Notes: MANTENIMIENTO is the most important Spanish technical journal about Maintenance.
This journal is published by AEM Asociacin Espaola de Mantenimiento (Spanish
Manitenance Asociation) which belong spanish utilities like IBERDROLA or UNION FENOSA ,
heavy industries like REPSOL or CEMENTOS MOLINS and important repair workshops like
Talleres PETIT (SARELEM).
8/14/2019 Art.ESierra-ETP 0MANTENIMIENTO.pdf
2/15
8/14/2019 Art.ESierra-ETP 0MANTENIMIENTO.pdf
3/15
Condition Based Maintenance in
Transformers
ETP METHODEmilio Sierra Gmez
Iberdrola Generacin, S.A.
The normal operation of transformers can be afected by several external factors.
Diagnostics systems are based onperiodical tests performace which have the aim todetermine when and where is going to appear alterations that afect in abnormal way
to some of transformer components.
This Condition Based Maintenance will allow us to detect incipient transformer
problems before of breakdown occur, allowing us:
To avoid urgent performances. To avoid high costs of repair and transport.
To avoid unavailabilities of long duration.
Optimization of hours men.
Diagnostic and evaluation systems could be:
Electrical
Physical-Chemical.
MantenimientoJulio-Agosto 2001
8/14/2019 Art.ESierra-ETP 0MANTENIMIENTO.pdf
4/15
The transformer diagnostic system developed by Unitronics and IBERDROLA, ETP
SYSTEM, performes the necessary tests to detect and to confirmany problem in
each part of the transformer, it means that the ETPdetermines the current status of
each part of the tranformer:
Solid and liquid insulation.
Windings.
Tap changer.
Magnetic core.
Transformer status knowledge will allow us to programme the most suitable actions:
To continue in service.
To limit functions.
Specific reviews.
To repair or to substitute
2.-ETP TRANSFORMER EVALUATION SYSTEM.
This system can be applicated to all kind of transformer or autotransformer, single-
phase or three phase, power or distribution transformer, independently of the power
of nominal voltage.
The ETP filosophyis based in basic principles of Condition Based Maintenance:
Non destructive tests. Reliable and repetitive. Results are automaticaly stored and facility of managing.
THE SYSTEM ETP is formed by four units of measurement (UM). Each part of the
transformer will be characterized by the measurements of two units.
8/14/2019 Art.ESierra-ETP 0MANTENIMIENTO.pdf
5/15
Winding: UM-1,UM-3
Tap changer: UM-1,UM-3
Magnetic package: UM-1,UM-5
Insulation: UM-2, tan d
ETP SYSTEM developed by Iberdrola/Unitronics is based in an adquisition system
controled by PC via RS232:
With the ETP System could be detected and confirmed the following problems:
TAP CHANGER
Faults in the Tap changer. High resistance connections.
WINDINGS
SHORTCIRCUIT between turns Winding cuts. Check the winding connections, CONNECTION GROUP Connections Slackening. Open windings. Hot spots in the windings.
INSULATION
Problems in oil- papper insulation, DEGRADATION. Absolute value of the insulation, LEAKAGE CURRENT.
8/14/2019 Art.ESierra-ETP 0MANTENIMIENTO.pdf
6/15
MAGNETIC CORE Defects in magnetic core Windings displacements
UNITRONICS ETP SYSTEM.
UM1B
This measurement unit performs a three-phase Transformer Turn Ratio test,
connection group checking and core problems testing based on exciting currents
measurement.
The test is made with AC and it automatically measures each winding in relation with
the other ones. Throught UM1B test results, we candetect following problems:
Short circuit between turns.
Winding cuts.
Tap changer problems.
Defects in magnetic core.
Check winding connections, CONNECTION GROUP
8/14/2019 Art.ESierra-ETP 0MANTENIMIENTO.pdf
7/15
UM2
This unit performs the following measurements in an automatic and guided way:
Recovery Voltage and Time Constant that allows us to predict an anomalousageing in paper/oil insulation.
Insulation Resistance and Polarization Index, that give us an overview of
insulation condition.
For the calculation of those parameters, this unit applies different D.C. voltage levels
between windings and ground. This test is totally non-destructive for the machine
and allows us to detect problems in the transformer like:
Degradation of solid dielectric
Degradation of liquid dielectric
Contamination of the insulation
This is the only one test that could detect the paper insulation status
independiently of oil and therefore it could give information about the machine
remanent life.
UM3
This unit performs low resistance measurements specially of the windings of any kind
of transformers or autotransformer, providing both simple and compound resistance
value for high and low voltage and tertiary. The results are provided at reference
temperature specified by the operator.
The UM3B unit permits to do the following measurements automatically:
Automatic winding resistance on the three phases.
Resistance values corrected in temperature.
Calculations of individual and compound resistance values (or Y).
8/14/2019 Art.ESierra-ETP 0MANTENIMIENTO.pdf
8/15
The measurement technique used is the metric ratio resistance method (measured
on four wires) and automatic magnetization/desmagnetization of the core, which
avoid breaks of the equipment of measurement, guarantees the safety of the
operator and the precision and repetitivity of the measurement
This test is totally non-destructive for the machine and allows us to detect problems
in the transformer like:
SHORTCIRCUIT between turns
Winding cuts.
Connections Slackening.
Open windings.
Hot spots in the windings
Tap changer defects
UM5
UM5B measures the short circuit impedance of power , distribution transformers and
autotransformers applying a voltage test to the high voltage winding of the
transformer and measuring the voltage excitation, the current excitation and phase
angle deviation between them: V1 and I1. Its carried out with the transformer LV
winding in short circuit.
With the short circuit impedance measurement it is possible to detect problems in
the transformer like:
Displacements between windings
Open winding
Short-circuiting between turns
8/14/2019 Art.ESierra-ETP 0MANTENIMIENTO.pdf
9/15
9
4.-Conclusiones.
This transformer evaluation method and the test system has been developed like a
combination of 40 years of IBERDROLA test experience, testing Power and
Distribution Transformer (more than 20.000 field test), and the system development
of UNITRONICS during the last 10 years.
ETP method performs the necessary non destructive tests in order to make a
complete transformer status analysis.
ETP System performs this method in a very easy and guided way. Some of tis
advantages are:
Reduced measurement time (2 4 hours, report generation included). Unification of the measurement systems. Instrumentation Cost reduction. Portable. Simplification of calculations Common data base to all tests Correction of results. Numerical and Graphical results presentation. Immediate reports production It facilitates the trend analysis
ETP allows to establish a Predictive Maintenance Program of Tranformer without the
need of high cost and complicated instruments. Also, it is not necesary large
transformer outage, becouse ETP system make a complete dignostic of the
transformer status in 3 hours.
8/14/2019 Art.ESierra-ETP 0MANTENIMIENTO.pdf
10/15
10
Example:
Following example shows a tap changer problem detected through ETP method.
POWER TRANSFORMER: 12 MVA-20/6,9 Kv-Dyn1 con regulacin en carga.
File: d:\SAGEN_WIN\Ensayos\TRPGENER79812\RDBTRPGENER79812.0
Date: 01-10-99
**** IDENTIFICATION ****
SITE NAME: C.T.CASTELLON
MACHINE TYPE: Transformador de Potencia
SERIAL NUMBER: 79812
MANUFACTURER: GENERAL ELECTRICA ESPAOLA
FUNCTION: T-2A1.T AUXILIAR
MADE BY: J.M. DEL RIO
UM-3 SERIAL NUMBER: 97014
**** TECHNICAL DATA ****
TYPE: TPAV12000/25 Three-phase
TERTIARY:: No
REFRIGERATION: OIL
MANUFACTURING YEAR: 1971
POWER (MVA): 12,000
NOM, Vcc (%) 7,080
HV VOLTAGE (KV): 20,000
LV VOLTAGE (KV): 6,928
HV CURRENT (A): 288,700
LV CURRENT (A): 833,400
8/14/2019 Art.ESierra-ETP 0MANTENIMIENTO.pdf
11/15
11
CONNECTION GROUP: Dyn1
** TAP CHANGERSELECTOR OF THE HV **
HANDLING NUMBER: 28158
REGULATION: Load
SWITCH TYPE: MA/2
MANUFACTURER: G.E.E.
TAPS NUMBER: 22
NOMINAL TAP: 11
CENTRAL TAPS NUMBER: 1
STEP (V): 200
ETP UM3 test detects a variation of winding resistance in HV winding:
Phase W in the position 5 of the Tap Changer.
**** MEASUREMENTS ****
DATE: 01-10-99
TRANSFORMER TEMPERATURE: 68,0 F
REFERENCE TEMPERATURE: 75,0 F
MEASURED WINDINGS: HV LV
TOTAL MEASUREMENT TIME (h:mm:ss): 0:48:20
** MEASUREMENTS OF THE HV **
MEASUREMENT TIME: 0:27:58
8/14/2019 Art.ESierra-ETP 0MANTENIMIENTO.pdf
12/15
12
COMPOUND RESISTANCE PHASE RESISTANCE
TAPR-AB(Ohm)
R-BC(Ohm)
R-AC(Ohm)
WR-A(Ohm)
WR-B(Ohm)
WR-C(Ohm)
Measurementelapsed Time
1 0,2102 0,2107 0,2093 0,320307 0,321841 0,317582 0:02:48
2 0,2079 0,2087 0,2071 0,3166 0,319055 0,314182 0:02:38
3 0,2064 0,2067 0,2053 0,314724 0,315646 0,311392 0:02:26
4 0,2044 0,2045 0,2034 0,311732 0,312038 0,308698 0:02:36
5 0,2031 0,2038 0,2054 0,307789 0,309894 0,314816 0:02:46
6 0,2001 0,2008 0,2001 0,304372 0,306509 0,304372 0:02:36
7 0,1967 0,1971 0,1958 0,2998 0,301027 0,297074 0:02:36
8 0,2011 0,2025 0,2006 0,305786 0,310085 0,30428 0:02:24
9 0,2029 0,2033 0,2033 0,308587 0,309804 0,309804 0:02:24
10 0,2047 0,2048 0,2036 0,312239 0,312546 0,308903 0:02:22No. 11 0,2064 0,2069 0,2055 0,31452 0,316054 0,311796 0:02:22
Note: In this chart and plot are only represented the first 11 positions
Grfico 1
In order to better definiton of transformer problem, we compare UM3 winding
resistance measurements with UM1 transformer turn ratio and exciting current
measurements. Following chart shows the Transformer Turn Ratio Measurements,
which shows TTR normal variation with the tap changer position.
8/14/2019 Art.ESierra-ETP 0MANTENIMIENTO.pdf
13/15
13
1.W U\2.u n 1.U V\2.v n 1.V W\2.w n
POS. Theo TTR Meas. TTR % Meas. TTR % Meas. TTR %
1 5,5 5,497 0,05 5,497 0,05 5,498 0,04
2 5,45 5,448 0,04 5,448 0,04 5,448 0,04
3 5,4 5,397 0,06 5,398 0,04 5,398 0,04
4 5,35 5,348 0,04 5,348 0,04 5,348 0,04
5 5,3 5,298 0,04 5,298 0,04 5,298 0,04
6 5,25 5,247 0,06 5,248 0,04 5,247 0,06
7 5,2 5,198 0,04 5,198 0,04 5,198 0,04
8 5,15 5,148 0,04 5,148 0,04 5,148 0,04
9 5,1 5,098 0,04 5,098 0,04 5,098 0,04
10 5,05 5,048 0,04 5,048 0,04 5,048 0,04
11a 5 4,998 0,04 4,998 0,04 4,998 0,04
12 4,95 4,948 0,04 4,948 0,04 4,948 0,04
13 4,9 4,898 0,04 4,898 0,04 4,898 0,04
14 4,85 4,848 0,04 4,848 0,04 4,848 0,04
15 4,8 4,798 0,04 4,798 0,04 4,798 0,04
16 4,75 4,748 0,04 4,748 0,04 4,748 0,04
17 4,7 4,698 0,04 4,698 0,04 4,698 0,04
18 4,65 4,648 0,04 4,648 0,04 4,648 0,04
19 4,6 4,598 0,04 4,598 0,04 4,598 0,0420 4,55 4,548 0,04 4,548 0,04 4,548 0,04
TTR vs Tap Changer Pos
0
1
2
3
4
5
6
1 4 710
13
16
19
Tap Changer
TTR
1.W U\2.u n
1.U V\2.v n
1.V W\2.w n
8/14/2019 Art.ESierra-ETP 0MANTENIMIENTO.pdf
14/15
14
EXCITING CURRENT TEST (110 V Test):
NOMINAL POSITION1.W U\2.u n 1.U V\2.v n 1.V W\2.w n
Exciting Current (A) 0,0064 0,0062 0,0064
Conclusions:
Winding resistance readings shows that Phase W, HV winding, tap changer position 5
has anormalous increasing of its resitance value.
Transformer turn ratio is normal in all tap changer position.
Exciting current readings are very similar in the three phases.
After ETP test results evaluation, in IBERDROLA Test report 2372 is recommended
tap changer revision, where is detected a fault:
8/14/2019 Art.ESierra-ETP 0MANTENIMIENTO.pdf
15/15
15
After tap-changer repair, it was mounted and a ETP test was made again. Following
Winding Resistance readings show that the problem has desappeared and now thevariations between taps are as expected.
Grfico 2