+ All Categories
Home > Documents > R56 Compliance Audit - BidNet

R56 Compliance Audit - BidNet

Date post: 01-Feb-2023
Category:
Upload: khangminh22
View: 0 times
Download: 0 times
Share this document with a friend
49
R56 Compliance Audit APPENDIX F - R56 Compliance Audit Page 1 of 8 9/16/2017 WAC Responsibility Customer Responsibility WAC Failure Customer Failure DESCRIPTION Passed Failed Passed Failed N/A Date Corrected Date Corrected Reference 1 GENERAL a. A copy of the Project Manager's Compliance Sheet has been completed, certified and supplied for attachment to this audit. X N/A N/A b. Project Manager's Compliance Sheet shows that all appropriate requirements have been met. X N/A N/A TOTALS FOR SECTION 0 0 0 0 2 2 a. The ceiling height is sufficient to meet requirements for equipment installation. X N/A Paragraph 3.6.1 b. Cable runway system meets the proper installation requirements. X N/A Paragraph 3.10.5 c. The floor is sealed as required. X N/A N/A Paragraph 3.6.2 d. Transmission line entry ports, holes or openings which penetrate the outer surface of the building have been properly sealed. X N/A Paragraph 3.7.1 e. Adequate lighting and air conditioning requirements met. X N/A N/A Paragraph 3.11 f. Minimum required fire suppression equipment is properly installed. X N/A Paragraph 3.12 g. A first aid kit is available and meets requirements. X N/A N/A Paragraph 3.13.1 h. Required personal protective safety items are available for servicing batteries which require such items. X N/A N/A Paragraph 3.13.2 i. A telephone, microwave link, or cellular phone has been made available. X N/A N/A Paragraph 3.14 j. Phone numbers of importance are posted at the site. X N/A N/A Paragraph 3.14 k. The minimum required signage is posted at the site. X N/A N/A Paragraph 3.15 TOTALS FOR SECTION 0 0 6 4 1 3 EXTERNAL GROUNDING a. An External Ground Bus bar (EGB) of suitably sized material is properly installed at the transmission line entry point. X N/A N/A Paragraph 4.4.3 b. The EGB grounding electrode conductor has been properly installed. X N/A N/A Paragraph 4.4.3 c. When a tower ground bus bar (TGB) is used, it meets the proper installation and bonding requirements. X N/A N/A Paragraph 4.4.3.1 BUILDING DESIGN AND INSTALLATION Customer Name: County of Routt-Steamboat Springs, CO Project Manager: Project #: Site Name: Mt Werner Inspector's Name: Roger Hays Audit Date: 9/1/2017
Transcript

R56 Compliance Audit APPENDIX F - R56Compliance Audit

Page 1 of 89/16/2017

WAC Responsibility Customer Responsibility WAC Failure

Customer Failure

DESCRIPTIONPassed Failed Passed Failed N/A

Date Corrected

Date Corrected

Reference

1 GENERAL

a. A copy of the Project Manager's Compliance Sheet has been completed, certified and supplied for attachment to this audit.

X N/A N/A

b. Project Manager's Compliance Sheet shows that all appropriate requirements have been met. X N/A N/A

TOTALS FOR SECTION 0 0 0 0 2

2

a. The ceiling height is sufficient to meet requirements for equipment installation. X N/A Paragraph 3.6.1

b. Cable runway system meets the proper installation requirements.X N/A Paragraph 3.10.5

c. The floor is sealed as required. X N/A N/A Paragraph 3.6.2

d. Transmission line entry ports, holes or openings which penetrate the outer surface of the building have been properly sealed.

X N/A Paragraph 3.7.1

e. Adequate lighting and air conditioning requirements met.X N/A N/A Paragraph 3.11

f. Minimum required fire suppression equipment is properly installed.X N/A Paragraph 3.12

g. A first aid kit is available and meets requirements.X N/A N/A Paragraph 3.13.1

h. Required personal protective safety items are available for servicing batteries which require such items. X N/A N/A Paragraph 3.13.2

i. A telephone, microwave link, or cellular phone has been made available. X N/A N/A Paragraph 3.14

j. Phone numbers of importance are posted at the site.X N/A N/A Paragraph 3.14

k. The minimum required signage is posted at the site.X N/A N/A Paragraph 3.15

TOTALS FOR SECTION 0 0 6 4 1

3 EXTERNAL GROUNDING

a. An External Ground Bus bar (EGB) of suitably sized material is properly installed at the transmission line entry point.

X N/A N/A Paragraph 4.4.3

b. The EGB grounding electrode conductor has been properly installed.

X N/A N/A Paragraph 4.4.3

c. When a tower ground bus bar (TGB) is used, it meets the proper installation and bonding requirements.

X N/A N/A Paragraph 4.4.3.1

BUILDING DESIGN AND INSTALLATION

Customer Name: County of Routt-Steamboat Springs, CO

Project Manager: Project #:

Site Name: Mt Werner

Inspector's Name: Roger Hays Audit Date: 9/1/2017

R56 Compliance Audit APPENDIX F - R56Compliance Audit

Page 2 of 89/16/2017

WAC Responsibility Customer Responsibility WAC Failure

Customer Failure

DESCRIPTIONPassed Failed Passed Failed N/A

Date Corrected

Date Corrected

Reference

d. Each transmission line outer shield is properly bonded to the tower or TGB at the transition of the vertical transmission line run with a weather sealed transmission line grounding kit.

X N/A Paragraph 4.7.9

e. Each transmission line outer shield is properly bonded to the EGB with a weather sealed transmission line grounding kit.

X N/A N/A Paragraph 4.7.9

f. The tower is properly bonded with the required number grounding conductors. X N/A

Paragraphs 4.7.6 & 4.9

g. Ice bridges / cable supports have been properly bonded to the EGB.X N/A Paragraph 4.7.10.2

h. Each ice bridge / cable support post has been properly bonded to the grounding electrode system. X N/A N/A Paragraph 4.7.10.2

i. Ice bridges / cable supports have been properly isolated from the tower. X N/A N/A Paragraph 4.7.10.2

j. Guy wires are properly bonded and their grounding conductor maintains a continuous vertical drop to the grounding electrode.

X N/A N/A Paragraph 4.7.6.2.1

k. Fencing has been properly bonded to a ground system as required.X N/A N/A Paragraph 4.7.10.1

l. Each fence gate is properly bonded to its supporting fence post as required. X N/A N/A Paragraph 4.7.10.1

m. Gate supporting fence posts are properly bonded as required.X N/A N/A Paragraph 4.7.10.1

n. Generator and support skids have been properly bonded as required. X N/A N/A

Paragraphs 4.7.7.1 & 6.9.7

o. Items listed below are properly bonded to the grounding electrode system as required. Paragraph 4.7.10

o.1 Metallic entry ports X N/A N/A Paragraph 4.7.10

o.2 Cable conduits or raceways X N/A N/A Paragraph 4.7.10

o.3 Metallic piping (water, gas, electrical conduits, etc..)X N/A N/A Paragraph 4.7.10

o.4 Air conditioner units X N/A N/A Paragraph 4.7.10

o.5 Metal siding and/or roofing on buildingsX N/A N/A Paragraph 4.7.11

o.6 Vent covers and grates X N/A N/A Paragraph 4.7.10

o.7 Metal fuel storage tanks (above or below ground)X N/A

Paragraphs 4.7.10 & 6.9.7

o.8 Building skid or pier foundations X N/A Paragraph 4.7.10

o.9 Anchors on prefabricated buildingsX N/A N/A Paragraph 4.7.10

o.10 Metallic structures for antenna supports, light fixtures, etc.X N/A N/A

Paragraphs 4.7.6.3 & 4.7.10

o.11 Satellite dish supports X N/A N/A Paragraph 4.8o.12 GPS antenna supports X N/A N/A Paragraph 4.8

o.13 Hand and safety rails X N/A N/A Paragraph 4.7.10o.14 Ladders and safety cages X N/A N/A Paragraph 4.7.10

o.15 Security bars and window frames X N/A N/A Paragraph 4.7.10o.16 Main electrical ground

X N/AParagraphs 4.3 &

6.2.2o.17 Main telco ground

X N/AParagraphs 4.3 &

4.7.10

R56 Compliance Audit APPENDIX F - R56Compliance Audit

Page 3 of 89/16/2017

WAC Responsibility Customer Responsibility WAC Failure

Customer Failure

DESCRIPTIONPassed Failed Passed Failed N/A

Date Corrected

Date Corrected

Reference

p. Approved bonding techniques have been used for the connection of dissimilar metals. X N/A Paragraph 4.5

q. Approved methods have been used for conductor connection and termination. X N/A N/A Paragraph 4.6

r. Bonding surfaces for lugs and clamps are free of paint and corrision and a conductive anti-oxidant compound has been applied.

X N/A N/AParagraphs 4.5.4 & 4.6.1

s. All painted or galvanized bonding surfaces for exothermic welds were cleaned and painted to inhibit rusting.

X N/A N/A Paragraph 4.6

t. All grounding conductors have been routed towards the EGB, TGB or the grounding electrode system and the minimum bending radius has been observed. X N/A Paragraph 4.4.2.2

u. Grounding conductors are routed as straight as possible and protected from physical damage as required.

X N/A N/A Paragraph 4.4.2.3

v. Grounding conductors maintain the minimum required separation from other cable groups. X N/A N/A Paragraph 9.9.3.2

w. Grounding conductors are securely fastened as required.X N/A N/A Paragraph 4.4.2.3

x. Grounding conductors meet or exceed the conductor size requirements. X N/A N/A

Paragraphs 4.4.2.1 & 4.8

y. Braided grounding conductors are not used anywhere in the external ground system. X N/A N/A Paragraph 4.7.9

TOTALS FOR SECTION 0 0 15 9 17

4 INTERNAL GROUNDING

a. A properly sized Master Ground Bus Bar (MGB) is installed as required. X N/A N/A Paragraph 5.3.1

b. The MGB grounding electrode conductor has been properly bonded and routed towards the grounding electrode system.

X N/A N/A Paragraph 5.3.1.3

c. All conductors connections to the MGB follow approved connection methods. X N/A N/A Paragraphs 5.4.3

d. Where required a Sub System Ground Bus Bar (SSGB) has been properly installed. X N/A N/A Paragraph 5.3.2

e. The SSGB has been bonded back to the MGB as required.X N/A N/A Paragraph 5.3.2.3

f. All conductor connections to the SSGB follow the approved connection methods. X N/A N/A Paragraphs 5.4.3

g. Where required an Internal Perimeter Ground Bus (IPGB) is properly installed. X N/A Paragraph 5.3.7

h. Only ancillary equipment is bonded to the IPGB.X N/A Paragraph 5.3.7

i. Each ancillary support apparatus is properly bonded to the IPGB, MGB, or SSGB. X N/A

Paragraphs 5.4.1 & 5.5.1.6

R56 Compliance Audit APPENDIX F - R56Compliance Audit

Page 4 of 89/16/2017

WAC Responsibility Customer Responsibility WAC Failure

Customer Failure

DESCRIPTIONPassed Failed Passed Failed N/A

Date Corrected

Date Corrected

Reference

j. Items listed below are properly bonded to the MGB, SSGB, or IPGB by the approved connection methods. Paragraphs 5.4.1 &

5.5.1

j.1 Piping systemsX N/A N/A

Paragraphs 5.5.1.6 & 5.5.1.7

j.2 Steel roof trusses X N/A N/A Paragraph 5.5.1.7

j.3 Exposed support beams or columnsX N/A N/A Paragraph 5.5.1.7

j.4 Ceiling grids X N/A N/A Paragraph 5.8.3.2

j.5 Raised equipment floor support structure at the proper intervals.X N/A N/A

Paragraphs 5.4.2 & 5.8.3.2

j.6 Any exposed metallic building materials (metal siding)X N/A N/A Paragraph 5.5.1.6

k. Surge Protection Device (SPD) metal housings are bonded to the MGB, SSGB or IPGB as required. X N/A Paragraph 5.5.1.6

l. Separately derived AC electrical systems are bonded to the MGB or SSGB as required. X N/A

Paragraphs 5.5.1.1 & 6.2.2

m. Primary telephone, control, and data network circuit SPDs are properly installed bonded to the MGB or SSGB as required.

X N/A N/A Paragraph 5.5.1.8.2

n. RF transmission line SPDs are bonded to the MGB or a separate equipment area SSGB as required. X N/A Paragraph 5.5.1.8.1

o. Cable runways are bonded to the MGB or SSGB as required.X N/A Paragraph 5.5.1.5

p. Each cable runway section is bonded to the adjoining section as required. X N/A Paragraph 5.5.1.5

q. Ground bus conductors and their extensions are sized as required.X N/A N/A

Paragraphs 5.3.5 & 5.3.6

r. All ground bus conductors, ground bus extensions and equipment grounding conductors are routed towards the MGB or SSGB as required. X N/A N/A Paragraph 5.3.4

s. Bonding connections to a ground bus or its extensions have been properly insulated as required. X N/A N/A Paragraph 5.3.4

t. Cabinets have been properly bonded back to the MGB, SSGB or ground bus by approved methods. X N/A N/A Paragraph 5.5.1.4

u. Racks have been properly bonded back to the MGB, SSGB or ground bus by approved methods. X N/A Paragraph 5.5.1.4

v. Any RGB located within a cabinet or rack is properly bonded back to the MGB, SSGB or ground bus as required.

X N/A Paragraph 5.3.3

w. Individual system component chassis equipment is properly bonded as required. X N/A Paragraph 5.5.1.3

x. Secondary telephone, control, and data network circuit SPDs are properly installed and bonded back to MGB or SSGB as required.

X N/A N/AParagraphs 5.5.1.8.3 & 5.8.3.1

y. All required control center and dispatch equipment is properly bonded back to the MGB, SSGB, or ground bus conductor as required. X N/A N/A Paragraph 5.8.3

R56 Compliance Audit APPENDIX F - R56Compliance Audit

Page 5 of 89/16/2017

WAC Responsibility Customer Responsibility WAC Failure

Customer Failure

DESCRIPTIONPassed Failed Passed Failed N/A

Date Corrected

Date Corrected

Reference

TOTALS FOR SECTION 0 0 7 11 12

5 POWER SOURCES

a. Circuit breakers are labeled to identify the receptacle outlet they are protecting. X N/A N/A Paragraph 6.2.6

b. Proper clearance requirements are being observed for power panels. X N/A Paragraph 6.2.4

c. Outlet boxes are permanently marked to identify their assigned circuit breakers and panels. X N/A Paragraph 6.2.10

d. Power receptacle outlets are mounted securely to the supporting structure. X N/A N/A Paragraph 6.2.11

e. Adequate service receptacle outlets are provided for the technician.X N/A N/A Paragraph 6.2

f. Each critical piece of equipment has a dedicated branch circuit and dedicated simplex receptacle. X N/A N/A Paragraph 6.2.10

g. Power receptacles are installed by the equipment load as required.X N/A N/A Paragraph 6.2.10

h. Extension cords including temporary outlet strips are not used in the final installation. X N/A N/A Paragraph 6.2.9

i. Exterior receptacle outlets and circuits are GFCI protected as required. X N/A N/A Paragraph 6.2.5.1

j. AC power receptacle outlets and strips are of the proper type and securely mounted off the floor. X N/A Paragraph 6.2.11

k. Appropriate clearance is being observed for safe servicing of UPS and battery banks. X N/A Paragraph 6.5.1

l. The neutral - ground bonding conductor has been properly installed in the main service disconnect as required.

X N/A Paragraph 6.2.1

m. Equipment grounding conductors have been installed as required.X N/A N/A Paragraph 6.2.7

n. Solar panels have been located away from objects that could damage or block sunlight to the panel.

X N/A N/A Paragraph 6.6.2

o. Proper mounting practices are being observed for solar panels or wind generators. X N/A N/A Paragraph 6.6.2

p. Battery racks are bolted to the floor or wall.X N/A N/A Paragraph 6.7.9

q. Battery conductors are enclosed in PVC, metallic conduit or raceways. X N/A N/A Paragraph 6.7.9

r. A battery disconnect and suitable circuit protection device has been installed as required. X N/A N/A

Paragraphs 6.7.9,& 10

s. When a standby power generator has been installed, it meets the proper installation requirements. X N/A N/A Paragraphs 6.8,& 9

t. Standby generators are located in areas only accessible by authorized personnel. X N/A N/A Paragraph 6.9.1

R56 Compliance Audit APPENDIX F - R56Compliance Audit

Page 6 of 89/16/2017

WAC Responsibility Customer Responsibility WAC Failure

Customer Failure

DESCRIPTIONPassed Failed Passed Failed N/A

Date Corrected

Date Corrected

Reference

u. Standby generators have an adequate area provided for servicing.

X N/A N/A Paragraph 6.9.1

v. Fuel storage tanks for standby generators are located within a secured area. X N/A Paragraph 6.9.2

w. A dedicated electrical circuit has been provided at the generator.X N/A N/A Paragraph 6.9.4

x. A transfer switch of the proper ampacity rating has been installed to perform the switching between commercial power and standby generator power. X N/A N/A Paragraph 6.9.3

y. A main service disconnect has been installed as required.X N/A N/A

Paragraphs 6.2.1 & 6.2.5 & 6.9.3

z. Electrical panelboard ampacity ratings are properly coordinated.X N/A N/A Paragraph 6.2 & 6.9.3

TOTALS FOR SECTION 0 0 11 6 9

R56 Compliance Audit APPENDIX F - R56Compliance Audit

Page 7 of 89/16/2017

WAC Responsibility Customer Responsibility WAC Failure

Customer Failure

DESCRIPTIONPassed Failed Passed Failed N/A

Date Corrected

Date Corrected

Reference

6

a. A Type 1 SAD/MOV surge protection device (SPD) is installed as required. X N/A N/A Paragraph 7.4.1

b. A Type 2 MOV surge protection device (SPD) is installed as required. X N/A N/A Paragraph 7.4.1

c. Primary SPDs for telephone circuits are installed as required.X N/A Paragraph 7.5

d. Secondary SPDs for telephone circuits are installed as required.X N/A N/A Paragraph 7.5

e. Primary SPDs for control circuits are installed as required.X N/A N/A Paragraph 7.5

f. Secondary SPDs for control circuits installed as required.X N/A N/A Paragraph 7.5

g. Primary SPDs for data network circuits are installed as required.X N/A N/A Paragraph 7.5

h. Secondary SPDs for data network circuits are installed as required.X N/A N/A Paragraph 7.5

i. All RF transmission lines, including unused spares, have coaxial RF type SPDs properly installed as required.

X N/A N/A Paragraph 7.6

j. Where a tower top amplifier has been installed, the sample port and its control cables have SPDs installed as required.

X N/A N/A Paragraph 7.6

k. Tower lighting system AC power and data/alarm circuits have SPDs properly installed as required. X N/A N/A Paragraph 7.8

TOTALS FOR SECTION 0 0 2 1 8

7

a. Equipment spacing and aisle widths conform to guidelines.X N/A Paragraph 9.3.1

b. Equipment is level and plumb.X N/A N/A Paragraph 9.5

c. Equipment is square with surrounding equipment and walls.X N/A N/A Paragraph 9.5

d. Where applicable, seismic installation practices have been observed. X N/A N/A Paragraphs 9.4.1

e. Cabinets and racks are secured as required.X N/A N/A Paragraphs 9.6

f. Cables and cable groups of different function maintain a minimum 5 cm (2 in.) separation as required.

X N/AParagraph 9.9.1.5 & 9.9.3.2

g. RF cables meet or exceed minimum bending radius requirements.

X N/A N/AParagraphs 9.9.1.4 & 9.9.8

h. Plenum-rated cables are installed as required.X N/A N/A Paragraph 9.9.2

i. Proper cable lengths are used.X N/A N/A Paragraph 9.9.1.2

j. Cables are properly secured at the required intervals. X N/A Paragraph 9.9

k. AC power conductors installed on cable runway systems meet installation requirements. X N/A N/A

Paragraphs 3.10.4 & 9.9.3

EQUIPMENT INSTALLATION

TRANSIENT VOLTAGE SURGE SUPPRESSION

R56 Compliance Audit APPENDIX F - R56Compliance Audit

Page 8 of 89/16/2017

WAC Responsibility Customer Responsibility WAC Failure

Customer Failure

DESCRIPTIONPassed Failed Passed Failed N/A

Date Corrected

Date Corrected

Reference

l. Cables are properly identified with a standard, double-ended system.X N/A Paragraph 9.9.12

m. Distribution frame wiring conforms to the proper punch-down or wire-wrap techniques. X N/A Paragraph 9.9.11

n. CAT-5 cables maintain the proper separation from AC power cables.X N/A N/A Paragraph 9.9.6.4

o. CAT-5 cables do not have any sharp bends.X N/A N/A Paragraph 9.9.6.5

p. CAT-5 cables meet all other installation requirements.X N/A N/A Paragraph 9.9.6

q. Cables installed below raised flooring systems are properly installed.

X N/A N/AParagraphs 3.10.2 & 9.9

r. Cables installed above suspended ceilings are properly installed.X N/A N/A Paragraph 9.9.3.3

s. Electrostatic discharge practices are observed as required.X N/A Paragraph 9.10

TOTALS FOR SECTION 0 0 8 6 5

WAC CUSTOMER

Number of Passed

Number of Failed

Number of Passed

Number of Failed

Total N/A

AUDIT TOTALS 0 0 49 37 54

MT WERNER R56 AUDIT

W E RNE R M OU N TAI N S I T E

RO UT T E CO UNT Y, C OL O RA DO

RF SITE

READINESS INSPECTION REPORT

Wireless Advanced Communications

Mt Werner R56 Audit

MT WERNER SITE

SITE READINESS INSPECTION REPORT

1. INTRODUCTION

Today’s public safety communications and E911 systems have more

features and more functionality than ever before. The introduction of

computers and computer networking technology has created the ability to

provide more mission critical flexibility. However, computers, computer

based equipment, and networks provide unique challenges in order to ensure

safe and reliable operation. This is especially true in a public safety

environment.

The design and development of communications sites is critical not only to

optimal functioning of the communications system, but also to the safety of

installation, maintenance, and dispatch personnel. With this in mind,

Motorola has developed the publication Standards and Guidelines for

Communication Sites (commonly known as R56). This publication is a

compilation of requirements, guidelines, and best practices gathered from

sources including ANSI, IEEE, NFPA-70 (commonly known as National

Electrical Code), OSHA, UL, and others.

On September 1st, 2017, Wireless Advanced Communications performed a

site readiness inspection at the Werner Mountain Conventional RF Site

located near Steamboat Springs, Colorado. The site was inspected as to its

suitability to RF equipment in the existing building.

The site was inspected for electrical safety, equipment reliability, and site

quality as related to the operation of a mission critical radio

communications network. The National Electrical Code® and the Motorola

publication, Standards and Guidelines for Communication Sites were used as the basis of the inspection and this report. This report contains the

following topics:

Site Identification

Site Description

Executive Summary

Disclaimer

Electrical Wiring Inspection Results

Building Design and Installation

External Grounding Inspection Results

Wireless Advanced Communications 3901 West Service Road, Evans, CO. 80620 Tel: 800-456-0247 Mt Werner R56 Audit

MT WERNER SITE

Wireless Advanced Communications 3901 West Service Road, Evans, CO. 80620 Tel: 800-456-0247

- 2 - Mt Werner R56 Audit

Internal Grounding Inspection Results

Power Sources Inspection Results

Transient Voltage Surge Suppression Inspection Results

Installation Inspection Results

This report is intended to be used in conjunction with the R56 audit form

provided as a separate document.

Project Identification

Identifying Name

Mt Werner

Customer or Buyer

Routt County

Motorola Contact for

this Document

Roger Hays, CETma,

(970-415-2902)

2. SITE IDENTIFICATION

Site Name

Mt Werner

Site Address

Steamboat Springs, Colorado

N 40.27.369’ W 106.44.430’

3. SITE DESCRIPTION

The Werner Mountain RF Site contains equipment for the county of Routt,

Colorado. The site is equipped with a backup generator and an automatic

transfer switch.

MT WERNER SITE

Wireless Advanced Communications 3901 West Service Road, Evans, CO. 80620 Tel: 800-456-0247

- 3 - Mt Werner R56 Audit

4. EXECUTIVE SUMMARY

The Mt Werner Site is in fair condition in regards to its intended use as a

conventional RF site. My main concerns are making sure the site’s Internal

Perimeter Ground Bus (IPGB) only has ancillary equipment bonded to it

and a minimum 4” gap on the opposite wall of Master Ground Bus bar

(MGB). Also two of the tower leg’s ground are showing very high

resistance to earth ground. This would indicate the tower legs are not

properly bonded to a tower ring.

The National Electrical Code® violations revealed at the site are a

potential life safety issue.

5. DISCLAIMER

Wireless Advanced Communication offers recommendations within this

report solely for the purpose of improving life safety at the site, and

improving system reliability and availability. This report is not intended as a design specification or an instruction manual for untrained persons. No

opinions or recommendations expressed in this report shall result in liability to WAC or the author for any losses, damages, expenses, claims or causes

of action incurred or sustained by any citizen, employee, representative or contractor of Routt County for any reason whatsoever. All work performed

to correct the identified deficiencies shall be performed by properly trained,

licensed and qualified personnel. All work shall be performed in

compliance with the National Electrical Code®; the Motorola document,

Standards and Guidelines for Communication Sites (R56); and all other

applicable federal, state, and local codes.

6. ELECTRICAL WIRING INSPECTION RESULTS

A cursory inspection of wiring revealed no problems. It is suggested that the

site be inspected by a qualified, licensed electrician in order to verify.

7. BUILDING DESIGN AND INSTALLATION

The design and development of communications sites is critical not only to

optimal functioning of the communications system, but also to the safety of

installation, maintenance, and dispatch center personnel. The importance of

MT WERNER SITE

Wireless Advanced Communications 3901 West Service Road, Evans, CO. 80620 Tel: 800-456-0247

- 4 - Mt Werner R56 Audit

implementing and following safety programs during construction as well as

during the system's useful life cannot be overemphasized.

AUDIT

ITEM

AUDIT REQUIREMENT RECOMMENDED

CORRECTIVE ACTION

2.a

The ceiling height is sufficient to meet

requirements for equipment installation

The ceiling shall be high enough

to accommodate equipment racks,

cable trays, cabling, and servicing

of the associated equipment.

The minimum ceiling height for

communication sites utilizing 84-

inch (7 foot) racks is

recommended to be 8.5 feet.

The ceiling height is less than

the recommended 8.5 feet.

See R56 Section 3.6.1.

2.b

Cable runway system meets the proper

installation requirements

A minimum separation of 12

inches above the top of the cable

runway and the ceiling shall be

maintained.

A minimum separation of 6 inches

between the top of an equipment

rack or cabinet and the bottom of

the cable runway shall be

maintained.

The cable runway doesn’t not

meet the 12 inches of separation

between the ceiling and the top

of the rack.

Reference can also be found in

NFPA 70 (NEC), Article 392.

See R56 Section 3.10.5.

MT WERNER SITE

Wireless Advanced Communications 3901 West Service Road, Evans, CO. 80620 Tel: 800-456-0247

- 5 - Mt Werner R56 Audit

AUDIT

ITEM

AUDIT REQUIREMENT RECOMMENDED

CORRECTIVE ACTION

2.d

Transmission line entry ports, holes or openings

which penetrate the outer surface of the building

have been properly sealed

All site buildings shall be weather

tight and shall deter entry by

animals, birds, and insects.

The building/shelter and the port

attachment to the building/shelter,

shall be designed to prevent

animals or birds from nesting in

and around the entry ports.

Unused transmission line ports

shall be properly sealed using a

cap supplied by the manufacturer.

Cable boots shall be the correct

size for the cable installed.

The MGB ground conductor is

not properly sealed where it

exits the transmission line port.

See R56 Section 3.7.1.

MT WERNER SITE

Wireless Advanced Communications 3901 West Service Road, Evans, CO. 80620 Tel: 800-456-0247

- 6 - Mt Werner R56 Audit

2.f

Minimum required fire suppression equipment is

properly installed

All sites must have fire

suppression equipment available

on site.

A fixed or total flood fire

suppression system does not

nullify the need for portable fire

extinguishers.

There must be a minimum 15-20

lbs. Class ABC extinguisher for

general firefighting. Dry

chemical extinguishers are

acceptable, although FE-36 or

Halotron are preferred around

sensitive electronic equipment.

There must be at a minimum 7-10

lbs. Class BC, carbon dioxide

(CO2) or equivalent type

extinguisher for fighting electrical

equipment fires.

Portable fire extinguishers shall be

maintained in a fully charged and

operable condition.

Fixed suppression systems shall

be equipped with adequate

automatic detection devices and

automatic alarms.

For fixed suppression systems,

appropriate warning signs shall be

posted at the entrance of the

protected area.

Smoke detectors shall not be

located directly above a cable

tray.

The site does not contain either

portable fire extinguisher.

Reference can also be found in

NFPA 10, NFPA 12, and NFPA

2001.

See R56 section 3.12.

MT WERNER SITE

Wireless Advanced Communications 3901 West Service Road, Evans, CO. 80620 Tel: 800-456-0247

- 7 - Mt Werner R56 Audit

8. EXTERNAL GROUNDING INSPECTION RESULTS

Some of the purposes for external grounding are:

• To help limit the voltage caused by accidental contact of the site AC supply

conductors with conductors of higher voltage.

• To help dissipate electrical surges and faults, to minimize the chances of

injury from grounding system potential differences.

• To help limit the voltages caused by lightning.

• To help maintain a low potential difference between exposed metallic

objects.

• To stabilize the AC voltage relative to the earth under normal conditions.

• To contribute to reliable equipment operation.

• To provide a common signal reference ground.

• See article 250 of the National Electrical Code® for more details.

MT WERNER SITE

Wireless Advanced Communications 3901 West Service Road, Evans, CO. 80620 Tel: 800-456-0247

- 8 - Mt Werner R56 Audit

MT WERNER SITE

Wireless Advanced Communications 3901 West Service Road, Evans, CO. 80620 Tel: 800-456-0247

- 9 - Mt Werner R56 Audit

AUDIT

ITEM AUDIT REQUIREMENT RECOMMENDED CORRECTIVE ACTION

3.d

Each transmission line outer shield is properly bonded

to the tower or TGB at the transition of the vertical

transmission line run with a weather sealed

transmission line grounding kit.

The transmission line ground kit shall be weather

sealed and installed per manufacturer

specifications.

The transmission line ground kit shall be bonded

a properly installed TGB or to an effectively

grounded vertical member of the tower using

manufacturer approved methods.

The ground kit lead shall be installed without a

drip loop, parallel to the transmission line, and

pointed down towards the earth to provide a

direct discharge path for lightning.

A transmission line ground kit shall be installed

near the antenna mounting location and at the

bottom of the tower near the cable’s vertical to

horizontal transition point.

Most of the transmission lines have the proper

gr my not be pound kit installed. Please make

sure all transmission line have the same kit.

Any unused transmission lines should be

removed.

Reference can also be found in ANSI T1.334-

2002 and ANSI T1.313-2003.

See R56 section 4.7.9.

3.f

The tower is properly bonded with the required number

grounding conductors

Tower grounding conductors shall be bonded to

the grounding electrode system using exothermic

weld or irreversible high-compression crimping

connections.

Two of the three tower leg grounding

conductors have high resistance readings

indicating they may not be properly bonded to

the tower grounding conductor.

Reference can also be found in ANSI T1.334-

2002, ANSI T1.313-2003, MIL-HDBK-419A

and ANSI/EIA/TIA-222-F-R2003.

See R56 sections 4.7.6 & 4.9

MT WERNER SITE

Wireless Advanced Communications 3901 West Service Road, Evans, CO. 80620 Tel: 800-456-0247

- 10 - Mt Werner R56 Audit

AUDIT

ITEM AUDIT REQUIREMENT RECOMMENDED CORRECTIVE ACTION

3.g

Ice bridges / cable supports have been properly bonded

to the EGB

At the building or shelter cable entry location, the

cable support system needs to be bonded back to

the EGB with a #6 AWG or coarser copper

conductor, or it needs to be bonded directly back

to the grounding electrode system with a #2

AWG or coarser, bare tinned, copper conductor.

Conductor bonding to the cable support system

shall be made using exothermic welding, or listed

two-hole lug and stainless steel hardware.

Conductor bonding to the EGB shall be made

using exothermic welding, irreversible high

compression fitting or listed two-hole lug and

stainless steel hardware.

To help ensure effective bonding of the ice

bridge/cable bridge system, the separate sections

of the structure should be bonded together #6

AWG or coarser, jacketed, copper conductors.

The ice bridge/cable bridge system is not

bonded to the EGB.

Reference can also be found in ANSI T1.334-

2002.

See R56 section 4.7.10.2.

MT WERNER SITE

Wireless Advanced Communications 3901 West Service Road, Evans, CO. 80620 Tel: 800-456-0247

- 11 - Mt Werner R56 Audit

AUDIT

ITEM AUDIT REQUIREMENT RECOMMENDED CORRECTIVE ACTION

3.o7

Metal fuel storage tanks (above or below ground)

All exterior above grade metallic objects that are

located within 6 ft. of the external grounding

system or within 6 ft. of a grounded object, shall

be bonded to the external grounding system with

a minimum # 6 AWG or coarser, copper

conductor.

Grounding conductors routed below or partially

below the earth surface shall be a minimum # 2

AWG or coarser, bare, copper conductor.

In high lightning prone geographical areas, or

areas of high soil resistivity, it is recommended to

bond all metallic items within 10 ft. of the

grounding electrode system or a grounded object.

The metal fuel tank located below the

generator platform needs to be bonded to the

grounding electrode system.

Reference can also be found in ANSI T1.313-

2003 and ANSI T1.334-2000.

See R56 sections 4.7.10 & 6.9.7.

MT WERNER SITE

Wireless Advanced Communications 3901 West Service Road, Evans, CO. 80620 Tel: 800-456-0247

- 12 - Mt Werner R56 Audit

AUDIT

ITEM AUDIT REQUIREMENT RECOMMENDED CORRECTIVE ACTION

3.o.8

Building skid or pier foundations

All exterior above grade metallic objects that are

located within 6 ft. of the external grounding

system or within 6 ft. of a grounded object, shall

be bonded to the external grounding system with

a minimum # 6 AWG or coarser, copper

conductor.

Grounding conductors routed below or partially

below the earth surface shall be a minimum # 2

AWG or coarser, bare, copper conductor.

In high lightning prone geographical areas, or

areas of high soil resistivity, it is recommended to

bond all metallic items within 10 ft. of the

grounding electrode system or a grounded object.

The building skid that support the RF site

building is not bonded to the grounding

electrode system.

Reference can also be found in ANSI T1.313-

2003 and ANSI T1.334-2000.

See R56 section 4.7.10.

MT WERNER SITE

Wireless Advanced Communications 3901 West Service Road, Evans, CO. 80620 Tel: 800-456-0247

- 13 - Mt Werner R56 Audit

AUDIT

ITEM AUDIT REQUIREMENT RECOMMENDED CORRECTIVE ACTION

3.o.16

Main electrical ground

All exterior above grade metallic objects that are

located within 6 ft. of the external grounding

system or within 6 ft. of a grounded object, shall

be bonded to the external grounding system with

a minimum # 6 AWG or coarser, copper

conductor.

Grounding conductors routed below or partially

below the earth surface shall be a minimum # 2

AWG or coarser, bare, copper conductor.

In high lightning prone geographical areas, or

areas of high soil resistivity, it is recommended to

bond all metallic items within 10 ft. of the

grounding electrode system or a grounded object.

Without a licensed electrician present during

the R56 audit it could not be determined if the

main electrical ground is properly bonded to

the grounding electrode system.

Reference can also be found in ANSI T1.313-

2003 and ANSI T1.334-2000.

See R56 sections 4.3 & 6.2.2.

3.o.17

Main telco ground

All exterior above grade metallic objects that are

located within 6 ft. of the external grounding

system or within 6 ft. of a grounded object, shall

be bonded to the external grounding system with

a minimum # 6 AWG or coarser, copper

conductor.

Grounding conductors routed below or partially

below the earth surface shall be a minimum # 2

AWG or coarser, bare, copper conductor.

In high lightning prone geographical areas, or

areas of high soil resistivity, it is recommended to

bond all metallic items within 10 ft. of the

grounding electrode system or a grounded object.

A ground for the main telco could not be seen.

Reference can also be found in ANSI T1.313-

2003 and ANSI T1.334-2000.

See R56 sections 4.3 & 4.7.10.

MT WERNER SITE

Wireless Advanced Communications 3901 West Service Road, Evans, CO. 80620 Tel: 800-456-0247

- 14 - Mt Werner R56 Audit

AUDIT

ITEM AUDIT REQUIREMENT RECOMMENDED CORRECTIVE ACTION

3.p

Approved bonding techniques have been used for the

connection of dissimilar metals

Bare copper, brass and bronze metals shall not be

allowed to come in direct or incidental contact

with bare steel, galvanized steel or aluminum

metal surfaces.

Copper conductors shall not be bonded directly to

steel, galvanized steel or aluminum surfaces

unless using exothermic welds specifically

intended for the purpose.

Copper conductors may be joined to steel,

galvanized steel or aluminum surfaces with the

use of a properly listed bimetallic (stainless steel

or electro tin-plated) transition connectors

equipped with stainless steel securing hardware.

Bimetallic transition clamps shall be of the type,

which provide adequate separation between the

dissimilar metals.

Bonding surfaces for clamped or bolted

connections shall be coated with the appropriate

type of conductive anti-oxidant compound.

Bare copper or tinned copper conductors must be

properly isolated from steel, galvanized steel and

aluminum surfaces with the appropriate type of

insulated standoffs or non-metallic conduit.

On the MGB, EGB, and TGB the ground

conductor lugs need to be coated with the

proper type of conductive anti-oxidant

compound.

Reference can also be found in ANSI T1.313-

2003, ANSI T1.334-2002, IEC 61024-1-2, IEE

STD 142-1991, BS 6651:1999, BS 7430:1998

and NFPA 70-2005.

See R56 section 4.5.

MT WERNER SITE

Wireless Advanced Communications 3901 West Service Road, Evans, CO. 80620 Tel: 800-456-0247

- 15 - Mt Werner R56 Audit

AUDIT

ITEM AUDIT REQUIREMENT RECOMMENDED CORRECTIVE ACTION

3.t

All grounding conductors have been routed towards

the EGB, TGB or the grounding electrode system and

the minimum bending radius has been observed

Grounding conductors shall be run as short,

straight, and smoothly as possible, with the

fewest possible number of bends and curves.

A minimum bending radius of no less than 8

inches and no less than 90 degrees shall be

maintained.

All bends, curves, and connections shall be

routed towards the grounding electrode system,

ground rod, or ground bar.

Some of the EGB ground kits need to be

shortened to the proper length.

Reference can also be found in ANSI T1.313-

2003, ANSI T1.334-2002, NFPA 780-2004 and

NFPA 70-2005.

See R56 section 4.4.2.2.

MT WERNER SITE

Wireless Advanced Communications 3901 West Service Road, Evans, CO. 80620 Tel: 800-456-0247

- 16 - Mt Werner R56 Audit

9. Internal Grounding Inspection Results

Safety of personnel and protection of sensitive electronic equipment from

ground faults, lightning, ground potential rise, electrical surges, and power

quality anomalies are of utmost importance at any communications site.

Though unexpected electrical events like lightning strikes and power surges

cannot be prevented, a properly designed and installed site grounding

electrode systems that may help minimize damage caused by these events.

MT WERNER SITE

Wireless Advanced Communications 3901 West Service Road, Evans, CO. 80620 Tel: 800-456-0247

- 17 - Mt Werner R56 Audit

AUDIT

ITEM

AUDIT REQUIREMENT RECOMMENDED

CORRECTIVE ACTION

4.g

Where required an Internal Perimeter Ground

Bus (IPGB) is properly installed

Note: The picture below is from a different RF

site but it shows what needs to happen to the Mt

Werner RF IPGB.

The IPGB provides a suitable

ground conductor to the MGB for

bonding ancillary support

apparatus, electrical conduits, and

other metallic items.

An IPGB conductor is not required

in rooms or areas that are within a

larger building where support

apparatus is not present or where it

is more practical to bond the

support apparatus to the MGB or

an SSGB.

When used, the IPGB shall be

installed such that it encompasses

the interior of the equipment room

or area with two separately

independent ground bus connectors

on opposite sides of the room.

The two bus conductors should

meet at a point within the

equipment area and approximately

opposite of the MGB.

At the location where the two bus

conductors meet, they shall be

separated by at least 4 inches.

The conductors shall be supported

approximately 2 inches from the

wall surface on insulated standoffs.

On the opposite wall from the

location of the MGB a minimum

4 inch separation needs to be

completed.

See R56 section 5.3.7.

MT WERNER SITE

Wireless Advanced Communications 3901 West Service Road, Evans, CO. 80620 Tel: 800-456-0247

- 18 - Mt Werner R56 Audit

AUDIT

ITEM

AUDIT REQUIREMENT RECOMMENDED

CORRECTIVE ACTION

4.h

Only ancillary equipment is bonded to the IPGB

Only metallic ancillary objects may

be connected to the IPGB.

The IPGB system shall not be used

for bonding communications

equipment, cabinets, or racks to the

MGB or a SSGB.

The radio rack and cable tray

ground conductors need to be

removed from the IPGB and

moved to the MGB.

Reference can also be found in

ANSI T1.334-2002.

See R56 section 5.3.7.

MT WERNER SITE

Wireless Advanced Communications 3901 West Service Road, Evans, CO. 80620 Tel: 800-456-0247

- 19 - Mt Werner R56 Audit

AUDIT

ITEM

AUDIT REQUIREMENT RECOMMENDED

CORRECTIVE ACTION

4.i

Each ancillary support apparatus is properly

bonded to the IPGB, MGB, or SSGB

All metallic ancillary support

apparatus within an equipment

room or specific equipment area

shall be bonded to the IPGB, MGB,

or SSGB with a #6 AWG or

coarser grounding conductor.

When rigid metallic conduit

(RMC) and/or electrical metallic

tubing (EMT), are effectively

joined with threaded couplings or

thread-less compression connectors

and they are joined to an

effectively bonded cabinet, they

may be considered adequately

bonded and do not require

additional bonding.

If metallic conduit does not meet

the above specifications, electrical

conduits shall be bonded to the

IPGB conductor at any point where

they cross within 6 inches of the

IPGB conductor.

Any metal boxes inside the

building that are not currently

bonded to the IPGB need to be

properly bonded.

Reference can also be found in

ANSI T1.334-2002.

See R56 sections 5.4.1 & 5.5.1.6.

MT WERNER SITE

Wireless Advanced Communications 3901 West Service Road, Evans, CO. 80620 Tel: 800-456-0247

- 20 - Mt Werner R56 Audit

AUDIT

ITEM

AUDIT REQUIREMENT RECOMMENDED

CORRECTIVE ACTION

4.k

Surge Protection Device (SPD) metal housings

are bonded to the MGB, SSGB or IPGB as

required.

SPD metallic housing shall be

bonded using a # 6 AWG or

coarser conductor.

The SPD metal box for the

incoming AC power needs to be

bonded to the MGB, or IPGB.

Reference can also be found in

NFPA 70-2005, Articles 250 and

800.

See R56 section 5.5.1.6.

MT WERNER SITE

Wireless Advanced Communications 3901 West Service Road, Evans, CO. 80620 Tel: 800-456-0247

- 21 - Mt Werner R56 Audit

AUDIT

ITEM

AUDIT REQUIREMENT RECOMMENDED

CORRECTIVE ACTION

4.l

Separately derived AC electrical systems are

bonded to the MGB or SSGB as required

Separately derived electrical

systems have no direct electrical

connection between the input and

output.

A generator is only considered to

be a separately derived system

when the automatic transfer switch

(ATS) breaks the neutral

conductor.

A separately derived system shall

bond to the grounding electrode

system using a # 2 AWG or

coarser, green-jacketed grounding

conductor.

Where applicable, the grounding

conductor should be sized to meet

NFPA 70-2008, article 250.66

requirements.

Without a licensed electrician

present during the R56 audit it

could not be determined if the

generator transfer switch

electrical ground is properly

bonded to the grounding

electrode system. If the generator

transfer switch does not break

the neutral conductor from the

main neutral do not add a second

neutral-ground conductor.

Reference can also be found in

NFPA 70-2008.

See R56 sections 5.5.1.1 & 6.2.2.

MT WERNER SITE

Wireless Advanced Communications 3901 West Service Road, Evans, CO. 80620 Tel: 800-456-0247

- 22 - Mt Werner R56 Audit

AUDIT

ITEM

AUDIT REQUIREMENT RECOMMENDED

CORRECTIVE ACTION

4.n

RF transmission line SPDs are bonded to the

MGB or a separate equipment area SSGB as

required

RF SPDs shall be installed and

bonded to the MGB or an SSGB

within 24 inches of the cable entry

point.

An RF SPD can be bonded to the

grounding electrode system by

directly bonding/securing it to the

MGB or an SSGB, or with the use

of a # 6 AWG or coarser grounding

conductor.

The RF SPD grounding conductor

route to the MGB grounding

electrode system should be no

greater than 20 linear feet. When

the grounding conductor is greater

than 20 linear feet, an additional #

2 AWG or coarser, copper

grounding conductor shall be

properly installed between the RF

SPD, or its associated SSGB, and

the nearest accessible location of

the common grounding electrode

system.

The 2 new VHF combiner SPDs

are currently bonded to the

IPGB and need to be removed

and bonded to the MGB.

Reference can also be found in

NFPA 70-2005, Articles 810.21,

820.93 and 820.100.

See R56 section 5.5.1.8.1.

MT WERNER SITE

Wireless Advanced Communications 3901 West Service Road, Evans, CO. 80620 Tel: 800-456-0247

- 23 - Mt Werner R56 Audit

AUDIT

ITEM

AUDIT REQUIREMENT RECOMMENDED

CORRECTIVE ACTION

4.o

Cable runways are bonded to the MGB or SSGB

as required

The cable runway system shall be

bonded to the MGB or an SSGB

with a # 6 AWG, or coarser copper

conductor.

When the cable runway is installed

parallel to the MGB or a separate

equipment room’s SSGB, it shall

be bonded to the associated bus bar

with bi-directional bonding

conductors.

The cable tray is currently

bonded to the IPGB and needs to

be removed and bonded to the

MGB.

Reference can also be found in

NFPA 70-2005, Article 392.

See R56 section 5.5.1.5.

MT WERNER SITE

Wireless Advanced Communications 3901 West Service Road, Evans, CO. 80620 Tel: 800-456-0247

- 24 - Mt Werner R56 Audit

AUDIT

ITEM

AUDIT REQUIREMENT RECOMMENDED

CORRECTIVE ACTION

4.p

Each cable runway section is bonded to the

adjoining section as required

Each joint of a cable runway (tray)

section shall have a bonding

jumper across the joint. All

bonding conductors shall be

installed so that they provide a

direct flow path towards the single

point grounding system.

Exception: When a cable runway

system has labeling that shows it is

UL listed for use as a grounding

conductor.

Cable runway bonding jumpers

shall be # 6 AWG, or coarser.

Bonding jumpers shall be installed

on all metallic non-current-carrying

portions of the cable tray system.

Cable trays shall not be used for

bonding equipment or ancillary

support apparatus to the MGB or

SSGB.

The cable tray joints need a

jumper installed across each

joint.

Reference can also be found in

NFPA 70-2008, Article 392.

See R56 section 5.5.1.5.

MT WERNER SITE

Wireless Advanced Communications 3901 West Service Road, Evans, CO. 80620 Tel: 800-456-0247

- 25 - Mt Werner R56 Audit

AUDIT

ITEM

AUDIT REQUIREMENT RECOMMENDED

CORRECTIVE ACTION

4.u

Racks have been properly bonded back to the

MGB, SSGB or ground bus by approved

method

All racks shall be bonded to a

ground bus conductor, SSGB or the

MGB.

All non-current carrying metallic

parts of the equipment rack shall be

effectively bonded.

The rack shall be bonded to one of

the following with a # 6 AWG

grounding conductor:

-MGB

-Rack ground bus bar (RGB)

-SSGB

-Ground bus conductor

Most of the racks are bonded to

the IPGB which needs to be

removed and bonded to the

MGB.

Reference can also be found in

NFPA 70-2008, Article 250.

See R56 section 5.5.1.4.

MT WERNER SITE

Wireless Advanced Communications 3901 West Service Road, Evans, CO. 80620 Tel: 800-456-0247

- 26 - Mt Werner R56 Audit

AUDIT

ITEM

AUDIT REQUIREMENT RECOMMENDED

CORRECTIVE ACTION

4.v

Any RGB located within a cabinet or rack is

properly bonded back to the MGB, SSGB or

ground bus as required

The RGB is typically a small

ground bus bar located within a

cabinet or rack for bonding

equipment located within the rack

or cabinet.

The RGB shall be bonded to the

MGB or SSGB with a # 2 AWG or

coarser, ground bus conductor.

The VHF radio rack RGB

installed at the top of the rack

needs to be bonded to the MGB.

Reference can also be found in

See R56 section 5.3.3.

4.w

Individual system component chassis equipment

is properly bonded as required

All system component chassis,

panels, card cages, cross connect

panels, test jack field panels, and

other equipment that are equipped

with a ground connection point

shall be bonded to the grounding

system with a # 6 AWG jacketed

grounding conductor.

The VHF MTRs are bonded to

the IPGB which needs to be

removed and bonded to the

MGB. The FBI Quantars need to

be bonded to the MGB. All other

equipment needs to be checked.

See R56 section 5.5.1.3.

MT WERNER SITE

Wireless Advanced Communications 3901 West Service Road, Evans, CO. 80620 Tel: 800-456-0247

- 27 - Mt Werner R56 Audit

MT WERNER SITE

Wireless Advanced Communications 3901 West Service Road, Evans, CO. 80620 Tel: 800-456-0247

- 28 - Mt Werner R56 Audit

10. POWER SOURCES INSPECTION RESULTS

Adherence to the National Electrical Code and applicable industry standards

is vital for the reliable and safe operation of communications equipment. In

order to make public safety communications systems as safe and reliable as

possible, the site power sources must be inspected by a qualified, licensed

electrician in order to ensure compliance with the NEC and R56 standards.

AUDIT

ITEM

AUDIT REQUIREMENT RECOMMENDED

CORRECTIVE ACTION

5.b

Proper clearance requirements are being

observed for power panels

Proper clearance around power

panels is necessary to comply with

the National Electrical Code® and

to ensure safety of personnel during

servicing.

A minimum depth clearance of 36

inches shall be provided in front of

any electrical panel that requires

operating or service.

The work space width required in

front of the electrical panel is the

greater of the width of the

equipment or 30 inches.

Equipment installed above or below

electrical panels shall not extend

more than 6 inches beyond the front

of the panel.

The batteries installed on the

ground below the electrical panel

exceed the 6 inches allowed

beyond the front of the panel.

Reference can also be found in

NFPA 70-2008, Article 110.26.

See R56 section 6.2.4.

MT WERNER SITE

Wireless Advanced Communications 3901 West Service Road, Evans, CO. 80620 Tel: 800-456-0247

- 29 - Mt Werner R56 Audit

AUDIT

ITEM

AUDIT REQUIREMENT RECOMMENDED

CORRECTIVE ACTION

5.c

Outlet boxes are permanently marked to

identify their assigned circuit breakers and

panels

All communications equipment

receptacles shall have their

electrical box or cover plate

permanently marked with the

service panel and appropriate circuit

identification.

The identification shall be readily

visible without requiring the

removal of the plug.

Currently the outlet boxes are not

permanently identified with their

assigned circuit breaker and

panel.

See R56 section 6.2.10.

MT WERNER SITE

Wireless Advanced Communications 3901 West Service Road, Evans, CO. 80620 Tel: 800-456-0247

- 30 - Mt Werner R56 Audit

AUDIT

ITEM

AUDIT REQUIREMENT RECOMMENDED

CORRECTIVE ACTION

5.j

AC power receptacle outlets and strips are of

the proper type and securely mounted off the

floor

Receptacle strips are limited to

specific applications where a

receptacle strip is suitable for use.

In all cases receptacle strips shall be

UL listed and of metal construction.

AC power receptacle strips shall

have a 3-prong power cord when

used for permanent installations.

Receptacle strips shall not include

ON/OFF switches unless the switch

is covered to prevent the switch

from being inadvertently switched

off.

Consumer-grade receptacle strips

shall not be used.

Receptacle strips shall be securely

mounted to the supporting structure

using appropriate hardware.

Receptacle strips shall not be

secured with tie-wraps.

The FBI installed power strip

installed below the cable tray fails

for many reasons listed above.

See R56 section 6.2.11.

MT WERNER SITE

Wireless Advanced Communications 3901 West Service Road, Evans, CO. 80620 Tel: 800-456-0247

- 31 - Mt Werner R56 Audit

AUDIT

ITEM

AUDIT REQUIREMENT RECOMMENDED

CORRECTIVE ACTION

5.k

Appropriate clearance is being observed for

safe servicing of UPS and battery banks

There shall be adequate spacing for

the safe servicing of the UPS and

battery banks.

Working space for a UPS shall not

be less than 36 inches in the

direction of live parts.

The width of the working space

shall be the width of the UPS or 30

inches, whichever is greater.

The state batteries do not meet

the required 36 inches of work

space in the direction of live parts.

Reference can also be found in

NFPA 70-2008, article 110.26.

See R56 section 6.5.1.

MT WERNER SITE

Wireless Advanced Communications 3901 West Service Road, Evans, CO. 80620 Tel: 800-456-0247

- 32 - Mt Werner R56 Audit

AUDIT

ITEM

AUDIT REQUIREMENT RECOMMENDED

CORRECTIVE ACTION

5.l

The neutral - ground bonding conductor has

been properly installed in the main service

disconnect as required

Unless otherwise permitted, there is

to be only one neutral-ground bond.

The neutral-ground bond is usually

found at the main disconnect panel

(first service disconnect).

Additional neutral-ground bonds

may be permitted, but only in the

case of a separately derived system

or other special applications (per the

National Electrical Code®).

More than one neutral-ground bond

can result in neutral current flowing

on the equipment grounding

conductors and/or metallic conduits.

Inspection of this audit item

typically requires a licensed

electrician. If unable to confirm

compliance, this audit item must be

failed and a follow-up inspection by

a licensed electrician is required.

The neutral-ground bonding

connection may be established with

a green grounding screw and/or an

appropriately sized bonding jumper.

Once the neutral-ground bond has

been established, the neutral

conductor shall remain isolated

from ground unless a separately

derived power source has been

installed.

Without a licensed electrician

present during the R56 audit it

could not be determined if the

proper neutral-ground conductor

has been properly installed in the

main service disconnect.

See R56 section 6.2.1.

MT WERNER SITE

Wireless Advanced Communications 3901 West Service Road, Evans, CO. 80620 Tel: 800-456-0247

- 33 - Mt Werner R56 Audit

AUDIT

ITEM

AUDIT REQUIREMENT RECOMMENDED

CORRECTIVE ACTION

5.v

Fuel storage tanks for standby generators are

located within a secured area

Fuel storage tanks located outside a

structure shall be protected from

damage and tampering, and shall be

enclosed within a fenced area.

The minimum recommended

distance between the storage tank

and fence is four feet.

The minimum recommended

distance between the tank and

shelter is ten feet.

The fuel tank is not installed

inside a secure fence but it’s also

understood the Forest Service will

not allow a fence to be installed in

this location.

See R56 section 6.9.2.

11. TRANSIENT VOLTAGE SURGE SUPPRESSION (TVSS)

INSPECTION RESULTS

The installation of Transient Voltage Surge Suppression (TVSS) devices is

a requirement for all communication sites and is essential for all facilities

where communication- related electronics and electrical equipment are in

use. Surges and transient power anomalies are potentially destructive

electrical disturbances, the most damaging being over-voltage occurrences

and short duration over-voltage events. Sometimes referred to as “spikes”,

high-energy transient power anomalies can arise from inductive load

switching or other events within the power system or capacitive and

inductive coupling from environmental events such as nearby lightning

activity. Environmental and inductive power anomalies are wideband

occurrences with a frequency range from close to DC to well into the RF

high frequency spectrum. It is critical that each point of-entry (AC,

telephone, LAN, signal/control and RF) into the equipment area be

protected against these anomalies. This protection is essential to reduce the

MT WERNER SITE

Wireless Advanced Communications 3901 West Service Road, Evans, CO. 80620 Tel: 800-456-0247

- 34 - Mt Werner R56 Audit

risk of personal injury, physical equipment damage, and loss of operations

(equipment down time). Although lightning can cause the most visible

damage, it is not the predominant cause of transient voltages.

AUDIT

ITEM

AUDIT

REQUIREMENT

RECOMMENDED CORRECTIVE ACTION

6.c

Primary SPDs for

telephone circuits are

installed as required

The SPD shall be installed at the entrance point into the

shelter and within close proximity to the electrical service

entrance and the master ground bus bar.

The SPD shall comply with all applicable codes, and be UL

497 listed or conform to the international CE certification

mark.

SPDs that have the grounding conductor incorporated by

the manufacturer as an integral part of the device shall

utilize a # 10 AWG, green jacketed, stranded copper

conductor for a single line device. A multi-line device shall

utilize a # 6 AWG, green jacketed, stranded copper

conductor.

A primary SPD for the telephone circuits installed by

the FBI could not be found.

Reference can also be found in NFPA 70-2008, article 800.

See R56 section 7.5.

12. Installation Inspection Results Adhering to good installation practices and following industry guidelines

for installations of communications equipment helps to ensure the safety of

personnel working at the site, ease of maintenance, and proper functioning

of communications equipment. Refer to RF56 section 9 for requirements.

MT WERNER SITE

Wireless Advanced Communications 3901 West Service Road, Evans, CO. 80620 Tel: 800-456-0247

- 35 - Mt Werner R56 Audit

AUDIT

ITEM

AUDIT REQUIREMENT RECOMMENDED

CORRECTIVE ACTION

7.a

Equipment spacing and aisle widths conform to

guidelines

A minimum depth clearance of 36

inches shall be provided in front of

any electrical panel that requires

operating or service.

A 36 inch aisle shall be maintained

between at least one end of an

equipment row and building wall or

other obstruction. Longer aisles

may require additional 36 inch

access breaks such that a fire in the

aisle does not prevent egress.

As stated in audit item 5b. The

batteries on the floor prevent the

required 36 inches of clearance in

front of the electrical panel.

Also 36 inches of clearance is

required between the 2 rows of

equipment (this would be difficult

to maintain with the size of the

interior).

Reference can also be found in

NFPA 70-2008, article 110.

See R56 section 9.3.1.

MT WERNER SITE

Wireless Advanced Communications 3901 West Service Road, Evans, CO. 80620 Tel: 800-456-0247

- 36 - Mt Werner R56 Audit

AUDIT

ITEM

AUDIT REQUIREMENT RECOMMENDED

CORRECTIVE ACTION

7.f

Cables and cable groups of different function

maintain a minimum 5 cm (2 in.) separation as

required

The four groupings are RF lines;

power cables; ground conductors;

and control, data, telephone, alarm

and reference cables.

Cable groups shall be separated by a

minimum distance of 2 inches from

other cable groups.

Different cable groups can come in

contact with each other if they are

installed and secured so as to

maintain a 90 degree angle crossing.

Transmission lines for transmitting

equipment shall be separated a

minimum distance of 4 inches from

electrical lights, power, and

signaling circuits.

The required 2 inches of

separation between different

cables groups in not maintained in

the cable tray.

Reference can also be found in

NFPA 70-2008, Articles 800, 810,

820, 830 and ANSI/TIA/EIA-568-B

and 569-B.

See R56 sections 9.9.1.5 & 9.9.3.2.

MT WERNER SITE

Wireless Advanced Communications 3901 West Service Road, Evans, CO. 80620 Tel: 800-456-0247

- 37 - Mt Werner R56 Audit

AUDIT

ITEM

AUDIT REQUIREMENT RECOMMENDED

CORRECTIVE ACTION

7.j

Cables are properly secured at the required

intervals

Cables and conductors shall be

secured at intervals of no greater

than 3 feet.

Nonmetallic cable ties shall be used

to secure cables and conductors.

Attachments shall be tight enough to

secure cables, yet not crushing the

cable.

Communication cables or wires

shall not be strapped, taped, or

attached by any means to the

exterior of any electrical conduit or

electrical raceway.

The CAT-5 cables around the

room need to be properly secured.

Reference can also be found in

NFPA 70-2008, article 800 and

ANSI/TIA/EIA-568-B and 569-B.

See R56 section 9.9.

MT WERNER SITE

Wireless Advanced Communications 3901 West Service Road, Evans, CO. 80620 Tel: 800-456-0247

- 38 - Mt Werner R56 Audit

AUDIT

ITEM

AUDIT REQUIREMENT RECOMMENDED

CORRECTIVE ACTION

7.l

Cables are properly identified with a standard,

double-ended system

Because the cables are installed in

groupings, it may be difficult to

follow the individual cable for

servicing. All cables must be

properly labeled.

Cables shall be identified with a

standardized, double-ended system

to facilitate cable and equipment

connection identification. Note the

following requirements for cable

labeling:

-Equipment identification for each

end of cable.

-Connector reference designator for

each end of cable.

-Direction along the cable where

terminating equipment is used.

Labeling shall indicate the

destination ends of the cable, in

terms of equipment name and

connector reference designator or

name.

Most CAT-5, RF and electrical

cables do not meet the proper

form of label.

Reference can also be found in

ANSI/TIA/EIA-606.

See R56 section 9.9.12.

MT WERNER SITE

Wireless Advanced Communications 3901 West Service Road, Evans, CO. 80620 Tel: 800-456-0247

- 39 - Mt Werner R56 Audit

AUDIT

ITEM

AUDIT REQUIREMENT RECOMMENDED

CORRECTIVE ACTION

7.m

Distribution frame wiring conforms to the

proper punch-down or wire-wrap techniques

Cross-connect wires shall be # 22 -

# 24 AWG plastic-insulated solid

copper wire.

Stranded wire shall not be used.

Wiring shall be properly secured

using industry-standard methods.

CAT 3, 4, 5, or 6 data wiring shall

enter punch terminals from the

middle such that one wire points up

while the other wire points down.

In this manner, the cable twist that

maintains the cable impedance stays

intact.

The wires in the “old” microwave

do not conform to the proper

requirement listed above.

See R56 section 9.9.11.

MT WERNER SITE

Wireless Advanced Communications 3901 West Service Road, Evans, CO. 80620 Tel: 800-456-0247

- 40 - Mt Werner R56 Audit

AUDIT

ITEM

AUDIT REQUIREMENT RECOMMENDED

CORRECTIVE ACTION

7.s

Electrostatic discharge practices are observed

as required

Static wrist straps shall be available

at the site.

Static proof packaging shall be

available at the site for storage and

transportation of static sensitive

components.

All precautions specifically stated

for the equipment being worked on

shall be adhered to in accordance

with the respective documentation

for the equipment.

An ESD wrist strap shall be worn

when handling ESD-sensitive

modules.

ESD-protected packaging shall be

available for containing modules

removed from equipment.

Static wrist straps and static proof

packaging need to be added to the

building.

Reference can also be found in

Motorola publication 68P81106E84.

See R56 section 9.10.


Recommended