6 MW biomass power plant Scheme is introduced Changsha boiler plant co., LTD Hunan the machine engineering co., LTD In June 2013
Transcript

6 MW biomass power plant

Scheme is introduced

Changsha boiler plant co., LTDHunan the machine engineering co.,

LTD

In June 2013

Presenter
Presentation Notes
6MW生物质电厂 方案介绍 长沙锅炉厂有限责任公司 湖南国机工程有限公司 2013年6月

1. SummaryPlans to build a plant, the total installed one machine as a furnace, is proposed to choose 1 x 35 t/h circulating fluidized bed boiler, 1 x 6 MW condensing steam turbine generators, boiler's rated steam pressure is 3.82 MPa(g), the rated steam temperature is 450 ℃.Main building according to the three column type (across different, oxygen fuel bin across, turbine across) arrangement; Chimney tower 1, USES the reinforced concrete structure, the high 60 m.

Presenter
Presentation Notes
1.概述 拟建电厂一座,总装机为一炉一机,拟选用1×35t/h循环流化床锅炉、1×6MW凝汽式汽轮发电机组,锅炉额定蒸汽压力为3.82MPa(g),额定蒸汽温度为450℃。 主厂房按三列式(锅炉跨、除氧燃料仓跨、汽机跨)布置;烟囱1座,采用钢筋混凝土结构,高60m。

Factory set up diesel generators as a black start power source.Factory using DCS centralized control mode, improve the level of automation control.Steam turbine generator cooling water system in circulating cooling method, the water source is assumed to be taken to the nearest water.Main workshop (bent) using reinforced concrete frame structure system, the turbine housing surface using composite roofing steel sheet, steel roof overlying turbine room crane beam steel structure.

Presenter
Presentation Notes
全厂设置柴油发电机作为黑启动电源。 全厂采用DCS集中控制方式,提高自动化控制水平。 汽轮机机组冷却水系统采用循环冷却方式,水源假定为就近取用的淡水。 主厂房采用钢筋混凝土框架(排架)结构体系,其中汽机房屋面采用钢屋架上覆复合压型钢板屋面,汽机房吊车梁采用钢结构。

This engineering design, the manufacture standard USES the law of the People's Republic of China on the current national standards, rules, regulations and rules.2. The unit type selectionIn order to improve the overall thermal efficiency, unit parameters using pressure 3.43 MPa (g), temperature 435 ℃, the machine furnace selection scheme is: 1 x 35 t/h + 1 x N6MW.2.1 circulating fluidized bed boiler units 1Rated evaporation: 35 t/hCombustion mode: circulating fluidized bed

Presenter
Presentation Notes
本工程设计、制造标准采用中华人民共和国现行的国家标准、规范、规程及规定。 2.机组选型 为提高机组整体热效率,机组参数选用压力3.43MPa(g),温度435℃,机炉选型方案为:1×35t/h+1×N6MW。 2.1 循环流化床锅炉 1台 额定蒸发量: 35t/h 燃烧方式: 循环流化床

The rated steam pressure: 3.82 MPa(g)The rated steam temperature: 450 ℃2.2 steam turbine 1Model: N6-3.43power:6 MWSpeed: 3000 r/minRated into the steam pressure: 3.43 MPa(g)Admission rated temperature: 435 ℃Rated into the steam quantity: 29 t/hThe exhaust steam pressure: 0.007 MPa(a)

Presenter
Presentation Notes
额定蒸汽压力: 3.82MPa(g) 额定蒸汽温度: 450℃ 2.2汽轮机 1台 型号: N6-3.43 功率: 6MW 转速: 3000r/min 额定进汽压力: 3.43MPa(g) 额定进汽温度: 435℃ 额定进汽量: 29t/h 排汽压力: 0.007MPa(a)

3. The plant layoutAccording to the design code for China, the factory covers an area of 15000 m2, as shown in the "general layout".

Presenter
Presentation Notes
3.厂区平面布置 根据中国设计规范要求厂区总占地面积15000m2,详见《总平面布置图》。

4. The fuel system4.1 transportation fuel

Design fuel: biomass fuel 80% + 20% mixed burning bituminous coal. Boiler

fuel into the factory USES the motor transport, cutting and broken inside the

plant, biomass fuel particle size 50 mm or less when charging, charging coal

particle diameter of 13 mm or less. Into the furnace fuel conveying system

using belt conveyor automation.

Presenter
Presentation Notes
4.燃料系统 4.1燃料运输 设计燃料:80%生物质燃料+20%烟煤混烧。锅炉进厂燃料采用汽车运输,厂内切割及破碎,入炉时生物质燃料粒径≤50mm,入炉煤粒径≤13mm。进炉燃料输送系统采用皮带自动化输送。

Skiploader翻斗式装载机

Biomass fuel stock-cutte on site

Double belt conveyors will guarantee the safety and

Reliability of the boilers’ fuel supply.

Biomass fuel conveyor gallery

Before the biomass furnace feeding system

5. The main building layoutThree columns is used in the main factory building type

parallel arrangement, across the boiler, oxygen fuel bin

and across the turbine. 7.00 meters layer set boiler open

platform.

Presenter
Presentation Notes
5.主厂房布置 主厂房采用三列式平行布置方式,即锅炉跨,除氧燃料仓跨,汽机跨。7.00米层设置锅炉露天运行平台。

Biomass power plant system

6. The hydraulic system6.1 circulating water systemThis project cycle cooling water system USES machine ventilation cooling tower secondary circulating water system. Each unit configuration two machine force ventilation cooling tower and circulating pump.6.2 the boiler make-up water systemAccording to the water quality data , regulations codes and units for soda quality requirements, the power plant boiler make-up water treatment system adopts pretreatment + level of desalination + mixed ion exchanger. The whole system is divided into three parts: preprocessing part, level of desalination part and ion exchange.

Presenter
Presentation Notes
6.水工系统 6.1循环水系统 本工程循环冷却水系统采用带机力通风冷却塔的二次循环供水系统。每台机组配置两座机力通风冷却塔和循环水泵。 6.2锅炉补给水系统 根据水质资料、规定规程及机组对汽水品质的要求,电厂的锅炉补给水处理系统采用预处理+一级除盐+混合离子交换器。整个系统分为三大部分:预处理部分、一级除盐部分及离子交换部分。

7.电气系统Electric Power System

根据业主及当地条件设置According to owner and local

conditions.

8. The thermal control systemBoiler, turbine and generator controlled by distributed control system (DCS), fuel pump, water pump, air compressor station is included in the DCS control system.Turbine DEH and turbine ETS will vary depending on the turbine ontology. Through communicate with the DCS or hard wiring way.Auxiliary workshop: water treatment system, cooling water system, feeding system, ash and slag system adopt PLC control, through the communication with DCS.Factory set up a centralized control room, centralized monitoring unit machine furnace electricity and utility system. Adopt LCD, keyboard and mouse to monitoring unit and the utility system.

Presenter
Presentation Notes
8.热工控制系统 锅炉、汽机、发电机采用分散控制系统(DCS)控制,燃油泵房、综合水泵房、空压站系统也纳入DCS控制。 汽轮机DEH及汽轮机ETS将随汽机本体供货.通过通讯或硬接线方式与DCS连接。 辅助车间:化水处理系统、冷却水系统、给料系统、除灰、除渣系统均采用PLC控制,通过通讯与DCS连接。 全厂设置一个集中控制室,集中监控机组机炉电及公用系统。采用LCD、键盘和鼠标实现对机组及公用系统的监控。

9. Civil engineering systemsMain factory buildings and other structures include: main workshop, induced draft fan for boiler, steam turbine generator pedestal, chimneys, stents, the flue, etc.Turbine room, oxygen coal (bent) using reinforced concrete frame structure system. Turbine housing surface adopts the steel roof truss, overlaying composite roofing steel sheet; Other floors, roof adopts the cast-in-place reinforced concrete beam and slab structure; Turbine room crane beam steel structure; Turbine base for the cast-in-situ reinforced concrete structure. Setting deformation joint between boiler furnace frame and main workshop, make two completely separated from the mechanical system.

Presenter
Presentation Notes
9.土建系统 主厂房建筑及构筑物包含:主厂房、锅炉基础、汽轮发电机基座、烟囱、引风机支架、烟道支架等。 汽机房、除氧煤仓间采用钢筋混凝土框架(排架)结构体系。汽机房屋面采用钢屋架,上覆复合压型钢板屋面;其它楼层、屋面均采用现浇钢筋混凝土梁板结构;汽机房吊车梁采用钢结构;汽机基座为现浇钢筋混凝土结构。锅炉炉架与主厂房之间设置变形缝,使两者受力体系完全分开。

Auxiliary system architecture include:1) hydraulic and water system building and structures:Including foundation of integrated water purifier, clear water reserviors, comprehensive water pump house, boiler make-up water treatment workshop, industrial waste water treatment station, outdoor unit sink, water and wastewater facilities etc.;2) electrical system architecture and structures, including outdoor substation, the lightning rod, etc.;3) fuel systems and structures, including fuel conveying trestle, library, etc.;4) affiliated buildings: including maintenance workshop and warehouse, guards, etc.

Presenter
Presentation Notes
辅助系统建筑将采用钢筋混凝土框架结构或砌体和钢筋混凝土混合结构。辅助系统建筑包括: 1)水工及化水系统建筑及构筑物: 包括一体化净水器基础、清水池、综合水泵房、锅炉补给水处理车间、工业废水处理站、机组排水槽、化水及废水室外设施等; 2)电气系统建筑及构筑物:包括室外变电站基础、避雷针基础等; 3)燃料系统及构筑物:包括燃料输送栈桥、燃料库等; 4)附属建筑:包括检修车间及材料库、门卫等。

10、temperature medium voltage biomass in 35 t/h CFB boiler is introduced10.1, boiler main parameters and performance indicators10.2 overall overview, biomass circulating fluidized bed boiler10.3 main technical characteristics, boiler

Presenter
Presentation Notes
10、35t/h中温中压生物质CFB锅炉介绍 10.1、锅炉主要参数及性能指标 10.2、生物质循环流化床锅炉总体概述 10.3、锅炉主要技术特点

10.1, boiler main parameters and performance indicatorsRated evaporation: 35 t/hThe rated steam pressure: 3.82 MPaThe rated steam temperature: 450 ℃The rated water temperature: 104 ℃Exhaust temperature: 150 ℃The design heat efficiency: 88.5%Cold air temperature :30 ℃A hot blast temperature :150 ℃Secondary air temperature :150 ℃Design fuel: biomass fuel (moisture content 35% or less) 80% + 20%

mixed burning bituminous coalFuel consumption: biomass fuel 20 t/h

Bituminous coal 6 t/hRunning layer level: 7000 mm

Presenter
Presentation Notes
10.1、锅炉主要参数及性能指标 额定蒸发量: 35t/h 额定蒸汽压力: 3.82MPa 额定蒸汽温度: 450℃ 额定给水温度: 104℃ 排烟温度: 150 ℃ 设计热效率: 88.5% 冷风温度 30 ℃ 一次热风温度 150℃ 二次热风温度 150 ℃ 设计燃料:生物质燃料80% (水分≤35%)+掺烧烟煤20% 燃料消耗量:生物质燃料 20t/h 烟煤 6t/h 运转层标高:7000mm

Boiler allows you to load the adjusting range is: 50-100%Boiler dimension:Width (boiler steel frame centerline) 4540 mm (including platform width 8420 mm)Depth (boiler steel frame centerline) 11580 mm (including platform depth 14200 mm)Height (drum center level) 28000 mm (including the canopy height 32998 mm)Fuel to adapt to the situation:1, can be fully burning biomass (biomass fuel moisture content 35% or less, but the runtime needs to join the cycle Material (loop material particle size of 0 ~ 1 mm, the moisture content < 10%), circulation material is recommended:Kaolin, clay, coal ash, etc.;2, can be fully developed bituminous coal, lean coal and lignite.Fuel particle degree requirements:The largest biomass fuel particles require 50 mm or less (charging before bark, waste wood and so on need to be broken,Twigs, straw, etc need to shear);Coal granularity requires 13 mm or less. Grain size distribution of coal proportion is: 1 mm below 25%,1-5 mm (60%), 5-13 mm (15%).

Presenter
Presentation Notes
锅炉允许的负荷调节范围:50-100% 锅炉外形尺寸: 宽度(锅炉钢架中心线) 4540 mm(包括平台宽度 8420mm) 深度(锅炉钢架中心线) 11580 mm(包括平台深度 14200mm)高度(汽包中心标高) 28000mm(包括防雨棚高度 32998mm) 燃料适应情况: 1、可全燃生物质燃料(生物质燃料水分≤35%),但运行时需加入循环物料(循环物料粒径为0~1mm ,含水率<10%),循环物料推荐使用:高岭土、粘土、煤灰渣等 ; 2、可全燃烟煤、褐煤、贫煤。 燃料颗粒度要求: 生物质燃料最大颗粒要求≤50mm(入炉前树皮、废木块等需破碎,树枝、秸秆等需剪切); 燃煤颗粒度要求≤13mm。煤的粒度级分配比例为:1mm以下占25%,1-5mm占60%,5-13mm占15%)。

10.2 overall overview, biomass circulating fluidized bed boilerTemperature in the boiler for medium voltage parameters, single drum, natural circulation, island type is decorated, all steel bearing combination of circulating fluidized bed boiler.Boiler using high temperature heat insulation volute cyclone separator gas-solid separation, operating floor elevation is 7000 mm.Boiler steel frame is composed of three spans, first across the chamber, the second span arrangement of high temperature insulation volute cyclone separator, feed back,The third cross layout tail flue - superheater, economizer and air preheater.Furnace membrane type water wall structure used to decorate in the upper chamber of a stove or furnace along the width direction of the three high temperature superheated steam screens and 2 chip water-cooling panel.For water cotton gauze wind plate at the bottom of the furnace and water cooling chamber; With water cooling bed room is connected to a duct layout 2 oil ignition burner,Used to start the ignition boiler.Boiler adopts front wall concentrated feeding method, at the bottom of the front wall water wall uniform arrangement of two biomass fuel feeding mouth, at its center placement one for coal over ( can be added as recycling material).

Presenter
Presentation Notes
10.2、生物质循环流化床锅炉总体概述 锅炉为中温中压参数、单汽包自然循环、岛式布置、全钢架支吊结合的循环流化床锅炉。 锅炉采用高温绝热蜗壳旋风分离器进行气固分离,运转层标高为7000mm。 锅炉本体钢架由三跨组成,第一跨布置炉膛,第二跨布置高温绝热蜗壳旋风分离器、返料器,第三跨布置尾部烟道—过热器、省煤器、空预器。 炉膛采用全膜式水冷壁结构,在炉膛上部沿宽度方向布置3片高温过热蒸汽屏和2片水冷屏。炉膛底部为水冷布风板和水冷风室;在与床下水冷风室相连的一次风道上布置2台油点火燃烧,用于锅炉启动点火。 锅炉采用前墙集中给料方式,在前墙水冷壁下部均匀布置二个生物质燃料给料口,在其中心位置布置一个给煤接管(可作循环物料加入口)。 布风板上设置三个排渣口,其中中间一个作为事故放渣以及停炉检修时使用。 两台蜗壳高温绝热旋风分离器位于炉膛出口和尾部竖井烟道之间,左右旋风分离器的下方各布置一台设有水冷料腿的返料器,返料器将旋风分离器分离下来的物料送回炉膛。 尾部竖井烟道依次布置了低温过热器、省煤器和空气预热器受热面,并在每级受热面进口端设置脉冲吹灰系统。过热器系统中设有一级喷水减温器。 锅炉采用两级配风,一次风从炉膛底部通过布风板进入炉膛,二次风分别从前后墙进入炉膛。 锅炉整体呈左右对称布置,支吊在锅炉钢架上。锅炉启动床料为煤灰渣。

Ventilation board set on three discharge mouth, one in the middle used as slag and the furnace overhaul accident.A volute cyclone separator are high temperature heat insulation between the furnace exit and the tail shaft flue, a down to the bottom of the cyclone separator feeder is equipped with water-cooled dipleg of return, return feeder cyclone separation material back to the furnace.Tail shaft flue arrangement in order of low temperature superheater,economizer and air preheater heating surface, and at every level of heating surface inlet side pulse blowing system. Superheater is equipped with level 1 water spray attemperator in the system.Boiler adopts two levels with the wind, a wind from the bottom of the furnace through ventilation plate into the chamber, secondary air enters the furnace to once upon a time back wall respectively.Boiler left and right sides is symmetrical arrangement on the whole, bearing on the boiler steel frame. Boiler startup bed material for coal ash.

10.3 main technical characteristics, boiler1, the chamber of a stove or furnace adopts full membrane type water wall structure, reliable sealing;2, adopt efficient volute inlet cyclone separator, high separation efficiency,Material circulation is smooth, not accumulation, cycle less material to join;3, overheated furnace water-cooled panel layout and screen, reduce screen dust, to reduce the temperature, reduce the bedThe possibility of high temperature anti-coking;4, continuous stable biomass feeding system;5, load adjustment than large, fuel wide adaptability;6, reliable wear design structure;7, set many years of CFB boiler design and manufacturing experience, guarantee of the boiler dhi sex good, strong security, high boiler efficiency;8, advanced management, good quality, excellent after-sales service.

Presenter
Presentation Notes
10.3、锅炉主要技术特点 1、炉膛采用全膜式水冷壁结构,密封可靠; 2、采用高效蜗壳式进口旋风分离器,分离效率高,物料循环顺畅、不堆积,循环物料加入少; 3、炉内布置水冷屏和过热屏,降低屏积灰、降低炉温,减少床料高温结焦的可能性; 4、连续稳定的生物质给料系统; 5、负荷调节比大,燃料适应性广; 6、可靠的防磨设计结构; 7、集多年CFB锅炉的设计和制造经验,保证锅炉的经济性好、安全性强、锅炉效率高; 8、先进的管理,良好的质量,优质的售后服务。

Thanks!