8/3/2019 Budget Administration Contractor)
1/38
Integrated Software Solution for model based Design & Construction
Budget Administration (contractor)User Manual
RIB Software AG
8/3/2019 Budget Administration Contractor)
2/38
Copyright
2 Budget Administration (contractor) 10-2010 (c) RIB Software AG
CopyrightThis manual is intended for use as a working document for users of RIB product
families.
The procedures described in this document and the products belonging to them are
the property of RIB Software AG.
We reserve the right to change the information in this document without prior
notice, and the contents pose no obligation to the RIB Software AG. The software
described in this document is provided in conjunction with a licence agreement.
All information is given without warranty. Reproduction or transfer of this document,
or parts of it, is only permitted with the explicit written permission of RIB Software
AG.
With respect to liability for the software described here, please refer to oursoftwarecontract conditions.Copyright RIB Software AG
Published by:RIB Software AGVaihinger Strae 151
70567 Stuttgart-Mhringen
Post office box 80 07 80
70507 Stuttgart
Tel.: +49 711 7873-0
Fax: +49 711 7873-119
E-Mail: [email protected]
Imprint: http://www.rib-software.com/impressum
TrademarkRIB iTWO, ARRIBA (Germany only), RIB|EPC, RIBTEC STRATIS,
DIGIMASS, TRIMAS, PONTI and ZEICON are registered trademarks of
RIB Software AG. Other product names mentioned in this documentation may be
owned by other trademark holders and are used only for information purposes.
This product contains software that was developed by the Apache Software
Foundation (http://www.apache.org/).
8/3/2019 Budget Administration Contractor)
3/38
Table of Contents
(c) RIB Software AG 10-2010 Budget Administration (contractor) 3
Table of ContentsBefore you begin... 5
1 Budget controlling 71.1 Definition of budget 71.2 Budget values from contract/job estimate 71.2.1 Fixed and variable budget values 8
1.2.2 Carriers of budget values 10
1.2.3 Fixed budget 14
1.2.4 Budget for lump sum items 14
1.2.5 Budget in reference items 15
1.2.6 Budget for change order items 15
1.3 Rules for working with budgets 161.3.1 Budgets for various quantity types 21
1.4 Comparisons with the budgets 212 Display budget values in the estimate 222.1 Budget display in 'Margin' 222.2 Budget (property) 222.3 Budget of the estimate details 242.4 Identify budget errors 253 Edit budget (BoQ and estimate) 263.1 Spread budget 26
3.2 Set flag for fixed budget 283.3 Delete flag for fixed budget 304 Edit budget (estimate only) 314.1 Update budget from DJC 314.2 Update budget from original DJC 314.3 Spread item budget over detail lines 324.4 Generate item budget from detail line budgets 324.5 Calculate budget bottom-up 32
8/3/2019 Budget Administration Contractor)
4/38
Table of Contents
4 Budget Administration (contractor) 10-2010 (c) RIB Software AG
4.6 Change budget about % 334.7 Generate item budget from URs 34
5 Additional budget functions 355.1 Rapid budget spread via shortcut + 355.2 Estimate filter for budget 355.3 Budget analysis 355.4 Options for phase transition for AQ quantities and budget 365.5 Automatic data synchronisation via the work item allocation 365.6 Rounding the budget values 36
Index 37
8/3/2019 Budget Administration Contractor)
5/38
Before you begin...
(c) RIB Software AG 10-2010 Budget Administration (contractor) 5
Before you begin...General instructionsBefore you begin, please observe the following notes:
We assume that you are familiar with your computer and its operating system.
The processes described are based on a complete program version with all
licences and administrator rights.
The instructions for the mouse functions are aimed at right-handed individuals.
We recommend our training sessions for effective work. The dates can be
found on our training calendar or on the Internet.
Instructions for using the documents For better clarity, we use various Font mark-ups:
Italicsfor interface elements
Bold lettering to emphasise certain text and input values for keys and key combinations
The following icons are used for navigation within the documents:Icon Meaning
Safety instructionsmust be read. They contain warnings which must not be ignored.
Notescontain important information such as exceptions or special cases.
Working stepsare instructions that should be followed in the given sequence.
Tipsfacilitate your work.
Examplesrelate to work steps or serve to clarify relationships.
Troubleshootingdeals with a problem and its solution.
Target (only in training documents and introductions)defines the next learning targetExercise (only in training documents and introductions)shows a practical example for better understanding.
Conclusion (only in training documents and introductions)provides a short summary of the course content.
8/3/2019 Budget Administration Contractor)
6/38
Before you begin...
6 Budget Administration (contractor) 10-2010 (c) RIB Software AG
Please send any suggestions and wishes regarding our documentation and online
help to the respective hotline.
8/3/2019 Budget Administration Contractor)
7/38
Budget controlling
(c) RIB Software AG 10-2010 Budget Administration (contractor) 7
Budget controllingVarious functions for budget editing, administration, controlling and analysis are
available in the framework of budget controlling (Budget-A licence).
Definition of budgetBudget = means available for covering costs
Budget = originally assumed costs = costs according to contract estimate
It is irrelevant which type of cost determination has resulted in these budget values.
It is up to you as the user to meet the accounting target of keeping the actual costs
within budget.
See also Budget values from contract/job estimate [ 7]
Fixed and variable budget values [ 8]
Fixed budget [ 14]
Budget for lump sum items [ 14]
Budget in reference items [ 15]
Budget for change order items [ 15]
Budget values from contract/job estimateThe definition
Budget = Costs according to contract estimate
results in a problem, because the current estimate status of Project Phase 3 is the
job estimate and not the contract estimate.
The comparison of costs with budgets is a constant task for the contractor in the
project phase of construction execution. However, you are required to update your
assumptions concerning the costs in project phase 3. This is achieved in the job
estimate. The cost statements of the job estimate are therefore no longer identical
to those in the contract estimate. Any comparison of current cost statements with
original assumptions would therefore necessitate a comparison of two estimate
stages, i.e. two project stages.
Such a comparison is only possible under certain conditions, since the structures of
the job estimate may have changed with respect to the contract estimate. From a
conceptual design point of view, this comparison could only be warranted between
1
1.1
1.2
8/3/2019 Budget Administration Contractor)
8/38
Budget controlling
8 Budget Administration (contractor) 10-2010 (c) RIB Software AG
objects of the contractual arrangement (contract items), and only on condition that
all AQ and IQ quantities are updated in the contract estimate as well. However, it is
not realistic to expect the user to manage two project stages in parallel. Moreover,
the contractual arrangement is subject to modifications via the change order items.
The question would then arise if these should also be updated in two project
stages.
The only solution is to have all values within the same project data stock that are
used for a particular comparison. Of course, you as the user always have the
option of editing your change orders in the contract estimate and subsequently
copying them to the job estimate.
The following solutions have been selected for the above-mentioned reasons:
If the project is transferred to phase 3, the DJCs of the contract estimate are
calculated as the budget values per UoM of the item and stored in the separate
fields Budget/UoM.
Budget values for the quantity total of the item and for divisions and the BoQ
are calculated based on these budgets/UoM according to the rules given
below.
For any items that are only introduced in phase 3, you can use a function to
transfer the DJC/UoM into the Budget/UoMfield.
The solution mentioned is also valid for the GC-BoQs.
See also Client perspective [ 8]
Contractor perspective [ 9]
Hierarchically structured objects, e.g. BoQ [ 13]
Objects from combinations of other object types [ 13]
Fixed and variable budget valuesBy definition, budgets are initially fixed quantities that are used for the comparison
with the actual costs that arise later. This does not imply, however, that the budgets
are always immutable fixed values for every project unit or the entire project.
Client perspectiveFor the client, the budget values usually represent fixed quantities, because he
defines budgets as the upper limits for the costs of complete units, i.e.
the project
1.2.1
1.2.1.1
8/3/2019 Budget Administration Contractor)
9/38
Budget controlling
(c) RIB Software AG 10-2010 Budget Administration (contractor) 9
the object element
the work category
the accommodation unit
etc.
He can also define per-unit of measure budgets for smaller units. For the client,
every budget for the quantity total of particular units is therefore a lump sum value.
However, even the client has a need to modify budget values with respect to
original values, e.g. for the following reasons:
Several accommodation units are built, and the buyers desire better finishings
and pay for these modifications. In this way, more funds become available in
certain units in certain work categories.
The construction volume or the quality of execution is modified with acceptance
of all consequences. Partial and total budgets change.
For several work categories or construction ranges, a higher quality of
execution is planned. Reductions are carried out in other ranges. Partial
budgets change, possibly also the total budget.
Budget values can therefore only be fixed values if type and extent of the
performances in the range have conclusively been defined. Therefore, budget
values must initially be modificable at any time. Lower level modifications are
required more frequently. The comparison with original values of upper levels is of
interest.
Significant modifications can be included using internal change orders, with the
effect that original values can be preserved and the effect of the changes is
identified separately. This work method of using purely internal change orders
should also be applied by the client. All change order items can be budget carriers.
Internal change orders that should not become a component of any enquiry obtain
the "Cost Risk" characteristic.
A client is ultimately free in the determination of the budgets. He can calculate
them via guesstimates or estimates. However, he can choose to ignore the
computation results eventually. To arrive at meaningful budget values, he
nevertheless has to fix them after type and extent of the performances have been
determined and manage any later changes separately. Any different method will
result in a loss of cost control. Budgets for each package must be considered the
minimum demand for structuring on the client's side.
8/3/2019 Budget Administration Contractor)
10/38
Budget controlling
10 Budget Administration (contractor) 10-2010 (c) RIB Software AG
Contractor perspectiveFor the contractor, parts of the revenue are budgets for cost coverage. There can
therefore only be budget changes if there are changes in revenue.
If a lump sum contract has been agreed on with the client, your situation is
comparable to that of the client: the budgets are usually fixed values. However,
even for this situation change order agreements with the client that result in
revenue changes can occur. In this case, the budget modifications are clearly
caused by the client's change orders, however.
The budget for a defined performance scope will be a fixed value in the case of
a lump sum contract with the client.
Change order items to the client are causes of budget modifications.
If a unit rate contract with the client has been agreed on, only the budgets per unit
of measure of the work items will be fixed values, while the budgets of the items
and all parent units will be variable in dependance on the billed quantities, since
the revenue will also depend on these quantities. Only items with a lump sum
quantity of 1.000, for which the billed quantities will also remain at 1.000, are
exceptions in this case. Change order items likewise only have a fixed value per
unit of measure.
The budgets per unit of measure of the contract items are fixed values for a
unit rate contract. All other budgets are variable and will depend on the
installed or billed quantities.
Project budgets are moreover influenced by the daywork awarded. The level of this
partial budget only becomes known once the billing total of these performances
has been determined.
Carriers of budget valuesBudget values can exist both for the construction project as a whole and for each
unit of the project.
Out of the existing data classes, the following object types in particular must be
mentioned as budget carriers:
Object elements
Work categories (packages)
Work category groups (parent SPs, e.g. "inhouse work" and "subcontractedservices")
1.2.1.2
1.2.2
8/3/2019 Budget Administration Contractor)
11/38
Budget controlling
(c) RIB Software AG 10-2010 Budget Administration (contractor) 11
Activities and activity groups
Work items (items/divisions/BoQ)
Individual work items (subitems, detail lines = cost codes)
Any combination of the above object types can also be a budget carrier, e.g. "Work
Category 'Heating' in Object Element 2" or "Finishing work in Accommodation Unit
27" or "Sanitary work on 2nd Floor".
Budgets are created either using cost guesstimates or cost estimates. The
originally estimated costs that resulted in a contractor's bid price are the budgets
for cost coverage. These budgets may also have to be modified in accordance with
any changes in revenue during the award procedure, with the effect that the
definition of budgets as being the revenue portions that are available for the
coverage of construction site costs ultimately remain valid.
If you regard BoQ and estimate with their levels of hierarchy as a unit, the budget
carriers are:
BoQ
Divisions
Items
Subitems
Detail lines
Since any detail lines are directly or indirectly filled with cost codes, the following
additional budget carrier exists:
Cost codes
Since a particular cost code can appear in many elements of the BoQ, the cost
code is a budget carrier that does not depend on the hierarchies of BoQ and
estimate, however. The budgets based on these two arrangements are
computationally interconnected via the estimate. It is for this reason that you can
use both the hierarchy elements of BoQ/estimate and the cost codes independent
of these elements as budget carriers within the project. A number of functions are
available to transfer budgets from the budget carriers of one arrangement to those
of the other arrangement and achieve equivalence in the project total.
You must eventually decide only whether the budgets of the BoQ elements are
sufficient for your controlling task or whether you also need to include the cost
codes as budget carriers into the controlling. For the first case, you normally have
to pay little attention to the budgets in those detail lines that are generated by the
program. You may always choose to hide the corresponding columns in the
estimate dialog box. In addition to the "classical" editings of the job estimate, the
8/3/2019 Budget Administration Contractor)
12/38
Budget controlling
12 Budget Administration (contractor) 10-2010 (c) RIB Software AG
second case also requires a sophisticated editing of the budgets in the detail lines
of the job estimate.
The following information from the conceptual design is helpful in deciding on the
work method:
1. A cost code-adjusted estimate of the actual execution types in the job estimate
is a prerequisite for a successful comparison of budgets and costs at cost code
level. For example, you must estimate an execution that was formerly
estimated as inhouse work but which is now awarded to a subcontractor, in the
respective CoC for the subcontracted service as well. This entails that the
decisive parent budget of the item be initially recorded as a revenue portion.
Next, the cost estimate is restructured according to the actual execution, and
only finally is the recorded budget of the item assigned to or spread over the
new detail line(s).
The budget by cost codes is then no longer available under the originally
estimated CoCs, but under the new CoCs according to actual execution type.
In this way, the comparison between budget and costs is performed for the
same type of CoC assignment, which permits a comparison across items.
Budgets under "old" CoCs are transferred to different CoCs.
2. For the monitoring of planned costs in the items in comparison with budgets, a
consideration of the budgets at item level is sufficient. Irrespective of the cost
codes in which the execution takes place, the estimated total costs must be
adhered to. Considering this principle, you will not pay any attention to the
budgets of the detail lines, i.e. by CoC, particularly because during the
restructuring of the job estimate, the original budgets of the detail lines either
disappear with the deletion of lines or cease to be correct upon the assignment
of new cost codes and the possible insertion of new lines. The CoCs are also
not required as budget carriers for the monitoring across BoQ areas (work
categories) or the entire project, which implies that any budget editing/analysis
by estimate detail line is unnecessary.
3. If controlling should be performed in the structure of the individual work
categories, budgets and costs must be planned and recorded in this structure.
This is always required for buildings that are turnkey-ready. The award
controlling and development of the award targets from the budgets must then
also be conducted in this structure. The required ordering of the BoQ/estimate
data by work categories is always achieved via the packages (SPs) and the
work item allocation between PA-BoQ/estimate and SP-BoQs. If you take an
extended perspective of the tasks of the SPs, you can also use them to
structure your inhouse work. The only difference is that it is not awarded to
S/Cs. In such a case, the work category classifications via BoQ and SP
8/3/2019 Budget Administration Contractor)
13/38
Budget controlling
(c) RIB Software AG 10-2010 Budget Administration (contractor) 13
automatically provide the budgets by work category. The cost codes are
therefore not required in addition as budget carriers. Any editing of budgets in
estimate detail lines is then unnecessary.
4. Compared to the situation described in Item 3 above, the somewhat more
complex case of a particular work item that must be spread over more than one
SP can also occur. In this case, the cost estimate will contain more than one
detail. You now must consider the budgets of subitems. However, since every
subitem is assigned to an SP, every partial budget is thus already assigned to
a particular work category, i.e.the CoC is not required as a budget carrier for
the controlling.
5. A switch from one to the other perspective with respect to budget carriers is
always possible. If the budgets of the detail lines and their possible adjustment
to the modifications of the job estimate are ignored in the BoQ/SP-oriented
approach, this work must of course be made up for once the cost codes are
given precedence as budget carriers at a later time. However, auxiliary
functions are available to spread the previous budgets in the structure of the
BoQ consistently to the estimate detail lines, thereby guaranteeing the
equivalence of the results in both structures.
6. If you worked by orienting yourself toward the cost codes as budget carriers
from the start, auxiliary functions will ensure that the budget considerations in
the BoQ structure result in equivalent results. This is necessary for obtaining
correct values in the S/C analysis anyway.
Hierarchically structured objects, e.g. BoQInitially, the principle applies that within a hierarchically structured order, the budget
value of a parent element is the total of the budgets for the subordinate elements.
The value of the parent element is therefore a calculated value.
However, it must also be possible to obtain budget values for a parent level for
which no budget values for the subordinate elements exist. This need exists e.g.
for a contractor in the case of a lump sum contract as long as the item BoQ does
not exist. Any previous values for the total budget must not be automatically
deleted upon the subsequent stepwise addition of the BoQ, which introduces items
that are not yet assigned budget values. This need also arises for the
client/architect if partial and total budgets were determined and the associated
enquiry BoQs are subsequently entered. Normally, no budget values for the items
are then introduced, but the total of the prospective costs from the items according
to the bid is compared to a corresponding partial budget at the parent level instead.
1.2.2.1
8/3/2019 Budget Administration Contractor)
14/38
Budget controlling
14 Budget Administration (contractor) 10-2010 (c) RIB Software AG
Objects from combinations of other object typesThe "classical" combination of object types would be "Activity - Work Item/Split
Quantity". It is used here as an example. The essential feature of such
combinations is the assignment of objects of a different type (work items) to the
leading object type (the activity). Normally, this is not done completely (using the
AQ quantity) but with split quantities. An n:m relationship exists between these
objects.
If budgets exist for these work items, the budget value of the activity is again
calculated as the total of the individual budgets according to the rule of the chapter
above.
The question arises if it should be possible to also record the budget value of the
activity. It must be recordable in any case if the activity stands by itself, i.e. if no
work items are assigned to it. However, it must also be recordable if work items are
assigned to it that have no budget values, e.g. because the BoQ only has budgets
for divisions (work categories). A control by comparing the budgets across all
activities and the budgets across the project BoQ is then only possible via object
areas that are connected by a 1:1 relationship (an activity group describes exactly
one complete BoQ area). As the user, you can e.g. achieve this by defining
activities that describe exactly one package in total, which is in turn described by
the S/C-BoQ. You thus define a parent activity that corresponds to the package.
The budget value of this parent activity corresponds to the total of the budgets of
the S/C-BoQ, i.e. of the package.
If several work items within an activity are budget carriers, and others are no
carriers because only budgets for divisions exist for them, the budget for the
activity cannot be calculated. It must also be recordable in this case. The control of
budgets is thus also only possible between areas that exhibit a 1:1 relationship.
It is left up to the user whether activity budgets should be recordable or not. For
any individual activities, he can decide for himself whether a budget calculated
from the assigned objects or rather a recorded budget value should apply.
Fixed budgetThe budget will be entered as a lump sum budget in the BoQs of the package,
independently of the type of contract (UR contract or lump sum).
A value can only be entered if the fixed budget flag is set.
1.2.2.2
1.2.3
8/3/2019 Budget Administration Contractor)
15/38
Budget controlling
(c) RIB Software AG 10-2010 Budget Administration (contractor) 15
Budget for lump sum itemsFor lump sum items (lump sum marker is set), or indirect lump sum items (a parent
division is a lump sum), only one total budget can be entered. The budget per unit
of measure, related to the AQ quantity, is displayed for your information
(Budget/UoM).
The total budget is calculated via BoQ quantity x budget / UoM and shown again in the budget / UoM
field with reference to the AQ quantities if an item budget is calculated or is entered as a fixed budget
and the item is then made into a lump sum. In the case of lump sum items, the revenue is fixed on the
side of the project alternative, so that only one corresponding budget is available. The costs are fixed
on the side of the packages when a lump sum is formed. Here, the BoQ quantity should be brought
into line with the AQ quantity (adjusted quantity).
Budget in reference itemsIn order to prevent data loss,
1. the total of the budgets from the estimate details is adopted as the budget of
the new (not visible) assembly detail when you create a reference item.
2. the budget of the previous (not visible) assembly detail is spread over the re-
imported estimate details when you liquidate a reference item.
Budget for change order itemsChange order items with a budget which is determined automatically will not be
considered for the following functions:
Update budget from DJC
Update budget from original DJC
Delete flag for fixed budget
Set flag for fixed budget
Generate item budget from detail line budgets
All other change order items are considered.
See also Update budget from DJC [ 31]
Update budget from original DJC [ 31]
Delete flag for fixed budget [ 30]
Set flag for fixed budget [ 28]
1.2.4
1.2.5
1.2.6
8/3/2019 Budget Administration Contractor)
16/38
Budget controlling
16 Budget Administration (contractor) 10-2010 (c) RIB Software AG
Generate item budget from detail line budgets [ 32]
Rules for working with budgetsSeveral rules concerning the behaviour of the dialogs concerning the editing of
budgets are given here:
If a unit rate contract exists, the overall budget of the project is a quantity-
dependent budget. The overall budget as a portion of revenue thus changes in
parallel to the revenue in terms of quantity dependence.
If a lump sum has been formed for a division or the BoQ, this revenue lump
sum also must result in a lump sum for the budget, because the budget is a
particular portion of the lump sum revenue. The budget is then a lump sumbudget. For its value, the program will suggest the budget total of the
subordinated elements based on the BoQ quantities. You can change this
default if desired. Manual modifications of this fixed budgets become necessary
if e.g. the contract lump sum should deviate from the bid total calculated so far.
Fixed budgets (lump sum budgets) can be spread across the subordinated
elements (top-down). You can choose from the following methods for the
spread:
Uniform spread across the number of subordinated items (this method isonly applicable in exceptional cases)
Spread in proportion of the ITs of the items
Spread in proportion to the costs of the items based on AQ quantities
The spread of fixed budgets across their subordinated elements is required in
order to be able to determine any split budgets associated with partially
complete performances via their IQ quantities.
A fixed budget is also recorded for elements at levels below a fixed budget for
which particular fixed budgets should be given in turn. This will exclude these
elements from the automatic spread of the fixed budget given at the parent
level. A budget rest is calculated for subsequent spreading by subtracting the
subordinated fixed budgets. This budget rest is then spread over the remaining
elements without fixed budgets.
By using "subordinated" fixed budgets in the case of lump sum contracts, you
can prevent modifications in the AQ quantities for certain items to result in
budget modifications in all other BoQ items due to the new allocation formula
arising from a quantity change. A "subordinated" fixed budget is set for all
1.3
8/3/2019 Budget Administration Contractor)
17/38
Budget controlling
(c) RIB Software AG 10-2010 Budget Administration (contractor) 17
elements that should not be affected by any quantity modifications in other
areas.
Provided that budgets were generated when moving the project to Phase 3,
either calculated projects or fixed budgets exist, depending on the respectively
selected switch settings.
Calculated budgets are always write-protected and can only be modified using
certain functions.
For the elements of each levels, fixed budgets can (conditionally) be recorded
(BoQ, division, item, subitem, detail line). A particular function is activated for
this purpose which revokes the write-protection of the calculated budget. The
calculated budget is then used as a default value for the fixed budget. If
another value is now recorded, the calculated value can only be reconstructed
conditionally.
A budget value can be reconstructed from the following sources:
from the 'Original DJC' field using a function
from the current DJC using a function
from the redistribution of a parent budget using a function
The calculated budget of a parent element is the budget total of the
subordinated elements for AQ quantities.
The budget values decisive for the forecast for the entire project are always
those based on AQ quantities. Total values are therefore displayed for AQ
quantities. Any values based on BoQ quantities are of purely theoretical
significance.
In the PA-BoQ, a fixed budget for a division or BoQ should only be recorded if
the corresponding element, or a parent element, is included in a lump sum. If
the revenue of a division or BoQ is quantity-dependent, the entire budget,
being a portion of the revenue, must also be quantity-dependent.
For a S/C-BoQ within a package, the input of fixed budgets is generally (i.e.
independent of any lump sum) free, provided the element or a parent element
is not linked to an element of the PA-BoQ via the work item allocation. If such alink exists, no independent budget exists for the S/C-BoQ (see the following
note).
If a fixed budget is set for a parent element, the difference formed with the
budget total for the subordinate elements is identified as Budget Error. The
"higher-level budget" is always decisive for the project. Provided that thebudget is not overdetermined, you can resolve a budget error by spreading the
fixed budget over its subordinated elements.
8/3/2019 Budget Administration Contractor)
18/38
Budget controlling
18 Budget Administration (contractor) 10-2010 (c) RIB Software AG
A budget overdetermination exists if a subordinated fixed budget exists at any
branch for a higher-level fixed budget. In this case a parent fixed budget cannot
be computationally spread, and a budget error remains.
For a lump sum formation, the program suggests the budget based on BoQ
quantities (= revenue basis) as a fixed budget, because the revenue lump sum
also references the BoQ quantity.
If an item is neither directly nor indirectly included in a lump sum, you can only
record a fixed budget per UoM.
In the case of direct or indirect lump sum formation, only a total fixed budget
can be recorded for items. The program proposes the budget that was
calculated based on the BoQ quantity (= revenue basis) as the default fixed
budget. The budget/UoM is then obtained as (total budget)/AQ quantity
If an item is directly included in a lump sum, its total fixed budget corresponds
to the BoQ quantity. The program suggests:
Total fixed budget= (Calculated budget/UoM) x (AQ quantity)
The new budget/UoM resulting from this is
Budget/UoM= (Total fixed budget)/(AQ quantity)
If BoQ and AQ quantities differ, the budget/UoM is therefore modified upon
lump sum formation. If the AQ quantity is modified, the value for Budget/UoMalso changes, because the total fixed budget must remain constant.
As usual, the budget for an IQ quantity of the lump sum item is then given by
Budget for IQ quantity= (Budget/UoM) x (AQ quantity)
If an item is indirectly included in a lump sum (i.e. a lump sum exists for the
division or BoQ), the item's Budget/UoM is obtained via the spread of the
parent fixed budget. This fixed budget is spread in proportion to the costs for
AQ quantities. It is nevertheless possible to assign a total fixed budget to the
item. The rules in accordance with the point above then apply for this recorded
budget.
The item budget is spread over the estimate components in relation to their
costs. If fixed budgets are contained in estimate lines, the above-mentioned
rules concerning the budget spread or the calculation of budget errors also
apply to the relationship between item and estimate lines.
If an item is neither directly nor indirectly included in a lump sum, you can only
record a fixed budget per UoM of the item for the estimate lines.. If an item is
either directly or indirectly included in a lump sum, you can only record total
8/3/2019 Budget Administration Contractor)
19/38
Budget controlling
(c) RIB Software AG 10-2010 Budget Administration (contractor) 19
fixed budgets in the estimate lines. The program then calculates the
Budget/UoM value.
The budgets in detail lines or subitems are only of conditional interest. The
budgets at item level and their assignment to packages are usually sufficient
for the determination of work category budgets.
The item budget is not necessarily calculated from the budgets of the estimate
components, unless the user determines this using an appropriate function.
The reason is that only the item has the valid budget as a share of the revenue.
The estimate cannot automatically create this value anew, because any
estimate modification would otherwise cause a budget modification that is
unaccompanied by any change in revenue.
If objects of a package (SP) are linked to objects of the project alternative (PA)
via the work item allocation, a concomitant dependency exists for the
respective budgets. In such a case, only the budget value under the PA is
significant. That amount is available for the S/C as is budgeted in the PA for the
same work item.
SP Budget= Total budget of the directly linked element of the PA
The budget available for an item of the S/C-BoQ depends on the budget which
is available for the assigned item(s) in the project BoQ. Finally, the following
applies to the billing quantities:
1:1: Budget
Project BoQ item budget for billed quantity= Total S/C-BoQ item budget
n:1: Budget total
Total project BoQ item budget for billed quantity= Total S/C BoQ item
budget
Therefore the billing quantity with the client is always decisive. The proportional
budget amount is available for those costs originating from the S/C -
irrespective of whether they invoice a lower or higher quantity.
An element of the SP-BoQ which is linked to an element of the PA does not
have its own budget, but has a budget dependent on the PA. In this case, the
budget in the SP element is a read-only fixed budget.
If items/subitems of the PA are copied into a BoQ of the SP with a permanent
link to the source element using the Work Item Allocationprogram, then the
total budget of the source element is copied to the element of the SP-BoQ and
is write-protected there. Due to the conditions in the SP-BoQ, the following
applies to the total budget:
Elementnot lump sum:
8/3/2019 Budget Administration Contractor)
20/38
Budget controlling
20 Budget Administration (contractor) 10-2010 (c) RIB Software AG
Total budget= (Budget per UoM) xAQ quantity (PA)
Elementlump sum:Total budget= (Budget per UoM) x BoQ quantity (PA)
If the linked element of the PA is a subitem, then the above formulae apply in
the same way for the budget portion of the subitem, whereby the appropriate
quantity of the subitem is calculated from the quantity of the item and the
internal quantity of the subitem. If the subitem is a "lump sum", then its internal
quantity = (Subitem quantity) / (AQ quantity of item).
For the work item allocation program, there is the option that budgets of directly
linked elements are balanced automatically according to the above rules. We
urge you to activate this option. Should elements be linked at a later date, then
this function carries over the budget of the element in the PA to the element in
the SP. If the option was not activated, then the budget transfer to the SP can
also be carried out using a special function.
For change orders to the client, special conditions for the budget determinationapply. Since the budget is the revenue portion available for cost coverage, and
since the revenue is only determined with a change order's final approval or
rejection, the estimated DJCs cannot be the only standard for the determination of
the budget. If you e.g. expect only 50% of the submitted price to be approved,
which is internally expressed using the corresponding valuation factors for change
orders, the budget must be reduced accordingly. You must monitor the determined
budget to ensure that the following value is not exceeded:
max. Budget =
URx (Valuation factor Cause) x (Valuation factor Amount) x
(100% - Planned margin %)
The program performs the preceding monitoring for the following change order
statuses, provided that a corresponding options switch is set for the respective
status:
submitted
rejected w/ protest
accepted in principle
The program calculates the budget accordingly and write-protects it. If the valuation
factors of the change order are modified, the budget is updated.
If the change order switches to a status that is not among those mentioned above,
the budget will not be calculated according to the above formula but must bedetermined freely depending on the submitted or final fixed price, just as for a
standard item.
8/3/2019 Budget Administration Contractor)
21/38
Budget controlling
(c) RIB Software AG 10-2010 Budget Administration (contractor) 21
For a limit of the budget according to the above formula, any included surcharges
for GC are added to the budget of the change order item. Any change orders for
work items that must be billed therefore indirectly modify the budget available for
GC. If portions of the change order budget should be effectively included in the GC
budget, this must be carried out manually by the user, i.e. you must reduce the
budget of the change order item manually and add the corresponding portion to
one or several items of the GC-BoQ. There is usually no need to carry out such a
redistribution.
Budgets for various quantity typesWork items (items) have budgets per unit of measure We can therefore calculate a
budget on any quantity basis:
BoQ quantity
AQ quantity
IQ quantity
BQ quantity
AQ - IQ quantity (remaining quantity)
The following simple rule applies to the budget calculation:
Budget= (Budget per unit of measure) x (Quantity)
Comparisons with the budgetsThe following comparisons with the budgets are of interest:
Budget - Planned costs
Budget - Actual costs
Budget - Forecast costs
Budget - Award target
For information on this, refer to the "Controlling" documentation.
1.3.1
1.4
8/3/2019 Budget Administration Contractor)
22/38
Display budget values in the estimate
22 Budget Administration (contractor) 10-2010 (c) RIB Software AG
Display budget values in the estimateThe budget values are displayed in the following locations:
in the Margin(estimate document)
in Budget(BoQ, division or item)
in the estimate detail lines
Budget display in 'Margin'In Marginof the Job Estimatedocument, the following amounts are displayed:
Revenue
Costs
Margin
Budget reserve
Budget error (budget without CoC reference)
The budget values are only shown in Phase 3 (execution).
a) Budget error= Total budget(Budget costs) - Budget on CoC details(excluding inhouse work)
The Budget errorvalue is accordingly only of interest if the budget is recorded at the level of the
estimate detail lines.
In the open estimate document, the margin can be displayed using Home| Estimate| Margin.
Budget (property)Budget/UoMValue calculated by the program. This value could have been obtained in one of
the following ways:
Calculated on the basis of the DJCs of the estimate upon transition of the
project into phase 3, if the corresponding option was set. This value
corresponds to the original DJCs, which have been imported into a separate
field. You can display this field in the tabular view of the item edit mode.
By spreading a fixed budget of a parent division or of the BoQ.
2
2.1
2.2
8/3/2019 Budget Administration Contractor)
23/38
Display budget values in the estimate
(c) RIB Software AG 10-2010 Budget Administration (contractor) 23
Via a forecast based on the budgets of detail lines by using the function
Generate Item Budget from Budgets of Detail Lines, which can be accessed via
the menu item Tools | Budgetin the open estimate.
For any unapproved change orders, via a calculation based on a user-defined
formula, provided that the corresponding option is set (see also the "Enquiry"
documentation).
BudgetThis displays the total budget on the basis of the realistic AQ quantity =
(Budget/UoM) x (AQ quantity)
Budget errorDifference between the visible total budget and the total of the budgets from the
detail lines of the estimate. A value is given here only if the item has a fixed budget
and the total of the budgets from the detail lines results in a different value.
Fixed budgetCharacterictic for the item identifying the budget as a fixed budget, i.e. a value that
can no longer be changed by calculation. Setting the flag makes it possible to enter
budget values, i.e. the write-protection for budgets is disabled. Depending on the
property Lump sumorNot lump sum, the following dependency exists:
The item has neither a direct nor an indirect (division or BoQ level) lump sum:Budget/UoMcan be entered. The total budget cannot be entered as it is
quantity-dependent, in parallel with the revenue.
The item has either a direct or an indirect (division or BoQ level) lump sum:
The total budget can be entered. The program then calculates the Budget/UoM
as follows:
Budget/UoM= (Total Budget) / (AQ Quantity)
In accordance with the logic for the revenue, the program suggests the
following value as the total budget when lumps sums are generated:
Suggested Total Budget= (Budget/UoM old) x (BoQ Quantity)
The Fixed Budgetflag is set automatically for lump sum items. Both the calculation
of a suggested total budget as described above and the calculation of a new
Budget/UoM via division by the AQ quantity happen automatically as well. If a fixed
budget is set without generating lump sums (Budget/UoM only), the program will
suggest the previously used value ofBudget/UoMas the fixed budget. The total
budget is the result on the basis of the AQ quantity.
If fixed budgets are set in estimate detail lines, so that the total does not
correspond to the fixed budget of the item, a budget erroris indicated:
8/3/2019 Budget Administration Contractor)
24/38
Display budget values in the estimate
24 Budget Administration (contractor) 10-2010 (c) RIB Software AG
Budget error=
(Total fixed budget of item) (Total of fixed budgets in estimate)
WARNINGBudget errors in items, which can only stem from the estimate, should not be checked in BoQ edit
mode but rather in the estimate itself, as the cause of the error can only be identified in the estimate.
The cause of a budget error can simply be that a fixed budget was set in one line of
the estimate although the redistribution of the remaining item budget to the other
lines had not yet been carried out. Another cause of the error could also be that a
parent fixed budget of a division/of the BoQ had been directly spread over estimate
detail lines (Spread to Estimate Detail Linesswitch activated): In this case, the item
budget (no fixed budget) from the distribution is not recalculated. It must be
updated manually using the function Generate Item Budget from Budgets of Detail
Lines.
The cause of very small budget errors can be that a previously calculated budget
value was entered in one estimate detail line in a supposedly identical way as a
fixed budget with the same value using 2 decimal digits. More than two decimal
digits were, however, reserved internally for the calculated value. The entered
value with only 2 decimal digits therefore causes a slight budget error. Other slight
budget errors are caused by rounding differences if the item budget was spread
over the detail lines using a function.
WARNINGPlease consider the following:
a) A calculated or a fixed budget (per UoM or in total) of an item is automatically spread over the
estimate lines in proportion to costs. If you would like to avoid this, the budget of the detail lines
must have been previously protected against modifications using the function Set Flag for Fixed
Budget(or manually). If, however, a fixed budget is set in a subitem/detail line, the item budget is
not automatically redistributed to the estimate detail lines; this must be done using the function
Spread Budget Over Detail Lines.
b) If direct or indirect lump sums are generated for the item, the rule that the total budget based on
the BoQ quantity will be decisive for is adopted for the estimate detail lines also. This implies that
the previously used Budget/UoM oldand the BoQ quantity are used for calculating the total
budget for each detail line, and then a new Budget/UoMis calculated via division by the AQ
quantity. The conversion is even carried out if the previous Budget/UoM oldwas a fixed budget.
Budget of the estimate detailsThe value Budget/Unitconsiders the cost factor of the cost code.
The item budget is determined automatically from the estimate detail lines,
provided that the item is located below a lump sum (division, BoQ).An automatic update is performed for the following modifications:
2.3
8/3/2019 Budget Administration Contractor)
25/38
Display budget values in the estimate
(c) RIB Software AG 10-2010 Budget Administration (contractor) 25
Modification of the budget of an estimate detail
Deletion of an estimate detail
Disabling of a subitem
Deletion of a fixed budget flag of a subitem
Identify budget errorsBudget errors are identified
for items without estimate details, provided that an estimate exists.
for divisions without subordinated items.
for subitems without subordinated estimate details.
2.4
8/3/2019 Budget Administration Contractor)
26/38
Edit budget (BoQ and estimate)
26 Budget Administration (contractor) 10-2010 (c) RIB Software AG
Edit budget (BoQ and estimate)You can select the following via Enhanced| Tools| Budget(BoQ) orEnhanced|
Specialities| Budget(Estimate):
Spread budget
Set flag for fixed budget
Delete flag for fixed budget
See also Edit budget (estimate only) [ 31]
Additional budget functions [ 35]
Spread budgetOnly active if the selected element contains a fixed budget. It is inactive for items.
Spread budgetBudgetIf item budgets should be spread over the elements of the estimate, select
Enhanced| Specialities| Budget| Spread Item Budget Over Detail Linesin the
opened Estimatedocument.
The Spread Budgetdialog box is displayed by the program.
In the tree, select the BoQ or division over which the budget should be spread.
Spread with deduction of subordinated fixed budgetsThis function refers to the case that divisions with fixed budgets appear in turn
below the element with the fixed budget to be spread. If the function is activated,
both the parent fixed budget and the subordinated fixed budgets are spread over
the respectively eligible elements. Eligible elements are elements without a fixed
budget. If the function is deactivated, subordinated fixed budgets are not spread.
WARNINGThe budget is only spread over elements that do not have a fixed budget.
If there are fixed budgets below the fixed budget to be spread, only the following
partial amount of the parent budget is spread over the elements without fixed
budgets:
(Fixed budget to be spread) =
(Fixed budget) (Subordinated fixed budget total for AQ)
= Remaining fixed budget
3
3.1
8/3/2019 Budget Administration Contractor)
27/38
Edit budget (BoQ and estimate)
(c) RIB Software AG 10-2010 Budget Administration (contractor) 27
This remaining fixed budget is spread over those elements that do not have a fixed
budget.
Spread of BudgetUse the following options to manage the spread:
Uniform portions to all itemsFor e.g. the case of 5 destination elements, each destination element will be
assigned 1/5 of the fixed budget. This option is only selected in special
situations, however: It is designed for e.g. the spreading of the fixed budget of
a building over several identical accommodation units. The destination
elements are the accommodation units in this case.
In proportion to item totals based on AQ quantitiesThe budget is spread over the items in the ratio of their (UR x AQ quantity) to
the total of the ITs at the level of the fixed budget based on AQ quantities. The
following equation applies here:
Budget/UoM=
(Remaining fixed budget) x (URxAQ quantity) / (IT total for AQ quantities)
You will make this selection for the S/C-BoQs, because no estimate available
in this case. Here, the spread is only made over elements that are not linked
with any elements of the PA-BoQ/the estimate.
In proportion to costs based on AQ quantitiesThis selection requires that an estimate is available. It is therefore not an option
for an S/C-BoQ. The program will not permit you to make this selection there.
The budget is spread over the items or the detail lines of the estimate by the
ratio of their DJCs for AQ quantities to the DJC total on the level of the fixed
budget based on AQ quantities.
The following equation applies here:
Budget/UoM=
(Remaining fixed budget) x (DJCxAQ quantity) / (DJC total for AQ quantities)
Spread over estimate detail linesIf this function is activated, a fixed budget derived from BoQ or division level is
only spread over the detail lines of the estimate. Budgets on the item level are
not modified. The values in the elements of the BoQ will only be updated by the
function Generate Item Budget from Budgets of Detail Lines. The following
behaviour is also caused by using the Spread budget in BoQfunction or by
changing a fixed budget:
Functionnot activated
8/3/2019 Budget Administration Contractor)
28/38
Edit budget (BoQ and estimate)
28 Budget Administration (contractor) 10-2010 (c) RIB Software AG
The parent fixed budget of BoQ or division is spread over the items in
accordance with the DJCs. Fixed budgets in detail lines do not affect this
distribution at item level. The calculated item budget is automatically
spread over the detail lines, i.e. the budgets of the estimate are
automatically updated, provided that no overdetermination due to fixed
budgets exists there.
Activated functionThe parent fixed budget of BoQ or division is spread over the detail lines in
accordance with the DJCs of the detail lines. Any fixed budgets in detail
lines remain unchanged. Any budgets on item level are not modified. The
difference between the updated budgets of the detail lines and the
unmodified budget of the item is displayed in the Budget errorfield. If you
as the user would like to adjust the item budgets to the budgets of the
estimate, you will have to use the corresponding function.
The function has no meaning for the executing contractor if there are no fixed budgets for BoQ or
division, i.e. in the case of the unit rate contract with the client. In such a case, item A has no effect on
item B.
WARNINGIn the case of fixed budgets for BoQ or division, the following applies:
a) This checkbox is only activated if budgets are actually to be determined for each individual cost
code and to be pursued consequently in this order. Then, the comparison of budgets and planned
costs on the cost code level has priority over the budget controlling in accordance with the
hierarchies of PA-BoQ and SP, which is always possible, of course. When the fixed budget is
spread, the codes of the estimate lines have priority over the codes of the DJCs of the items. If no
special significance is attached to the budgets in the detail lines because the controlling tasks can
already be fulfilled in the structure of BoQ and SP, this function is not activated.
See also
Spread item budget over detail lines [
32]
Set flag for fixed budgetUsing this function, the flags for fixed budget can be set on certain selected levels
of BoQ and estimate. The Set Fixed Budget at Leveldialog box appears.
The following levels are eligible:
BoQ
BoQ Level 1-5
Item
3.2
8/3/2019 Budget Administration Contractor)
29/38
Edit budget (BoQ and estimate)
(c) RIB Software AG 10-2010 Budget Administration (contractor) 29
not to be billed as a lump sum
directly to be billed as a lump sum
indirectly to be billed as a lump sum
Subitem
Estimate detail line
You can determine the levels at which the fixed budget flag is to be set by
activating the corresponding function.
Depending on the structuring of the BoQ or estimate and the hierarchy level currently selected in the
tree, not all functions may be available to you.
The fixed budget flag is set for all elements of the BoQ or estimate that correspond
to the function activated in this dialog box. Any previous (calculated) budget is
included as a fixed budget value in the process.
The budget can be shown in this way, for example, via a correspondingly defined
table configuration:
Ref. No. ... Fixed budget Budget/UoM Budget Budget error1. ...
5.636.762,20 0,00
1.1. ...X 800.000,00 -1.730,77
1.1.10 ...295.146,80 295.146,80 0,00
1.1.20 ...357.876,43 357.876,43 0,00
1.1.30 ...128.707,54 128.707,54 0,00
1.1.40 ... X 20.000 20.000,00 0,001.2 ...
X 180.000,00 0,00
1.2.10 ...16,63 831,47 0,00
1.2.20 ...26,18 130.000,58 0,00
1.2.30 ...10,73 16.092,98 0,00
1.2.40 ...21,46 32.185,96 0,00
A fixed budget has initially been entered and spread in proportion to the costs
in Sections 1.1 and 1.2.
A fixed budget has then been entered for Item 1.1.40 as well.
In the BoQ, the budget is immediately forecast to the hierarchies, and thedifference is displayed as the budget error. A renewed distribution would cause the
budget error to be spread across Items 1.1.10 to 1.1.30. If, in this case, the budget
8/3/2019 Budget Administration Contractor)
30/38
Edit budget (BoQ and estimate)
30 Budget Administration (contractor) 10-2010 (c) RIB Software AG
was overdetermined due to a fixed budget being set for all items of Section 1.1, the
budget error would be retained after the distribution.
Delete flag for fixed budgetThis deletes the Fixed Budgetflag in accordance with your selection in the
structure within the dialog box.
Element below which fixed budgets should be deletedThe element selected in the tree of the BoQ or the estimate, including its
subelements, is proposed as the range for which the fixed budget flag should be
deleted. However, you can also select a different range here, provided that it
contains any 'Fixed Budget' flags. For the selected element, the fixed budget flagsare deleted in all its subelements.
Entered fixed budgetThe entered fixed budget of the selected element is displayed here for information
purposes.
WARNINGOn the level of contract lump sums, you should not delete the fixed budget.
3.3
8/3/2019 Budget Administration Contractor)
31/38
Edit budget (estimate only)
(c) RIB Software AG 10-2010 Budget Administration (contractor) 31
Edit budget (estimate only)The functions for editing budgets in the BoQdocument are also available in the
estimate document. In addition are available:
Update budget from DJC
Update budget from original DJC
Spread item budget over detail lines
Generate item budget from detail line budgets
Calculate budget bottom-up
Change budget by ...%
Generate item budget from URs
See also Edit budget (BoQ and estimate) [ 26]
Additional budget functions [ 35]
Update budget from DJCThis function requires the existence of an estimate for the concerned elements. Itprompts a recalculation of the current Budget/UoMvalues of the item based on the
DJCs.
For security reasons, the program will query you whether the budget values of all
items should be overwritten by the estimated costs.
The current status of the job estimate is used in this context, which may no longer correspond to the
status of the bid estimate as far as the DJCs are concerned.
Update budget from original DJCThe function prompts a replacement of the current Budget/UoMvalues of the items
by the values from the field Original DJC. The values in the Original DJCfield could
have been obtained as follows:
By moving the project into phase 3.
In this case, the values will correspond to the DJCs of the bid/contract
estimate.
Via input in the tabular view of the BoQ edit mode.
4
4.1
4.2
8/3/2019 Budget Administration Contractor)
32/38
Edit budget (estimate only)
32 Budget Administration (contractor) 10-2010 (c) RIB Software AG
For security reasons, the program will query you whether the budget values of all
items should be overwritten by the estimated costs.
Spread item budget over detail linesUse this function to spread item budget over detail lines.
It is irrelevant in this context whether the item budget is a fixed budget or not.
A confirmation query concerning the spread of the budget values appears.
If you have selected a division, a BoQ or the entire estimate, the function applies to
all respectively subordinated items. In this area, the budget of every single item isspread over the associated detail lines, provided they are not protected frommodification by the use of fixed budgets.
Please note the following information:
a) Spread Budgetin conjunction with the activated function Spread Over Estimate Detail Lineshas a
different effect:
In this case, not the individual item budgets are spread but rather the higher-level fixed
budget in proportion of the costs of all detail lines of all items that are not protected by the
use of fixed budgets. The existing item budget is not spread and also not modified.
b) It is possible that no "free space" is available for spreading a budget/fixed budget over lower
levels, i.e. each structure branch below the fixed budget is completely assigned with fixed
budgets at some point (i.e. the budgets are overdetermined). This is the case if either each
subitem, or detail line, contains a fixed budget, or if subitems with fixed budgets are always
located between each detail line and the item. In this case, the program does not do anything,
(but) any possibly existing budget error persists. Any spread then only becomes possible once
the path from the fixed budget to at least one detail line is "cleared" of other fixed budgets.
Generate item budget from detail line budgetsYou can use this function to form the total of the detail line budgets and include it
into the item as its budget.
It is irrelevant in this context whether the item budget is a fixed budget or not. If you have selected a
division or a BoQ or the whole estimate, the function applies to all subordinated items.
For security reasons, a confirmation request is displayed beforehand.
Any budget error that may have arisen at item level is resolved.
4.3
4.4
8/3/2019 Budget Administration Contractor)
33/38
Edit budget (estimate only)
(c) RIB Software AG 10-2010 Budget Administration (contractor) 33
Calculate budget bottom-upThis function determines all item budgets anew from the estimate details. At thesame time, all fixed budgets within the selected branch are recalculated from the
subordinated budgets. This applies to subitems, divisions and to the BoQ.
For security reasons, a confirmation request is displayed beforehand.
This function overwrites fixed budgets without a corresponding query.
Change budget about %Use this function to increase or reduce budget values by a particular percentage
which exist in the detail lines of the estimate within a selectable BoQ area and/or a
selectable cost code.
The % - Modification of the Cost Codes of the Budgetdialog box appears.
Structure/areaIn the structure of the estimate, select the BoQ area in which the modification
should be performed.
Select the first element and click FrominArea.Next, select the last element and click ToinArea.
The selected area is displayed.
Cost CodeIf you would like to modify the budgets of a particular cost code only, select the
cost code here. You may also specify whether the budgets of the subordinated
CoCs should also be modified. If you specify a CoC, only budgets in detail lines
containing this CoC are modified. Any other budgets of the determined BoQ area
remain unchanged.
If the cursor is positioned in this field, you can search for a particular cost code.
Including subordinated cost codesIf this function is activated, subordinated cost codes are considered as well.
% changeThe following options are available within this group:
Current amountDisplay of the current budget amount.
If no value is displayed here, clickAnalyse.
Change by %
4.5
4.6
8/3/2019 Budget Administration Contractor)
34/38
Edit budget (estimate only)
34 Budget Administration (contractor) 10-2010 (c) RIB Software AG
Enter a percentage here by which you would like to change the budgets.
If you would like to reduce the budgets, you must enter a number with negative
sign here.
Changed amountThe modified amount is displayed here once you quit the Change by %field
using the key.
AnalyseClick here to determine the budget amount for the selected area.
Click OKif you would like to carry out the modification.
Please observe the following notes:
a) The budget modification is only performed for the estimate detail lines, provided that no fixed
budget is set there.
b) The budget is not modified for higher-level subitems with fixed budget and at item level. At these
levels, any modification will result in a budget error.
c) Once again, the principle applies that no automatic budget modification based on changes in the
estimate is ever carried out at item level. Any adjustment of the budget at item level is therefore
only prompted by the function Generate Item Budget from Detail Lines.
Generate item budget from URsThe Budget from URsdialog box appears and allows you to enter surcharges or
discounts to the UR or UR breakdowns.
Here, you should activate UR breakdownsif, for items with the UR Breakdownflag,
the budget is to be determined via UR breakdowns.
Enter a surcharge valueordiscount valuein % forURand possibly forUR
breakdowns, since not all items are required to have the UR Breakdownflag.
The budgets are now determined from the estimated URs or UR breakdowns for allitems below the element selected in the structure.
If the element selected in the tree is the Estimate, the budget can only be determined via the UR
breakdowns if all of the BoQs have the same UR breakdown.
4.7
8/3/2019 Budget Administration Contractor)
35/38
Additional budget functions
(c) RIB Software AG 10-2010 Budget Administration (contractor) 35
Additional budget functionsYou will find an overview over additional budget functions below:
Rapid budget spread via shortcut +
Change fixed budget
Estimate filter for budget
Budget analysis
Options for phase transition for AQ quantities and budget
Automatic data synchronisation via the work item allocation
Generate budget BoQ
Budget and award target in the evaluation
Rounding the budget values
See also Edit budget (BoQ and estimate) [ 26]
Edit budget (estimate only) [ 31]
Rapid budget spread via shortcut +At item level, this shortcut is available for the function Spread Budget Over Detail
Lines.
The function Spread Budget in BoQis executed at BoQ and division levels.
If the function Spread Budget over Estimate Detailsis to be accessed from a
parent level, you must continue to use the shortcut ++.
Estimate filter for budgetAll budget fields are available in the filter.
Budget analysisIn the execution phase, two budget evaluations are available in Estimate- Total
Job Costs:
Budget analysis according to job estimate
Budget analysis according to cost codes
5
5.1
5.2
5.3
8/3/2019 Budget Administration Contractor)
36/38
Additional budget functions
36 Budget Administration (contractor) 10-2010 (c) RIB Software AG
By switching the option With Details(in Group Item Reportsin Report Configuration) in the Print
Options, you can also print the budget evaluation forsubitemsand detail lines.
For further information on this topic, consult the "Bid Estimate" and "Controlling"
documentations.
Additional budget evaluations via reports are available
in the BoQ
in the packages
Options for phase transition for AQ quantities andbudgetIn the System Options (Project / Project Alternative- Phase Change Project), you
can useAQ quantitiesto set defaults for the behaviour of the AQ quantity during
phase transitions. You can also enter a setting which allows this information to be
individually customised in the project.
Calculations for the budget estimate can be defined in Budgets and Original DJC.
Please refer to the "System and User Options" documentation for more details.
Automatic data synchronisation via the work itemallocationIn the framework of the work item allocation, you have the option of configuring an
automatic budget synchronisation (PA -> SP).
The optionAutomatic Budget Synchronisation (PA -> SP)is relevant in the case of
budgets which are managed within the project alternative either in a budget BoQ or
in a bid BoQ with an estimate, as it can be used to transfer the budget online to the
associated BoQ of the packages.
Rounding the budget valuesThe budget is not rounded in the BoQ. The budget is used with absolute precision
in the same way as the DJCs, since the budget is derived from the costs here.
5.4
5.5
5.6
8/3/2019 Budget Administration Contractor)
37/38
Index
(c) RIB Software AG 10-2010 Budget Administration (contractor) 37
Index
8/3/2019 Budget Administration Contractor)
38/38
Index
BBudget, 7
Additional Functions, 35
Analysis, 35
Automatic Data Synchronization via work item
allocation, 36
Calculate bottom-up, 33
Change about %, 33
Change order items, 7, 10, 15
Client perspective, 8
Comparisons, 21
contract/job estimate, 7
Contractor perspective, 10
Display (Margin), 22
Editing (BoQ and Estimate), 26
Editing (Estimate only), 31
Editing rules, 16
Estimate filter, 35
Fixed, 8
Identify error, 25
Lump sum contract, 10
Lump sum items, 15
Options Phase Change, 36
Rapid spread, 35
Reference items, 15
Rounding, 36
Unit rate contract, 10
Update from DJC, 31
Update from original DJC, 31
Variable, 8
Budget controlling, 7Budget for lump sum items, 15CChange order items
Budget, 15
DDelete
Flag for Fixed Budget, 30
DisplayBudget (Margin), 22F
Fixed budget, 14Flag for Fixed Budget
Delete, 30
Set, 28
IIdentify
Budget error, 25
Item BudgetGenerate from detail line budgets, 32
Generate from URs, 34
Spread over detail lines, 32
RReference items
Budget, 15
SSet
Flag for Fixed Budget, 28
Spread, 26B d t 26