Oh910i1-8594.pptx/1
Oak Harbor Facilities PlanCity Council Workshop
March 6, 2013
Oh910i1-8594.pptx/2Oh910i1-8594.pptx/2
Tonight’s Agenda
• Facilities Plan Status Update
• Rate Analysis Update
• Schedule and Next Steps
– Technical Aspects
– Public Interface
– Milestone Council Decisions
• How to Stay Involved
• Questions?
Oh910i1-8594.pptx/3Oh910i1-8594.pptx/3
Facilities Plan Status
Oh910i1-8594.pptx/4Oh910i1-8594.pptx/4
Proposed SiteWindjammer Vicinity
Oh910i1-8594.pptx/5Oh910i1-8594.pptx/5
Windjammer Charrette Concept for MBRConceptual Plan View
Oh910i1-8594.pptx/6Oh910i1-8594.pptx/6
Total Project Cost SummaryYear 2030
$83.0
$7.6
$2.9
$50
$55
$60
$65
$70
$75
$80
$85
$90
$95
$100
All Facilities Through Year 2030
Proj
ect C
ost,
Mill
ions
Treatment Facility Wastewater Conveyance Effluent Discharge
Oh910i1-8594.pptx/7Oh910i1-8594.pptx/7
Phasing Scenarios Depend on City Growth
0.0
0.5
1.0
1.5
2.0
2.5
3.0
3.5
4.0
4.5
2000 2005 2010 2015 2020 2025 2030 2035
Max
imum
Mon
th F
low
, mgd
Measured Data
Scenario 1, No Growth
Scenario 2, Intermediate Growth
Scenario 3, Comprehensive Plan
1
23
Notes:1: Current measured capacity is 3.0 mgd.2: Capacity required at projected year of startup (2017) ranges from 3.0 to 3.2 mgd.3: Assuming 3.4 mgd of capacity is constructed in Phase 1, years of service
(prior to Phase 2) range from 4 to 13 years.
1
2
3
Oh910i1-8594.pptx/8Oh910i1-8594.pptx/8
Phasing Also Depends on Navy Participation
• Navy currently contributes about 20% of flow to City facilities
• Scenario 1: Navy continues as a customer
– WWTP sized for City and Navy flows/loads
• Scenario 2: Navy does not continue as a customer
– WWTP sized for City only flows/loads
Oh910i1-8594.pptx/9Oh910i1-8594.pptx/9
$83.0
$72.1
$7.6
$7.6
$2.9
$2.9
$50
$55
$60
$65
$70
$75
$80
$85
$90
$95
$100
All Facilities Through Year 2030 Scenario 1: City + Navy
Proj
ect C
ost,
Mill
ions
Treatment Facility Wastewater Conveyance Effluent Discharge
The City's cost sharefor this scenario is
$60.0 M
Total Project Cost SummaryPhase 1, Scenario 1
Oh910i1-8594.pptx/10Oh910i1-8594.pptx/10
$83.0
$72.1
$64.8
$7.6
$7.6
$2.9
$2.9
$2.9
$50
$55
$60
$65
$70
$75
$80
$85
$90
$95
$100
All Facilities Through Year 2030 Scenario 1: City + Navy Scenario 2: City Only
Proj
ect C
ost,
Mill
ions
Treatment Facility Wastewater Conveyance Effluent Discharge
The City's cost sharefor this scenario is
$60.0 M
The City's cost sharefor this scenario is
$67.7 M
Total Project Cost SummaryPhase 1, Scenarios 1 and 2
Oh910i1-8594.pptx/11Oh910i1-8594.pptx/11
Phase 1 Scenario Summary
Scenario 1City + Navy
Scenario 2City Only
Phase 1 Project Cost $82.6 M $67.7 M
Navy Share (%) 27% n/a
Navy Share of Cost $22.6 M n/a
City Share of Cost $60.0 M $67.7
Oh910i1-8594.pptx/12Oh910i1-8594.pptx/12
Milestone Dates for Plan Approval
Date Action
March 6, 2013 Present Draft Plan to Public
March 19, 2013 Seek Council Approval to Submit Draft Plan
Summer 2013 Ecology Conditional Approval (pending environmental)
Q4 2013 - Q1 2014 Final Environmental Approvals
Oh910i1-8594.pptx/13Oh910i1-8594.pptx/13
Rate Analysis Update
Oh910i1-8594.pptx/14Oh910i1-8594.pptx/14
Two Scenarios for Navy Participation
• Scenario 1: City + Navy
– City provides service to Navy at startup of Phase 1 and through Year 2030
– All project/O&M costs are shared
• Scenario 2: City Only
– City, Navy operate independent facilities through Year 2030 (Navy no longer a customer)
– All project/O&M costs are born by City
Oh910i1-8594.pptx/15Oh910i1-8594.pptx/15
Navy Cost-Sharing Assumptions
• WWTP Project Costs– Navy share based on percentage of
maximum month flow (ranges from 21% to 18%)
• WWTP O&M Costs– Navy share based on percentage of average
annual flow (ranges from 17% to 14%)• Collection System Project Costs– Navy provides 100% of costs associated with
conveying Navy flow to Windjammer Vicinity• Outfall Project Costs– Navy share based on percentage of peak
flow (approximately 19% at 2030)
Oh910i1-8594.pptx/16Oh910i1-8594.pptx/16
WWTP Funding Assumption Review
• 2010 rate study included assumptions for the WWTP funding
• Assumptions were conservative given the project was 5 plus years in the future
• Revised assumptions are conservative yet still reflect current conditions
• Question: How do the assumptions impact the adopted rate transition plan?
Oh910i1-8594.pptx/17Oh910i1-8594.pptx/17
Estimated Rate Impact, August 14, 2012“Base Case” Assumed $70 million Project
Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8 Year 9Base Case $40.00 $42.00 $47.00 $52.00 $57.50 $64.75 $72.85 $81.95 $92.20
$0.00
$10.00
$20.00
$30.00
$40.00
$50.00
$60.00
$70.00
$80.00
$90.00
$100.00
Mon
thly
Sew
er B
ill
Summary of Required Single Family Monthly Sewer Bill
“Base Case”Monthly Rate:
$92.20
Oh910i1-8594.pptx/18Oh910i1-8594.pptx/18
Variables include:1. Borrowing term2. Interest rate3. Navy participation
Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8 Year 9Base Case $40.00 $42.00 $47.00 $52.00 $57.50 $64.75 $72.85 $81.95 $92.20 Option 1 $40.00 $42.00 $47.00 $52.88 $59.48 $68.41 $80.38 $96.45 $115.74 Option 2A $40.00 $42.00 $47.00 $52.00 $57.50 $66.13 $76.04 $89.35 $104.99 Option 2B $40.00 $42.00 $47.00 $52.00 $57.50 $64.69 $74.39 $85.55 $98.38 Option 3 $40.00 $42.00 $47.00 $52.00 $57.50 $63.54 $70.21 $77.58 $85.73
$0.00
$20.00
$40.00
$60.00
$80.00
$100.00
$120.00
$140.00
Mon
thly
Sew
er B
ill
Summary of Required Single Family Monthly Sewer Bill
Estimated Rate Impact, August 14, 2012Rate Scenarios for $93.5 million Project
Monthly Rates range from $85 to
> $115(Depending on
variable assumptions)
Oh910i1-8594.pptx/19Oh910i1-8594.pptx/19
Updated WWTP Funding Assumptions
• 2 Borrowing terms evaluated: 20 and 30 years• 2 Interest Rates evaluated: 4.5% and 6.0%• Updated City’s sewer reserves balance• Reconciled other key rate analysis
assumptions– Project cost escalated to mid-point– City portion of project cost based on Navy
participation– Cost of bonding– WWTP O&M components and costs– Project start/end dates
Oh910i1-8594.pptx/20Oh910i1-8594.pptx/20
Three Potential Phase 1 Funding Scenarios
• Scenario 1: City + Navy– 30 years, 4.5% interest– Results in lowest City rate
• Scenario 2A: City Only– 30 years, 4.5% interest– Rate is higher than Scenario 1; still < “Base
Case”• Scenario 2B: City Only– 20 years, 6.0% interest– Highest rate; > “Base Case”
Oh910i1-8594.pptx/21Oh910i1-8594.pptx/21
Comparison of Potential Monthly Sewer Bills
Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8 Year 9Base Case $40.00 $42.00 $47.00 $52.00 $57.50 $64.75 $72.85 $81.95 $92.20 Scenario 1: City + Navy; 30-yrs; 4.5% $40.00 $42.00 $47.00 $51.70 $56.87 $62.56 $68.81 $75.69 $83.26 Scenario 2A: City Only; 30-yrs; 4.5% $40.00 $42.00 $47.00 $52.00 $57.50 $64.40 $72.13 $80.78 $90.48 Scenario 2B: City Only; 20-yrs; 6.0% $40.00 $42.00 $47.00 $52.88 $59.48 $68.11 $77.99 $89.68 $107.62
$0
$20
$40
$60
$80
$100
$120
Mon
thly
Sew
er B
ill
Required Single Family Monthly Sewer Bill
Oh910i1-8594.pptx/22Oh910i1-8594.pptx/22
Summary of Rate Impacts, WWTP
• Lowest City rates result from City + Navy partnership in new facilities
• For “City Only” scenario, City rates held below “Base Case” with current, reasonable assumptions
• Opportunities to reduce City rate impact due to new WWTP continue to be explored– Grants/low-interest loan programs– Borrowing strategy– “Value Engineering”– Project Delivery Method
• Overall rate analysis for sewer utility is ongoing
Oh910i1-8594.pptx/23Oh910i1-8594.pptx/23
Schedule/Next Steps
Oh910i1-8594.pptx/24Oh910i1-8594.pptx/24
Objectives for Next Phase of ProjectThrough Year-end
• Facilities Plan approved
• Confirm planning assumptions through “Value Engineering”
• Select final location for WWTP within Windjammer Vicinity
• Complete preliminary design of WWTP
• Select most appropriate method of construction
• Complete final design of outfall to Oak Harbor
Oh910i1-8594.pptx/25Oh910i1-8594.pptx/25
Key Features of Approach Moving Forward
• Continue to make every effort to deliver an appropriate facility while controlling cost and impact on ratepayers
• Maintain flexibility by considering options for final WWTP site location
• Select final location considering public input, cost and City policy directives
Oh910i1-8594.pptx/26Oh910i1-8594.pptx/26
Step 1 – Value Engineering
• Completed on large projects to add value, control cost
• Condition of some funding sources• Facilitated by an independent 3rd party and
panel of experts• Summer 2013: Results and
recommendations offered to City Council for consideration
Oh910i1-8594.pptx/27Oh910i1-8594.pptx/27
Step 2 – Select Final WWTP Location Within Windjammer Vicinity
Oh910i1-8594.pptx/28Oh910i1-8594.pptx/28
Step 2 – Select Final WWTP Location Within Windjammer Vicinity
A. Spring/Summer 2013: Public meetings, Council deliberations establish policy, guiding principles
– Property acquisition
– Use of open space
– Additional features/benefits associatedwith facility
– Integration with othernearby land-use plans
Oh910i1-8594.pptx/29Oh910i1-8594.pptx/29
Step 2 – Select Final WWTP Location Within Windjammer Vicinity
B. Summer/Fall 2013: Working Group Meetings, Charrette leverage public input to develop options within Windjammer Vicinity
Oh910i1-8594.pptx/30Oh910i1-8594.pptx/30
Step 2 – Select Final WWTP Location Within Windjammer Vicinity
C. Fall 2013: Project team presents analysis of options to City Council for decision
– Confirm Value Engineering Recommendations
– Confirm treatment facility location
– Confirm approach to integrate facility into surroundings
• Transportation
• Parks/Open Space
• Commercial/Retail
• Government/Public Facilities
Oh910i1-8594.pptx/31Oh910i1-8594.pptx/31
Step 3 – WWTP Preliminary Design
A. Fall 2013: Procure key process equipment for design (membranes, UV) based on qualifications and competitive pricing
Oh910i1-8594.pptx/32Oh910i1-8594.pptx/32
Step 3 – WWTP Preliminary Design
B. Combine technical detail, public input to develop final “look & feel” of facility
Concept inspired by June 2012 Charrrettprocess.
Oh910i1-8594.pptx/33Oh910i1-8594.pptx/33
Step 3 – WWTP Preliminary Design
B. Combine technical detail, public input to develop final “look & feel” of facility
Alternate concept showing potentially different site use.
Oh910i1-8594.pptx/34Oh910i1-8594.pptx/34
Step 3 – WWTP Preliminary Design
B. Combine technical detail, public input to develop final “look & feel” of facility
Working Group Meetings
throughout preliminary
design.
Oh910i1-8594.pptx/35Oh910i1-8594.pptx/35
Step 3 – WWTP Preliminary Design
C. Develop drawings and specifications to 30 percent level detail
D. Evaluate alternatives to complete the Project– Design-Bid-Build– Design-Build– General Contractor/Construction Manager
E. Spring 2014: Select delivery option and proceed to final design in early 2014
Oh910i1-8594.pptx/36Oh910i1-8594.pptx/36
Step 4 – Outfall Final Design
• “Fast track” to provide necessary information for permitting
• Complete in parallel with Steps 1 – 3• Design complete in fall 2013• Construction possible in 2014, pending
results of construction delivery analysis
Oh910i1-8594.pptx/37Oh910i1-8594.pptx/37
Significant Council Actions & Decisions
Date Action/Decision
Mar 19, 2013
Council authorizes submission to Ecology; Approves next phase of project
Summer 2013
Council sets policy and guiding principles to select final location
Fall 2013Council selects final location of treatment facility
Spring 2014Council approves approach to complete project
Oh910i1-8594.pptx/38Oh910i1-8594.pptx/38
Overall Project Schedule
OAK HARBOR CLEAN WATER FACILITYPROPOSED SCHEDULE FOR PROJECT COMPLETION
2013 2014 2015 2016 2017
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
PREDESIGN PHASE
APPROVEFACILITIES PLAN
CONSTRUCTION PERIOD
START UP
Agency DraftSubmission
Submit Plans & Specs
FINAL DESIGN PHASE
Oh910i1-8594.pptx/39Oh910i1-8594.pptx/39
How can I stay involved?
Oh910i1-8594.pptx/40
Send an email or give us a call if you would like to participate:
Joe Stowell, City Engineer 360-279-4520 [email protected]
Oh910i1-8594.pptx/41Oh910i1-8594.pptx/41
Questions?