate Topograhical Survey
Increased time on the Design programme
PISC Design review to include hydraulic performance. Re-design where necessary
I-A-70 Jambi – WWTP Site Land Not Available Search for a new site LG Ensure the ownership papers are acquired and approved
A-71 Part of the land are unavailable
The design for the WWTP site will be incorrect
LG Re-design the works
A-72 The LG’s budget associated with Earthworks inadequate.
Earthworks Contract A is not completed on time that will impact the Contract B programme timeframe
DGHS Early discussions required on methods of financing the earthworks contracts for example through LG, DGHS or ADB. Assist LG with completion of earthworks.
A-73 Extremely Poor Ground Conditions
Higher cost of construction and longer timeframes to deliver the works
PISC Establish a suitable Geotechnical Investigation and re-establish a budget estimate.
A-74 WWTP Design does not meet the Discharge Standards
New plant will not mee the local legislation on discharge standards and fines may be incurred
PISC PISC to design the plantto meet the necessary disscharge standards
A-81 Jambi – Pump Station Site
Pump Station Land is unavailable
No pump stations hence a requirement to identify new land, re-design.
LG Ensure the ownership papers are acquired and approved.
Review and re-design the works
A-82 Resettlement of inhabitatnts at site
Higher cost associated with construction of the plant and social issues associated with resettlement of the area.
LG DGHS send letter to Mayor for asking recommitment for budget allocation in 2018.
Consultant to re-design
A-83 Restrictions to access at the site
Impractical for tanker use, difficult to access for operation and maintenance staff.
LG Find alternative route for access route.
PISC to re-design
ADB Loan 3123-INO: Metropolitan Sanitation Management Investment Project
Quarterly Report No. 1, February 2018 56
Risk ID Risk Areas Description Impact
Likelihood Consequences Risk Rating
Responsible Party
Mitigation
Rar
e
Un
like
ly
Po
ssib
le
Like
ly
Alm
ost
Ce
rtai
n
Mar
gin
al
Min
or
Mo
de
rate
Maj
or
Seve
re
Low
Me
diu
m
Hig
h
Cri
tica
l
A-90 Jambi - Networks Inadequate Design Increased time on the programme PISC Design review to include hydraulic performance. Re-design where necessary
A-91 Inadequate Topograhical Survey
Increased time on the Design programme
PISC Design review to include hydraulic performance. Re-design where necessary
B PROCUREMENT
B-01 Bidding Committee The number of eligible committees at provincial level cannot be established. Some committee have reasonable procurement capacity but no experience with ADB.
Implementation of the Bidding becomes longer so the project may be delayed and cost overrun may occur
DGHS Provide a realistic model for the Committee and plan accordingly
Some members of the Bidding Committee are from DGHS
B-02 Bidding documents Base on the regulation for all project with amount above of IDR 100 billion require approval from DGHS approval from ADB for ICB package. Possibility Bidding Documents are not approved
Implementation of the Bidding becomes longer so the project may be delayed and cost overrun may occur
DGHS Intensive communication and coordination with DGHS and ADB.
Support from PISC including on-the-job training in procurement to the executing and implementing agencies during project implementation
B-03 Number of Bidders. Limited participants who meet the minimum requirements (technical and financial) as set forth in the Bidding Document
Bidding Failed and need for further pre qualification/tender negotiation excercise.
The poor selection of contractors due to low bids, with no technical capability to handle the project will lead to cost overruns, schedule delays, poor quality of construction, and a final result that is not acceptable
DGHS Identify the most qualified contractors early via an ethical prequalification system and draft out the most suitable contract type as applicable to the conditions of the project.
B-04 Bidding interventions
There are certain party outside interfere the committee that affect the process and the results of the tender
Bidding Failed, Packages are cancelled
DGHS DGHS guarantees the independence of the Bidding process and rule out any unethical behavior
Implement full E-Procurement
B-05 House Connections
1,000 house connections are being constructed under the Contracts. LG is responsible for all the others. If the contracts are not coordinated the flows through the sewer will be insufficient.
Inadequate/diluted flows at the WWTP, Extensive flushing of sewers
DGHS Careful coordination between DGHS and LG on the timing of wet connection works
Implement full E-Procurement
C CONSTRUCTION
ADB Loan 3123-INO: Metropolitan Sanitation Management Investment Project
Quarterly Report No. 1, February 2018 57
Risk ID Risk Areas Description Impact
Likelihood Consequences Risk Rating
Responsible Party
Mitigation
Rar
e
Un
like
ly
Po
ssib
le
Like
ly
Alm
ost
Ce
rtai
n
Mar
gin
al
Min
or
Mo
de
rate
Maj
or
Seve
re
Low
Me
diu
m
Hig
h
Cri
tica
l
C-01 Weather and Climatic conditions
Rainy season with high rainfall will temporarily stop the activity in the field.
The work on the site will temporarily obstructed, project will be delayed and cost overrun
DGHS Preparing the construction schedule with anticipation of temporary closures based on seasonal change and allow additional time in the schedule to compensate for delays caused by inclement weather; Consider alternative construction methodologies
C-02 Poor safety procedures. Reduce risk to workers and the public during construction
Number of accidents involving construction activities
Project will be delayed and cost overrun
DGHS Contractor to ensure that a Safety Plan
is provided from the start of the Construction programme and manages safety processes in accordance with the manual and the Clients requirements.
C-03 Traffic closures not coordinated with local community
There will lead to protests from the community around the project,
Project stop and Project will be delayed and cost overrun
DGHS PISC for
associated Design issues
Socialization is conducted to the affected communities more early by involving the local government and the authorities i.e the traffic police.
Designing a work area that takes into account the surrounding conditions as well as traffic management
Community Liaison to ensure that the local community are fully engaged with the project from the outset.
C-04 Overlapping with other project in schedule
Project have interfaces with other works ie Makassar there will be overlapping with Canal Project for WWTP and Parking Areas with PS-A
Project will be delayed and cost overrun
DGHS Coordinate as early as possible and as often as possible, so that work schedules can be synchronized, and need to adjust the scope of each work to get the best results for both projects
C-05 Decommissioning septic tanks
No decommissioning of septic tanks
Hydrogen sulphide corrodes the concrete constructed septic tank over time causing a hazard and possible fatal situation.
DGHS DGHS to identify the means of providing a budget for decommissioning of septic tanks
C-06 Construction Noise Construction or pile driving noise and vibration impacting adjacent businesses or residents
Complainsts about Construction efforts
DGHS Community Liaison to ensure that the local community are fully engaged with the project from the outset.
Use sound proofing and vibration handling equipment where necessary
ADB Loan 3123-INO: Metropolitan Sanitation Management Investment Project
Quarterly Report No. 1, February 2018 58
ADB Loan 3123-INO: Metropolitan Sanitation Management Investment Project
Quarterly Report No. 1, February 2018 59
7.2 Delays in consultant recruitment/ issuance of DIPA
7.2.1 PISC Mobilization.
A challenge to the PISC at this stage of the project, is mobilising the necessary key International staff
which exist for a number of reasons listed below;
1. The project was tendered in June 2016 and finally awarded in October 2017 following a long
period of negotiation during which key experts signed CVs to accept the positions, the period
between signing and commencing tasks proved too long for the named Team Leader, Andrew
Mclernon, who accepted another position. Andrew will be replaced by Malcolm Ehrlich.
2. On intial review of all available data, PISC realised that the number of key personnel actually
required to deliver the design would be greater than that proposed in the RFP. Whilst
preparing a comprehensive Addendum, PISC have found it difficult to fill all positions which is
requirement by CPMU in order to sign off the Addendum.
3. Based on previous projects, the PISC have experience in mobilising International Experts to
Indonesia and the minimum time normally allowed for HR to process visas can be two months.
There are a mixture of key personnel on the project from UK, Phillippines and Australia. Staff
from Phillippines have an additional requirement to receive an Overseas Employment
Certificate (EOC), from Phillippines as well as going through the necessary process’s in
Indonesia.
PISC management immediately identified the risk proposed through and made adjustments to the
mobilization plan to ensure the output targets and outcomes contained in the TOR can be achieved
and can immediately coordinate with the PPIU and LPMU in the region. It is important to regularly
review and update the plan and this will be done so for each monthly report.
In accordance with the original plan, and agreed upon in the Inception Report, the team mobilisation
for each city will be carried out at the Supervision of Construction stage, while the Design Review and
re-design phase will be fully implemented in Jakarta. However, to obtain accurate data and latest plans
from each PPIU, the Consultant still needs to conduct surveys and verifications in Pekanbaru, Jambi
and Makassar.
7.3 Potential covenant compliance issues
Part of the purpose of the PISC is to identify any early signs of Critical Items that may impact on the
outcome of the Contract, its timeframe or cost. The main issues that PISC have recognised are covered
throughout this report and those apparent as covenant compliance issues are those in respect of
Land Acquisition – WWTP and Pump Station Sites
Earthworks Contracts being fulfilled – issues with all sites
Budgets associated with LG – major budget concerns associated with LG for earthworks, house
connections and a social safeguard programme
Quality associated with the physical design – the designs that have been passed on to PISC to
implement Tender and Construction Supervision are insufficient to do so
Additional Studies to provide a detailed design ie topographical/geotechnical studies required
even though detailed designs have been provided
ADB Loan 3123-INO: Metropolitan Sanitation Management Investment Project
Quarterly Report No. 1, February 2018 60
7.4 Project Audit Issues
ADB shall disclose the annual audited financial statements for the Project and the opinion of the
auditors on the financial statements within 30 days of the date of their receipt by posting them on
ADB’s website. The annual audited financial statements itself are prepared by EA by assign BPK or
BPKP as official auditor for MSMIP Project.
Until now it has not been decided yet which institutions will audit this project, both for Output 1 and
Output activities 2. DGHS as executing agency should immediately decide whether BPK or BPKP will
act as project audit so that parties can be aware of audit issues.
ADB Loan 3123-INO: Metropolitan Sanitation Management Investment Project
Quarterly Report No. 1, February 2018 61
8 Expected Activities in the next Quarter The following activities are expected to be implemented as deailed under the Project Schedule in the
next quarter between 2nd January 2018 and 2nd April 2018
Topographical Surveys for sites where required
Geotechnical Investigations for sites where required
Continuation and finalization of cost estimates for Makassar Contracts C to allow Satker
Makassar to launch prequalification
Continuation of detailed design for Makassar Contract C
Preparation of General Specifications associated with all National Contracts related to the
project
Preparation of the Tender Documents for Makassar Contract C
Preparation of Drawing Packages associated with Makassar Contract C
Detailed Design for the networks associated with Pekanbaru
Initial review on Social Safeguards and Resettlement
Initial review on Gender and Social Development
Initial review of the Environmental Status of the project
Continue recruitment of staff in accordance with the Contract and with he Addendum 1 when
approved
ADB Loan 3123-INO: Metropolitan Sanitation Management Investment Project
Quarterly Report No. 1, February 2018 62
App A – Project Organisation
ADB Loan 3123-INO: Metropolitan Sanitation Management Investment Project
Quarterly Report No. 1, February 2018 63
App B – Design Phase Project Schedule
ADB Loan 3123-INO: Metropolitan Sanitation Management Investment Project
Quarterly Report No. 1, February 2018 64
Pekanbaru
ADB Loan 3123-INO: Metropolitan Sanitation Management Investment Project
Quarterly Report No. 1, February 2018 65
Jambi
ADB Loan 3123-INO: Metropolitan Sanitation Management Investment Project
Quarterly Report No. 1, February 2018 66
Makassar
ADB Loan 3123-INO: Metropolitan Sanitation Management Investment Project
Quarterly Report No. 1, February 2018 67
App C – Staffing Schedule
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 402021
O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D JJAKARTA
Key Personnel (International)
16 Original 16.00
34 Addendum No. 1 34.00
6 Original 6.00
10.25 Addendum No. 1 10.25
4 Original 4.00
6 Addendum No. 1 6.00
3 Original 3.00
9 Addendum No. 1 9.00
4 Original 4.00
4 Addendum No. 1 4.00
3 Original 3.00
3 Addendum No. 1 3.00
3 Original 3.00
7 Addendum No. 1 7.00
0 Original 0.00
4 Addendum No. 1 4.00
0 Original 0.00
6 Addendum No. 1 6.00
0 Original 0.00
6 Addendum No. 1 6.00
0 Original 0.00
4 Addendum No. 1 4.00
0 Original 0.00
4 Addendum No. 1 4.00
0 Original 0.00
10 Addendum No. 1 10.00
Key Personnel (National)
40 Original 40.00
39.5 Addendum No. 1 39.50
16 Original 16.00
39 Addendum No. 1 39.00
18 Original 18.00
18 Addendum No. 1 18.00
3 Original 3.00
6 Addendum No. 1 6.00
6 Original 6.00
10 Addendum No. 1 10.00
4 Original 4.00
10 Addendum No. 1 10.00
0 Original 0.00
10 Addendum No. 1 10.00
0 Original 0.00
6 Addendum No. 1 6.00
0 Original 0.00
6 Addendum No. 1 6.00
0 Original 0.00
6 Addendum No. 1 6.00
0 Original 0.00
3 Addendum No. 1 3.00
0 Original 0.00
4 Addendum No. 1 4.00
0 Original 0.00
5 Addendum No. 1 5.00
Non Key Personnel (National)
40 Original 40.00
39.5 Addendum No. 1 39.50
40 Original 40.00
38 Addendum No. 1 38.00
40 Original 40.00
38.5 Addendum No. 1 38.50
40 Original 40.00
38.5 Addendum No. 1 38.50
6 Original 6.00
38.5 Addendum No. 1 38.50
40 Original 40.00
39 Addendum No. 1 39.00
40 Original 40.00
38.5 Addendum No. 1 38.50
40 Original 40.00
38.5 Addendum No. 1 38.50
0 Original 0.00
38.5 Addendum No. 1 38.50
0 Original 0.00
35 Addendum No. 1 35.00
0 Original 0.00
6 Addendum No. 1 6.00
0 Original 0.00
6 Addendum No. 1 6.00
0 Original 0.00
5 Addendum No. 1 5.00
0 Original 0.00
5 Addendum No. 1 5.00
0 Original 0.00
38.5 Addendum No. 1 38.50
0 Original 0.00
38 Addendum No. 2 38.00
0 Original 0.00
38.5 Addendum No. 1 38.50
0 Original 0.00
38.5 Addendum No. 1 38.50
Period of Services
2017 2018 2019 2020
STAFFING SCHEDULE - JAKARTA
No. Name PositionKey or Non
KeyNationality Input
Original/
Addendum No. 1
2. Anthony Gunadi Wastewater Treatment Process Engineer Key International
1.Andrew Mclernon/
Malcolm EhrlichTeam Leader / Wastewater Specialist Key International
4. Napolean Lagura Mechanical Expert Key International
3. Ananda De Costa Civil/Structural Expert Key International
6. Joselito Losario Environmental Specialist Key International
5. Rosemary Faletese Gender and Social Development Specialist Key International
8. Brian Hayden Senior Infrastructure Specialist (Start Up) Key International
7. Victoria R Pineda Social Safeguards / Resettlement Specialist Key International
10. William Sharp Civil Expert Key International
9. Paul Jenkins Design Manager Key International
12. TBN Geotechnical Expert Key International
11. TBN Senior Electrical Expert Key International
1. Benny Aryanto Deputy Team Leader Key National
13. TBN Senior Procurement & Contract Specialist Key International
3. Afdatira MIS Specialist Key National
2. Thariq Marzuki Financial Management Specialist Key National
5. Treesnowati Benefit Monitoring Specialist Key National
4. Indiarto Budi Electrical Expert Key National
7. Wildan Civil Engineer Key National
6. Budiman Cost Estimator Key National
9. Henry Mechanical Engineer Key National
8. Yani Haryardi Structural Engineer Key National
11. Leo De Santos Sewerage Engineer 2 Key National
10. Fihaus Sewerage Engineer 1 Key National
13. M. Zaki Geotechnical Engineer Key National
12. Teuku Fajar Sodik Procurement and Contract Specialist Key National
2. TBN Accounting Specialist Non Key National
1. Utami Kusumaningrum Office Manager Non Key National
4. TBN GIS - IT Support Non Key National
3. TBN Bilingual Secretary Non Key National
6. Safrizal Atmawijaya Office Boy Non Key National
5. TBN Engineering Support 1 / Drafting Non Key National
8. TBN Guard 2 Non Key National
7. TBN Guard 1 Non Key National
10. TBN Engineering Support 3 / Drafting Non Key National
9. TBN Engineering Support 2 / Drafting Non Key National
12. TBN Mechanical CAD Non Key National
11. TBN Structural CAD Non Key National
14. TBN Process CAD Non Key National
13. TBN Electrical CAD Non Key National
16. TBN Technical Translator Non Key National
15. TBN Document Controller Non Key National
18. TBN Administrator (CPMU) Non Key National
17. TBN Administrator (PISC) Non Key National
4.25
2.00
6.00
0.00
0.00
4.00
Total Person Month
OriginalAdd.
No. 1Balance
18.00
-0.50
23.00
0.00
3.00
4.00
6.00
4.00
6.00
6.00
4.00
4.00
10.00
5.00
-0.50
-2.00
-1.50
-1.50
32.50
10.00
6.00
6.00
6.00
3.00
4.00
38.50
6.00
5.00
5.00
38.50
38.00
38.50
-1.00
-1.50
-1.50
38.50
35.00
6.00
ADB Loan 3123-INO: Metropolitan Sanitation Management Investment Project
Quarterly Report No. 1, February 2018 68
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40
2021
O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J
PEKANBARU
Key Personnel (International)
27 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00
27 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00
12 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 12.00
12 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 12.00
Subtotal 39.00 39.00 0.00
Key Personnel (National)
27 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00
27 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00
27 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00
27 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00
24 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 24.00
24 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 24.00
6 Original 1.00 1.00 1.00 1.00 1.00 1.00 6.00
6 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 6.00
4 Original 1.00 1.00 1.00 1.00 4.00
4 Addendum No. 1 1.00 1.00 1.00 1.00 4.00
4 Original 1.00 1.00 1.00 1.00 4.00
4 Addendum No. 1 1.00 1.00 1.00 1.00 4.00
4 Original 1.00 1.00 1.00 1.00 4.00
4 Addendum No. 1 1.00 1.00 1.00 1.00 4.00
12 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 12.00
12 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 12.00
27 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00
27 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00
27 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00
27 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00
4 Original 1.00 1.00 1.00 1.00 4.00
4 Addendum No. 1 1.00 1.00 1.00 1.00 4.00
6 Original 1.00 1.00 1.00 1.00 1.00 1.00 6.00
6 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 6.00
0 Original 0.00
2 Addendum No. 1 0.25 1.00 0.75 2.00
Subtotal 172.00 174.00 2.00
Non Key Personnel (National)
27 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00
27 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00
27 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00
27 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00
27 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00
27 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00
27 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00
27 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00
6 Original 1.00 1.00 1.00 1.00 1.00 1.00 6.00
27 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00
6 Original 1.00 1.00 1.00 1.00 1.00 1.00 6.00
0 Addendum No. 1 0.00
6 Original 1.00 1.00 1.00 1.00 1.00 1.00 6.00
22 Addendum No. 1 0.25 1.00 0.75 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 22.00
6 Original 1.00 1.00 1.00 1.00 1.00 1.00 6.00
22 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 22.00
27 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00
27 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00
27 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00
27 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00
27 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00
27 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00
27 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00
27 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00
27 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00
27 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00
27 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00
27 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00
27 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00
27 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00
27 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00
27 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00
27 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00
27 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00
27 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00
27 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00
27 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00
27 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00
14. TBN Field Supervisor 6 Non Key National 0.00
19. TBN Guard 2 Non Key National 0.00
18. TBN Guard 1 Non Key National 0.00
17. TBN Office Boy Non Key National 0.00
16. TBN Field Supervisor 8 Non Key National 0.00
15. TBN Field Supervisor 7 Non Key National 0.00
8. TBN Surveyor Support 2 Non Key National 16.00
13. TBN Field Supervisor 5 Non Key National 0.00
12. TBN Field Supervisor 4 Non Key National 0.00
11. TBN Field Supervisor 3 Non Key National 0.00
10. TBN Field Supervisor 2 Non Key National 0.00
9. TBN Field Supervisor 1 Non Key National 0.00
2. TBN Accounting Specialist Non Key National 0.00
7. TBN Surveyor Support 1 Non Key National 16.00
6. TBN Engineering Support 2 / Drafting Non Key National -6.00
5. TBN Engineering Support 1 / Drafting Non Key National 21.00
4. TBN GIS - IT Support Non Key National 0.00
3. TBN Bilingual Secretary Non Key National 0.00
9. Johan KhadafiPublic Relations / Sanitation Marketing
SpecialistKey National 0.00
1. TBN Office Manager Non Key National 0.00
13. TBN Cost Estimator Key National 2.00
12. Agus Yudiarto Social Safeguard / Resettlement Key National 0.00
11. Harly Suhartono Gender and Social Development Specialist Key National 0.00
10. Julianty Health and Safety Coordinator Key National 0.00
3. Rusman Sihotang Structural Engineer Key National 0.00
8. Achmad Basari Procurement and Contract Specialist Key National 0.00
7. Bistok Panjaitan Electrical Engineer Key National 0.00
6. Adi Andhika Geotechnical Specialist Key National 0.00
5. Mohammad Alexin Putra Mechanical Engineer Key National 0.00
4. Hani Andriani Environmental Expert Key National 0.00
1. Paul JenkinsCity Office Leader / Sewerage Construction
Supervisor - PekanbaruKey International 0.00
2. Tanto Widyo Hendarto Sewerage Engineer Key National 0.00
1. Leo Sando Silvado Sewerage Engineer Key National 0.00
2. Roodolfo Nicolas WWTP / Construction Supervisor - Pekanbaru Key International 0.00
STAFFING SCHEDULE - PEKANBARU
No. Name PositionKey or Non
KeyNationality Input
Original/
Addendum No. 1
Period of ServicesTotal Person-
Month Input
Original
Addend
um No.
1
Balance2017 2018 2019 2020
ADB Loan 3123-INO: Metropolitan Sanitation Management Investment Project
Quarterly Report No. 1, February 2018 69
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40
2021
O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J
JAMBI
Key Personnel (International)
27 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00
27 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00
12 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 12.00
12 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 12.00
Subtotal 39.00 39.00 0.00
Key Personnel (National)
27 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00
27 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00
27 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00
27 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00
24 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 24.00
24 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 24.00
6 Original 1.00 1.00 1.00 1.00 1.00 1.00 6.00
6 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 6.00
4 Original 1.00 1.00 1.00 1.00 4.00
4 Addendum No. 1 1.00 1.00 1.00 1.00 4.00
4 Original 1.00 1.00 1.00 1.00 4.00
4 Addendum No. 1 1.00 1.00 1.00 1.00 4.00
4 Original 1.00 1.00 1.00 1.00 4.00
4 Addendum No. 1 1.00 1.00 1.00 1.00 4.00
12 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 12.00
12 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 12.00
27 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00
27 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00
27 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00
27 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00
4 Original 1.00 1.00 1.00 1.00 4.00
4 Addendum No. 1 1.00 1.00 1.00 1.00 4.00
6 Original 1.00 1.00 1.00 1.00 1.00 1.00 6.00
6 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 6.00
0 Original 0.00
2 Addendum No. 1 0.25 1.00 0.75 2.00
Subtotal 172.00 174.00 2.00
Non Key Personnel (National)
27 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00
27 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00
27 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00
27 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00
27 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00
27 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00
27 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00
27 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00
6 Original 1.00 1.00 1.00 1.00 1.00 1.00 6.00
27 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00
6 Original 1.00 1.00 1.00 1.00 1.00 1.00 6.00
0 Addendum No. 1 0.00
6 Original 1.00 1.00 1.00 1.00 1.00 1.00 6.00
22 Addendum No. 1 0.25 1.00 0.75 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 22.00
6 Original 1.00 1.00 1.00 1.00 1.00 1.00 6.00
22 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 22.00
27 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00
27 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00
27 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00
27 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00
27 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00
27 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00
27 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00
27 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00
27 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00
27 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00
27 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00
27 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00
27 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00
27 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00
27 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00
27 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00
27 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00
27 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00
27 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00
27 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00
27 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00
27 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.0019. TBN Guard 2 Non Key National 0.00
18. TBN Guard 1 Non Key National 0.00
12. TBN Field Supervisor 4 Non Key National 0.00
17. TBN Office Boy Non Key National 0.00
16. TBN Field Supervisor 8 Non Key National 0.00
15. TBN Field Supervisor 7 Non Key National 0.00
14. TBN Field Supervisor 6 Non Key National 0.00
13. TBN Field Supervisor 5 Non Key National 0.00
6. TBN Engineering Support 2 / Drafting Non Key National -6.00
11. TBN Field Supervisor 3 Non Key National 0.00
10. TBN Field Supervisor 2 Non Key National 0.00
9. TBN Field Supervisor 1 Non Key National 0.00
8. TBN Surveyor Support 2 Non Key National 16.00
7. TBN Surveyor Support 1 Non Key National 16.00
13. TBN Cost Estimator Key National 2.00
5. TBN Engineering Support 1 / Drafting Non Key National 21.00
4. TBN GIS - IT Support Non Key National 0.00
3. TBN Bilingual Secretary Non Key National 0.00
2. TBN Accounting Specialist Non Key National 0.00
1. TBN Office Manager Non Key National 0.00
7. Agustinus Sukowidodo Electrical Engineer Key National 0.00
12. Cahaya Hondro Social Safeguard / Resettlement Key National 0.00
11. Sri Mulyasari Gender and Social Development Specialist Key National 0.00
10. Fawitasari Fransisca Health and Safety Coordinator Key National 0.00
9. BurhanuddinPublic Relations / Sanitation Marketing
SpecialistKey National 0.00
8. Slamet Haryanta Procurement and Contract Specialist Key National 0.00
1. Adung Sewerage Engineer Key National 0.00
6. Rendi Dwi Kartiko Geotechnical Specialist Key National 0.00
5. Dyos Santoso Mechanical Engineer Key National 0.00
4. Sentot Prasetyo Wijayanto Environmental Expert Key National 0.00
3. Yan Haryadi Structural Engineer Key National 0.00
2. Muhamad Nasir Sewerage Engineer Key National 0.00
2. Andrew Connel WWTP / Construction Supervisor - Jambi Key International 0.00
1. Malcolm EhrlichCity Office Leader / Sewerage Construction
Supervisor - JambiKey International 0.00
STAFFING SCHEDULE - JAMBI
No. Name PositionKey or Non
KeyNationality Input
Original/
Addendum No. 1
Period of ServicesTotal Person-
Month Input
Original
Addend
um No.
1
Balance2017 2018 2019 2020
ADB Loan 3123-INO: Metropolitan Sanitation Management Investment Project
Quarterly Report No. 1, February 2018 70
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40
2021
O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J
MAKASSAR
Key Personnel (International)
28 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 28.00
28 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 28.00
12 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 12.00
12 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 12.00
Key Personnel (National)
28 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 28.00
28 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 28.00
28 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 28.00
28 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 28.00
24 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 24.00
24 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 24.00
6 Original 1.00 1.00 1.00 1.00 1.00 1.00 6.00
6 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 6.00
4 Original 1.00 1.00 1.00 1.00 4.00
4 Addendum No. 1 1.00 1.00 1.00 1.00 4.00
4 Original 1.00 1.00 1.00 1.00 4.00
4 Addendum No. 1 1.00 1.00 1.00 1.00 4.00
4 Original 1.00 1.00 1.00 1.00 4.00
4 Addendum No. 1 1.00 1.00 1.00 1.00 4.00
12 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 12.00
12 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 12.00
28 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 28.00
28 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 28.00
28 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 28.00
28 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 28.00
4 Original 1.00 1.00 1.00 1.00 4.00
4 Addendum No. 1 1.00 1.00 1.00 1.00 4.00
6 Original 1.00 1.00 1.00 1.00 1.00 1.00 6.00
6 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 6.00
0 Original 0.00
2 Addendum No. 1 0.25 1.00 0.75 2.00
Non Key Personnel (National)
28 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 28.00
28 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 28.00
28 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 28.00
28 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 28.00
28 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 28.00
28 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 28.00
28 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 28.00
28 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 28.00
6 Original 1.00 1.00 1.00 1.00 1.00 1.00 6.00
28 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 28.00
6 Original 1.00 1.00 1.00 1.00 1.00 1.00 6.00
0 Addendum No. 1 0.00
6 Original 1.00 1.00 1.00 1.00 1.00 1.00 6.00
22 Addendum No. 1 0.25 1.00 0.75 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 22.00
6 Original 1.00 1.00 1.00 1.00 1.00 1.00 6.00
22 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 22.00
28 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 28.00
28 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 28.00
28 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 28.00
28 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 28.00
28 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 28.00
28 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 28.00
28 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 28.00
28 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 28.00
28 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 28.00
28 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 28.00
28 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 28.00
28 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 28.00
28 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 28.00
28 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 28.00
28 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 28.00
28 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 28.00
28 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 28.00
28 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 28.00
28 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 28.00
28 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 28.00
28 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 28.00
28 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 28.00
17. TBN Office Boy Non Key National 0.00
16. TBN Field Supervisor 8 Non Key National
19. TBN Guard 2 Non Key National 0.00
18. TBN Guard 1 Non Key National 0.00
0.00
15. TBN Field Supervisor 7 Non Key National 0.00
14. TBN Field Supervisor 6 Non Key National 0.00
13. TBN Field Supervisor 5 Non Key National 0.00
12. TBN Field Supervisor 4 Non Key National 0.00
11. TBN Field Supervisor 3 Non Key National 0.00
10. TBN Field Supervisor 2 Non Key National 0.00
9. TBN Field Supervisor 1 Non Key National 0.00
8. TBN Surveyor Support 2 Non Key National 16.00
7. TBN Surveyor Support 1 Non Key National 16.00
6. TBN Engineering Support 2 / Drafting Non Key National -6.00
5. TBN Engineering Support 1 / Drafting Non Key National 22.00
4. TBN GIS - IT Support Non Key National 0.00
3. TBN Bilingual Secretary Non Key National 0.00
2. TBN Accounting Specialist Non Key National 0.00
1. TBN Office Manager Non Key National 0.00
13. TBN Cost Estimator Key National 2.00
12. Dwi Apriyanti Social Safeguard / Resettlement Specialist Key National 0.00
11. Euis Masripah Gender and Social Development Specialist Key National 0.00
10. Dwi Prihanto Health and Safety Coordinator Key National 0.00
9. Harudin HartonoPublic Relations / Sanitation Marketing
SpecialistKey National 0.00
8. Yosep Sri Nuryanto Procurement and Contract Specialist Key National 0.00
7. Harlen Siahaan Electrical Engineer Key National 0.00
6. Suharso Bambang Geotechnical Specialist Key National 0.00
5. Henry Pranajaya Mechanical Engineer Key National 0.00
4. Adam Yajid Environmental Expert Key National 0.00
3. Safrial Rambe Structural Engineer Key National 0.00
2. Mulia Tobing Sewerage Engineer Key Natiomal 0.00
1. Burhanuddin Muhammad Sewerage Engineer Key National 0.00
2. Carlos De La Cruz WWTP / Construction Supervisor - Makassar Key International 0.00
1. Colin LeggCity Office Leader / Sewerage Construction
Supervisor - MakassarKey International 0.00
Original
Addend
um No.
1
Balance2017 2018 2019 2020
STAFFING SCHEDULE - MAKASSAR
No. Name PositionKey or Non
KeyNationality Input
Original/
Addendum No. 1
Period of Services Total Person Month
ADB Loan 3123-INO: Metropolitan Sanitation Management Investment Project
Quarterly Report No. 1, February 2018 71
App D – Progress Meetings
Day/Date : Thursday, 11 January 2018
Time : 09.00 – 11.00 WIT (West Indonesian Time)
Participants : CPMU and PISC (attendand list attached)
Location : Meeting Room of Head of Subdirectorate Wastewater, DSEH, DGHS Building 7fl.
Subject : Progress Report Meeting
No Meeting Result
A. General
Mr. Bryan Hayden as Acting TL introduce new experts that recently mobilized by PISC namely : Antoni Gunadi (Inernational Procces Engineer), and Wardiyanto (Geotechnocal Engineer).
Bryan present some key issues started with package scheme for construction works in each cities both funded by APBD/APBN and also by ADB Loan. There is Major Change that documented in ADB document mentioned that the scope of works are reduced to excced budget that cannot cover especially for ADB Loan.
The other issue is that the Earthworks for tree cities running not well due to budget limitation of Pemkot and the implication is uncertainty of earthwork completion and disrupt IPAL Construcion.
There is new regulation of Ministry of Environmental and Forestry (Permen LHK 68/2016) regarding efluent standar of domestic waste that shoud be consider for review design of IPAL in three cities, especially Amoniak parameter.
PISC has inform the schenario to take over remain earthworks by puit in Construction of IPAL as preparation actitivites. The consequences is the cost will be increase and due to ADB budget loecked, o the additional budget will cover by APBN.
There is major change document issued by ADB that inform reducing scope of works due to budget increase for 32%. The number of proverty connections in Makassar reduced from 14,400 units into 11,000 units (24%), Jambi from 20,200 units into 10,300 units (49%)and Pekanbaru from 17,200 units into 11,100 units (36%). PISC should check the design of those cities whether basaed on initial plan or already follow the major change.
Refer to schedule sample prepared by PISC for Makassar that show the full completion works especially for defect liability will be in year of 2022, mean that the loan should be extended.
B. Makassar
CPMU asks PISC to prepare new Detail Schedule for all cities as consequences of land issues.
The design of PS-A in citihall is refer to initial plan, and Design Pemkot for parking areas in the same location will be adjusted to PS-A design.
The design of IPAL by MWH is based on initial site avaibility with consider of canal construction plan by Dinas PU SDA Province of South Sulawesi.
The capacity of system based on 14,400 units for sewerage and IPAL.
PISC already check the reccomendation of Geotechnical Survey of MHW and its contractors due to methods of pipelaying construction (open cut and trenchless) and
ADB Loan 3123-INO: Metropolitan Sanitation Management Investment Project
Quarterly Report No. 1, February 2018 72
No Meeting Result
dewatering. PISC consider no need to conduct more geotechnical survey. It is sufficient to guide PISC to prepare review design of IPAL and Sewerage.
The design flow for Makassar considered ADWF (Average Dry Weather Flow) = EP x L/EP/day (EP = equivalent person); PDWF (Peak Dry Weather Flow) = 500 L/s = 43.2 ML/d; and PWWF (Peak Wet Weather Flow) = 1100 L/s = 95.04 ML/d for design togehter with by-pass system (completed with coarse filtration) if the flow is above PDWF.
C. Jambi
The design of sewerage and IPAL of Jambi is the worst among others, and PISC will fires conducted Geotechnical and Topographical Survey as support justification in review design.
PISC already prepared the final layout of IPAL for earthworks in 2018 if neccesary by Pemkot.
The design of IPAL Jambi is not complete with by-pass system as in Makassar, so the IPAL should able to treat PWWF (Peak Wet Weather Flow) that 5 time of ADWF (Average Wet Weather Flow). PISC will check it more detail regarding this finding and proposed to design as Makassar did.
There is no new information from Pemkot of Jambi regarding status of land for inlet and outlet pipe in Pumping Station.
There is no complete document of review/appraisal especially drawing of IPAL by MWH to Local Consultant’s DED. It was in ADB and CPMU will ask ADB the documents and send to PISC.
CPMU asks PISC to prepare new Detail Schedule for all cities as consequences of land issues.
D. Pekanbaru
PISC already prepared the final layout of IPAL for earthworks in 2018 if neccesary by Pemkot.
The design of IPAL Pekanbaru is not complete with by-pass system as in Makassar, so the IPAL should able to treat PWWF (Peak Wet Weather Flow) that 5 time of ADWF (Average Wet Weather Flow). PISC will check it more detail regarding this finding and proposed to design as Makassar did.
There is no complete document of review/appraisal especially drawing of IPAL by MWH to Local Consultant’s DED. It was in ADB and CPMU will ask ADB the documents and send to PISC.
CPMU asks PISC to prepare new Detail Schedule for all cities as consequences of land issues.