- Inquired requests for information as discrepancies with blue prints occurred.
- Estimated man hours on change and proposal orders.
- Documented daily work logs, performance and duties performed.
- Attended and documented daily/weekly safety meetings with general contractors and construction managers.
- Resolved conflicts on a regular basis by coordinating with foreman, inspectors, trades, contractors and safety officials.
- Started the day by determining what tasks are priority, then proceeded to assign the team their daily and/or weekly tasks.
- Created schedules and determined sequencing.
- Controlled inventory, the staging of material and just-in-time deliveries.
- Supervised the quality of work done by employees and subcontractors in all areas of the project.
- Enforced safety standards, including a clean job site and proper use of tools.
- Collaborated with individual trade contractors to ensure strict time lines are met.
- Reviewed blueprints and submittals on a regular basis before and during installation to ensure accuracy.
- Prepared reports of the overall progress of the project.
DUSTIN THOMAS 6408 Meadowbrook Avenue, Cleveland, Ohio | 216-410-0805 | [email protected]
SOUTH EUCLID LIBRARY
South Euclid, Ohio
A new construction assignment with the majority of the mechanical equipment installed underneath a two foot raised floor.
WILLOUGHBY SOUTH
HIGH SCHOOL Willoughby, Ohio
16 million dollar renovation consisting of over 40 rooftop units.
LUBRIZOL CORPORATION
Wickliff, Ohio
Temporary shut down job, consisting of up to 8’x8’ exhaust duct demolition and to reinstall the exhaust system.
MEDICAL MARTCleveland, Ohio
425 million dollar new construction plan. Ittook approximately two years to complete the750,000 square-foot facility.
PROGRESSIVE FIELD
Cleveland, Ohio
This endeavor was a seven month, off season renovation with a strict opening day deadline.