Page 1: Issue: November 2019 - KERALA RAIL...EVENTS AND UPDATES PROPOSED RAIL ROUTE IN NEWS SILVER LINE: MEDIA COVERAGE Discussion on the programme “Varthmanakalam” Discussion on Red FM

FROM THE MD'S DESK

Issue: November 2019

A Monthly Newsletter From The Kerala Rail Development Corporation Ltd

K-Rail, a joint venture between Government of Kerala and Ministry of Railways - Government of India, is all set to revolutionize the very concept of travel in Kerala, with its path-breaking projects that will connect people to places and opportunities like never before. K-Rail will lend a new dimension to the railway infrastructure in Kerala with its super-fast, safe rail services, which will not only make intra-state travel easy and convenient for millions, but also help fast-track the socio-economic development of State – especially the less developed regions. K-Rail will be undertaking end-to-end development and execution work for an identified basket of projects, which include site surveys, preparation of Detailed Project Reports (DPR), attaining mandatory approvals/sanctions and implementation of the sanctioned projects.

K-RAIL

The Silver Line project was

introduced at a function held on

the 4th of September 2019,

which was jointly organized by

the Trivandrum Chamber of

Commerce and Industry (TCCI)

and Trivandrum Agenda Task

Force. The function was

attended by a host of

An event was organised jointly by Trivandrum Chamber of Commerce and Industry (TCCI) and Trivandrum Agenda Task Force on 04.09.2019

1. Silver Line: O�cial Announcement

2. SILVER LINE GETS CABINET NODThe Cabinet meeting of Kerala State

Ministers held on the 7th of August 2019

gave the o�cial clearance for

implementation of Silver Line project by

the Kerala Rail Development Corporation

Limited (K-Rail). According to Shri. V Ajith

Kumar, MD, K-Rail, the double line stretch

spanning 532 Km will reduce the railway

tra�c congestion in the state, which is

now operating at 115% capacity.

3. LiDAR Survey Gets ApprovalThe LiDAR (Light Detection and

Ranging) Survey is an aerial

remote-sensing survey method that

will help study the 532 Km stretch

semi-high-speed railway line,

extending from Kochuveli to

Kasaragod. The on-field survey will be

carried out by the Hyderabad-based

agency GeoKno.

The LiDAR method makes use of light

in the form of a pulsed laser to

measure ranges/variable distances to

the Earth. These light pulses,

combined with other data recorded by the system, will generate high-precision

three-dimensional information about the shape of the Earth in that area and also

the surface/geographical characteristics, which helps in planning, designing and

implementing the project.

4. The Metro ConnectKeeping in mind the increasing number of passengers travelling from Kochi to

di�erent parts of Kerala, the Semi High Speed Rail (SHSR) will have an integrated

station in the second phase of Kochi Metro, near Infopark at Kakkanad.

Shri. Tom Jose IAS, Chief Secretary – Government of Kerala, announced the same at

a presentation on Silver Line, organized by K-Rail and Better Kochi Response Group

(BKRG) on the 26th of October 2019.

5. Silver Line Gets Massive Support from Traders’ and Merchants’ Union

K-Rail Managing Director Shri. V. Ajith Kumar speaks at a session organized by the Malabar Chamber of Commerce in Kozhikode on the 02.11.2019

Silver Line, which is all set to

change the way the people in

Kerala commute, will also open up

a new world of opportunities for

business in the State. This has been

accepted with much enthusiasm by

the business/trading fraternity.

K-Rail Managing Director

Shri. V. Ajith Kumar said that the

proposed Semi High- Speed Rail

(SHSR) corridor from

Thiruvananthapuram to Kasaragod

will improve business prospects

Presentation on Silver Line at the annual convention of the Quilon Management Association (QMA) held on the 30.11.2019.

“The initial steps to put this

dream project on track are

progressing at a fast pace.

This mega project will

fast-track end-to-end rail

tra�c in Kerala”, said K-Rail

Managing Director Shri. V

Ajith Kumar, while speaking

at the event.

6. TRAFFIC SURVEY CONDUCTED SUCCESSFULLYThe Tra�c & Transportation survey

for Silver Line was carried out

successfully in September and

October 2019, at the identified

locations. The main objective of the

survey was to assess the existing

tra�c and transportation

characteristics of the commuters

between Thiruvananthapuram and

Kasaragod. All modes of transport

on this stretch were covered under

the study.

7. Soil Investigation Survey UnderwayThe Soil Investigation (Geotechnical

Investigation) survey commenced on the

27th of August 2019 and is in progress. The

purpose of this investigation is to provide all

necessary inputs for designing the civil

engineering structures for the project.

At K-Rail, we are thrilled about the

journey that we have embarked on.

A foresighted project that will take

intra-state rail transportation to the

next level, Silver Line aims to make

fast, comfortable, safe and

world-class travel accessible to the

common man at an a�ordable cost,

while ensuring minimal land

acquisition and synergized

development of cities across

Kerala. We will, through project

Silver Line, strive to accelerate

Kerala’s infrastructure, economic

and social development.

As you are aware, Silver Line is

a 100% green initiative that will

help reduce the State’s carbon

footprints significantly. As of

now, the initial/ preparatory

work of the LiDAR has been

successfully completed. Both

MOD and DGCA have granted

clearance for flying for this

aerial survey. Processes

including Soil Investigation,

Environmental Impact

Assessment (EIA) and Social

Impact Assessment (SIA) are

currently underway. The tra�c

survey has been completed and

the results are expected by

January 2020. Once

operational, Silver Line will o�er

next-generation intra-state rail

travel experience to millions

with its fast, convenient and

passenger-friendly services; and

K-Rail is proud and honoured to

make this dream project a

reality for the people of Kerala.

SOON, KERALA WILLCHANGE THE WAY IT TRAVELSSilver Line: Semi High Speed Rail Corridor “Silver Line”, K-Rail's Semi High Speed Rail project, will connect the North and

South regions of the State with train services that will operate at a maximum speed of

200 km/hour, reducing the total travel time to less than 4 hours. Silver Line will redefine

intra-state travel in Kerala with its high quality, time-saving services and provide e�cient

last mile connectivity through aggregate and feeder services. This will ensure maximum

passenger convenience and encourage more and more people to use public transport.

Silver Line is expected to bring about host of positive changes to the way people in

Kerala travel by creating a fast, e�cient and reliable mode of long-distance transport,

which will decongest roads, reduce accidents, minimize air pollution and most

importantly, ease the current rail passenger rush.

EVENTS AND UPDATES

PROPOSEDRAIL ROUTE

IN NEWS

SILVER LINE:MEDIA

COVERAGE

Discussion on the programme “Varthmanakalam”

Discussion on Red FM Radio

Kerala Rail Development Corporation Ltd (K-Rail) has attained approval/clearance from the Directorate General of Civil Aviation (DGCA) and Ministry of Defence for conducting aerial survey for the proposed Thiruvananthapuram-Kasaragod Silver Line.

EditorAnil Kumar G, JGM/CSSub-EditorNidhiya Joseph, Technical Assistant

0471 2325330 www.krdcl.co.in0471 232 7330 [email protected]

Contact us: Kerala Rail Development Corporation Ltd.5th floor, Trans Towers, Vazhuthacaud, Thycaud P.OThiruvananthapuram, Kerala-695014

dignitaries including Kerala Government and K-Rail o�cials. Shri. Tom Jose IAS,

Chief Secretary, Government of Kerala, who was the Chief Guest at the function

announced that the Semi High-Speed Project will be tentatively called “Silver Line”.

Shri. V Ajith Kumar, Managing Director - K-Rail, made a detailed presentation on

“Semi High-Speed Rail Corridor” and expressed hope that Silver Line will change

the way people in Kerala travel.

across multiple industries in the State, especially in the Malabar region. He informed that

the construction work of the project would commence in 2020 after attaining necessary

approvals from the Indian Railways and is expected to be operational by 2025.