AOA Ops and Safety Conference
John DowFAS Implementation Lead
Airspace Regulation
22 June 2015
Overview
• SARG Organisation Structure• Airspace Change Process
– Challenges• Looking ahead
Organisation Structure
22 June 2015
Safety & Airspace Regulation Group
Phil RobertsAirspace, ATM & Aerodromes
Harry DalyInt’l
CNS/ATM
Stuart LindseyManager Airspace
Chris PeartManager
ATM
Graeme Ritchie
Manager Aerodrome
s
Andy Wells
Manager Infrastructu
re
SARG
AAA
Phil RobertsAirspace, ATM &
Aerodromes
Harry DalyInt’l CNS/ATM
Stuart LindseyManager Airspace
Chris PeartManager ATM
Graeme RitchieManager
Aerodromes
Andy WellsManager
Infrastructure
Airspace Regulation
Head of Airspace Regulation
Principal Airspace Regulator
x2
Airspace Regulators
Airspace Regulator
IFP
Airspace Regulator
NAV
Airspace Specialist
Cartographic
ATM Specialists
PBN Implementation Lead
FAS Implementation Lead
Airspace Change Process22 June 2015
Airspace Change Process
• Airspace Charter (CAP 724) provides a high-level description of CAA’s responsibilities and principles to conduct the planning of airspace in the UK
• CAA Guidance on the Application of the Airspace Change Process (CAP 725) provides guidance on the process for changes to UK airspace
• Compliant with National Law• Sets CAA’s Statutory Duties• Section 70 Air Transport Act 2000• Air Navigation Directions 2001 (2004)
• Regulator: • Owns, and is fully responsible for, the Airspace Change Process (ACP)
• Change Sponsor:• Owns, and is responsible for developing, the airspace change proposal
• Provides a framework for Change Sponsors• Abides by criteria set out in HM Government’s Consultation Principles• Defines the Roles and Responsibilities of stakeholders• Provides specific guidance for consultation and environmental assessments
• Environmental Guidance to the Civil Aviation Authority on Environmental Objectives Relating to the Exercise of its Air Navigation Functions (2014) – the ‘Air Navigation Guidance’
Overview of Airspace Change Process
• Transparency of the Process• Size and scope of the potential change programme• Change sponsors perceive the process to be:
• Too long • Too expensive• And a successful outcome is not guaranteed
Airspace Change Process - Challenges
Looking Ahead
22 June 2015
Looking Ahead• Airport Commission
– Findings due to be published imminently• Future Airspace Strategy
– DfT; Case for FAS• EU pilot Common Project
– ATM Functionalities 1-6– Deployment Programme
• VOR Rationalisation• PBN Deployment
Finish