1 BROOKHAVEN SCIENCE ASSOCIATES
Site Preparation Lessons Learned
Michael P. Bromfield, Construction EngineerConvention Facilities Advisory Committee Review
March 1011, 2009
7/28/2019 03 Bromfield r3
2/18
2 BROOKHAVEN SCIENCE ASSOCIATES
Site Preparation Lessons Learned
Outline Site Preparation Purpose
Existing Site
Prior BNL Work
Site Preparation Scope
Lessons Learned
Path Forward
7/28/2019 03 Bromfield r3
3/18
3 BROOKHAVEN SCIENCE ASSOCIATES
Site Preparation Purpose
Site Preparation was included as an earlyprocurement (authorized pre-CD-3) to: Provide an activity that reduced schedule risk to the
Ring Building by:
Reducing potential for unknown utilities or site conditionsdelaying construction start
Reduce GC schedule risk during early construction
Be mobilized to correct any deficiencies left over from
previous activity at the site (leftover facilities orenvironmental liabilities)
It provided a number of other benefits as well
7/28/2019 03 Bromfield r3
4/18
4 BROOKHAVEN SCIENCE ASSOCIATES
Site Preparation - Existing Site
Ring Bldg Footprint
Construction AreaPerimeter
Existing Buildings tobe removed prior toconstruction
7/28/2019 03 Bromfield r3
5/18
5 BROOKHAVEN SCIENCE ASSOCIATES
Prior Work by BNL
On-going BNL program removed excessfacilities/structures Relocated Warehouse Facilities
Demolished Existing Facilities and Slabs/Foundations
Prepared Recycling Area and recycled concrete foundations
Remove Rail Road tracks and ties
Performed clean up and removal of oil-water separators andrelated sanitary piping
7/28/2019 03 Bromfield r3
6/18
6 BROOKHAVEN SCIENCE ASSOCIATES
Site Preparation Scope
Site Preparation Scope/Construction Packages Clear and Grub Trees
Abandon Existing Site Utilities/Relocate Utilities
Abandon Monitoring Wells/Relocate Wells
Verify no environmental liabilities
Provide Utilities for Construction (power and communication)
7/28/2019 03 Bromfield r3
7/187 BROOKHAVEN SCIENCE ASSOCIATES
Site Prep Status
All base scope work completed -2/17/09 running underbudget
Some minor punchlist / closeout items remain Added some items to scope
Enlarged recharge basin & stockpiled structural fill due to
seasonal environmental permit constraint Added maintenance of erosion control until Ring Bldg
Contractor mobilizes
Added clean-up of miscellaneous debris
No evidence of environmental liabilities Ready for Ring building GC
7/28/2019 03 Bromfield r3
8/188 BROOKHAVEN SCIENCE ASSOCIATES
Site Preparation Site Clearing
View of Cleared Site From NSLS I
7/28/2019 03 Bromfield r3
9/189 BROOKHAVEN SCIENCE ASSOCIATES
Site Preparation Site Clearing
Tree Clearing Along Grove Street
7/28/2019 03 Bromfield r3
10/1810 BROOKHAVEN SCIENCE ASSOCIATES
Site Preparation Electrical
7/28/2019 03 Bromfield r3
11/1811 BROOKHAVEN SCIENCE ASSOCIATES
Site Preparation Lessons Learned
Summary Site access control requirements
NSLS-II CM Staff increased knowledge of BNLsystems, procedures, personnel and points of contact
Understanding of requirements for shutdowns,notifications, permits and utility tie-ins
Utility mark-outs and surveys will assist Ring Buildingutility installation
Improved coordination of field inspectors and safetyengineers in oversight of contractor performance
7/28/2019 03 Bromfield r3
12/1812 BROOKHAVEN SCIENCE ASSOCIATES
Site Preparation Lessons Learned
Better understanding of site access control requirements
Repeated unauthorized incursions of area by Lab personnel- Despite Signs, Roadblocks and Web & Email Postings
Additional time & effort spent:- Chasing Unauthorized Personnel from Area,
- Maintaining Signs & Barricades
On-site fauna destroyed construction fencing in path to food,
habitats Need for well managed permanent fence instead of temporary
construction fence
7/28/2019 03 Bromfield r3
13/1813 BROOKHAVEN SCIENCE ASSOCIATES
Site Preparation Lessons Learned
NSLS-II CM Team new to BNL Different Culture
Outside world experience
Site Preparation work facilitated: Knowledge / Understanding of BNL/DOE expectations and
requirements
Enhanced familiarity with BNL systems, procedures, personneland points of contact
7/28/2019 03 Bromfield r3
14/1814 BROOKHAVEN SCIENCE ASSOCIATES
Site Preparation Lessons Learned
Lessons Learned
Understanding of requirements for shutdowns,notifications, permits and utility tie-ins
Determine Timeframe required for coordination with BNLDepts.
Requirements for off-hour work due to maintenance ofoperations, personnel availability.
7/28/2019 03 Bromfield r3
15/1815 BROOKHAVEN SCIENCE ASSOCIATES
Site Preparation Lessons Learned
Lessons Learned
Utility mark-outs and surveys will assist Ring Building Utilityinstallation:
Facilitated planning for temporary utilities, as well as familiaritywith existing and surrounding site utilities, infrastructure;
Exposed unmarked structures, utilities, and identified known-unknown utilities.
7/28/2019 03 Bromfield r3
16/1816 BROOKHAVEN SCIENCE ASSOCIATES
Site Preparation Lessons Learned
Lessons Learned Improved coordination of field inspectors and safety engineers in
oversight of contractor performance:
Good Planning & Project Oversight by CF & ESH Teams, Collaborative Approach With Contractors Mitigated Weather
Impacts & Potential Impacts due to Scope Changes,
No Impact to Vehicular & Pedestrian Traffic.
7/28/2019 03 Bromfield r3
17/1817 BROOKHAVEN SCIENCE ASSOCIATES
Site Preparation Lessons Learned
Lessons Learned and experience brought From Outside Staff:
New Technologies, Systems for Administering, managing
projects; Implementation of Primavera Contract Manager,
Slight Modification of BNL Procedures to incorporateexperiences
Experience with CM scheduling and estimating methods Experience with claims prevention and mitigation
7/28/2019 03 Bromfield r3
18/1818 BROOKHAVEN SCIENCE ASSOCIATES
Path Forward
Employ Lessons Learned on Site Preparation
Start Permitting Process Early,
Recommend Site Access Control Measures to Ring BuildingContractor
Continue to Coordinate with BNL Site Operations to precludedelays,
Keep current with BNL Procedures / Systems
Partner with Ring Building GC to expedite mobilizationand communication, to facilitate efficient resolution ofissues as they will inevitably arise.