#BSL2015 @BAMconstruction @ferrovial @kiergroup
BAM Ferrovial Kier (BFK) JVThe challenges and the wins of Information Management on Crossrail at Farringdon Station
1. Introduction to Crossrail Farringdon Station
2. Technology – live!
3. Implementation Process
4. BIM in action – live!
5. Q&A
Agenda
CROSRAIL PROJECT
General Overview
90km’s of
Surface Network Upgraded
21km’s of
Twin-Bore Tunnels
28Surface Station
Upgrades
8Major
Sub-Surface Stations
West Ticket Hall
East Ticket Hall
Platform tunnel Eastbound
Platform tunnel Westbound
Farringdon Overview
Introduction Summary
• Complex project
• Lots of site constraints
• Huge number of interfaces
PROJECT CHALLENGES
BIM SOLUTIONS
• Model for Coordination Interfaces + Stakeholders
• More robust construction planning
• Using it to visually depict status of design
• Collection of Asset Data
• CAD authoring tools and models
• Design schedules
• Work packaging
• Data management and access
• Models compare functionality
• 4D 5D 6D
• Our largest challenges
Technology
Team Structure
BIM Manager
BIM Champions
Tool Box Talks & Workshops
Rest of Work Force
BIM Forum
Parent Company
Commitment
Design Commercial Planning Quality H & S Construction
Number of employees split by their knowledge/usage of BIM
Total employees: 295
BIM Implementation Targets
BIM Capabilities – measured for success:
AwarenessKnowledgeActive Users
5 1015 20 25 25 30 35 40 46 55
70 80
20 25 30 35 40 45 50 6075
90110
130150
20 3050
70 80 90 100
130
160
190
220
250
295
Jun-14 Jul-14 Aug-14 Sep-14 Oct-14 Nov-14 Dec-14 Jan-15 Feb-15 Mar-15 Apr-15 May-15 Jun-15
Objectives:
Number of employees split by their knowledge/usage of BIM
Total employees: 295
AwarenessKnowledgeActive Users
Current AwarenessCurrent KnowledgeCurrent Active Users
5 1015 20 25 25 30 35 40 46 55
7080
20 25 30 35 40 45 5060
7590
110130
150
20 3050
7080
90100
130
160
190
220
250
295
Jun-14 Jul-14 Aug-14 Sep-14 Oct-14 Nov-14 Dec-14 Jan-15 Feb-15 Mar-15 Apr-15 May-15 Jun-15
BIM Status 2015
Current Status:
Current status of the number of employees split by their knowledge/usage of BIM
24%
32%13%
31%
AwarenessKnowledge
Users
Rest of employees
Total employees: 295
TotalAwareness: 204Knowledge: 133User: 39Remaining: 91
BIM Status 2015
69%
45%13%
• Demonstration of real benefits at Farringdon
• 3D Visualisulation
- Inerface with existing works
- BIM in action
• 4D Visulatisulations
- Platform construction
• 6D Asset data
- Examples of asset information from the model
BIM in Action
• Complex project with lots of interfaces
• Embraced BIM, with support of senior management
• 3D, 4D, 5D and 6D BIM implemented
• 69% of staff have reached minimum of “awareness”
category
Summary
• Continued roll out includes:- FieldBIM
- Full 5D roll out
- Greater granularity of 4D by site team
- Involvement of subcontractors
Summary