+ All Categories
Transcript
Page 1: ERP 101 Series: Engineering Revisions and Engineering Change Order (ECO)

ERP 101Engineering Revisions and Engineering Change Orders (ECO)David BushSenior Manufacturing Consultant,Rootstock

Page 2: ERP 101 Series: Engineering Revisions and Engineering Change Order (ECO)

The ERP 101 Webinar SeriesDate Topic

Aug 2, 2016 An Introduction to ERP for Manufacturing

Aug 16, 2016 Engineering – Learn how to create Part Master Records and Bills of Material

Aug 30, 2016 Engineering – Learn how Change Orders and/or Revisions ensures that ERP system data is accurate and up-to-date

Oct 11, 2016 Shop Floor – Explore how ERP is used to create and maintain Work Centers, Routings and Procedures

TBA Shop Floor – See how scheduling the Shop Floor through ERP controls Labor and Machines

TBA Procurement – Link your Vendors and Purchased Parts via ERP

TBA MRP – Step though an overview of this vital ERP subset

TBA Sales – See how you can link your Customers and Products via ERP

TBA Manufacturing Accounting – An overview using standard cost

TBA Manufacturing Accounting – An overview using weighted cost

Page 3: ERP 101 Series: Engineering Revisions and Engineering Change Order (ECO)

Meet Our Speakers

David BushSenior Manufacturing Consultant, Rootstock• 30+ years of manufacturing and MRP/ERP

systems experience• Previously at General Microcircuits,

Consona Corporation, Relevant Business Systems, Inc

Page 4: ERP 101 Series: Engineering Revisions and Engineering Change Order (ECO)

A Recap• In the last episode, we discussed:

– Part Numbers• Format• Description• UOM• Source• Type• Using Parts to Create Bills of Material

Page 5: ERP 101 Series: Engineering Revisions and Engineering Change Order (ECO)

A Recap• Bills of Material (BOM)

– Multiple Levels– Components, Sub Assemblies, Reference Items, Tools and Fixtures– Scrap factors and Set-up Quantities

All of this is used by MRP to calculate material needs

Page 6: ERP 101 Series: Engineering Revisions and Engineering Change Order (ECO)

In This Episode• What additional considerations could affect material planning?

– We have our part numbers, and we’ve put them together in a bom.• We’ve identified the quantity required to build the next higher assembly.• We’ve adjusted that quantity by various factors.

– What happens when change occurs?• New styles offered• Safety features added• Parts no longer available

How do we control changes that affect MRP?

Page 7: ERP 101 Series: Engineering Revisions and Engineering Change Order (ECO)

Handling Change that Affects MRP• Revisions• Engineering Change Orders

Page 8: ERP 101 Series: Engineering Revisions and Engineering Change Order (ECO)

What Is an Engineering Revision?

• An alpha-numeric code that identifies a specific change or adjustment to a part. F/E, Rev 0, Rev A, Rev A1, etc.

• A documented change to a part, subassembly or final assembly– May be minor or significant but does not affect form, fit or function (revised parts are

interchangeable)– May be prompted by sales, engineering design or availability from vendor.– Formal method required by company to control the change and it’s possible effects

Page 9: ERP 101 Series: Engineering Revisions and Engineering Change Order (ECO)

What Does an Engineering Revision Control?• Revisions typically include Pending, Released and Implemented statuses.• How is each Revision used? • Department sign-offs typically done outside of the system under Revision

control.

• System only recognizes Implemented Status, so – Why use Pending and Released status at all?– What benefits come from controlling these statuses?– Revision Status tells MRP what to plan.– Revisions may happen at any level of a bom from purchased parts to finished

goods.

Page 10: ERP 101 Series: Engineering Revisions and Engineering Change Order (ECO)

What Does an Engineering Revision Control?• What if the revision is to add and/or delete parts, rather than change

existing parts. How is that handled?• Part no longer available for purchase, replaced with new part.• New options added and others deleted.

– Revision still required, but now the date feature of Revisions comes into play. Add Revision Date and Delete Revision Date.

Example: Part A is being replaced by Part B. A revision is needed for both parts.. Part A will have a ‘Delete’ Revision and part B will have an ‘Add’ Revision, both with same date. Let’s look at our bicycle for an example of how and why this might be done.

Page 11: ERP 101 Series: Engineering Revisions and Engineering Change Order (ECO)

Lets Look At An Example• Braking system redesigned due to

problem with brake pads.• New fiber pads will replace the old

rubber pads on this purchased assembly.

How would Revision control be used, and what issues would need to be handled?

Page 12: ERP 101 Series: Engineering Revisions and Engineering Change Order (ECO)

Changes to Purchased Sub-Assembly

• 1. Is new part number required or can it be handled via Revision Control?

• 2. Create Revision at the purchased part (brake assembly) level.

• 3. Determine how change will affect existing stock and purchase orders. Will they:– A. Be used up and then switch to new assy?– B. Be scrapped?– C. Be reworked by you or the vendor?

Page 13: ERP 101 Series: Engineering Revisions and Engineering Change Order (ECO)

An Important Consideration• Revision Control does not control physical inventory.. that is

done at the part number level, not part number/revision.• So, it is possible to have different revisions in inventory of the

same item.• This must be handled by material control. • The ERP system MAY track revisions in inventory, but we’ll

discuss that option during the webinar on physical inventory.

Page 14: ERP 101 Series: Engineering Revisions and Engineering Change Order (ECO)

What if MORE Control is Required?• What if informal sign-offs won’t cut it? Now we move to

Engineering Change Orders (ECO).– ECO’s work in conjunction with Revision Control to provide a more

formal system to handle change.– Main difference between ECO and Revisions is a formal sign-off by

various departments BEFORE the change can be implemented. • A. - Pending, Released and Implemented Status remain, but at ECO level

instead of Revision.• B. - Individuals are typically given the ability within the ERP system to create

and maintain ECO’s.• C. Sign-offs are required (again, within the system by those given that ability)

by Engineering, Material Control, Purchasing and possibly other departments.

Page 15: ERP 101 Series: Engineering Revisions and Engineering Change Order (ECO)

In Review• Change is INEVITABLE and the ERP system is designed to

handle it via Revisions and ECOs.• Revision Control is a less formal method, but still requires

status changes and implementation/deletion dates.• ECO’s incorporate all of the features of Revision Control, but

add a more formal system of sign-offs within the ERP system. ECO’s become the controlling mechanism.

Page 16: ERP 101 Series: Engineering Revisions and Engineering Change Order (ECO)

Where Do We Go From Here?• Shop Floor Control

– Work Centers– Processes– Operations– Sub-contract Operations– Setup and Run Considerations– Scheduling Labor and/or Machines

Page 18: ERP 101 Series: Engineering Revisions and Engineering Change Order (ECO)

The ERP 101 Webinar SeriesDate Topic

Aug 2, 2016 An Introduction to ERP for Manufacturing

Aug 16, 2016 Engineering – Learn how to create Part Master Records and Bills of Material

Aug 30, 2016 Engineering – Learn how Change Orders and/or Revisions ensures that ERP system data is accurate and up-to-date

Oct 11, 2016 Shop Floor – Explore how ERP is used to create and maintain Work Centers, Routings and Procedures

TBA Shop Floor – See how scheduling the Shop Floor through ERP controls Labor and Machines

TBA Procurement – Link your Vendors and Purchased Parts via ERP

TBA MRP – Step though an overview of this vital ERP subset

TBA Sales – See how you can link your Customers and Products via ERP

TBA Manufacturing Accounting – An overview using standard cost

TBA Manufacturing Accounting – An overview using weighted cost

Sign Up Now


Top Related