Page 1: 2013  Stormwater Workshop June 13, 2013

2013 StormwaterWorkshop

June 13, 2013

Sponsored ByMichiana Stormwater Partnership

John J. DillonDirector, LTCP Management

City of South Bend

Page 2: 2013  Stormwater Workshop June 13, 2013

South Bend Consent Decree Entered May 2, 2012 Required to Develop a CSO LTCP

Eliminate dry weather overflows Reduce # of wet weather overflows events

to 4 or fewer. Disinfect overflows in order to meet

Michigan water quality standards at state line.

Page 3: 2013  Stormwater Workshop June 13, 2013

Dam

Overflow Pipe

St. JoeRiver

Pipe To Wastewater

Treatment Plant

Runoff

Why Our Sewers Overflow

CombinedSewer

Sewage

Page 4: 2013  Stormwater Workshop June 13, 2013

Plan OverviewProject Description Cost

(2007 Dollars)Cost

(2013 Dollars)Wastewater Treatment Plan Upgrades WWTP Upgrades $52,416,000 $61,068,000

Phase 1 CSO Collection System Controls

Removal of storm water from South Bend's Facility by implementing sewer separation, detention basin management, or Green Infrastructure Measures.

$49,777,000 $57,993,000

Phase 2 CSO Collection System Controls

CSO Controls Upstream of East Race

Memorial Park Storage Tank $22,220,000 $25,888,000

Old Fire Station Storage Tank $8,683,000 $10,116,000

Ice Rink Parking Lot Storage Tank $20,821,000 $24,258,000

Randolph and Sampson $17,313,000 $20,171,000

Nuner School Storage Tank $7,103,000 $8,275,000

CSO Controls Downstream of East Race

Leeper Park Storage Tank $40,670,000 $47,383,000

Brownsfield Park Storage Tank $6,182,000 $7,202,000

Storage Conduit $42,817,000 $49,884,000

Parallel Interceptor $41,970,000 $48,898,000

Phase 2 Contingency $36,779,000 $42,332,000

Engineering, Legal, Admin Cost $48,912,000 $56,882,000

Other Collection System Projects Sewer Extensions and Replacements, River Crossing #5, and Engineering $74,228,000 $86,480,000

Amount Spent on Phase 1 (2004-2010) $39,570,000 $39,570,000

Total Capital Cost $509,460,000 $586,400,000

Page 5: 2013  Stormwater Workshop June 13, 2013

WWTP Upgrades

Primary Clarifiers Rehabilitation

No. 2

Anaerobic Digester Upgrade

No. 6 No. 7

Final Clarifiers Upgrade

Aeration Influent Channel and Tank Modifications

Page 6: 2013  Stormwater Workshop June 13, 2013

Phase 1 CSO LTCP Projects – Upstream of East Race

³

Page 7: 2013  Stormwater Workshop June 13, 2013

³Phase 1 CSO LTCP Projects – Downstream of East Race

Page 8: 2013  Stormwater Workshop June 13, 2013

Phase 2 CSO Collection System Controls ³

Page 9: 2013  Stormwater Workshop June 13, 2013

LTCP Schedule