Date post: | 08-May-2023 |
Category: |
Documents |
Upload: | khangminh22 |
View: | 0 times |
Download: | 0 times |
Warehouse Demolition Project Manual
Woodswether Terminal
Warehouse Demolition Project
Revision 0 January 27, 2017
2 | P a g e
Port KC – Warehouse Demolition – Woodswether Terminal
January 27, 2017
DIVISION 00
CONTRACTING REQUIREMENTS
3 | P a g e
Port KC – Warehouse Demolition – Woodswether Terminal
January 27, 2017
Section 000006
Table of Contents
4 | P a g e
Port KC – Warehouse Demolition – Woodswether Terminal
January 27, 2017
TABLE OF CONTENTS
Page Page
DIVISION 00 – CONTRACTING REQUIREMENTS
Document
0 000006 Table of Contents 3 thru 6
0 002200 Instructions to Bidders 7 thru 10
0 004100 Bid Form 11 thru 12
DIVISION 01 – GENERAL REQUIREMENTS
0 Section 011100 Summary of Work 14 thru 16
0 Appendix
011100
Scope of Work Matrix 17 thru 19
0 Section 013100 Project Coordination and Meetings 20 thru 23
0 Section 013300 Submittals 24 thru 26
0 Section 013529 Safety and Emergency Response 27 thru 33
0 Section 014200 Definitions and Standards 34 thru 42
0 Section 015300 Temporary Barriers and Controls 43 thru 47
0 Section 015600 Temporary Utilities and Facilities 48 thru 54
0 Section 017800 Contract Closeout 55 thru 58
DIVISION 02 – EXISTING CONDITIONS
0 Section 024100 Demolition 60 thru 69
0 Section 025100 Materials and Waste Management 70 thru 78
0 Section 025500 Regulated and Hazardous Material
Transport
79 thru 82
0 Section 028200 Asbestos Abatement 83 thru 88
5 | P a g e
Port KC – Warehouse Demolition – Woodswether Terminal
January 27, 2017
CONTRACT DRAWINGS
Drawing No. Rev Drawing Title
1 Site Plan
2 Pictures
3 Pictures
4 Pictures
5 Pictures
6 | P a g e
Port KC – Warehouse Demolition – Woodswether Terminal
January 27, 2017
REFERENCE DOCUMENTS
Exhibit Title
A Phase I Pre-Demo Asbestos and Haz. Material Survey Report
B
Asbestos and Hazardous Materials Survey Report (dated 01/20/2017)
Port KC - As-Built Plans (dated 01/20/2017)(dated 01/12/1999)
7 | P a g e
Port KC – Warehouse Demolition – Woodswether Terminal
January 27, 2017
Section 002200
Instructions to Bidders
8 | P a g e
Port KC – Warehouse Demolition – Woodswether Terminal
January 27, 2017
SECTION 002200 – INSTRUCTIONS TO BIDDERS
1.0 DECLINATION TO BID
1.1 Immediately advise of intent to decline bidding, and please specify reasons for declination,
and return all Bid Documents to PORT KC.
2.0 GENERAL INFORMATION
2.1 Request For Proposal: Warehouse Building Demolition and Site Stabilization Project –
2.2 The Bid proposal solicited herein is for a contract to be awarded by PORT KC for
Construction Services as described in the attached bid documents. A sample PORT KC
Contract Agreement has been provided for reference for the Bidder.
2.3 Project General Description:
• Provide all labor, materials, and equipment required to provide the construction
services described within the approved plans and specifications.
2.4 These Instructions to Bidders shall govern the submission of Bid proposals. It is the
Bidder’s responsibility to read this entire document; review the Request for Proposal
(RFP) and all enclosures, attachments, and Bid Documents; and to comply with all
requirements specified herein. Proposals that do not conform to these instructions may be
considered as non-compliant or non-responsive.
2.5 In the event of a conflict between this Instructions to Bidders and the Request for Proposal
(RFP), the more stringent shall apply.
3.0 BID PRICING
3.1 Bidder's PRICE shall include all costs associated with providing and maintaining
insurance in accordance with PORT KC's Insurance Requirements as indicated by the
Contract Agreement attached.
3.2 Bidder shall include in its pricing all bonding requirements stipulated in the RFP.
3.3 Bidder shall NOT include sales and/or use taxes in its PRICE.
3.4 Bidder's PRICE shall include costs for setting up its equipment including all incidentals
required to safely operate and maintain equipment as required to accomplish the
intended task, and that may be required for stability of such equipment.
3.5 Bidder shall submit its proposal pricing utilizing PORT KC's Bid Form and Bid Price
Breakdown form.
3.6 Bid Pricing must be valid for sixty (60) days after the Bid Due Date.
4.0 BID DATES
4.1 RFP Issue: Monday, January 30, 2017
4.2 Pre-bid meeting at the terminal: Thursday, February 2, 2017 at 9 a.m. CST. This is
- Woodswether Terminal
9 | P a g e
Port KC – Warehouse Demolition – Woodswether Terminal
January 27, 2017
a mandatory meeting for all bidders.
4.3 Last date for questions or Requests for Information submitted to PORT KC regarding this
solicitation is: Tuesday, February 7, 2017 by 5:00 p.m. CST. Responses will be issued
to bidders no later than Wednesday, February 8, 2017 by 3:00 p.m. CST.
4.4 Bids Due: Friday, February 10, 2017 by 1:00 p.m. CST
4.4.1 Only bid submissions received on or before the bid due date and time will be
considered. Please advise immediately if unable to meet this requirement.
4.5 Bid Opening: Friday, February 10, 2017 at 1:30 p.m. CST
5.0 BID SUBMISSION
5.1 PORT KC is not responsible for any costs or expenses in preparing and/or submitting this
Bid proposal.
5.2 Bid submission must include, at a minimum, the following fully executed documents (see
also the Bid Documents section):
5.2.1 PORT KC’s Bid Form.
5.2.2 PORT KC’s Addenda Confirmation Form.
5.3 All Bidders must have previously submitted Qualification data acceptable to PORT KC
for their Bids to be accepted.
5.4 Should Bidder have any value-added proposals of ways to save costs, shorten schedule,
or otherwise make the project more successful, these should be included as additional line
items in their proposals, but the provided Bid Forms must be completed for the WORK as
specified.
6.0 CONTACTS
6.1 Should Bidder find discrepancies or omissions in the Bid Documents, or should their intent
be unclear or ambiguous, Bidder must notify PORT KC of issue in writing. PORT KC
will not be bound by, and Bidder must not rely on, any oral interpretations or clarifications
of the Bid Documents.
6.2 Any and all bid questions shall be submitted to [email protected].
7.0 SUPPLEMENTAL INFORMATION FOR BIDDERS
7.1 Terms utilized in this Instructions to Bidders and Bid Documents shall be as commonly
defined or the meaning specifically assigned in any Bid Document.
7.2 All Bid Documents received as part of this bid solicitation are the sole property of PORT
KC and are intended solely for the WORK proposed herein.
7.3 No license or grant for any other use of the Bid Documents is extended.
8.0 MILESTONE SCHEDULE
8.1 Anticipated Notice To Proceed: Wednesday, February 22, 2017
8.2 Contractor shall coordinate all activities with site operator to minimize impact to PORT
KC ongoing operations.
8.3 Demolition complete and Port KC property cleared of all debris on or before April 30,
Monday, February 6, 2017
2017.
10 | P a g e
Port KC – Warehouse Demolition – Woodswether Terminal
January 27, 2017
9.0 REJECTION OF BIDS
9.1 PORT KC reserves the right to reject any or all Bids, waive any formality in bidding or
award only selected portions of the WORK.
9.2 By submitting a Bid proposal, Bidder acknowledges and agrees that PORT KC can reject
work for the reasons noted, or any reason, and that Bidder shall not seek any recourse of
any kind against PORT KC due to rejections.
10.0 EXCEPTIONS TO BID
10.1 The base Bid shall conform in all respects with the Request for Proposal (RFP).
10.2 Notices of discrepancies, omissions or clarifications must be in writing.
10.3 Alternate proposal(s) may be offered for PORT KC’s consideration, provided the
requested base WORK Bid proposal is submitted and all deviations or exceptions are
separately listed for the Alternate Bid Proposal.
10.4 Price(s) may be offered for PORT KC’s consideration, based upon lower-tier
subcontracting any or all portions of the WORK, provided that the bid proposal gives the
names and locations of each lower-tier subcontractor and a complete description of
WORK to be sub-subcontracted.
END OF SECTION 002200
11 | P a g e
Port KC – Warehouse Demolition – Woodswether Terminal
January 27, 2017
Section 004100
Bid Form
12 | P a g e
Port KC – Warehouse Demolition – Woodswether Terminal
January 27, 2017
SECTION 004100 – BID FORM
NOTE: For Iinvitations for Bids, the terms "Offer" and "Offeror" shall mean "Bid" and " Bidder" respectively; and for Requests for Proposal, the terms "Bid" and "Bidder"
shall mean Offer and "Offeror", respectively, in this solicitation and any associated exhibits. Bids must be submitted on all quantities specified on this schedule.
NAME & TITLE OF OFFEROR'S REPRESENTATIVE: __________________________________________________________________________________________ (print or type)
NAME OF OFFEROR: ________________________________________________________________________________________________________________ (print or type)
SIGNATURE: _________________________________________________________________________________________________ DATE: _______/_______/________
ITEM
NO.DESCRIPTION UNIT
QTY
(EST.)
UNIT PRICE
$
EXTENDED PRICE
$
001 Demolish and Remove Existing Warehouse Building Structure LS 1
SUBTOTAL
MOBILITATION
PERFORMANCE AND PAYMENT BOND
TOTAL BID
Port KC - Woodswether Terminal
Warehouse Demolition and Removal
BID SCHEDULE
The Offeror is required to Sign and Date Each Page of the Schedule
Submit All Pages with the Offer
MOBILIZATION
13 | P a g e
Port KC – Warehouse Demolition – Woodswether Terminal
January 27, 2017
DIVISION 01
GENERAL
REQUIREMENTS
14 | P a g e
Port KC – Warehouse Demolition – Woodswether Terminal
January 27, 2017
Section 011100
Summary of Work
15 | P a g e
Port KC – Warehouse Demolition – Woodswether Terminal
January 27, 2017
DIVISION 1 - GENERAL REQUIREMENTS
SECTION 011100 - SUMMARY OF WORK
PART 1 - GENERAL
1.1 SUMMARY
A. The Port Authority of Kansas City (Port KC) is seeking qualified contractors to demolish
and remove an abandoned warehouse at their Woodswether Terminal located at 400 State
Street, Kansas City, Missouri.
B. The Work consists of the environmental remediation, asbestos abatement,
decommissioning, and demolition of all building components, foundations, associated
equipment, and all required civil Works necessary to completely remove the building and
associated elements from the site.
1.2 SITE DESCRIPTION
A. The Work includes asbestos abatement, removal and disposal of regulated materials
including universal wastes. The Work consists of demolition and complete removal of an
old warehouse structure that has not been in service for many years. Items to be
demolished and removed or otherwise noted include, but are not limited to the following:
1. Warehouse building structure with an approximate area of 28,000 square feet. The
entire building structure and miscellaneous attachments from the concrete
floor/foundation up shall to be removed.
2. The elevated concrete floor slab/foundation shall be demolished and completely
removed. The concrete piers shall not be demolished and shall remain in place.
Cut all concrete piers to a height 2 feet below the existing surrounding grade. All
reinforcing steel shall be cut flush with the final top of concrete pier.
3. All mechanical and electrical equipment associated with the building.
4. Structural steel to an elevation 2 feet below the existing surrounding grade.
5. Below grade conveyor structure and all associated mechanical and electrical
equipment.
6. All underground utility lines within 5 feet of building footprint.
7. Remove all existing debris under the elevated floor slab.
B. Several items will remain as part of the Work (See Contract Drawings) including the
following:
1. Railroad tracks beyond 5 feet from building footprint.
2. Pavement beyond 5 feet from building footprint.
3. Active and charged water lines and fire hydrants shall be protected in place.
16 | P a g e
Port KC – Warehouse Demolition – Woodswether Terminal
January 27, 2017
3. Active and charged water lines and fire hydrants shall be protected in place.
1.3 SITE LIMITATIONS
A. The Port KC Woodswether Terminal is located within the flight path of the Charles B
Wheeler Downtown Airport and has a crane height restriction for the entire property. .
Port KC has an FAA approved crane permit on file with the airport for the entire
Woodwether Terminal property for any type of crane as long as it does not exceed a
height of 70 feet above exiting ground. The contractor shall conduct all Work in
accordance with this permit.
1.4 UNIT PRICE
A. Contractor included unit prices for additional services as outlined in the Bid Form and
Schedule of Values. These unit prices include all labor, materials, equipment, permitting,
transportation and disposal fees (if applicable), etc. to complete the activity based on the
unit identified.
1.5 SCRAP CREDIT
A. No scrap credit is requested for this project.
1.6 CODES AND STANDARDS
A. All Work and Services provided in the Project shall be in accordance with Applicable
Law.
PART 2 - PRODUCTS - NOT APPLICABLE.
PART 3 - EXECUTION - NOT APPLICABLE
END OF SECTION 011100
4. Overhead electric power lines serving adjacent storage dome structure.
existing ground.
17 | P a g e
Port KC – Warehouse Demolition – Woodswether Terminal
January 27, 2017
Appendix 011100
Scope of Work Matrix
18 | P a g e
Port KC – Warehouse Demolition – Woodswether Terminal
January 27, 2017
APPENDIX 011100 – SCOPE OF WORK MATRIX
This list is not intended to be an all-inclusive list of the Contractor’s Work. Contractor is
responsible for following the specifications and requirements outlined throughout the
Contract Documents.
Notes:
1. “Removal” shall include proper handling, storage, transportation and disposal.
WORK DESCRIPTION
Responsibility
By
Owner
By
Contractor
1.
Relocation of existing electric service to warehouse
building and adjacent buildings.
◆
5. De-energization of all electrical power to warehouse
prior to any structural demolition work. ◆
6.
Confirmation of electrical system de- energization from
warehouse prior to any demolition work.
◆
10. Removal of all building and exterior light fixture ballasts
and bulbs (i.e., universal wastes).
◆
11. Removal of all light poles and foundations connected to
or associated with warehouse.
◆
12. Removal of mercury containing circuitry including relay
panels, switches, etc.
◆
13. Removal of any remaining office equipment and
supplies not removed by Owner.
◆
14.
Removal of all chemical containers, chemical and oil
drums, totes, compressed gas cylinders and other like
◆
Contact utility companies to shut off all active utilities
serving warehouse building.
◆
16.
Cut to grade, cap and abandon in place all below ground
utilities within 5 feet of building footprint.
◆
17. Removal of any remaining maintenance tools and tool
racks not removed by Owner.
◆
18.
Removal of all remaining bulk and piece maintenance
materials (flat stock, pipe, cable, etc.) and material racks
◆
22. Removal of all mechanical equipment to existing
surrounding grade.
◆
23.
Removal of all above-ground electrical equipment and
cabling, and aboveground raceways, unless otherwise
stated herein. Confirm system de- energization by
Owner prior to removal.
◆
APPENDIX 011100 – SCOPE OF WORK MATRIX
This list is not intended to be an all-inclusive list of the Contractor’s Work. Contractor is
responsible for following the specifications and requirements outlined throughout the
Contract Documents.
Notes:
1. “Removal” shall include proper handling, storage, transportation and disposal.
WORK DESCRIPTION
Responsibility
By
Owner
By
Contractor
1. Relocation of existing electric service to warehouse
building and adjacent buildings.
◆
2. De-energization of all electrical power to warehouse
prior to any structural demolition work. ◆
3. Obtain demolition permit from KCMO. Obtain othe
permits required to progress work as needed.
◆
4. Confirmation of electrical system de- energization from
warehouse prior to any demolition work.
◆
5. Removal of all building and exterior light fixture ballasts
and bulbs (i.e., universal wastes).
◆
6. Removal of all light poles and foundations connected to
or associated with warehouse.
◆
7. Removal of mercury containing circuitry including relay
panels, switches, etc.
◆
8. Removal of any remaining office equipment and
supplies not removed by Owner.
◆
9. Removal of all chemical containers, chemical and oil
drums, totes, compressed gas cylinders and other like
containers prior to Work.
◆
10. Contact utility companies to shut off all active utilities
serving warehouse building.
◆
11. Cut to grade, cap and abandon in place all below ground
utilities within 5 feet of building footprint.
◆
12. Removal of any remaining maintenance tools and tool
racks not removed by Owner.
◆
13. Removal of all remaining bulk and piece maintenance
materials and material racks not removed by Owner.
◆
14. Removal of all mechanical equipment to existing
surrounding grade.
◆
19 | P a g e
Port KC – Warehouse Demolition – Woodswether Terminal
January 27, 2017
WORK DESCRIPTION
Responsibility
By
Owner
By
Contractor
24.
Removal of all control equipment, panels, monitors,
instruments, instrument cabling, and raceways.
◆
25.
Removal of all above-ground piping, plumbing piping
and fixtures, tubing, insulation and supports.
◆
27.
Removal of all architectural elements (roofing, siding,
windows, doors, door hardware, window and door
frames, etc.).
◆
28. Removal of all structural steel from buildings, structures,
etc.
◆
29. Removal of all fixed lift devices (elevators, cranes, crane
rails, trolley beams, loading dock lifts, hydraulics, etc.).
◆
30.
Removal of existing above-grade exterior slabs,
footings, and supports within the Work limits to match
the existing surrounding grade.
◆
31. Removal of existing interior equipment pedestals,
equipment containment structures, containment curbs, in
◆
32.
Removal and proper disposal of non-concrete building
walls and vertical building partitions above the existing
lowest slabs inside all buildings within the Work limits.
◆
36.
Removal of all Regulated Materials (e.g., mercury;
universal wastes; PCB impacted paints, caulk, oils, lead
impacted soils, oil impacted soils, etc.) present at the
◆
37. Prepare Stormwater Pollution Prevention plan and
obtain a construction stormwater permit, as necessary
◆
38.
Meet requirements of the Construction Storm Water
Permit and Storm Water Pollution Prevention Plan
(SWPPP).
◆
39. Responsibility for project site security and safety during
the Work.
◆
END OF APPENDIX 011100
WORK DESCRIPTION
Responsibility
By
Owner
By
Contractor
15. Removal of all above-ground electrical equipment and
cabling, and aboveground raceways, unless otherwise
stated herein. Confirm system de- energization by
Owner prior to removal.
◆
16. Removal of all control equipment, panels, monitors,
instruments, instrument cabling, and raceways.
◆
17. Removal of all above-ground piping, plumbing piping
and fixtures, tubing, insulation and supports.
◆
18. Removal of all architectural elements (roofing, siding,
windows, doors, door hardware, window and door
frames, etc.).
◆
19. Removal of all structural steel from buildings, structures,
etc.
◆
20. Removal of all fixed lift devices (elevators, cranes, crane
rails, trolley beams, loading dock lifts, hydraulics, etc.).
◆
21. Removal of existing above-grade exterior slabs,
footings, and supports within the Work limits to match
the existing surrounding grade.
◆
22. Removal of existing interior equipment, equipment
containment structures, containment curbs or walls
within building or below floor/foundation.
◆
23. Removal and proper disposal of concrete building
floor/foundation.
◆
24. Removal of all Regulated Materials (e.g., mercury;
universal wastes; PCB impacted paints, caulk, oils, lead
impacted soils, oil impacted soils, etc.).
◆
25. Prepare Stormwater Pollution Prevention plan and
obtain a construction stormwater permit, as necessary.
◆
26. Meet requirements of the Construction Storm Water
Permit and Storm Water Pollution Prevention Plan
(SWPPP).
◆
27. Responsibility for project site security and safety during
the Work.
◆
END OF APPENDIX 011100
20 | P a g e
Port KC – Warehouse Demolition – Woodswether Terminal
January 27, 2017
Section 013100
Project Coordination
and Meetings
21 | P a g e
Port KC – Warehouse Demolition – Woodswether Terminal
January 27, 2017
SECTION 013100 - PROJECT COORDINATION AND MEETINGS
PART 1 - GENERAL
1.01 SUMMARY
A. This Section includes administrative provisions for coordinating construction
operations on Project including, but not limited to, the following:
1. Project meetings.
2. Requests for information (RFIs).
B. Related Work Specified Elsewhere:
1. For preparing and submitting Contractor's construction Progress Schedule:
SECTION 013200.
2. For Submittal Requirements: SECTION 013300.
3. For coordinating closeout of the Contract: SECTION 017800.
1.2 DEFINITIONS
A. The meanings for all defined terms are identified in Section 014200.
1.3 PROJECT MEETINGS
A. Pre-Demolition Conference:
1. Owner’s Representative will conduct a meeting prior to Mobilization and
within 10 Days after the Notice to Proceed date, to review items stated in
the following agenda and to establish a working understanding between the
parties as to their relationships during performance of the Work.
2. Pre-Demolition conference shall be attended by:
a. Representative(s) of Contractor including Contractor’s Superintendent
and Site Safety Officer.
b. Representative(s) of Owner.
c. At Owner's option, representatives of principal Subcontractors and
Suppliers.
3. Meeting Agenda:
a. Construction Schedules.
b. Sequencing of Critical Path Activities.
c. Designation of Key Personnel and their duties; lines of communication.
d. Demolition Permit
e. Environmental Compliance.
f. Utility coordination, turn off, and procedures for disconnect.
g. Health and Safety, first-aid.
22 | P a g e
Port KC – Warehouse Demolition – Woodswether Terminal
January 27, 2017
h. Procedures for testing.
i. Temporary utilities.
j. Traffic Control.
k. Security.
l. Disposal site and approved permit.
m. Deliveries of Equipment and Materials.
4. Location of Meeting: Port KC offices.
5. Reporting:
a. Within three working days after the meeting, the Owner’s
Representative will prepare and distribute minutes of the meeting to
Owner and Contractor.
b. Contractor shall provide copies to Subcontractors and major Suppliers.
B. Construction Progress Meetings:
1. Contractor will at a minimum conduct weekly site meetings and at other times
as requested by Owner to discuss progress. Representatives of Owner and
Contractor shall be present at each meeting. With Owner's and Owner’s
Representative’s concurrence, Contractor may request attendance by
representatives of Subcontractors, Suppliers, or other entities concerned
with current program or involved with planning, coordination, or
performance of future Activities. Owner or Owner’s Representative may
request participation by Subcontractors, Suppliers or others to participate in
these meetings. All participants in the meeting shall be familiar with the
Project and authorized to conclude matters relating to the Work.
2. Contractor and each Subcontractor represented shall be prepared to discuss
the current construction progress report and any anticipated future changes
to the Schedule. Each Subcontractor shall comment on the Schedules of
Contractor and other Subcontractors and advise if their current progress or
anticipated Activities are compatible with that Subcontractor's Work.
3. Meeting Agenda:
a. Review of construction progress since previous meeting.
b. Field observations, interface requirements, conflicts.
c. Issues which may impede construction Schedule.
d. Hours of Work.
e. Hazards and risks.
f. Environmental report (waste characterization, permitting, transport,
disposal)
g. Housekeeping.
h. Corrective measures and procedures to regain construction Schedule if
necessary.
23 | P a g e
Port KC – Warehouse Demolition – Woodswether Terminal
January 27, 2017
PART 2 - PRODUCTS - NOT APPLICABLE.
PART 3 - EXECUTION - NOT APPLICABLE.
END OF SECTION 013100
24 | P a g e
Port KC – Warehouse Demolition – Woodswether Terminal
January 27, 2017
Section 013300
Submittals
25 | P a g e
Port KC – Warehouse Demolition – Woodswether Terminal
January 27, 2017
SECTION 013300 – SUBMITTALS
PART 1 - GENERAL
1.1 PRE-WORK SUBMITTALS
A. Contractor shall issue the following submittals to, and ensure ample review time for,
Owner and Owner’s Representative.
Submittal
After Notice of
Award. Pre-
Mobilization
After Notice to
Proceed. Prior
to Start of Work
Site-Specific Health and Safety Plan (the “Safety
Plan”) ✓
Execution Plan / Permit Requirements
(Applications, Work Plans etc.) ✓
Spill Control Plan ✓
SWPPP Implementation Plan ✓
Dust Control Plan ✓
Dewatering Plan ✓
Traffic and track-out Control Plans ✓
Permits and Notifications ✓
Emergency Plan ✓
Waste Management Plan ✓
Safety Data Sheets (SDS) ✓
Project Schedule ✓
Executed Contract including Schedule of Values ✓
Performance and Payment Bond ✓
Certificate of Insurance ✓
1.2 WORK SUBMITTALS
A. Contractor shall issue the following submittals to Owner and Owner’s Representative
during the Work.
Submittal
After Notice of
Award. Pre-
Mobilization
After Notice to
Proceed. Prior
to Start of Work
Site-Specific Health and Safety Plan (the “Safety
Plan”) ✓
Execution Plan (Demolition Plan, HazMat /
Asbestos Abatement Plan), including Permit
Requirements (Applications, Work Plans etc.)
✓
Spill Control Plan ✓
SWPPP Implementation Plan ✓
Dust Control Plan ✓
Dewatering Plan ✓
Traffic and track-out Control Plans ✓
Permits and Notifications ✓
Emergency Plan ✓
Waste Management Plan ✓
Safety Data Sheets (SDS) ✓
Project Schedule ✓
Executed Contract including Schedule of Values ✓
Performance and Payment Bond ✓
Certificate of Insurance ✓
26 | P a g e
Port KC – Warehouse Demolition – Woodswether Terminal
January 27, 2017
1. Waste Management Records including results of waste characterization (as
received)
2. Progress Schedules (weekly)
3. Agency Inspection Records (as received)
4. SWPPP reporting requirements (weekly)
PART 2 - PRODUCTS - NOT APPLICABLE.
PART 3 - EXECUTION - NOT APPLICABLE.
END OF SECTION 013300
27 | P a g e
Port KC – Warehouse Demolition – Woodswether Terminal
January 27, 2017
Section 013529
Safety and Emergency
Response
28 | P a g e
Port KC – Warehouse Demolition – Woodswether Terminal
January 27, 2017
SECTION 013529 – SAFETY AND EMERGENCY RESPONSE
PART 1 - GENERAL
1.1 GENERAL REQUIREMENTS
A. This Section addresses special procedures and requirements that shall be followed
for protection of health and safety of persons at the Project Site.
B. Contractor is responsible for site health & safety of its personnel and those of its
subcontractors. Owner or Owner’s Representative(s) are not responsible for health
and safety at the site.
C. Health and safety requirements established in this Section are based on Site
conditions anticipated from available Site data.
1. Procedures are intended for Work activities including, but not limited to:
a. Asbestos Abatement.
b. Scaffolding (if necessary)
c. Ladders.
d. Work on roofs
e. Demolition
f. Backfilling
g. Confined Space
2. Contractor shall be responsible for reviewing and revising their safety
program based on actual conditions encountered at the Site and to conform
with all applicable laws and regulations.
D. Before Work at the Site proceeds, all personnel involved in performing Work
activities shall read, understand, and sign the Site Health and Safety Plan (SHSP)
prepared by Contractor.
1.2 SUBMITTALS
A. Submit as specified in SECTION 013300.
B. Submittals shall include, but are not limited to:
1. Site health and safety plan (SHSP).
2. Personnel certificates of training.
3. Asbestos abatement license for Contractor
4. Daily logs of air monitoring.
5. Site entry register.
29 | P a g e
Port KC – Warehouse Demolition – Woodswether Terminal
January 27, 2017
1.3 SITE HEALTH AND SAFETY PLAN
A. General: Contractor shall prepare and submit a Site Health and Safety Plan (SHSP)
to Owner and Owner’s Representative. Contractor shall be responsible for the
safety and health of its staff and that of its Subcontractors. Owner and Owner’s
Representative will not be responsible for approving Contractor’s SHSP. Owner
and Owner’s Representative shall be notified in writing and consulted before any
changes to SHSP are implemented. Contractor shall include at a minimum the
items described in the following paragraphs.
B. Key Personnel:
1. Contractor shall designate a full-time onsite health and safety representative
(HSR) who will be responsible for the compliance to the SHSP including,
but not limited to the following activities:
a. Monitor workers’ breathing zone and periodically at the Site for
combustible gases, dusts, asbestos.
b. Oversee all operations at the Site.
c. Maintain proper medical surveillance.
d. Provide hazard communications to personnel at the Site.
e. Train personnel in safe operating procedures.
f. Advise Contractor on health and safety matters.
2. The SHSP shall name the HSR and an alternate, with necessary contact
information prior to the start of any onsite activities.
3. The HSR shall be a Certified Safety Professional (CSP) or Associate Safety
Professional (ASP) with a minimum of 3 years of experience with similar
projects.
4. The HSR shall not have any other responsibilities at the site and be
dedicated to the management of safety for Contractor.
5. The HSR identified in the proposal shall not be replaced without written
authorization of Owner or Owner’s Representative. Contractor shall
provide a minimum of 48 hour notice with documentation that the
replacement will meet the minimum standards identified above.
C. Health Risk Analysis: Contractor shall develop a health risk analysis to include all
hazards which may be encountered during the project.
D. Training Requirements:
1. General: Contractor shall provide training for personnel, including
supervisors, observers, and workers active on the Site. Training in safety
precautions, procedures, and personal protective equipment shall comply
with at a minimum, but not be limited to:
a. 29 CFR 1910.120 (e) – Hazardous Waste Operations and Emergency
Response-Training.
30 | P a g e
Port KC – Warehouse Demolition – Woodswether Terminal
January 27, 2017
b. 29 CFR 1910.146 – Permit-required confined spaces.
c. 29 CFR 1910.1200 – Hazard communication.
d. 29 CFR 1910.1001 – Asbestos
e. 29 CFR 1926 - OSHA Standards for the Construction Industry
f. 29 CFR 1926.59 - OSHA Hazard Communication Standard for
Construction Industry
g. Any other requirements not listed to conduct the work in accordance
with all Applicable Laws and Regulations.
2. Health and Safety Training: Prior to commencement of Work activities,
health and safety training shall be conducted by the HSR to review pertinent
sections of the SHSP.
a. All workers shall attend.
b. Personnel not attending shall be given a similar pre-Work orientation
individually or in groups by the HSR.
c. If a significant change in on-Site operations occurs during Work
activities, another Site-specific training session shall be given.
d. A record of training and attendance shall be provided in the Project
safety log.
3. Training Certification: Contractor shall submit copies of current training
certifications for all Project personnel to Owner and Owner’s
Representative prior to entry onto the Work Site.
4. Site Visitors: A visitor seeking entry into an exclusion zone or
contamination reduction zone on Site shall present documents of current
health and safety training and medical surveillance
examination/certification equivalent to that required for on-Site Work.
a. HSR shall provide orientation on relevant sections of the SHSP.
E. Personal Protective Equipment:
1. Contractor shall include in SHSP all personal protective equipment (PPE)
anticipated for use on Site according to level of protection indicated by
health risk analysis.
2. Level D with high visibility safety vest shall be the minimum level of
protection set for Site operations.
F. Site Security and Control:
1. Include procedures for Site security and control in SHSP.
2. Indicate Site exclusion and contamination reduction zone boundaries in
SHSP.
3. Provide register log form for entering and leaving the Site.
G. Contingency Plan:
31 | P a g e
Port KC – Warehouse Demolition – Woodswether Terminal
January 27, 2017
1. SHSP shall include a contingency plan for health and safety emergencies.
2. This plan shall incorporate any Site-specific or Owner-specific
requirements.
3. A copy of the contingency plan shall remain on-Site, signed by and
available for review by all personnel.
H. Standard Operating Procedures:
1. Contractor shall be familiar with and include in SHSP Owner’s standard
operating procedures (SOP) relevant to Work activities performed on Site.
PART 2 - PRODUCTS
2.1 PERSONAL PROTECTIVE EQUIPMENT
A. Level of Protection. Contractor shall include in SHSP all personal protective
equipment (PPE) anticipated for use on Site.
1. Level D Protection: Work activities shall be conducted with a minimum of
Level D protection indicated below. Contractor is responsible for
identification and providing additional protective equipment as deemed
necessary based on the identified hazards at the site. Level D protection
shall at a minimum consist of:
a. Work boots with steel toe and steel shank.
b. Hard hat.
c. Safety glasses
d. Safety vest
2.2 FIRST AID PROVISIONS AND EMERGENCY EQUIPMENT
A. Fire Extinguishers: Type and number of fire extinguishers shall be determined by
Contractor in accordance with Applicable Laws and regulations and submitted as
part of the SHSP. Inspection and maintenance shall be the responsibility of
Contractor. Other fire stations equipped with the appropriate type and size of fire
extinguishers shall be established by Contractor as needed. These stations shall be
clearly marked and identified in the SHSP. All combustible or flammable
materials used onsite shall be stored in Underwriter’s Laboratory (UL) listed
and/or Factory Mutual (FM) approved containers.
B. Contractor shall arrange for local emergency rescue support (i.e. local fire
department) or provide any and all emergency rescue equipment, such as safety
harness and lifeline, and/or basket stretcher that is required to rescue an individual
from an excavation cave-in and/or confined space.
PART 3 - EXECUTION
3.1 SITE SECURITY AND CONTROL
32 | P a g e
Port KC – Warehouse Demolition – Woodswether Terminal
January 27, 2017
A. Work Zones:
1. An exclusion zone for Work activities shall be established by the HSR.
2. Both zones shall be clearly delineated with the use of barrier tape or snow
fencing.
3. Contractor’s Site office, parking area, and other support operations shall be
located outside the exclusion zone.
4. Any changes in the exclusion zone shall be presented in a written SHSP
amendment by the HSR to Owner and Owner’s Representative for approval.
5. Boundaries of the exclusion and contaminated reduction zones shall be
clearly posted by Contractor.
B. Site Register: Contractor shall maintain a register of all personnel visiting,
entering, or working (on the Site) (in the exclusion zone).
C. Contractor is responsbile for securing Work Zone and Site office from
tresspassers.
D. Contractor shall coordinate with Owner and Owner’s Representative to provide
access as necessary for parties involved in other projects on the site, if any.
E. Signs: Before Site operations begin, Contractor shall post signs at the perimeter
of the exclusion zone stating:
DEMOLITION AREA – KEEP OUT
DANGER – NO SMOKING
AUTHORIZED PERSONNEL ONLY
1. Signs shall be printed in bold large letters on contrasting backgrounds.
2. Signs shall be visible from all points, where entry might occur and at such
distances from the restricted area that personnel may read the signs and take
necessary protective steps before entering.
3.2 CONTINGENCY PLAN
A. The following part of the SHSP shall be posted in Site construction office trailers,
kept in all Site vehicles, and provided to supervisory personnel on Site.
1. Emergency Action – Standard Operating Procedures:
a. Name, address, and telephone number of the nearest medical treatment
facility shall be conspicuously posted. A map and direction for locating
the facility, plus the travel time, shall be readily available.
b. If the facility lacks toxicological capability, arrangements shall be
made for consultant services.
c. Arrangements to quickly obtain ambulance, emergency, fire, and
police services. Telephone numbers and procedures for obtaining these
services shall be conspicuously posted.
d. Prior to mobilization at the Site, personal contact shall be made with
33 | P a g e
Port KC – Warehouse Demolition – Woodswether Terminal
January 27, 2017
emergency room personnel, the poison control center, and the local fire
department and police. If outside of an established town, contact shall
be made with county officials and local emergency services.
e. An eye wash kit and first aid equipment shall be readily available on
Site. Personnel shall have first aid and medical emergency training.
f. Sufficient water and/or dry chemical fire extinguisher and neutralizing
agents shall be maintained on Site to cope with any situation until
emergency services can arrive.
2. Medical Emergencies
a. For any person who becomes ill or injured on Site and the injury or
illness is minor, follow the requirements of the Site Health & Safety
Plan.
b. The SHSP shall outline how decontamination will occur should a
medical emergency arise in the containment area.
3. Site-Specific Information: The following shall be provided on a Site-
specific basis:
a. Nearest Hospital:
Name.
Address.
Phone number.
Directions from the Site (map attached).
b. Nearest Fire Department:
Phone number.
c. Facility Contact:
Phone number.
d. Other emergency contacts.
3.3 CONFINED SPACE
A. Confined Space: As part of the SHSP, Contractor shall identify all tasks that shall
be considered confined space entry (e.g., entrance into manholes, buildings and
trenches), any procedure for entry into these spaces (i.e., air testing), and permit
requirements.
END OF SECTION 013529
34 | P a g e
Port KC – Warehouse Demolition – Woodswether Terminal
January 27, 2017
Section 014200
Definitions and
Standards
35 | P a g e
Port KC – Warehouse Demolition – Woodswether Terminal
January 27, 2017
SECTION 014200 - DEFINITIONS AND STANDARDS
PART 1 - GENERAL
1.1 SPECIFICATION FORMAT AND CONTENT EXPLANATIONS:
A. Specification Format: The Specifications are organized into Divisions and
Sections based on the Construction Specifications Institute's (CSI) Section Format
and Master Format numbering system. Some portions may not fully comply and
no particular significance will be attached to such compliance or noncompliance.
1. Divisions and Sections: For convenience, a basic unit of Specification text
is a "Section," each unit of which is numbered and named. These are
organized with related Sections, into "Divisions," which are recognized as
the present industry consensus on uniform organization and sequencing of
Specifications. The Section title is not intended to limit meaning or content
of Section, or to be fully descriptive of requirements specified therein, or to
be an integral part of text.
2. Section Numbering: Used for identification and to facilitate cross-
references in Contract Documents. Sections are placed in numeric
sequence; however, numbering sequence is not complete, and listing of
Sections in Table of Contents at beginning of the Project Manual must be
consulted to determine numbers and names of Specification Sections in
these Contract Documents.
3. Page Numbering: Numbered independently for each Section. Section
number is shown with page number at bottom of each page, to facilitate
location of text.
4. Parts: Each Section of Specifications generally has been subdivided into
three basic "parts" for uniformity and convenience (PART 1 - GENERAL,
PART 2 - PRODUCTS, and PART 3 - EXECUTION). These "Parts" do not
limit the meaning of text within. Some Sections may not contain all three
"Parts" when some are not applicable, or may contain more than three
"Parts" to add clarity to organization of Section.
5. Underscoring of Titles: Used strictly to assist reader of Specification in
scanning text for key words in content. No emphasis on or relative
importance is intended except where underscoring may be used in body of
text to emphasize a duty, critical requirement, or similar situation.
6. 6. Project Identification: Project file number and identification are recorded
at bottom of each page of Specifications to minimize possible misuse of
Specifications, or confusion with other Project Specifications.
B. Specification Content:
36 | P a g e
Port KC – Warehouse Demolition – Woodswether Terminal
January 27, 2017
1. These Specifications apply certain conventions in the use of language and
the intended meaning of certain terms, words, and phrases when used in
particular situations or circumstances. These conventions are explained as
follows:
a. Imperative and Streamlined Language: These Specifications are
written in imperative and abbreviated form. This imperative language
of the technical Sections is directed at Contractor, unless specifically
noted otherwise. Incomplete sentences shall be completed by inserting
"shall," " Contractor shall," and "shall be," and similar mandatory
phrases by inference in the same manner as they are applied to notes
on the Drawings. The words "shall be" shall be supplied by inference
where a colon (:) is used within sentences or phrases. Except as worded
to the contrary, fulfill (perform) all indicated requirements whether
stated imperatively or otherwise.
b. Specifying Methods: The techniques or methods of specifying
requirements varies throughout text, and may include "prescriptive,"
"compliance with standards," "performance," "proprietary," or a
combination of these. The method used for specifying one unit of Work
has no bearing on requirements for another unit of Work.
c. Overlapping and Conflicting Requirements: Where compliance with
two or more industry standards or sets of requirements is specified, and
overlapping of those different standards or requirements establishes
different or conflicting minimums or levels of quality, notify Owner’s
Representative in writing for a decision, which Owner’s Representative
will render in writing within a reasonable time.
d. Abbreviations: Throughout the Contract Documents are abbreviations
implying words and meanings which shall be appropriately interpreted.
Specific abbreviations have been established, principally for lengthy
technical terminology and in conjunction with coordination of
Specification requirements with notations on Drawings and in
Schedules. These are normally defined at first instance of use.
Organizational and association names and titles of general standards
are also abbreviated.
C. Assignment of Specialists: In certain instances, Specification text requires that
specific Work be assigned to specialists in the operations to be performed. These
specialists shall be engaged for performance of those units of Work, and
assignments are requirements over which Contractor has no choice or option.
These assignments shall not be confused with, and are not intended to interfere
with, enforcement of building codes and similar regulations governing the Work,
local trade and union jurisdictions, and similar conventions. Nevertheless, final
responsibility for fulfillment of Contract requirements remains with Contractor.
D. Trades: Except as otherwise specified or indicated, the use of titles such
as "carpentry" in Specification text, implies neither that the Work must be
performed by an accredited or unionized tradesperson of corresponding generic
37 | P a g e
Port KC – Warehouse Demolition – Woodswether Terminal
January 27, 2017
name (such as "carpenter"), nor that specified requirements apply exclusively to
work by tradespersons of that corresponding generic name.
1.2 DRAWING SYMBOLS:
A. Except as otherwise indicated, graphic symbols used on Drawings are those
symbols recognized in the construction industry for purposes indicated. Refer
instances of uncertainty to Owner’s Representative for clarification.
1.3 INDUSTRY STANDARDS:
A. A. Applicability of Standards: Except where the Contract Documents include
more stringent requirements, applicable construction industry standards have the
same force and effect as if bound or copied directly into the Contract Documents.
Such standards are made a part of the Contract Documents by reference and are
stated in each Section.
1. Referenced standards, referenced directly in Contract Documents or by
governing regulations, have precedence over non-referenced standards
which are recognized in industry for applicability to the Work.
2. Where compliance with an industry standard is required, the latest standard
in effect at time of opening Bids shall govern.
3. Where an applicable code or standard has been revised and reissued after
the effective date of the Contract and before performance of Work affected
by the revision, Owner’s Representative will decide whether to issue a
Change Order to proceed with the revised standard.
4. In every instance the quantity or quality level shown or specified shall be
the minimum to be provided or performed. The actual installation may
comply exactly, within specified tolerances, with the minimum quantity or
quality specified, or it may exceed that minimum within reasonable limits.
In complying with these requirements, indicated numeric values are
minimum or maximum values, as noted, or appropriate for the context of
the requirements. Refer instances of uncertainty to Owner’s Representative
for a decision before proceeding.
5. Each entity engaged in construction on the Project is required to be familiar
with industry standards applicable to that entity's construction Activity.
Copies of applicable standards are not bound with the Contract Documents.
a. Where copies of standards are needed for performance of a required
construction Activity, Contractor shall obtain copies directly from the
publication source.
B. Abbreviations and Names: Trade association names and titles of general standards
are frequently abbreviated. Where such acronyms or abbreviations are used in the
Specifications or other Contract Documents, they mean the recognized name of
the trade association, standards generating organization, authority having
jurisdiction, or other entity applicable to the context of the text provision.
38 | P a g e
Port KC – Warehouse Demolition – Woodswether Terminal
January 27, 2017
1.4 DEFINED TERMS
A. Wherever used in the Bidding Requirements or Contract Documents and printed
with initial capital letters, whether singular or plural thereof, all such terms shall
have the meaning provided in Section 1 of the Decommissioning and Demolition
Agreement or as follows:
1. Activity or Activities: A discrete part of a contract that can be identified for
planning, scheduling, monitoring, and controlling the construction Work.
Activities included in a construction Schedule consume time and resources,
but shall not include planned work stoppages. Activities shall not normally
reflect the Work of more than one trade.
a. Critical Activities: Activities on the Critical Path and have zero or
negative Float. Critical Activities must start and finish on the planned
early start and finish times.
b. Predecessor Activity: An Activity that precedes another Activity in the
network.
c. Successor Activity: An Activity that follows another Activity in the
network.
2. Addenda: Written or graphic instruments issued prior to the opening of Bids
which clarify, correct, or change the Bidding Requirements or the proposed
Contract Documents.
3. Adjacent Facilities: All property that is (1) located on the Site and is
designated to remain in place, and (2) neighboring properties or property
located in adjacent rights of way. Such Adjacent Facilities are identified on
the Contract Drawings and include but are not limited to the following:
a. Mid America Rail lines and facitilites
b. Roadways
c. Buildings and structures adjacent and not within the Phase 1 Area
which are to be demolished in a subsequent Phase.
4. Application for Payment: The form acceptable to Owner which is to be used
by Contractor during the course of the Work in requesting progress or final
payments and which is to be accompanied by such supporting
documentation as is required by the Contract Documents.
5. Baseline Schedule: The Schedule submitted and accepted by the Owner’s
Representative for the Work.
6. Bid: The offer or proposal of a Bidder submitted on the prescribed form
setting forth the prices for the Work to be performed.
7. Bidder: The individual or entity who submits a Bid directly to Owner.
facilities.
39 | P a g e
Port KC – Warehouse Demolition – Woodswether Terminal
January 27, 2017
8. Bidding Requirements: The advertisement or invitation to Bid, Instructions
to Bidders, Bid security of acceptable form, if any, and the Bid Form with
any supplements.
9. Business Day: Any day, except for Saturdays, Sundays and any holidays in
which banks in the State where the Site is located are closed.
10. Contractor’s Superintendent: Resident onsite person that manages and
directs all aspects of the Work to be conducted by Contractor and its
subcontractors.
11. General Requirements: Sections of Division 01 of the Specifications.
12. Landfill: Refers to a third party Landfill
13. Leak or Leaking: Any instance of a toxic substance present on any portion
of the external surface of an item of equipment or container.
14. Notice of Award: The written notice by Owner to the Successful Bidder
stating that upon timely compliance by the Successful Bidder with the
conditions precedent listed therein, Owner will sign and deliver the
Agreement.
15. PCBs: Polychlorinated biphenyls.
16. Progress Schedule: A Schedule, prepared and maintained by Contractor,
describing the sequence and duration of the Activities comprising
Contractor’s plan to accomplish the Work within the Contract Times.
17. Project: The total construction of which the Work to be performed under
the Contract Documents may be the whole, or a part.
18. Project Manual: Document that includes all plans, specifications, exhibits
describing the requirements for the project. This document becomes part of
the agreement for the project.
19. Owner’s Representative: Representative onsite overseeing the Project
Activities on behalf of Owner.
20. Samples: Physical examples of materials, equipment, or workmanship that
are representative of some portion of the Work and which establish the
standards by which such portion of the Work will be judged.
21. Schedule of Submittals: A Schedule, prepared and maintained by
Contractor, of required submittals and the time requirements to support
Scheduled performance of related construction Activities.
22. Shop Drawings: All drawings, diagrams, illustrations, Schedules, and other
data or information which are specifically prepared or assembled by or for
Contractor and submitted by Contractor to illustrate some portion of the
Work.
23. Site: Lands or areas indicated in the Contract Documents as being furnished
by Owner upon which the Work is to be performed, including rights-of-way
40 | P a g e
Port KC – Warehouse Demolition – Woodswether Terminal
January 27, 2017
and easements for access thereto, and such other lands furnished by Owner
which are designated for the use of Contractor.
24. Specifications: That part of the Contract Documents consisting of written
requirements for materials, equipment, systems, standards and
workmanship as applied to the Work, and certain administrative
requirements and procedural matters applicable thereto.
25. Successful Bidder: Bidder submitting a responsive Bid to whom Owner
makes an award.
26. Supplier: A manufacturer, fabricator, Supplier, distributor, materialman, or
vendor having a direct contract with Contractor or with any Subcontractor
to furnish materials or equipment to be incorporated in the Work by
Contractor.
27. Underground Facilities: All underground pipelines, conduits, ducts, cables,
wires, manholes, vaults, tanks, tunnels, or other such facilities or
attachments, and any encasements containing such facilities, including
those that convey electricity, gases, steam, liquid petroleum products,
telephone or other communications, cable television, water, wastewater,
storm water, other liquids or chemicals, or traffic or other control systems.
28. Waste Management Records: All records related to management of wastes
generated by the Work, including but not limited to waste profiles and
characterization data, waste shipping papers, bills-of-lading, Special Waste
or Hazardous Waste manifests, weigh tickets/disposal receipts, Salvagable
Material and/or recyclable material weight tickets.
1.5 TERMINOLOGY
A. The words and terms discussed in Paragraph 1.05.B through F are not defined but,
when used in the Bidding Requirements or Contract Documents, have the
indicated meaning.
B. Intent of Certain Terms or Adjectives:
1. The Contract Documents include the terms “as allowed,” “as approved,” “as
ordered,” “as directed” or terms of like effect or import to authorize an
exercise of professional judgment by Owner’s Representative. In addition,
the adjectives “reasonable,” “suitable,” “acceptable,” “proper,”
“satisfactory,” or adjectives of like effect or import are used to describe an
action or determination of Owner’s Representative as to the Work. It is
intended that such exercise of professional judgment, action, or
determination will be solely to evaluate, in general, the Work for
compliance with the information in the Contract Documents and with the
design concept of the Project as a functioning whole as shown or indicated
in the Contract Documents (unless there is a specific statement indicating
otherwise). The use of any such term or adjective is not intended to and shall
not be effective to assign to Owner’s Representative any duty or authority
to supervise or direct the performance of the Work, or any duty or authority
to undertake responsibility contrary to the provisions in the
1.5 B through E
41 | P a g e
Port KC – Warehouse Demolition – Woodswether Terminal
January 27, 2017
Agreement/General Conditions or any other provision of the Contract
Documents.
C. Day:
1. The word “day” means a calendar day of 24 hours measured from midnight
to the next midnight.
D. Furnish, Install, Perform, Provide, Construction:
1. The word “furnish,” when used in connection with services, materials, or
equipment, shall mean to supply, pay for and deliver said services,
materials, or equipment to the Site (or some other specified location) ready
for use or installation and in usable or operable condition.
2. The word “install,” when used in connection with services, materials, or
equipment, shall mean to put into use, pay for and/or place in final position
said services, materials, or equipment complete and ready for intended use.
3. The words “perform” or “provide,” when used in connection with services,
materials, or equipment, shall mean to furnish, pay for and install said
services, materials, or equipment complete and ready for intended use.
4. When “furnish,” “install,” “perform,” or “provide” is not used in connection
with services, materials, or equipment in a context clearly requiring an
obligation of Contractor, “provide” is implied.
5. The word “construction” when used in the Contract Documents includes,
but is not limited to, the following services: environmental remediation;
abatement of Regulated Materials, demolition; deconstruction;
dismantlement; material scrap or Salvage; waste hauling and disposal;
hazardous material handling and disposal; special waste handling, disposal
and recycling.
E. Unless stated otherwise in the Contract Documents, words or phrases that have a
well-known technical or construction industry or trade meaning are used in the
Contract Documents in accordance with such recognized meaning.
1.6 CODES AND STANDARDS
A. All Work and Services provided in the Project shall be in accordance with
Applicable Law.
B. Publications of the following nationally recognized organizations are applicable
to the engineering, design, manufacture, and testing of the equipment included in
the Specifications to the extent referenced in this Specification. All references to
publications are to the latest adopted issue of each together with all latest Addenda,
amendments, or additions thereto as of the date of this Agreement. References
shall be made in accordance with the abbreviations listed below:
1. American National Standards Institute (ANSI):
a. A10 Series - Safety Requirements for Construction and Demolition.
2. National Electrical Contractors Association (NECA):
42 | P a g e
Port KC – Warehouse Demolition – Woodswether Terminal
January 27, 2017
a. Electrical Design Library - Temporary Electrical Facilities.
3. National Fire Protection Association (NFPA)
a. 10 - Portable Fire Extinguishers
b. 70 - National Electrical Code.
c. 241 - Safeguarding Construction, Alterations, and Demolition
Operations.
4. National Electrical Manufacturers Association (NEMA).
5. Underwriters Laboratories (UL).
C. In the event that conflicts arise between Applicable Law and the standards of
practice, or specifications described herein, the more stringent code shall apply.
Contractor shall provide a written position of any such conflict clarifications to
Owner in writing.
PART 2 - PRODUCTS - NOT APPLICABLE.
PART 3 - EXECUTION - NOT APPLICABLE
END OF SECTION 014200
43 | P a g e
Port KC – Warehouse Demolition – Woodswether Terminal
January 27, 2017
Section 015300
Temporary Barriers and
Controls
44 | P a g e
Port KC – Warehouse Demolition – Woodswether Terminal
January 27, 2017
SECTION 015300 - TEMPORARY BARRIERS AND CONTROLS
PART 1 - GENERAL
1.1 SUMMARY
A. This Section includes General Requirements for:
1. Safety and protection of Work.
2. Safety and protection of existing Owner property, including adjacent
private property.
3. Barriers.
4. Security.
5. Environmental controls.
6. Access roads and parking areas.
7. Traffic control and use of roadways.
B. Related Work Specified Elsewhere
1. Temporary Utilities and Facilities: SECTION 015600.
1.2 DEFINITIONS
A. The meanings for all defined terms are identified in SECTION 014200.
PART 2 - PRODUCTS – NOT APPLICABLE
2.1 STORMWATER POLLUTION PREVENTATION PLAN
A. Contractor shall prepare a Stormwater Pollution Prevention Plan covering
the work outlined in the Contract Documents.
B. Contractor shall submit a copy to the Owner for review before finalizing.
2.2 STORMWATER PERMIT
A. Contractor shall obtain a stormwater permit for the work covered by the
Contract Documents as applicable.
B. Contractor shall provide a copy of the permit obtained prior to conducting
any work at the site.
PART 3 - EXECUTION
3.1 PROTECTION OF WORK AND PROPERTY
A. General
45 | P a g e
Port KC – Warehouse Demolition – Woodswether Terminal
January 27, 2017
1. Construct and maintain all necessary temporary drainage and stormwater
protection in accordance with the SWPPP and stormwater permit.
2. Conduct all pumping necessary to keep excavations, floors, pits,
trenches, manholes, and ducts free of water throughout this Project.
3.2 BARRIERS
A. General:
1. Furnish, install, and maintain suitable barriers as required to protect the
Work, adjacent property outside the Phase 1 Area, Mid America
Railroad and associated structures, existing water line designated to
remain, and roadways from demolition operations. Remove at
completion of the Work.
2. Materials may be new or used, suitable for the intended purpose, but shall
not violate requirements of applicable codes and standards or regulatory
agencies.
3. Barriers shall be of a neat and reasonable uniform appearance,
structurally adequate for the required purposes.
4. Maintain barriers in good repair and clean condition for adequate
visibility. Relocate barriers as required by progress of Work.
5. Repair damage caused by construction and restore the area to original or
better condition. Clean the area to the satisfaction of Owner.
3.3 ENVIRONMENTAL CONTROLS
A. Dust Control
1. Provide positive control methods and apply dust control materials to
minimize raising dust from demolition, excavation or backfilling
operations; and to prevent airborne dust from dispersing into the
atmosphere.
2. When using water for additional dust control the Contractor shall record:
a. the date; and
b. the area(s) at the facility where water is applied.
3. Observe and enforce vehicle speed limit of 15 mph or less on the Site to
minimize fugitive dust generated from vehicle traffic.
B. Water and Erosion Control
1. Provide methods to control surface water from the Site to prevent damage
to adjoining properties in accordance with the Project SWPPP and the
Drawings. Contractor shall meet the stricter of the requirements
specified herein, indicated on the Drawings, or stated in the Project
SWPPP.
46 | P a g e
Port KC – Warehouse Demolition – Woodswether Terminal
January 27, 2017
2. Plan and execute construction and earthwork by methods to control
surface drainage from cuts and fills, and from borrow and waste disposal
areas, to prevent erosion and sedimentation.
a. Hold the areas of bare soil exposed at one time to a minimum.
b. Provide temporary control measures such as berms, dikes, and drains.
3. Control fill, grading, and ditching to direct surface drainage away from
excavations, pits, tunnels, and other construction areas; and to direct
drainage to proper runoff.
4. Provide, operate, and maintain hydraulic equipment of adequate capacity
to control surface and groundwater.
5. Treat and dispose of surface runoff water in a manner to prevent flooding,
erosion, sedimentation, or other damage to any portion of the Site or to
adjoining areas, and in accordance with the storm water permit obtained
for the demolition and remediation Activities.
C. Debris Control and Clean-Up
1. Keep the Site free at all times from accumulations of debris, waste
materials, and rubbish caused by construction operations and
employees. Responsibilities shall include:
a. Adequate trash receptacles about the Site, emptied promptly when
filled.
b. Periodic cleanup to avoid hazards or interference with operations at
the Site and to maintain the Site in a reasonably neat condition.
c. The keeping of construction materials such as forms and scaffolding
neatly stacked.
d. Immediate cleanup to protect the Work by removing splattered
concrete, asphalt, oil, paint, corrosive liquids, and cleaning solutions
from walls, floors, and metal surfaces before surfaces are marred.
2. Prohibit overloading of trucks to prevent Spills on access and haul routes.
Provide periodic inspection of traffic areas to enforce requirements.
3. Final cleanup is specified in SECTION 017800 - Contract Closeout.
D. Pollution Control
1. Provide methods, means, and facilities required to prevent contamination
of soil, water, or atmosphere by the discharge of hazardous materials or
TSCA Materials from Site operations.
2. Provide equipment and personnel, perform emergency measures required
to contain any Spills, and remove contaminated soils or liquids. Contain
all soils on Site and return to areas of excavations to be used as fill on
Site. Only when approved by the Owner’s Representative,
47 | P a g e
Port KC – Warehouse Demolition – Woodswether Terminal
January 27, 2017
excavate and dispose of any contaminated earth off-Site in approved
locations, and replace with suitable compacted fill.
3. Contractor shall provide analytical results of proposed fill materials prior
to importing it to the site indicating the material does not contain
constituents above the IDEM standards.
4. Take special measures to prevent harmful substances from entering
public waters, sanitary, or storm sewers and ditches.
3.4 ACCESS ROADS AND PARKING AREAS
A. Existing On-Site Roads and Parking Areas:
1. Designated existing on-Site roads and parking facilities may be used for
construction traffic.
a. Provide temporary additional roads as needed for required
construction access.
b. Maintain existing construction, and restore to original, better, or
specified condition at completion of Work.
c. Do not allow heavy vehicles or construction equipment in parking
areas.
d. Employee parking during construction shall be in area designated on
the Contract Drawings.
3.5 TRAFFIC CONTROL AND USE OF ROADWAYS:
A. Site shall be accessed by using State Highway 62.
B. Contractor shall be responsible for any permitting, traffic control and repairs
as required by the City of Charlestown or Clark County.
C. Trucks waiting to loaded should assemble on the site along the roadway.
Trucks should avoid lining up on State Highway 62.
D. Maintenance of Roadways:
1. Repair roads, walkways, and other traffic areas damaged by Contractor’s
operations. Keep traffic areas as free as possible of excavated materials
and maintain in a manner to eliminate dust, mud, and hazardous
conditions.
2. All operations and repairs shall meet the approval of Owner or agencies
having jurisdiction.
END OF SECTION 015300
State Street gate only.
City, State, or other governing authority.
shall not block railroad crossing at any time.
48 | P a g e
Port KC – Warehouse Demolition – Woodswether Terminal
January 27, 2017
Section 015600
Temporary Utilities and
Facilities
49 | P a g e
Port KC – Warehouse Demolition – Woodswether Terminal
January 27, 2017
SECTION 015600 - TEMPORARY UTILITIES AND FACILITIES
PART 1 - GENERAL
1.1 SUMMARY:
A. This Section includes requirements of a temporary nature not normally
incorporated into final Work. It includes the following:
1. Utility services.
2. Construction and support facilities.
3. Construction aids.
4. Safety and health.
5. Fire protection.
B. Related Work Specified Elsewhere:
1. Safety and Emergency Response: SECTION 013529
2. Temporary Barriers and Controls: SECTION 015300
3. Field Offices and Sheds: SECTION 015200
4. Material and Waste Management: SECTION 025100
5. Regulated and Hazardous Material Transport: SECTION 025500
1.2 REFERENCES:
A. American National Standards Institute (ANSI):
1. A10 Series - Safety Requirements for Construction and Demolition.
B. National Electrical Contractors Association (NECA):
1. Electrical Design Library - Temporary Electrical Facilities.
C. National Fire Protection Association (NFPA):
1. 10 - Portable Fire Extinguishers.
2. 70 - National Electrical Code.
3. 241 - Safeguarding Construction, Alterations, and Demolition Operations.
D. National Electrical Manufacturers Association (NEMA).
E. Underwriters Laboratories (UL).
1.3 DEFINITIONS
A. The meanings for all defined terms are identified in SECTION 014200.
50 | P a g e
Port KC – Warehouse Demolition – Woodswether Terminal
January 27, 2017
1.4 SUBMITTALS: NONE
1.5 QUALITY ASSURANCE:
A. Regulations: Comply with industry standards and Applicable Law, including but
not limited to:
1. Building Code requirements.
2. Health and safety regulations.
3. Utility company regulations.
4. Police, Fire Department, and rescue squad rules.
5. Environmental protection regulations.
B. Standards:
1. Comply with NFPA 10 and 241, and ANSI A10 Series standards
“Temporary Electrical Facilities."
2. Comply with NEMA, NECA, NECS, and UL standards and regulations for
temporary electric service. Install service in compliance with NFPA 70.
C. Inspections: Arrange for authorities having jurisdiction to inspect and test each
temporary utility before use. Obtain required certifications and Permits.
1.6 PROJECT CONDITIONS:
A. Conditions of Use: Keep temporary services and facilities clean and neat in
appearance. Operate in a safe and efficient manner. Take necessary fire prevention
measures. Do not overload facilities, or permit them to interfere with progress. Do
not allow hazardous, dangerous, unsanitary conditions, or public nuisances to
develop or persist on the Site.
PART 2 - PRODUCTS
2.1 MATERIALS AND EQUIPMENT:
A. Water: Provide potable water from a location approved by the Owner.
B. Electrical Outlets: Provide properly configured, NEMA-polarized outlets to
prevent insertion of 110- to 120V plugs into higher voltage outlets. Provide
receptacle outlets equipped with ground-fault circuit interrupters, reset button, and
pilot light for connection of power tools and equipment.
C. Electrical Power Cords: Provide grounded extension cords. Use hard-service
cords where exposed to abrasion and traffic. Provide waterproof connectors to
connect separate lengths of electric cords if single lengths will not reach areas
where construction Activities are in progress. Do not exceed safe length-voltage
ratio.
51 | P a g e
Port KC – Warehouse Demolition – Woodswether Terminal
January 27, 2017
D. Lamps and Light Fixtures: Provide energy efficient general service lamps of
wattage required for adequate illumination and provide guard cages or tempered-
glass enclosures where exposed to breakage. Provide exterior fixtures where
exposed to moisture.
E. Heating Units: Provide temporary heating units that have been tested and labeled
by UL, FM, or another recognized trade association related to the type of fuel
being consumed.
F. Fire Extinguishers: Provide hand-carried, portable, UL-rated, Class A fire
extinguishers for temporary offices and similar spaces. In other locations, provide
hand-carried, portable, UL-rated, Class ABC, dry-chemical extinguishers or a
combination of extinguishers of NFPA recommended classes for the exposures.
Comply with NFPA 10 and NFPA 241 for classification, extinguishing agent, and
size required by location and class of fire exposure.
PART 3 - EXECUTION
3.1 TEMPORARY UTILITIES:
A. Furnish, install, and maintain temporary utilities required for adequate safety and
security during conduct of the Work. Modify, relocate, and extend systems as
Work progresses. Repair damage caused by installation or use of temporary
facilities. Grade the areas of Site affected by temporary installations to required
elevations and grades, and clean the area. Remove on completion of Work or until
service or facilities are no longer needed or are replaced by authorized use of
completed permanent facilities.
B. The types of temporary construction utilities and facilities required include, but
not by way of limitation, water distribution, drainage, dewatering equipment,
enclosure of Work, heat, ventilation, electrical power distribution, lighting,
hoisting facilities, stairs, ladders, and roads.
3.2 TEMPORARY ELECTRICAL:
A. Use of Existing System:
1. Owner's existing system may not be used for temporary electricity. Cost of
providing and power use shall be paid by Contractor.
3.3 TEMPORARY HEAT AND VENTILATION:
A. General:
1. Provide temporary heat, ventilation, and cooling as required to maintain
adequate environmental conditions to facilitate progress of the Work, to
meet specified minimum conditions for the installation of materials, and to
protect materials and finishes from damage. Protect from adverse effects of
low temperatures or high humidity, and to prevent hazardous accumulations
of dust, fumes, vapors, or gases.
52 | P a g e
Port KC – Warehouse Demolition – Woodswether Terminal
January 27, 2017
2. Methods of heating and fuel shall be suitable for particular purposes.
Portable heaters shall be standard approved units with controls.
3. Cost for temporary heat, cooling and ventilation shall be paid by Contractor.
B. Use of Existing Systems:
1. Existing systems shall not be used for temporary heating, cooling, or
ventilating.
3.4 TEMPORARY WATER:
A. Use of Existing System:
1. Owner's existing system may be used for temporary potable or non- potable
water. Contractor shall coordinate with the City Public Works Department
for access and supply of temporary water to be used for the Work
2. Contractor shall provide meters if requried and pay for all potable and non-
potable water required for the Project.
B. Temporary Water Source:
1. Contractor shall coordinate with the City Public Works Department for the
supply of temporary water to be used for the Work.
2. Contractor shall provide all connections from the City’s source to the Site,
as necessary.
3. Cost for temporary water shall be paid by Contractor.
3.5 TEMPORARY TELEPHONE AND INTERNET SERVICE:
A. General:
1. Owner will not provide telephone or internet service.
3.6 TEMPORARY SANITARY FACILITIES:
A. Contractor-Furnished Facilities:
1. Furnish, install, and maintain temporary sanitary facilities for use through
construction period by Contractor, Owner’s Representative, and Owner.
Remove on completion of Work.
2. Provide for all construction workers under this Contract.
3. Toilet facilities shall be of the chemical, aerated recirculation, or
combustion type, properly vented, and fully enclosed with a glass- fiber-
reinforced polyester shell or similar nonabsorbent material.
B. Wash Facilities:
1. Install potable water-supplied wash facilities at locations convenient to
construction personnel involved in the handling of compounds and
materials where wash-up is necessary to as required to maintain a safe,
healthy and sanitary condition.
53 | P a g e
Port KC – Warehouse Demolition – Woodswether Terminal
January 27, 2017
2. Where recommended or required by governing authorities and regulations
or recognized standards provide emergency safety showers, emergency eye-
wash fountains, showers, and similar facilities. Dispose of drainage
properly. Supply soap and other cleaning compounds appropriate for each
condition.
C. Drinking Water Fixtures:
1. Provide containerized tap-dispenser type drinking water units.
2. Supply and maintain toilet tissue, paper towels, paper cups and similar
disposable materials as appropriate for each facility. Provide appropriate
covered waste containers for used material.
3. Costs for providing temporary sanitary facilities shall be paid by Contractor.
D. Use of Existing Facilities:
1. Existing restroom facilities shall not be used.
3.7 SEWERS AND DRAINAGE:
A. General:
1. Provide temporary containers as required to remove, treat and dispose of
contaminated effluent off the Site in accordance with Applicable Law.
B. Use of Existing Facilities:
1. Existing onsite sewers shall not be used.
2. Wastes, oils, chemicals, etc. shall not be discharged to the onsite sewers at
any time. These materials shall be properly handled and disposed in
accordance with SECTIONS 025100 and 025500.
3. No materials shall be discharged to the onsite ponds or Ohio River.
3.8 TEMPORARY CONSTRUCTION AIDS:
A. General:
1. Provide construction aids and equipment required by personnel and to
facilitate the execution of the Work; lighting, scaffolds, staging, ladders,
stairs, ramps, runways, platforms, railings, hoists, cranes, chutes, and other
such facilities and equipment.
2. Materials may be new or used, must be suitable for the intended purpose,
and meet the requirements of applicable codes, regulations, and standards.
B. Use of Existing Elevators, Hoists, and Similar Facilities:
1. Existing facilities shall not be used.
C. Temporary Onsite Fuel Tanks
1. No fuel tanks larger than 5 gallons shall be stored on site.
Missouri River.
54 | P a g e
Port KC – Warehouse Demolition – Woodswether Terminal
January 27, 2017
3.9 TEMPORARY FIRE PROTECTION:
A. General:
1. Contractor shall be responsible for development of a fire prevention and
protection program for all Work.
2. The program shall comply with the applicable provisions for safety and
protection specified in the Contract Documents and with applicable parts of
the NFPA 10 and 241.
3. Locate fire extinguishers where convenient and effective for their intended
purpose, but not less than one extinguisher on each floor at or near such
usable stairwell, or in each Work area.
4. Store combustible materials in containers in fire-safe locations.
5. Maintain unobstructed access to fire extinguishers, fire hydrants, temporary
fire protection facilities, stairways, and other access routes for fighting fires.
Prohibit smoking in hazardous fire exposure areas.
6. Provide supervision of welding operations and similar sources of fire
ignition.
7. Post warning and instructions at each extinguisher location, and instruct
construction personnel on proper use of extinguishers and other available
facilities at Project Site. Post local fire department telephone number on or
near each Work area within the Project Site.
3.10 INSTALLATION AND REMOVAL:
A. Relocation:
1. Relocate aids as required by progress of demolition, storage limitations, or
Work requirements and to accommodate requirements of Owner and other
contractors at the Site.
B. Removal:
1. Remove temporary materials, equipment, and services at completion of the
Project.
C. Repair:
1. Clean and repair damage caused by installation or by use of temporary
facilities.
2. Grade the areas of the Site affected by temporary installations to required
elevations and clean the area.
END OF SECTION 015600
55 | P a g e
Port KC – Warehouse Demolition – Woodswether Terminal
January 27, 2017
Section 017800
Contract Closeout
56 | P a g e
Port KC – Warehouse Demolition – Woodswether Terminal
January 27, 2017
SECTION 017800 - CONTRACT CLOSEOUT
PART 1 - GENERAL
1.1 SUMMARY:
A. This Section includes administrative and procedural requirements for Contract closeout
including, but not limited to, the following:
1. Inspection procedures.
2. Project record document submittal.
3. Final cleaning.
B. Closeout requirements for specific demolition Activities are included in the appropriate
Sections of the Specifications.
C. Related Work Specified Elsewhere:
1. Submittals: SECTION 013300.
1.2 DEFINITIONS
A. The meanings for all defined terms are identified in SECTION 014200.
1.3 SUBSTANTIAL COMPLETION:
A. Preliminary Procedures:
1. Before requesting inspection for Certification of Substantial Completion,
complete the following and list exceptions in the request:
a. In the Application for Payment that coincides with, or first follows, the date
Substantial Completion is claimed, show 100% completion for the Work.
Include supporting documentation for completion as indicated in these
Contract Documents and a statement showing an accounting of changes
to the Contract Price.
If 100% completion cannot be shown, include a list of incomplete items,
the value of incomplete Work, and reasons the Work is not complete
(the Punch List Items).
2. Submit damage or settlement surveys, property surveys, and similar final record
information.
3. Discontinue and remove temporary facilities from the Site, along with demolition
tools and similar elements.
4. Complete final cleanup requirements..
B. Inspection Procedures:
1. Contractor shall provide to Owner and Owner’s Representative at least 3 day
written notice of requested inspection.
2. On receipt of a request for inspection, Owner and Owner’s Representative will
57 | P a g e
Port KC – Warehouse Demolition – Woodswether Terminal
January 27, 2017
either proceed with inspection or advise Contractor of unfilled requirements.
Owner’s Representative will prepare the Certificate of Substantial Completion
following inspection or advise Contractor of demolition that must be completed or
corrected before the certificate will be issued.
3. Owner and Owner’s Representative will repeat inspection when requested and
assured by Contractor that the Work is Substantially Complete.
4. Results of the completed inspection will form the basis of requirements for final
acceptance.
1.4 FINAL ACCEPTANCE:
A. Preliminary Procedures:
1. Before requesting final inspection for certification of Final Acceptance and final
payment, complete the following. Please list all exceptions in the request.
a. Submit the final payment request with releases and supporting documentation
not previously submitted and accepted. Include insurance certificates for
products and completed operations where required.
b. Submit consent of surety to final payment.
c. Submit evidence of final, continuing insurance coverage complying with
insurance requirements described in the Agreement.
B. Re-inspection Procedure:
1. Owner and Owner’s Representative will re-inspect the Work upon receipt of notice
that the Work, including Punch List items from earlier inspections, has been
completed, except for items whose completion is delayed under circumstances
acceptable to Owner.
a. Upon completion of re-inspection, Owner’s Representative will prepare a
certificate of final acceptance. If the Work is incomplete, Owner will advise
Contractor of Work that is incomplete or of obligations that have not been
fulfilled but are required for final acceptance.
2. If necessary, re-inspection will be repeated.
PART 2 - PRODUCTS (NOT APPLICABLE)
PART 3 - EXECUTION
3.1 FINAL CLEANING:
A. General:
1. Contractor shall keep the Site free from accumulations of waste materials, rubbish,
and other debris resulting from the Work. Regular Site cleaning is included in
SECTION 015300.
B. Cleaning:
1. Employ experienced workers or professional cleaners for final cleaning.
58 | P a g e
Port KC – Warehouse Demolition – Woodswether Terminal
January 27, 2017
a. Complete the following cleaning operations before requesting inspection for
certification of Substantial Completion.
Clean the Site, including landscape development areas, of rubbish, litter,
and other foreign substances. Sweep paved areas broom clean; remove
stains, Spills, and other foreign deposits. Rake grounds that are neither
paved nor planted to a smooth, even-textured surface.
b. Remove temporary structures, tools, Equipment, supplies, and surplus
materials.
c. Remove temporary protection devices and facilities which were installed to
protect previously completed Work.
C. Special Cleaning:
1. Cleaning for specific units of Work is specified in applicable Sections of
Specifications.
D. Removal of Protection:
1. Remove temporary protection and facilities installed for protection of the Work
during demolition.
E. Compliance:
1. Comply with regulations of authorities having jurisdiction and safety standards for
cleaning. When not otherwise indicated in the Contract Documents, the following
shall apply:
a. Do not burn waste or debris materials.
b. Do not discharge volatile, harmful, or dangerous materials into drainage
systems.
c. Remove waste and debris materials from the Site and dispose of lawfully.
F. Repairs:
1. Repair roads, fences, and other items damaged or deteriorated because of
demolition operations.
END OF SECTION 017800
59 | P a g e
Port KC – Warehouse Demolition – Woodswether Terminal
January 27, 2017
DIVISION 02
EXISTING
CONDITIONS
60 | P a g e
Port KC – Warehouse Demolition – Woodswether Terminal
January 27, 2017
Section 024100
Demolition
61 | P a g e
Port KC – Warehouse Demolition – Woodswether Terminal
January 27, 2017
DIVISION 2 - EXISTING CONDITIONS
SECTION 024100 – DEMOLITION
PART 1 - GENERAL
SUMMARY:
A. This Section includes the decommissioning, dismantlement, demolition, and removal
requirements of non-regulated materials for Contractor’s Work indicated and referenced
in SECTION 011100 and specified herein.
RELATED SECTIONS:
A. DIVISION 01 SECTIONS
B. Material and Waste Management: SECTION 025100
C. Regulated and Hazardous Materials Transport: SECTION 025500
D. Asbestos Abatement: SECTION 028200
E. DIVISIONS 31 AND 32 SECTIONS
DEFINITIONS
A. The meanings for all defined terms are identified in SECTION 014200.
SUBMITTALS:
A. Submit as specified in DIVISION 01.
ONSITE SUPERINTENDENT QUALIFICATIONS
A. Contractor’s Superintendent shall provide a full-time, resident onsite person qualified to
manage and direct all aspects of the Work to be conducted by the Contractor and its
subcontractors.
B. Superintendent shall have a minimum of 5 years experience directing asbestos abatement
and demolition activities at facilities with similar equipment (i.e. process equipment,
storage tanks, electrical substations, etc.) and structures.
C. Superintendent shall be the same person for both the asbestos abatement and demolition
portions of the project. The proposed Superintendent identified in the bid documents shall
not be replaced without written approval of the Owner.
1. To request a change in Superintendent for the project, an RFI shall be submitted to
the Owner at least 2 weeks before the planned replacement.
2. The RFI shall include a resume and documentation that the replacement
Superintendent has the minimum experience and training for this project.
3. Owner reserve the right to reject the request for replacement and require the
Contractor to provide another qualified candidate for review.
62 | P a g e
Port KC – Warehouse Demolition – Woodswether Terminal
January 27, 2017
SITE CONDITIONS:
A. Owner will not occupy either the buildings or areas in the asbestos abatement or
demolition Work areas.
B. Condition of Structures to be demolished:
1. Owner assumes no responsibility for actual condition of structures and utilities in
the Work to be decommissioned and demolished.
2. Site conditions existing at time of inspection for bidding purposes will be
maintained by Owner to the extent practicable.
3. All buildings and other structures on the Site to be demolished will be vacated by
Owner and use discontinued prior to the start of the Work.
C. Protections:
1. Ensure the safe passage of persons on public rights of way around the area of
demolition. Conduct operations to prevent injury to persons, and to adjacent
buildings, structures, railroad tracks, water lines designated to remain, roadways,
and other facilities that are to be removed in subsequent phases or will remain after
Substantial Completion. Restrict access temporarily (if possible) or erect temporary
covered passageways as required to ensure safe passage of persons on public rights
of way during the conduct of the operations.
2. Provide interior and exterior shoring, bracing, or support to prevent movement,
settlement, or collapse of structures to be demolished and Adjacent Facilities to
remain.
3. Protect Adjacent Facilities and neighboring landowners property from dust and
damage caused by the Work.
4. Remove protections at completion of Work.
D. Explosives:
1. The use of explosives is not permitted.
E. Traffic:
1. Conduct demolition operations and the removal of debris and salvaged material to
ensure no interference with roads, streets, walks, railroad track operations and other
adjacent occupied or used facilities that will remain after the Work.
2. Do not close, block, or otherwise obstruct streets, walks, or other occupied or used
facilities without prior permission from the Owner, City, or other jurisdictional
authority. Provide alternate routes around closed or obstructed traffic ways if
required.
3. Observe and enforce vehicle speed limit of 15 mph or less on the Site to minimize
fugitive dust generated from vehicle traffic.
F. Promptly report to Owner any damage caused to Adjacent Facilities or adjacent property
caused by the demolition and/or remediation operations and promptly repair any such
damage at no cost to Owner or owners of the Adjacent Facilities or property.
63 | P a g e
Port KC – Warehouse Demolition – Woodswether Terminal
January 27, 2017
G. Utility Services:
1. Maintain existing utilities indicated to remain; keep in service and protect against
damage during demolition operations. Utilities that shall be protected include:
a. Existing water line designated to be protected as shown in the Contract
Drawings.
2. Do not interrupt existing utilities serving occupied or used facilities including
neighboring businesses and property, except when authorized in writing by the
Owner’s Representative or Owner. Provide temporary services during interruptions
to existing utilities.
3. Contractor shall verify disconnection of utilities serving each structure and area
included in the demolition activities when authorized by the Owner’s
Representative and Owner. Disconnecting, locking out and tagging indicated
utilities before starting demolition operations and maintaining disconnection during
the Work shall be the responsibility of Owner.
PERMITS
A. Contractor shall obtain and comply with all local, state and federal Permits and their
associated requirements to conduct the demolition prior to starting the Work in
accordance with SECTION 013300.
1. Contractor will pay for any permit fees required to obtain the permits.
2. Contractor will be responsible for conducting all demolition Work in accordance
with any permits including activities not specifically called out in the Contract
Documents.
3. In the event that the permit requirements include activities not explicitly included
in the specification, Contractor shall comply and include in its cost the activities
required to fully comply with any permits.
PART 2 - PRODUCTS
MATERIALS FOR ABANDONMENT OF UNDERGROUND FACILITIES
A. Material for the filling of the below ground structures identified in paragraph 3.06 of this
Part shall meet the specification provided in SECTION 312323.
B. Other underground utilities shall be sealed at the ends with grout or flowable fill of
mixture and strength to adequately fill, set, and provide a seal at both ends a distance of
at least 3 times the diameter of the pipe into the each Underground Facilities present at
the Project Site. Grout mix may vary depending on size and construction of piping, and
intended method of placement.
1. Type I Portland cement grout complying with ASTM C150
2. Fine and coarse aggregates complying with ASTM C33
3. Low strength concrete having the following specifications:
64 | P a g e
Port KC – Warehouse Demolition – Woodswether Terminal
January 27, 2017
4. Compressive strength (28-day) minimum: 1,200 psi
5. Aggregate size (maximum): 1 inch
6. Slump: 6 inches (+ / - 1 inch)
7. Air content: 4 to 6 percent
8. Cement content: minimum 200 lbs. per cubic yard
SALVAGEABLE MATERIALS:
A. Remove and return the following equipment and materials to Owner:
1. NONE
B. Remove, store, redesign as required, and reinstall as indicated the following equipment
and materials:
1. NONE
C. All other existing items and materials to be removed shall become the property of
Contractor, except for Hazardous, Special or TSCA Waste. Contractor shall manage all
materials in accordnace with SECTION 025100.
D. All recycled materials shall be tracked as part of the overall project. Owner strongly
encourages recycling of materials. Tracking manifests or bills of lading including types
of materials, weight of the materials and final location for recycling shall be provided on
a weekly basis throughout the project. Any final documentation not provided during the
project shall be provided prior to the acceptance of final payment.
PART 3 - EXECUTION
GENERAL
A. Provide, erect and maintain temporary controls as indicated in the applicable DIVISION
1 Sections.
B. Demolition activities shall conform to all Applicable Law and Codes for demolition of
structures, safety of adjacent structures, dust control, noise control, service utilities and
hazardous materials management. Work shall be conducted without interference to public
or access to public areas. Dust control and management of loose material that may become
airborne during demolition shall prevent dust migration and loose material transport to
Adjacent Facilities.
C. Cleanup to the pre-Work condition any dust that migrates off Site to Adjacent Facilities.
Cleanup of any dust that migrates to Adjacent Facilities shall be the sole responsibility of
Contractor at no additional cost to Owner.
D. Ensure that site drainage, designated drainage structures, natural drainage or diversions
are not obstructed during the Work. Maintain these structures and drainage ways during
the conduct of the Work.
E. Manage all materials and wastes in accordance with SECTION 025100.
65 | P a g e
Port KC – Warehouse Demolition – Woodswether Terminal
January 27, 2017
INSPECTION:
A. Prior to commencement of demolition Work, inspect areas in which demolition will be
performed. Photograph existing conditions of structures, surfaces, equipment, or
surrounding properties which could be misconstrued as damage resulting from demolition
operations. File record photographs with Owner prior to starting Work.
PREPARATION:
A. Contractor must secure approval from the Owner’s Representative in writing indicating
that all Regulated Materials have been satisfactorarily removed, and other elements of the
environmental abatement Work, including but not limited to asbestos abatement, have
been completed, prior to building demolition.
B. Contractor shall remove, treat and dispose of all standing water and other liquids from all
basements and sumps within the Work Area.
C. It will be the responsibility of Contractor to remove, treat and dispose this water off the
Site at an approved facility in accordance with Applicable Law and SECTIONS 025100
and 025500.
D. All piping, conduits, and Underground Facilities shall be decommissioned by Contractor
in accordance with following when specified as Contractor’s responsibility in DIVISION
01:
1. Contractor shall locate all piping, conduits, and Underground Facilities including,
but not limited to, petroleum based fluids, automotive fluids, hydraulic fluid, fuel
oil, industrial sewer, solvent, de-icing fluid, and used oil piping.
2. All aboveground and below ground piping, tanks and conduits shall be drained and
be free of free-flowing liquids and flammable vapors and cleaned prior to being
released for general demolition. All of these items shall be cleaned prior to
demolition. Cleaning means to flush water or cleaning agent by hydro-mechanical,
hydro-jetting, or other methods as approved by the Owner’s Representative or
Owner. Cleaning shall be sufficient to remove all liquids or solids from the pipeline
such that it may be properly disposed offsite. In the event that, any remaining
material cannot be removed (i.e. solid residual oil, etc.), the piping shall be cut out
and disposed in accordance with SECTION 025100.
3. Disconnect supply lines from the each associated apparatus and drain and clean all
existing piping, conduits, and Underground Facilities including process piping,
utility piping, and sewers. This includes the removal of residual accumulations of
solids and liquids, or verification that no residuals exist in these lines.
4. Residual liquids and solids may contain elevated concentrations of Regulated
Materials. Remove and manage all residual materials contained in the piping,
conduits, and Underground Facilities in accordance with SECTION 025100 and
Applicable Law prior to decommissioning. No information regarding the amounts
of residual water and/or solids, if any, in these lines is available.
5. Contractor shall inspect the piping, conduits, and Underground Facilities with
Owner and/or Owner’s Representative to determine the presence and magnitude of
residual contents. If present, the contents of the piping shall be characterized by
66 | P a g e
Port KC – Warehouse Demolition – Woodswether Terminal
January 27, 2017
Contractor. Contractor shall, in conjunction with the Owner’s Representative,
determine the most logistically feasible points at which to sample the contents of
piping, conduits, and Underground Facilities. Contractor shall employ all
appropriate spill control measures prior to opening any piping, conduits, and
Underground Facilities, as identified in Contractor’s Spill Control Plan.
6. Contractor shall be responsible for identifying the locations, drain points, and
termination points of all piping, conduits, and Underground Facilities prior to
draining. If sections of piping, conduits, and Underground Facilities run under the
floor slab, Contractor shall address these areas per this section.
7. Contractor may disconnect and remove portions of piping, conduits, and
Underground Facilities to facilitate the pipe draining efforts. Contractor must
employ all spill control measures, according to Contractor’s Spill Control Plan. Any
spillage of such materials shall be immediately recovered by Contractor. In addition,
any other building surfaces or media impacted by spillage of piping residuals shall
be decontaminated or abated at no further cost to Owner.
8. Locate and remove oil trap assemblies that contain appreciable amounts of oil from
the respective air lines. Drain each designated oil trap of free-flowing oil. The oil
may be consolidated with other oil removed from the Work. Once drained of oil,
traps may be included with the general demolition debris for disposal.
9. Cut and cap piping, conduits, and underground utilities that penetrate foundations or
basement walls. Cut flush with grade or wall and fill at least 3 times the diameter of
the pipe with grout or flowable fill per the requirements in this section.
E. Contractor shall identify and note above grade concrete with visible oil staining which
will be removed. Stained concrete shall be segregated and disposed of offsite in
accordance with SECTION 025100, and not be reused at the site.
F. Mercury switches (MerCoid) and other mercury containing devices (i.e. pressure gauges,
thermometers, etc.) that remain in the facility shall be removed and disposed by
Contractor and managed as Universal Waste. Mercury containing devices shall be
extracted and disposed in whole (i.e. do not break and remove mercury) to prevent
releases.
G. Provide interior and exterior shoring, bracing, or support to prevent movement,
settlement, or collapse of structures to be demolished and adjacent facilities to remain:
1. In accordance with the Site Health and Safety Plan, cease operations and notify
Owner and Owner’s Representative immediately of any unsafe conditions. Take
precautions to support structure until determination is made for continuing
operations.
H. Contractor shall establish and maintain a noise, dust, vibration, and track-out control
system.
I. Locate, identify, stub off, and verify that Underground Facilities and utility services that
are indicated to remain have been disconnected.
1. Provide minimum of 72 hour advance written notice to Owner if shutdown of
service is necessary during demolition.
DEMOLITION:
67 | P a g e
Port KC – Warehouse Demolition – Woodswether Terminal
January 27, 2017
A. Perform demolition in a systematic manner. Use such methods as required to complete
demolition in accordance with demolition Schedule and governing regulations.
B. Locate demolition equipment and promptly remove debris in order to avoid imposing
excessive loads on supporting walls, floors, or framing.
C. Demolish foundation walls to existing grade as specified in the Contract Drawings.
D. If unanticipated mechanical, electrical, or structural elements which conflict with intended
Work are encountered, Contractor shall investigate and measure both nature and extent of
the conflict. Submit report to Owner and Owner’s Representative in written, accurate
detail. Contractor shall follow the procedures in Section 9 of the Decommissioning and
Demolition Services Agreement for changes in scope. Rearrange demolition Schedule as
necessary to continue overall job progress without delay.
E. Pollution Controls:
1. Use water sprinkling, temporary enclosures, and other suitable methods to limit the
amount of dust and dirt rising and scattering in the air to the lowest practical level.
Comply with Applicable Law pertaining to environmental protection.
2. Collect and properly dispose of water that is used for pollution control or wash
down.
3. Provide services for effective air and water pollution controls as required by
Applicable Law.
4. Limit use of water when it may create hazardous or objectionable conditions such
as ice, flooding, and pollution.
5. Clean Adjacent Facilities and property of dust, dirt, and debris caused by demolition
operations.
ABANDONMENT OF BELOW-GROUND STRUCTURES
A. Abandon any below-ground structures within the Project Site according to the procedures
described herein. Below-ground structures shall include: foundations; below grade walls;
current and former equipment pits, manholes, vaults, deep trenches, sumps, tunnels, and
any other similar structures but shall not include any below-ground structures designated
for filling under Section 3.06. For the purposes of this section, abandonment of below-
ground structures entails:
1. Capping underground piping or protrusions in foundation walls or floor that will
remain;
2. Filling of basements, pits, tunnels and other below-ground structures with concrete
removed and crushed onsite.
3. Manhole covers and rings shall be removed and backfilled in soil areas. The
manhole structure shall be filled with controlled low strength material (CLSM) in
accordance with SECTION 312323 following removal of the cover and ring. Pipes
exiting the manholes or cavities shall be sealed or plugged prior to placement of the
CLSM backfill.
4. Manhole covers in concrete and asphalt paved areas shall be secured to rings (either
68 | P a g e
Port KC – Warehouse Demolition – Woodswether Terminal
January 27, 2017
bolted or welded) and left in place. The underground manhole structure shall be
filled with controlled low strength material (CLSM) in accordance with SECTION
312323 prior to securing the manhole covers. Pipes exiting the manholes or cavities
shall be sealed or plugged prior to placement of the CLSM backfill.
FILLING OF BELOW GROUND STRUCTURES
A. All below ground structures shall be filled in accordance with SECTION 312323 and the
Contract Drawings to match the existing grade of the surrounding area.
B. Contractor shall fill all segments of underground structures per the contract limits in such
a manner to minimize the occurrence of voids, until piping is completely filled.
CAPPING OF UNDERGROUND FACILIITIES
A. Capping shall be employed to minimize storm runoff or other materials from infiltrating
the Underground Facilities, including but not limited to sanitary, storm, and industrial
sewer system piping that will remain in place.
B. Capping will also be accomplished for any piping or other protrusions from the foundation
walls or floor to remain in place.
C. Contractor to flush out underground facilities to be abandoned in place prior to capping.
Flush water and fluids shall be captured, characterized an properly disposed in accordance
with SECTION 025100 and Applicable Law.
D. Capping of Underground Facilities shall comply with Applicable Law. If no local
requirements are in place, Contractor shall provide the intended type of cap and method
of installation to the Owner’s Representative for review and approval. All underground
piping and conduits, regardless of size, must be capped at both ends unless otherwise
identified.
E. Methods for capping may include, but not be limited to, flush-mount expandable caps,
fitted steel or hard plastic caps with water tight sealant, foam fill (surficial only), concrete
cap, or other equivalent method.
SALVAGE
A. Contractor shall take title to all Salvagable Material when such Salvagable Material is
loaded onto a Contractor’s or Subcontractor’s vehicle.
B. Contractor shall identify the location and provide weight tickets for all Salvagable
Material removed from the site.
C. Location and weight tickets shall be submitted to the Owner’s Representative on a weekly
basis as the project proceeds.
D. Contractor is responsible for the security of Salvagable Materials as they are being
stockpiled onsite prior to the Contractor taking title to these materials.
DISPOSAL AND TRANSPORT OF DEMOLITION MATERIALS:
A. All materials and wastes generated by the demolition operations shall be transported and
disposed of, recycled or reused in accordance with SECTIONS 025100 and 025500.
B. Burning of removed materials from demolished structures is not permitted.
69 | P a g e
Port KC – Warehouse Demolition – Woodswether Terminal
January 27, 2017
CLEANUP, BACKFILL, AND REPAIR:
A. Upon completion of the Work, remove tools, equipment, and demolished materials from
Site. Remove protections and restore the site in accordance with final grading plan.
B. Final grading shall be completed in accordance with the Contract Drawings and
DIVISIONS 31 and 32.
C. Any silt fencing and other erosion/sedimentation controls required as part of the SWPPP
shall be removed upon completion of the Work or termination of related permits.
END OF SECTION 024100
70 | P a g e
Port KC – Warehouse Demolition – Woodswether Terminal
January 27, 2017
Section 025100
Materials and Waste
Management
71 | P a g e
Port KC – Warehouse Demolition – Woodswether Terminal
January 27, 2017
SECTION 025100 – MATERIALS AND WASTE MANAGEMENT
PART 1 - GENERAL
1.1 SUMMARY
A. Contractor shall furnish all labor, materials, equipment, and related items required for
the proper handling, transportation and disposal of all materials generated during the
Work. For the purpose of this specification, the material or waste types that may are
expected to be encountered at the site are as follows:
1. Salvage: Metals and other materials with intrinsic value which Contractor will
take ownership of and provide Owner with a credit.
2. Recyclable Materials: Materials without intrinsic value that may be recycled
such as crushed concrete, bricks, etc.
3. Non-hazardous Solid Waste: Debris that is not regulated as Hazardous Waste or
Special Waste and which can be disposed at an Owner-approved disposal facility.
4. Hazardous Waste: waste regulated under the Resource Conservation and
RecoveryAct (RCRA)
5. Asbestos Containing Wastes: wastes regulated under National Emission Standards
for Hazardous Air Pollutants (NESHAP)
6. Polychlorinated biphenyl (PCB) Impacted Waste: waste regulated under
theToxic Substance Control Act (TSCA)
7. Universal Wastes: wastes regulated under the Resource Conservation and
RecoveryAct (RCRA)
8. Potentially contaminated surface water or groundwater.
9. Other waste classification which prohibits disposal at a solid waste landfill.
B. Contractor is responsible for determining the proper characterization of all materials
generated during the Work and recycling or disposal methods to ensure that waste is
recycled or disposed according to procedures that are consistent with Applicable Law.
This shall be accomplished through coordination with the Owner’s Representative as
described herein.
C. Note: the term “waste management” herein is a general term referring to the management
of waste streams, and is not meant to refer to any waste handling companies with similar
titles.
1.2 RELATED SECTIONS
A. The requirements of this section apply to ALL elements of the Work. Related sections
include, but are not limited to, all DIVISION 1 and DIVISION 2 sections, where relevant
and applicable:
72 | P a g e
Port KC – Warehouse Demolition – Woodswether Terminal
January 27, 2017
1.3 DEFINITIONS
A. The meanings for all defined terms are identified in SECTION 014200.
1.4 SUBMITTAL AND PROJECT RECORD DOCUMENTS
1. Waste Management Plan
2. Waste Management Records
1.5 QUALIFICATIONS
A. Contractor will identify to Owner the waste disposal facility to be used by Contractor for
disposal of Non-Hazardous Solid Waste. The designated waste disposal facility must be
licensed and approved by the appropriate local, state, and/or federal agency for the
intended use.
B. Contractor will identify to Owner the recycling firms and facilities to be used by
Contractor. The designated recycling firms and facilities must be licensed and approved
by the appropriate local, state, and/or federal agency for the intended use.
1.6 SCHEDULING
A. Contractor must identify the waste management and disposal procedures in Contractor’s
Waste Management Plan for Owner’s approval.
B. Contractor must identify the materials to be recycled, sources of materials and recycling
firms to be used in Contractor’s Execution Plan for Owner’s approval.
1.7 PERMITTING
A. Contractor shall ensure that it and its Subcontractors have any and all required permits
and authorizations and their respective employees have any and all required certifications
and training to allow them to handle, package, transport, and dispose of all Regulated,
Special, Asbestos, TSCA, Universal, Hazardous Wastes generated during the course of
the Work in accordance with Applicable Law.
PART 2 - PRODUCTS
2.1 PACKAGING MATERIALS AND PRODUCTS
A. Packaging materials allowed include, but are not limited to, the following:
1. Removable head drums or steel roll-off boxes, DOT approved.
2. Miscellaneous plastic bags.
3. Drum labels and markings which conform to the requirements of 40 CFR 262,
29 CFR 1926 and Applicable Law.
4. Water and liquid storage tanks of appropriate chemical compatibility with
73 | P a g e
Port KC – Warehouse Demolition – Woodswether Terminal
January 27, 2017
wastes generated during the Work to be determined by Contractor.
B. Spill prevention and countermeasure materials and control products in accordance with
Contractor’s Spill Control Plan, including plastic sheeting and absorbent materials
consistent with the requirements of Title 49 CFR 173 and all Applicable Law.
PART 3 - EXECUTION
3.1 WASTE CHARACTERIZATION
A. Waste streams are to be characterized by Contractor as designated in these specifications
and in accordance with Contractor’s Waste Management Plan. Contractor shall sample
and analyze waste material for characterization purposes in accordance with requirements
of the receiving facility and Applicable Law. Analysis must be conducted by a NELAP
certified laboratory. Contractor shall include the methods and procedures it proposes for
the sampling and analysis of materials generated in the Waste Management Plan.
B. Contractor must determine the material waste profile for disposal based on
characterization results, generator knowledge, and other pertinent information. Waste
profiles developed by Contractor must be reviewed and approved by the Owner’s
Representative and/or Owner.
C. In the event that Contractor is unable to determine the classification or profile of a waste,
Contractor must notify the Owner’s Representative. Contractor must supply a detailed
description of the waste to be disposed and a sample of the waste, if requested, to the
Owner’s Representative to assist in determining the characteristic and/or profile of the
waste material.
D. All empty containers produced by Contractor that had previously contained Hazardous
Waste must be disposed as a Hazardous Waste unless the container meets requirements
and standards of Applicable Law for an “empty container” and is approved for alternative
disposal by Owner.
3.2 SALVAGABLE MATERIALS AND NON REGULATED WASTE
A. Contractor shall manage all Salvageable Materials in accordance with Applicable Law.
3.3 RECYCLABLE MATERIALS
A. Contractor shall manage all recyclable materials in accordance with Applicable Law.
B. Contractor is responsible for any characterization or profiling that may be required as part
of the recycling process.
C. Material recycling shall be conducted in accordance with all Applicable Law.
3.4 STORAGE AND PACKAGING OF WASTES AND RECYCLABLE MATERIALS
A. Contractor is to establish secured storage area(s) on the Site for temporary storage of all
waste materials as necessary. The storage facility must meet the requirements under
Applicable Law for the particular waste being stored.
74 | P a g e
Port KC – Warehouse Demolition – Woodswether Terminal
January 27, 2017
B. Contractor shall store all hazardous and liquid waste in containers appropriate for
transport as required by Applicable Law.
C. Prior to removal from the Project Site, combustible debris must be stored/managed in
such a manner to prevent combustion.
3.5 NON-HAZARDOUS WASTE GENERATION AND DISPOSAL
A. Contractor shall obtain approval of Owner in writing prior to disposal of any wastes
characterized as Non-Hazardous Waste.
B. Contractor shall identify to Owner for approval the waste disposal facility to be used by
Contractor for disposal of Non-Hazardous Solid Waste. The designated waste disposal
facility must be approved by Owner prior to use.
3.6 HAZARDOUS WASTE GENERATION AND DISPOSAL
A. Contractor shall manage all Hazardous Waste in accordance with Applicable Law
B. Contractor shall obtain approval of Owner in writing prior to disposal of any wastes
characterized as Hazardous Waste.
C. Contractor shall identify to Owner for approval the waste disposal facility to be used by
Contractor for disposal of Hazardous Waste. The designated waste disposal facility must
be approved by Owner prior to use.
D. A Hazardous Materials Survey was completed in addition to the Asbestos Survey (Exhibit
A). This inventory is not all-inclusive; there may be additional hazardous or regulated
wastes within the Work Area that require proper disposal.
E. Lead-based Paint (LBP )
1. EPA and the Department of Housing and Urban Development (HUD) defines lead-
based paint as paint or other surface coating that contains lead greater than or
equal to 0.5 percent by weight (5,000 micrograms per gram (ug/g) or 5,000 parts
per million (ppm) by weight). Based on the age of the buildings it is assumed that
paints within the building may contain lead. No lead sampling was performed as
part of this Hazardous Materials Survey. However, Contractor should treat all
paints as lead containing unless testing proves otherwise.
2. Components which contain lead do not necessarily need to be removed prior to
demolition activities; however, deteriorated lead-based paint inside occupied areas
may need to be removed prior to demolition activities to reduce the risk of exposure
to contractors. Contractor needs to be made aware of the presence and locations of
LBP and take the necessary precautions to protect their workers which may include
personal protective equipment (PPE) and/or removal of flaking/peeling paint.
OSHA regulations indicate air-monitoring must be conducted during demolition
activities in affected areas which contain lead.
75 | P a g e
Port KC – Warehouse Demolition – Woodswether Terminal
January 27, 2017
3.7 ASBESTOS CONTAINING MATERIALS GENERATION AND DISPOSAL
A. Contractor shall manage all Asbestos-containing materials in accordance with Applicable
Law and SECTION 028200.
B. Contractor shall obtain approval of Owner in writing prior to disposal of any wastes
characterized as Friable or Non-Friable Asbestos Containing Material.
C. Contractor shall identify to Owner for approval the waste disposal facility to be used by
Contractor for disposal of Friable and Non-Friable Asbestos-Containing Waste. The
designated waste disposal facility must be approved by Owner prior to use.
3.8 TSCA WASTE GENERATION AND DISPOSAL
A. Contractor shall manage all TSCA Waste in accordance with Applicable Law
B. Contractor shall obtain written approval of Owner prior to disposal of any wastes
characterized as TSCA Waste.
C. Contractor shall identify to Owner for approval the waste disposal facility to be used by
Contractor for disposal of TSCA Waste. The designated waste disposal facility must be
approved by Owner prior to use.
D. The subject property was not inspected for electrical equipment that may contain PCBs,
which were widely used in until the mid-1970s at which time they were banned from use.
Various transformers and other oil-containing equipment have been identified at the site;
PCB levels have not been previously tested. Prior to disposal of any oils remaining in
transformers or other equipment, Contractor shall test and determine if PCBs are present.
E. Fluorescent light fixtures were present within the building and based on the age of the
building, PCB-containing ballasts could be present. Leaking or unlabeled ballasts should
be disposed as TSCA Waste.
F. Owner has not tested the Site for PCB-containing caulk materials.
G. Owner has not tested the Site for PCB-containing concrete materials. Prior to demolition,
all concrete shall be tested for PCBs in accordance with the following guidelines:
1. Sampling design:
a. All suspected stained area(s) should be sampled
b. At each separate location, collect at least 3 samples of each type of porous
surface, regardless of the amount of each type of porous surface present. At
least 1 of 3 samples should be biased toward stained surfaces (if present), with
the remainder randomly distributed over the porous surface.
c. In areas where PCB equipment was used or where PCBs were stored, samples
should be collected at a frequency of 1 sample/100 square feet.
2. Sample collection:
a. Discrete samples shall be generated by collection of drill cuttings using an
impact hammer drill.
76 | P a g e
Port KC – Warehouse Demolition – Woodswether Terminal
January 27, 2017
b. If an in impact hammer drill is used, a bit no larger than 1-inch diameter shall
be used to drill holes not to exceed 0.5-inches in depth. As necessary at each
discrete location, more than one drill hole may be required to provide adequate
sample volume/weight.
c. The minimum volume/weight of each composite sample to be analyzed shall
be governed by the laboratory requirements. The volume of any sample shall
not exceed one, four-ounce jar.
d. Sampling methods should be consistent for all samples (i.e., do not mix
chiseling samples with drilled samples).
e. Drill bits shall be decontaminated with Alconox and distilled water, rinsed
with distilled water, and dried prior to use at a different location. All other
items (spoons, gloves, equipment, etc.) that may come in contact with the
sample shall be either decontaminated using a similar approach or disposed of
and replaced with new materials between each location.
3. Sample analysis:
a. Samples shall be analyzed for polychlorinated biphenyls (PCBs) using EPA
Method 8082. Turnaround time for sample results shall be dependent on
situation requirements, method restraints, and laboratory capacity. Samples
shall be packaged in a cooler on ice so that the samples arrive at the laboratory
at +/- 4˚C.
b. A chain-of-custody shall be prepared and shipped with the samples to the
laboratory. A chain-of-custody can be obtained from the laboratory and should
be completed with signatures as noted.
3.9 PCB REMEDIATION WASTE GENERATION AND DISPOSAL
A. Contractor shall manage all PCB remediation waste in accordance with Applicable Law.
B. Wastes characterized as PCB remediation waste shall be transported off-site and disposed
of at an Owner approved facility in accordance with all Applicable Law. Contractor shall
obtain approval of Owner prior to disposal of any wastes characterized as PCB
remediation waste.
3.10 UNVERSAL WASTE GENERATION AND DISPOSAL
A. Contractor shall manage all Universal Waste in accordance with Applicable Law.
B. Contractor shall obtain approval of Owner prior to disposal of any wastes characterized
as Universal Waste.
C. Contractor shall identify to Owner for approval the waste disposal facility to be used by
Contractor for disposal of Universal Waste. The designated waste disposal facility must
be approved by Owner prior to use.
D. Fluorescent light fixtures and other spent lamps are present within the building and shall
be removed and disposed by Contractor.
77 | P a g e
Port KC – Warehouse Demolition – Woodswether Terminal
January 27, 2017
E. Mercury switches (MerCoid) and other mercury containing devices (i.e. pressure gauges,
thermometers, etc.) that remain in the facility shall be removed and disposed by
Contractor as Universal Waste. Mercury containing devices shall be disposed in whole
(i.e. do not break and remove mercury) to prevent releases.
3.11 REFRIGERANT
A. Remove refrigerant from mechanical equipment according to Applicable Law before
starting demolition and recycle or dispose of appropriately.
3.12 WASTE WATER DISPOSAL AND DISCHARGE
A. Contractor is to collect liquid waste produced during the demolition activities in
containers suitable for transport and disposal as required in the Contract Documents (i.e.
decontamination water, high pressure wash water, etc.).
B. Contractor will be required to acquire one or more samples of non-hazardous liquids from
each container for characterization.
1. Samples will be analyzed for the following parameters, at a minimum:
a. Volatile Organic Compounds (US EPA Method SW 846)
b. Polynuclear Aromatic Hydrocarbons (US EPA Method 8270 SIM)
c. RCRA Metals (US EPA Method 6010/7470/7471)
d. Glycols (US EPA Method 8015).
e. Any additional analyses necessary to obtain disposal approval.
C. Sewer discharge is not available as a disposal option for this site. Liquid waste shall be
transported and disposed of at an approved facility in accordance with all Applicable Law.
D. In the event that liquid wastes are not suitable for a particular disposal facility, Contractor,
in conjunction with the Owner’s Representative, shall determine if on- site treatment of
liquid wastes is a viable option to render the waste stream appropriate for discharge at that
facility.
E. Any on-site treatment system proposed by Contractor shall be in accordance with
Applicable Law and approved by Owner prior to use. Contractor shall be required to
demonstrate the efficiency of the treatment system through sampling and analysis prior to
effluent discharge. Any permitting, sampling, reporting for this system will be the
responsibility of and paid for by the Contractor.
In the event that the waste characterization testing indicates that the water is either a
Hazardous Waste or TSCA Waste, Contractor may not conduct on-site treatment and the
Waste shall be transported and disposed of at an approved facility in accordance with all
Applicable Law.
78 | P a g e
Port KC – Warehouse Demolition – Woodswether Terminal
January 27, 2017
3.13 TRANSPORT FOR OFF-SITE DISPOSAL
A. Contractor is to use only licensed and bonded transporters to accomplish the off-site
transport and disposal of all solid wastes, recyclable materials and hazardous/special
wastes generated during performance of the Work. Transportation shall be conducted in
accordance with SECTION 025500.
3.14 MANIFEST AND BILL-OF-LADING
A. Contractor must coordinate the preparation of shipping records, including Universal
Hazardous Waste Manifests for transport of hazardous waste as required by Applicable
Law. Contractor must submit such shipping records to Owner’s Representative or Owner
for review and signature at least 48 hours prior to off-site transport in accordance with the
Waste Management Plan. Under no circumstances shall wastes (non-hazardous or
Regulated Materials) be removed from the premises without signature by, or knowledge
of, the Owner’s Representative.
B. Contractor is required to prepare a bill-of-lading for transport of solid waste as required
by the transporter and in conformance with all applicable transport regulations and
requirements.
3.15 DISPOSAL RECEIPTS AND EXECUTED MANIFESTS
A. The Contractor is required to submit to the Owner’s Representative copies of weigh
tickets/disposal receipts and fully executed manifest copies for all wastes. All such copies
shall be issued within 48 hours of transport.
B. A listing of materials recycled including total volumes, sources of recycled materials
including locations in building and recycling firms utilized must be maintained by
Contractor and provided to Owner on a weekly basis, with any outstanding information
provided at project completion.
END OF SECTION 025100
79 | P a g e
Port KC – Warehouse Demolition – Woodswether Terminal
January 27, 2017
Section 025500
Regulated and
Hazardous Material Transport
80 | P a g e
Port KC – Warehouse Demolition – Woodswether Terminal
January 27, 2017
SECTION 025500 - REGULATED AND HAZARDOUS MATERIALS TRANSPORT
PART 1 - GENERAL
SUMMARY
A. Contractor shall furnish all labor, training, materials and equipment, and related items
required for the appropriate packaging and transportation of all Regulated Materials and
Wastes generated at the Project Site during the Work.
RELATED SECTIONS
A. The requirements of this section apply to ALL elements of the Work. Related sections
include, but are not limited to, all DIVISION 01 and DIVISION 02 sections, where
relevant and applicable:
DEFINITIONS
A. The meanings for all defined terms are identified in SECTION 014200.
REGULATORY REQUIREMENTS
A. Comply with Applicable Law for the packaging and transportation of the Regulated
Materials and Wastes.
SUBMITTALS AND PROJECT RECORD DOCUMENTS
A. Provide all required submittals as identified in SECTION 013300.
B. Complete and submit all shipping papers, Hazardous Waste Manifests, and waste
management forms described in SECTION 025100.
QUALIFICATIONS
A. Transporters used by Contractor must have all appropriate licenses and Permits, and
copies of all such documentation shall be present with each vehicle used onsite and off-
site containing waste streams generated during this Work.
B. All personnel involved with the packaging and transportation of the Regulated Materials
must have the appropriate Department of Transportion (DOT) training and provide
evidence of such training to Owner and Owner’s Representative prior to offsite
transportation.
SCHEDULING
A. Contractor shall expeditiously characterize and transport offsite for disposal Regulated
Materials in accordance with SECTION 025100.
81 | P a g e
Port KC – Warehouse Demolition – Woodswether Terminal
January 27, 2017
B. Contractor shall comply with Applicable Law regarding accumulation time limits
pertaining to Regulated Materials. For example, Hazardous Wastes shall not be stored on-
Site for more than 90 days.
PART 2 - PRODUCTS – NOT APPLICABLE
PART 3 - EXECUTION
IDENTIFICATION OF WASTE MATERIALS FOR TRANSPORTATION
A. Contractor shall be responsible for the characterization of any materials that may be
required for off-site transportation in accordance with SECTION 025100.
B. For transportation purposes, it is assumed that all materials listed under 49 CFR 172.101
are considered Hazardous Materials. Contractor shall evaluate all Regulated Materials
discovered at the facility to designate which specific materials are to be classified as
Hazardous Materials for transportation purposes.
PACKAGING, LABELING, AND PLACARDING
A. Contractor shall package all Hazardous Materials for transportation and storage in
accordance with 49 CFR 172.101, any applicable sections of 49 CFR 173 and other
Applicable Law.
SHIPPING DOCUMENTS
A. Shipping Papers
1. Contractor shall prepare the shipping papers for all shipments of non-regulated
materials in accordance with the requirements of 49 CFR 172, Subpart C and 49
CFR 172.101. Shipping papers shall be provided to the Owner’s Representative for
review and Owner’s signature prior to transport offsite.
B. Waste Management Records
1. Contractor must prepare shipping papers including any Hazardous Waste manifest
for transport of Regulated Materials in accordance with SECTION 025100.
Contractor must submit such Waste Management Records to the Owner’s
Representative for review prior to signature prior to removal of any such material
from the Site.
C. Shipment Review
1. At the time the waste manifest is prepared, Contractor must make available for
review by the Owner’s Representative all packaged and/or bulk loaded Regulated
Materials and Wastes. In the period between observation by the Owner’s
Representative and off-site transport, Contractor must make provisions to ensure
that the waste is not changed in any manner.
82 | P a g e
Port KC – Warehouse Demolition – Woodswether Terminal
January 27, 2017
D. Emergency Response
1. Contractor is to provide transporter with an Emergency Response Guide concurrently with the
manifest to the driver of the transport vehicle before the material is loaded onto the vehicle.
END OF SECTION 025500
83 | P a g e
Port KC – Warehouse Demolition – Woodswether Terminal
January 27, 2017
Section 028200
Asbestos Abatement
84 | P a g e
Port KC – Warehouse Demolition – Woodswether Terminal
January 27, 2017
SECTION 028200 - ASBESTOS ABATEMENT
PART 1 - GENERAL
1.1 GENERAL INFORMATION
A. Pre-Demolition Asbestos Inspection completed by Owner identifies the locations of the Regulated
Materials that require removal prior to demolition. A copy of this report is included in Exhibit A.
B. Contractor’s Base Bid price assumes that the building materials identified in the aforementioned
report contain asbestos requiring abatement prior to demolition activities.
1.2 REGULATORY REQUIREMENTS
A. In addition to and complimenting the Codes and Standards listed in SECTION 014200, the following
shall apply to the Work:
1. Comply with requirements and specifications of Environmental Protection Agency (EPA)
regulations, Occupational Safety & Health Administration (OSHA) regulations and State of
Missouri regulations.
2. Comply with National Emission Standards for Hazardous Air Pollutants (NESHAP), 40 CFR
Part 61, Subpart M.
B. All persons performing asbestos abatement Work shall be qualified to perform such Work. Submit
such evidence that all workers have attended training courses associated with asbestos abatement and
are certified in accordance with Applicable Law.
C. Air monitoring shall be performed by independent, third party certified asbestos inspector obtained
by Contractor.
D. Contractor shall give notification to EPA and/or state NESHAPs coordinator and other regulatory
agencies as required in advance of Work. A ten (10) day minimum notification is required.
E. Contractor shall be responsible for obtaining approval for disposal at one of the approved waste
disposal site identified in SECTION 025100.
1.3 DEFINITIONS
A. The meanings for all defined terms are identified in SECTION 014200.
1.4 SUBMITTALS
A. The following submittals will be required prior to the implementation of the asbestos abatement
activities
1. Submit Schedule and detailed procedure to be used in the abatement of asbestos in
compliance with Applicable Law.
2. Submit evidence of worker training completion and required certifications prior to
commencement of the Work.
3. Copy of EPA and/or state notification and amendments, as necessary.
4. Copies of any regulatory response or confirmation regarding asbestos abatement
5. Copy of approval for disposal at one of the approved waste disposal site identified in
85 | P a g e
Port KC – Warehouse Demolition – Woodswether Terminal
January 27, 2017
SECTION 025100
B. The following Submittals will be required during the implementation of the asbestos abatement
activities:
1. Asbestos shipping records and landfill scale tickets.
2. Submit evidence of worker training completion and required certifications for additional staff
that may Work on the abatement project.
1.5 CONTRACTOR’S RESPONSIBILITIES
A. Provide equipment and materials as required to seal off area, remove asbestos, clean area, and dispose
of asbestos in accordance with Applicable Law.
B. Provide proper worker protection clothing (including coveralls, headcover, and footwear),
respirators, filters, and other items, as required. Eye protection and hard hats shall be available as
appropriate.
C. Provide proper worker protection during abatement activities on the roof as part of the Project in
accordance with the Contractor’s Site Health & Safety Plan.
D. Provide all temporary utilities including, but not limited to, lighting, electrical extension cords,
portable light fixtures, ground fault protection, water hoses, vacuums, pumps, filters and filtering
equipment, brooms, mops, and related essential items.
E. Contractor will be responsible for providing water for use at the site to wet the materials and the bags
prior to disposal.
F. Contain and properly dispose of all wash water from the containment area cleaning and
decontamination facility.
G. Provide a decontamination facility adjacent to the Work area for housing change room, shower area,
and equipment area if required. Provide with lockers or acceptable provisions to secure street and
Work clothes, towels, soap, and other necessary hygiene requirements if required.
H. Establish and maintain a system or log showing the following:
1. The number of barrels, drums and other containers, and sealed packages loaded onto the truck
for each trip to the approved disposal site.
2. The number of barrels, drums and other containers, and sealed packages buried at the disposal
site and the signature by the disposal site operator receiving the material. If a barrel or drum is
recycled for reuse, the number of bags taken from the drum and buried shall be recorded.
I. Contractor will be responsible for providing power for lighting, blowers, etc. related to the asbestos
abatement activities.
J. Owner will make available to Contractor the following items:
1. Area for unloading and loading of equipment and materials, and picking up of waste.
PART 2 - PRODUCTS: NOT USED
PART 3 - EXECUTION
3.1 ASBESTOS SAMPLING
A. Contractor shall collect samples of any suspect asbestos-containing materials that are discovered
86 | P a g e
Port KC – Warehouse Demolition – Woodswether Terminal
January 27, 2017
during demolition activities. Analytical results shall be provided to Owner’s Representative prior to
commencement of abatement or demolition.
B. In the event that asbestos is present in any of these areas, Contractor shall conduct abatement activities
in accordance with this section and the alternate bid price provided in the bid.
3.2 ASBESTOS ABATEMENT AIR MONITORING
A. Independent third party air monitoring will be provided by Contractor to confirm compliance with
Applicable Law. Air monitoring will be performed at the following intervals and in each Work area:
1. Prior to start of Work to identify fiber levels of ambient air.
2. During the abatement process to identify fiber levels inside and outside the Work areas. If
monitoring results show that airborne concentrations are in excess of allowable limits,
Contractor will be notified and be required to stop removal of asbestos and correct the condition
causing the increase.
3. Following final cleanup after all surfaces have dried and before containment barriers are
removed to ensure that the final decontamination levels have been met (as indicated in
Paragraph 3.03).
B. Samples shall be collected to identify the concentrations of asbestos fibers by laboratory analysis.
Following final cleanup, minimum analytical method shall be by Phase Contrast Microscopy
developed by NIOSH and performed by a certified laboratory participant in the NIOSH Proficiency
Analytical Testing Program.
C. Contractor is responsible for any personnel air monitoring inside and outside of the Work and
containment areas as required by Applicable Law.
D. Contractor will provide Owner’s Representative with a 24-hour notice for conducting the visual
inspection of the containment areas for final clearance inspection and air monitoring samples.
3.3 FINAL WORK AREA CLEAN-UP AND DECONTAMINATION
A. General Requirements: After all asbestos-containing or contaminated materials have been removed
and bagged for disposal, remove all appropriately contained asbestos containing wastes and perform
a final clean-up and decontamination of each Work area. Final cleaning shall be performed only after
all waste is packaged and removed, but prior to dismantling any barrier, decontamination facility, or
protective coverings. Cleaning will be subject to the Owner’s Representative’s approval based on a
visual inspection and/or surface dust wipe tests, and air testing results by the independent third party
air monitoring contractor.
B. Decontamination
1. Clean all waste containers and equipment with a HEPA-filtered vacuum, wash in the Shower
Room, and then remove from the Work area.
2. Wipe clean all surfaces in the Work area and, after drying, thoroughly decontaminate with a
HEPA-filtered vacuuming device.
C. Final Clearance Inspection
1. Contractor will provide Owner’s Representative with a 24-hour notice for conducting the visual
inspection of the containment areas for final clearance inspection and air monitoring samples.
87 | P a g e
Port KC – Warehouse Demolition – Woodswether Terminal
January 27, 2017
2. If the independent air monitoring Contractor observes any asbestos waste or fibers within the
Work area during the inspection, perform additional cleanup and decontamination to correct
the situation.
3. If the independent air monitoring Contractor approves the cleaning through visual inspection,
this Contractor will collect air samples inside the Work area. Contractor shall assume that the
clearance analytical results will be available within 3 working days of sample collection.
4. If the air sample results are above acceptable limits, perform additional cleaning and
decontamination; and repeat the final inspection steps identified above.
5. If the air sample results are below acceptable limits, Owner’s Representative will give approval
to remove and package for disposal all protective coverings, all additional plastic sheeting,
seals, and other disposable items, and the Decontamination Facility.
6. Contractor shall not remove any containment area until final clearance authorization is
provided by the Owner’s Representative of each containment area.
3.4 WASTE GENERATION AND DISPOSAL
A. Asbestos Containing Materials
1. Asbestos wastes include all building materials, insulation, disposable clothing and protective
equipment, plastic sheeting and tape, exhaust systems or vacuum filters, or any equipment which
has been contaminated with asbestos and cannot be completely cleaned by vacuuming followed
by washing in the Decontamination Facility. Any panels, supports, or other demolished
building materials which are removed to gain access to asbestos materials shall be considered
asbestos wastes unless Contractor can demonstrate to Owner’s Representative an ability to
remove and totally clean them.
2. Handle, package, store, transport, and dispose of all asbestos wastes as specified in this Section
and Applicable Law.
3. Promptly place all waste material in plastic bags. Count or measure the volume of each filled
container, and maintain a written record of such for inspection by Owner’s Representative.
4. Affix warning labels, having waterproof print and permanent adhesive, to the lid and/or sides
of all containers. Warning labels shall be conspicuous and legible, and contain the proper
wording.
5. Thoroughly wet all waste when packaged. Insufficiently wetted bags shall be opened, rewetted,
and resealed. When a waste container is full, securely seal with tape. Seal drums with a solid
lid and retaining ring; label, and then transport.
B. Waste Container Removal and Disposal Documentation
1. To comply with the requirement that waste disposal at the approved disposal site be
documented, remove waste containers from Work areas only under the observation of Owner’s
Representative; and complete a waste disposal documentation form or log for each load of
waste removed from an area.
2. Transport the waste, and complete or obtain all required licenses, manifests, dump slips, or
other forms. Copies of all forms or licenses shall be given to Owner’s Representative prior to
any payments for Work completed.
88 | P a g e
Port KC – Warehouse Demolition – Woodswether Terminal
January 27, 2017
3.5 NON-ASBESTOS RELATED CLEAN-UP WORK
A. Periodically accomplish removal of non-asbestos related debris, resultant dirt, and surplus or
damaged materials to keep the Site reasonably clean. Periodic cleaning shall encompass removal of
tools not in active use, and scaffolding and other equipment no longer needed.
B. Upon completion of the asbestos removal Work, remove all temporary construction, facilities, and
unused materials.
3.6 RECORDING OF ASBESTOS REMOVED
A. Establish and maintain a system or log showing the following:
B. The number of barrels, drums and other containers, and sealed packages loaded onto the truck for
each trip to the approved disposal site.
C. The number of barrels, drums and other containers, and sealed packages buried at the disposal site
and the signature by the disposal site operator receiving the material. If a barrel or drum is recycled
for reuse, the number of bags taken from the drum and buried shall be recorded.
3.7 REMOVAL AND DISPOSAL OF SMALL DIAMETER PIPING WITH ACM INSULATION
A. Small diameter piping of 6-inch OD (refers to outside diameter of the insulation) or less can be
wrapped, cut and disposed of in bulk (i.e. piping, insulation and skin) as ACM.
END OF SECTION 028200
89 | P a g e
Port KC – Warehouse Demolition – Woodswether Terminal
January 27, 2017
CONTRACT
DRAWINGS
CALL BEFORE
YOU DIG
1-800-336-9193
FIBEROPTICCABLE!
DESCRIPTIONDESCRIPTIONREVISION # BY DATEREVISION # BY DATE
FES #:
DRAWN BY:
CHECKED BY:
SHEET NUMBER
DRAWN BY:
CHECKED BY:
SHEET NUMBER
DATE:DATE:
ofof
LEGEND:LEGEND:
LOCATION & DESCRIPTION:
26861
D. DESEN
Fence
Railroad Right Of Way
Fiber Optic Cable
Track Removal
Future Industry Owned Trackage
Proposed Industry Owned Trackage
Existing Industry Owned Trackage
Proposed Railroad Owned Trackage
Existing Railroad Owned TrackageK. MOORE-COOKS
BID DOCUMENTS ONLY
For Use In Agreement With:
500 ftN
➤➤
N© 2016 Google© 2016 Google
State S
t
Woodswether Rd
Warehouse to be demolishedand removed. Approx. 28,000sf
Site Plan
CALL BEFORE
YOU DIG
1-800-336-9193
FIBEROPTICCABLE!
DESCRIPTIONDESCRIPTIONREVISION # BY DATEREVISION # BY DATE
FES #:
DRAWN BY:
CHECKED BY:
SHEET NUMBER
DRAWN BY:
CHECKED BY:
SHEET NUMBER
DATE:DATE:
ofof
LEGEND:LEGEND:
LOCATION & DESCRIPTION:
26861
D. DESEN
Fence
Railroad Right Of Way
Fiber Optic Cable
Track Removal
Future Industry Owned Trackage
Proposed Industry Owned Trackage
Existing Industry Owned Trackage
Proposed Railroad Owned Trackage
Existing Railroad Owned TrackageK. MOORE-COOKS
BID DOCUMENTS ONLY
For Use In Agreement With:
Site Pictures
View of Bldgfrom east end
View of Bldgfrom south side
CALL BEFORE
YOU DIG
1-800-336-9193
FIBEROPTICCABLE!
DESCRIPTIONDESCRIPTIONREVISION # BY DATEREVISION # BY DATE
FES #:
DRAWN BY:
CHECKED BY:
SHEET NUMBER
DRAWN BY:
CHECKED BY:
SHEET NUMBER
DATE:DATE:
ofof
LEGEND:LEGEND:
LOCATION & DESCRIPTION:
26861
D. DESEN
Fence
Railroad Right Of Way
Fiber Optic Cable
Track Removal
Future Industry Owned Trackage
Proposed Industry Owned Trackage
Existing Industry Owned Trackage
Proposed Railroad Owned Trackage
Existing Railroad Owned TrackageK. MOORE-COOKS
BID DOCUMENTS ONLY
For Use In Agreement With:
Site Pictures
View of Bldgfrom north side
CALL BEFORE
YOU DIG
1-800-336-9193
FIBEROPTICCABLE!
DESCRIPTIONDESCRIPTIONREVISION # BY DATEREVISION # BY DATE
FES #:
DRAWN BY:
CHECKED BY:
SHEET NUMBER
DRAWN BY:
CHECKED BY:
SHEET NUMBER
DATE:DATE:
ofof
LEGEND:LEGEND:
LOCATION & DESCRIPTION:
26861
D. DESEN
Fence
Railroad Right Of Way
Fiber Optic Cable
Track Removal
Future Industry Owned Trackage
Proposed Industry Owned Trackage
Existing Industry Owned Trackage
Proposed Railroad Owned Trackage
Existing Railroad Owned TrackageK. MOORE-COOKS
BID DOCUMENTS ONLY
For Use In Agreement With:
Site Pictures
West End of Bldg
View offoundationpiers
View offoundationpiers
CALL BEFORE
YOU DIG
1-800-336-9193
FIBEROPTICCABLE!
DESCRIPTIONDESCRIPTIONREVISION # BY DATEREVISION # BY DATE
FES #:
DRAWN BY:
CHECKED BY:
SHEET NUMBER
DRAWN BY:
CHECKED BY:
SHEET NUMBER
DATE:DATE:
ofof
LEGEND:LEGEND:
LOCATION & DESCRIPTION:
26861
D. DESEN
Fence
Railroad Right Of Way
Fiber Optic Cable
Track Removal
Future Industry Owned Trackage
Proposed Industry Owned Trackage
Existing Industry Owned Trackage
Proposed Railroad Owned Trackage
Existing Railroad Owned TrackageK. MOORE-COOKS
BID DOCUMENTS ONLY
For Use In Agreement With:
Site Pictures
Pictures insidethe building
Asbestos and Hazardous Materials Survey Report: Warehouse at
Woodswether Terminal 400 State Street
Kansas City, Missouri
Port KC 400 State Street
Kansas City, Missouri
Woodswether Terminal Project No. 86867
01/20/2017
Asbestos and Hazardous Materials Survey Report:
Warehouse at Woodswether Terminal
400 State Street Kansas City, Missouri
prepared for
Port KC Woodswether Terminal
Kansas City, Missouri
Project No. 86867
01/20/2017
prepared by
Burns & McDonnell Engineering Company, Inc. Kansas City, Missouri
COPYRIGHT © 2017 BURNS & McDONNELL ENGINEERING COMPANY, INC.
INDEX
Port KC Asbestos and Hazardous Materials Survey Report: Warehouse at Woodswether
Terminal 400 State Street
Kansas City, Missouri Project No. 86867
Report Index Chapter Number Chapter Title
Number of Pages
1.0 Introduction 1 2.0 Asbestos Survey Procedures 2 3.0 Hazardous Materials Survey Methods 1 4.0 Results 1 5.0 Recommendations 1 Appendix A Certifications and Accreditations 1
Asbestos and Hazardous Materials Survey Report Table of Contents
Port KC i Burns & McDonnell
TABLE OF CONTENTS
Page No.
1.0 INTRODUCTION ............................................................................................... 1-1 1.1 Inspector Credentials ........................................................................................... 1-1 1.2 Functional Spaces Included in Survey ................................................................. 1-1
1.2.1 Historical Records Review ................................................................... 1-2
2.0 ASBESTOS SURVEY PROCEDURES ............................................................. 2-1 2.1 Asbestos Sampling Methods ................................................................................ 2-1 2.2 Asbestos Containing Material Definitions ........................................................... 2-2
3.0 HAZARDOUS MATERIALS INVENTORY ........................................................ 3-1 3.1 Hazardous Materials Survey Methods ................................................................. 3-1
3.2 Lead Based Paint Sample Results………………………………………………3-1
4.0 RESULTS .......................................................................................................... 4-1 4.1 Asbestos Results .................................................................................................. 4-1 4.2 Hazardous Materials Inventory Results ............................................................... 4-1
5.0 RECOMMENDATIONS ..................................................................................... 5-1 5.1 Asbestos Recommendations ................................................................................ 5-1 5.2 Hazardous Materials Recommendations .............................................................. 5-1
APPENDIX A - CERTIFICATIONS AND ACCREDITATIONS
APPENDIX B – EHS LABORATORY REPORT
Asbestos and Hazardous Materials Survey Report Table of Contents
Port KC ii Burns & McDonnell
LIST OF TABLES
Table 1 .................................................................................... Hazardous Materials Inventory Table 2-1 ......................................................... Functional Spaces and Homogeneous Materials Table 2-2 …………………………………....Suspect Asbestos Sample Results and Locations Table 2-3 …………………………………..Positive Asbestos Sample Results and Locations Table 2-4 ………………………..………….Lead Based Paint Sample Results and Locations
LIST OF FIGURES
Figure 1 ..................................................................................................................... Photo Log Figure 2 .................................................................................................................. Aerial View
Asbestos and Hazardous Materials Survey Report INTRODUCTION
Port KC 1-1 Burns & McDonnell
1.0 INTRODUCTION
This report summarizes the results of an asbestos and hazardous material survey performed at the Port KC
Woodswether Terminal Warehouse at 400 State Street in Kansas City, Missouri. The survey was
completed by Burns & McDonnell Engineering Company, Inc. (Burns & McDonnell), on January 12,
2017.
Professional judgment was used to determine survey methods, procedures, and report format, particularly
regarding the location and number of collected samples. Although efforts were made to follow customary
practices of environmental and/or industrial hygiene sciences to identify all suspect hazardous materials,
no guarantee or warranty is provided regarding the existence or absence of such materials, and a
possibility remains for the presence of additional suspect materials that were inaccessible, including
above ceilings, behind walls & mirrors, underground, etc. Therefore, prior to renovation or demolition
activities, a contractor must first verify locations and amounts of materials identified in this report, then
be alert to isolate any newly discovered, suspect hazardous materials and promptly communicate the
discovery to the owner, manager, and/or general contractor as appropriate and seek further direction to
properly protect occupants, workers and the public. Semi-destructive sampling methods were used,
causing unavoidable blemishes or damage to facility structures and finishes. Findings in this report are
based on conditions at the time of the survey and results rely on third-party laboratory analyses.
1.1 Inspector Credentials
Missouri-certified inspector, Mr. Adrian Wenker conducted the survey and collected the associated
samples at the Site. Asbestos inspector accreditation was assured by following the EPA Model
Accreditation Program (MAP) for asbestos training, as required by the Asbestos School Hazard
Abatement Reauthorization Act (ASHARA). Inspector certifications and accreditations are provided as
Appendix A
1.2 Functional Spaces Included in Survey
The areas included in this survey were grouped by the inspector(s) into functional spaces, which are
areas/mechanical systems within the building that are used for a specific purpose and may be included in
future renovation activities. Functional spaces included in this survey are listed below.
All interior and exterior areas of the building except the roof, were entered and visually
inspected to determine the presence of suspect materials.
Asbestos and Hazardous Materials Survey Report INTRODUCTION
Port KC 1-2 Burns & McDonnell
1.2.1 Historical Records Review
No historical inspection records were found.
Asbestos and Hazardous Materials Survey Report ASBESTOS SURVEY PROCEDURES
Port KC 2-1 Burns & McDonnell
2.0 ASBESTOS SURVEY PROCEDURES
2.1 Asbestos Sampling Methods
The purpose of this asbestos survey was to identify whether asbestos is present in building areas that may
be impacted by anticipated demolition activities. Therefore, this survey was primarily intended to meet
the EPA National Emissions Standards for Hazardous Air Pollutants (NESHAP) for asbestos in 40 CFR
61, Subpart M, which requires, prior to demolition or renovation activities, that the owner is responsible
to “thoroughly inspect the affected facility” for the presence of asbestos. Applicable portions of the
Occupational Safety and Health Administration (OSHA) standard 29 CFR 1926.1101 for asbestos were
also followed. Other guidelines, including the ASTM E2356-10, Standard Practice for Comprehensive
Building Asbestos Surveys, were reviewed and utilized as needed or noted in this report.
The accredited inspector(s) visited each functional space and identified materials suspect for asbestos that
were uniform in color, texture, and apparent date of installation (per ASTM) as homogeneous areas.
Suspect materials are commonly grouped into one of three classifications:
Thermal-system insulation (TSI)
Surfacing Materials
Miscellaneous Materials
Then, according to OSHA 29 CFR 1926.1101(K)(5)(B) and EPA MAP bulk sampling methods, the
inspector(s) collected a sample(s) from each homogeneous area, and followed the MAP exception for TSI
that ‘convenience sampling…may be more appropriate for…non-school buildings”.
Semi-destructive sampling methods were used and this caused unavoidable minor impact and blemishes
to facility structures and finishes. Amended water spray was used during sample collection to control
dust and fiber release. Wetted bulk samples were placed into individual, sealable containers. The
inspector(s) retained the samples until submittal to the laboratory.
An effort was made to collect at least three samples of each suspect, homogeneous material, unless the
inspector determined that the material was small and appeared to be of a consistent, manufactured product
(per ASTM standard) such that fewer samples would be representative, or where three would not be
practical. Typically, no samples were collected of non-suspect materials such as: fiberglass, foam glass,
rubber, glass, steel, concrete, porcelain, and wood. Sampling did not include cloth-like casing of electric
wiring, which, if found, may be assumed positive. In some cases where suspect materials are present,
asbestos may be assumed or presumed without collecting bulk samples.
Asbestos and Hazardous Materials Survey Report ASBESTOS SURVEY PROCEDURES
Port KC 2-2 Burns & McDonnell
A total of 18 bulk asbestos samples were collected from the Site. Sampled items include: window
glazing, floor tile, adhesive, mastic, TSI, and plaster. A Photo Log is provided as Figure 1.
Samples were submitted to Environmental Hazards Services, LLC (EHS) of Richmond, Virginia for
asbestos analysis. EHS is certified by the National Voluntary Laboratory Accreditation Program
(NVLAP), Laboratory Number 101882-0, to perform laboratory analyses for bulk asbestos samples. EHS
analyzed the bulk samples using polarized light microscopy (PLM) with dispersion staining in accordance
with the EPA test method for the determination of asbestos in bulk samples (EPA 600/R-93/116). The
laboratory provides the approximate percentage of asbestos fibers in the sample and also identifies the
crystal form of the asbestos. Some collected samples had two or more layers, such as a material with
adhesive, and the laboratory analyzed all layers.
2.2 Asbestos Containing Material Definitions
Materials are considered asbestos-containing material (ACM) if they contain greater than one percent
(1%) asbestos. ACM is categorized by the inspector as either:
Friable (can be crumbled, pulverized, or reduced to powder by hand pressure, when dry),
Category I non-friable (asbestos-containing packings, gaskets, resilient floor coverings
and asphalt roofing products), or
Category II non-friable (any other non-friable asbestos material).
Asbestos and Hazardous Materials Survey Report HAZARDOUS MATERIALS INVENTORY
Port KC 3-1 Burns & McDonnell
3.0 HAZARDOUS MATERIALS INVENTORY
3.1 Hazardous Materials Survey Methods
The Burns & McDonnell inspector walked through the building in an effort to visually identify and
catalogue (no sampling) the quantity and location of polychlorinated biphenyl (PCB)-containing
materials, mercury-containing materials, and other visible, hazardous materials.
PCBs are no longer commercially produced in the United States. However, PCBs are still present in
products where PCBs have been used including electrical transformers, electrical lamp ballasts, hydraulic
fluids, etc. The facility was surveyed for the potential presence of such materials. According to the EPA,
suspect materials, including transformers and lighting ballasts, must be considered positive for PCBs
unless the product is clearly marked with a label stating “NO PCBs” in the product.
Mercury can be present in liquid form, such as in switches/thermostats, which were identified in this
survey. Electrical lamps including fluorescent tubes, neon, compact fluorescent lamps, high-pressure
sodium, mercury vapor, metal halide, and high-intensity discharge (HID) lamps may contain mercury at
levels classifying tube disposal as hazardous waste according to the EPA. Recently, lighting companies
have begun producing “low-level” mercury lamps. These “green” lamps are typically marked by green
end caps (Phillips brand) or green labeling (GE and Sylvania brand). Other lighting companies may have
varying methods of identifying low-level mercury lamps. Lighting tubes were identified and counted.
3.2 Lead Based Paint Sample Results
Paint samples were collected from four surfaces and submitted for analysis to determine if the paint is
lead based as defined in 24 CFR Part 35.86. Paint is considered lead based if it contains lead equal to or
in excess of 1.0 milligram per square centimeter or 0.5% by weight. OSHA lead regulations for general
industry can be found in 29 CFR 1910.1025. OSHA has established a Permissible Exposure Limit (PEL),
which is based on an 8-hour, Time-Weighted-Average (TWA), at not greater than 50 µg/m³, with an
action level set at 30 µg/m³. In order to minimize lead vapor exposure, grinding, sawing, or torch cutting
should not be used on lead paint,. Care should be taken to not use hot work methods in demolishing lead
coated structures. If lead is encountered on the site, employees must be notified and informed by their
employer as to safe work practices.
None of the analyzed samples contained lead.
Asbestos and Hazardous Materials Survey Report RESULTS
Port KC 4-1 Burns & McDonnell
4.0 RESULTS
Results of the surveys are representative of conditions on the day of sampling. There is a possibility that
other materials may be discovered during future activities.
4.1 Asbestos Results
The EHS laboratory report is provided as Appendix B. As indicated in Appendix B and summarized in
Table 2-3, both friable TSI and category I non-friable ACM were identified during the survey of the Site.
Friable ACM includes approximately 100-square feet (ft2) of thermal system insulation on a tank in the
boiler room and associated TSI on piping. Category I non-friable ACM includes approximately 350 ft2
Floor Tile (9”x9”) and mastic, and 20 windows containing asbestos window caulk. Material quantities
presented in Table 2 are considered to be estimates only.
4.1 Lead-Paint Results
Although none of the samples are considered to be lead-based paint, the laboratory identified low
concentrations of lead in each of the paint samples (i.e. lead-containing paint).
4.2 Hazardous Materials Inventory Results
A summary of the hazardous materials, and associated quantities identified during the survey is presented
in Table 1:
Table 1 Material Quantity Unit
High Intensity Discharge (HID) Light Bulbs Throughout warehouse
19 --
Green Waste, First Floor Office 1 --
Mercury on Thermostat in warehouse 1 --
Potential Polychlorinated Biphenyl (PCB) Ballasts associated with fluorescent light fixtures
10 --
Asbestos and Hazardous Materials Survey Report RECOMMENDATIONS
Port KC 5-1 Burns & McDonnell
5.0 RECOMMENDATIONS
5.1 Asbestos Recommendations
This survey has identified the presence of friable and non-friable ACM. All ACM identified in this
survey must be properly abated by an asbestos contractor licensed in the State of Missouri and in
accordance with all applicable local, state, and federal regulations prior to demolition.
Retain a copy of this survey report for future reference and update by the building owner.
In the future, if a specific remediation or demolition project scope of work is developed, a project-specific
specification is recommended to be prepared for the project, and included in the construction project
manual.
5.2 Lead-Paint Recommendations
The paint is not considered to be lead-based paint, but since it does contain low concentrations of lead,
contractors must be made aware of the lead concentrations and take actions to follow the OSHA lead
construction regulations to reduce and limit potential worker exposure to lead fumes or lead dust.
5.3 Hazardous Materials Recommendations
This survey has identified the presence of potential hazardous materials. All hazardous materials
identified in this survey should be properly characterized and profiled prior to disposal or recycling in
accordance with applicable local, state, and federal guidelines prior to demolition.
TABLE 2-1
FUNCTIONAL SPACES AND HOMOGENEOUS MATERIALS Kansas City Ports
Kansas City, Missouri 1/12/2017
FUNCTIONAL SPACE No.
LOCATION HOMOGENEOUS MATERIALS
1
Warehouse Office
TSI.= Tank Insulation TSI.= Line Insulation Misc.= Window Caulk Misc.= 9”x9” Floor tile w/mastic Misc.= Plaster Misc.= Wall Adhesive Misc.= White Block Misc.= Drywall
Misc- Miscellaneous TSI- Thermal System Insulation
TABLE 2-2
SUSPECT ACM RESULTS Kansas City Ports
Kansas City, Missouri 1/12/17
Location (Functional Space) and
Description Sample
No. Homogeneous Material Type
PLM Results (Present/ NAD1)
TEM Results (% and type asbestos)
Warehouse Office: Boiler Room; TSI- Tank Insulation
112-1 TSI 45% Chrysotile -
Warehouse Office: Boiler Room; TSI- Tank Insulation
112-2 TSI 45% Chrysotile -
Warehouse Office: Boiler Room; TSI- Pipe Insulation
112-3 TSI 55% Chrysotile -
Warehouse Office: Boiler Room; TSI- Pipe Insulation
112-4 TSI 55% Chrysotile -
Warehouse Office: Second Floor, SE Office; Window Caulk
112-5 Miscellaneous 3% Chrysotile -
Warehouse Office: Second Floor, NE Office; 9”x9” floor tile w/ mastic
112-6 Miscellaneous 5% Chrysotile
<1% Chrysotile, Trace in mastic
-
Warehouse Office: Second Floor, NE Office; 9”x9” floor tile w/ mastic
112-7 Miscellaneous 5% Chrysotile
2% Chrysotile in mastic
-
Warehouse Office: Second Floor, NE Office; 9”x9” floor tile w/ mastic
112-8 Miscellaneous 5% Chrysotile
3% Chrysotile in mastic
-
Warehouse Office: Second Floor Restroom; 9”x9” floor tile w/ mastic
112-9 Miscellaneous 5% Chrysotile
2% Chrysotile in mastic
-
Warehouse Office: Second Floor, NE Office; Plaster 112-10 Miscellaneous NAD -
Warehouse Office: Second Floor, Inner Office; Wall Adhesive
112-11 Miscellaneous NAD -
Warehouse Office: Second Floor, Inner Office; Wall Adhesive
112-12 Miscellaneous NAD -
Warehouse Office: Second Floor, SE Office; Window Caulk
112-13 Miscellaneous 3% Chrysotile -
Warehouse Office: Stairwell; Plaster 112-14 Miscellaneous NAD -
Warehouse Office: Second Floor; White Block 112-15 Miscellaneous NAD -
Warehouse Office: Second Floor; White Block 112-16 Miscellaneous NAD -
Warehouse Office: First Floor; Drywall 112-17 Miscellaneous NAD -
Location (Functional Space) and
Description Sample
No. Homogeneous Material Type
PLM Results (Present/ NAD1)
TEM Results (% and type asbestos)
Warehouse Office: First Floor, SE Office; Window Caulk
112-18 Miscellaneous NAD -
NAD- No Asbestos Detected by PLM Analysis; PLM- Polarized Light Microscopy TEM- Transmission Electron Microscopy TSI- Thermal System Insulation Bold- Samples positive for asbestos.
TABLE 2-3
POSITIVE ASBESTOS SAMPLE RESULTS AND LOCATIONS Kansas City Ports
Kansas City, Missouri 1/12/2017
Location (Functional Space) and Description Sample No.
Homogeneous Material Type
PLM Results (Present/ NAD)
Estimated Quantity
Warehouse Office: Boiler Room; TSI- Tank Insulation
112-1-112-2
TSI 45% Chrysotile 100 Ft2
Warehouse Office: Boiler Room; TSI- Pipe Insulation
112-3- 112-4
TSI 55% Chrysotile 30 LF
Warehouse Office: Second Floor, SE Office; Window Caulk
112-5, 112-13
Miscellaneous 3% Chrysotile 20 windows
Warehouse Office: Second Floor, NE Office; 9”x9” floor tile w/ mastic
112-6- 112-9
Miscellaneous 5% Chrysotile <1-3% Chrysotile
350 Ft2
NAD- No Asbestos Detected by PLM Analysis; PLM- Polarized Light Microscopy TEM- Transmission Electron Microscopy TSI- Thermal System Insulation Bold- Samples positive for asbestos.
TABLE 2-4
LEAD PAINT SAMPLE RESULTS AND LOCATIONS Kansas City Ports
Kansas City, Missouri 1/12/2017
Sample # Location Lead Result (% by weight)
PB-1 First Floor Office Foyer 0.11%
PB-2 Exterior wood paint, East Structure attached to warehouse
0.011%
PB-3 Warehouse by electrical room 0.0085%
PB-4 Support by shaft and electrical room in warehouse
0.0072%
Lead-based paint equals or exceeds 0.5% lead, lower detections of lead are considered to be lead-containing paint.
PHOTO LOG
9”x9” Floor Tile with mastic (5% Chrysotile in tile, trace-3% Chrysotile in Mastic.
Boiler Insulation (45% Chrysotile)
500 ftN
➤➤
N© 2016 Google
© 2016 Google
© 2016 Google
State S
t
Woodswether Rd
Warehouse to be demolishedand removed. Approx. 28,000sf
Asbestos BulkAnalysis Report
Client:
Report Number:
Project/Test Address:
Client Number:
Reported Date:
Received Date:
Analyzed Date:
Burns & McDonnell Engineering 01/16/2017
26-3514
01/19/2017
17-01-01681
7469 Whitepine Rd
Telephone: 800.347.4010
Richmond, VA 23237
Environmental Hazards Services, L.L.C.
86867, KC Ports; Kansas City, MO
Laboratory ResultsFax Number:
816-822-3494
9400 Ward Pkwy.Kansas City, MO 64114
01/17/2017, 01/18/2017
Layer Type AsbestosClient SampleNumber
OtherMaterials
Lab Gross DescriptionLab SampleNumber
Brown Fibrous;Homogeneous
17-01-01681-001 0112-1 50% Fibrous Glass5% Non-Fibrous
45% Chrysotile
45%Total Asbestos:
Brown Fibrous;Homogeneous
17-01-01681-002 0112-2 50% Fibrous Glass5% Non-Fibrous
45% Chrysotile
45%Total Asbestos:
Gray Fibrous;Homogeneous
17-01-01681-003 0112-3 40% Cellulose5% Non-Fibrous
55% Chrysotile
55%Total Asbestos:
Gray Fibrous;Homogeneous
17-01-01681-004 0112-4 40% Cellulose5% Non-Fibrous
55% Chrysotile
55%Total Asbestos:
Tan Chalky;Homogeneous
17-01-01681-005 0112-5 97% Non-Fibrous3% Chrysotile
3%Total Asbestos:
1 of 4Page
Tan Vinyl; Homogeneous17-01-01681-006A 0112-6 95% Non-FibrousTile 5% Chrysotile
5%Total Asbestos:
Yellow/Black Adhesive;Inhomogeneous
17-01-01681-006B 0112-6 2% Cellulose98% Non-Fibrous
Mastic Trace <1% Chrysotile
Unable to cleanly separate mastics. Possible contamination from tile.
Trace <1%Total Asbestos:
Dark Red Vinyl;Homogeneous
17-01-01681-007A 0112-7 95% Non-FibrousTile 5% Chrysotile
5%Total Asbestos:
Black Adhesive;Homogeneous
17-01-01681-007B 0112-7 3% Cellulose95% Non-Fibrous
Mastic 2% Chrysotile
2%Total Asbestos:
Tan Vinyl; Homogeneous17-01-01681-008A 0112-8 95% Non-FibrousTile 5% Chrysotile
5%Total Asbestos:
Black Adhesive;Homogeneous
17-01-01681-008B 0112-8 2% Cellulose95% Non-Fibrous
Mastic 3% Chrysotile
3%Total Asbestos:
Tan Vinyl; Homogeneous17-01-01681-009A 0112-9 95% Non-FibrousTile 5% Chrysotile
5%Total Asbestos:
Black Adhesive;Homogeneous
17-01-01681-009B 0112-9 2% Cellulose96% Non-Fibrous
Mastic 2% Chrysotile
2%Total Asbestos:
Yellow/Brown Granular;Inhomogeneous
17-01-01681-010 0112-10 100% Non-FibrousNAD
Environmental Hazards Services, L.L.C
Project/Test Address:
Client Number: Report Number:26-3514 17-01-01681
86867, KC Ports; Kansas City, MO
OtherMaterials
AsbestosLab SampleNumber
Layer Type Lab Gross DescriptionClient SampleNumber
2 of 4Page
Brown Brittle;Homogeneous
17-01-01681-011 0112-11 100% Non-FibrousNAD
Brown Brittle;Homogeneous
17-01-01681-012 0112-12 100% Non-FibrousNAD
Red Paint-Like; Pink/TanChalky; Inhomogeneous
17-01-01681-013 0112-13 97% Non-Fibrous3% Chrysotile
Chrysotile present throughout
3%Total Asbestos:
Tan Granular;Homogeneous
17-01-01681-014 0112-14 100% Non-FibrousNAD
Tan Chalky; BrownFibrous; Inhomogeneous
17-01-01681-015 0112-15 10% Cellulose90% Non-Fibrous
NAD
Tan Chalky; BrownFibrous; Inhomogeneous
17-01-01681-016 0112-16 10% Cellulose90% Non-Fibrous
NAD
Gray Chalky; BrownFibrous; Inhomogeneous
17-01-01681-017 0112-17 15% Cellulose85% Non-Fibrous
NAD
Red/Gray Paint-Like; RedChalky; Inhomogeneous
17-01-01681-018 0112-18 100% Non-FibrousNAD
Environmental Hazards Services, L.L.C
Project/Test Address:
Client Number: Report Number:26-3514 17-01-01681
86867, KC Ports; Kansas City, MO
OtherMaterials
AsbestosLab SampleNumber
Layer Type Lab Gross DescriptionClient SampleNumber
3 of 4Page
Environmental Hazards Services, L.L.C
Project/Test Address:
Client Number: Report Number:26-3514 17-01-01681
86867, KC Ports; Kansas City, MO
OtherMaterials
AsbestosLab SampleNumber
Layer Type Lab Gross DescriptionClient SampleNumber
Tasha Eaddy
1% Asbestos
Analyst:
Reporting Limit:
Method:
QC Blank:
QC Sample:
Meredith Outlaw
EPA Method 600/R-93/116, EPA Method 600/M4-82-020
QA/QC Clerk
Reviewed By Authorized Signatory:
83-M22010-3, 87-M12011-3
SRM 1866 Fiberglass
NAD = no asbestos detectedLEGEND:
The condition of the samples analyzed was acceptable upon receipt per laboratory protocol unless otherwise noted on this report. Each distinct
component in an inhomogeneous sample was analyzed separately and reported as a composite. Results represent the analysis of samples submitted
by the client. Sample location, description, area, volume, etc., was provided by the client. This report cannot be used by the client to claim product
endorsement by NVLAP or any agency of the U.S. Government. This report shall not be reproduced except in full, without the written consent of the
Environmental Hazards Service, L.L.C. California Certification #2319 NY ELAP #11714 NVLAP #101882-0 VELAP 460172. All information concerning
sampling location, date, and time can be found on Chain-of-Custody. Environmental Hazards Services, L.L.C. does not perform any sample collection.
Environmental Hazards Services, L.L.C. recommends reanalysis by point count (for more accurate quantification) or Transmission Electron Microscopy
(TEM), (for enhanced detection capabilities) for materials regulated by EPA NESHAP (National Emission Standards for Hazardous Air Pollutants) and
found to contain less than ten percent (<10%) asbestos by polarized light microscopy (PLM). Both services are available for an additional fee.
400 Point Count Analysis, where noted, performed per EPA Method 600/R-93/116 with a Reporting Limit of 0.25%.
* All California samples analyzed by Polarized Light Microscopy, EPA Method 600/M4-82-020, Dec. 1982.
4 of 4Page
Exi
stin
g W
ater
Lin
e
Exi
stin
g S
torm
Sew
er L
ine
Exi
stin
g O
H E
lec
Line
Exi
stin
g G
as L
ine