MODEL DEPICTING DAM RAISE, THRUST BLOCK, ABUTMENTS, DRAINAGE TUNNEL AND PLUNGE POOL.
Dam Site Staging Area with 600 Ton Crane
First Concrete Pour on Right Side of Dam(6 of 79 blocks are now complete)
Left Abutment and Left Side Dam Raise
INTAKESITE PLAN
DRAINAGE TUNNEL
INTAKE STRUCTURE PROFILE
Intake Portal Location
Right Abutment, Right Side Dam Raise and Intake Portal
Intake Portal
Intake Portal (when under construction)
Gate Shaft Top Portal
Bottom of Gate Shaft
POWERHOUSE SITE GENERAL LAYOUT
SURGE CHAMBER PROFILE
Inside the Adit Tunnel
Lower Project Site
New Powerhouse Site
Turbine Pit Wall Pour 1
New Penstock at SCIP
Turbine Generator Parts Stored on Site
Generation Outage
All work in the existing tunnel and new penstock must be completed during the generation outage when the tunnel will be sealed and dewatered.
The generation outage will be scheduled during August and September 2014 so that the new intake may be submerged to allow commissioning of the generation equipment.