+ All Categories
Home > Documents > POLITECHNIKA WROCLAWSKA Design of a Water Network Using EPANET Faculty of Environmental Engineering...

POLITECHNIKA WROCLAWSKA Design of a Water Network Using EPANET Faculty of Environmental Engineering...

Date post: 22-Jan-2023
Category:
Upload: pwr-wroc
View: 0 times
Download: 0 times
Share this document with a friend
23
POLITECHNIKA WROCLAWSKA Design of a Water Network Using EPANET 07-02-2014 Tânia Moreira Dias Faculty of Environmental Engineering Automatics in Environmental Engineering
Transcript

POLITECHNIKA WROCLAWSKA

Design of a Water Network Using

EPANET

07-02-2014

Tânia Moreira Dias

Faculty of Environmental Engineering

Automatics in Environmental Engineering

Design of a Water Network using EPANET

1

Índice

1. Introduction ............................................................................................................... 2

2. General description of water network and hydraulic model ..................................... 3

2.1 Water network .................................................................................................... 3

2.2 Water Demand ................................................................................................... 8

2.3 Pumping Station ............................................................................................... 10

2.3.1 Controls applied to the pumping station .......................................................... 12

2.4 Water Tank ...................................................................................................... 13

3. Result of preliminary design of water network ....................................................... 14

3.1 Pressure distribution in the whole system and put screenshot ............................ 14

3.2 Velocity in the Pipes ........................................................................................ 16

3.3 Operational state of the pumping station ......................................................... 18

4. Cost reduction analysis............................................................................................ 19

4.1 Description of proposed system optimization ..................................................... 19

4.2 Cost reduction analysis ........................................................................................ 21

5. Conclusion ............................................................................................................... 22

Design of a Water Network using EPANET

2

1. Introduction

In order to ensure the availability of sufficient quantity of good quality of water, it

becomes imperative in a modern society to plan and build suitable water supply schemes,

which provides potable water to the community, which includes households and industry,

according to their demand.

This report consists on the description of the process of creation of a water network for a

fictional city using for that purpose the EPANET Software.

This report is divided in three main steps, the first one was to design a water network to

provide water to a fictional city. This city includes regular customers, people living in

households, and a high water demand factory that is responsible for the manufacture of

Jeans. This water network includes a tank, a pumping station and a reservoir.

The second step was to test the hydraulic model that was built in the first place and try to

make it functional.

The third and last step was to take the hydraulic model produced and try different

scenarios always aiming the cost reduction of the building of this water network.

Design of a Water Network using EPANET

3

2. General description of water network and hydraulic

model

2.1 Water network

Within this project was provided a scanned version of the map of the city, FIG X, that as

one can see consists on the representation of the demand points and their elevation, the

pipes that make the connection between the junctions, the tank and the reservoir.

Figure 1- Topographic Map of the City

Design of a Water Network using EPANET

4

In order to create the water supply system in EPANET Software, first map was vectored

using the AutoCad Software. The AutoCad drawing included only the isolines and the

pipes that connect the nodes of water demand. There was also the need to scale the map

to ‘real life’ measures, for that the length of the pipes were measured in the paper and

then re-sized with 1:5000 scale.

The drawing was after transferred to EPANET using the EPACAD, with this software is

possible to export the file in format .dxf and select only the layer containing the pipes of

the hydraulic model to start building your network.

It was also provided the total demand of water and the percentage of water demand at

each junction. With this data was possible to calculate the average water demand in each

node as one can see in the Table 1.

Table 1- %total water demand at each node

% total water demand

average water demand @ node, dm3/s

1 15,0% 20,34 2 15,5% 21,018 3 11,0% 14,916 4 16,0% 21,696 5 3,0% 4,068 6 10,5% 14,238 7 16,5% 22,374

8 12,5% 16,95 sum 100,0% 135,6

Design of a Water Network using EPANET

5

The Figure2 represents the water network after the input of all initial provided data, which

includes the elevation of the nodes, the length of the pipes, the location of the tank and

the Jeans Factory.

Figure 2- Components of the network for the city

Design of a Water Network using EPANET

6

The figure 2 represents the non-optimized water network that was modeled. Here it is

possible to see the location of the tank, the nodes and the pipes that connect them and a

pumping station. It is also possible to see the identification of the junctions and pipes

which are characterized in the tables below.

Table 2- Characterization of the Pipes

Length Diameter Roughness

Link ID m mm mm Pipe 1 344.85 176.2 0.05 Pipe 2 192.11 315 0.05 Pipe 3 290.71 220.4 0.05 Pipe 4 344.85 600 0.05 Pipe 5 286.27 312.8 0.05

Pipe 6 526.19 220.4 0.05 Pipe 7 258.06 312.8 0.05 Pipe 8 380.29 277.6 0.05 Pipe 9 268.52 396.6 0.05 Pipe 10 390.29 396.6 0.05 Pipe 11 219.03 396.6 0.05 Pipe 12 288.12 396.6 0.05 Pipe 13 50 396.6 0.05 Pipe 14 1 220.4 0.05 Pipe 15 2 220.4 0.05 Pipe 16 5 220.4 0.05 Pipe 17 7 220.4 0.05 Pipe 18 100 220.4 0.05

Pipe 19 7 220.4 0.05 Pipe 20 5 220.4 0.05

Design of a Water Network using EPANET

7

The water network is constituted by 20 HDPE pipe PN10, each one with different lengths

and diameter, as is described in Tab2. In this table are marked the maximum and

minimum diameter of the pipes, in red and green, respectively. The diameters of the pipes

were chosen using a manufacturer table below.

Table 3- Manufacturer Table of Pipe diameters

outside diameter (mm)

thickness of the wall (mm)

internal diameter (mm)

OD e ID 125 7,4 110,2 140 8,3 123,4 160 9,5 141 180 10,7 158,6 200 11,9 176,2 225 13,4 198,2 250 14,8 220,4 280 16,6 246,8 315 18,7 277,6 355 21,1 312,8 400 23,7 352,6 450 26,7 396,6

500 29,7 440,6 560 33,2 493,6 630 37,4 555,2

710 42,1 625,8 800 47,4 705,2 900 53,3 793,4

1000 59,3 881,4 1200 70,6 1058,8

𝐼𝑛𝑡𝑒𝑟𝑛𝑎𝑙 𝐷𝑖𝑎𝑚𝑒𝑡𝑒𝑟 = 𝑂𝑢𝑡𝑠𝑖𝑑𝑒 𝐷𝑖𝑎𝑚𝑒𝑡𝑒𝑟 − 2 × 𝑇ℎ𝑖𝑐𝑘𝑛𝑒𝑠𝑠 𝑜𝑓 𝑡ℎ𝑒 𝑤𝑎𝑙𝑙

Design of a Water Network using EPANET

8

Table 4- Characterization of the Junctions

Elevation Base Demand Head Pressure

Node ID m LPS m m Junc 7 107.34 22.374 166.69 59.35 Junc 8 106.41 20.34 166.70 60.29 Junc 9 108.65 20.34 166.69 58.04 Junc 10 107.35 16.95 166.65 59.30 Junc 11 105.32 14.238 166.45 61.13 Junc 12 103.73 21.696 166.60 62.87 Junc 13 102.47 14.916 166.89 64.42 Junc 14 104.42 21.018 166.80 62.38 Junc 15 102.375 4.068 167.22 64.85

Junc 16 102.723 4.068 167.41 64.69 Junc j2 105.32 75 166.41 61.09 Junc j14 102.7 0 167.43 64.73 Junc j15 102.7 0 167.43 64.73 Junc j16 102.7 0 103.22 0.52 Junc j17 102.7 0 103.22 0.52 Junc j19 102.7 0 167.43 64.73 Junc j20 102.7 0 167.43 64.73 Junc j21 102.7 0 103.11 0.41 Junc j22 102.7 0 167.54 64.84 Junc j23 102.7 0 167.46 64.76 Junc j1 102.7 0 167.43 64.73 Junc j3 102.7 0 167.43 64.73

Junc j4 102.7 0 103.22 0.52

2.2 Water Demand

First, it was considered the Average Water Demand for the population of 135, 6 LPS and

later it was created the pattern in the Graph 1 according to their needs.

In this graph is possible to notice a smaller water demand during the night, because most

of the population is sleeping and the highest peaks registered in the morning, when people

are getting ready to leave the house and at the beginning of the night, when they arrive

home.

Design of a Water Network using EPANET

9

Graph 1- Water Demand Population

The manufacture of Jeans has a high demand for water, so it was established the average

water demand of 75 LPS and was created a pattern for the demand during the 24 hours of

the day.

This factory is operating 24 hours a day but the demand is not constant during these hours.

As one can see in the pattern, the highest demand occurs in the morning period, drops a

little bit during the lunch hours and is reestablished at 15:00 to the morning values. After

19:00 the demand drops because part of the employees is not working and there is less

production during the night.

Graph 2- % average water demand jeans factory

0

1

2

3

4

5

6

0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23

%WD

%WD

0,000

0,500

1,000

1,500

2,000

2,500

3,000

0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23

% average water demand

% average water demand

Design of a Water Network using EPANET

10

2.3 Pumping Station

If gravity is insufficient to supply water at an adequate pressure, then pumps need to be

installed to boost the pressure. Pumps can be either permanently operational or

intermittent. They can be controlled by a time-switch, pressure or a water level in a tank

or reservoir.

Pumping Stations are facilities that include pumps and other equipment for pumping the

water from the reservoir to the network, allowing the supply of water to the population.

Because of the demand of water by the city and industry, first it was designed a pumping

station with four pumps, three big pumps (from these three, two are active and one is in

the reserve) and a smaller active pump.

It was chosen Wilo as the pump manufacturer and the selection of the pumps. This process

take into account the duty points, flow and total head in the system and the characteristics

of the water.

Duty Points Water , Pure

Flow Total Head

Temperature (ºC)

Density (kg/m3)

Viscosity (mm2/s)

Pump5,6 and7 140 66 10 1 1,36 Pump1 70 66 10 1 1,36

After the selection of the pump that best fits the system, it was created in EPANET their

hydraulic curve and the efficiency curve, using the performance curve of the pump,

supplied by wilo-select.com

Figure 3- Performance Curve of Pump5, Pump6 and Pump7

Design of a Water Network using EPANET

11

Figure 6- Cross Section of Pumping Station

Figure 4- Performance Curve of Pump1

Figure 5- Plan View of the Pumping Station

Design of a Water Network using EPANET

12

2.3.1 Controls applied to the pumping station

;Automation for pump1

LINK pump1 CLOSED AT TIME 0

LINK pump1 OPEN AT TIME 9

LINK pump1 CLOSED AT TIME 12

;Automation for pump5

LINK pump5 CLOSED AT TIME 0

LINK pump5 OPEN AT TIME 15

LINK pump5 CLOSED AT TIME 19

These controls were applied to the system and they mean that from 0h to 8h, only the

pump6 works because the demand is not that big during the night. From 9h to 12, the

pump6 and the pump1 work together. From 12h to 15, only the pump6 works. At 15h the

pump5 works together with pump6 until 18h. And finally, from 18h to 24h, only the

pump6 works.

Design of a Water Network using EPANET

13

2.4 Water Tank

The water tank is located north of the system, it has 50 m of diameter, the initial and

maximum level of 4,5m and minimum level of 0,5 m.

In this figure it’s possible to see that the tank is located 20 meters above the last node

elevation.

Design of a Water Network using EPANET

14

Graph 3- Price of Electricity

3. Result of preliminary design of water network

3.1 Pressure distribution in the whole system and put screenshot

Figure 7- Minimum Pressure Distribution

This figure represents the minimum values of pressure distribution in the system. As

expected, the pressure near the pumping station is higher than in the rest of the network.

0

0,05

0,1

0,15

0,2

0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23

€ kWh

Design of a Water Network using EPANET

15

Figure 8- Maximum Pressure Distribution

In Figure8 is possible to see that the maximum pressure is high in the all system and

decreases, gradually, upstream of the pumping station.

Figure 9- Average Pressure Distribution

In Figure9, one can see that by the time when pressure values are average, they are higher

in the low areas of the city and lower in the higher areas of the city

With high pressures, there are more leakage problems and higher energy and maintenance

costs.

Design of a Water Network using EPANET

16

3.2 Velocity in the Pipes

Graph 4- Velocity in the Pipes

In Graph4 are represented the maximum, minimum and average velocity in the system

pipes. It is possible to see that the highest velocities are registered on the pipes that are

part of the pumping station and the highest value is about 5 m/s.

0

1

2

3

4

5

Velocity in the Pipes

Minimum

Maximum

Average

Design of a Water Network using EPANET

17

Figure 10- Average Velocity Distribution

The figure10 represents the velocity registered in the pipes during the most time of the

day, time statistics average. It’s possible to notice that the velocity in higher in the pipes

that connect the reservoir to the most functional pump, in the pipes that connect the

pumping station to the rest of the network and also the pipe that supplies water from the

network to the Jeans Factory. In the most parts of the network, the velocity in the pipes is

between 0,1 and 1 m/s.

Design of a Water Network using EPANET

18

3.3 Operational state of the pumping station

By the end of the creation of the pumping station, the graph shows that the system flow

balance is good, since the flow that is produced is equal to the one that is consumed.

Table 5 - Pumping Costs

Percent Average Kw-hr Average Peak Cost

Pump Utilization Efficiency /m3 Kwatts Kwatts /day

pump5 16.67 67.96 0.25 89.76 89.83 11.50

pump6 100.00 68.76 0.25 95.15 116.35 64.16

pump7 0.00 0.00 0.00 0.00 0.00 0.00

pump1 12.50 66.83 0.26 88.67 88.70 8.52

Total Cost 84.18

Demand Charge

0.00

In this state, the pumps average efficiency was set to at 75% and, according to the energy

report on EPANET, the cost of energy per day, to pump water to the system is 84,18€.

Graph 5- System Flow Balance

Design of a Water Network using EPANET

19

4. Cost reduction analysis

4.1 Description of proposed system optimization

Figure 11-Improved Water Network

In this part of the report, the aim was to create a more economically efficient water

network by reducing the pumping costs. In this improved system, represented in

Figure11, there are only two pumps, which performance curves are shown below. Only

the pump6 works during the 24 hours of the day and the pump1 is installed just as a

reserve.

Design of a Water Network using EPANET

20

Figure 12- Performance Curve Pump6

Figure 13-Performance Curve Pump1

For cost reduction reasons, the Pump6 was controlled to perform at 0.9 relative speed at

0 hours into the simulation. This change in the speed alone is responsible saves about 20

€ per day, without affecting the balance of the system.

Design of a Water Network using EPANET

21

Figure 14- System Flow Improved System

From the Figure14, one can see that the system is well balanced even though there’s only

one functional pump.

4.2 Cost reduction analysis

Table 6- Pumping Costs Improved System

Percent Average Kw-hr Average Peak Cost

Pump Utilization Efficiency /m3 Kwatts Kwatts /day

pump6 100,00 71,32 0,18 81,43 92,43 55,41

pump1 0,00 0,00 0,00 0,00 0,00 0,00

Total

Cost

55,41 €

Design of a Water Network using EPANET

22

Graph 6- Comparison of pumping costs

With the improved system, the pumping costs were reduced in 34%. Since the minimum

of reduction of costs was settled in 25%, it is possible to say that the changes applied on

the pumping station were successful.

5. Conclusion

In a water distribution system, the components sharing capital costs are pumps and

pumping stations, pipes of various commercially available sizes and materials, storage

reservoir; and recurring costs such as energy usage.

In this simulation, for the reduction of costs, the only changes occur in the design of the

pumping station, it was reduced the number of pumps from 4 to 2 and changing the

relative speed of the pump in the improved system. In the comparison of pumping costs

was only take into account the costs of the energy used by the pumps but the comparison

should also include the prices of the pumps that were installed in each of the simulated

systems. So, there were obviously more ways to make the system more efficient such as

using the water from the tank to supply water in times were the demand is lower.

84,18

55,41

0

10

20

30

40

50

60

70

80

90P

rice

per

day

(€

)

Cost of Pumping

First Design Improved Design


Recommended