+ All Categories
Home > Documents > Political Economy of Contractual Disputes in Private Water and Sanitation:Lessons from Argentina

Political Economy of Contractual Disputes in Private Water and Sanitation:Lessons from Argentina

Date post: 04-Dec-2023
Category:
Upload: independent
View: 0 times
Download: 0 times
Share this document with a friend
20
Annals of Public and Cooperative Economics 82:1 2011 pp. 25–44 POLITICAL ECONOMY OF CONTRACTUAL DISPUTES IN PRIVATE WATER AND SANITATION: LESSONS FROM ARGENTINA by Hulya DAGDEVIREN University of Hertfordshire, UK ABSTRACT ∗∗ : This paper examines the causes of the contractual disputes in the water and sanitation sectors and the resulting reversal of the privatization process. The evidence has been gathered from four major case studies in Argentina. The discussion is based on the evidence contained in the legal submissions made by the Government of Argentina and the disputing companies to the International Centre for the Settlement of Investment Disputes. The findings of the paper offer important lessons for the design and management of similar contracts for other countries. 1 Introduction Many countries in the developed and developing world have implemented extensive restructuring and privatization of their essential services such as water, sanitation and electricity, often involving long-term contracts. Performance improve- ments have been achieved in some countries (Estache et al. 2005, Shirley 2002), while in others privatization of essential services has been accompanied by legal battles and renegotiations between governments and the private companies. 1 In Latin America, 76 per cent of all contracts in the water and sanitation sector were disputed and renegotiated, on average, within 1.6 years after contracts signed (Guasch and Straub 2009). A large proportion of renegotiations in the utility sectors were initiated at the request of the private operators and majority ended in favour of them, resulting in increase in tariffs, cuts in investment obligations and annual fees paid to the I am grateful to Procuraci´ on del Tesoro de la Naci´ on (PTN), especially to Mr Gabriel Bottini and Ms Mariana Lozza, for providing invaluable research materials, the case files and other support. I am indebted to Degol Hailu, the former director of the International Policy Centre for Inclusive Growth, for facilitating this research and the United Nations Development Programme – Argentina Office, for the same. I have benefited from conversations with Ricardo Ortiz and Santiago Urbiztondo and I am thankful to them. E-mail: [email protected] ∗∗ esum´ e en fin d’article; Zusammenfassung am Ende des Artikels; resumen al final del art´ ıculo. 1 See, for example, Estache (2006) and Guasch (2004) for the experience in Latin America, Lobina (2005) for South Africa and Belize, and Hall (2007) for East Africa. C 2011 The Author Annals of Public and Cooperative Economics C 2011 CIRIEC. Published by Blackwell Publishing Ltd, 9600 Garsington Road, Oxford OX4 2DQ, UK and 350 Main Street, Malden, MA, MA 02148, USA
Transcript

Annals of Public and Cooperative Economics 82:1 2011 pp. 25–44

POLITICAL ECONOMY OF CONTRACTUAL DISPUTESIN PRIVATE WATER AND SANITATION:

LESSONS FROM ARGENTINA

byHulya DAGDEVIREN∗

University of Hertfordshire, UK

ABSTRACT∗∗: This paper examines the causes of the contractual disputes in thewater and sanitation sectors and the resulting reversal of the privatization process.The evidence has been gathered from four major case studies in Argentina. Thediscussion is based on the evidence contained in the legal submissions made by theGovernment of Argentina and the disputing companies to the International Centrefor the Settlement of Investment Disputes. The findings of the paper offer importantlessons for the design and management of similar contracts for other countries.

1 Introduction

Many countries in the developed and developing world have implementedextensive restructuring and privatization of their essential services such as water,sanitation and electricity, often involving long-term contracts. Performance improve-ments have been achieved in some countries (Estache et al. 2005, Shirley 2002), whilein others privatization of essential services has been accompanied by legal battles andrenegotiations between governments and the private companies.1 In Latin America,76 per cent of all contracts in the water and sanitation sector were disputed andrenegotiated, on average, within 1.6 years after contracts signed (Guasch and Straub2009). A large proportion of renegotiations in the utility sectors were initiated at therequest of the private operators and majority ended in favour of them, resultingin increase in tariffs, cuts in investment obligations and annual fees paid to the

∗ I am grateful to Procuracion del Tesoro de la Nacion (PTN), especially to Mr GabrielBottini and Ms Mariana Lozza, for providing invaluable research materials, the case files andother support. I am indebted to Degol Hailu, the former director of the International PolicyCentre for Inclusive Growth, for facilitating this research and the United Nations DevelopmentProgramme – Argentina Office, for the same. I have benefited from conversations with RicardoOrtiz and Santiago Urbiztondo and I am thankful to them. E-mail: [email protected]∗∗ Resume en fin d’article; Zusammenfassung am Ende des Artikels; resumen al final delartıculo.1 See, for example, Estache (2006) and Guasch (2004) for the experience in Latin America,Lobina (2005) for South Africa and Belize, and Hall (2007) for East Africa.

C© 2011 The AuthorAnnals of Public and Cooperative Economics C© 2011 CIRIEC. Published by Blackwell Publishing Ltd, 9600 Garsington Road,Oxford OX4 2DQ, UK and 350 Main Street, Malden, MA, MA 02148, USA

26 HULYA DAGDEVIREN

government (Guasch 2004). These trends raise concerns about the integrity and socialwelfare implications of such deals and raise serious questions about promotion ofprivatization for essential public services.

The aim of this paper is to move beyond the standard considerations of efficiencyafter privatization of utilities and analyze the real process of service delivery byexamining the interfaces between users, governments, regulators, legislators andsuppliers on the basis of the disputes and renegotiations in the water and sanitationsector after privatization. Argentina is chosen as a case study for analysis because itpresents us with a rich material base for the topic of this paper and its experienceoffer important lessons for other developing countries.

Argentina privatized most of its utility services in the 1990s. In comparison, itwas a success story for it attracted considerable foreign investment (FDI), includinginto its water and sanitation sectors, through privatization. The Bilateral InvestmentTreaties (BITs), entered with more than fifty nations in the 1990s, played aninstrumental role in this. The BITs provided guarantees against expropriation andfor profit transfers. They also included a designated arbitration mechanism in whichthe International Centre for Settlement of Investment Disputes (ICSID) of the WorldBank or the United Nations Commission on International Trade Law (UNCITRAL)could act as adjudicators (Ortiz 2006). The outcomes of privatization also appearedpositive in terms of the performance of utilities. The public sector’s capacity todevelop and implement administrative, regulatory and legal procedures for contractenforcement has been notable especially in comparison to the experience in lowincome countries.

In water and sanitation, altogether, 18 concession contracts were signed acrossthe country by the Provincial governments or the Federal State (Table 1).2 Mostconcession contracts were awarded through competitive bidding either on the basis oflowest-tariff or highest concession fee criteria. Multinational companies accounted foraround two-thirds of the concession awards. Only a decade later, Argentina witnesseda sharp increase in the number of cases submitted for international arbitration,3

largely because of the crisis that hit the country in 2001 when the federal governmentpassed an Emergency Law in January 2002, abolished the Currency Board andstarted a renegotiation of all public utility contracts (Urbiztondo 2003, Calomiris2007). By 2009, one-third of all concession contracts in water and sanitation werecancelled (Table 1) and the services were re-nationalized.

But not all cases in water and sanitation were triggered by the crisis. A numberof investment disputes had started well before the crisis. In this paper, we presentevidence from four of the six water and sanitation contracts that were cancelled beforetheir due date since 1997 whose details are presented in shaded rows in Table 1.These are: a. Compania de Aguas del Aconquija (CAA) in the Province of Tucuman.b. Azurix Buenos Aires (ABA) in the Province of Buenos Aires. c. Aguas Provincialesde Santa Fe (APSF) in the Province of Santa Fe. d. Aguas Argentina SA (AASA) inthe City of Buenos Aires.

2 There was also one management contract in the sector for a period of two years.3 More than 60 contracts for public services with private companies went to the WorldBank’s ICSID after the government abandoned the denomination and indexation of utilitytariffs to the US dollar (Haselip 2005)

C© 2011 The AuthorAnnals of Public and Cooperative Economics C© 2011 CIRIEC

CONTRACTUAL DISPUTES IN PRIVATE WATER AND SANITATION 27

Tab

le1

–T

he

exte

nt

of

pri

vati

zati

on

inw

ater

and

san

itat

ion

inA

rgen

tin

a

Nam

eof

Com

pany

,Se

rvic

eA

rea

CC

Met

hod

&C

riter

ia%

Stat

usof

Year

Priv

atis

edPo

pula

tion

perio

dfo

rCC

Aw

ard

priv

ate

Maj

orsh

areh

olde

rsC

ontra

ct

Agu

asA

rgen

tinas

(AA

SA),

BA

City

,199

39.

000.

000

30C

B,3

Bid

s,Lo

wes

ttar

iff90

Agb

ar23

%;S

uez

46.3

%C

ance

lled,

2006

Agu

asC

ordo

besa

s,19

971.

200.

000

30C

B,1

Bid

100

Ben

itoR

oggi

oe

Hijo

s(L

)51

.2%

;Inv

erso

raC

entra

l(L

)28%

;Ser

vici

osde

lC

entro

(L)1

6.3%

Ope

ratio

nal

Agu

asde

Bal

carc

e,B

A,

1994

420.

000

20C

B,4

Bid

s,Lo

wes

ttar

iff10

0C

amuz

ziG

azom

etri

SpA

70%

;LLC

30%

Ope

ratio

nal

Agu

asde

Cam

pana

,BA

,19

9877

.800

30C

B,4

bids

,Hig

hest

CC

fee

100

Con

trera

sH

erm

anos

51%

;Es

uco

49%

Ope

ratio

nal

Agu

asde

Cor

rient

es,1

991

520.

000

30..

.10

0Jo

rge

Gut

nisk

i(L)

20%

;Pa

blo

Cha

mas

(L)8

0%O

pera

tiona

l

Agu

asde

Form

osa,

1995

185.

000

30..

.10

0Ph

oeni

x(L

),Sa

gua

Inte

rnat

iona

l(L)

,Sim

ali

(L)

Ope

ratio

nal

Agu

asde

laR

ioja

,200

215

0.00

030

...

100

Latin

agua

s(L

)100

%O

pera

tiona

lA

guas

deLa

prid

a,B

A,

1996

...

20C

B,4

Bid

s,Lo

wes

ttar

iff10

0C

amuz

ziG

azom

etri

SpA

100%

Ope

ratio

nal

Agu

asde

Salta

,199

895

0.00

030

CB

,2B

ids

100

JCR

(L)4

5%;L

atin

agua

s(L

)45%

Ope

ratio

nal

Agu

asde

lGra

nB

A,2

000

1.70

0.00

030

...

100

AC

S27

%;A

guas

Bilb

aoB

izka

ia20

%;I

mpr

egilo

43%

Can

celle

d,20

06

Con

tinue

d

C© 2011 The AuthorAnnals of Public and Cooperative Economics C© 2011 CIRIEC

28 HULYA DAGDEVIREN

Tab

le1

–C

on

tin

ued

Nam

eof

Com

pany

,Se

rvic

eA

rea

CC

Met

hod

&C

riter

ia%

Stat

usof

Year

Priv

atis

edPo

pula

tion

perio

dfo

rCC

Aw

ard

priv

ate

Maj

orsh

areh

olde

rsC

ontra

ct

Agu

asPr

ovin

cial

esde

Sant

aFe

(APS

F),1

995

2.00

0.00

030

Low

estt

ariff

100

Suez

51.7

%;A

gbar

Can

celle

d,20

06

Azu

rixB

ueno

sA

ires

(AB

A),

1999

1.70

0.00

030

CB

,3B

ids

Hig

hest

CC

fee

100

Azu

rix,E

nron

(100

%)

Can

celle

d,20

02

Cat

amar

ca,2

000

250.

000

30C

B,H

ighe

stC

Cfe

e10

0Fo

men

tode

Con

stru

ccio

nes

yC

ontra

tas

50%

;Veo

lia50

%

Can

celle

d,20

08

Com

pani

ade

Agu

asde

lA

conq

uija

(CA

A),

Tucu

man

,199

5

>1.

000.

000

30C

B,1

Bid

,Low

estt

ariff

100

Veol

iaEn

viro

nmen

t90%

(form

erly

Vive

ndi)

Can

celle

d,19

97

Men

doza

WS,

1998

900.

000

95C

B,3

Bid

s,H

ighe

stC

Cfe

e70

Saur

32%

;Sou

thW

ater

(L)

32%

InD

ispu

te

Sant

iago

delE

ster

o,19

9741

0.00

030

...

100

Cas

tTV

(L)1

5%;C

uri

Her

man

os(L

)15%

;Ed

itoria

lElL

iber

al(L

)15

%;S

agua

Int.

(L)4

5%

Ope

ratio

nal

Serv

icio

sde

Agu

asde

Mis

ione

s,19

9930

0.00

030

CB

100

Act

ivid

ades

deC

onst

rucc

ion

ySe

rvic

ios,

90%

Ope

ratio

nal

Suda

mer

ican

ade

Agu

as,

Pila

rBA

,199

212

025

CB

,3B

ids

100

Suda

mer

ican

ade

Agu

as80

%O

pera

tiona

l

Abb

revi

atio

ns:B

A:B

ueno

sA

ires.

CB

:Com

petit

ive

Bid

ding

.CC

:Con

cess

ion

Con

tract

.L:L

ocal

inve

stor

.So

urce

:Wor

ldB

ank

and

PPIA

F,PP

IPro

ject

Dat

abas

e.

C© 2011 The AuthorAnnals of Public and Cooperative Economics C© 2011 CIRIEC

CONTRACTUAL DISPUTES IN PRIVATE WATER AND SANITATION 29

The contractual disputes in the cases of CAA and ABA started prior to thefinancial crisis in 2001 while in the cases of APSF and AASA after the crisis. Inall four cases, tariffs as well as service and investment objectives had been subjectto renegotiations between the companies and the responsible public authorities priorto the application of the companies for international arbitration. In some cases, thedisagreements were resolved in the process of these renegotiations, frequently infavour of the private companies, while in other cases they ended up with formalsubmissions, made by the respective companies, for international arbitration.

The analysis of the case studies provides important lessons for other developingcountries that have pursued similar reforms or are in the process of adopting suchreforms. Most importantly, they point to the inherent conditions in private waterand sanitation systems which under certain circumstances may lead to reversal ofprivatization. Such radical changes can even occur in the presence of appropriateregulatory institutions, rules and mechanisms as a result of three factors permanentlypresent in water and sanitation services: imperfect and asymmetric information,incompleteness of contracts and political economy issues.

Several practical issues emerge from the experience of Argentina. First, theprimary interest of the companies throughout the period after privatization has beento improve their financial position, justly or opportunistically, by requesting changesin three areas: increases in tariffs/revenues, reductions in their risk exposure andinvestment obligations. Second, the problems in the design and content of contractsfrequently lay at the heart of disputes and renegotiations. Third, the negligence ofsocial context by the state in the process of privatization has been an importantdriver of disputes and renegotiations as evidenced by the role service chargesplayed in the implementation and enforcement of contracts. Largely because of this,public authorities often gave into the pressures and compromised from investmentand service extension targets rather than accepting the politically sensitive tariffincreases. Fourth, the concept of ‘independent regulation’ as a panacea for the illsof the private service supply is problematic in that it does not recognize the intricateeconomic, political and social interests and the conflicts within.

This paper starts in Section 2 with a discussion of the common causes ofdisputes and renegotiations in water and sanitation sector in Argentina and continueswith an assessment of the political economy aspects of such disputes in Section 3.Following the conclusions in Section 4, reviews of four case studies described aboveare presented in the appendix without interpretation. These case studies haveprovided the material for the analysis presented in the main body of this paper.

2 Main causes of disputes and renegotiations

There are many dimensions of the conflicts in the water and sanitation services.Some of these are case specific. In some cases, the Government of Argentina (GoA)argued that the winning consortiums submitted aggressive and opportunistic bidsand forced regulators and/or administrative authorities to renegotiate later. This wasaffirmed by previous research in some cases (e.g. Guasch 2004). For example, Azurixwon the water and sanitation contract in the Province of Buenos Aires by offering aC© 2011 The AuthorAnnals of Public and Cooperative Economics C© 2011 CIRIEC

30 HULYA DAGDEVIREN

concession fee, at least, six times greater than that of the next bidder and in less thana year after the takeover, it requested a renegotiation of the terms and conditions. Onthe basis of references to media and other publicity, the GoA raised similar concernsfor the AASA consortium that won the concession in the City of Buenos Aires. It ar-gued that the consortium knew other bidders’ proposals and was in a position to offerthe lowest tariff which they sought to renegotiate after the concession was granted.

While there are a range of case specific causes of disputes, two common andinterrelated issues recurred in all cases covered in this paper irrespective of thembeing related to the crisis or not. The first is related to the investment obligationsof the companies while the second is to the application of tariff regime and the coststhat could be passed on to customers.

2.1 Investment related disputes and renegotiations

During renegotiations, the private operators sought to reduce their risks,increase tariffs and establish an automatic tariff review process in response to thechanges in agreed price indices without regulatory evaluation and verification ofimpact on costs (what is known as ‘pass-through costs’). The counterparty from thepublic sector, on the other hand, often focused on the investment obligations andattainment of expansion goals.

One of the regularities that emerge from the case studies covered in this paperis that investment goals appear to have been soft targets of easy compromise inthe presence of disagreements between the parties. Quite often, governments, unableto agree on tariff rises with fear of public opposition, consented to reduce, suspendor reschedule investment obligations in order to reach some sort of settlement andprovide the private sector with an indirect source of revenue. In other words, loweringinvestment targets was a trade-off for politically thorny rises in water charges. Therenegotiations before and after the crisis with APSF in the Province of Santa Feand AASA in the City of Buenos Aires (Appendix 2) all resulted in reductions andsuspensions in the original investment obligations. In some cases cuts in investmentwere accompanied by tariff increases.

The evidence produced by GoA in response to the companies’ claims beforethe ICSID demonstrates that non-compliances with investment and service levelobligations were widespread and severe in all cases in view of original contractualprovisions and related agreements. ABA’s non-compliance with water and sanitationexpansion targets ranged between 13 and 95 per cent in the regions it operated. AASAinvested 45 per cent less than it originally was contracted for. APSF’s investment wasshort of original expansion targets by more than 80 per cent. (PTN 2004, 2007a, b). Amore detailed analysis of contractual non-compliances regarding investment targetscould be found in Casarin et al. (2007) and Azpiazu et al. (2005).

Previous research indicates that companies have focused on the maintenanceof existing infrastructure rather than extending it to low income areas of poorfinancial viability (Baer and Montes-Rojas 2008). In some cases, the contractsexplicitly excluded the water and sanitation supply in the peri-urban areas (Bottonand Merlinsky 2006). In other cases contracts failed to specify the consequences ofnon-compliance with investment targets (Guasch 2004). However, assessing the true

C© 2011 The AuthorAnnals of Public and Cooperative Economics C© 2011 CIRIEC

CONTRACTUAL DISPUTES IN PRIVATE WATER AND SANITATION 31

extent of contractual breaches is fraught with difficulties because of the repeatedrenegotiations which led to considerable reduction in investment targets.

2.2 Tariff related disputes and renegotiations

The hazards associated with tariff increases after water privatization in de-veloping countries is well established in the literature (Loftus and McDonald 2001,Smith 2004, De Azevedo and Baltar 2005, Kirkpatrick et al. 2006, UNDP 2006). Watercharges have also been at the centre of disputes and renegotiations in Argentina.Typically, they have been triggered as a result of:

a) payment difficulties by the low income user groups;b) differences in the interpretation of the regulatory framework by the companies

and the public agencies.

One lesson that can be drawn from the evidence contained in the case studies isthat when the contractual rights of the private companies in the water and sanitationsector are instituted without a rigorous analysis of their implications for the relevantsocial context, they are likely to be unsustainable. For example, tariff rises after theprivatization of water and sanitation services in the Province of Santa Fe, the City ofBuenos Aires and the Province of Tucuman, though were permitted by contracts, theyall led to social unrest, political pressure on local governments, non-payment of billsand low revenues for the private operator, leading to renegotiations between the re-spective companies and the public agencies within one to two years after privatization(Appendix 1 and 2). Frequently, such renegotiations involved considerable reduction incompanies’ investment and service level obligations and modification in tariff reviewprocedure, for instance, involving automatic and more frequent adjustment to servicecharges. In the first two cases mentioned above, the bargaining for tariffs turnedinto a broader review of the whole contractual and regulatory processes in which theprevious risk allocation system changed significantly in favour of the concessionaires.In the last case the contract was terminated by the company while negotiations wereongoing.

Another major source of conflicts was the differences in the interpretation of theregulatory framework,4 describing what could be passed on tariffs, what triggers tariffreviews and what the procedures are for tariff adjustment. The review of the evidencein Argentina suggests that when the regulatory framework contains clauses that areopen to interpretations or its various elements are inconsistent or they are ineffectivein the presence of contingencies (a predominant feature of incomplete contracts), thenthe service supply after privatization can become hostage to the conflicts arisingfrom such circumstances. The case studies in the appendix provide a wide range ofexamples.

In the City of Buenos Aires, for example, tariff reviews had been a highlycontentious issue after the crisis. According to the contract changes in the peso-USdollar parity could trigger a tariff review which led the company to request tariff

4 The regulatory framework consisted of the provisions of the relevant concession con-tracts, water acts and terms and conditions of bidding.

C© 2011 The AuthorAnnals of Public and Cooperative Economics C© 2011 CIRIEC

32 HULYA DAGDEVIREN

adjustment. The GoA’s interpretation of the regulatory framework was different: thecrisis did not only lead to a change in the peso-dollar parity but it led to a completeabandonment of the Currency Board. The previous contractual framework had notprovided any guidance if the pegged exchange rate regime were altered. More impor-tantly, this case presented a serious legal inconsistency because what the contract per-mitted (i.e. the indexation of tariffs to the US dollar) was explicitly prohibited by theConvertibility Law at the time (Chisari and Ferro 2005, Baer and Montes Rojas 2008).

Similarly in Tucuman, the treatment of taxes had been an issue for the deter-mination of tariffs. The contract had defined all taxes as costs, hence transferable ontariffs, but this was later revised within the Bidding Terms and Conditions. Althoughthis revision was legally binding it was in the interest of the company to insist on thevalidity of the draft contractual specification.

A number of conflicts between the public authorities and the companies arecaused by the directives issued by the Privatization Commission at the stage oftendering and bidding. While these aimed to clarify confusions, rectify errors orincorporate omitted information, Commission’s acts in some cases raise questionsabout its motivation: Was it too concerned for the speedy and lucrative executionof its task that it acted imprudently to maintain a high investor appetite? Forexample, the treatment of the concession fee started a dispute between the operatorand the public authorities in the Province of Buenos Aires (Appendix 1). In theutilities sector, the concession fee usually reflects a compensation for the right touse the existing assets previously financed from tax revenues. The legal documentsgoverning the concession did not allow it to be passed on tariffs. However, a directiveissued by the Privatization Commission at the prompt of the concessionaire haddefined it as ‘amortizable investment’ which then – by one interpretation – could beregarded as cost with reference to the Water Act of the Province. In the same case,another directive by the Privatization Commission permitted the winning consortiumto abandon the use of the coefficients that distinguished tariffs between differentzones of the supply area. This implied a significant rise in water charges and therevenues of the operator, at the cost of consumers. However, the contract did notpermit the water bills to be higher than the last bills before privatization whicheffectively made the Commission’s directive redundant.

These examples demonstrate that inconsistencies within and between theregulatory framework and the terms of the contract can create conflicts between thecompanies and the public authorities. Even in cases where such discords are resolvedthrough existing regulatory proceedings, the relationship between the companies andpublic authorities may be frustrated in the process. This is well demonstrated by thedispute about tariff increases associated with the rise in real estate and tax valueof properties in the Province of Buenos Aires where Azurix operated (Appendix 1).While the regulator eventually approved the updating of property values and henceallowed increases in tariffs, resolving certain elements of this dispute took about twoyears. By that time the company had terminated the contract. Did the regulatorpurposefully delay the process, as argued by the private operator? It may be sobecause the associated rise in water and sanitation charges could have been politicallyunsustainable. Alternatively, it may be the case that resolution of disputes involvingverification etc. normally takes a long time and there was no ‘conspiracy’ against theoperator, as argued by the GoA in its defense files submitted to the ICSID. Whichever

C© 2011 The AuthorAnnals of Public and Cooperative Economics C© 2011 CIRIEC

CONTRACTUAL DISPUTES IN PRIVATE WATER AND SANITATION 33

is the real reason, both point to the difficulties associated with the governance ofprivate supply of water and sanitation services.

Furthermore, the desire of the private operators to reduce their exposure tovarious risks through re-interpretation of the regulatory framework has been animportant driver of the renegotiations. For example, in the cases of APSF and AASA,the original tariff determination was based on price-cap. However, after repeatedrenegotiations the original contractual specification was changed and a mixed tariffsystem, combining price-cap with a rate of return regime, was introduced.5 In the caseof APSF, this was achieved through the introduction of the concept of ‘economic andfinancial equilibrium of the concession’ into the regulatory framework for the recoveryof all costs. In the case of AASA, the term ‘net financial exposure’ was incorporatedfor the same purpose.

A mixed tariff regime of this kind is potentially very gainful for the companiesbut disadvantageous for service users. Tariffs cover all costs and provide somereturn while any costs savings, for example due to improvements in efficiency, areretained by the companies rather than being passed on to consumers. Such costsavings constitute an indirect return for companies in addition to the rate of returnincorporated into service charges.

After the crisis, each company endeavoured to return to the previous statusquo and repeatedly requested the re-establishment of ‘the economic and financialequilibrium’ in the process of bargaining. They requested automatic adjustment oftheir tariffs reflecting the change in the exchange rate without the proof of impact ontheir costs which would have been justified under a pure price-cap system. The publicsector counterpart, on the other hand, required the companies to prove the impact ofprice changes on their cost structure.

Furthermore a detailed reading of the case files submitted to the ICSIDhighlight the importance of the fact that risk is a dynamic phenomenon in business.It may appear moderate during normal economic circumstances. But at times ofsevere financial and economic crisis it may be amplified to unsustainable levels. Risktaking in some areas is largely a private matter without significant externalities. Inthe provision of public services such as water and sanitation, however, it can havesignificant social cost and affect the sustainability of the service supply. This is clearlyrevealed in cases where companies pursued an investment funding strategy basedon high levels of unhedged debt, denominated in US dollars. This was a profitablebusiness model when peso-dollar parity was stable since loans in international markethad longer maturity and lower interest rates.

Another revelation is that tendency of companies to maintain a high leverageratio was associated with perverse incentives embedded in the original or renegotiatedcontractual framework which permitted cost of borrowing to be passed on service

5 Under a price cap regime, the predetermined tariffs are adjusted when there is a changein a price index specified in the contract. This system is considered to be providing incentivesto the operators for cost efficiency as any cost saving under a price-cap would be a gain for theprivate operator. However, it is also known for its perverse incentives causing underinvestment.On the other hand, in a rate of return system, tariffs are set in a way to cover all contractuallyspecified costs and provide a fixed rate of return for the operator. This system often leads tooverinvestment and cost inefficiency.

C© 2011 The AuthorAnnals of Public and Cooperative Economics C© 2011 CIRIEC

34 HULYA DAGDEVIREN

charges and lowered tax obligations of the companies. Such benefits would not havebeen available had the companies financed investments largely through own capital.The companies insisted that the government (or more accurately, the public) bearthe cost of the risks associated with their high leverage while the designated publicrenegotiation unit refused to do so.

3 Political economy of disputes and renegotiations

The cumulative evidence contained in the four case studies underscores acrucial issue. Privatization of water and sanitation with complete focus on efficiencyand utility performance and negligence of political economy considerations can leadto the adverse consequences seen in Argentina. Privatization does not privatize theentire governance of the contracts and process of service provision in water andsanitation for two reasons: First, the market structure in the sector is monopolisticand abuse of market power under private ownership is probable. Second, water isan essential service with considerable externalities. Hence, the state and its variousagencies, including regulators, remain in the sphere of governance to ensure thattariffs do not yield monopoly rents; water quality conform to health and safetystandards and adequate investments are undertaken not only to ensure presentsupply but also the future security of supply.

Nevertheless, private supply of essential services remains problematical evenin the presence of regulators between the consumers and the private operators asdemonstrated by the cases discussed in this paper. This is because there are inherentproblems in the management of such contracts. Some of these are already discussedextensively in the literature. First, the uncertainties regarding what the future holdsand the long-term nature of the concessions inevitably lead to what is termed as‘incomplete contracts’ by Hart et al. (1997) and Hart (2003) between the publicauthority and the private company. This is very well demonstrated in Argentina byrepeated renegotiations of contracts and the differences in their interpretation.

Second, effectiveness of regulation is complicated and problematic as a result ofthe potential for ‘capture’ (Stigler 1971, Posner 1974, Parker and Kirkpatrick 2004,Minogue and Carino 2006, Dal Bo 2006) as well as inherent information asymmetriesbetween regulators and companies (Sappington and Stiglitz 1987, Martimort 2006).Such information asymmetries determine the power of different agents and influencegains or losses to different parties. The case files submitted to the ICSID Tribunalsby the GoA contain myriad evidence of difficulties faced by the regulators due toabsent, defective, misleading or inconsistent information presented by the companies.For example, in the case of ABA, the GoA argued that the company had submittedunsatisfactory five-year plans and annual progress reports, causing considerabledelays in the implementation of expansion programmes. In the case of AASA, it wasmaintained that the company submitted information on costs without justificationand with inconsistencies which made the assessment difficult; failed to observe itsobligations to present audited economic and financial projections and compare thesewith those of a model company, which it never designed and submitted.6

6 Every five years, the AASA had to demonstrate that it was at least as efficient as themodel company, designed by itself. The company never complied with this requirement and the

C© 2011 The AuthorAnnals of Public and Cooperative Economics C© 2011 CIRIEC

CONTRACTUAL DISPUTES IN PRIVATE WATER AND SANITATION 35

However, these theories overlook the importance of the role of politics andpolitical economy factors after privatization in sectors such as water and sanitation.Because water is an essential service with substantial externalities, conflict ofinterests between social/public and private objectives becomes more pronounced afterprivatization. When/if the welfare of users is negatively affected by the actions orinactions of profit driven private operators (e.g. high water and sanitation charges,water contaminations) they will put political pressure on public authorities.

The sustainability of private supply under such conditions would depend oncountry or case specific factors such as the capacity and integrity of institutions(including regulatory, judicial and administrative bodies), state of general and sectorspecific laws, general economic conditions, conditions of income distribution andpoverty, state of infrastructure for water and sanitation and investment needs.

The cases presented in this paper lend us many examples which demonstratethe importance of non-economic factors, especially political factors, in the governanceof private water and sanitation services and enable us to make a set of observations.First of all, the political and economic costs of failure of privatization of waterutilities were too high for administration to bear. This has affected the outcomes ofrenegotiations with companies before the crisis. A senior regulatory expert, who wasa witness for the GoA in the dispute proceedings of the AASA, put this succinctly bystating that government had to give in to the pressures for renegotiations in order toavoid failure:

‘. . .such an important concession looked at by all the world . . : It was not possiblefor it to fail, it was imperative to find remedies to give it sustainability. . .’ (PTN,2006b: 35)

The intervention of the World Bank in 1996 for finalizing the renegotiations betweenthe CAA and the provincial government in Tucuman – in spite of the legislature’sreluctance for approval – can be seen in the same light (Appendix 1). Failures wouldhave damaged the credibility of the neo-liberal ideology – of which privatization wasa major element – that the Bank promoted.

Second, the conflicts between the private and public interests in water andsanitation have not been sufficiently contemplated in the process of privatization,contract design and regulatory mechanisms. Such considerations have emerged onlyas afterthoughts following a series of disputes and renegotiations with the privatecompanies. A prominent example is the fact that the GoA defended the EmergencyLaw and its implications for public services before the ICSID with reference to adoctrine in international law on the defence of necessity. It argued that the EmergencyLaw aimed to protect a ‘fundamental human right in the face of a grave and imminentperil’ caused by the crisis and it was necessary, reasonable and proportionate.7

Had this consideration about ‘defence of necessity’ been built into the regulatoryframework as well as the BITs the economic and political challenges after the

evaluation of its investments, operations and performance were conducted in the absence ofthis important benchmarking instrument.7 The unaffordability of the US dollar indexed service charges in the light of the economiccrisis, when poverty rose by more than 50 per cent and unemployment increased to 36 per cent,has been central to the arguments of the GoA.

C© 2011 The AuthorAnnals of Public and Cooperative Economics C© 2011 CIRIEC

36 HULYA DAGDEVIREN

privatization of services could have been reduced although this may also have reducedthe appeal of the water and sanitation utilities for private investors.

Third, the contracts in this sector are designed without the participation ofusers who are one of the major stakeholders. They have had very limited and indirectrole, if any, in influencing the process of privatization. It was presumed that variouscomplaint mechanisms and regulatory actions are sufficient to address the concerns ofthe service users. User groups have had no voice in the ICSID proceedings, except forthe case of AASA where the Tribunal allowed written representations from a numberof NGOs in 2007. The legislation for service users to participate in the renegotiationsbetween public authorities and the companies was enacted only in 2002 following theeconomic crisis, possibly as an attempt by the Federal Government to improve itshand in the game of renegotiations.

Fourth, the case studies provide some valuable evidence regarding the role ofthe regulators. A repeatedly asserted claim by the companies was that the regulatorslacked independence and their decisions were directly or indirectly influenced bythe governmental departments. While this may be the case, there is also plenty ofevidence on how companies have negotiated not only with the regulators but alsowith the key ministries, sometimes bypassing the regulators, sometimes hoping touse the ministries to pressurize the regulators. However, there was also tendencyfor regulators to be used as scapegoats in the process of the disputes. The tribunalsand companies accused them for lack of independence while the governments andresearchers have charged them for being captured by private interests. For example,the tribunal in the case of CAA blamed the regulator for being politically motivatedfor it initially approved the incorporation of taxes into tariffs but a short while laterreferred this matter to the Attorney General, leading to the reversal of the initialdecision. The problem with this judgment is that it fails to recognize that reversalor change in regulators’ decisions, following due procedures, is common becausemany aspects of essential services under private ownership and their regulation areinherently subject to challenges by different interest groups as some of the evidencepresented so far points out.

Finally, the resolution of the conflicts between the private and public interestsis not only a legal or administrative process but a political one which often involvenormative judgments. For example, in a controversial judgment, the ICSID tribunaldecided in favour of the shareholders of the CAA in the dispute regarding the extentto which taxes could be passed on tariffs. It justified its decision on the grounds thatthe disputed amount (8–10 per cent of monthly bills) between the counterparties is‘a relatively small sum for the average customer’ but for CAA it was considered tobe a substantial amount relative to its projected return (ICSID 2007). Clearly, thesignificance of the burden caused by a rise in monthly water bills would depend onhouseholds’ income levels. A ten per cent rise in water charges may have seriousconsequences for the welfare of the poor households. Hence, reference to ‘averagecustomer’ is not useful in a context where the payment problems are experiencedby the poor and the low income groups. Even if they constitute a small proportion ofpopulation, such conflicts have the potential to destabilize the whole system as theydid in the case of CAA. From this perspective, the conclusion of the tribunal maybe seen to have a high degree of subjectivity and negligence in the evaluation of themerits of the counter arguments.

C© 2011 The AuthorAnnals of Public and Cooperative Economics C© 2011 CIRIEC

CONTRACTUAL DISPUTES IN PRIVATE WATER AND SANITATION 37

The political sensitivity of service supply is particularly evident in cases ofincidents involving deterioration in the quality of water. The problems with waterquality, especially the ongoing incidents of high nitrate levels in the peak demandperiods, was one of the reasons for the termination of the AASA’s contract in theCity of Buenos Aires. The company argued that a small proportion of population(0.6 per cent) was affected and that this was only a pretext for the termination ofcontract. Similar water quality problems in San Miguel where CAA operated and inthe province of Buenos Aires where ABA operated attracted considerable politicalattention due to the public pressure about water quality. The companies blamedthe governments for causing or not preventing the panic. In the case of CAA, theICSID tribunal concluded in favour of the claimants and decided that the incidents ofturbidity in Tucuman were non-harmful and affected a small part of the populationand occurred for one to two months.

Once again, the subjectivity of this judgment could be shown with reference toseveral points. First, the tribunal had the advantage of assessing the circumstances,retrospectively, a long time after the incident took place when more information wasavailable, public pressure vanished, the uncertainties disappeared. Making such aclear judgment may not be possible while the events unfold, public protests continueand the duration of the turbidity is unknown. Second, the provision of polluted waterfor one-to-two months can hardly be categorized as a short period of time. Third,polluted water would and should cause a serious concern no matter how small is theproportion of population affected. Panic may be inevitable between the time when theturbidity appears and when the results about its non-hazardous nature are revealed.Even in cases where the cloudy and odorous water is certified to be safe to drink, it isunreasonable to expect the public to do so. Water is expected to be delivered in goodquality not only in terms of its nutrients and bacteriological content but also in termsof its appearance, e.g. free from any colour or odours. Otherwise, it is natural for therespective companies and public offices, especially regulators, governors, governmentsand legislators to come under public pressure.

4 Conclusions

The discussion presented in this paper aimed to open ‘the black box’ in theprivate water and sanitation concessions in Argentina with potentially useful lessonsfor other countries. Several themes of the paper could be highlighted. One of theseis that the shift from the public to private provision of water and sanitation wasadvocated by a narrow perspective that purely focused on performance and efficiency,neglecting the intricate processes as well as legal, economic, political and socialconflicts that characterize such systems as demonstrated by the evidence presentedin this paper.

The case studies in this paper show that disputes and renegotiations havefrequently been instigated by three factors, essentially reflecting the conflict ofinterests of different parties in the system: companies’ claim about the deteriorationin the financial and economic viability; social unrest about affordability of watercharges or water quality and differences in the interpretation of contractual and legalrules, affecting the rewards and responsibilities of the parties to the contract.C© 2011 The AuthorAnnals of Public and Cooperative Economics C© 2011 CIRIEC

38 HULYA DAGDEVIREN

Repeated renegotiations often resulted in significant changes in the originalcontractual specifications, tariff regime and investment and service improvementstargets. Some have produced considerable gains for the operating companies. Servicecharges and investment targets have been the principal subject of disputes andnegotiations. Political sensitivity of the former often led to compromises from thelatter. The regulatory systems that used a mixed tariff regime operated in favourof the companies as they enabled them to benefit from all the advantages ofthe price-cap and rate of return regimes without releasing their benefits for thepublic.

Heavy indebtedness of the water and sanitation companies in foreign currenciesplayed a crucial role in determining the scale of impact of the crisis on their viability.Some incentives in the micro and macroeconomic environment have been influentialin their choice of financial policy such as the low foreign interest rates, stability of theexchange rate, the ability of companies to pass the cost of borrowing on to consumers.The resulting leverage levels did not cause much concern until after the devaluationof peso that led to an explosion in the level of indebtedness after the crisis and defaultby some companies.

The disputes and renegotiations with private operators also highlight theinherent problems in the design of the contracts. Writing contracts without any scopefor reinterpretations and achieving consistency between contractual specificationsand other legal provisions is very difficult. It appears to be even more difficult todraw socially, economically and politically acceptable contracts that strike a goodbalance between the incentives for private operators to provide good quality servicesand improve the system while at the same time catering for the need for full andaffordable access by the population.

Political factors played a crucial role in private water and sanitation services.Changing politics together with changing economic conditions facilitated the entryof private companies to the sector in the 1990s as well as their exit only a decadelater. Political authorities and lobbying activities have been endlessly present inthe renegotiation of contracts. The permanent presence of politics in this sectoris due to the fact that public/social interests emerge as a major factor in deter-mining the viability of private contracts. The stability of policy changes for theaccommodation of private interests or profit would be precarious in the presence ofpublic discontent about the safety, affordability and reliability of supply. Governmentsmay or may not contain the dissatisfaction of public and private interests and theconflicts between them as reflected by the process of renegotiations and disputesin Argentina. Their stance has been influenced by a variety of factors includingtheir political orientation, time of elections, strength of public opposition, the social,economic and political costs of maintaining the concessions or allowing them tofail.

The independence of regulators from politics has been doubtful. Thereis considerable evidence that regulators gave in to pressures by the compa-nies as well as by the governments. There was also a tendency for the com-panies and the state to use the regulators as scapegoat in the process ofdisputes.

C© 2011 The AuthorAnnals of Public and Cooperative Economics C© 2011 CIRIEC

CONTRACTUAL DISPUTES IN PRIVATE WATER AND SANITATION 39A

pp

end

ix1

–T

he

case

stu

die

so

nco

ntr

actu

ald

isp

ute

s(p

recr

isis

)

Com

pani

aD

eA

guas

Del

Aco

nqui

ja(C

AA

)A

zurix

Bue

nos

Aire

s(A

BA

)

Priv

atiz

atio

nIn

1995

,CC

for3

0yr

sIn

1999

,CC

for3

0yr

sM

ajor

itySh

areh

olde

rsVi

vend

iUni

vers

alSA

Azu

rixC

orpo

rotio

nC

riter

iafo

rthe

awar

dof

CC

Low

estt

ariff

s.N

oco

nces

sion

Fee

Hig

hest

Con

cess

ion

Fee.

US$

438.

6m

illio

nPo

pula

tion,

Serv

ice

area

1m

illio

n,Pr

ovin

ceof

Tucu

man

1.7

mill

ion,

Prov

ince

ofB

ueno

sA

ires

Reg

ulat

or,T

ariff

Reg

ime

ERSA

CT,

Pric

eC

apO

RA

B,P

rice

Cap

Subj

ects

ofD

ispu

te1

67%

tarif

finc

reas

eaf

terp

rivat

izat

ion

whi

chca

used

popu

laru

nres

t.C

Cpe

rmitt

edth

eris

e.Th

eC

once

ssio

nFe

ew

asre

cogn

ized

as‘in

vest

men

t’by

PC,b

utno

tby

CC

.AB

Afo

llow

edPC

&re

quire

da

retu

rnon

the

Fee.

2C

Ctre

ated

allt

axes

asco

sts,

butB

TCex

clud

edso

me.

CA

Afo

llow

edth

eC

Can

dpa

ssed

allt

axes

onta

riffs

.Thi

sle

dto

publ

icop

posi

tion,

non-

paym

enta

ndde

clin

ein

CA

A’s

reve

nues

PCof

fere

da

chan

gein

the

estim

atio

nof

unm

eter

edta

riffs

,whi

chdi

dno

texi

stin

CC

.Its

appl

icat

ion

was

stop

ped

byth

ere

gula

tora

fter

tarif

finc

reas

esan

dcu

stom

erco

mpl

aint

s.3

Two

inci

dent

sof

wat

ertu

rbid

itybu

ilt-u

ppr

essu

reon

CA

Aan

dth

ego

vern

men

t.C

AA

inbo

thca

ses

argu

edth

atth

etu

rbid

ityw

asha

rmle

ssan

daf

fect

edsm

allp

ropo

rtio

nof

popu

latio

n.

CC

allo

wed

forp

rope

rty

reva

luat

ion

whi

chw

ould

have

rais

edta

riffs

.Th

ere

gula

tort

ook

two

year

sto

allo

wre

valu

atio

n.Th

isw

asaf

terA

BA

had

term

inat

edth

eC

C.

4C

Cpe

rmitt

edta

riffa

djus

tmen

tby

US

pric

ein

dice

sun

derc

erta

inco

nditi

ons.

AB

Aar

gued

that

adju

stm

entw

asau

tom

atic

ifsp

ecifi

edco

nditi

ons

emer

ge.F

orth

ere

gula

tora

djus

tmen

twas

nota

utom

atic

butd

epen

ded

onth

epr

oofo

fim

pact

onco

sts.

5A

BA

argu

edth

atth

ere

wer

esu

bsta

ntia

ldel

ays

inth

eco

mpl

etio

nan

dde

fect

sin

the

cons

truct

ion

ofsi

xin

frast

ruct

ure

wor

kspr

omis

edby

the

prov

ince

.AR

deni

edth

ese

alle

gatio

ns.

6W

ater

qual

itypr

oble

min

Apr

il-M

ay20

00.A

BA

argu

edth

atth

isw

asdu

eto

are

serv

oirc

ontro

lled

byth

ePr

ovin

ce.A

Rar

gued

that

AB

Aw

asre

spon

sibl

efo

rdel

iver

ing

wat

erin

good

qual

ityaf

ters

uita

ble

treat

men

t.R

eneg

otia

tions

Initi

ated

byG

ov.i

n19

96.P

artie

sag

reed

fora

25%

cuti

nta

riffs

and

susp

ensi

onof

inve

stm

entd

utie

s.Th

eag

reem

entw

asca

ncel

led

byth

epa

rliam

ent.

Late

rthe

Wor

ldB

ank

inte

rven

edbu

tthe

resu

lting

agre

emen

twas

reje

cted

once

agai

n.

Star

ted

in20

00.N

oag

reem

ent.

The

com

pany

term

inat

edth

eC

Cin

2001

&fil

edfo

rban

krup

tcy

in20

02.T

heA

Rar

gued

that

this

had

noth

ing

todo

with

the

issu

esou

tline

dab

ove

butt

heco

llaps

eof

ENR

ON

,AB

A’s

pare

ntco

mpa

ny.

Stat

usof

cont

ract

Term

inat

edby

CA

Ain

1997

AB

Afil

edfo

rBan

krup

tcy

in20

02A

rbitr

atio

nPr

ocee

ding

sIn

itiat

edby

CA

Ain

1996

.IC

SID

Cas

e.In

itiat

edby

Azu

rixin

2002

.IC

SID

Cas

e.Le

galA

rgum

ents

Bre

ach

ofB

ITbe

twee

nA

rgen

tina

and

Fran

ceB

reac

hof

BIT

betw

een

Arg

entin

aan

dth

eU

SC

ompe

nsat

ion

Req

uest

US$

317

mill

ion,

mos

tlyfo

rfor

egon

epr

ofits

Bet

wee

nU

S$48

2–57

1m

illio

nD

ecis

ion

onth

eC

ase

Aw

ard

forC

AA

&Vi

vend

iin

2007

.GoA

isto

pay

US$

105

mill

ion

with

6%in

tere

stan

dle

gale

xpen

ses.

PEN

DIN

G.

Aw

ard

forA

zurix

in20

06.A

Ris

topa

yar

ound

US$

165

mill

ion

with

2.44

%in

tere

stan

dIC

SID

’sex

pens

es.C

ON

CLU

DED

Sour

ce:I

CSI

D(2

007)

and

PTN

(200

3,20

04).

Abb

revi

atio

ns:C

C:C

once

ssio

nC

ontra

ct;B

TC:B

iddi

ngTe

rms

and

Con

ditio

ns;G

ov:G

over

nmen

t;A

R:A

rgen

tine

Rep

ublic

;PC

:Priv

atis

atio

nC

omm

issi

on.

C© 2011 The AuthorAnnals of Public and Cooperative Economics C© 2011 CIRIEC

40 HULYA DAGDEVIREN

Ap

pen

dix

II–

Th

eC

ases

of

Co

ntr

actu

alD

isp

ute

s(P

ost

-Cri

sis)

Agu

asPr

ovin

cial

esde

Sant

aFe

(APS

F)A

guas

Arg

entin

aSA

(AA

SA)

Priv

atiz

atio

nC

Cin

1995

for3

0ye

ars

CC

in19

93fo

r30

year

sC

riter

iafo

rthe

awar

dof

CC

Low

estt

ariff

s.N

oco

nces

sion

Fee

Low

estt

ariff

s.N

oco

nces

sion

Fee

Maj

ority

Shar

ehol

ders

Suez

and

Agb

arSu

ez,A

gbar

,Viv

endi

,Ang

lian

Wat

erPo

pula

tion

inse

rvic

ear

eaA

ppro

x.2

mill

ion,

Sant

aFe

Ove

r9m

illio

n,C

ityof

Bue

nos

Aire

sR

egul

ator

&Ta

riffR

egim

eEN

RES

S.Pr

ice-

Cap

regi

me

inth

ebe

ginn

ing.

Afte

rRen

egot

iatio

ns,

pric

e-ca

pw

asm

ixed

with

aco

st-p

lus

regi

me.

ETO

SS.P

rice-

Cap

regi

me

inth

ebe

ginn

ing.

Afte

rRen

egot

iatio

ns,

pric

e-ca

pw

asm

ixed

with

aco

st-p

lus

regi

me.

Subj

ects

ofD

ispu

te1

Cla

iman

tsre

quire

dta

riffr

evie

wto

take

into

acco

untt

hech

ange

inth

eex

chan

gera

te.C

Cpe

rmitt

edta

riffr

evie

wif

US$

-Pes

opa

rity

chan

ged.

But

AR

argu

edth

atth

eab

ando

nmen

toft

hefix

edex

chan

gera

tere

gim

ere

quire

da

diffe

rent

appr

oach

toth

eta

riff

revi

ewpr

oces

s.

Cla

iman

tsre

quire

dta

riffr

evie

wto

take

into

acco

untt

hech

ange

inth

eex

chan

gera

te.C

Cpe

rmitt

edta

riffr

evie

wif

US$

-Pes

opa

rity

chan

ged.

But

AR

argu

edth

atth

eab

ando

nmen

toft

hefix

edex

chan

gera

tere

gim

ere

quire

da

diffe

rent

appr

oach

toth

eta

riff

revi

ewpr

oces

s.2

Cla

iman

tsre

quire

dA

PSF’

sde

btto

beta

ken

into

acco

unti

nth

eta

riffr

evie

ws

afte

rthe

cris

is.A

Rob

ject

edon

the

basi

sth

atfu

ndin

gin

vest

men

tby

debt

oreq

uity

isa

busi

ness

deci

sion

.A

ssoc

iate

dris

ksca

nnot

betra

nsfe

rred

toth

eSt

ate.

AR

emph

asiz

edla

ckof

com

plia

nce

byA

PSF

with

cont

ract

uala

ndin

vest

men

tobl

igat

ions

.

Cla

iman

tsre

quire

dA

ASA

’sde

btto

beta

ken

into

acco

unti

nth

eta

riff

revi

ews

afte

rthe

cris

is.A

Rar

gued

that

AA

SAha

dpu

rsue

da

high

lyris

kyin

debt

edne

ssin

fore

ign

curr

ency

.The

risks

asso

ciat

edw

ithsu

cha

busi

ness

deci

sion

coul

dno

tbe

trans

ferr

edto

the

Stat

e.A

Rem

phas

ized

lack

ofco

mpl

ianc

eby

AA

SAw

ithco

ntra

ctua

land

inve

stm

ento

blig

atio

ns.

Ren

egot

iatio

ns(R

N)

Bef

ore

cris

isTh

efir

stR

N, i

nitia

ted

byG

over

nmen

tin

1997

due

toso

cial

unre

stab

outI

C.T

heag

reem

enti

n19

99re

duce

dA

PSF’

sin

vest

men

tob

ligat

ions

,scr

appe

dIC

butr

aise

dal

ltar

iffs

by14

%.

The

seco

ndR

N,i

nitia

ted

byG

over

nmen

tin

2000

due

toco

ntin

uing

paym

entd

ifficu

lties

bylo

w-in

com

egr

oups

.The

agre

emen

test

ablis

hed

anau

tom

atic

tarif

frev

iew

proc

ess,

redu

ced

APS

F’s

inve

stm

ento

blig

atio

nsan

dra

ised

tarif

fsby

10%

Initi

ated

byA

ASA

in19

97du

eto

non-

paym

ento

fIC

and

new

envi

ronm

enta

lpla

ns.T

heag

reem

enti

n19

99re

duce

dA

PSF’

sin

vest

men

tobl

igat

ions

,scr

appe

dIC

butr

aise

dta

riffs

,deb

twas

built

into

tarif

fs,a

utom

atic

annu

alta

riffr

evie

ws

intro

duce

dto

refle

ctch

ange

sin

Peso

-US$

parit

yan

dU

Spr

ice

indi

ces.

Afte

rcris

isC

ontin

ued

from

2002

to20

04w

ithou

tan

agre

emen

t.A

PSF

pres

sed

forr

etur

nto

the

prev

ious

cond

ition

s.A

Rar

gued

that

APS

Fw

astr

ying

toof

fload

itsla

rge

debt

inU

S$on

tota

xpa

yer.

Con

tinue

dfro

m20

02to

2005

.Atra

nsito

ryA

gree

men

twas

reac

hed

in20

03w

ithno

tarif

fris

ebu

treq

uire

din

vest

men

tofA

RS

260

mill

ion.

No

final

agre

emen

tcou

ldbe

reac

hed

until

the

term

inat

ion

ofC

C.

Stat

usof

cont

ract

Term

inat

ion

byA

PSF

in20

05,B

ankr

uptc

yin

2006

.Te

rmin

ated

byG

over

nmen

tin

2006

.A

rbitr

atio

nPr

ocee

ding

sIn

itiat

edby

Suez

and

Agb

arin

2003

.IC

SID

case

.In

itiat

edby

shar

ehol

ders

in20

03.I

CSI

D&

UN

CIT

RA

L.Le

galA

rgum

ents

Bre

ach

ofB

ITs

with

Fran

cean

dSp

ain

Bre

ach

ofB

ITs

with

Fran

ce,S

pain

and

the

UK

Req

uest

edC

ompe

nsat

ion

US$

243.

8m

illio

nw

ith11

.2%

com

poun

din

tere

st.

Dec

isio

non

the

Cas

ePe

ndin

gPe

ndin

g

Sour

ce:P

TN(2

006a

,200

6b,2

007a

,200

7b).

Abb

revi

atio

ns:C

C:C

once

ssio

nC

ontra

ct;A

R:A

rgen

tine

Rep

ublic

;PC

:Priv

atis

atio

nC

omm

issi

on;I

C:I

nfra

stru

ctur

eC

harg

e.

C© 2011 The AuthorAnnals of Public and Cooperative Economics C© 2011 CIRIEC

CONTRACTUAL DISPUTES IN PRIVATE WATER AND SANITATION 41

REFERENCES

AZPIAZU D., SCHORR M., CRENZEL E., FORTE G. and MARIN J.C., 2005,‘Agua potable y saneamiento en Argentina. Privatizaciones, crisis, inequidades eincertidumbre future’, Cuadernos Del Cendes, 59 (3), 45–67, Centro De EstudiosDel Desarrollo.

BAER W. and MONTES-ROHAS G., 2008, ‘From privatization to renationalisation:what went wrong with privatizations in Argentia?’, Oxford Development Studies, 36(3), 323–337.

BORTOLOTTI B. and SINISCALCO D., 2004, The Challenge of Privatization – AnInternational Analysis, Oxford University Press.

BOTTON S. and MERLINSKY G., 2006, ‘Urban water conflicts in Buenos Aires,Argentina’, in Urban Water Conflicts, UNESCO, Paris.

CALOMIRIS C., 2007, ‘Devaluation with contract redenomination in Argentina’,Annals of Finance, 3, 155–192.

CASARIN A. A., DELFINO J. A. and DELFINO M. E., 2007, ‘Failures in waterreform: lessons from the Buenos Aires’s concession’, Utilities Policy, 15, 234–247.

CHISARI O. and FERRO G., 2005, ‘Macroeconomic shocks and regulatory dilemmas:the affordability and sustainability constraints and the Argentine default experi-ence’, The Quarterly Review of Economics and Finance, 45, 403–420.

DAL BO E., 2006, ‘Regulatory capture: a review’, Oxford Review of Economic Policy,22 (2), 203–225.

DE AZEVEDO L. G. T. and BALTAR A. M., 2005, ‘Water pricing reforms: Is-sues and challenges of implementation’, Water Resources Development, 21(1),19–29.

ESTACHE A., 2006, ‘PPI partnerships vs. PPI divorces in LDCs’, Review of IndustrialOrganization, 29, 3–26.

ESTACHE, A., PERELMAN, S. and TRUJILLO, L., 2005, ‘Infrastructure performanceand reform in developing and transition economies: evidence from a survey ofproductivity measures’, World Bank Policy Research Working Paper 3514.

GUASCH J. L., 2004, Granting and Renegotiating Infrastructure Concessions: DoingIt Right. WBI development Studies, The World Bank, Washington DC.

GUASCH J. L. and STRAUB S., 2009, ‘Corruption and concession renegotiations:evidence from the water and transport sectors in Latin America’ Utilities Policy,17, 185–190.

HALL D., 2007, ‘Energy privatization and reform in East Africa’, Public ServicesInternational Research Unit’, Business School, University of Greenwich.

HART O., 2003, ‘Incomplete contracts and public ownership: remarks and an applica-tion to public-private partnerships’, Economic Journal, 113, C69–C76.

HART O., SHLEIFER A. and VISHNY R. W., 1997, ‘The proper scope of government:theory and an application to prisons’, Quarterly Journal of Economics, 112 (4),1127–1161.

C© 2011 The AuthorAnnals of Public and Cooperative Economics C© 2011 CIRIEC

42 HULYA DAGDEVIREN

HASELIP J., 2005, ‘Renegotiating electricity contracts after an economic crisis andcurrency devaluation: the case of Argentina’, The Electricity Journal, 18 (3), 78–88.

ICSID, 2007, Award for the Arbitration Case by Companıa de Aguas del AconquijaS.A. and Vivendi Universal S.A. International Centre for the Settlement of Invest-ment Disputes (ICSID), Case No. ARB/97/3.

KIRKPATRICK C., PARKER D. and ZHANG Y.-F., 2006, ‘An empirical analysis ofstate and private-sector provision of water services in Africa’, The World BankEconomic Review, 20 (1), 143–163.

LOBINA E., 2005, ‘Problems with private water concessions: a review of experiencesand analysis of dynamics’, Water Resources Development, 21 (1), 55–87.

LOFTUS A. J. and MCDONALD D. A., 2001, ‘Of liquid dreams: A political ecologyof water privatization in Buenos Aires’ in Environment and Urbanization, 13 (2),179–199.

MARTIMORT D., 2006, ‘An agency perspective on the costs and benefits of privatiza-tion’, Journal of Regulatory Economics, 30, 5–44.

MINOGUE M. and CARINO L., eds, 2006, Regulatory Governance in DevelopingCountries, Cheltenham, Edward Elgar.

ORTIZ R., 2006, ‘The bilateral investment treaties and the cases at ICSID: the Ar-gentine experience at the beginning of the XXI century’, Report for Foro Ciudadanode Participacion por la Justicia y los Derechos Humanos.

PARKER P. and KIRKPATRICK C., 2004, ‘Economic regulation in developing coun-tries: a framework for critical analysis’, in P. Cook, C. Kirkpatrick, M. Minogueand D. Parker, eds, Leading Issues in Competition, Regulation and Development,Cheltenham: Edward Elgar.

POSNER R. A., 1974, ‘Theories of economic regulation’, Bell Journal of Economicsand Management Science, Vol. 5, No. 2, pp. 335–358.

PTN 2003, Counter-Memorial by the Argentine Republic on Arbitration Case byAzurix Corporation. Procuracion del Tesoro de la Nacion (PTN), ICSID CaseNo. ARB/01/12.

PTN 2004, Rejoinder Memorial by the Argentine Republic on Arbitration Case byAzurix Corporation’, ICSID Case No. ARB/01/12.

PTN 2006a, Counter-Memorial by the Argentine Republic on Arbitration Case bySuez, Sociedad General de Aguas de Barcelona S.A. and InterAguas ServiciosIntegrales del Agua S.A. ICSID Case No. ARB/03/17.

PTN 2006b, Counter-Memorial by the Argentine Republic on Arbitration Case bySuez, Vivendi Universal SA, Sociedad General de Aguas de Barcelona S.A. andAnglian Water Limited. ICSID Case No. ARB/03/19.

PTN 2007a, Rejoinder Memorial by the Argentine Republic on Arbitration Caseby Suez, Sociedad General de Aguas de Barcelona S.A. and InterAguas ServiciosIntegrales del Agua S.A. ICSID Case No. ARB/03/17.

PTN 2007b, Rejoinder Memorial by the Argentine Republic on Arbitration Case bySuez, Vivendi Universal SA and Sociedad General de Aguas de Barcelona S.A,Anglian Water Limited. ICSID Case No. ARB/03/19.

C© 2011 The AuthorAnnals of Public and Cooperative Economics C© 2011 CIRIEC

CONTRACTUAL DISPUTES IN PRIVATE WATER AND SANITATION 43

SAPPINGTON D. E. M. and STIGLITZ J. E., 1987, ‘Privatization, information andincentives’, Journal of Policy Analysis and Management, 6 (4), 567–82.

SHIRLEYM M., 2002, Thirsting for Efficiency, World Bank.

SMITH L., 2004, ‘The murky waters of the second wave of neoliberalism: corporatiza-tion as a service delivery model in Cape Town’, Geoforum 35, 375–393.

STIGLER G. J., 1971, ‘The theory of economic regulation’, The Bell Journal ofEconomics and Management Science, Vol. 2, No. 1. pp. 3–21.

UNDP, 2006, Human Development Report 2006 – Beyond scarcity: Power, povertyand the global water crisis, United Nations Development Programme, PalgraveMacmillan.

URBIZTONDO S., 2003, ‘Renegotiation with Public Utilities in Argentina: analysisand proposal’, Fundacion de Investigaciones Economicas Latinoamericanas (FIEL),Working Paper No. 77.

Economie politique des litiges des contrats dans le domaine prive de l’eauet des installations sanitaires publiques. Lecons d’Argentine

L’article examine les causes des discussions des contrats dans les secteurs de l’eau etle secteur sanitaire et le revirement qui en resulte dans le processus de privatisation.Des donnees ont ete rassemblees a partir de quatre grandes etudes de cas en Argentine.Le debat est base sur les donnees reprises dans les soumissions legales realisees parle gouvernement argentin et les entreprises qui contestent au «International Centrefor the Settlement of Investment Disputes». Les resultats de l’article proposent deslecons importantes pour l’elaboration et la gestion de contrats similaires dans d’autrespays.

Politische Okonomie der Vertragsstreitigkeiten mit privaten Wasserver-und Abwasserentsorgungsunternehmen: Lehren aus Argentinien

In dem Beitrag werden die Grunde von Vertragsstreitigkeiten im Wasser- und Ab-wassersektor sowie die sich daraus ergebende Umkehr des Privatisierungsprozessesuntersucht. Die Ergebnisse entstammen vier großen Studien aus Argentinien, wobeidie Diskussion auf Befunden aus Eingaben der argentinischen Regierung undder streitenden Unternehmen an das Internationale Zentrum zur Beilegung vonInvestitionsstreitigkeiten basiert. Die Ergebnisse der Untersuchung bieten anderenLandern eine wichtige Lehre fur die Formulierung und das Management ahnlicherVertrage.

Economıa polıtica de los litigios en los contratos en el ambito privado de losservicios de aguas y en las instalaciones sanitarias publicas. Lecciones

de Argentina

El artıculo examina las causas de las discrepancias en los contratos en los sectoresdel agua y sanitario, ası como los virajes que se han producido en los procesos deC© 2011 The AuthorAnnals of Public and Cooperative Economics C© 2011 CIRIEC

44 HULYA DAGDEVIREN

privatizacion. Estos datos se han reunido a partir de cuatro grandes estudios de casoen Argentina. El debate esta fundamentado en los datos obtenidos de los procesoslegales sustanciados por el gobierno argentino y las empresas que responden al“International Centre for the Settlement of Investment Disputes”. En sus conclusionesel artıculo propone lecciones importantes para la elaboracion y la gestion de contratossimilares en otros paıses.

C© 2011 The AuthorAnnals of Public and Cooperative Economics C© 2011 CIRIEC


Recommended