Building Committee Timeline
1st Committee Meeting – October 30,2013 Architect Selected and Contracted for Concept
Design – December 2013 Existing Facility Redrawn in Digital Format –
January 2014 Wish List Floor Plan and Elevations Prepared to
Meet Needs Established by the Planning and Visioning Committee – January 27, 2014
‘Wish List Floor Plan’Included the following: Gymnasium (High School Dimensions) First Floor Meeting Rooms Mezzanine with 4 or 5 meeting rooms Elevator to serve existing second floor and
Mezzanine Expanded Kitchen Locker Rooms Storage Rooms Garage
Building Committee Timeline
Presented Plans in Open Houses – February 2014 Celebration Dinner – February 9, 2014 Budget Established – February / March 2014 PPC Directs Building Committee to Determine a
Concept Plan that Meets the Established Budget of $1.24M
Essential Goals
Stay within modified budget of $1.3M – Including Permit and Design Fees, Soft Costs Not Included
Meet the needs of the Youth Program Provide One Large Meeting Area (Similar to
Location of the Celebration Dinner)
Family Life Center
Next Steps Congregation Vote to Proceed with Detailed
Design of Concept Plan – Nov 23, 2014 Begin Design / Permitting – Dec 2014 Obtain Bids for Project – Spring 2015 Present Proposed Project Costs to
Congregation – Summer 2015 Obtain Approval of PPC to Award Contracts Begin Construction – Fall 2015?