1
Company / Owner
Marine Contractor
Main Contractors - JV
OUTLINE:
.1Introduction
.2Resources
.3Progress Percentage
◦Construction Status
.4Financial Summary
.5Variation Orders
2
The project consists mainly of the detailed design and construction of LPG Jetty which includes:
•Access Trestle & Loading Platform
•2 No. Berthing Dolphins & 4 No. Mooring Dolphins & Catwalks
•Marine Loading Arms (x2)
•LPG and vapour return lines & Cathodic Protection System
•Fire fighting system & Electrical power supply and lighting
•Contractual project dates:24-Feb-14 24-Oct-14
•Computed Completion Date :21-feb-15
3
4
Manpower 1-Nov-2014 1-Jan-2015
Staff 51 54
Direct Labor 41 64
Equipment Quantity Rented/ Owned
Barge 1 Owned
Flexi float barge 1 Owned
Tug Boat 1 1 Owned
Tug Boat 2 1 Rented
Speed Boat 1 Rented
Vibro Hammer 1 Owned
Diesel Hammer 1 Owned
Crawler Crane 1 Owned
Mobile Crane 3 Rented
Air-Compressor 4 Owned
Welding Machine 20 Owned
Truck Mounted Crane
1 Owned
5
Status Expected Completion Date
Trestle 100% Complete
Platform 100% Complete
Loading Arm 100% Complete
Pile Static Load Test 100% Complete
Pipe Line 80% 31-Jan-15
Mooring Dolphins 80% 25-Jan-15
Berthing Dolphins 75% 31-Jan-15
Catwalks 75% 5-Feb-15
Abutement & Access 50% 28-Jan-15
Electrical 30% 10-Feb-15
Marine Furniture (QRH,BAS,Fenders,..) 20% 12-Feb-15
Commissioning 4-Feb to 18-Feb-15
Construction
6
Front View
10” FF Pipe4” Vapour Pipe6” LPG Pipe
2.5” Water Pipe
U-Channel Pipe Support
Concrete Pipe Support
Pipe 13-Jan-15
FireFighting 80%
Vapour 80%
LPG 80%
Water 80%
7
Invoice No.
Description
Initial Amount (JOD)
Agreed Amount (JOD)
Issue Date Due DateSettlement Date
Overdue Period (days)
Status
001
Advance payment
10%1,723,255.00 1,723,255.00 5-Feb-14 6-Mar-14 8-Jun-14 94 Closed
002 IPC-1 2,356,981.61 1,926,073.33 7-May-14 2-Jul-14 19-Aug-14 48 Closed
003 IPC-2 1,092,297.77 969,456.65 7-Jun-14 2-Aug-14 1-Sep-14 30 Closed
004 IPC-3 1,507,114.54 1,245,493.82 12-Jul-14 6-Sep-14 1-Oct-14 25 Closed
005 IPC-4 1,174,215.32 1,583,941.28 11-Aug-14 6-Oct-14 10-Nov-14 35 Closed
006 IPC-5 1,617,218.84 1,006,200.22 8-Sep-14 3-Nov-14 12-Nov-14 9 Closed
007 IPC-6 2,638,679.75 1,919,859.74 7-Oct-14 2-Dec-14 12-Nov-14 Closed
008 IPC-7 1,571,120.29 1,005,264.70 29-Oct-14 24-Dec-14 30-Nov-14 Closed
009IPC-8
1,864,144.68 993,963.07 2-Dec-14 27-Jan-15 Not Yet Open
010IPC-9
1,366,814.24 1,212,026.19 2-Jan-15 27-Feb-15 Not YetOpen
Issued 14-Jan-2015
.1Steel Water Tank to feed the fire fighting system•Issued on Nov. 17th 2014 (202,425.00) JD, Progress : 30%
.2Firefighting Pumps Room•Issued on 17th 2014 (40,700.0) JD, Progress : 95%
.3LPG and Vapour Return Tie-In to Existing Networks•Issued on 17th 2014 (64,509.61) JD, Progress : 100%
.4Design, Supply and Installation of Main Power cable•Issued on Dec. 24th (18,246.99) JD, Progress : 80%
.5Design, Supply and Installation of a Standby Power Generator•Issued on Dec. 24th (18,198.69) JD, Progress : 80%
8
9
General Layout
General Layout
Trestle Modules
Pipe Lines on Trestle
Mooring Dolphins
13
Firefighting Tank + Pump Room
14
Static Load Test
15
Loading Arm PrecommissioningLoading Arm Construction
16
Firefighting Monitor Towers
17
Abutment
18
Tie in at Loading Arm
19
Tie in Point
20
Cable Trays onshore + Trestle
Q & A21