Date post: | 22-Jan-2023 |
Category: |
Documents |
Upload: | khangminh22 |
View: | 0 times |
Download: | 0 times |
SAFETY AUDIT REPORT
THE ANDHRA SUGARS LIMITED
SAGGONDA
REPORT NO: RPT/793/ANDHRA SUGARS SAGGONDA/APRMS/2019-20/RO
Prepared by
Asia Pacific Risk Management Services Pvt. Ltd
6th Floor, Mookambika Complex
No.4, Lady Desika Road
Mylapore, Chennai – 600004,
Tamil Nadu, India
Email: [email protected]
Web: www.aprms.com
RPT/ /THE ANDHRA SUGARS LTD-SAGGONDA/APRMS/2019-20/R0 Page 1 of 52
RPT/793/THE ANDHRA SUGARS LTD-SAGGONDA/APRMS/2019-20/R0 Page 2 of 52
CONTENTS
Sl.
No
DESCRIPTION PAGE NO.
1. Introduction 4
2. Executive summary 9
3. Review of previous audit records 11
4. Brief details of the plant 11
5. Brief details of the process 15
6. Safety Policy 27
7. Safety Organization 27
8. Safety Communication, Motivation and training 28
9. Safety budget 29
10. Safety committee 29
11. Occupational health center and first aid facilities 29
12. Safety Manuals and rules 31
13. Compliance with statutory regulations 31
14. New equipment review 34
15. Accident reporting, analysis and investigation 35
16. Plant safety inspection 35
17. Personnel Protective Equipments 35
18. House keeping 36
RPT/793/THE ANDHRA SUGARS LTD-SAGGONDA/APRMS/2019-20/R0 Page 3 of 52
19. Machine guarding and general area guarding 37
20. Material handling equipment 37
21. Electrical and personnel safe guarding 38
22. Hydrogen filling and Liquid Hydrogen area 41
23. Work environment monitoring 41
24. Prevention of occupational diseases 41
25. Work permit 41
26. Firefighting system and fire prevention observations 42
27. Safe Operating Procedures 48
28. Emergency preparedness Plan 48
29. Process safety 52
30. Civil 53
31. Effluent treatment and waste disposal 53
32. Others 54
33 PAC manufacturing 58
34 Chlorine Accidents –Accidents happened else where 59
RPT/793/THE ANDHRA SUGARS LTD-SAGGONDA/APRMS/2019-20/R0 Page 4 of 52
1. Introduction
The Andhra Sugars Limited, Chemicals and Fertilizers Division is located at Saggonda,
30 Kms from Kovvur in West Godavari District in the state of Andhra Pradesh. Products
manufactured in the plant are Chlorine gas, Liquid Chlorine, Caustic Soda Lye,
Caustic Soda Flakes, Hydro Chloric Acid, Sodium Hypo Chlorite, Hydrogen Gas, Liquid
Hydrogen, Sulphuric Acid and Poly Aluminum Chloride.
The safety audit was conducted on 11th to 12th September 2019 by the following
team:
1 Mr.H.Ramakrishnan
2.Mr A.Lakshman
Due considerations were given for the existing safe guards in the plant.
The consultants wish to place on record their sincere thanks to the management and
staff of The Andhra Sugars Ltd., for their excellent cooperation and participation in
the study.
Date:17.10.2019
In order to comply with the provisions of manufacture, storage and import
ofhazardous chemical rules, 1989 and also to enhance its safety standards, the
organization engaged the services of M/ s Asia Pacific Risk Management Services
Private Limited, Chennai to conduct a comprehensive Occupational Health and
Safety Audit as per IS 14489:1998.
RPT/793/THE ANDHRA SUGARS LTD-SAGGONDA/APRMS/2019-20/R0 Page 5 of 52
Safety Audit Goals
Audits are normally designed to achieve one or more of the following goals
To provide the auditee with an opportunity to assess its own OS & H system
against standards and identify areas for improvement.
To determine the conformity of the implemented OS & H systems with specified
requirements and identify areas for improvement.
To meet regulatory requirements.
Audit Objectives
Occupational Safety and Health (OS & H) audits are conducted
To carry out a systematic critical appraisal of all potential hazards involving
personnel, plant, services and operational methods.
To ensure that OS & H system fully satisfy the legal requirements and those of
company’s written safety policies, objectives and progress.
Audit Methodology
Appraisal of Audit procedures to the concerned executives.
Familiarization visit to various sections of the unit.
Visit to various sections for in- depth study of hazard potential.
Study of the maintenance system of process vessels, machines, pipes,
equipments, buildings etc.,
Interaction with various levels of employees.
Perusal of documents relating to OS &H.
Appraisal of major observations to the functional heads who are decision
makers to improve SHE system.
Documents Perused
The following records are pursued during the audit.
1. OS & H policy
2. Safety Department’s organization chart
RPT/793/THE ANDHRA SUGARS LTD-SAGGONDA/APRMS/2019-20/R0 Page 6 of 52
3. Safety Budget
4. Safety promotional & motivational measures
5. Training records on safety, fire and first-aid
6. Record of plant safety inspections
7. Accident investigation reports
8. Accidents and dangerous occurrences – statistics and analysis.
9. Record of tests and examinations of equipment and structures as perstatutes
10. Safe operating procedures for various operations
11. Record of work permits
12. Record of monitoring of toxic and flammable and other substances at work
place
13. Maintenance and testing records of the detection and fire fighting equipment
14. Occupational Health Centre/First Aid Details
15. Medical records of employees
16. Records of industrial hygiene surveys (noise, ventilation and illumination levels,
airborne substances and explosive gases)
17. Material safety datasheets
18. On-site emergency plan and record of Mock Drills
19. Communication Systems adopted in the unit
20. Records of waste disposal
21. Housekeeping inspection records
22. Minutes of safety committee meetings
23. Approval of layouts; and other approval from statutory authorities
24. Records of any modifications carried out in plant or process
25. Maintenance procedure records
26. Calibration and testing records
27. Shut down and maintenance procedures
28. In service inspection manuals
29. Records including that of material handling
30. Inspection books and other statutory records
31. Records of previous audits
32. HAZOP Study Reports
RPT/793/THE ANDHRA SUGARS LTD-SAGGONDA/APRMS/2019-20/R0 Page 7 of 52
33. Safety in transportation of hazardous substances
34. Personal Protective Equipment
35. Pressure Vessels, Pipes and Fittings
36. Lifting Machines and Tackles
37. Mobile Equipment and Vehicular Traffic
38. Tank Storage Area Vessel-Details
39. Onsite Gas Cylinder Storage Area-Details
RPT/793/THE ANDHRA SUGARS LTD-SAGGONDA/APRMS/2019-20/R0 Page 8 of 52
Areas covered under audit
1. Safety policy
2. Organization Setup
3. Safety Education and Training
4. Employees participation in OS &H
5. Safety Manual &Rules
6. Compliance with Statutory Requirements
7. New equipment review /inspection
8. Accidents reporting, investigation and analysis
9. Risk assessment including hazard identification
10. Plant safety inspections
11. Health and safety improvements plans /targets
12. First aid facilities – Occupational Health Centre
13. Personal protective equipment
14. Housekeeping
15. Machine and general area guarding
16. Material handling equipment
17. Electrical and personal safeguarding
18. Ventilation, illumination and noise
19. Work environment monitoring system
20. Occupational Health
21. Safe operating procedures
22. Work permit system
23. Fire prevention, protection and fighting system
24. Emergency preparedness plan
25. Process / plant modification procedures
26. Transportation
27. Hazardous waste storage and disposal
28. Safety in storage and warehousing
29. Contractor safety system
30. Boilers, Pressure Vessels and Utilities
RPT/793/THE ANDHRA SUGARS LTD-SAGGONDA/APRMS/2019-20/R0 Page 9 of 52
2. 0 Executive Summary
Presently plant do not have separate safety department. Suggested to have a
separate safety department to oversee the safety activities. This will help in
focusing the safety related activities in monitoring and implementing the
safety improvement plans including the Power plant.
Road Tankers are parked outside the caustic plant near to PAC plant. Several
accidents are reported recently in road tanker parking area in other plants.
Control has to be exercised for road tanker in –out timings, No cooking in the
parking area, Road tanker personnel’s stay in the parking /waiting area are to
be considered.
Transformer 1 and Transformer 2 each 10/16 MVA are aged more than 30 years.
Furfural test is being carried out regularly to monitor the insulation. Life
assessment study to be carried out and the replacement plan to be taken up
by the Andhra Sugars to prevent power failures /accidents.
NIFS Nitrogen injection system fire protection is provided for the 70 KA rectifier
panel.
Plant requires electrical lock out system for safe working in electrical
equipments. Only TAG OUT system is followed in the plant. LOTO system to
cover all dangerous machinery and energy sources are properly shut off and
are not started up unexpectedly while maintenance or service work is being
completed. Suggested for a survey of LOTO implementation equipments like
padlocks, valve lock outs and others for effective implementation.
Anti-toe away system has to be considered for Hydrogen and chlorine filling
vehicles for safety
FRP tanks for HCl acid storage are newly installed.
RPT/793/THE ANDHRA SUGARS LTD-SAGGONDA/APRMS/2019-20/R0 Page 10 of 52
Vanadium pentoxide toxic chemical is stored along with electrical spares in
H2SO4 plant Substation. This should be stored separately to avoid exposure to
dusts. As per officials a separate storage room is being constructed and the
same needs to be expedited.
PAC Powder area: Power cable passes from ground floor to the elevated
floors. This poses fire spread through cable tray. Fire retardant paint coating to
be provided to prevent fire spread.
Road tanker loading area: This area requires safety platform with safety belt
hooking arrangements to prevent accidents –fall from height. Accidents have
happened in Oil tanker filling stations in Petroleum deports due to non-
availability of safe working arrangements.
Thermography of critical electrical installations is required to assess the system
healthy condition.
Lightning arrester study recommendations are to be implemented.
RPT/793/THE ANDHRA SUGARS LTD-SAGGONDA/APRMS/2019-20/R0 Page 11 of 52
Empty land
No occupation –Low hazard
Company owned land
No occupation –Low hazard
Gopavaram Village
Low hazard
Company land, Drain Low hazard
3. 0 Review of previous audit recommendations
Previous safety audit was conducted in the year 2018 and all the observations are
completed and some of them are under review.
4. Brief Details of the plant
4.2 Public utilities:
4.2.1 Fire services –Kovvur 30 Kms from the plant
4.2.2 Police Station: Gopalapuram 22 Kms from
plant
4.2.3 Railway station: Kovvur 30 Kms from plant
4.2.4 Nearest hospitals are
1. P.H.C – HUKKUMPETA 08811 – 253511
4.1 Location and surrounding properties
RPT/793/THE ANDHRA SUGARS LTD-SAGGONDA/APRMS/2019-20/R0 Page 12 of 52
2. Community Health Centre – GOPALAPURAM 9652636709
3. PRASANNA NURSING HOME, PRAKKILANKA 08813 – 282254
4. KOTNIS HOSPITAL, PRAKKILANKA 08813 – 282523
5. GOVT HOSPITAL, KOVVUR 08813 – 231450
6. APEX HOSPITAL, RAJAHMUNDRY 0883 – 2439191
7. SANJANA ORTHOPEDIC, RAJAHMUNDRY 0883 – 2431455
8. S.M.R.M.V. HOSPITAL, TANUKU 08819 – 224905
4.3.0 Total plant area is 320 Acres
4.4 Products manufactured with capacity:
4.5 Key raw materials their sources and inventory
S.NO LIST OF RAW
MATERIALS SOURCE
CAPACITY OF
THE YARD
STOCK
AVAILABILITY
S.NO MANUFACTURING PRODUCTS INSTALLED
CAPACITY
PERMITTED
CAPACITY
1 Caustic Soda 500 TPD 500 TPD
2 Liquid Chlorine 240 TPD 240 TPD
3 Hydrochloric Acid (33%) 1000 TPD 1000 TPD
4 Sulphuric Acid 300 TPD 300 TPD
5 Hydrogen (Bottling) 2.4 TPD 2.83 TPD
6 Caustic soda Flakes 140 TPD 140 TPD
7 Liquid Hydrogen 1 TPD 1 TPD
8 Sodium Hypo Chlorite (100%) 40 TPD 40 TPD
9 Poly Aluminum Chloride 90 TPD (18%) 90 TPD (18%)
RPT/793/THE ANDHRA SUGARS LTD-SAGGONDA/APRMS/2019-20/R0 Page 13 of 52
1 SALT Andhra Pradesh/
Gujarat 15,000 MT 25 DAYS
2 SULPHUR Import from middle
east 15,000 MT 2 MONTHS
3 HYDRATED
ALUMINA Hindalco / NALCO 5,000 MT 5 MONTHS
4.6 Storage Tank farm details
Sl Tank no Material
stored
Type
oftan
k
Storage
temp.
and
pressure
Type of fire
protection inerting, fixed
Water spray, foam, dyke
1 D203 A,B,C,D,E Caustic
Soda 32%
MSRL 50*C Atm
80*C
Dyke wall
2 D204,A,B,C Caustic
Soda 48%
MS 50*C Atm Dyke wall
3 D710,A,B,C,D,F Liq Chlorine M.S -2to-10*C
2.0 to 10
Kg/Cm2
Dyke wall and
neutralizing system
4 D901 E,F,G,H
D 911
A,B,C,D,E,F,G,H
Hydrochloric
Acid
MSRL 50*C Atm Dyke wall
D902
A,B,C,D,E,F, G,
H
Hydrochloric
Acid
FRP 50*C Atm Dyke wall
RPT/793/THE ANDHRA SUGARS LTD-SAGGONDA/APRMS/2019-20/R0 Page 14 of 52
Sl Tank no Material
stored
Type
oftank
Storage
temp.
and
pressure
Type of fire
protection inerting, fixed
Water spray, foam, dyke
5 Storage
Tank
1,2,3,4,5,
Sulphuric
acid
M.S 50*C Atm Dyke wall
6 D 801A,B,C,
D
Sodium
Hypochlorite
HDPE 12-15*C Dyke wall
7 Day tank
1
1 and 2
Sodium
Hypochlorite
MSRL 12-15*C Dyke wall
8 V 105
A,B,C,D,E,F,
G,H
Poly
Aluminum
Chloride
FRP Atm
Pressure
and
Dyke wall
9 V101 (at
PAC
unit)
Crude
PAC
FRP 60*C
Atm
Dyke wall
4.7 Boilers
Sl
n
o
Boiler
registry
numbe
r
Boiler
capacit
y
Type
of
boile
r
Boiler
ratin
g
M2
Year of
Manufactur
e
Max.
Working
Pressure
Kg/CM
2
Make
1 AP 2648 10 TPH Wate
r tube 427 1985 14.7
Cethar
Vessels P Ltd
2 AP 3816 15 TPH
Wate
r
Tube
592 2003 17.25 Cetharvessel
s P Ltd
3 AP 3989 15.43 TPH WHB 2091 2005 48.4
Thermal
systems (P)
Ltd
4 AP 939 6 TPH HMT 177 1978 13.3 NESTLER Ltd
4.8 Thermic fluid boilers
1. Thermic fluid heater for heating of heat transfer salt in Bertram’s flaking plant
RPT/793/THE ANDHRA SUGARS LTD-SAGGONDA/APRMS/2019-20/R0 Page 15 of 52
(70TPD)-Fuel H2 & HFO (Heavy fuel oil)
2. Thermic fluid heater for heating of heat transfer salt in Blow Knox flaking plant
(60TPD)-Fuel H2 & HFO (Heavy fuel oil)
5.0 Brief details of the process.
Caustic Soda Lye and Flakes Plant
Caustic soda (32%) is manufactured by electrolysis of brine solution.
NaCl+H2O -------- NaOH +1/2 Cl2 +1/2H2
Main raw materials are NaCl and Power and the process is described follows:
Raw salt is dissolved in the Saturator, and the saturated brine of about 320 gpl
concentration is prepared. The impurities such as, Calcium, Magnesium, Sulphates
etc. are removed from the Saturated Brine by the addition of Barium Carbonate and
Sodium Hydroxide respectively.
The treated Brine passes through Clarifier. The precipitated impurities, along with
insoluble’s like, sand and clay are settled in clarifier. The overflow from clarifier is sent
through the series of filters (anthracite filter, Dr. M .filter). Organic matters and fine
impurities are filtered in these filters. From Dr. M. Filter purified brine is sent to ion
exchange units for further purification. The polished brine gets heated up in chlorine
recuperator before admitting to the Ion exchange units.
This purified brine enters the Electrolysers. The electrolyser element assembly consists
of anode (titanium) and cathode (nickel) and cation exchange semi permeable
membrane, the membrane is placed between anode and cathode. On giving DC
current the brine solution undergoes electrolysis and forms NaOH and hydrogen on
the cathode side and chlorine on the anode side. The weak brine of about 240 gpl
RPT/793/THE ANDHRA SUGARS LTD-SAGGONDA/APRMS/2019-20/R0 Page 16 of 52
concentration is returned to the brine plant for re-saturation and purification. Caustic
soda of around 32% concentration, Hydrogen and chlorine gas are produced.
32% caustic soda from electrolyser is further concentrated into 48% in triple effect
evaporation plant by using steam as heating medium.
Caustic Soda Flakes Manufacturing:
Caustic soda flakes manufactured by concentrating caustic soda from 32% /48 % to
99% by multiple effect evaporation with the use of falling film technology in two steps.
First step is concentration of caustic soda rising up from 32% to 48% in the first stage
of the triple effect evaporator and the second step is rising the concentration from
48% to 62 %/73 % by using steam and in the third step to 99 % from 62%/73% with the
use of heat transfer salt in long tube concentrator (evaporator).
The 50% caustic lye will be pumped to the single effect evaporator through a pre
heater. An additive solution prepared by dissolving sugar in caustic lye will be dosed
into feed caustic lye in order to destroy oxidizing agents like chlorates and any
dissolved air in the feed lye so that the corrosion attack of the evaporator equipment
will be minimized.
The evaporation will be under vacuum. The water vapors will be condensed by
means of water to the barometric condenser. The steam ejector or vacuum pump
provides the vacuum to the system.
The 62% caustic liquor from 62% caustic separator bottom will be pumped to the
anhydrous caustic concentrators system, operating 4 Nos in parallel.
The 62% caustic in anhydrous caustic evaporators is heated counter currently with
inorganic molten salt which in turn will be heated in vertical furnace where fuel oil or
hydrogen is used as fuel.
RPT/793/THE ANDHRA SUGARS LTD-SAGGONDA/APRMS/2019-20/R0 Page 17 of 52
The molten caustic and super-heated vapours will be separated in a separator. The
water vapours will be cooled and condensed in a Surface condenser operating the
system under vacuum. The molten caustic (99%) from the separator is collected into
anhydrous caustic storage tank and overflows into flaker pan where it is converted
into flakes by cooling the anhydrous caustic soda by circulating cooling water in the
flaker to its fusion point, the flakes will be directly filled in HDPE bags with alkathene
liners inside and weighed.
Chlorine Cooling, Drying, Compression, Liquefaction, Storage and Filling
The Chlorine gas is cooled, by exchanging heat with polished brine, then cooled by
cooling water and finally by chilled water to 18*C and then passes through mist filter
to remove NaCl mist.
Moist chlorine is passed through Drying Tower, where concentrated Sulphuric Acid is
circulated and moisture content in chlorine is reduced to below10ppm.
The dry chlorine gas is compressed to a pressure of 2.5 to 3.0 Kg/Cm2 by liquid ring
centrifugal compressors and sent to the Liquefaction Plant through dry chlorine mist
filters.
The compressed gas is condensed by Freon refrigeration system.
Liquid Chlorine flows by gravity to liquid chlorine storage tanks. Uncondensed gas
(sniff gas) is delivered to the HCl Unit.
From the storage tanks chlorine sent to filling by padding with dry compressed air of
about 11 kg/Cm2 pressure.
Hydrogen Bottling Process Description
The hydrogen gas coming out from the cell house at 80o C is cooled to 40oC in Hydrogen
cooler and passed through mist filter to remove NaOH mist and then scrubbed with cold
RPT/793/THE ANDHRA SUGARS LTD-SAGGONDA/APRMS/2019-20/R0 Page 18 of 52
soft water in a packed column to free the gas from alkali carryover if any. The column is
provided with sloping bottom and proper sealed type draining arrangement for removal
of any accumulated oil and carbon deposit without risking of air ingress into the system.
The scrubbed gas is led .through a safety seal to a wet type gas holder of 50 m3capacity.
A safety seal is interposed between scrubber and gas holder to prevent any over
pressurization of the system. The safety seal will release the gas through vent pipe if
the pressure rises above 110-120 mm WC. The vented gas will be let off to atmosphere
at about 2 m above the highest level in the area through a flash back arrestor. The
safety seal is provided with water supply and a sealed type overflow system.
The scrubbed gas is led to the gas holder through a moisture trap cum flash arrestor.
The trap has been provided with soft water connection and sealed type overflow.
Similar trap is provided at gas holder outlet also.
Knock out drums are provided between hydrogen gas compressors suction header
and compressors suction lines. In this knock out drum moisture in H2 gas gets
separated and drained once in 8 hrs. The collected water is drained through safety
seal pots. H2 enters the compressor through suction strainer and compressed to the
desired bottling pressure of 150 bars. The compressor is of 5 stage “SULZER “make air
cooled type. The compressor is provided with pressurized/ purge type control panel.
RPT/793/THE ANDHRA SUGARS LTD-SAGGONDA/APRMS/2019-20/R0 Page 19 of 52
A Pressure Maintenance Valve is fitted at outlet of compressor to maintain gas
pressure at the outlet of compressor within narrow limits during cylinder filling
operations.
A high pressure purge bottle is provided in the HP gas system to facilitate removal of
carried over moisture and oil in the gas stream. A drain valve provided is operated
every hour.
The gas from the purge bottle passes through a fine filtration equipments, pre filter,
micro filter and activated carbon filter. Each filter is provided with separate drain
valve to free the gas from oil mist and water vapour.
High pressure hydrogen gas after getting cooled by chilled water is fed high pressure
hydrogen filling manifold through a header fitted with isolation valves for supplying
and cutting off gas to individual manifold for filling cylinders both loose and trailer
mounted.
Flash back arrestors with integral non- return valve are provided at top end of all
hydrogen vent line to facilitate safe venting of hydrogen. All vent line outlets are
taken up to a height about 2 m above highest working level in the surrounding area.
Hydrogen leak detectors are provided in the plant at 5 strategic locations.
Hydrochloric Acid Manufacturing
The Hydrogen gas from electrolysis after cooling is partly used in the production of
Hydrochloric Acid, by reacting Chlorine in a furnace to form Hydrogen Chloride in
the form of gas, which is absorbed in water to form Hydrochloric Acid of 33%
strength.
RPT/793/THE ANDHRA SUGARS LTD-SAGGONDA/APRMS/2019-20/R0 Page 20 of 52
The HCl synthesis unit consists of three principal parts.viz. The burner, the synthesis
chamber- heat exchanger assembly, receptor and tail gas tower.
The HCl gas after absorption in Cooler –Absorber and tail gas towers will be diverted
to waste HCl scrubber in order to scrub with DM water. The resultant very dilute HCl
acid will be utilized in HCl production by mixing with feed water. The HCl
concentration in the scrubber exit gas will be maximum 10mg/NM3. Thus the
unabsorbed HCl emission from HCl Plant is effectively removed by treating with water
in scrubbers. The scrubbing is counter current and the scrubber uses one inch PVC
rings as media.
Sodium Hypochlorite
As a pollution abatement measure and to recover the waste chlorine as much as
possible, the vent chlorine from various sources is absorbed in 18% caustic to produce
sodium hypo chlorite, which is sold.
The absorption system consists of three absorbers. Each absorber is packed with
randomly distributed packing.
Reaction: Cl2+ 2NaOH ---NaOCl +NaCl+H2O
The reaction is highly exothermic and heat of reaction is removed by circulation of
scrubbing liquid through coolers.
The first and second stage absorbers are mounted on sumps. The Cl2 gas enters the
first stage absorber from bottom and then enters the second stage absorber.
Practically chlorine is absorbed in first stage absorber itself; only a very small quantity
of chlorine enters the second stage from where effluent gas is practically free of
chlorine. The third stage absorber is provided for safety.
RPT/793/THE ANDHRA SUGARS LTD-SAGGONDA/APRMS/2019-20/R0 Page 21 of 52
Finally the residual waste gases after absorption are let out to the atmosphere
through a chimney of 60 M height. Cl2 detector is provided in the stack line.
The sodium hypo tower pumps and waste chlorine blowers are connected to the
emergency supply and UPS in order to operate them continuously without
interruption during power failure time also.
Sulphuric Acid Manufacturing
Sulphuric acid is manufactured by Double Contact Double Absorption to achieve
higher yield of product.
Sulphur is melted in melting pits fitted with steam coils. Molten Sulphur is fired in
Sulphur furnace with pre dried process air. Sulphur is converted to Sulphur- -di-oxide.
S+O2 ------ SO2 +Heat
The heat liberated is utilized to produce steam in waste heat boiler (WHB). The outlet
gas from WHB enters into five pass converter having V2O5 catalyst where SO2 is
converted to SO3. This is also an exothermic process.
2SO2+O2 ------- SO3 +Heat
The outlet gases are absorbed in Inter Pass Absorption tower (IPAT) where 98.4% acid
is in circulation. The IPAT outlet acid concentration is adjusted to 98.4% by addition
of DM water.
Since SO3 absorption and water dilution to acid are exothermic processes, the
process acid is continuously cooled in acid coolers.
SO3 + H2O -H2SO4 +Heat
The V pass outlet gases are cooled and absorbed in Final Absorption Tower (FAT),
function of which is similar to IPAT. The conversion efficiency of SO2 to SO3 is 99.7%
RPT/793/THE ANDHRA SUGARS LTD-SAGGONDA/APRMS/2019-20/R0 Page 22 of 52
compared to 97-98% in single contact single absorption process. Hence in DCDA
process emission from plant stack is reduced.
The outlet gases from IPAT and FAT are passed through demisters/ mist eliminators to
prevent carryover of acid mist along with residual gases.
The vent gases from FAT are let out through the stack after passing through an alkali
scrubber, where dilute caustic soda solution is in continuous circulation for
neutralization of SO2 and SO3 gases escaping through the stack. This alkali scrubbing
system is also meant to take care of any excessive emissions during start up periods
and intermediate stoppages for long time. The alkali scrubbing system comprises of
a dilute caustic solution tank, a packed scrubbing tower and circulation pump.
The alkali scrubber liquor, sodium sulphite is effectively used for dechlorination of
return brine in the membrane cell caustic soda plant.
Poly Aluminum Chloride (PAC) Manufacturing
The production of liquid Aluminium chloride consists of etching of alumina with an
aqueous solution of hydrochloric acid.
The reaction takes place in a glass lined reactor equipped with three blade
agitator and a heating jacket.
The reactor is installed on a weighing scale.
At first HCl coming from storage tank is loaded by a centrifugal pump. When loading
of HCl is completed, agitator is started for better mixing of HCl and Aluminium, which
is being added gradually.
RPT/793/THE ANDHRA SUGARS LTD-SAGGONDA/APRMS/2019-20/R0 Page 23 of 52
The alumina is fed to the reactor by an extendable plastic pipe that is disconnected
from feeding nozzle after alumina feeding is completed.
After loading the temperature is increased up to 70oC by feeding low pressure steam
in the jacket.
At the beginning aluminum chloride reaction occurs between 35-50oC depending
on the concentration of raw materials. This reaction is exothermic. When the
temperature of 70oC is reached steam with medium pressure (8-9 Kg/Cm2) is fed
through jacket.
As the difference between internal and external surface (jacket) cannot exceed
110oC to avoid damage to the glass lining, it is necessary to use steam at two different
thermal levels (3 bar and 8 bar pressure).
At first step the reaction is exothermic and temperature increases to 105oC and then
the temperature increases to 160oC in order to complete PAC formation reaction
(reaction time is about 165minutes).
Once the reaction time is completed, in order to avoid thermal shocks to the liner
inside the reactor, the cooling procedure must be very smooth. Starting with warm
water is composed by a water collecting tank, recirculation pump and a thermo
stated water heat exchanger. When the internal temperature has reached to 90oC,
the product is diluted with water (predetermined quantity) in order to reach the
concentration of PAC solution. The reaction mass is discharged by compressed air.
The total batch time is eight hours. By adding sodium aluminate solution high basicity
PAC can be obtained in a separate preparation Tank.
A safety filter is installed on the discharge line in order to check if any problem on
reactor glass lining has occurred.
RPT/793/THE ANDHRA SUGARS LTD-SAGGONDA/APRMS/2019-20/R0 Page 24 of 52
The discharged product is further cooled to 60oC in a graphite cooler and then
discharged in the crude PAC tank.
As alumina is fed to the reaction unit in slight excess quantity and some insoluble
material is present in the raw materials, crude PAC has to be filtered. The filtration
system is composed of a filter press and a diaphragm pump. The solids removed
during filtration are discharged through a screw conveyor in a small sludge cart and
disposed as landfill in low lying areas.
After filtration PAC solution is fed to the storage.
All vents of the tanks and reactors are connected to a scrubber that washes the gas
with water before letting to atmosphere. The overflow from the scrubber is collected
in a storage tank.
The overflow of the scrubber is slightly acidic and can be used in various operations
of PAC dilution in the plant without having any impact in the product quality.
In case of opening of safety valve in the reactor, the HCl vapours are released in to
a safety tank that is full of water, which can absorb HCl.
5 Block wise process details are as below
S.No. Production
Block
Products made Type of raw
material
used
In plant
quantity of key
raw materials
Type of reactions
in the block
1. Cell Hall Caustic Soda,
Chlorine,
Hydrogen
(Unprocessed)
Salt (NaCl) 1.60 MT/ Ton of
Caustic Soda
Electrolysis
2. Evaporatio
n Plant
Caustic Soda Lye Caustic Soda
Lye
1.0 MT / Ton Evaporation and
Separation
RPT/793/THE ANDHRA SUGARS LTD-SAGGONDA/APRMS/2019-20/R0 Page 25 of 52
3. Flaking
Plant
Caustic Soda
Flakes
Caustic Soda
Lye
1.0 MT / Ton Evaporation and
Separation
4. Chlorine
Plant
Liquid Chlorine Chlorine Gas
& Sulphuric
Acid
1.05 MT of
Chlorine gas &
50 Kgs of
Sulphuric acid/
MT of Liq.Cl2
Drying,
Compression &
Condensation
5. Hydro
Chloric
Acid
HCL (33%) Chlorine &
Hydrogen
0.32 Mt of
Chlorine & 0.01
MT of
Hydrogen per
ton of HCL
Burning, Cooling
& Absorption
6. Sodium
Hypo
Chlorite
Sodium Hypo
Chlorite
Caustic Soda
& Chlorine
0.180 MT of
Caustic Soda &
0.107 MT of
Chlorine/ M.T
of Sodium
hypo
Absorption &
Chilling
7. Hydrogen
Bottling
Hydrogen Gas
Filling
Hydrogen
Gas
1.0 NM3 per 1.0
NM3
Compression &
Filling
8. Sulphuric
Acid Plant
Sulphuric Acid Sulphur 0.33 MT per MT
of H2SO4
Melting, Burning,
Catalytic
Conversion &
Absorption
9. PAC Plant Poly Aluminium
Chloride
Alumina
Hydrate,
Sodium
Aluminate &
HCL
0.3 MT Alumina,
0.7 MT HCL, 0.1
MT of Sodium
Aluminate per
MT of PAC
Reaction at
elevated
temperature &
Pressure in GL
reactors
10. Liquid
Hydrogen
Liquid Hydrogen Hydrogen
Gas, Helium
Gas, Liquid
Nitrogen
1.1 MT of H2
gas per MT.
15.0 MT of LN2
per MT
Compression,
Purification,
Chilling
RPT/793/THE ANDHRA SUGARS LTD-SAGGONDA/APRMS/2019-20/R0 Page 26 of 52
6.0 Safety Policy
Plant has an integrated management system policy covering quality,
environment, health and safety and signed by CMD
IMS policy is signed by CMD and adopted from1.7.2011 Annexure 1
It fulfills the requirements of AP Factory Rules
All employees are made aware of policy statement during induction training.
1.0 More display of safety policy is various department and locations will create more
awareness
7.0 Safety Organization
Safety department is headed by the Mechanical Department head and assisted by
Technical assistants. Fire department responsibilities are also managed by
Mechanical department head.
SAFETY ORGANISATION
7.1 Suggested to have a separate safety department exclusively. This will help in
Executive Director
Safety In-charge
Chairman & Managing
Director
Junior Engineer
RPT/793/THE ANDHRA SUGARS LTD-SAGGONDA/APRMS/2019-20/R0 Page 27 of 52
focusing the safety related activities in monitoring and implementing the safety
improvement plans.
8. 0 Safety training Communication and motivation
Plant has a plan of 6 hours per person per year for imparting training.
Plant has developed 33 Training programs scheduled and conducted in the
year 2019. Refer Annexure 2
Work permit system
Working at height
Personal Protective Equipment
First Aid
Fire prevention System
Chlorine Cylinders filling and handling
Electrical safety
Confined space entry
Material handling
Maintenance of Transformers
Contract Workmen safety
Training programme for truck drivers on defensive driving
Personal Protective equipment Electrical
Scaffoldings Arrangement for maintenance works
Static Electricity Hazards Preventive measures
Use of fire Extinguishers
Fire prevention system
Operating personal regarding Personal Protection &
Emergency action etc.
Safety contests are organized as a part of Safety Day celebrations during the
month of February.
RPT/793/THE ANDHRA SUGARS LTD-SAGGONDA/APRMS/2019-20/R0 Page 28 of 52
9. 0 Safety Budget
There is no constraint for purchase of safety and fire equipments. This shows
the management’s commitment on safety.
Safety budget is utilized for the following:
Procurement of Personal Protective equipments and consumables
Fire protection equipments spares
Statutory inspection and certification like pressure vessel testing
National Safety day celebrations and
Fire hydrant system maintenance
10. 0 Safety Committee
Safety Committee is formed as per Factories Act and AP Factories Rules,
1950.
Safety Committee consists of 15 members from various functional
departments of the unit.
Safety committee meetings are held quarterly and minutes are verified.
11. Occupational Health center and First aid facilities
OHC is available in the plant
The medical officer is available in general shift. OHS is staffed with Para
medical staff covering Round the clock.
Exclusive driver for the Ambulance is available in all the shifts.
Twelve first aid boxes with medicines are kept at following locations and
periodically checked
1. Hydrochloric Acid Plant & Hypo Plant
2. Hydrogen Plant
RPT/793/THE ANDHRA SUGARS LTD-SAGGONDA/APRMS/2019-20/R0 Page 29 of 52
3. Chlorine Filling Section
4. Work Shop
5. Cell House & D.C.S
6. Chlorine Compressor
7. Evaporation Plant/ Bertrams Plant
8. Laboratory/ Brine Plant
9. Power House
10. HTLT 1 & 2
11. R.O Plant
12. PAC Plant
Thirty trained first aiders are in the plant covering all the shifts.
GENERAL SHIFT “ A ” - SHIFT
1. G.U. Bhaskara Rao, Elect. Engineer 1. S.N. Venkata Ratnam, Chemist
2. R.V.V.S.N. Murthy, Elect. Engineer 2. B.V.K. Prasad, Chemist
3. M.V. Satyanarayana Murthy, A. E (Mech) 3. N.V.V. Prasad, Asst. Chemist
4. M. Srirama Krishna, Sr. Chemist 4. U. Narendra Babu, Asst. Chemist
5. N.V.V. Srinivasa Rao, Head Time Keeper 5. B.N.V. Gopala Krishna, Asst. Chemist
6. L. Vasudeva Rao, Asst. Fitter 6. D. Suresh Babu, Fitter Gr-III
7. Desireddy Rama Krishna, Asst. Fitter 7. U. Sreehari Prasad, J.E (Mech)
8. K. Balaji, Inst. Mech-Gr-III 8. Y. Raja Rao, Supervisor (Inst)
9. V.K. Satish Kumar, Electrician Gr-II 9. U. Posi Babu, Security H/G
“ B ” – SHIFT “ C ” - SHIFT
1. D.V.V.S.S. Prasad, Chemist 1. N. Ashok Chowdary, Chemist
2. K. Yesu Babu, Welder Gr. III 2. K. Pream Sagar, Wireman Gr-III
3. P.V. Rama Sastry, Fitter Gr-III 3. CH.S.R.K. Murthy, Helper
4. K. Murali Mohan, Asst. Electrician 4. R.B.V.N.S. Prasad, Chemist
5. M.V.V. Satish Kumar, Supervisor (Mech) 5. M. Phanindra Babu, Supervisor
(Mech)
RPT/793/THE ANDHRA SUGARS LTD-SAGGONDA/APRMS/2019-20/R0 Page 30 of 52
Medical examinations: Statutory Medical examination is conducted as per AP
Factory Rules and the records available in the plant.
Medical emergency practice:
After receipt of the communication from the time office about the incident, we will rush
to the incident area by ambulance. After thorough examination of the Patient, if it is major
injury, he will be sent to Dispensary by ambulance. In the dispensary, he will be given First
Aid and taken to the ESI Hospital or other necessary hospital for further treatment purpose.
If the patient is in normal condition with minor injury, then the patient will be given
treatment in our dispensary. After found normal he will be send back to work.
12. 0 Safety Manual and Rules
Safety manual
Plant is certified for EMS and OSHAS system. Department manuals are available
with Standard Operating Procedures.
13. 0 Compliance with statutory requirements
Following are the important Acts and Rules applicable to this unit.
1. Factories Act &Rules
2. Indian Electricity Act &Rules
3. Pollution Control Act &Rules
4. Gas cylinder rules
5. Contract Labor Act &Rules
6. Weights and Measures Act &Rules
7. Petroleum Act
8. Indian Boilers Act
Detailed legal register is available and is updated periodically. Details are as below:
RPT/793/THE ANDHRA SUGARS LTD-SAGGONDA/APRMS/2019-20/R0 Page 31 of 52
Sl. No Subject Form in which
Application to
be made
Present
status,
Renewal up
to
1. Water (P&C of pollution) Act, 1974 and
rules, 1981
APPCB/VSP/RJY449/CFO/HO/2019 Dt:16-
10-19
Form- D 31-08-2024
2. Air (P&C of pollution) Act, 1981 and rules,
1982/83
APPCB/VSP/RJY449/CFO/HO/2019 Dt:16-
10-19
Form- I 31-08-2024
3. Hazardous waste (M&H) rules, 2016
APPCB/VSP/RJY449/CFO/HO/2019 Dt:16-
10-19
Form- I 31-08-2024
4. Hazardous wastes (Management,
Handling and Trans boundary movement)
Rules,2016
Form- 4 Every June
5. Environment Protection Act, 1986 Form- V Every
September
6. Public Liability Insurance Act, 1991 Document 31st March
2020
7. Environmental Protection Rules – Env.
Clearance
EIA & CFE Once get
valid 7 years
8. The Factories Act, 1948/1987 Form no- 4 Every year
9. The Indian Electricity Rules Act, 2003 H.T agreement
/
Appendix VIII
--------
10. Arms Act, 1959 and Arms Rules, 1962 Form- II 31-03-2020
11. The Explosive Act, 1884 The Explosive rules
1983 Petroleum Act, 1934
Form IX & XV 31-12-2024
RPT/793/THE ANDHRA SUGARS LTD-SAGGONDA/APRMS/2019-20/R0 Page 32 of 52
12. Gas Cylinder Rules 2004 Hydrogen Gas
Cylinders Storage
Form- F 30-09-2023
13. Gas Cylinder Rules 2004 Hydrogen Gas
Cylinders Filling
Form- E 30-09-2023
14. Gas Cylinder Rules 2004 Chlorine Cylinders
Storage
Form- F 30-09-2023
15. Gas Cylinder Rules 2004 Chlorine Cylinders
Filling
Form- E 30-09-2023
16. Gas Cylinder Rules 2004 Testing and
Examination of Hydrogen Cylinders
- 30-09-2026
17. Gas Cylinder Rules 2004 Testing and
Examination of Chlorine Cylinders
- 30-09-2026
18. Under Explosive Act see rules act 1884 sec
49&50 Licenses to store chlorine
Form- III 31-03-2019**
19. Under Explosive Act see rules act 1884 sec
49&50 Licenses to store Liquid Nitrogen
Form- III 30-09-2024
20. Licensed to Transport Compressed Gas in
a Pressure Vessels Vehicle noAP-37-Y-2392
Form- IV 30-03-2021
21. Indian Boilers Act Regulations 389 Boiler
AP-3989
Form- VI 01-02-2020
22. Indian Boilers Act Regulations 389 Boiler
AP-3816
Form- VI 01-01-2020
23. Indian Boilers Act Regulations 389 Boiler
AP-939
Form- VI 01-02-2020
24. Indian Boilers Act Regulations 389 Boiler
AP-2648
Form- VI 01-08-2020
25. Contract Labour (Regulation & Abolition)
Act, 1970
Form No- 2 Continued
26. Employees Provident Fund Act, 1952 Form 5 A Continued
27. Employees Family Pension Scheme, 1971 Form 5 A Continued
28. Employees Deposit Linked Insurance
Scheme,1976
Form 5 A Continued
RPT/793/THE ANDHRA SUGARS LTD-SAGGONDA/APRMS/2019-20/R0 Page 33 of 52
29. Employees Group Saving Linked Insurance Policy Continued
30. Individual Happy Family Floater Policy Application 30-09-2020
31. Manufacturer/ packer of pre packed
commodities, under rule 27 of the Legal
Metrology Packaged Commodities Ruled,
2011
Certificate Continued
32. Bureau of Indian Standards certification
marks license:
PAC- Caustic Soda – Lye and Solid (Flakes)
CM/L- 4581066
CM/L-
6600042110
31-03-2020
20-06-2020
33. E- Waste Rules- 2016 -- Continued
34. Employees Compensation Act, 1923 -- Continued
35. Employee State Insurance Act, 1948 Form- 01 Continued
36. Food Safety Standards Act, 2006 Form- A 14-04-2022
Note: Sl. No. 18, we have applied for the renewal of Chlorine storage license well within the time.
we are awaiting for the license renewal from the PESO.
14. 0 New Equipment review/Inspection
Plant design consultants are M/s Thyssen Krupp Industrial solutions India. Lamella clarifier
system is developed by the plant and successfully established in brine plant.
Plant to consider evolving a check list for management of change
The checklist is to include the following:
1. Any process change should be wetted by engineering packages.
2. Engineering data sheet entry to be made for any specification change
3. Insurance related aspects need to be covered –introducing the changes to be
incorporated in the policy for additional assets involved.
4. Any change in on site emergency plan subsequent to change
5. Design code compatibility on the equipments on which modification
6. Statutory compliance or reporting of the modification.
RPT/793/THE ANDHRA SUGARS LTD-SAGGONDA/APRMS/2019-20/R0 Page 34 of 52
A model of the points to be considered is annexed to this report. Annexure
15. 0 Accident investigation and near miss reporting
No reportable accidents happened in the plant
Near miss incident investigations: Near miss accidents are investigated and
corrective actions are taken.
It is suggested to have preventive actions (similar locations) to be included in the
investigation report.
16. 0 Plant safety inspection
16.1 In the plant safety inspection and audit are carried out systematically and
documented. Standard operating procedures are available and followed.
16. 2 The status of the objectives and targets shall be reviewed periodically and
recorded.
17. 0 Personal Protective Equipment
17. 1 Plant is certified for EMS. Hazard Identification and Risk assessment register is
available. PPE s identified for the operations and procured.
17. 2 Safety Officer reviews and ensures the special PPE s is available for use.
17.3 Critical PPEs available in the plant are
Sl PPE description Quantity
1 Eye wash cum shower combination units 29
2 SCBA 27
RPT/793/THE ANDHRA SUGARS LTD-SAGGONDA/APRMS/2019-20/R0 Page 35 of 52
3 Breathing air cylinders 43
4 Emergency life breathing apparatus 04
5 Emergency escape breathing
Apparatus
15
6 Ear muff 40
7 Cryogenic suit 02 at LH2 plant
8 Heat resistant suits 02 at LH2 plant
9 Heat resistant blanket 1000mmx6000 mm 02 at Acid plant
10 Cryogenic hand gloves 02 pairs atLH2
plant
11 Wind sacks 07
12 Canister gas mask 41
13 Spare canisters 13
14 Full face masks 06
15 Hose connected type face masks 05
16 Particulate filters 104
17 Air blower with intended hose mask 1
Escape breathing Apparatus are checked monthly and the check sheet being
followed is attached in Annexure 3
SCBA PM Check list is attached in Annexure 4
RPT/793/THE ANDHRA SUGARS LTD-SAGGONDA/APRMS/2019-20/R0 Page 36 of 52
17. 0 Housekeeping
Housekeeping is an essential part of Occupational Safety and Health program.
Housekeeping can prevent 50 % of accidents and near misses.
18. 1 Spill kits are to be made available for the storages and labs
19. 0 Machine guarding and Safety reliefs
Any machine part, function, or process which may cause injury must be safeguarded.
Where the operation of a machine or accidental contact with it can injure the
operator or others in the vicinity, the hazards must be either controlled or eliminated.
Section 21 of factories Act 1948 and various sections of AP Factories Rules require
safety guarding of machines and processes against injury and ill health of personnel.
19.1 Chlorine filling area: Safety latch for crane hook and spreader beam hook is
required.
19.2 Spreader beams are locally made. Testing by competent person is required.
Suggested to verify the standard spreader beam capacity.
19.3 Tonners are lifted with lifting hooks clamped on the rips. There is possibility of
throat opening in the hooks due to repeated use. Throat opening to be checked in
periodical maintenance.
20.0 Material handling equipments & Road safety
20.1 Material handling equipments are tested as per AP Factories Rules and
certificates are available.
20.2 Lot of dust is generated by vehicle movement in the plant roads and
water spray is carried out in the plant. Effectiveness to be monitored and the
water sprinkling frequency has to be increased.
RPT/793/THE ANDHRA SUGARS LTD-SAGGONDA/APRMS/2019-20/R0 Page 37 of 52
20.3 Fire tender is parked inside the Chlorine bullet area. This needs to be
parked in safe area away from the bullet storage for easy operation.
20.4 Inside the fenced area of Chlorine bullets several trucks and transport
vehicles are parked. This needs to be avoided.
21. 0 Electrical and Personnel Safe Guarding
21.1 In the substation UPS room used batteries are kept. They are potential fire
hazard. They should be removed from the battery room once they are found
defective or life is expired.
21.2 In the substation UPS room Normal plug point is available. Flame proof
plug point and flame proof tools are to be used inside the battery room.
21.3 Battery terminals need cap to prevent shorting while tightening the
terminals during inspection.
21.4 Substation battery room exhaust is not run continuously. Continuous
running is required to avoid any accumulation of Hydrogen generated during
charging and discharging cycles.
21.5 Transformer 1 and Transformer 2 each 10/16MVA are aged more than 30
years. Furfuraltestis being carried out regularly to monitor the insulation. Life
assessment.
Study to be carried out and the replacement plan to be taken up by the Andhra
Sugars to prevent power failures / accidents.
(ix) he shall ensure that the transformers of 10 MVA and above
RPT/793/THE ANDHRA SUGARS LTD-SAGGONDA/APRMS/2019-20/R0 Page 38 of 52
rating or in case of oil filled transformers with oil capacity more
than 2000 Liters are provided with fire fighting system as per IS -
3034:1993 or with Nitrogen Injection Fire protection system:
21.6 In10/16MVAtransformer No1 Oil leakage from the top flanges are observed.
Suggested to check the oil level in conservator and maintain it for the loss and
correct the same at the earliest.
21.7 All transformers neutral conductor to be provided with HV insulation to
prevent contact with the neutral bar under short circuit conditions.
21.8 Buchholz relay is tested during the annual maintenance from the control
panel for functioning but mechanical check for the contacts to close by Nitrogen
passing to be checked to ensure the mechanical contacts are closing for tripping.
21.9 Transformer 4 and 5 each 10/16MVA are newly installed. The soak pit is
made by tank form buried below the ground. The man whole portion of the tank
form need to raise above ground to check and remove any water accumulation
inside. Also provide a vent pipe with inverted U shape to release the gas generated
during draining the transformer oil under fire condition and to avoid rain water entry
during rains.
21.10 70 KA rectifier transformer DM water level is in closed loop. Low level alarm
in the tank needs to be verified and provided if not available. DM water level
monitoring may be carried out.
21.11 NIFS Nitrogen injection system fire protection is provided for the 70 KA
rectifier panel.
RPT/793/THE ANDHRA SUGARS LTD-SAGGONDA/APRMS/2019-20/R0 Page 39 of 52
21.12 Provide Guard for the HV DC bus bars in rectifier transformer area. This job
is being carried out.
21.13 Provide warning Signs “DANGER, HIGH VOLTAGE DC, ENTRY ONLY FOR
AUTHOURISED PERSONNEL” in HV DC bus bar area.
21.14 HT/LT SS1 Emergency generator diesel day tanks needs earthing to
prevent static charge accumulation.
21.15 In HT LT SS1 an Auto transformer is available for motor checking. The
transformer Cable cellar below HT LTSS1: Lot of unwanted materials are stored in
the cable cellar. Also contractors are entering the cable cellar to keep their things.
Any fire / handling things can damage the cables and will result in disruption. Cable
cellar should be cleared of storage of materials and entry should be for authorized
personnel only.
21.16 H2SO4Plant33/0.433KVSS:Transformerisindoortypewith3sidesclosed.
Ventilation is adequate as per plant officials. This needs to be verified for summer
times.
21.17 Auxiliary Supply panel with lead acid batteries for Transformer control
panels is 132 KV substations. The room with lead acid batteries rack requires flame
proof equipments like FLP switches, FLP exhaust. This room also requires H2 Detector.
22. 0 Hydrogen filling and Liquid Hydrogen area
22. 1 In hydrogen purity analyzer room lights and switches are non-flame proof one.
Requires flame proof fittings.
23. 0 Work environment monitoring
RPT/793/THE ANDHRA SUGARS LTD-SAGGONDA/APRMS/2019-20/R0 Page 40 of 52
23. 1 Periodical internal air quality monitoring is required as chlorine, HCl, H2SO4 are
manufactured, stored and transported in the plant.
24. 0 Prevention of occupational diseases
Occupational Health is the promotion and maintenance of the highest degree of
physical, mental and social well-being of workers in all occupations by preventing
departures from health, controlling risks and the adaptation of work to people, and
people to their jobs. (ILO / WHO 1950).
Several measures adopted in the organization in prevention of occupational
hazards:
Pre-employment medical examination of all new employees are carried out
and the records are available
Medical examination for the hazardous operations is identified and the medical
examinations are conducted.
25. Work permit
Work permit system procedure is available in plant. There are several permits in the plant
to carry out the work safety. These includes
Gas/Acid Line maintenance work permit
Excavation work permit
Hot work permit
Working at Height Permit
Vessel / Confined space entry work permit
Electrical work permit
General work permit.
.
25. 1 Plant requires electrical lock out system for safe working in electrical
equipments. Only TAG OUT system is followed in the plant. LOTO system to cover all
dangerous machinery and energy sources are properly shut off and are not started
RPT/793/THE ANDHRA SUGARS LTD-SAGGONDA/APRMS/2019-20/R0 Page 41 of 52
up unexpectedly while maintenance or service work is being completed. Suggested
for a survey of LOTO implementation equipments like padlocks, valve lock outs and
others for effective implementation.
25. 2 During audit In SS HTLT1 electricians are attending panel maintenance. They do
not have electrical work permit / General work permit as required for the work. This
needs to be viewed seriously and permit system needs to be followed for all the
works.
26. 0 Firefighting systems and Fire prevention observations
Plant has Fire fighting crew with 18 Security staff covering all the shifts. Apart
from this plant personnel are also trained in fire fighting periodically.
Plant has emergency crew with members from security, Medical, Chemical,
Civil, Electronics, Electrical, Instrument and Automobile Departments for
meeting any emergency.
Fire hydrant system and Fire extinguishers details
Storage Tanks 2 no’s
Capacity 650m3’each
Pump capacities Motor Driven pump 273 m3 /hr. at 8Kg/cm2 -1 no
Diesel engine driven pump 273 m3 /hr. at 7.0Kg/cm2 -1 no
Jockey pump 10.8 m3 /hr. at 8.0Kg/cm2-1 no
Number of fire hydrant points 60
Number of water monitors 05
Plant has a fire tender to meet any emergency.
Fire Buckets 140 numbers are available in various locations of the plant.
Fire extinguishers details: 278 fire extinguishers of various types are provided in
various locations of the plant.
RPT/793/THE ANDHRA SUGARS LTD-SAGGONDA/APRMS/2019-20/R0 Page 42 of 52
Medium velocity sprinkler / Deluge system
Sl Location Type Spray
Nozzle
MODE
L
No
of
spray
nozzles
No
of bulbs
Flow
rate
M3/
hr
Bulb
fusion
tempin Deg C
S.NO
I
EQIPMENT DESCRIPTION
FIRE EXTINGUISHERS:
QTY
1 ABM Foam 9lit.cap.(stored pressure type) 14
2 ABM Foam 9lit.cap.(cartridge type) 07
3 ABM Foam 50lit.cap.(cartridge type) 01
4 ABC Clean Agent 4kg cap. 06
5 BC DCP 5 Kg .cap (cartridge type) 34
6 BC DCP 6 Kg.cap (stored pressure type) 4
7 BC DCP 10 Kg.cap.(cartridge type) 14
8 ABC DCP 2 Kg.cap.(stored pressure type) 07
9 ABC DCP 5 Kg.cap.(stored pressure type) 18
10 ABC DCP 6 Kg.cap.(stored pressure type) 04
11 ABC DCP 9 Kg.cap.(stored pressure type) 06
12 ABC DCP 10 Kg.cap.(stored pressure type) 05
13 BC CO2 2 Kg.cap.(gas type) 05
14 BC CO2 3.2 Kg.cap.(gas type) 06
15 BC CO2 4.5 Kg.cap.(gas type) 92
16 BC CO2 6.5 Kg.cap.(gas type) 10
17 BC CO2 6.8 Kg.cap.(gas type) 23
18 BC CO2 9 Kg.cap.(gas type) 16
19 BC CO2 22.5 Kg.cap.(gas type) 04
20 BC DCP 75 Kg.cap. (cartridge type) 01
21 BC DCP 9 Kg.cap. (cartridge type) 01
Total 278
RPT/793/THE ANDHRA SUGARS LTD-SAGGONDA/APRMS/2019-20/R0 Page 43 of 52
1 H2 Bottling
plant
No 1
MVWS K-64-120 40 - 181 -
2 H2 Bottling
plant
No 2
Deluge K-42-120 45 45 225 79
3 HT/LT No1
cable
cellar
MVWS K-41-140 64 - 186 -
4 LH2 Plant
Tanker
Filling
Deluge K42-110 78 78 225 79
5 LH2 Plant
Tanker
parking
Deluge K-91-110 36 36 225 79
Fire detection and alarm system
RPT/793/THE ANDHRA SUGARS LTD-SAGGONDA/APRMS/2019-20/R0 Page 44 of 52
Sl Location Smoke
detect
or
Heat
Dete
ct or
Manu
al call
points
Loop
power
sound
er
Line
fault
isolator
Flame
detecto
rs
1
3.8 MW HFO generator
House control room &
132/33 KV Substation
12 8 1 1 1 --
2 Rectifier room No-3 6 -- 1 1 -- --
3 HT/LT cable gallery
room and DG room 16 8 4 4 -- --
4 HT/LT Room first floor 16 -- 2 2 1 --
5 CSP DCS Control Room 16 -- 2 2 -- --
6 DCS Control Panel
Equipment Room 6 -- 1 -- 1 --
7 Rectifier Control Room 4 -- -- 1 -- --
8 DCS Instrumentation
Panel Room 4 -- -- -- -- --
9 Polarization Rectifier
Control Room 8 -- 1 1 1 --
10 Battery Room -- 4 -- -- -- --
11 HT/LT Switch Gear
Room- 1 & 2 12 -- 1 1 -- --
12 Liquid hydrogen plant -- -- 3 -- -- 4
13 STORES 4 -- -- -- -- --
14
Bertram’s Flaking Plant
DCS Control Panel
Room & Control Room
4 -- -- -- -- --
15 VFD Room at CL2 Plant 2 -- -- -- -- --
16 VFD Room at Brine
plant 2 -- -- -- -- --
Total 112 20 16 13 4 4
RPT/793/THE ANDHRA SUGARS LTD-SAGGONDA/APRMS/2019-20/R0 Page 45 of 52
26.1 Provide list of areas covered in each zone in the panel for easy identification
when there is an indication.
26.2 Rectifier Transformer area smoke detection system needs to be extended.
26.3 HTLT SS1 cable cellar is at ground level and the panel room is at first floor. In
several places cable entry from the bottom are not covered properly. This will result
infirepropagationfromcellarandviceversa.Suggestedforfirespreadpreventionby
proper sealing or with fire retardant paint coated for 1 meter on both sides. ( N02 DG
AMF panel cable entry there is gap)
26.4 Plant has the following UPS systems. Observations on the inspected UPS
systems are follows. Safety requirements for UPS is attached in Annexure 6
LIST OF UPS SYTEMS AND THEIR LOCATIONS
SL CAPCITY
IN KVA
MAKE LOCATION PURPOSE
1 3 Siemens Control room For No1 Rectifier
2 3 HL -REL Control room For No2 Rectifier
3 2.5 HL-REL Control room For No3 Rectifier
4 300 EMERSON Control room For Polarization
rectifier
5 2*10 Accutech
Infosystems Pvt
Ltd
Control room For No 4 Rectifier
6 160 Synergy HT/LT 2 For Hypo plant
7 300 HL REL HT/LT2 For Hypo plant
8 20 Accutech
Infosystems Pvt
Ltd
LH2 Plant For Laboratory
RPT/793/THE ANDHRA SUGARS LTD-SAGGONDA/APRMS/2019-20/R0 Page 46 of 52
9 10 -do- MCC3 Room
top floor
For laboratory
26.5 300 KVA + 160 KVA UPS Room: There are 4 numbers of 2T ac units are working
continuously 24x7. Domestic AC units are not rated for continuous operation.
Additional capacity AC units are to be fixed and run cyclically so that no ac unit will
run continuously for more than 8 hours. Accidents have occurred in Pharma units labs
due to continuous working ac units. Similarly Rectifier control room has 24x7 working
ac units.
26.6 300 KVA + 160 KVA UPS Room: In UPS room under false flooring power cables
are laid along with communication cables. So false flooring requires smoke detector.
26.7 300 KVA + 160 KVA UPS Room: It is suggested to provide compartments for
UPS and Battery units separately. The battery rack needs to be maintained at 25*C
and the UPS can work up to 35 Deg C safely. Also exhaust will generate heat from
the UPS unit. Providing separate AC systems / unit will conserve power and also
Separation of battery racks and UPS can be achieved.
26.8 H2SO4 plant: Panel room requires smoke detector provision.
26.9 Anti-toe away system has to be considered for Hydrogen and chlorine filling
vehicles for safety
26.10 For flaking plant furnace, LPG is used as pilot fuel. LPG is drawn from
commercial cylinders through manifold. In the manifold there are five inlet points and
one outlet point. There were only two LPG cylinders kept connected to the manifold.
It was observed that on removal of cylinder the adopter connecting the LPG cylinder
and manifold was left over as such. If the isolation valve provided at the adopter of
RPT/793/THE ANDHRA SUGARS LTD-SAGGONDA/APRMS/2019-20/R0 Page 47 of 52
the manifold passes, LPG will leak into the surroundings. Hence it is suggested to
keep the adaptor connected to the cylinder even the cylinder is empty till another
cylinder is connected.
26.11 Dual fuel (Hydrogen and fuel oil) are used for flaking plant furnace. It was told
that HAZOP study has been conducted by the plant supplier.
26.12 PMCCN1&N2VFDroom: Cleanagent fire extinguishing modules may be
provided for fire fighting as providing other systems at height will be difficult.
27. Safe Operating procedure
Safe Operating procedures are available in each department considering the safety
in Operations, environmental requirements and Occupational health. SOP s are
prepared as per the EMS.
27.1 Operators may be trained periodically on SOP and whenever the SOP s is
updated
27.2 SOP s updating is to be carried out whenever there is process changes are
taken up.
28. Emergency Preparedness plan
On site Emergency preparedness plan considering possible emergency
scenarios is available and is in accordance with MSIHC Rules.
Mock drill report : refer annexure 5
Key personnel for managing On Site emergency plan are
OFFICE RES
EXECUTIVE DIRECTOR 4360
RPT/793/THE ANDHRA SUGARS LTD-SAGGONDA/APRMS/2019-20/R0 Page 48 of 52
FACTORY MANAGER 4366 4391
PERSONNEL MANAGER 4327 4390
ADVISER (MECHANICAL) 4326 4388
DY. CHIEF ELE. ENGINEER 4313 4383
INSTRUMENT ENGINEER 4325 4378
ASSISTANT ENGINEER CIVIL 4309
MEDICAL OFFICER 4337
SAFETY INCHARGE 4339 4389
Plant has Fire fighting crew with 18 members covering all the shifts. Apart from
this plant personnel are also trained in fire fighting periodically
GENERAL SHIFT “A” - SHIFT
1. U. Adinarayana Murthy, Asst. Security Officer 1. V. Rama Krishna, Security Head Guard
2. B. Murali Mohan, Security Head Guard 2. D. Raja Babu, Security Guard
3. D.V. Rama Krishna, Security Guard 3. CH. Mutyala Rao, Security Guard
4. P. Vijaya Kumar, Security Guard
5. K. Chitti Moshai, Security Guard
“B” – SHIFT “C” - SHIFT
1. MD. Mahaboob Alam, Security Head Guard 1. U. Posi Babu, Security Head Guard
2. B. Nageswara Rao, Security Guard 2. N. Veera Krishna, Security Guard
3. P. Posa Rao, Security Guard 3. A. Chamcha Rao, Security Guard
4. K. Sesha Rao, Security Guard 4. D. Venkata Krishna, Security Guard
5. K. Srinivas, Security Guard 5. CH. Israil, Security Guard
RPT/793/THE ANDHRA SUGARS LTD-SAGGONDA/APRMS/2019-20/R0 Page 49 of 52
Emergency grew with specific areas are identified and employees responsible for the
same is as follows:
EMERGENCY CREW
U. ADINARAYANA MURTHY SECURITY
MD. ALAM SECURITY
V. RAMA KRISHNA SECURITY
U. POSIBABU SECURITY
Y. MOHAN KUMAR MEDICAL
N.V.V. SRINIVASA RAO MEDICAL
K. YESU BABU CHEMICAL
GARAPATI VENKATESWARA RAO CHEMICAL
N. SANYASI RAO MECHANICAL
ALLU SRINIVASA RAO MECHANICAL
A. SATYANARAYANA CIVIL
P. RAMA KRISHNA ELECTRONICS
B.G. KONDALA RAO ELECTRICAL
V.K. SATISH KUMAR ELECTRICAL
P. SASI BUSHAN KUMAR INSTRUMENT
Y. KASI INSTRUMENT
M. RAJESH AUTO MOBILE
Plant has emergency crew with members from security, Medical, Chemical,
Civil, Electronics, Electrical, Instrument and Automobile Departments for meeting any
emergency.
District authorities and their contact details are
DISTRICT AUTHORITIES & EMERGENCY TELEPHONE NO’S
RPT/793/THE ANDHRA SUGARS LTD-SAGGONDA/APRMS/2019-20/R0 Page 50 of 52
DISTRICT COLLECTOR ELURU 08812 230050
REVENUE DIVISIONAL OFFICER KOVVUR 08813 231488
MANDAL REVENUE OFFICER GPR 08813 274451
DISTRICT MEDICAL OFFICER ELURU 08812 230278
DY. SUPERINTENDENT OF POLICE JRG 08821 225503
INSPECTOR OF FACTORIES ELURU 08812 231190
POLLUTION CONTROL BOARD ELURU 08812 249668
POLICE STATION GPR 08813 252433
FIRE STATION KOVVUR 08813 231101
MUTUAL AID
[A] JOMC - JEGURUPADU 0883 2453179
[B] GTPS - VIJJESWARAM 08813 285408
11 chlorine and Hydrogen leak detectors are available in the plant
Emergency mock drills are conducted during general shift hours. During general
shift hours senior managers and officials will be present and weakness in the system
will not get exposed. It is advised to conduct emergency mock drills during odd hours,
rainy days and holidays.
29.0 Process Safety
29.1 Working persons in the hydrogen compression and bottling area are provided
with Electrostatic dissipative shoes. Periodically integrity of these shoes shall be
ensured.
RPT/793/THE ANDHRA SUGARS LTD-SAGGONDA/APRMS/2019-20/R0 Page 51 of 52
29.2 Lye storage and loading area should be lined with alkali resistant tiles.
29.3 As per IS 4262 if a common bund wall is made for more than one tanks, then
capacity of the bund should be enough to hold the content of the largest tank (after
deducting the space occupied by the other tanks). The bund wall and the floor of the
bunded area should be made of acid resistant material. The slope of the floor should
end up in a sump having drain pipe with valve approachable from outside. The drain
should discharge into an acid resistant neutralization sump of adequate size. The
height of the bund wall and its distance from the tank periphery should be so adjusted
that the jet of acid released from any part of the body of the tank may not fall outside
the brim of the bund wall.
29.4 All storage tanks do not have hazard indication. All storage tanks shall be marked
with hazard indication label as per NFPA
29.5 FRP tanks for HCl acid storage are newly installed. Less than 2 years old. FRP tank
test procedure guidelines developed with the following standards
ASTM E 1067-07 Standard Practice for AE Examination of Fiberglass Reinforced
Plastic Resin (FRP)Tanks;
ASME, Boiler and Pressure Vessel Code; and
RTP-1, Reinforced Thermoset Plastic Corrosion-Resistant Equipment
30.0 Civil
30.1 4x10/16 MVA transformers have a soak pit located outside the yard. It does not
have any vent. Vent is required as the transformer oil drained during emergency will be
hot and will generate fumes. To avoid over pressurization of choke pit vent is required.
Provide vent of goose neck type to avoid rain water ingression.
30.2 Similarly the choke pit has to be checked periodically for free from moisture /
water as hot oil during draining in emergency will create steam and will cause steam
RPT/793/THE ANDHRA SUGARS LTD-SAGGONDA/APRMS/2019-20/R0 Page 52 of 52
explosion.
30.3 PMCC N1&N2 panel room there is only one entrance is available. Escape route
is required.
31.0 Effluent treatment and waste disposal
ASL has implemented various recycling systems of waste water streams and the generated
effluents from the 500 TPD Caustic Soda Plant, 300 TPD Sulphuric Acid Plant & 90 TPD PAC
plant operations will be treated in existing ETP followed by R.O. After neutralization,
clarification, disinfection and filtration the water is going to R.O. Plant as feed water. The
R.O. permeate is being utilised for cooling water makeup and reject is being utilised in
brine saturator.
About 766 KLD of effluents will be generated from the Chemicals & Fertilisers division of
Saggonda unit. The existing ETP is designed to treat about 1200 KLD or a maximum hourly
flow of 35 KL. This means that the present ETP capacity will suffice, quantity – wise to meet
the hydraulic effluent load generated from the 500 TPD Caustic Soda Plant operations as
well as from the Sulphuric Acid plant & PAC plant operations.
The various categories of effluent streams from different sections of the Caustic Soda plant
namely Cell House, Chlorine liquefaction, DM Water plant, Secondary brine purification,
HCl plant and Hypo plants are collected through an exclusive epoxy lined drain system
into the equalisation tank.
The effluents from caustic soda plant have wide variations in their PH values and therefore
the first step in the ETP is the PH correction. ETP consists of an equalisation tank where
different effluents streams join and get mixed and this is followed by a neutralization tank
where PH is brought to 7.5 to 8.0 by the addition of Caustic Soda Lye or Hydrochloric Acid.
The effluents from the equalization tank are pumped into the clarifier, where suspended
solids in the effluent are settled. The clarifier is circular is shape with a conical bottom and
a slow speed rake mechanism drags the suspended solids to the centre of the conical
bottom. The sludge settled is drawn to the sludge drying beds for drying. The clear and
treated effluent is obtained from the clarifier overflow collected into receiving tank and
pumped to R.O. Plant.
EQUIPMENT DETAILS OF EFFLUENT TREATMENT PLANT
1) Equalisation cum Neutralisation Tanks
Size : 6.0 X 6.0 X 2.25 m SWD
Volume : 81.0 M3 Each
M.O.C. : RCC / EPOXY
No. of Units : 2
Hydraulic Retention Time : 2 Hours.
Mixing : Agitation with Mechanical Agitators- 2 Nos
Drive for Agitation : 5.0 HP / 60 RPM
2) Chemical Dosing Tanks
RPT/793/THE ANDHRA SUGARS LTD-SAGGONDA/APRMS/2019-20/R0 Page 53 of 52
Size : 1.5 m X 2.0 m SWD
Volume : 3.5 M3 each
M.O.C : HDPE
No. of Units : 2 (one for NaOH and another for HCl)
3) Pumps for feed to Clarifier
Capacity : 60 M3 / Hr. each
Head : 15 m
Motor : 12.5 HP / 1440 RPM
No. of Units : 2
4) Over flow weir box
Size : 2.9 X 2.9 X 0.5 m SWD
Volume : 4.2 M3
M.O.C : MS / EPOXY
No. of Units : 1
5) Clarifier
Size : 8.0 m X 2.5 m SWD
Volume : 125 M3
M.O.C : MS / EPOXY
HRT : 9.5 hours
Sludge hoper Slope : 1 in 12
Sludge removal : Scrapper Mechanism
Drive for Scrapper : 1.0 HP
No. of Units : 1
6) Treated Effluent Holding Tank
Size : 4.0 m X 4.5 m SWD
Volume : 57 M3
M.O.C : MS / FRP
No. of Units : 1
7) Pump for Treated Effluent to R.O. Plant
Capacity : 60 M3 / Hr.
Head : 30 m
Motor : 15 HP / 1440 RPM
No. of Units : 2
8) Sludge Drying Beds
Size : 4.0 X 3.0 X 0.25 m
Volume : 3.0 M3 each
M.O.C : RCC
No. of Units : 2
9) On-Line pH analysers
RPT/793/THE ANDHRA SUGARS LTD-SAGGONDA/APRMS/2019-20/R0 Page 54 of 52
Effluent inlet to ETP : 1 no.
Effluent outlet from ETP : 1 no.
II. R.O. Plant Process Description:
We have installed Reverse Osmosis(R.O.) plant of capacity 40 m3/hr for the treatment and
reuse of the effluents generated from the process operations of our Saggonda unit. Main
operations of R.O. plant are as follows:-
a) Chemical Treatment
b) Clarification
c) Primary Filtration
d) Ultra Filtration and
e) R.O. Filtration
Reverse Osmosis is a membrane process in which synthetic semi permeable membranes
are used to remove dissolved impurities from water.
a) Clarification system:
The clarifier serves the purpose of reducing suspended solids, colloidal silica & removal
of heavy metals from effluent water.
High Rated Solid Contact Clarifier (HRSCC):
It works mainly on two basic principles namely coagulation/flocculation and Hydraulic
separation. Coagulation & Flocculation occurs in the flocculation zone when the feed
stream comes in intimate contact with chemical mixtures and the suspended sludge
particles from previously treated water. This contact also promotes flocs growth as
smaller particles agglomerate into larger heavier particles.
The hydraulic separation principle uses an up flow design to move water into the settling
zone for clarification.
The HRSCC provides three zones for better clarification.
i) Rapid mix zone:- Where raw water re-circulated precipitates and fresh reagents
are rapidly mixed together.
ii) Slow miz zone:- Where gentle mixing permits floc formation and brings the floc
into intimate contact with the suspended particles.
iii) Clarification or settling zone:- Where the up ward flow (rise rate) is reduced to a
low value to permit the precipitation to settle out.
Settled sludge is moved continuously along the floor towards centre of unit by means
of a slowly rotating scrapper which covers the entire floor area.
The sludge from the HRSCC will be led into the sludge drying bed.
The clarifier effluent is collected in the clarified water tank and further it is pumped to
the Multigrade filter.
b) Multigrade Filter System:-
The clarified water is passed through a Multigrade filter to reduce the suspended solids
RPT/793/THE ANDHRA SUGARS LTD-SAGGONDA/APRMS/2019-20/R0 Page 55 of 52
present in the water. This filter is provided to keep a check on the suspended solids.
The suspended particles in the feed water get entrapped in the filter media. Pebbles
of two different sizes and sand used as filter media. The filter will have to be
backwashed with effluent water for 10 to 150min. daily. The filtered water is then passed
through the Ultra filtration unit.
c) Ultra filtration system:-
Ultra filtration is a low pressure membrane process for the removal of colloidal silica,
colloidal particles, all particulate matter, suspended solids and bacteria.
The feed effluent flows from the inside of the fibres, permeates through the membrane
and is removed as the product from the shell side.
Ultra Filtration (UF) is a unit operation often used to remove suspended solids, colloids,
traces of oil and macro molecules from liquid streams. As pre treatment to reverse
osmosis system. UF significantly increases the membrane life for the R.O. membranes
and reduces the cleaning frequencies, thereby reducing operating expense for R.O.
system.
Over view of Ultra filtration (UF):
Ultra filtration (UF) is a pressure driven unit operation in which particulate, colloids,
emulsified oils, and macro molecules are separated from a liquid feed stream upon
passage through a porous semi permeable membrane. On the separation of size
spectrum, UF falls between Nano filtration (Membrane pore sizes below app 0.01 micro
meter) and micro filtration (pore sizes grater than 1.0 micro meter).
UF has greater removal efficiency and gives higher quality product water.
The UF permeate water from the UF module will then flow to RO feed tank from where
it will be pumped to RO system.
d) Reverse Osmosis System:-
Reverse Osmosis process is a membrane process in which synthetic semi permeable
membranes are used to remove dissolved impurities from water. When a semi
permeable membrane separates a dilute and concentrated solution of slats, due to
osmosis, the water from the dilute solution side passes though the membrane to the
concentrated side till osmotic equilibrium is attained. Any process in excess of the
osmotic pressure reverses the direction of flow of water and water from the
concentrated side enters the dilute side. This process is called the reverse osmosis.
It is very essential to ensure that the water fed to reverse osmosis membranes is free
from particulate matter, scale forming salts Ca & Mg and silica to prevent membrane
fouling. Also, the water should be free from organic matter, heavy metals and oxidising
agents like free chlorine. For that dosing S.M.B.S. and Anti scalant chemicals to the
system.
Capacities:
HRSCC Feed flow rate : 1X 49 m3/hr
RPT/793/THE ANDHRA SUGARS LTD-SAGGONDA/APRMS/2019-20/R0 Page 56 of 52
MGF Flow rate : 1X 40 m3/hr
UF Feed flow rate : 1X 40 m3/hr
RO Feed flow rate : 1X 40 m3/hr
Recovery : 70%
Permeate flow rate : 1X 28 m3/hr
R.O. permeate is being utilised for cooling water makeup/green belt development
and R.O. reject is being utilised for Brine Saturator. Plant wastes generated are disposed as below in compliance with Hazardous waste
disposal authorization
S.NO WASTE DESCRIPTION DISPOSAL METHOD
1 BRINE SLUDGE
Disposed into lined land fill in
our own premises 2 SATURATOR SLUDGE
3 ALUMINA SLUDGE
FROM PAC PLANT
4 SULPHUR SLUDGE Send to Kovvur SSP plant for
utilized as filler material
5 SPENT V2O5 CATALYST Send to TSDF parawada
32.0 Others
32.1 Hydrogen is filled in individual cylinders as well as in road trucks containing
hydrogen cylinder banks. It is advised not to allow filled road truck rest near the plant
and to send out the filled road truck after finishing formalities as quick as possible.
32.2 Wherever sulphuric acid is handled like in chlorine drying area, it is recommended
to display caution like “WEAR GOGGLES” and ensureit.
32.3 Dyke requirement for Tank farm as per OSID is
RPT/793/THE ANDHRA SUGARS LTD-SAGGONDA/APRMS/2019-20/R0 Page 57 of 52
OISD (Oil industry Safety Directorate) 118
General;
(a) The tank height shall not exceed one and half times the diameter of the tank
or 20 m whichever is less. For the installations covered under Oil Mines Regulation,
the maximum height of the tank, dyke requirements etc. shall be as per Oil Mines
Regulations
(b) Piping from / to any tank located in a dyked enclosure should not pass
through any other dyked enclosure. Piping connected to tanks should run directly
to outside of dyke to the extent possible to minimise piping within the enclosures.
(c) The minimum distance between a tank shell and the inside toe of the dyke
wall shall not be less than half the height of the tank.
(d) There shall be access on all four sides of each dyke area and roads should be
linked to minimize the effect if one road is cut off during the fire.
This needs to be followed to prevent spigot flow outside the tank farm in case of
leak from the tank.
32.4 21m3x4 Hypo storage tanks are not provided with dyke.
33.Poly Aluminum Chloride (PAC) Manufacturing
33.1 Plant DCS room requires smoke detector. False flooring also requires smoke
detector.
33.2 24x7 AC units are in DCS. Additional AC units are to be provided and no ac is
working more than 8 hours continuously has to be ensured to prevent fire hazard.
33.3 Hcl Storage tank farm: The pumps are inside the dyke. Pumps should be
outside the dyke farm for safety.
33.4 HCl Tank farm dyke capacity is less as against the requirement of 550 M3.
(110% capacity of the largest tank)
RPT/793/THE ANDHRA SUGARS LTD-SAGGONDA/APRMS/2019-20/R0 Page 58 of 52
33.5 PAC flaking area: Power cable passes from ground floor to the elevated floors.
This poses fire spread through cable tray. Fire retardant paint coating to be provided
to prevent fire spread.
33.6 Road tanker loading area: This area requires safety platform with safety belt
hooking arrangements to prevent accidents –fall from height. Accidents have
happened in Oil tanker filling stations in Petroleum depots due to non-availability of
safe working arrangements
34.0 Chlorine Accidents –Accidents happened else where
RPT/ /THE ANDHRA SUGARS LTD-SAGGONDA/APRMS/2019-20/R0 Page 52 of 52
Annexure 2 Training plan 2019
THE ANDHRA SUGARS LIMITED [C & F DIVISION]
SAGGONDA
PROPOSED TRAINING PLAN -2019
HR– F 001/ REV: 02/Dt.01-11-2017
SL.
No Name of the Training Programme
Faculty of Dept
Schedule Targeted
Manpower
1. Operating personnel safety regarding personal protection and emergency action
Safety / Chemical January 40
2. Chlorine leaks handling Safety / Chemical January 30
3. Hydrogen gas cylinders safety Safety / Chemical February 40
4. Operation and maintenance of plants in co-
ordination with other plants and departments
Chemical February 35
5. Training programme for truck drivers on
defensive driving
Safety March 50
6. Static Electricity hazards – Preventive measures Electrical / Safety March 40
7. Personal Protective Equipment Safety March 50
8. Chlorine cylinder filling and handling safety Safety / chemical March 40
9. First aid Dr. J. Bhanu
Prasad
March 30
10. Maintenance of Transformers Electrical March 25
11. Lubrication oil & grease to various pumps and
gear boxes
Mechanical March 35
12. Confined space entry Safety / Chemical April 30
13. Material handling Safety / Chemical April 40
14. Personal protective equipment electrical Electrical May 40
15. Effect of Brine Plant disturbances on
Electrolysis
Chemical May 30
16. Personal Protective Equipment Safety June 40
17. Safety during Chlorine cylinder filling Chemical /
Safety
June 40
RPT/ /THE ANDHRA SUGARS LTD-SAGGONDA/APRMS/2019-20/R0 Page 53 of 52
18. Coupling alignment of pumps Mechanical June 20
19. Fire prevention system Safety July 30
20. Operation of different types of Pumps Mechanical July 30
21. Training programme for truck drivers on safe
transportation of Hazardous chemical
Safety / Admin August 50
22. Chemical process control Chemical/Inst August 40
23. Work permit system Safety September 40
24. Electrical Switch gears Electrical September 35
25. Chlorine leak handling Safety / Chemical October 20
26. Contract work men safety Safety / admin October 60
27. Maintenance of Motors Electrical October 25
28. Use of fire Extinguishers Safety November 50
29. Personal protective equipment Safety November 50
30. Mechanical shaft seals Mechanical November 35
31. Electrical safety Electrical December 30
32. Scaffoldings Arrangement for maintenance
works
Safety /
Mechanical
December 30
33. Variable frequency drive (VFD) Electrical December 40
RPT/ /THE ANDHRA SUGARS LTD-SAGGONDA/APRMS/2019-20/R0 Page 54 of 52
Annexure 3 Preventive maintenance check list -Escape Breathing Apparatus
THE ANDHRA SUGARS LIMITED
C&F DIVISION, SAGGONDA
PREVENTIVE MAINTENANCE CHECK LIST
EMERGENCY LIFE /ESCAPE BREATHING APPARATUS
FORMAT NO: SFTY – F 001
FREQUENCY: MONTHLY DATE:
Ta
g
No
.
LOCATIO
N
Cylinder Condition of Sign of
plant
person
Remark
s
No. H.T
Due
Pres-
sure
Bar
Loc
k
clip
Cylinde
r Valve
Should
er
Strap
Pr.
Gau
ge
Face
mask
Hose
&hose
connectio
n
condition
1 LH2 plant ELBA
2 LH2 plant ELBA
3 LH2 plant EEBA
4 LH2 plant EEBA
3 CL2 filling EEBA
4 CL2 filling EEBA
5 CL2 filling EEBA
6 Cl2
compress
or
EEBA
7 Cl2
compress
or
EEBA
8 Time
office
ELBA
9 Time
office
ELBA
10 Cell
house
EEBA
11 Cell
house
EEBA
12 DCS EEBA
13 DCS EEBA
RPT/ /THE ANDHRA SUGARS LTD-SAGGONDA/APRMS/2019-20/R0 Page 55 of 52
Annexure 4 SCBA Preventive Maintenance Check list
THE ANDHRA SUGARS LIMITED
C&F DIVISION, SAGGONDA PREVENTIVE MAINTENANCE CHECK LIST
SELF CONTAINED BREATHING APPARATUS FORMAT NO:SFTY – F001 FREQUENCY: MONTHLY DATE:
Ta
g
N
o.
LOCATI
ON
Cylinder Condition of Condition of
Face Mask
Rem
arks /
Sign
of
plant
perso
n
N
o
.
H.
T
D
u
e
Pre
s--
sur
e
Ba
ck
Pla
te
De
ma
nd
Valv
e
Cyl
.
Str
ap
Ass
ly.
Wa
ist
Bel
t
Buc
kle
set
Shoul
der
Strap
Shoulde
r
Adjusta
ble
Strap
Pr.
Gau
ge
Wh
is-
tle
Glas
s
Head
Band
1 HCL
plant
2 HCL
plant
3 CL2
filling
4 CL2
filling
5 CL2
filling
6 Cl2
compre
ssor
7 Time
office
8 Time
office
9 Cell
house
10 Cell
house
11 Cell
house
12 DCS
13 Acid
plant
14 Acid
plant
15 LH2
plant
RPT/ /THE ANDHRA SUGARS LTD-SAGGONDA/APRMS/2019-20/R0 Page 56 of 52
Annexure 5 : Mock drill report
THE ANDHRA SUGARS LIMITED
Chemical & Fertilizers Division
SAGGONDA-534 318
REPORT ON THE MOCK DRILL – REHEARSING ON-SITE EMERGENCY PLAN DATED
24th APRIL, 2019
Mock drill of the On-site Emergency plan, on-field exercise was conducted in the Factory
premises on Wednesday, 24th April, 2019, during surprised visit of Dy. Chief Inspector of
factories and Inspector of factories, Eluru and witnessed the mock drill as observers.
PREPARATORY MEASURES
Prior to this mock drill, Oral information by phone from personnel manager to the key
persons on the day on ‘Emergency preparedness and response‘ arranged to line
supervisors for mock drill on chlorine and exact time will be announced later.
ACCIDENT SCENARIO
Liquid Chlorine leak from ‘OUTLET LINE OF D710’B’ STORAGE TANK.’
The following persons has participated in the Mock Drill and following rolls.
Works main controller Mr. G. Ramesh
Manager (Personnel) Mr. M. Srinivas
(Observer accompanying to Dy. chief inspector of factories)
Safety in-charge Mr. T.V. Subba Rao
Works incident controller Mr. K.V. Subba Rao
Emergency communication Mr. M. Prasannakumar
Off site Measures Mr. V.V.S. Kishore kumar
Mr. R.V.V.S.N. Murthy
Chemical Department Mr. B.V.K. Prasad
Mr. B. Malleswararao
Mechanical Department Mr. M. Durga Nagendra
Mr. L. Vasu Deva Rao
Mr. P.V. Manikanta
RPT/ /THE ANDHRA SUGARS LTD-SAGGONDA/APRMS/2019-20/R0 Page 57 of 52
Electrical Department Mr. G.U. Bhaskararao
Mr. CH.V.B.A. Siva kumar
Mr. T. Rama Mohan
Mr. M. Satish
Civil Department Mr. N. Lokesh
Search& rescue Team Mr. V. Ramakrishna
Mr. G. Elisha
Mr. K. Srinivas
Mr. MD. Alam
Electronics Mr. P. Rama Krishna
Medical Mr. Y. Mohan Kumar
Head Count Mr. N.V.V. Srinivasarao
Observers Mr. R. Prasad Kumar
Mr. B. Suresh
MOCK DRILL:
Initially instrument department people activated the chlorine sensor in chlorine storage
tanks.
Mock drill was commenced at 3.45 PM.
FIRST RESPONDENTS:
3.45 PM DCS Operating People Informed to Chlorine plant Chemist over Phone,
regarding chlorine sensor alarm sounding at Chlorine Storage Tanks.
3.46 PM DCS in-charge communicated the information to neighboring HCL plant
chemist, H2SO4 Plant chemist and hydrogen bottling people and
Department head (Works main controller), works incident controller and
Manager (Personnel) about the incident.
3.47 PM As per prior instructions of Manager (Personnel), Security staff stopped the
Vehicular traffic in side the Factory premises. Truck operators were sent to
safe area.
3.47 PM Chemist and Fitter wearing SCBA sets rushed to the Chlorine storage tanks area
to investigate location, source and size of leak.
RPT/ /THE ANDHRA SUGARS LTD-SAGGONDA/APRMS/2019-20/R0 Page 58 of 52
3.47 PM Works incident controller observed wind direction and cautioned the down
stream people.
3.52 PM Chlorine plant chemist informed the preliminary investigation details to Works
incident controller and Works main controller. Chlorine leak observed at
outlet pipe line of D710 ”B” storage tank.
WIND DIRECTION
Prevailing wind direction found towards the North-west side and likely
affected places will be Factory main gate, Time Office, lorry yard and PAC
plant etc.
3.54 PM Works main controller instructed DCS in-charge to make announcement for
all key persons to assemble at Emergency control room.
3.55 PM Announcements are made in PA system thrice stating- “Attention please,
Mock Drill, Chlorine leak at Chlorine Storage Tanks, key persons to assemble
at emergency control room located at the Hcl plant Chemist Room.”
KEY PERSONS RESPONSE
Response timings of Key persons to Emergency control room are noted.
Works Main Controller 4.00 PM A.E (Instrumentation) 3.58 PM
Safety In charge 4.00 PM J. E (Civil) 4.02 PM
A.C.E. Engineer 3.59 PM Electrical Engineer 3.58 PM
Works incident controller 3.59 PM Sr. Supervisor (Electronics) 4.00 PM
DISCUSSIONS IN EMERGENCY CONTROL ROOM:
4.02 PM Works main controller fed accurate information regarding chlorine leak to
the key persons.
4.03 PM Works main controller taken decision to bring ON-SITE EMERGENCY in to
force.
4.03 PM As per the instructions of Works main controller time keeper sounded
emergency siren.
Following decisions were derived after discussion.
Mechanical Department to try to arrest the chlorine leak.
Chemical Department to Stop the plant and arrange content transfer.
Electrical Department to provide facilities as needed by WIC.
RPT/ /THE ANDHRA SUGARS LTD-SAGGONDA/APRMS/2019-20/R0 Page 59 of 52
Electronics Department to make announcements in P.A. System.
Instrument Department to communicate information to management and
mutual aid industries.
Safety department to arrange necessary PPE’s.
PUBLIC ANNOUNCEMENT CENTRE:
Electronics supervisor started to make announcements continuously at 5 min. time
intervals regarding mock-drill and escape routes until the normalcy restored as
per instructions of works main controller.
SEARCH & RESCUE:
4.03 PM As per instructions of Manager (Personnel), Two Security guards performed
search and rescue operations. They bought one victim from chlorine storage
tanks area; first aid was given in the ambulance van and shifted the victim
to O.H.C.
PERSONNEL EVACUATION:
4.04 PM As per instructions of Manager (Personnel), Security staff started evacuation
with the help of Hand mikes from East side to the Assemble Point No-2&3
located at caustic lye loading and LH2 Plant.
4.22 PM Head counts were taken by the Time keeper 25 persons were evacuated.
Enquiries were made about the persons not found at surrounding areas.
EMERGENCY COMMUNICATION CENTRE:
4.04 PM Instrument department has set up emergency communication centre and
communicated the information to the top executives of the industry, other
units of ASL group, Mutual-aid industries and VRO & President of the neighbor
village.
ON- SITE EMERGENCY ACTIONS:
4.05 PM As per instructions of works main controller, Chlorine plant chemist and Fitter
went to the Chlorine filling points and diverted the liquid chlorine from the
common filling header to DC Header Through five empty Chlorine tonners
at a common header pressure of 9.5 Kg/cm2.
4.04 PM Works incident controller, Safety in-charge and support teams reached the
designated Base camp, East side of Chlorine storage tanks.
RPT/ /THE ANDHRA SUGARS LTD-SAGGONDA/APRMS/2019-20/R0 Page 60 of 52
4.06 PM Plant chemist and Mechanical supervisor examined the location of leak
spot.
4.07 PM Works incident controller examined the leak spot and leak severity.
4.08 PM As per instructions of works incident controller, Electrical Department
arranged a pedestal fan near the leak spot.
4.09 PM The Header pressure came down to 7.0 Kg/cm2 only, so as per instructions of
Works main controller, diversion points are increased to five numbers.
4.10 PM Then header pressure dropped to 4 Kg/cm2.
4.11 PM Mechanical people went to leak spot and removed the insulation. And
found leak spot is at horizontal pipe.
4.12 PM As per instructions of works incident controller, Mechanical people arranged
clamp to rectify the leak. Leak got controlled.
4.13 PM Works incident controller and chemist went to leak spot and examined and
found no chlorine coming out.
4.14 PM Works incident controller reported to works main controller that leak control
measures are completed.
4.15PM Civil department persons supplied few bags of lime powder for making
containment and neutralization of liquid chlorine spill.
OFF-SITE MEASURES:
4.10 PM Electrical Engineer and A.E Chemical with gas masks, Chlorine gas monitor
and walkie-talkie traveled on vehicle along the wind direction (path) to a
distance about 1.5 kilometers to estimate the off-site effects. They identified
no effect around the factory. They communicated their observations at
different places to the works main controller.
POST EMERGENCY MEASURES:
4.22 PM Works main controller and key persons reached to Chlorine Leakage area
and reviewed the accident scenario and effectiveness of the emergency
actions performed.
4.23 PM Works main controller after conforming that leak was totally controlled,
made declaration on lifting the On-site emergency.
4.27 PM Time keeper sounded ALL CLEAR siren for 30 seconds.
4.28 PM DCS in-charge made announcements twice in the PA system
RPT/ /THE ANDHRA SUGARS LTD-SAGGONDA/APRMS/2019-20/R0 Page 61 of 52
stating.“Mockdrill is over, On-site emergency is lifted and normalcy was
restored in the Factory.”
4.29 PM Evacuated plant personnel were sent back to the respective work places.
4.30 PM Vehicular movement is allowed inside the Factory.
OBSERVATIONS:
1. Time taken for preliminary investigation 07 Min.
2. Time taken for announcement after preliminary Investigation 03Min.
3. Time taken for key persons to assemble at Emergency control Room
after announcement
Works main controller 05 Min.
Works incident controller 03 Min.
Safety in charge 05 Min.
Add. C. E. E 04 Min.
Electrical Engineer 03 Min.
A.E Instrumentation 03 Min.
J.E (civil) 07 Min.
Sr. Supervisor (Electronics) 05 Min.
Time taken for rescue operation from Announcement 08 Min.
Time taken for evacuation from Announcement 09 Min.
Leak rectification work starting after observation of leak 27 Min.
Total time for all clear 45 Min.
REMARKS:
For mock drill operations 10 numbers SCBA sets were utilized
(Chemical-3 No’s, Mechanical- 3 No’s, Electrical- 2 No’s, Rescue
team- 2 No’s) and total 4 No’s of air cylinders are fully consumed and
6 no’s of air cylinders consumed partially.
10 No’s canister masks are used for this Mock Drill.
SUM-UP MEETING
At 4.50 PM Dy. Chief inspector of Factories and all the key persons and other
participants of the Mock drill were met in the Conference hall. Mock drill
performance event wise reviewed with the participants.
RPT/ /THE ANDHRA SUGARS LTD-SAGGONDA/APRMS/2019-20/R0 Page 62 of 52
Dy. Chief Inspector of Factories was mentioned that the MOCK DRILL
performance was satisfactory, co-ordination is good and it is to be further
improved to minimize the lapses and time gap.
Deputy Chief Inspector of factories gave following suggestions:
1. Sequence of mock drill to be reviewed.
2. Mock drill should be conducted in realistic way, all departments has to act as per
requirement in consultation with incident controller/main works controller to reduce
the time taken.
3. Following teams separately to be formed for meeting emergencies.
a) Rescue team
b) Fire fighting and First aid teams
d) CL2 and H2 Mitigation teams
4. Monitoring the wind direction shall be continuous and rescue operations to be done
as per it, Announcement to be done to guide people into escape routes as per it.
*********************************
Annexure 6
UPS systems with VRLA batteries require the following for safety and fire prevention.
Several accidents happened in other units resulting in huge loss of property.
-Batteries life has to be monitored and replaced as per manufacturer’s
recommendations. Normally it is of 5 years. Plant maintains separate
register for this.
Room temperature has to be 25*C. Every 5*C rise in temperature will
reduce life of batteries by half.
Regular inspection of batteries for bulging is practiced in the
plant. UPS battery stand has to be earthed.
Flame proof equipments, light, switches are to be used.
RPT/ /THE ANDHRA SUGARS LTD-SAGGONDA/APRMS/2019-20/R0 Page 63 of 52
Annexure 7 Management of change key points
Plant modification: following table provides the checklist for plant modification may
be used.
S.No Description
1.0 Design
1.1 Standard code for designing
1.2 Adequate anchoring of equipment and
structures
1.3 Process flow and PID made, necessary
changes on the existing PID is suitably
modified after Hazop
1.4 New EMP & OHS and SMP need to be
identified and addressed
1.5 Process adequacy verified
1.6 Responsibility enters for engineering data
sheet identified.
1.7 Mechanical structural design and its
adequacy checked
2.0 Electrical
2.1 Hazard classification for electrical fittings
2.2 Lock out provision
2.3 Clear access for emergency switches
2.4 Provide proper signs for switch
boards/panels
2.5 Proper grounding of the equipment
2.6 All the static electricity earthing provisions
are made
3.0 Safety regulations
3.1 Design of pressure vessel/ piping
3.2 Pressure relief devices to be provided
RPT/ /THE ANDHRA SUGARS LTD-SAGGONDA/APRMS/2019-20/R0 Page 64 of 52
3.3 Obtain test certificate from manufacturer /
competent authority
3.4 PG’s & TG’s to be fixed in proper place
3.5 Hot surfaces to be insulated
3.6 Safety interlock built in safety system are
study in conjunctions with operating /
existing system and it’s satisfactory.
4.0 Operation procedure
4.1 Explain operational procedure, safety
aspects
4.2 SOP to be prepared
4.3 Present operation manuals to be modified
5.0 Work area
5.1 Access for operation and maintenance
5.2 Free from toxic, dust or fumes
5.3 Proper colour to be done
5.4 Noise control to be ensure
5.5 Eye wash and shower provided
5.6 Adequate lighting provided
5.7 Adequate ventilation provided
5.8 Direction of flow marked
5.9 Fire extinguishers and fire hydrants
5.10 Proper drainage provided
5.11 Hand railings, stairways, wall ways
5.12 Display of proper boards
6.0 Guarding
6.1 Protection of moving parts of machine
6.2 Guards provided for transmission parts
7.0 Any other
7.1 Spare parts needs to be addressed