+ All Categories
Transcript
Page 1: A0 · 2020-05-19 · Project Number: Location: Project: Date Plotted: 23.10.2019 File Name: LT96_KIND_1104_0041_00_00 - Kinardochy Reactive Compensation SS 275(400kV) AIS SUBSTATION

Hinweise:

- Alle Maße sind in mm- Draufsicht siehe Zeichnung E50105-R3422-V995

400kV TERMINAL TOWERTBC

DEERFENCE

15000 5000

APPROX. 25000

7.3m

SECTION A-ASCALE 1:500

EXISTING GROUND LVL TBC

115.0000

115.0000115.0000

115.0000

65000

ORIENTATION OF TOWERS TBC

CONDUCTORS & CLEARANCESTO BE DESIGNED

CONDUCTORS & CLEARANCESTO BE DESIGNED

400kV TERMINAL TOWER

E=276993.776N=755756.288

LVL=TBC

TOWER 230R

400kV OHLMELGARVE-DENNY [ELY1]

TOP = RMID= B

BOT = Y

400kV OHLMELGARVE-DENNY [ELY1]

TOP = RMID= B

BOT = Y

ORIENTATION OF TOWERS TBC

275kV OHLFUTURE KINARDOCHY-BRACO WEST [KB1]TOP = BMID= RBOT = Y

275kV OHLFUTURE TUMMEL-KINARDOCHY [MK1]TOP = BMID= RBOT = Y

PHASING TBC

AA

BB

C

C

4mHIGH SECURITY FENCE

STATCOM BUILDING

GIS & CONTROL BUILDINGOHL GANTRY

GIB

4m HIGH SECURITY FENCE2m WIDE PERIMETER WALKWAY/PATH

STATCOM BUILDING

100 MVAR MSCDN

GIB

GIB

GIB

GIB

DIESELGENERATOR

OHL GANTRY

DNO SUPPLIES

GIS & CONTROLBUILDING

5m WIDE ROAD

DIESELGENERATOR

301700

2117

00

6801

5

22355

3450

0

39000

100150

22015 21245

3024

0

3200

5

4000

9850

1350

0

1332

5

1071

2

9242

9209

8349

±225 MVAR STATCOM

PRELIMINARY DESIGN ONLY

NOT TO BE USED FOR

CONSTRUCTION

Rev:

Checked:

Drawn: Approved:

Date:

Description:

0BPMR

23.10.19

ACCESS GATE AMENDED.

0m

SCALE AT 1:500

37.5m25m12.5m 50m

SUBSTATION MINIMUM ELECTRICAL CLEARANCESREQUIREMENTS TO BE IN ACCORDANCE WITH SSE SUBSTATION DESIGN SPECIFICATION DOC No. SP-PS-399

REF CLEARANCE (mm)NOMINAL SYSTEM VOLTAGE

400kV 275kV 132kV 33kV

E PHASE TO EARTH 2800 2100 1200 500

Ph PHASE TO PHASE 3600 2400 1400 430

S DESIGN CLEARANCE FOR SAFETY 5500 4800 3500 2900

SD SAFETY DISTANCE 3100 2400 1400 800

Ds WORKING & ACCESS CLEARANCE (VERTICAL) 5200 4500 3500 2900

Dsh WORKING & ACCESS CLEARANCE (HORIZONTAL) 4600 3900 2900 2300

IH INSULATION HEIGHT (PEDESTRIAN ACCESS) 2400 2400 2400 2400

WHERE EQUIPMENT CONFIGURATIONS HAVE NOT BEEN SUBJECT TO TYPE OF ROUTINE TESTS IN ACCORDANCE WITH IEC 60694 THECLEARANCES FOR PHASE TO EARTH AND PHASE TO PHASE ABOVE SHALL APPLY.THEY APPLY UNDER CONDITIONS OF MAXIMUM SWING AND SAG.

WHEN DESIGNING ELECTRICAL CONNECTIONS THE FOLLOWING ALLOWANCES HAVE BEEN MADE TO COVER TOLERANCES IN ELECTRICALAND CIVIL WORK AND THE SETTLEMENT OF FOUNDATIONS:- 132kV - 80mm; 33kV - 80mm

NOTES:-1. BASED ON DESIGN REQUIREMENTS TAKEN FROM KINARDOCHY

SUBSTATION DRD LT96-DRD-G1-REV1 (TBC).2. LAYOUT SHOULD BE READ IN CONJUNCTION WITH SLD SSEN DRAWING

NUMBER: LT96_KIND_1117_00_0004_0D_DRAFT.3. ALL DIMENSIONS SHOWN IN MILLIMETRES (mm) U.N.O.4. PROPOSED LAYOUT FOR DEVELOPMENT PURPOSES ONLY.5. SITE DEVELOPED FOR POTENTIAL UPGRADE TO 400kV IN FUTURE

THEREFORE 400kV ELECTRICAL CLEARANCES HAVE BEEN USED WHEREAPPROPRIATE.

6. GIS AND CONTROL BUILDING TAKEN FROM PROPOSED PETERHEAD 400kVSUBSTATION, REFER TO SSEN DRAWING NUMBERS:LT135_PEHE_0805_0001_00_00 - FOR PLANNING-400KV GIS CONTROLBUILDING GA AND LT135_PEHE_0805_0002_00_00 - FORPLANNING-400KV GIS CONTROL BUILDING ELEVATIONS.

7. GIS AND CONTROL BUILDING FOOTPRINT ASSUMED SUITABLE FOR 275kVOR 400kV EQUIPMENT.

8. IT IS ASSUMED THAT MSCDN WOULD REQUIRE TO BE COMPLETELYREDESIGNED FOR UPGRADE TO 400kV.

9. STATCOM MAY BE ABLE TO BE RE-UTILISED IF SUBSTATION IS UPGRADEDTO 400kV BUT WILL REQUIRE AN ADAPTIVE SCT.

10. ALL EQUIPMENT SHOWN TO BE FINALISED AND CONFIRMED BY SSENENGINEER/DESIGN TEAM AND UNTIL DONE SO ALL ASPECTS OF THESHOWN DESIGN ARE SUBJECT TO CHANGE.

11. AIS PLANT INFORMATION TAKEN FROM STANDARD SSE FRAMEWORKLAYOUTS.

12. STATCOM BASED ON SIMILAR UNIT INSTALLED AT MELGARVE; RATINGSTBC - FOR EXAMPLE (±225MVAR, CONNECTED TO 275KV BUSBARRUNNING AT 20KV).

13. ASSUMED STATCOM TRANSFORMER LOCATED ON WEST OF STATCOMCOMPOUND BUT CONNECTUON FROM GIS COULD BE MODIFIED TOACCOMODATE A DIFFERENT TRANSFORMER POSITION.

14. CURRENTLY NO INFORMATION ON MSCDN REQUIRED AT THIS SITE.INDICATIVE SPACE ENVELOPE ONLY.

15. BUILDING OUTLINE INDICATIVE ONLY - DESIGN TO BE CONFIRMED.16. GIS BAYS 8,9,10,11 AND 12 ARE SPACE PROVISION ONLY. GIB ENTRIES TO

BE PROVIDED.17. OVERHEAD LINE ROUTES AND POSITION OF TOWERS (TERMINAL OR

OTHERWISE) TO BE CONFIRMED AND SUBJECT TO SEPARATE SECTION 37CONSENT.

18. OHL REQUIRE TO BE MODELLED TO ENSURE NO INFRINGEMENT OFELECTRICAL CLEARANCES.

19. PLATFORM LEVEL TBC AT DETAIL DESIGN STAGE AFTER GROUNDINVESTIGATION SURVEY AND CUT/FILL BALANCE OPTIMISED.

20. ELECTRICAL PHASING TO BE CONFIRMED.21. ACCESS ROUTE TO SITE TBC.22. PROPOSED PLATFORM AREA = 63870m² / 15.78acres.

!!!TO BE PRINTED IN COLOUR!!!

LEGEND:-SCT STATIC COMPENSATION TRANSFORMERSGT SUPER GRID TRANSFORMERET EARTHING TRANSFORMERNER NEUTRAL EARTHING RESISTORES EARTH SWITCHDISC DISCONNECTOR (RCP)DG DIESEL GENERATORCB CIRCUIT BREAKERCSE CABLE SEALING ENDCVT CAPACITIVE VOLTAGE TRANSFORMERSA SURGE ARRESTERPI POST INSULATORGIB GAS INSULATED BUSBARH HIGH LEVEL (POST INSULATOR)

PLANT PROPOSED

SSE Inveralmond House, 200 Dunkeld RoadPerth, PH1 3AQ, UK www.sse.com

Drawing Status:

Scale:

Date:

Drawing Number: Sheet No: Revision No:

Approved:

Checked:

Drawn:

Title:

Project Number: Location:

Project:

Date Plotted: 23.10.2019

File Name: LT96_KIND_1104_0041_00_00 - Kinardochy Reactive Compensation SS 275(400kV) AIS SUBSTATION (BASED ON SIEMENS SUBMISSION).dwg

A0

DOCUMENT REFERENCE:

LIST OF ALL RELEVANT DRAWINGS OR DOCUMENTS THAT DIRECTLY RELATE TOTHE CURRENT REVISION OF THE DRAWING

21 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

A

B

C

D

E

F

G

H

J

K

L

M

N

P

Q

R

21 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

A

B

C

D

E

F

G

H

J

K

L

M

N

P

Q

R

KINARDOCHY 275kV REACTIVE COMPENSATION SUBSTATION

LT000096 TUMMEL

KINARDOCHY 275kV REACTIVE COMPENSATION SUBSTATIONPROPOSED SUBSTATION LAYOUT & ELEVATION AT SITE 4FOR PUBLIC CONSULTATION PURPOSE - SHEET 1

FOR INFORMATION

1:500 @ A0

PMR

LT96_KIND_1104_0041 01 0B

DRAFT

Top Related