EGLINTON CROSSTOWN LRTChaplin Avenue Construction Liaison Committee March 28, 2017
2
Agenda
• Avenue Station Update• Chaplin Station Update
3
Avenue Station Updates
March/April 2017• Piling is complete at the main and secondary entrance• Monitoring instrument installations from Lascelles Blvd to Braemar Ave
ongoing; over 70 instruments being installed• Excavation will begin at each entrance – starting at Secondary Entrance
– Excavation is completed one level at a time with tie backs and supports installed before moving to next level
– Truck traffic to the site will be approximately 5 trucks per hour per site
2017• Excavation works will continue at Secondary entrance until late
summer, followed by tunneling works• Excavation works will continue at Main entrance until late 2017,
following by tunneling works
4
Construction Staging Update
• Removal of pedestrian detour at secondary entrance under review.
5
Avenue Station Aerial Rendering
6
Construction Progress Picture
7
Construction Progress Picture
8
Construction Progress Picture
9
Construction Progress Picture
10
Construction Progress Picture
Chaplin Station Construction Update
Spring 2017• Continue piling at the Tertiary Entrance• Continue piling at the south side of the station box• Subsurface Utility Engineering (SUE) investigation for
wet utilities relocation• Secondary Entrance site setup• Commence wet utilities relocation
Chaplin Station: Current Construction Stage 1
Began February 28 for approximately five (5) months
TTC Changes
Chaplin Station Concept: Aerial View
Main Entrance
Secondary Entrance
*60% rendering
Tertiary Entrance
Chaplin Station Construction Progress
15
Demolition of 321 Chaplin Cres
Chaplin Station Construction Progress
16
Demolition of 641 Eglinton
Ave W
Chaplin Station Construction Progress
17
Piling at the Main Entrance
site
Chaplin Station Construction Progress
18