4100ES Fire Alarm System Technician Training
Assessment Overview ..................................................................................................... 4
Technician Workflows ..................................................................................................... 5
Assessment 1-1: Angels Awaiting Wings Installation/Commissioning ......................... 6
Assessment 1-1: Task Checklist ..................................................................................... 9
Assessment 1-2: Angels Awaiting Wings Service/Break-Fix ..................................... 10
Assessment 1-2: Task Checklist ................................................................................... 12
Assessment 2-1: Patriot Palace Installation/Commissioning ..................................... 13
Assessment 2-1: Task Checklist ................................................................................... 16
Assessment 2-2: Patriot Palace Service/Break-Fix .................................................... 17
Assessment 2-2: Task Checklist ................................................................................... 19
Assessment 3-1: Skyway Motors Installation/Commissioning .................................... 20
Assessment 3-1: Task Checklist ................................................................................... 23
Assessment 3-2: Skyway Motors Service/Break-Fix .................................................. 24
Assessment 3-2: Task Checklist ................................................................................... 26
Assessment 3-3:Palace Project Service/Break-Fix ..................................................... 27
Assessment 3-3: Task Checklist ................................................................................... 28
Assessment 4-1:Ruwais Burooj 1 Installation/Commissioning .................................... 29
Assessment 4-1: Task Checklist ................................................................................... 30
Assessment 5-1: Jeffery P. Malone Memorial Hospital Installation/Commissioning ... 31
Assessment 5-1: Task Checklist ................................................................................... 32
Assessment 5-2: Jeffery P. Malone Memorial Hospital ................................................. 33
Assessment 5-2 Task Checklist .................................................................................... 34
Assessment 6: Michael J. Pinder Regional Airport Service/Break-Fix........................ 35Assessment 7-1: Service Gateway................................................................................ 36
4100ES Technician Core Competency Score Sheet ..................................................... 38
4100ES Technician Core Competency Score Sheet (Continued)................................. 39
4100ES Technician Core Competency Score Sheet (Continued) .................................40
7/26/2019 Asessment Book - ME
4/41
4100ES Fire Alarm System Technician Training
Assessment OverviewThe Purpose of this Handbook
This handbook contains your formal assessments for this course. During eachassessment, you have the opportunity to demonstrate core competencies that proveyour capabilities working on a 4100ES Fire Alarm System.
Grading
Grading is done on a Competency Score Sheet (contained at the end of this book).
The Competency Score Sheet lists critical skills necessary to pass this course.The sheet also specifies the opportunities throughout the course where you candemonstrate your ability to perform these skills (e.g., Assessments 2-2 and 4-1).
You have more than one assessment opportunity to demonstrate some competencies.You may only have a single opportunity to demonstrate other competencies.
Note: You are not assessed on any competency that you have not had time to practice. Once you have demonstrated the ability to perform a competency, your instructor
initials a box on your Competency Score Sheet to indicate this accomplishment.
You must demonstrate your ability to complete ALL core competencies to become aCertified Technician on the 4100ES Fire Alarm System.
At the end of each assessment contained in this handbook there is a supplementalworksheet that contains the following three columns:
1. Task The action you perform to complete an objective. For exampleDownload CFIG
2. Milestone Your goal. For example, Successfully Downloaded CFIG
3. Customer(s) Each assessment task you perform directly benefits one or morecustomers. These customers include other technicians and/or inspectors back atyour District Office, Authorities Having Jurisdiction (AHJs), your Customer
which could include their IT department, and/or their Contractors.These customers are the groups who will assess you back in the Real Worldwith questions such as:
Did you perform satisfactory work?
Was the work done correctly? Was it done right the first time?
7/26/2019 Asessment Book - ME
5/41
4100ES Fire Alarm System Technician Training
Technician Workflows
7/26/2019 Asessment Book - ME
6/41
4100ES Fire Alarm System Technician Training
Assessment 1-1: Angels Awaiting Wings
Installation/Commissioning
Time Limit
You have 40 Minutesto complete this Assessment.
Scenario
You are a Commissioning Technician assigned to install a 4100ES Fire Alarm Systemat the Angels Awaiting WingsAssisted Living Facility in Dubai. You are supplied withthe following document.
Instructions
Based on this information and knowledge that you have gained during your practiceexercises:
1. Perform the required installation and programming tasks.
2. Call the instructor to your workstation for grading when you are finished.
IMPORTANT: Double-check your work! You will not be able to make changes toyour job once the instructor begins to grade your work.
Angels Awaiting Wings 4100ES Job
Project number: 112772
Order number: 2979
Job Number: 111U001A
Location: Al Khaleej Street, Dubai
Customer: Angels Awaiting Wings Assisted LivingFacility
Contractor: Dave and Daughters
Customer Contact: Joe MagnetMaintenance Supervisor
7/26/2019 Asessment Book - ME
7/41
4100ES Fire Alarm System Technician Training
Equipment being installed: 4100ES FACP, 3 Smoke Sensors, 2 NAC
Circuits (1 Horn Circuit and 1 VisualCircuit)
Location of Main Panel: Wall in Lobby
AC Breaker Location: Utility Room behind receptionist
Secondary Power Supply: Shall have sufficient capacity tooperate the system under quiescent load
for a minimum of 24 hours and, at theend of that period, shall be capable of
operating all alarm notification
appliances used for evacuation or to
direct aid to the location of an
emergency for five minutes.
Panel Operation: General Alarm operation Any alarmwill activate all NAC circuits. A
single key press will acknowledge all
alarm conditions. Horns will turn OFF
on Silence, but Synchronized Visuals
will remain ON until the Alarm
Condition has been cleared and the
system has been reset.
Other Requirements: Installation, pictures, as well as
Inspection and Testing reports shall bestored at the panel in non-volatile
compact flash memory. (ROC document is
located in your Job Aids folder)
Specific Job Information: Labels
PHOTO SENSORS
M1-2 Lobby Area
M1-3 Day Room
M1-8 Hall
Heat Sensor
7/26/2019 Asessment Book - ME
8/41
4100ES Fire Alarm System Technician Training
AUDIBLE
SIG4 HORNSOther Information: Time shall be displayed in 24 hr. format
7/26/2019 Asessment Book - ME
9/41
4100ES Fire Alarm System Technician Training
Assessment 1-1: Task Checklist
Task Milestone Customer(s)
1. Complete information in the
Panel tabInformation accurate and complete
Break/Fix TechnicianIs this informationaccurate?
2. Download CFIG Successfully downloaded CFIGMultipleDoes the Panel function
properly?
3. Create and populate folders
in Mass StorageFolders created and populated
Technicians/InspectorsAre these folders clearlylabeled so I can readilyaccess them?
4. Complete information in the
Hardware tab
Information accurate and complete
Break/Fix TechniciansIs this informationaccurate and in the
proper location for whenI do my job?
5. Program IDNet
ContractorIs this informationaccurate and in theproper location forwhen I do my job?
6. Program NACs
ContractorIs this informationaccurate and in theproper location forwhen I do my job?
7. Customer achieves
occupancy at the agreed
upon time
The job was completed on time
MultipleDid the technicianfulfill their obligations ontime?
7/26/2019 Asessment Book - ME
10/41
4100ES Fire Alarm System Technician Training
Assessment 1-2: Angels Awaiting Wings
Service/Break-Fix
Time Limit
You have 20 Minutesto complete this Assessment.
Scenario
Two years have elapsed since the commissioning of the Angels Awaiting WingsAssisted Living Facility in Dubai. You are a Break/Fix Technician assigned to thiscustomer site. Your District Office supplies you with the following document.
Instructions
Based on this information and knowledge you have gained during your practiceexercises and the previous assessment:
1. Perform the required installation and programming tasks.
Note: For the instructors convenience throughout this course, please save yourjob file with a later revision (e.g., 111U001A becomes111U002A).
2. Call the instructor to your workstation for grading when you are finished.
IMPORTANT: Double-check your work! You will not be able to make changes toyour job once the instructor begins to grade your work.
Angels Awaiting Wings Job
Call was received: 9:00AM Wednesday
Project number: 112772
Order number: 2979
Job number: 111U001A
Location: Al Khaleej Street, Dubai.
Customer: Angels Awaiting Wings Assisted LivingFacility
7/26/2019 Asessment Book - ME
11/41
4100ES Fire Alarm System Technician Training
Original Equipment 4100ES FACP, 3 Smoke Sensors, 2 NAC
Installation: circuits (1 Horn Circuit and 1 Visual
Circuit)
Customer Requested A System Trouble must be acknowledged
Software Change(s): every 12 hours.
Time and Date format changed to 12 hr.
Login required to change the Time and
Date. This login requires a new user
added with a Passcode of 17272.
Customer have requested for Single Hard
Reset while activating the System Reset
Switch from the panel
All horns shall play temporal code
Customer Requested Add a Smoke Sensor at the Building 2
Hardware Change(s): Nurse Station M1-6 Photo Smoke Sensor
Perform the necessary changes build and save the job and call your instructor.
7/26/2019 Asessment Book - ME
12/41
4100ES Fire Alarm System Technician Training
Assessment 1-2: Task Checklist
Task Milestone Customers
1. Configure Access Levels
Information accurate and complete
CustomerIs this informationaccurate and in theproper location?
2. Configure Passcodes
3. Configure System Options
4. Configure IDNet
5. Install Smoke Sensor M1-6 Smoke Sensor installedCustomerIs the smoke sensoroperational?
6. Complete the work on time The work was completed on timeCustomerWas the job completedon time?
7/26/2019 Asessment Book - ME
13/41
4100ES Fire Alarm System Technician Training
Assessment 2-1: Patriot Palace Installation/Commissioning
Time Limit
You have 2 Hoursto complete this Assessment.
Scenario
You are a Commissioning Technician assigned a job to Install a 4100ES Fire Alarm
System in newly constructed New England Pharmaceuticals,a three story officebuilding in Abu Dhabi. The customer has opted to include an InfoAlarm Display as wellas audio components in the existing panel. They have requested a new MessageLibrary to increase their 4100ES Audio capabilities. Perform installation andprogramming tasks based on the information provided.
Call the instructor to your workstation when you are finished.
IMPORTANT: Double-check your work! You will not be able to make changes to
your job once the instructor begins the grading process.Instructions
Save job file PRAC5Bas 112U001Aand then update the job with information providedin this assessment.
Patriot Palace Job
Project number: 020979
Order number: 7929
Job Number: 112U001A
Location: Abu Dhabi
Customer: New England Pharmaceuticals
Contractor: Brogan BrothersEquipment Being Installed: Add a 35W Audio Amplifier and InfoAlarm
to Bay 1 of the Transponder
Location of Main Panel: Main Entrance
7/26/2019 Asessment Book - ME
14/41
4100ES Fire Alarm System Technician Training
AC Breaker Location: Room 102
Secondary Power Supply: Shall have sufficient capacity tooperate the system under quiescent load
for a minimum of 24 hours and, at the
end of that period, shall be capable of
operating all alarm notification
appliances used for evacuation or to
direct aid to the location of an
emergency for five minutes.
Panel Operation: All speaker circuits shall operateGeneral Alarm, OFF on Silence. The
Second Floor speakers shall be
controlled by the first circuit of the
75W Audio Amplifier and the Third Floor
speakers shall be controlled by the
second circuit of the 75W Audio
Amplifier.
The Annunciator Display Card (located in
Slot 7 of the main can) shall have the
4th switch programmed to turn ON the
Second Floor speakers to Audio Channel
1. The corresponding LED must be
programmed to annunciate the ON state of
the speaker circuit. The fifth switch
shall be programmed to turn ON the Third
Floor speakers to Audio Channel 1. The
corresponding LED must be programmed to
annunciate the ON state of the speaker
circuit.
Update the Audio Message File
(File supplied by instructor)
Other Requirements: Install Mode shall be preserved whendownloading CFIG as the Monitor and
control modules have yet to be
installed.
The Contractor has requested training
th I t ll M d f t ll
7/26/2019 Asessment Book - ME
15/41
4100ES Fire Alarm System Technician Training
Specific Job Information: AUDIBLESecond Floor Speakers
Third Floor Speakers
Other Information: The time shall be displayed in 24hr.format
7/26/2019 Asessment Book - ME
16/41
4100ES Fire Alarm System Technician Training
Assessment 2-1: Task Checklist
Task Milestone Customer
1. Add an InfoAlarm*
Properly Install andProgram each hardwarecomponent
CustomerWas the hardware properlyinstalled?
2. Add an Audio Amplifier*
3. Add a New Audio Chipset (instructor
supplied)
Perform a Download of anAudio File
CustomerAre the Audio Messages what Iasked for?
4. Add to Existing Annunciator
ProgrammingAdded AnnunciatorProgramming
CustomerCan I easily control my newspeakers?
5. Use Install Mode to Clear Multiple
Panel TroublesPanel left with singletrouble
Technician(s)/ContractorsDoes this make my job easier?
6. Train Contractor on how to use
Install Mode** Trained Contractor
Contractor
Did the Technician explain InstallMode to me so I can utilize thisfeature?
7. Enable the Customer to achieve
occupancy at the agreed upon time.The job was completed ontime.
CustomerDid the technician fulfill theirobligations on time?
7/26/2019 Asessment Book - ME
17/41
4100ES Fire Alarm System Technician Training
Assessment 2-2: Patriot Palace
Service/Break-FixTime Limit
You have 1 Hourto complete this Assessment.
Scenario
Two years have elapsed since the commissioning of the New England Pharmaceuticalsoffice building. You are a Break/Fix Technician assigned to this customer site. Theowner of this office complex has contacted your District Office to report the FACP isreporting multiple troubles. You obtain the latest file on record for Patriot Place fromyour dispatch.
Instructions
Based on this information and knowledge you have gained during your practiceexercises and the previous assessment:
Leave the Room for a Brief Break
1. Restore the Instructor provided 222x002Ajob file. (Do not download the job to yourpanel.)
2. Perform the required troubleshooting to resolve all troubles.
3. Call the instructor to your workstation for grading when you are finished.
Patriot Place Job
Call was received: 9:00AM Wednesday
Project number: 020979
Order number: 7929
Job number: 222U002A
Location: Abu Dhabi
7/26/2019 Asessment Book - ME
18/41
4100ES Fire Alarm System Technician Training
Equipment being installed: None at this time
Customer RequestedSoftware Change(s): The Wrong Floor Annunciates when a
call is placed from the Remote
Firefighter Phone.
The 3rd Floor Speaker Switch does
not work.
Customer RequestedHardware Change(s): None at this time
7/26/2019 Asessment Book - ME
19/41
4100ES Fire Alarm System Technician Training
Assessment 2-2: Task Checklist
Task Milestone Customer
1. Troubleshoot and correct
deficiency
Student finds, corrects, and reportsdeficiencies
Customer
Did the Technician find and fix theproblems on my FireAlarm System?
2. Troubleshoot and correct
deficiency
3. Troubleshoot and correct
deficiency
4. Troubleshoot and correct
deficiency
5. Complete the work on time The work was completed on time
CustomerWas the work donein the specifiedtime?
7/26/2019 Asessment Book - ME
20/41
4100ES Fire Alarm System Technician Training
Assessment 3-1: Skyway Motors Installation/Commissioning
Time Limit
You have 1 Hour and 15 Minutesto complete this Assessment.
Scenario
Part of your commissioning assignment for the Skyway Motors High-Rise job is to meet
the customers request to add a bank of elevators to their 4100ES Fire Alarm System.You are also asked to add an Audio WalkTest Group.
Call the instructor to your workstation when you are finished.
IMPORTANT: Double-check your work! You will not be able to make changes toyour job once the instructor grades your work.
InstructionsOpen job file PRAC7Aand save as 113U001Aand then update the job with information
provided in this assessment.
Skyway Motors Job
Project number: 032952
Order number: 6151
Job Number: 113U001A
Location: 1121 Skyway Motors, Dubai
Customer: Scott Anderson
Contractor: Daigneault Do it All Construction
7/26/2019 Asessment Book - ME
21/41
4100ES Fire Alarm System Technician Training
Equipment Being Installed: An 8-Point Relay Card 4100-3206 tocontrol Primary, Alternate, and Shunt
Trip for the elevator located in
Building 2.
The Relay Card will be located in the
Main Fire Panel, Bay 2, Block F.
The following will be building 2
Elevator Lobby Detectors. Edit the
labels accordingly
M1-2 Smoke Detector First Floor Lobby
M1-3 Smoke Detector Second Floor Lobby
M1-6 Smoke Detector Third Floor Lobby
M1-5 Heat Detector Machine Room
Panel Operation:
An alarm reported from the Second orThird Floor Lobby detector is to
activate the Primary Elevator Capture
Relay and turn ON the Annunciator LED
labeled Elevator Primary.
An alarm reported from the Firstfloor Lobby Detector is to activate
the Alternate Elevator Capture Relay
and turn ON the Annunciator LEDlabeled Elevator Alternate.
An alarm reported from the MachineRoom detectoris to activate the
Shunt Trip Relay and turn ON the
Annunciator LED labeled Elevator
Shunt Trip.
An Annunciator Switch shall beprogrammed to bypass the elevator
operation for Building 2.
An LED shall be programmed toannunciate the bypass and a Trouble
shall be reported at the Main Panel
7/26/2019 Asessment Book - ME
22/41
4100ES Fire Alarm System Technician Training
Other Requirements: Program an Audio WalkTest Group fortesting Building 1 devices (to enable
customer to perform future maintenance/
testing).
Specific Job Information: Building 1 Devices shall be:
M1-1 Pull Station
M1-6 Smoke Sensor
Building 1 Speakers shall be:
2ND and 3RD Floor Speakers
Program a Switch and LED(labeled as Elevator Bypass )on the INFOALARM Displayto Bypass this elevator operation.
7/26/2019 Asessment Book - ME
23/41
4100ES Fire Alarm System Technician Training
Assessment 3-1: Task Checklist
Task Milestone Customer
1. Add a 4-Point Flat Relay
Card
Elevator is operationalCustomerDoes my elevator
function properly?
2. Program the Annunciator Successfully programmed AnnunciatorCustomerCan I operate myelevator?
3. Add an Elevator Bypass
SwitchElevator Bypass Switch operational
MultipleCan I Bypass ElevatorOperation to do my
job?
4. Program and Test
an Audio WalkTest GroupAble to Program and Test an AudioWalkTest Group
TechnicianCan I now use theAudio WalkTestFeature?
5. Meet with Authority Having
Jurisdiction*Satisfy AHJs request(s)
AHJDoes this work meetmy requirements?
6. Enable the Customer to
achieve occupancy at the
agreed upon time.
The job was completed on time
CustomerWas I able to getoccupancy on time?
* After you complete the other tasks, let your instructor know you are ready for ameeting with the AHJ.
7/26/2019 Asessment Book - ME
24/41
4100ES Fire Alarm System Technician Training
Assessment 3-2: Skyway Motors Service/Break-Fix
Time Limit
You have 30 Minutesto complete this Assessment.
Before You Begin
Restore Instructor provided job file 223U002A (do not download this job to your panel).
Scenario
Two years later you are dispatched to the Skyway Motors high-rise for a report of a
Bypass Switch not working on Elevator Bank 2 Located on Box 2 Bay 2 set of switches.You plan to troubleshoot this issue to determine if it is a problem that you areresponsible for. If so, you must make on-site repairs necessary to restore the BypassSwitch functionality.
Call the instructor to your workstation when you are finished with this assessment.
IMPORTANT: Double-check your work! You will not be able to make changes toyour job once the instructor grades your work.
Call was received: 8:00AM Thursday
Project number: 032952
Order number: 6151
Job number: 223U002A
Location: Skyway Motors, DubaiCustomer: Scott Anderson
Equipment being installed: None at this time
Customer RequestedSoftware Change(s): N t thi ti
7/26/2019 Asessment Book - ME
25/41
4100ES Fire Alarm System Technician Training
7/26/2019 Asessment Book - ME
26/41
4100ES Fire Alarm System Technician Training
Assessment 3-2: Task Checklist
Task Milestone Customer
1. TroubleshootDetermine the root cause of theproblem and then if needed, restoreNormal Functionality
CustomerIs my ElevatorBypass Switch backto normal?
2. Answer Customer
Question at end of first
Section.
Successfully answer customer questionafter troubleshooting FACP
Customer
Did the Techniciansufficiently answermy question?
3. Complete the Work in a
Timely MannerThe work was completed in a timelymanner
CustomerWas this work donequickly?
7/26/2019 Asessment Book - ME
27/41
4100ES Fire Alarm System Technician Training
Assessment 3-3:Palace Project
Service/Break-FixTime LimitYou have 30 Minutesto complete this Assessment.
Scenario
Your office calls you (while in the middle of your Skyway Motors job). They request that
you drop everything and immediately travel to Presidential Sheik Palace. The reportstates that a gentleman was smoking a big cigar in the Lobby Area in Building 1. Anobservant elevator attendant saw a large amount of smoke around the smoke sensor,but was surprised when the Fire Alarm System did not go into Alarm.
Instructions
Restore Instructor provided job file 223U003A (do not download this job to your panel).
Call the instructor to your workstation when you are finished.
IMPORTANT: Double-check your work! You will not be able to make changes toyour job once the instructor grades your work.
Call was received: 8:10AM Thursday
Project number: 012345
Order number: 6151
Job number: 223U003A
Location: AbuDhabi, U.A.E
Customer: State Government
Equipment being installed: None at this time
Customer RequestedSoftware Change(s): None at this time
Customer RequestedHardware Change(s): N t thi ti
7/26/2019 Asessment Book - ME
28/41
4100ES Fire Alarm System Technician Training
Assessment 3-3: Task Checklist
Task Milestone Customer
1. Explain to the customer why
the Fire Alarm System did
not go into alarm
Satisfy the customer with your answerCustomerDo I understandwhy this happened?
2. Complete this Service
Interaction in a TimelyManner
Completed in a timely manner
CustomerWas I satisfied withthe results of thisService Interaction?
When you are finished with this Assessment,return to Assessment 3-2 for completion.
7/26/2019 Asessment Book - ME
29/41
4100ES Fire Alarm System Technician Training
Assessment 4-1:Ruwais Burooj 1
Installation/CommissioningTime Limit
You have 2 Hoursto complete this Assessment.
Scenario
Longtime customer Burooj1 is adding a staff accommodation to their facility. Due totheir location in Ruwais where sandstorms are prevalent, they are specificallyrequesting that Weather Alert audio messages override Fire Alarm Audio.
Instructions
1. Open job file PRAC11Aand save it as 114U001A.
2. Create the appropriate Ladder Logic to meet your customer requirements.
3. Call the instructor to your workstation when you are finished.
4. For this exercise you are mentoring a new technician. Be prepared to explain allaspects of this service call.
IMPORTANT: Double-check your work! You will not be able to make changes toyour job once the instructor grades your work.
7/26/2019 Asessment Book - ME
30/41
4100ES Fire Alarm System Technician Training
Assessment 4-1: Task Checklist
Task Milestone Customer
1. Program Weather Alert to
override a Fire Alarm
Message
Meet customer requirement
CustomerDoes the WeatherAlert Override the
Fire AlarmMessage?
2. Explain programming to a
new Technician that you are
mentoring
Explain Ladder Logic
New TechnicianDo I understandthis ladder logic?
3. Enable the Customer to
achieve occupancy at the
agreed upon time.
The job was completed on time
CustomerWas the job
completed on time?
S S
7/26/2019 Asessment Book - ME
31/41
4100ES Fire Alarm System Technician Training
Assessment 5-1: Jeffery P. Malone Memorial Hospital Installation/Commissioning
Time Limit
You have 1 Hourto complete this Assessment.
ScenarioYou just finished installing a complete Fire Alarm System featuring 4100ES Panels atthe Jeffery P. Malone Memorial Hospital. Your District procedure is for you to generateand print a TrueAlarm Service Report and save it to your Offices drive. Aftergenerating this report, Gordon, one of your districts inspectors, looks over yourshoulder and begins asking questions.
Call the instructor to your workstation when you are finished generating the report.
IMPORTANT: Double-check your work! You will not be able to make changes toyour job once the instructor grades your work.
4100ES Fi Al S t T h i i T i i
7/26/2019 Asessment Book - ME
32/41
4100ES Fire Alarm System Technician Training
Assessment 5-1: Task Checklist
Task Milestone Customer
1. Generate a TrueAlarm
Service Report
Was able to generate an TrueAlarm
Service Report
District OfficeDid the Technicianfollow our setprocedures?
2. Answer Inspector QuestionsAppropriately answered Inspector
questions
Inspector
Do I understandbasic TrueAlarmConcepts afterspeaking with thisTechnician?
3. Enable the Customer to
achieve occupancy at the
agreed upon time.
The job was completed on time
CustomerWas the jobcompleted on time?
4100ES Fire Alarm System Technician Training
7/26/2019 Asessment Book - ME
33/41
4100ES Fire Alarm System Technician Training
Assessment 5-2: Jeffery P. Malone Memorial Hospital
Time Limit
You have 40 Minutesto complete this Assessment.
Scenario
Your task is to program the second floor smoke evacuation equation. This equationshould override the energy management programming and have the second floorpositively pressurized and the first and third floors negatively pressurized when an
alarm is reported from the second floor.
Instructions
1. Open the job file PRAC7Aand save it as 225U002A.
2. Add an 8 point relay card on Bay 2 and label as following
Relay 1 labeled - 1STFLOOR SUPPLY
Relay 2 labeled - 1ST FLOOR EXHAUST Relay 3 labeled - 2ND FLOOR SUPPLY
Relay 4 labeled - 2ND FLOOR EXHAUST
Relay 5 labeled - 3RD FLOOR SUPPLY
Relay 6 labeled - 3RD FLOOR EXHAUST
3. Write the equation necessary to override the energy management programming
(which cycles the supply and exhaust fans ON and OFF every 15 minutes betweenthe hours of 8AM and 5PM at a Priority 9,9) when an alarm is reported from thesecond floor.
Your equation must negatively pressurize the second floor and positively pressurizethe first and third floors when an alarm is reported on the second floor.
4. Call the instructor to your workstation when you are finished.
IMPORTANT: Double-check your work! You will not be able to make changes toyour job once the instructor grades your work.
4100ES Fire Alarm System Technician Training
7/26/2019 Asessment Book - ME
34/41
4100ES Fire Alarm System Technician Training
Assessment 5-2 Task Checklist
Task Milestone Customer
1. Add and Program the Relay
Card into the Programmer
The card was configured into the
Programmer
CustomerIs this informationaccurate and in theproper location?
2. Create the Custom Control
Equation
The equation was created and the
system was validated
CustomerDoes my systemfunction as
planned?
3. Enable the Customer to
achieve occupancy at the
agreed upon time.
The job was completed on time
CustomerWas the jobcompleted on time?
4100ES Fire Alarm System Technician Training
7/26/2019 Asessment Book - ME
35/41
4100ES Fire Alarm System Technician Training
Assessment 6: Michael J. Pinder Regional Airport Service/Break-Fix
Time Limit
You have 30 Minutes complete this Assessment.
Scenario
You and your team member are Break/Fix Technicians assigned to a call at the MichaelJ. Pinder Regional Airport. You had a request to disable a point within Terminal 2. Thecustomer has also requested information on Alarm Verification Tallies. This feature wasconfigured a year ago when the Fire Alarm System was commissioned and the
customer is curious if the feature has been activated.
Instructions
1. Disable the AHU Relay in Terminal 2 (located a mile away from your location in the
Airports main hub).
2. Generate the appropriate report and discuss the results with your customer.
Call the instructor to your workstation when you are finished.IMPORTANT: Double-check your work! You will not be able to make changes to
your job once the instructor grades your work.
4100ES Fire Alarm System Technician Training
7/26/2019 Asessment Book - ME
36/41
4100ES Fire Alarm System Technician Training
Assessment 7-1: Service Gateway
1. How many user accounts can be active at a single time on the Service Gateway?
A. 1
B. 2
C. 3
D. 4
2. True or False A Service Gateway session must always be initiated at the ServiceGateway computer. ___________
3. The Service Gateway Feature is compatible with:A. Only 4100ES Panels
B. Only 4100ES and 4100U Panels
C. Any Simplex Fire Alarm Panel with Command Line Prompt capabilities
D. Only Legacy Panels with Command Line Prompt capabilities
4. This Command initiates a Service Gateway Session from a Remote Device:A. Gatepass
B. Host
C. Terminal
D. Show
5. Describe a customer site where you could use Service Gateway software toincrease your productivity. (If you do not have an applicable current customer site,describe a future opportunity where the software would be useful):
6. Explain a customer site where you either would not or could not use ServiceGateway software. Why?
4100ES Fire Alarm System Technician Training
7/26/2019 Asessment Book - ME
37/41
4100ES Fire Alarm System Technician Training
4100ES Fire Alarm System Technician Training
7/26/2019 Asessment Book - ME
38/41
y g
Tyco Fire Protection Products
Office Park Building #56, Dubai Internet City / Dubai / United Arab Emirates
4100ES Technician Core Competency Score Sheet
Student Name ______________________ District Office ________________________
Instructor: For each Required Core Competency, add you initials to appropriate Assessment Checkbox and initial the Complete box for each when student proves competency
Required Core CompetencyAssessment Locations
1-1 1-2 2-1 2-2 3-1 3-2 3-3 4-1 4-2 5-1 5-2 6-1 6-2 7-1 Complete
1. Perform a CFIG Download
2. Test System Operation AgainstCustomer Specification AfterMaking Program Changes
3. Add and Configure Cards in theProgrammer*
4. Add and Program anIDNet Device*
5. Program Control Points(NACs and Relays)
6. Program Access Levels for4100ES Features
7. Program Passcodes for EndUsers
8. Program System Options
9. Address System Components
10. Import an Audio Chipset
11. Use and Explain the InstallMode Feature to a Contractor
12. Program an AnnunciatorUsing High Level Modes
* Definitions used for the competencies in this course:Configure:Hardware programming (e.g., Class A vs. B NACs on a Power Supply, Adding Mezzanine Cards)Program: Programming device or system functionality (Editing Point Lists, writing SMPL, modifying point and device types
4100ES Fire Alarm System Technician Training
7/26/2019 Asessment Book - ME
39/41
y g
Tyco Fire Protection Products
Office Park Building #56, Dubai Internet City / Dubai / United Arab Emirates
4100ES Technician Core Competency Score Sheet (Continued)Required Core Competency
Assessment Locations
1-1 1-2 2-1 2-2 3-1 3-2 3-3 4-1 4-2 5-1 5-2 6-1 6-2 7-1 Complete
13. Program an AnnunciatorUsing Low Level Modes14. Interpret and Explain SystemOperation to an End User
15. Restore a Job File
16. Troubleshoot aCard Missing/Failed Trouble byRuling Out Five Probable CausesBefore Replacing the Card
17. Troubleshoot ProgrammingIssues Using Features
Built-In to the Programmer
18. Troubleshoot a Field WiringIssue
19. Restore System to a PreviousWorking Version
20. Execute a Programming Planusing a Wizard
21. Create and Explain a DBCompare Report
22. Create and Utilize User PointLists, when Necessary
23. Utilize System Point Lists,when Appropriate
4100ES Fire Alarm System Technician Training
7/26/2019 Asessment Book - ME
40/41
Tyco Fire Protection Products
Office Park Building #56, Dubai Internet City / Dubai / United Arab Emirates
4100ES Technician Core Competency Score Sheet(Continued)
Required Core CompetencyAssessment Locations
1-1 1-2 2-1 2-2 3-1 3-2 3-3 4-1 4-2 5-1 5-2 6-1 6-2 7-1 Complete
24.Create a Ladder LogicDiagram from a Job Specification
25. Explain expected system
operation using a Ladder LogicDiagram
26. Implement Programming Planin Custom Control Editor
27. Generate and Explain aTrueAlarm Service Report to anEnd User
28. Use Control Priorities in
Custom Control Programming30. Use Terminal Modecommands to Verify SystemOperation
31. Explain When and Why theService Gateway would be Used
This student has demonstrated all Core 4100ES Competencies and has achieved 4100ES Certification
________________________________________ __________________________Instructor Signature Date