FINAL PUBLIC MEETINGOCTOBER 25, 2016
www.denvergov.org/federalcorridor
¿Necesita un traductor? Por favor, levanten la mano.
9 MILES, ENTIRE CITY LIMITS
2015 TO LATE 2016 STUDY COMPLETION
STUDY OVERVIEW
www.denvergov.org/federalcorridor
WALKING, TRANSIT, BIKING AND DRIVINGEVALUATION OF BUSINESS AND ENVIRONMENTAL CONCERNS
STUDY GOAL: PRIORITIZE OPPORTUNITIES AND DEVELOP IMPLEMENTATION PLAN
FOCUS
www.denvergov.org/federalcorridor
CRITICAL NORTH-SOUTH LINK ALONG WEST SIDE OF DOWNTOWN
SOME OF THE MOST DIVERSE NEIGHBORHOODS IN THE CITY
30,000 TO 40,000 VEHICLES PER DAY
INTERSECTIONS WITH HIGHEST ACCIDENT RATES IN THE CITY
2ND BUSIEST RTD TRANSIT CORRIDOR
ABOUT
www.denvergov.org/federalcorridor
1. ANALYZE EXISTING CONDITIONS
2. GATHER INPUT AND FEEDBACK
3. PRIORITIZE PROJECTS AND OPPORTUNITIES
4. DEVELOP IMPLEMENTATION STRATEGIES
5. GATHER ADDITIONAL INPUT AND FEEDBACK
PROCESS
www.denvergov.org/federalcorridor
FEDERAL BOULEVARD
STUDY
PROJECT MANAGEMENT TEAM
STAKEHOLDER
TASK FORCEGENERAL PUBLIC
APPROACH
www.denvergov.org/federalcorridor
STUDY TIMELINE
EXISTING CONDITIONS
CORRIDOR PLAN(OPPORTUNITIES AND
IMPLEMENTATION)
www.denvergov.org/federalcorridor
PUBLIC INVOLVEMENT
www.denvergov.org/federalcorridor
PUBLIC INVOLVEMENT
www.denvergov.org/federalcorridor
PUBLIC INVOLVEMENT
www.denvergov.org/federalcorridor
PUBLIC INVOLVEMENT
www.denvergov.org/federalcorridor
CRITICAL SUCCESS FACTORS
www.denvergov.org/federalcorridor
CRITICAL SUCCESS FACTORS
www.denvergov.org/federalcorridor
VISION STATEMENT
“Federal Boulevard will be a well-connected multimodal and high capacity boulevard that supports and celebrates diverse local business, residents, cultures, natural resources and community.
Traveling the Corridor will be safe, easy, and comfortable for all modes of transportation.”
www.denvergov.org/federalcorridor
FRAMEWORK ELEMENTS
www.denvergov.org/federalcorridor
TYPICAL CROSS-SECTION
www.denvergov.org/federalcorridor
PRIMARY INTERSECTION
www.denvergov.org/federalcorridor
SECONDARY INTERSECTION
www.denvergov.org/federalcorridor
MIDBLOCK CROSSING
www.denvergov.org/federalcorridor
TRANSIT STOP AND STATION ELEMENTS
www.denvergov.org/federalcorridor
PROJECTS AND PROCESS
www.denvergov.org/federalcorridor
PROJECTS
75 MAJOR RECOMMENDATIONS26 QUICK WIN PROJECTS33 NEAR-TERM PROJECTS16 LONG-TERM PROJECTS
www.denvergov.org/federalcorridor
PROJECTS
QUICK WINS: 1-2 YEARS NEAR-TERM: 2-10 YEARSLONG-TERM: 10-20 YEARS
www.denvergov.org/federalcorridor
PROCESS
www.denvergov.org/federalcorridor
PROCESS
75 MAJOR RECOMMENDATIONSwww.denvergov.org/federalcorridor
PROJECTS
8 - CORRIDOR WIDE14 - ZONE A SOUTH9 - ZONE B15 - ZONE C15 - ZONE D7 - ZONE E7 - ZONE A NORTH
www.denvergov.org/federalcorridor
QUICK WIN HIGHLIGHTS (1-2 YEARS)
INSTALL BENCHES AT TRANSIT STOPS
INSTALL BENCHES AT TRANSIT STOPS
TEST AND PILOTDEDICATED BUS LANES
TEST AND PILOTDEDICATED BUS LANES
TEST AND PILOTINCREASED
PUBLIC SPACE
TEST AND PILOTINCREASED
PUBLIC SPACE
UPGRADE CROSSINGS TO MEET ADA STANDARDS
UPGRADE CROSSINGS TO MEET ADA STANDARDS
www.denvergov.org/federalcorridor
NEAR-TERM HIGHLIGHTS (2-10 YEARS)
NEWTRANSIT SHELTERS
NEWTRANSIT SHELTERS
DESIGN CROSSING IMPROVEMENTS
DESIGN CROSSING IMPROVEMENTS
COMPLETESIDEWALK NETWORK
COMPLETESIDEWALK NETWORK
REDUCE SPEEEDING AND RACING
REDUCE SPEEEDING AND RACING
www.denvergov.org/federalcorridor
LONG-TERM HIGHLIGHTS (10-20 YEARS)
LANDSACPEDBUFFERS
LANDSACPEDBUFFERS
NEWMEDIANS
NEWMEDIANS
GRADE SEPERATEDTRAIL CROSSINGS
GRADE SEPERATEDTRAIL CROSSINGS
DISTRICT GATEWAYSDISTRICT GATEWAYS
www.denvergov.org/federalcorridor
CORRIDOR VISION
www.denvergov.org/federalcorridor
SMART CITY TECHNOLOGY
www.denvergov.org/federalcorridor
CURB CUTS AND SHARED PARKING
www.denvergov.org/federalcorridor
PILOT PROGRAMS
www.denvergov.org/federalcorridor
REDUCE STREET RACING: DESIGN AND ENFORCEMENT
www.denvergov.org/federalcorridor
DESTINATION + CREATIVE DISTRICTS
www.denvergov.org/federalcorridor
BRANDING + PROGRAMMING
www.denvergov.org/federalcorridor
REDUCE BILLBOARD DENSITY
www.denvergov.org/federalcorridor
NEIGHBORHOODBUILDING BLOCKS
www.denvergov.org/federalcorridor
ZONE A SOUTH - EVANS TRANSFER HUB
IMPROVED WAITING ENVIRONMENTCONNECTING TO MULTI-MODAL
ROUTES
IMPROVED WAITING ENVIRONMENTCONNECTING TO MULTI-MODAL
ROUTES
www.denvergov.org/federalcorridor
ZONE B - SANDERSON GULCH
SAFER CROSSINGPARKS AND TRAILS IDENTITY AND
WAYFINDING
SAFER CROSSINGPARKS AND TRAILS IDENTITY AND
WAYFINDING
www.denvergov.org/federalcorridor
ZONE C - LITTLE SAIGON
ENHANCE DISTRICT IDENTITYSIGNATURE URBAN DESIGN FEATURES
ENHANCE DISTRICT IDENTITYSIGNATURE URBAN DESIGN FEATURES
www.denvergov.org/federalcorridor
ZONE D - STADIUM DISTRICT
TREE PLANTING PROGRAMDEVELOP PARTNERSHIPS TO CREATE LOCAL
BRANDING
TREE PLANTING PROGRAMDEVELOP PARTNERSHIPS TO CREATE LOCAL
BRANDING
www.denvergov.org/federalcorridor
ZONE E - FEDERAL AND SPEER
PEDESTRIAN SAFETY AND ACCESSACTIVATE ADJACENT OPEN SPACES
MULTI-MODAL AMENITIES
PEDESTRIAN SAFETY AND ACCESSACTIVATE ADJACENT OPEN SPACES
MULTI-MODAL AMENITIES
www.denvergov.org/federalcorridor
ZONE A - NORTH GATEWAY
IMPROVED GATEWAY INTO CITYSUPPORT CAMPUS ENVIRONMENTS
EMBRACE LOCAL SITES
IMPROVED GATEWAY INTO CITYSUPPORT CAMPUS ENVIRONMENTS
EMBRACE LOCAL SITES
www.denvergov.org/federalcorridor
IMPLEMENTATION PLAN
www.denvergov.org/federalcorridor
PROJECT PHASING
www.denvergov.org/federalcorridor
QUICK WINS (1-2 YEARS) NEAR-TERM PROJECTS (2-10 YEARS)LONG-TERM PROJCTS (10-20 YEARS)
FUNDING OPPORTUNITIES
www.denvergov.org/federalcorridor
FEDERAL PROGRAMSSTATE PROGRAMSCITY PROGRAMSLOCAL/REGIONAL PROGRAMS
NEXT STEPS
www.denvergov.org/federalcorridor
NEXT STEPS
www.denvergov.org/federalcorridor
PROVIDE FEEDBACK AND COMMENTS
SURVEY AVAILABLE HERE OR ONLINE @www.denvergov.org/federalcorridor