Implementation of Explosive Destruction Technology for Mustard Projectiles
March 12, 2014
Presented to:Kentucky Chemical Demilitarization Citizens’ Advisory Commission and Chemical Destruction Community Advisory Board
Presented by:Jeff BrubakerSite Project ManagerAllison RespessAssistant Project Manager for Explosive Destruction Technology
A Partnership for Safe Chemical Weapons Destruction
Explosive Destruction Technology at Blue Grass
ACWA determined it was appropriate to direct Bechtel Parsons to move forward with process to select an EDT to destroy mustard projectiles at Blue Grass
More than 15,000 155 mm mustard projectiles, with fewer than 200 in over-pack containers, along with two Department of Transportation, known as DOT, bottles containing mustard agent will be processed through the EDT
PEO ACWA decision considerations included: Environmental Assessment and resulting Finding of No Significant Impact and stakeholder involvement
BPBG awards a contract to UXB International in Nov 2013 for a Static Detonation Chamber.
Design, permitting and preparation of Site Plan Safety Submission began with first UXB technical submittals in December 2013.
2
A Partnership for Safe Chemical Weapons Destruction
Public Involvement
Participating in CAC/CDCAB Explosive Destruction Technology (EDT) Working Group meetings
Information exchange important as EDT permitting, design maturity progresses
Working group members and public will be kept informed as EDT moves forward
3
Members of the BGCAPP team met with CAC/CDCAB EDT Working Group members on March 4, 2014.
INSERT PHOTO
A Partnership for Safe Chemical Weapons Destruction
Preliminary schedule
4
Activity Date StatusNEPA Process (FONSI Issued) March 2012 – Oct. 21, 2013 Completed
Limited Notice to Proceed October 30, 2013 Completed
Contract Award to UXB International, Inc. November 2013 CompletedBlue Grass Static Detonation Chamber (SDC) System Design November 2013 - December 2014 Working
RCRA Part B Permit Modification Mid March 2014 – Spring 2016 Upcoming
Title V Air Permit Mid March 2014 – Fall 2014 UpcomingManufacturing, Assembly, and Factory Acceptance Testing Spring 2014 – Spring 2015 Upcoming
Construction, Installation, and Systemization Fall 2014 – Fall 2016 Upcoming
SDC Equipment Delivery Spring/Summer 2015 Upcoming
Start of Operations Winter 2016/Early 2017 Upcoming
End of Operations Fall 2017 Upcoming
A Partnership for Safe Chemical Weapons Destruction
5
Activity Start Date Finish DatePre-application meeting announcements:newspapers, radio, T.V., mailing list Mid March 2014 Mid March 2014
60-day public comment review and consideration period
Mid March 2014(60-days begins with publication of meeting announcements)
Mid May 2014
Submittal of Class 3 Permit Modification Request to Kentucky Department for Environmental Protection (KDEP)
Mid March 2014 Mid March 2014
KDEP review of Class 3 Permit Modification Request Mid March 2014
Mid Sept. 2014 –application review time 365 days(divided into two periods of 6 months each) but Regulatory Review times are variable and beyond BGAD/BPBG control
Prepare and Submit to KDEP a Temporary Authorization Request to Begin Construction – (after submittal of Permit Modification Request with expeditious review as stated in Federal Regulatory Requirements)
Late March 2014 Late May 2014
KDEP review and approval of Temporary Authorization Request Late May 2014 Late September 2014
Pre-application meeting Mid April 2014(30 days after announcements) Late April 2014
KDEP considers and responds to public comments Mid May 2014
Mid July 2014(generally 30 to 60 days following close of comment period)
Schedule ― Request for Class 3 Modification to BGAD RCRA Hazardous Waste (Part B) Permit
Explosive Destruction Technology –regulatory permitting process
A Partnership for Safe Chemical Weapons Destruction
6
Activity Start Date Finish DatePrepare Title V Revision Application Early March 2014 Early March 2014Government review/comment resolution Early March 2014 Early May 2014
KDEP deems application complete (60 day) Early May 2014 Early July 2014
KDEP issues Draft Permit (60 Day) Early July 2014 Early September 2014Note: Cabinet must issue or deny permit within 18 months of submittal of complete application.
Schedule – Title V Air Permit, Major Modification
Explosive Destruction Technology –regulatory permitting process (cont.)
A Partnership for Safe Chemical Weapons Destruction
Key Engineering attributes for permits
Selected 30 percent design documents included in Request for Class 3 Modification to BGAD RCRA Hazardous Waste Permit
Submission includes:– Process flow diagrams– Piping and instrument diagrams– Mass and energy balance
30 percent design documents reviewed and updated as part of standard engineering processes
Permit Modification Request updated once design is finalized
7
A Partnership for Safe Chemical Weapons Destruction
Explosive Destruction Technology –Mass and Energy Balance
8
Mass and Energy Balance:– The M&EBs are a summary of all the streams that enter,
pass through, and leave the system.– They must account for both mass flows and energy
requirements.– The M&EBs are included with the process flow diagrams
and are the starting blocks for the preliminary design.– They define not only the flow quantities,
but also the temperature and pressures of the streams.
A Partnership for Safe Chemical Weapons Destruction
Static Detonation Chamber/Pollution Control System in Dynasafe workshop
9
Pollution Control SystemISO Containers SDC 1200 C with steel structure
A Partnership for Safe Chemical Weapons Destruction
Static Detonation Chamber 1200 C similar to BGCAPP unit
10
A Partnership for Safe Chemical Weapons Destruction
Explosive Destruction Technology –Construction sequencing
Civil, structural and architectural– Site mobilization and underground utilities– Steel-laced concrete foundation– Steel superstructure
Static Detonation Chamber and associated equipment Exterior enclosure Interior air ductwork, electrical, piping, fire protection,
air monitoring, etc.
11
A Partnership for Safe Chemical Weapons Destruction
12
Questions/Discussion