Install Pit BRGNBN-CON-GDE-1656 | Rev 1.0 | 02 APR 15
Owner: Lance Parkes - Standards & Field Practices, Construction Standards & Processes
© NBN Co Limited 2015 | ACN 136 533 741 Page 1 of 11This document is provided for information purposes only and its contents are subject to change. NBN Co does not make any representations orwarranties as to the currency, accuracy or completeness of the information contained herein or that the processes and information outlined complywith all (or any) laws, codes of practice or standards. The recipient must make its own inquiries to satisfy itself as to the currency, accuracy andcompleteness of this document and the information contained in it. The contents of this document should not be relied upon by any Delivery Partneror any other person as a substitute for knowledge, experience, care, skill, or any other contractual or legal obligation. Not for general distribution.
For Official Use Only
This build reference guide (BRG) provides a guide in relation to pit installation. It references rules and guidelines from the following
documents:
NBN-COO-P&D-490: Type 2.0 Architecture: Passive Network Design Rules
NBN-TE-CTO-483: NBN Co Conduit and Pit Network Deployment: Brownfields
NBN-TE-CTO-194: New Developments: Deployment of the NBN Co Conduit and Pit Network – Guidelines for Developers.
Note:
Before and during this task ensure all applicable safety requirements are followed.
Do not deviate from the specifications provided, without prior approval from NBN.
Do not commence digging without first checking for other assets via the Dial Before You
Dig website or 1100 phone number.
7/23/2019 Install Pit in NBN project
http://slidepdf.com/reader/full/install-pit-in-nbn-project 2/11
For Official Use Only
NBN-CON-GDE-1656 | Rev 1.0 Install Pit BRG
NBN Co Limited | Uncontrolled when printed Page 2 of 11
Pit Location
Ensure a minimum separation of 1m fromall poles excluding transformer poles.
Ensure a minimum separation of 15m from
any pad mounted transformer or pole with a
transformer installed on it (EPR zone).
Ensure a minimum separation of 1m from
back of kerb where practical.
Ensure a minimum separation of 3m fromthe property boundary for all pits installed
on corners.
Ensure pit is aligned with the kerb in
communications alignment.
Do not install pit on an angle (as in photo).
7/23/2019 Install Pit in NBN project
http://slidepdf.com/reader/full/install-pit-in-nbn-project 3/11
For Official Use Only
NBN-CON-GDE-1656 | Rev 1.0 Install Pit BRG
NBN Co Limited | Uncontrolled when printed Page 3 of 11
Excavation of Site
Excavate site to required size and depth.
Excavate site larger than the pit to accommodate correct
compaction methods – typically a minimum distance of
150mm beyond the outer wall of the pit is sufficient.
Ensure that the excavated site allows for conduit to be
installed at the correct depth.
7/23/2019 Install Pit in NBN project
http://slidepdf.com/reader/full/install-pit-in-nbn-project 4/11
For Official Use Only
NBN-CON-GDE-1656 | Rev 1.0 Install Pit BRG
NBN Co Limited | Uncontrolled when printed Page 4 of 11
Pit Foundation
Ensure a foundation of sand, refinedcrushed rock, or stabilized sand is used to
a depth of 100mm.
Make the required alterations to the pit
foundation in order to level out pit with
ground surface level or pavement.
7/23/2019 Install Pit in NBN project
http://slidepdf.com/reader/full/install-pit-in-nbn-project 5/11
For Official Use Only
NBN-CON-GDE-1656 | Rev 1.0 Install Pit BRG
NBN Co Limited | Uncontrolled when printed Page 5 of 11
Conduit Entries to Pits
Ensure the conduit entries are correct. Ensure the correct size hole saw is used for conduit entries to allow the bushes
to be a tight fit into the pit.
Ensure conduits are cut square and flush to interior wall of the pit with conduits
inserted fully into the bush and PVC glued.
Ensure entry/exit points at opposite ends of the pit are aligned in order for cabling
to be hauled through easily.
Do not extend conduit too far into pit, at an angle or without a bush.
Note: the conduit example in the photo is now a difficult rectification as there is a
good chance the cable will be damaged and split bushes will be required.
7/23/2019 Install Pit in NBN project
http://slidepdf.com/reader/full/install-pit-in-nbn-project 6/11
For Official Use Only
NBN-CON-GDE-1656 | Rev 1.0 Install Pit BRG
NBN Co Limited | Uncontrolled when printed Page 6 of 11
Do not misalign conduit entry and exit points as this could cause
hauling issues.
Ensure the top of the entry for the conduit is level with, or below, the
minimum depth of cover required, i.e. 450mm for all street conduits.
Ensure the bottom of the entry for the conduit is 50mm above the inside
base of the pit to avoid infiltration of silt into the pit
7/23/2019 Install Pit in NBN project
http://slidepdf.com/reader/full/install-pit-in-nbn-project 7/11
For Official Use Only
NBN-CON-GDE-1656 | Rev 1.0 Install Pit BRG
NBN Co Limited | Uncontrolled when printed Page 7 of 11
Back Filling
Contour the backfill material into the ribs in order to provide maximumstrength and to maintain the pits structural integrity.
Use sand, refined crushed rock or stabilized sand as backfill material.
Do not allow the walls of the pit to warp during the backfilling process.
Ensure a non-mechanical hand operated compactor is used to hard-pack
backfill.
Compact in layers 150mm in depth or under.
Use this process to fill the whole excavation with allowance for final
surface reinstatement.
P6, P8 and P9 pits came with two PVC cable bearers fitted into the
interior of the pit, these bearers must be installed before back filling
commences along with the gaskets.
7/23/2019 Install Pit in NBN project
http://slidepdf.com/reader/full/install-pit-in-nbn-project 8/11
For Official Use Only
NBN-CON-GDE-1656 | Rev 1.0 Install Pit BRG
NBN Co Limited | Uncontrolled when printed Page 8 of 11
Ensure in grassed areas, backfill material stops within 50mm
of the finished surface level and that top soil or turf is installed
to the finished surface level (visible clumps of dirt, clay androcks will not be acceptable).
Alternatively allow for laying of pavement or temporary hard
surface reinstatement.
Check temporary hard surfaces reinstatement for trip
hazards.
Ensure all spoil and rubbish is removed at completion of pit
installation.
Incorrect backfilling methods will result soil subsidence
around pits post installation causing safety issues
All new NBN pits require NBN branded lids any new pits with
Telstra infrastructure inside require Telstra lids
7/23/2019 Install Pit in NBN project
http://slidepdf.com/reader/full/install-pit-in-nbn-project 9/11
For Official Use Only
NBN-CON-GDE-1656 | Rev 1.0 Install Pit BRG
NBN Co Limited | Uncontrolled when printed Page 9 of 11
Where possible, the installation of a
pit in both pathway and verge orgarden bed simultaneously should
be avoided.
7/23/2019 Install Pit in NBN project
http://slidepdf.com/reader/full/install-pit-in-nbn-project 10/11
For Official Use Only
NBN-CON-GDE-1656 | Rev 1.0 Install Pit BRG
NBN Co Limited | Uncontrolled when printed Page 10 of 11
Labelling
Label the NBN breakout conduit duringinstallation.
Label any breakout conduit that link Telstra
pits to Telstra pits.
Label and seal any breakout conduit that link
Telstra pits to NBN pits.
Do not wait until PC to label the conduit as
returning later will take extra time and may beforgotten.
7/23/2019 Install Pit in NBN project
http://slidepdf.com/reader/full/install-pit-in-nbn-project 11/11
For Official Use Only
NBN-CON-GDE-1656 | Rev 1.0 Install Pit BRG
NBN Co Limited | Uncontrolled when printed Page 11 of 11
Update Documentation during
Construction Update the Construction Plan with red lines to reflect ‘as
built’.
Prepare dilapidation reports with before and after
photographs and addresses during construction.
Do not wait until PC to update documentation as updating
documentation during PC will take more time
This is not intended to be an exhaustive list of instructions – please see your site supervisor for more detailed information.