Date post: | 23-Apr-2023 |
Category: |
Documents |
Upload: | khangminh22 |
View: | 0 times |
Download: | 0 times |
TRANSPORT CONNECTION IN NORTHERN MOUNTAINOUS PROVINCES PROJECT
Resettlement Plan
Cao Bang Province
Project Number : TA7245-VIE
April 2011 (FINAL DRAFT)
PPTA 7245-VIE: Transport Connection in Northern Mountainous Provinces Project
Resettlement Plan
Cao Bang Province Page ii
CURRENCY EQUIVALENTS
(As of March 2011)
Currency Unit = Dong (VND)
$1.00 = VND 20,900
ABBREVIATIONS
ADB = Asian Development Bank
CARB = Compensation, Assistance and Resettlement Board
CPC = Commune People’s Committee
DARD = Department of Agriculture and Rural Development
DP = Displaced Person
DOF = Department of Finance
DONRE = Department of Natural Resources and Environment
DPC = District People’s Committee
FHH = Female-headed household
GOV = Government of Viet Nam
HH = Household
IMO = Independent Monitoring Organization
IOL = Inventory of Losses
LMO = Land Management Organizations
LURC = Land Use Rights Certificate
MARD = Ministry of Agriculture and Rural Development
MOLISA = Ministry of Labour, Invalids and Social Assistance
NGO = Non-government Organization
PDOT = Provincial Department of Transport
PPC = Provincial People’s Committee
PPMU = Provincial Project Management Unit
RCS = Replacement Cost Study
ROW Right of Way
RP = Resettlement Plan
RT = Resettlement Taskforce
SC = Steering Committee
PPTA 7245-VIE: Transport Connection in Northern Mountainous Provinces Project
Resettlement Plan
Cao Bang Province Page iii
GLOSSARY
Assistance Means additional support provided to DPs losing assets (particularly
productive assets), incomes, employment or sources of living, to supplement
payment of compensation for acquired assets, in order to achieve, at a
minimum, full restoration of living standards and quality of life.
Cut-off date Means the date prior to which the occupation or use of any part of the
project area makes residents or occupiers or users of the same eligible to be
recognized as DPs. In this Project, the cut-off date coincides with the
completion of the inventory of losses survey.
Detailed
Measurement
Survey (DMS)
Means the finalization and/or validation of the results of the inventory of
losses (IOL), severity of impacts, and list of DPs. The final cost of
compensation, assistance and resettlement is determined following
completion of the DMS. The DMS will be done by different Compensation, Assistance and Resettlement Board in the phase of RP implementation once the
benchmarks of the project site demarcation are put on the ground.
Displaced Person
(DP)
(referred to as
“Affected Persons”
as per Government
law)
Displaced Persons in a project area could be of three types:
(i) persons with land use rights to land lost in its entirely or in part;
(ii) persons who lost the land they occupy in its entirely or in part
who have no land use rights to such land, but who have claims
to such lands that are recognized or recognizable under
national laws; and
(iii) person who lost the land they occupy in its entirely or in part
who have neither land use rights nor recognized or recognizable
claims to such land.
The involuntary resettlement apply to all three types of displaced persons
Livelihood
restoration
Means the re-establishment or improve of sources of income and livelihood
of relevant DPs through the RP policy and its implementation.
Inventory of Losses
(IOL)
Means the process of identification, location, measurement and valuation of
replacement cost of all fixed assets that will be recovered or adversely
affected by or as a result of the project. These include, (without limitation or
being an exhaustive list) lands used for residence, commerce, agriculture,
ponds; dwelling units, stalls and shops, other structures, such as fences,
tombs, wells; trees with commercial value, sources of income and livelihood.
It also includes the assessment of the severity of the impact of land and
property on the affected assets and the severity of impact to the livelihood
and productive capacity of DPs. IOL is carried in the phase of RP
preparation.
Land recovery (also
referred to land
acquisition)
Means the processes by which all or part of land and property owned,
possess, occupies or uses, are compulsorily recovered or otherwise
acquired from an individual, household, firm or private institution by the
State or are acquired by agreement. Decision on land recovery will be done
through two steps (i) Decision at the provincial or city for the whole project
areas and subsequently (ii) Decision by the district to each individual.
Resettlement or
Relocation
Means the physical relocation of an DP from the DP’s pre-project place of
residence and/or business.
Replacement Cost
Means the amount calculated before displacement which is needed to
replace an affected asset without deductions for taxes, and/or costs of
transaction as follows:
(i) Productive land (Agricultural, fishpond, garden, forest) based on market
prices that reflect recent land sales of comparable land in the district and
other nearby areas, and in the absence of such recent sales, based on
PPTA 7245-VIE: Transport Connection in Northern Mountainous Provinces Project
Resettlement Plan
Cao Bang Province Page iv
productive value;
(ii) Residential land based on market prices that reflect recent sales of
comparable houses and residential land in the district and other nearby
areas, and in the absence of such recent land sales, based on sales in other
locations with similar attributes;
(iii) Houses and other related structures based on current market prices of
materials and labor without depreciation nor deductions for salvaged
building materials;
(iv) Standing crops equivalent current market value of the crop at the time of
compensation;
(v) Perennial crops and trees, cash compensation equivalent to current
market value given the type, age and productive value (future production) at
the time of compensation.
(vi) Timber trees, the price that would currently be paid for the tress on the
nearest market based on the diameter of each tree at breast height.
Replacement Cost
Study
Means the process involved in determining the replacement cost of land,
houses and other affected assets based on surveys by qualified appraisers
or assessors.
Vulnerable People Means individuals or distinct groups of people who might suffer
disproportionately or face the risk of being further marginalized by the
effects of land and property recovery or resettlement and specifically
includes: (i) female headed households with dependents (ii) households with
disabled persons, (iii) households falling under the current MOLISA
benchmark poverty line, (iv) children and elderly households who are with
no other means of support, (v) landless households, and (vi) non-integrated
and vulnerable ethnic minorities.
PPTA 7245-VIE: Transport Connection in Northern Mountainous Provinces Project
Resettlement Plan
Cao Bang Province Page v
TABLE OF CONTENTS
EXECUTIVE SUMMARY I
A. Background 1
B. The Cao Bang Subproject Description 1
II. SCOPE OF LAND ACQUISITION AND RESETTLEMENT 2
A. Inventory of Losses (IOL) 2
B. Affected Households 2
C. Affected Land and Non-Land Assets 2
III. SOCIO-ECONOMIC INFORMATION 3
A. Socio-Economic Profile of Subproject Area 3
B. Socio-Economic Profile of Affected Households 3
IV. INFORMATION DISCLOSURE, CONSULTATION AND PARTICIPATION 4
A. Consultations 4
B. Information Disclosure 5
V. GRIEVANCE REDRESS MECHANISM 5
VI. POLICY FRAMEWORK AND ENTITLEMENTS 6
A. Legal Framework 6
B. Reconciliation of Government and ADB Policy on Resettlement 7
VII. PROJECT OBJECTIVES AND ENTITLEMENTS 9
A. Objectives 9
B. Project Entitlements 10
VIII. RESETTLEMENT BUDGET AND FINANCING PLAN 12
A. Source of Resettlement Funds 12
B. Replacement Cost Survey 12
C. Resettlement Costs 13
IX. INSTITUTIONAL ARRANGEMENTS 14
A. Cao Bang Provincial People’s Committee 14
B. Provincial Project Management Unit (PPMU) of PDOT 14
C. District Compensation and Resettlement Board 14
D. Commune Peoples Committee 15
X. IMPLEMENTATION SCHEDULE 15
XI. MONITORING AND REPORTING 16
APPENDIX 1: IOL FORM 17
APPENDIX 2: MINUTES OF COMMUNITY CONSULTATION MEETING 22
APPENDIX 3: LIST OF APS AND AFFECTED ASSETS 23
APPENDIX 4: ADB ACCOUNTABILITY MECHANISM 24
LIST OF FIGURES
Figure 1:Class V Road Cross Section ............................................................................................. 1
PPTA 7245-VIE: Transport Connection in Northern Mountainous Provinces Project
Resettlement Plan
Cao Bang Province Page vi
LIST OF TABLES
Table 1: Detailed Road Descriptions 1
Table 2. Number of Affected Households 2
Table 3. Scope of Land Acquisition 2
Table 5 : Public Consultation Conducted Error! Bookmark not defined.
Table 6 : Summary of Perceived Benefits and Adverse Effects of Road Project 4
Table 7: Gaps Between National Laws and ADB Policy 7
Table 8: Entitlement Matrix of the Project 10
Table 9: Summary of Replacement Cost Survey (VND/m2) 13
Table 10: Summary of Compensation and Allowance 13
Table 11: Resettlement Implementation Schedule 15
PPTA 7245-VIE: Transport Connection in Northern Mountainous Provinces Project
Resettlement Plan
Cao Bang Province Page i
EXECUTIVE SUMMARY
1. Project. This Resettlement Plan (RP) is developed for the Transport Connection in Northern Mountainous Provinces Project. For Cao Bang Province, the Project will improve Road 202 with a total length of 30.2 km. The road will be upgraded to Class V with a carriageway of 3.5 meters (m) width and an embankment width of 6.5 m.
2. The RP was prepared based on available design during the Project Preparation Technical Assistance (PPTA) During loan implementation, following the completion of detailed design, detailed measurement survey (DMS) will be undertaken to determine the households and organizations who will be affected, actual impacts on their land and assets. Consultation meetings will be undertaken with the affected people. The Updated RP will be disclosed to the affected people, submitted to ADB for review and concurrence. Once the Updated RP has been agreed between ADB and PPC, PPC can commence implementation of the Updated RP.
3. Scope of Resettlement Impacts. The impacts are not significant. Per results of the IOL carried out in August 2010, a total of 77households (HHs) will be affected by the project in which (i) 27 HHs affected with agricultural land; (iii) 33 HHs affected with garden land and, 18 HHs affected with forest land. All households are marginally affected as loss of land is between (1 to 9 %) of their total landholdings. There is no case of relocation.
4. Socio-Economic Conditions. Affected households are mostly Dao, followed by Nung and Tay ethnic minority groups. Based on the socio-economic survey, there are 15 households who are classified as poor households while another three households are headed by women.
5. Consultation, Information Disclosure and Grievance Redress. In the preparation of this Resettlement Plan, consultation meetings were held, for each of the subproject roads. Representatives of communal leader, village leader, local NGOs and DPs, with 15 participants attended the meeting. A grievance redress mechanism has also been established. The RPs will also be disclosed in all affected communes and a PIB will be distributed to all APs.
6. Government’s Legal Framework, ADB Safeguard Policy Statement, and Project Objectives. The Project’s objectives and principles are based on the laws and regulations of the Government of Viet Nam (GOV) and the ADB’s Safeguard Policy Statement (2009). The overall objective of the policy is to ensure that all people affected by the subproject are able to maintain and, preferably, improve their pre-subproject living standards and income-earning capacity from compensation and life rehabilitation assistance for the loss of movable and immovable assets.
7. Cut-off date. The subproject cut off date was the date of completing inventory of losses, which was August 25th 2010. Hence, all cases arising after this date will not be identified as the project’s DPs.
8. Project Entitlements. The project entitlements developed and presented in the entitlement matrix correspond to the impacts identified during the IOL. Compensation will be based on the principle of replacement cost. Types of assistance will be provided to households based on the severity of impacts and their vulnerability to hardship. It should be noted that the entitlements in the RP can not be downgraded but can be enhanced, as necessary
9. Resettlement Budget. The RP Cost Estimates is VND 3,725,0000 (178,200 USD). Cost of land acquisition, payment for non-land assets, assistance, administration and contingency costs will be funded by the provincial government.
10. Institutional Arrangement. The PPC and District Compensation and Resettlement Board will be responsible in the updating, implementation and monitoring of the resettlement plan. A team of international and national consultants from the Project Coordination Consultant will provide support and guidance on all resettlement-related activities.
11. Implementation Schedule. PPC will submit the Updated RP based on detailed design to ADB for ADB review and concurrence prior to resettlement implementation. Compensation and clearance of land will not commence until the Updated RP has been agreed between the PPCs and ADB and that provisions in the agreed Updated RP has been satisfactorily implemented.
PPTA 7245-VIE: Transport Connection in Northern Mountainous Provinces Project
Resettlement Plan
Cao Bang Province Page ii
12. PPC, through PPMU, will not issue a site possession notice to the Works contract to commence construction activities for a specific section, until the head of the district resettlement committee (or board) has officially confirmed in writing that (i) payment and assistance has been fully provided to the affected persons and rehabilitation measures are in place for that specific section as per the respective RP; (ii) already compensated displaced persons for that specific section have been cleared from the area in a timely manner; and (iii) that the specific section of the project is free from any encumbrances.
Table ES-1: Indicative Implementation Schedule
Main Resettlement Plan Activities Implementation Schedule
Preparation of Resettlement Plan (PPTA)
RP Preparation (IOL, consultation, RCS) Sep, 2009, Jul-Aug 2010
Disclosure of Draft RP to Affected People April 11
PPC submission to ADB for review and concurrence April 2011
Uploading of RP on ADB website May 2011
Updating of Resettlement Plan (Loan Implementation)
Establishment of the District Compensation Board July,2012
Land clearance/boundary setting for the Project July,2012
Training for resettlement staff. July,2012
Consultation with the Affected Households July-Aug ,2012
Conduct of Replacement Cost Survey by a Qualified Appraiser July-Aug ,2012
Detailed Measurement Survey. Jul-Aug,2012
Disclosure of Updated RP to the Affected People Aug 2012
Submission of Updated RP to ADB for review and concurrence Sep, 2012
ADB issues concurrence of Updated RP Sep 2012
Award of Civil Works Contract Sep 2012
Implement Updated Resettlement Plan
Compensation payments Oct-Nov 2012
Implement rehabilitation measures Oct-Nov 2012
Clearance of acquired land Dec 2012
DCARB to issue letter of confirmation that RP has been satisfactorily implemented
Dec 2012
PPC, through PPMU, to issue Notice of Site Possession to civil works contractor
Dec 2012
Start of Civil Works Construction Dec 2012- Onwards
Monitoring (from RP updating to civl works construction) July 2011 -onwards
13. Monitoring. Resettlement activities will be monitored by PPC and CARB. The PPMU will provide guidance and advise as required. No external monitoring organization (EMO) wil be hired as the impacts are not significant.
PPTA 7245-VIE: Transport Connection in Northern Mountainous Provinces Project
Resettlement Plan
Cao Bang Province Page 1
I. PROJECT DESCRIPTION
A. Background
1. The Asian Development Bank (ADB) is funding the Technical Assistance (TA) of the Transport Connection in Northern Mountainous Provinces Project to help Viet Nam Government implement its poverty reduction and road improvement programs. The project zone includes 06 provinces in the North of Viet Nam, namely: Bac Kan, Cao Bang, Ha Giang, Tuyen Quang, Lao Cai and Yen Bai.
2. These provinces have high rate of poverty and ethnic minority population. The road network consists predominantly of unpaved, narrow roads. Many sections are impassable during the rainy season. Travel time and cost from mountainous remote areas to social infrastructure will be reduced, and the economic activities along the roads will be enhanced.
B. The Cao Bang Subproject Description
3. For Cao Bang Province, the Project will improve Road 202 (Subproject 0201) with a length of 30.2 km: located in Ca Thanh, Yen Lac and Vu Nong communes of Nguyen Binh District; and Hung
Dao, Huy Giap and Dinh Phung communes of Bao Lac District. The road will be upgraded to Class V with a carriageway of 3.5 meters (m) width and an embankment width of 6.5 m (see Figure 1).
Figure 1:Class V Road Cross Section
Table 1: Detailed Road Descriptions
1
1 The initial project scope included 2 roads; however, the project scope was reduced in March 2011 to 1 road (Road 202). Road 209 has been removed.
PPTA 7245-VIE: Transport Connection in Northern Mountainous Provinces Project
Resettlement Plan
Cao Bang Province Page 2
II. SCOPE OF LAND ACQUISITION AND RESETTLEMENT
A. Inventory of Losses (IOL)
4. During design implementation, PPTA Consultants in cooperation with Cao Bang PPMU, local commune authorities carried out Inventory of Losses (IOL) for all affected land, assets, trees in the project area. The following summarizes the IOL process and related procedures:
(i) Preparation of the IOL for affected assets in the project area in Sep 2009 and updated in August, 2010.
(ii) Conducted community meetings with various stakeholders (medical station, local NGOs and households whose houses are located along the road sides) in order to notify them about the dates and procedures of the IOL.
5. The survey form used for the IOL is presented in Appendix 1. The Minutes of Community Consultation Meetings in Appendix 2 and the list of HHs with their affected land/assets in Appendix 3.
B. Affected Households
6. Per results of the IOL, carried out in August 2010, a total of 77 households (HHs) stand to lose part ot their residential, agricultural, garden and forest land and various fixed assets with the construction of the project roads. Among the 77 affected households (AHs): (i) 72 HHs will be affected through loss of residential land; (ii) 27 HHs affected with agricultural land; (iii) 33 HHs affected with garden land and, 18 HHs affected with forest land, (See Table 2 )
7. All AHs are partially and marginally affected and there is no case of relocation nor loss of shop or business.
Table 2. Number of Affected Households
Routes Number of Households
2
Res. Agri. Garden Forest. Total
Road 202 48 27 33 18 77
8. The IOL data on land acquisition are preliminary. A more reliable determination of impacts will be carried out during the DMS. Detailed provision of land/asset impacts are shown below.
C. Affected Land and Non-Land Assets
9. Land. Total land to be acquired is 209,122 m2. Total affected forest land is 201,272 m
2,
accounting for 96,2% of the total land acquisition. The proposed roads are located mainly in mountainous area dominated by forestry land. All DPs are legal land users. Forestry land belongs to both private and public owners. Private HHs are losing an average of 232 m
2 of forestry land. Private
HH usually own several hectares (between 3.0 to 5.0 has) of forestry land in the project area. Average agricultural landholding in the area is 500 to 600 m
2 in several plots
.
Table 3. Scope of Land Acquisition
Routes Land Area for Acquisition (m
2)
Res. Agri. Garden Forest. Total
Road 202 1,971 2,940 2,939 201,272 209,122
10. Secondary Structures. There are no houses affected by the road improvement. A few secondary structure such as breeding structures (14 m
2) will be affected. For households losing
residential land, a part of their concrete yard (2,998 m2) will be affected.
2 An AP might be affected various kinds of land including residential land, agricultural land and forest land, so sum up numbers of the affected household could not equal to actual APs numbers mentioned in Column Total.
PPTA 7245-VIE: Transport Connection in Northern Mountainous Provinces Project
Resettlement Plan
Cao Bang Province Page 3
11. Crops and Trees. Almost all 77 DPs affected through loss of land, will also lose trees/crops: 19,542 timbers, 155 fruit-trees and 2,940 m
2 of paddy rice and maize field.
III. SOCIO-ECONOMIC INFORMATION
A. Socio-Economic Profile of Subproject Area
12. Cao Bang is a mountainous province in the northeast of Vietnam. The national poverty line is established by Ministry of Labour, Invalids and Social Assistance (MOLISA). For the period from 2006 to 2010; the rural poverty line is VND 200,000/person/month while the urban poverty line is VND 260,000/person/month. The incidence of poverty in Cao Bang province in 2008 was 39.2% (new standard).
13. Ethnic groups in the province accounts for 95% of the total population. Ethnic composition includes Tay (41.9%), Nung (32.9%), H’mong (8.3%) and Dao (4.5%). Kinh accounts for 4.6% of the total population.
B. Socio-Economic Profile of Affected Households
14. The socio-economic survey (SES) was conducted among 51%3 of the total number of DPs
which corresponds to 59 households (270 persons). The respondents, heads of households, stated that they all went to school and reached high school level.
15. Population and Household Size. Among the 59 surveyed HH, there are 133 are males And 137 females. The average HH size is 4.6 persons/HH.
16. Age Distribution. Regarding the age distribution of the surveyed population, there are about
36.5% (74 persons) between 21 and 60 years old; 50.8% (103) above 20 years old and 12.8% (26) are those who are 60 years old and above.
17. Ethnic Groups. Among the 59 surveyed HH, all belongs to an ethnic group, mainly Dao (48 HHs), followed by Nung (10 HHs) and Tay (1 HH).
18. Poor and Vulnerable Households. There are 10 households classified as poor households by the commune following MOLISA poverty criteria. There are no household with disabled persons, invalids, elderly people without support or war heroes (“policy” households).
19. Households headed by women. The SES found three households headed by women.
20. Income Sources. The main primary source of income of most households is agriculture with nearly 85.1%. The main crops planted are rice, maize and peanuts. Additional sources of income are livestock (cows, buffalos), poultry (chicken and ducks) and pig rearing. Business activities accounts for 13.4% of the main source of income of DPs. It is worth noting that income from women represents 47% of the total income of household. Average income of households is about 1,400,000 VND per month.
21. Houses and Basic Facilities. Most of the houses are built with permanent materials. All HHs are connected to the state power network; electricity is used mainly for lightning. Wood or gas are generally used for cooking.
22. Water and Sanitation. Piped water is not available in the Project area. All HH still use water from stream and pond. Most of the households surveyed (97%) do not have toilet. Only 2% have in-house toilet.
3 Rehabilitation of Road 202 has been reduced from 46 km to 30.2 km in March 2011. The total number of affected HH was first 116.; It has been reduced to 77. The SES was conducted among the 116 affected HH at tte time of the survey.
PPTA 7245-VIE: Transport Connection in Northern Mountainous Provinces Project
Resettlement Plan
Cao Bang Province Page 4
IV. INFORMATION DISCLOSURE, CONSULTATION AND PARTICIPATION
23. Disclosure of information and consultations are conducted during preparation and implementation of subprojects to ensure that DPs and other stakeholders have timely information about land acquisition, compensation and resettlement, as well as opportunities to participate in and express their preferences and concerns regarding the resettlement program. from the commune, ward and/or village authorities organized meetings and consultation and disseminated information to ensure that the DPs are well informed and consulted as early as project preparation.
A. Consultations
24. Consultation and information dissemination has been an integral component of the RP preparation. During the preparation of this RP, significant information dissemination and consultation with primary stakeholders has been undertaken, through IOL, village level meetings, sample household surveys, and meetings with other key stakeholders.
25. Two Resettlement Workshops, attended by representatives from the 6 PDOTs, were held in Lao Cai on October 27th 2009 and in Hanoi on December 7th 2009. The workshops consisted of the following presentation: Project’s components; ADB Requirements prior to Appraisal and Loan Negotiation; GOV’s laws and procedures on land acquisition; ADB’s Safeguard Policy Statement; Project’s Policy Framework and Entitlements; Project Impacts and Entitlements for each type of impact; Proposed Resettlement Strategies; Preparation of Resettlement Plan; Budget Costs and Tentative Implementation Schedule. The workshop also allowed the participants to share their opinion and suggestions in order to improve the preparation and implementation of the Resettlement Plan.
26. In the preparation of Resettlement Plan, the PPTA Social Safeguard Consultants, Cao Bang PPMU coordinated with the commune local authorities in subproject areas to hold consultation meetings for each of the project roads. In Road 202, a meeting at the commune level was held on 28 August 2010 and 15 representatives from the households attended the meeting. During the IOL survey, all HHs were also informed about the proposed project by the survey team. A project map has also been posted at the commune People's committee billboard, by PPMU and social consultant
27. The purpose of the meeting was to provide information to and consult with DPs and other stakeholders regarding: (i) project information; (ii) the scope and objectives of the subproject based on preliminary design; (iii) the policies, principles, entitlement and procedures for land acquisition, compensation and resettlement; (iv) implementation schedule and, (iii) preliminary estimates of land acquisition requirements and grievance redress.
28. All participants agreed with the project implementation and the proposed policy for the project. They expect that the project will be implemented soon so that local people have better opportunity in economic and social development for communes in the area. Other discussion on the subproject’s Perceived Benefits and Adverse Effects are provided in Table 6.
Table 4 : Summary of Perceived Benefits and Adverse Effects of Road Project
Benefits Adverse Effects
1. Improved roads will provide safer traffic condition for local people.
2. People will have better access to schools by making roads easier to navigate specially during rainy season. Easier and safer for children to go to school.
3. Better transportation contributes in promoting product exchanges and trading activities and facilitates the movement of products from source to markets.
4. Improved roads and transportation will help improve the standard of living of local people.
5. The people within the project area can earn additional income from jobs in construction work
1. Number of traffic accidents may increase.
2. Number of social evils may increase. Improved roads will provide easier access for outsiders who may bring with them vices such as drug addiction and prostitution, trafficking of women and children and spread of communicable diseases.
3. Disruption in daily living of people during construction period like their mobility in going to school and market.
4. Households who will be directly affected in terms of their houses and livelihood are concerned that they will not be paid on time nor given assistance for repairing their houses or relocating.
PPTA 7245-VIE: Transport Connection in Northern Mountainous Provinces Project
Resettlement Plan
Cao Bang Province Page 5
Benefits Adverse Effects
and for providing lodging and food to Contractors and construction workers coming from outside.
6. The people can benefit from livelihood and crop production training, awareness rising which are proposed to be conducted during the project implementation.
29. In addition, the participants also suggested that they should participate in the project implementation: (i) during the resettlement implementation, the DPs should be informed, consulted prior to compensation implementation, and they should be represented as a member in the CARB, which will participate in implementation of DMS, pricing, and payment process; (ii) during the road construction, the Contractor should mobilize local people to work as laborers in construction work, and (iii) they are willing to work in Operation and Maintenance (O&M).
30. During loan implementation, households will continuously be informed and consulted specifically on the project schedule and activities. Results of the DMS, entitlements and value of assets will also be disclosed to the DPs. Suggestions from women and other vulnerable households specific to mitigating impacts or addressing impacts will be carefully taken into account. During RP updating, separate meetings will be held with women. There will be also announcements during market days.
31. The updated Resettlement Plan (Draft and approved) will be prepared following the Detailed Design and disseminated to the affected communities and uploaded on the ADB’s website.
B. Information Disclosure
32. Key information in the draft RP will be disclosed to the DPs through the distribution of public information booklets in Vietnamese language during market days prior to ADB Management Review Meeting or before ADB follow-up mission. Disclosure to the DPs will be done prior to submission of draft RP to ADB. The draft RP and the RP agreed between ADB and Government will be uploaded on the ADB website.
33. Public Information Booklet. A public information booklet has been prepared (see Annex 5).
V. GRIEVANCE REDRESS MECHANISM
34. Grievances related to any aspect of the Project will be handled through negotiation aimed at achieving consensus. Complaints will pass through 3 stages before they could be elevated to a court of law as a last resort.
35. First Stage, Commune People’s Committee. An aggrieved affected household may bring his/her complaint before any member of the Commune People’s Committee, either through the Village Chief or directly to the CPC, in writing or verbally. It is incumbent upon said member of CPC or the village chief to notify the CPC about the complaint. The CPC will meet personally with the aggrieved affected household and will have 30-45 days following the lodging of the complaint to resolve it (Note: in remote and mountainous areas, the complaint should be resolved within 45-60 days. The CPC secretariat is responsible for documenting and keeping file of all complaints that it handles.
36. Upon issuance of decision of CPC, the household can make an appeal within 30 days. If the second decision has been issued and the household is still not satisfied with the decision, the household can elevate his/her complaint to the DPC.
37. Second Stage, District People’s Committee. Upon receipt of complaint from the household, the DPC will have 30-45 days (or 45-60 days if it is in remote or mountainous areas) following the lodging of the complaint to resolve the case. The DPC is responsible for documenting and keeping file of all complaints that it handles.
38. Upon issuance of decision of DPC, the household can make an appeal within 30 days. If the second decision has been issued and the household is still not satisfied with the decision, the household can elevate his/her complaint to the PPC.
PPTA 7245-VIE: Transport Connection in Northern Mountainous Provinces Project
Resettlement Plan
Cao Bang Province Page 6
39. Third Stage, Provincial People’s Committee. Upon receipt of complaint from the household, the PPC will have 30-45 days (or 45-60 days if it is in remote or mountainous areas) following the lodging of the complaint to resolve the case. The PPC is responsible for documenting and keeping file of all complaints that reaches the same.
40. Upon issuance of decision of PPC, the household can make an appeal within 30 days. If the second decision has been issued and the household is still not satisfied with the decision, the household can elevate his/her complaint to the court within 45 days. PPC will then deposit the compensation payment in an escrow account.
41. Final Stage, the Court of Law Arbitrates. Should the complainant file his/her case to the court and the court rule in favor of the complainant, then PMU-MT will have to increase the compensation at a level to be decided by the court. In case the court will rule in favor of PPC, then the amount deposited with the court is what the complainant will receive.
42. The DPs will be provided with support and assistance by local based organizations, in case they have limited capacity in case they have questions or complaints.
43. If efforts to resolve complaints or disputes are still unresolved and unsatisfactory following the project’s grievance redress mechanism, the households have the right to send their concerns or problems directly to ADB’s Operations Department, i.e., Transport and Communications Division, Southeast Asia Department (SERD) or through ADB Viet Nam Resident Mission. If the households are still not satisfied with the responses of SERD, they can directly contact the ADB's Office of the Special Project Facilitator (OSPF) as outlined in the "Information Guide to the Consultation Phase of the ADB Accountability Mechanism" (Appendix 4).
4
VI. POLICY FRAMEWORK AND ENTITLEMENTS
A. Legal Framework
44. The Resettlement Legal Framework and Entitlements for the Project have been built upon the laws of the Government of Viet Nam and the ADB Safeguard Policy Statement (2009). However, provisions and principles adopted in the Resettlement Legal Framework for the project supersede the provisions of relevant decrees currently in force in Viet Nam wherever a gap exists. The overall objective of the policy is to ensure that all people affected by the subproject are able to maintain and, preferably, improve their pre-subproject living standards and income-earning capacity from compensation and life rehabilitation assistance for the loss of movable and immovable assets.
45. The policy is based on the laws and regulations of the Government of Viet Nam (GOV) of Cao Bang Province and the ADB. The principal Vietnamese laws and regulations include:
The 2003 Land Law dated 26 November 2003;
Decree 181/2004/ND-CP dated 29/10/2004of the Government guiding the execution of amended land law 2003;
Decree 197/2004/ND-CP date 03/12/2004 of the Government on compensation, assistance and resettlement in the event of land recovery by the State;
Decree No. 188/2004/ND-CP dated November 16, 2004 of the Government on methods of determining land prices and land prices framework;
Circular No. 114/2004/TT-BTC dated November 16, 2004 of Ministry of Finance guiding the implementation of Decree No. 188/2004/ND-CP of the Government;
Decree No. 17/2006/ND-CP dated January 27, 2006 of the Government amending and supplementing some articles of the Decree guiding the implementation of the Land Law and Decree No. 187/2004/ND-CP on the transfer state-owned companies into joint stock companies.
Decree No. 84/2007/ND-CP dated May 25, 2007 of the Government on additional regulations on the granting of land use right certificates, land acquisition, implementation
4 The information guide is also available on the ADB’s website: http://adb.org/SPF/default.asp .
PPTA 7245-VIE: Transport Connection in Northern Mountainous Provinces Project
Resettlement Plan
Cao Bang Province Page 7
of land use rights, compensation order and procedure, resettlement when the State recovers land and settle claims about land;
Decree No. 123/2007/ND-CP dated 27 July 2007 amending and supplementing some articles of Decree No. 188/2004/ND-CP dated 16 November 2004 on methods of determining land prices and frame land prices;
Decree 69/2009/ND-CP dated August 13, 2009 of the Government of Vietnam regulating additional planning of land use plan, land prices, land acquisition, compensation, assistance and resettlement;
Circular 14/2009/TT - BTNMT dated January 10, 2009 by MONRE regulating compensation, assistance and resettlement procedures and land acquisition, land allocation, land lease in details;
Decision No. 3336/2009/QD-UBND dated December 31th, 2010 of Cao Bang Province People's Committee promulgating the compensation policy, assistance and resettlement when the State recovers land in the province of Cao Bang;
Decision No. 3165/2009/QD-UBND dated 22/12/2009 of the Cao Bang PPC promulgating the table of land prices in the Cao Bang province in year 2010.
Decision 776/2009/QD-UBND dated April 28, 2009 of Cao Bang PPC regulating the unit price for housing and other architectural objects when acquired in the Cao Bang province;
Decision No.52/2008/QD-UBND dated January 11, 2008 by Cao Bang PPC promulgating the unit prices for crop and tree when acquired in the Cao Bang province;
B. Reconciliation of Government and ADB Policy on Resettlement
46. With the promulgation of Decree 197/2004/ND/CP (3/12/2004) and Decree 69/2009/ND-CP and relevant decrees stated above, the policies and practices of the Government have become more consistent with ADB’s social safeguards policies. Nonetheless, provisions and principles adopted in this Resettlement Plan will supersede the provisions of the relevant decrees currently in force in Viet Nam wherever a gap exists, as provided for under Decree 131/2006/ND-CP (November 2006), which regulates the management and use of official development assistance.
47. It should also be noted that as per Decree 69/2009, Article 23, it states "Apart from the support prescribed in Articles 18, 19, 20, 21 and 22 of this Decree, basing themselves on the local realities, the provincial-level People’s Committee shall decide on other supporting measures to stabilize life and production of persons who have land recovered; special cases shall be submitted to the Prime Minister for decision”, therefore, if additional gaps not mentioned below are found during RP updating, the required assistance or support will be included in the Updated RP.
48. The differences between the Government’s Laws and Decrees and ADB Policy with regard to resettlement and compensation, and how to address these gaps for this Project are shown in the table below.
Table 5: Gaps Between National Laws and ADB Policy
Key Issues National Laws ADB Policy Project Policy
Definition of Vulnerable groups
Vulnerable households are those households living below the poverty line as set by MOLISA and social policy households who receive special cash allowances from the Government. These households have household members who are invalids, who have heroic mothers, martyrs, and those who made contribution to the revolution.
Vulnerable groups those below the poverty line, the landless, the elderly, women and children, and Indigenous Peoples.
(i) female headed households with dependents (ii) households with disabled persons, (iii) households falling under the current MOLISA benchmark poverty line, (iv) children and elderly households who are with no other means of support, (v) landless households, and (vi) non-integrated and vulnerable ethnic
PPTA 7245-VIE: Transport Connection in Northern Mountainous Provinces Project
Resettlement Plan
Cao Bang Province Page 8
Key Issues National Laws ADB Policy Project Policy
minorities; and (vii) social policy households as defined by the Government
Provision of Assistance to Economically Displaced Households.
Decree 197/2004 (as amended by Decree 69/2009) states that affected households losing 30% or more of their productive land will be provided assistance.
However, Article 23 of Decree 69/2009 also states that based on actual conditions at the local area, PPC shall determine other assistance methods to ensure accommodation and life stabilization.
It also states that households who are directly involved in agricultural production and derive their major income from the land that are to be acquired by the Government, PPC shall consider the assistance level on a case by case basis based on actual conditions.
Decree 17, 2006 also states that In any case where any household or individual from whom land is recovered has a living standard which is classifies either as a poor household according to criteria set for poor households by MOLISA, they must be assisted to overcome the poverty. The actual amount and time of assistance will be decided by the People’s Committee of a province or city under Central control but it must not be less than 3 years and must not exceed 10 years counting from the day of completion of land recovery.
Provide economically displaced persons with needed assistance.
Improve the standards of living of the displaced poor and other vulnerable groups, including women, to at least national minimum standards.
Focus on strategies to avoid further impoverishment and create new opportunities to improve status of the poor and vulnerable people.
Households who lose less than 30% of their agricultural land who are determined to depend heavily in agriculture for their livelihood will be provided with additional assistance similar to those losing 30% or more of their land.
Specific measures will be provided to ensure that all vulnerable groups are assisted to improve or at least restore living standards to pre-project levels and in a manner that is culturally sensitive and appropriate.
Non-titled users
Clause 2 of Article 23, Decree 69/2009, the Peoples’ Committees of the provinces or centrally-run
Non-titled housheolds, including displaced tenants, sharecroppers and squatters, are not entitled
Poor and vulnerable non-titled users will be provided appropriate assistance to help them improve their
PPTA 7245-VIE: Transport Connection in Northern Mountainous Provinces Project
Resettlement Plan
Cao Bang Province Page 9
Key Issues National Laws ADB Policy Project Policy
cities shall consider providing such support on case-by-case basis.
to compensation for land but are entitled to payment for non-land assets and assistance to restore their pre-project living standards. If they are poor and vulnerable, appropriate assistance must be provided to help them improve their socio-economic status.
socio-economic status. The type of assistance will be identified during RP updating as per consultation with households.
Unregistered
businesses
Compensate and support
only registered
manufacturing and business
enterprise or households
Promptly compensate all
economically displaced
persons for the loss of
income or livelihood
sources at full replacement
cost, and assist through
credit facilities, training and
employment opportunities.
Assist displaced
persons/households who
do not fall under registered
business by providing
assistance in cash or in-
kind during transition
period.
Houses and structures
Decree 197/2004, Articles 18-20: Houses and structures constructed prior to land use plans or the right of way announcements will be assisted at 80% of replacement cost.
Structure to be compensated 100% of replacement cost, without depreciation and regardless of status of the DP on the land as long as structure was put prior to the cut-off date
Houses and other structures on land without sufficient conditions for compensation that were constructed prior to the decision on land recovery (cut-off date) will be compensated 80% of new construction price.
Plus: cash assistance amounting to 20% of new construction price if at the time of construction there is no clear or proper announcement of land use plan or ROW.
Entity that
conducts the
valuation of
acquired
assets
Provincial and cities people’s
committee under central
authority will establish
specific land prices based on
the principles stated in
clause 1, Article 56, Land
Law.
Qualified organizations may
provide consultancy on land
prices (Article 57, Land Law)
Qualified and experienced
experts will undertake the
valuation of acquired
assets
Qualified and experienced
experts will be engaged to
conduct replacement cost
surveys for the project
which will be used as input
by the District
Compensation Boards
under the District People’s
Committee for determining
compensation amounts.
VII. PROJECT OBJECTIVES AND ENTITLEMENTS
A. Objectives
49. The overall objectives of the resettlement policy for this RP are (i) to minimize, if not avoidable, resettlement impacts; (ii) if impacts are unavoidable, RP is prepared in a way to ensure that DPs are not worse off; rather, they should be able to at least maintain or otherwise improve their pre-project living standards and income-earning capacity. Principles adopted for this Project, irrelevant to current
PPTA 7245-VIE: Transport Connection in Northern Mountainous Provinces Project
Resettlement Plan
Cao Bang Province Page 10
situation but might be relevant in the future in case there will be major changes in alignment designs, are presented below:
a. Involuntary resettlement and impacts on land, structures and other fixed assets will be minimized where possible by exploring all alternative options.
b. Compensation will be based on the principle of replacement cost at the time of compensation.
c. Displaced persons without title or any recognizable legal rights to land are eligible for resettlement assistance and compensation for non-land assets at replacement cost.
d. Residential land, residential house and agricultural land for replacement should be close to the previous places as much as possible and be suitable to displaced persons.
e. Meaningful consultation will be carried out with the affected households and concerned groups and ensure participation from planning up to implementation. The comments and suggestions of the DPs and communities will be taken into account.
f. The RP will be disclosed to DPs in a form and language(s) understandable to them prior to submission to ADB.
g. Resettlement identification, planning and management will ensure that gender concerns are incorporated.
h. Special measures will be incorporated in the resettlement plan to protect socially and economically vulnerable groups such as households headed by women, children, disabled, the elderly, landless and people living below the generally accepted poverty line.
i. Existing cultural and religious practices will be respected and, to the maximum extent practical, preserved.
j. Culturally appropriate and gender-sensitive social impact assessment and monitoring will be carried out in various stages of the project.
k. Resettlement transition stage should be minimized. Restoration measures will be provided to displaced persons before the expected starting date of construction in the specific location.
l. Budget for payment of compensation, resettlement and support will be prepared sufficiently and made available during project implementation. Sites for resettlement and restoration will be available as required.
m. Reporting and monitoring will be defined clearly as part of the management system of resettlement. Independent assessment of the duration and results of the land recovery should be carried out.
n. PPC, through PPMU, will not issue notice of possession to contractors until CARB has officially confirmed in writing that (i) payment has been fully disbursed to the displaced persons and rehabilitation measures are in place as per Updated RP agreed between PPC and ADB; (ii) already-compensated displaced persons have cleared the area in a timely manner; and (iii) the area is free from any encumbrances. No land recovery or site clearing will be done until and after the Updated RP has been agreed between PPC and ADB and the provisions in the Updated RP have been implemented satisfactorily.
B. Project Entitlements
50. The project entitlements (i.e. compensation and support) developed and presented in the entitlement matrix below correspond to the impacts identified during the IOL. It should be noted that these entitlements can not be downgraded. Entitlements may be enhanced, as necessary, following the conduct of DMS and consultation with DPs. Entitlements adopted are based on government policies and decisions and ADB policies. Entitled persons are those who satisfy the cut-off-date.
Table 6: Entitlement Matrix of the Project
Impact/ Loss
and Application(*)
Eligible Persons Entitlements Implementation Issues
Loss of
Productive Land
(paddy, garden,
forest land)
Households or
persons with
(i) LURC; or (ii) in the
process of acquiring
Cash compensation at
replacement cost which is
equivalent to current market
price and free from
DPs who lose 30% or more
of their agricultural land will
be provided with additional
assistance such as
PPTA 7245-VIE: Transport Connection in Northern Mountainous Provinces Project
Resettlement Plan
Cao Bang Province Page 11
Impact/ Loss
and Application(*)
Eligible Persons Entitlements Implementation Issues
LURC (iii) are eligible
to acquire LURC
according to the
regulations of GoV;
and (iv) covered by
customary rights,
such as members of
ethnic minority
groups.
transaction costs (e.g.,
taxes, certification,
administration costs).
Cash assistance equivalent
to 5 times of the current
market price of agricultural
land.
If agricultural land is within
the residential area, cash
assistance amounting to
20% to 50% of current
market price of adjacent
residential land.
transitional allowance (e.g.
rice allowance).
DPs who lose less than 30%
of their agricultural land who
are determined to depend
heavily in agriculture for their
livelihood and whose land is
below the minimum land
quota in the commune will
also be provided with
additional assistance similar
to those losing 30% or more
of their agricultural land.
Land Users who have
no formal legal rights
nor recognized or
recognizable claims
to such land.
No compensation for public
land and land allocated by
GoV/ local authorities to
institutions or individual DP,
but full replacement cost for
non-land assets and
investment on land to land
user.
Loss of
Residential Land
Households or
persons with (i)
LURC; or (ii) in the
process of acquiring
LURC (iii) are eligible
to acquire LURC
according to the
regulations of GoV;
and (iv) covered by
customary rights,
such as members of
ethnic minority
groups.
Cash compensation at
replacement cost which is
equivalent to current market
price and free from
transaction costs (e.g.,
taxes, certification,
administration costs).
Land Users who have
no formal legal rights
nor recognized or
recognizable claims
to such land.
No compensation for public
land and land allocated by
GoV/ local authorities to
institutions or individual DP,
but full replacement cost for
non-land assets and
investment on land to land
user.
Loss of Houses
and Secondary
Structures
Owners with or
without acceptable
proof of rights over
the land; with or
without building
permit.
Cash compensation at
replacement cost which is
equivalent to the current
market value of a newly built
structure and with no
depreciation or deduction for
salvageable materials.
Impacts on
Crops, Trees and
Aquaculture
Products
Owners regardless of
land tenure status
Annual crops and
aquaculture products
equivalent to current market
value of crops/aquaculture
PPTA 7245-VIE: Transport Connection in Northern Mountainous Provinces Project
Resettlement Plan
Cao Bang Province Page 12
Impact/ Loss
and Application(*)
Eligible Persons Entitlements Implementation Issues
products at the time of
compensation;
For perennial crops trees,
cash compensation at
replacement cost equivalent
to current market value
given the type, age and
productive value (future
production) at the time of
compensation.
Timber trees based on
diameter at breast height at
current market value.
Impacts on Public
Facilities,
Communal
Owned Assets
and Collective
Assets
Owners of assets Cash compensation to cover
the cost of restoring the
facilities or assets
OR
In-kind compensation (such
as PPMU to replace
materials and/or provide
labor).
To be agreed between
PPMU and owner during RP
updating
Temporary
Impacts During
Construction
Households or
persons with (i)
LURC; or (ii) in the
process of acquiring
LURC (iii) are eligible
to acquire LURC
according to the
regulations of GoV;
and (iv) covered by
customary rights,
such as members of
ethnic minority
groups.
For Non-Land Assets,
regardless of tenure
status.
Land. For the portion to be
used temporarily during
construction: (i) rental in
cash which will be no less
than the net income that
would have been derived
from the affected property
during disruption; (ii)
restoration of the land within
3 months after use.
For non land assets,
payment will be based on
replacement cost as
indicated above.
VIII. RESETTLEMENT BUDGET AND FINANCING PLAN
A. Source of Resettlement Funds
51. All land acquisition, compensation and resettlement costs of the subproject are taken from provincial counterpart funds of Cao Bang province.
B. Replacement Cost Survey
52. All compensation will be based on the principle of replacement cost. Replacement cost is the amount calculated before displacement which is needed to replace an affected asset without deduction for taxes and/or transaction costs.
53. A Replacement Cost Survey has been prepared to assess if the compensation rates issued by the Cao Bang People’s Committee corresponds to replacement costs. The survey took place in the middle of August 2010. The market rates have been determined through desk study and field survey. Information about price was mainly collected through direct interviewees with affected and non affected households, especially households Affected households were prioritized for the selection of
PPTA 7245-VIE: Transport Connection in Northern Mountainous Provinces Project
Resettlement Plan
Cao Bang Province Page 13
sample for the survey. However, to have objective results, non affected households who have similar characteristics (similar location and assets) were also selected for the survey.
54. Households who have recently bought land and built structure on this land were also interviewed. In addition, information was also collected from various provincial departments and commune, district and other stakeholders.
55. The results of this replacement cost survey are summarized in Table 9. The market prices identified through this survey will be used in the costs estimates.
Table 7: Summary of Replacement Cost Survey (VND/m2)
No Items PPC
Compensation rates (VND)
Market Rates (VND)
Rates Used for Cost Estimates
(VND)
A LAND
1 Residential Land (m2) 367,000 367,000-400,000 385,000
2 Agricultural Land (m2) 23,000 50,000 50,000
3 Forest Land (m2) 7,500 - 9,000
4 Garden Land (m2) 54,000 - 60,000
B STRUCTURE
1 House (m2) 1,050,000 1,050,000-1,500,000 1,250,000
2 Secondary structures (m2) 230,000 230,000-300,000 280,000
3 Yard (m2) 54,000 54,000-80,000 68,000
C TREE AND CROPS
1 Timber (each) 2,000 2,000-5,000 3,000
2 Fruit Tree (each) 250,000 - 250,000
3 Paddy (Rice) (m2) 2,000 2,000-5,000 3,000
C. Resettlement Costs
56. The RP budget is estimated at 3,725,0000 VND (178,200 USD). Table 10 summarizes the subproject resettlement costs including (i) compensation for land acquired permanently or temporarily; (ii) compensation for structures, crops and trees; (iii) allowances; and (iv) implementation and contingency costs. Budget for the RP will be financed by the Government as part of its counterpart fund.
Table 8: Summary of Compensation and Allowance
No Items
Road 202 Unit Price (VND)
Road 202 Total
Quantity Amount (VND)
I COMPENSATION & ASSISTANCES A LAND 2 893 483 946 2 893 483 946
1 Residential Land (m2) 1 971 385 000 758 720 193 758 720 193
2 Agricultural Land 4 287 2 940 50 000 146 979 795
3 Forest Land 201 272 9 000 1 811 449 346 1 811 449 346
4 Garden Land 2 939 60 000 176 334 612 176 334 612
B STRUCTURE - 143 821 461 143 821 461
1 House (m2) - - -
2 Secondary Structures (m2) 14 280 000 4 031 916 4 031 916
3 Yard (m2) 2 056 68 000 139 789 545 139 789 545
C TREE AND CROPS - 106 188 188 106 188 188
1 Timber (tree) 19 542 3 000 58 627 350 58 627 350
PPTA 7245-VIE: Transport Connection in Northern Mountainous Provinces Project
Resettlement Plan
Cao Bang Province Page 14
2 Fruit Tree (tree) 155 250 000 38 742 050 38 742 050
3 Crop/ paddy rice (m2) 2 940 3 000 8 818 788 8 818 788
4 Sub-total (I) - 3 064 124 506 3 064 124 506
II ALLOWANCES -
4 Allowance for career change (5 x comp. Rate for ag. Land) 2 940 115 000 338 100 000 338 100 000
Sub-total (II) 338 100 000 338 100 000
III MANAGEMENT COST -
1 Administration (2%) 69 631 872 69 631 872
2 Contingency (5%) 174 079 680 174 079 680
Sub-total (III) 243 711 552 243 711 552
TOTAL (I+II+III) 3 725 305 147 3 725 305 147
USD 178 244
57. Once the Updated RP is acceptable to ADB, compensation payment can commence. During payment, the PPMU and local authorities will require the presence of both husband and wife to receive payment and sign payment documents. Before handing over of payments to the DPs, breakdown of compensation will be explained in detail using local language.
IX. INSTITUTIONAL ARRANGEMENTS
A. Cao Bang Provincial People’s Committee
58. The Cao Bang Provincial People’s Committee, is responsible for the following:
a) Review and approve the RP (and its update) prepared for the Project
b) Direct its relevant departments such as Departments of finance, construction, agriculture and rural development, transport and environment to help in the preparation, updating, and implementation of the RP.
c) Approve the unit rates submitted by CARB to enable CARB in finalizing the compensation plans.
d) Approve the compensation plan and overall RP budget which will be reviewed and submitted by the DOF
e) Settle complaints and outstanding issues.
B. Provincial Project Management Unit (PPMU) of PDOT
59. The responsibilities of the PPMUs under PDOTs are to:
a) Participate as a member of district resettlement committee;
a) Integrate construction, land acquisition and resettlement, indigenous peoples development plan and gender mainstreaming activities;
b) Establish proper PDP databases for each road sections;
c) Participation in the compensation payment to affected households;
d) Regularly liaise with the concerned RDC and PRC regarding the list of PDPs, compensation payments and grievance resolution; and
e) Submit regular progress reports to PDOT and SC on civil works, construction and RP activities.
C. District Compensation and Resettlement Board
60. The responsibilities of the District Resettlement Committee are to:
a) Carry out consultation and dissemination of information on the RP;
b) Organize, plan and carry out land acquisition, compensation, assistance and other resettlement activities in the district as per agreed RP
PPTA 7245-VIE: Transport Connection in Northern Mountainous Provinces Project
Resettlement Plan
Cao Bang Province Page 15
c) Conduct the DMS and prepare compensation plans for DPs and submit them to PPC for review
d) Carry out replacement cost survey to ensure that payments to the DPs are at replacement cost. Update rates on a a regular basis.
e) Conduct consultation and participation activities, and coordination with various stakeholders in updating and implementing the RP.
f) Pay compensation and allowances, to DPs after Updated RP has been agreed between PPC and ADB. Ensure the timely delivery of payments of compensation, assistance and other entitlements to DPs; and
g) Assist in the resolution of grievances at the district level.
h) Report on a quarterly basis on the progress of RP updating and implementation.
i) Report on impacts caused during construction.
D. Commune Peoples Committee
61. The CPC will assist the CARB in their resettlement tasks. Specifically, the CPC will be responsible for the following: (i) participate in the updating and implementation of RP; identify potential replacement land for affected households; (iii) ensure that vulnerable and severely affected households are properly consulted and that the concerns and grievances of these households are heard, recorded and addressed in a timely manner; (iv) certify DMS and payments made to affected households; and (v) assist in the resolution of grievances.
X. IMPLEMENTATION SCHEDULE
62. The implementation schedule for resettlement activities for the subproject is presented in the following table including (i) activities that have been completed to prepare the RP; (ii) resettlement implementation activities; and, (iii) monitoring activities.
1. Table 9: Resettlement Implementation Schedule
Main Resettlement Plan Activities Implementation Schedule
Preparation of Resettlement Plan (PPTA)
RP Preparation (IOL, consultation, RCS) Sep, 2009, Jul-Aug 2010
Disclosure of Draft RP to Affected People April 11
PPC submission to ADB for review and concurrence April 2011
Uploading of RP on ADB website May 2011
Updating of Resettlement Plan (Loan Implementation)
Establishment of the District Compensation Board July,2012
Land clearance/boundary setting for the Project July,2012
Training for resettlement staff. July,2012
Consultation with the Affected Households July-Aug ,2012
Conduct of Replacement Cost Survey by a Qualified Appraiser July-Aug ,2012
Detailed Measurement Survey. Jul-Aug,2012
Disclosure of Updated RP to the Affected People Aug 2012
Submission of Updated RP to ADB for review and concurrence Sep, 2012
ADB issues concurrence of Updated RP Sep 2012
Award of Civil Works Contract Sep 2012
Implement Updated Resettlement Plan
PPTA 7245-VIE: Transport Connection in Northern Mountainous Provinces Project
Resettlement Plan
Cao Bang Province Page 16
Main Resettlement Plan Activities Implementation Schedule
Compensation payments Oct-Nov 2012
Implement rehabilitation measures Oct-Nov 2012
Clearance of acquired land Dec 2012
DCARB to issue letter of confirmation that RP has been satisfactorily implemented
Dec 2012
PPC, through PPMU, to issue Notice of Site Possession to civil works contractor
Dec 2012
Start of Civil Works Construction Dec 2012- Onwards
Monitoring (from RP updating to civl works construction) July 2011 -onwards
XI. MONITORING AND REPORTING
63. For the subproject, PPMU and CARB will collaborate to carry out internal monitoring of resettlement planning and implementation activities. The scope of internal monitoring will cover an assessment of: (i) compliance with the agreement resettlement policies and procedures and (ii) the availability and efficient use of personnel, material and financial resources; and, identifies the need for (iii) remedial actions to correct any problems that arise. An external monitor will not be engaged as impacts are not significant.
64. The CARB will prepare quarterly progress reports on the resettlement activities and submits it to PPMU. The report includes information on key monitoring indicators, namely:
(i) Displaced persons and compensation: the number of DPs by category of impact; the status of delivery of compensation and subsistence, moving and other allowances.
(ii) Status of rehabilitation and income restoration activities: The number of DPs severely affected by a) loss of productive assets and/or b) displacement; the number of vulnerable DPs; the status of relocation of displaced DPs; the status of technical and other assistance for income restoration.
(iii) Information disclosure and consultation: number and scope of public meetings and/or consultations with DPs; status of notifications to DPs; summary of DP needs, preference and concerns raised during meetings and consultations.
(iv) Complaints and grievances: summary of types of complaints received; steps taken to resolve them; outcomes; and, any outstanding issues requiring further management by district or provincial authorities or ADB assistance.
(v) Financial management: the amount of funds allocated for compensation, operations and other activities; the amount of funds disbursed for each.
(vi) Resettlement schedule: completed activities as per schedule; delays and deviances, including reasons; revised resettlement schedule.
(vii) Coordination of resettlement activities with award of contract for civil works: status of completion of resettlement activities and projected date for award of civil works contracts.
(viii) Implementation problems: problems that have arisen, reasons and proposed strategies to remedy; outstanding issues.
65. Upon receipt of monthly reports, the PPMU consults with CARB to clarify and/or resolve any outstanding issues. On a quarterly basis, the PPMU collates the monthly progress reports for all subprojects in the province, and submits a report to the SC. In turn, the SC prepares a Project monitoring report to be submitted to ADB.
PPTA 7245-VIE: Transport Connection in Northern Mountainous Provinces Project
Resettlement Plan
Cao Bang Province Page 17
APPENDIX 1: IOL FORM
Owner (HH head): ____________________________ HH code ______________
Hamlet: ___________________ Commune : _________________ District: _________________
Sub-project: ________________________
Affected assets of HH: Residential land: □ Garden land: □ Agriculture land: □ Aquaculture land: □ : □ Structure: □ Trees: □ Crops: □
1. SOCIO-ECONOMIC INFORMATION
1.1 Household’s Information
Type of HH: poor HH: □ Policy HH: □ Female-Headed HH : □ Ethnic HH: □
No of HH members: .......... ; of which ....... male, ........ female
Education level of HH head (specify): .............; Age of HH head: ......................; Job of HH head:…………………; HH head ethnic:………….;
Number of children in school age:…………; Number of children quit going to school:………………; Reasons for quitting:…………………………
Date moving to current location:…………………………….
Inhabitants status:……………………………….
1. 2. Economic Information of Household
1.2.1 Status of Land Use
Type of land Area of land (m2)
1. Residential land
2 Garden land
3. Agriculture land
4. Aquaculture land
5. Forestry land
1.2.2 Income sources of household
Income source Main source Secondary source
1. Planting
2. Breeding
3. Fishery
4. Business
5. Handicraft
6. Services
7. Salary
8. Hired labor
9. Others (specify)
In which, Income of Male:………………., of Female……………………….
Who is in charge of spending decision: Husband Wife Both
1.2.2. Income sources of household
PPTA 7245-VIE: Transport Connection in Northern Mountainous Provinces Project
Resettlement Plan
Cao Bang Province Page 18
1 Water sources for drinking/ cooking:……. 1- Rain water 5- Buy 2- Dig well 6- Public tap-water 3- Dig well/drill well 7- Tap water 4- Canals, rivers, pools 8- Others
2 Water sources for cleaning: …………..
3 Health: ………… 1- 2 composite latrine 3- Public toilet 2- Septic tank 4- No toilet
4 Energy- Lighting: ………….. 1- State electric system 6- Coal 2- Electric Generator 7- Gas 3- Battery 8- No 4- Petroleum 9 - Others 5- Wood
5 Energy - Cooking: ………….
2 DETAILED MEASUREMENT SURVEY (IOL)
2.1 Land
Type of land
Category of land
Total area of land available (m
2)
Legality of land
(specify)
Land acquired by the Project (m
2)
permanently temporarily
1
2
3
4
5
6
Notes:
1. Type of land: Residential land (urban, rural), garden land, cultivation land, land for aquaculture, forest land, etc.
2. Category of land: Classify only for agricultural land (category 1 to 6), and land for aquaculture.
3. Legality: Specify clearly the situation of land use of household such as hold / did not held the Land Use Right Certificate, waiting for LURC, land user is eligible under the Land Law, rental land, land allocated temporarily, encroached land, disputed land, etc.
4. Land acquired permanently: Land should be acquired by the Project for construction and will be not returned back to the affected people.
5. Land acquired temporarily: Land should be acquired by the Project during the construction, using for widening the construction access road for material transportation, material storage, worker’s house, etc and it will be returned back to land owners.
2.2 Principal Structure – House and/or shop
Type of house,
structure
Purpose of use
Total area (m
2)
Area demolished
(m2)
Description
Additional notes if necessary:
_____________________________________________________________________________
_____________________________________________________________________________
PPTA 7245-VIE: Transport Connection in Northern Mountainous Provinces Project
Resettlement Plan
Cao Bang Province Page 19
2.3 Other structures and assets
Type of structure and assets Unit Quantity
1
2
3
4
5
6
7
8
Additional notes if necessary:
_____________________________________________________________________________
_____________________________________________________________________________
2.4 Trees and crops
Kind of trees and crops Unit Description/productivity Note
1 Group 1
2 Group
3 Group
4 Group
5 Group
6 Group
7
Group 1: Longan, Coconut, Mango, Star Apple, Group 2: Orange, Mandarin, Grape fruit, Custard-Apple, Guava Group 3: Cashew, Pepper, Coffee, Dragon fruit Group 5: Pine apple, Sugar cane Group 6: Eucalyptus, Bamboo, Others
2.5. Business and income losses
DPs have affected businesses
Business
type
Business status No. of employees Monthly Profit (VND) Registration No-registration Long-term Short term
1
2
3
Business type: 1- Small store/kiosk 4- Gas Station, garage 2- Retail Shop 5- Warehouse, Industrial factory 3- Services (hair dressing) 6- Others:……………………………
3. RELOCATION OPTIONS OF DP (for permanent relocating DPs only)
● Individual relocate in other place: □
● Willing to relocate in the resettlement site: □
● Do not know where to move: □
PPTA 7245-VIE: Transport Connection in Northern Mountainous Provinces Project
Resettlement Plan
Cao Bang Province Page 20
12. Sketch
Sketch location of house, structures affected by the Project
To the North (approx.)
Stick picture of affected house
N
Note: _________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
PPTA 7245-VIE: Transport Connection in Northern Mountainous Provinces Project
Resettlement Plan
Cao Bang Province Page 21
4. Trees, Crops
Type of trees, crops Unit Quantity Note
1
2
3
4
5
6
7
8
9
10
11
12
13
Signature of HH Head Representative of PPMU
(Sign & seal)
Representative of CPC
(Sign & seal)
Representative of IOL Team
(Sign & seal)
PPTA 7245-VIE: Transport Connection in Northern Mountainous Provinces Project
Resettlement Plan
Cao Bang Province Page 22
APPENDIX 2: MINUTES OF COMMUNITY CONSULTATION MEETING
PPTA 7245-VIE: Transport Connection in Northern Mountainous Provinces Project
Resettlement Plan
Cao Bang Province Page 23
APPENDIX 3: LIST OF APS AND AFFECTED ASSETS
PPTA 7245-VIE: Transport Connection in Northern Mountainous Provinces Project
Resettlement Plan
Cao Bang Province Page 24
APPENDIX 4: ADB ACCOUNTABILITY MECHANISM
PPTA 7245-VIE: Transport Connection in Northern Mountainous Provinces Project
Resettlement Plan
Cao Bang Province Page 25
APPENDIX 5: Project Information Booklet
The Transport Connection in Northern Mountainous Provinces Project is part of the effort of the Government of Vietnam (GOV) with joint funding from the Asian Development Bank (ADB) to improve the land transportation network as a means of reducing poverty.
In Cao Bang Province, the Project will improve road 202 on 30.2 km in Nguyen Binh and Bao Lac Districts. The road will be paved and widen.
The PPMU of the Cao Bang Department of Transport is the Executing Agency for this Project. The construction of the road is expected in 2013.
Why is this Project necessary to implement?
The project aims to reduce poverty in rural areas, improve economic situation and productivity in agriculture.
The road density in the project area is quite low in comparison with other regions of the country. Most of the roads are in poor condition.
There is a link between poverty and lack of infrastructure in rural areas of Viet Nam, especially in the mountainous province areas where many ethnic minority groups settle.
What will be the impacts?
Because the proposed roads will be constructed based on existing routes and existing Right-of way (RoW), the road widening will be limited. It is estimated that a total 116 households will be affected by the project. All Households are marginally affected and there is no case of relocation and/or loss of shop or business. Who are the affected persons (APs)?
Entitled APs are those persons who will have been surveyed during the inventory of losses survey and will be verified during detailed measurement survey. Persons who encroach into the area after the cut-off-date will not be entitled to compensation or any other form of resettlement assistance.
What are the resettlement policies and principles of the Project?
The basic resettlement principles of the Project are:
a) All APs are entitled to be compensated for their lost assets (e.g., land, structure, crop, trees), incomes and businesses at replacement cost, and will be provided with rehabilitation measures sufficient to assist them to improve or at least maintain their pre-Project living standards, incomes and productive capacity if ncessary.
b) Lack of legal rights to the assets lost, will not automatically prevent APs from entitlement to compensation.
c) Payment of compensation for affected assets will be completed prior to commencement of any construction activities.
When will the Detailed Measurement Survey be conducted?
This activity is expected to be carried out at in 2012, and will be led by a detailed measurement survey team composed of Project representatives (PPMU staff) and the Resettlement Committees of each affected district.
The survey will only be carried out in the presence of the APs, and APs will be given sufficient advance notice prior to conducting the survey.
Each AP will be asked to assist in completing the Detailed Measurement Survey Form for their household. This form will identify all the losses that the household will experience from the Project, and will be the basis for the compensation package for them. The AP will then be given the AP Compensation Form, which summarizes the losses and the total amount of compensation. The household can review this form for 7 days, and if they agree with the details, the head of the household will be asked to sign the form.
How are the constructions impacts supervised and monitored?
PPMU will monitor the contractor during construction work. Any disturbances to the lives of people along the pipeline will be recorded and issues reported to PPMU for resolution within 7 days.
PPTA 7245-VIE: Transport Connection in Northern Mountainous Provinces Project
Resettlement Plan
Cao Bang Province Page 26
If there are disagreements or problems arising during the Project such as compensation or general project-related disputes, do I have the right to complain?
Any AP may file a complaint or grievance. The Project includes a Grievance Redressal Process and APs may present their complaints to the concerned local administrative officials and RCs, either verbally or in writing.
The complaint can be filed first at the commune level and can be elevated to the highest provincial level if the APs are not satisfied with the decisions made by the commune or district.
If efforts to resolve complaints or disputes are still unresolved and unsatisfactory following the project’s grievance redress mechanism, the households have the right to send their concerns or problems directly to Asian Development Bank - Transport and Communications Division, Southeast Asia Department (SERD) or through ADB Viet Nam Resident Mission. If the households are still not satisfied with the responses of SERD, they can directly contact the ADB's Office of the Special Project Facilitator (OSPF) . (www.adb.org)
Anybody living in the construction site who is affected by the construction or annoyed by the contractors, of anybody who has questions or concerns about the Project, can contact PPMU at the following address:
Mr XXXX PPMU xxxxxxxxxx
# Cao Bang City, Cao Bang Province Telephone number: ()