Italian Pilot on License Shared Access Location: 201 viale America, Rome
Duration: May 2015 - April 2016
Participants EC Joint Research Centre
Italian Ministry for Economic Development Fondazione Ugo Bordoni
Nokia NSN Red Technologies
Fairspectrum Cumucore
Poste Mobile Athonet
Serving society
Stimulating innovation
Supporting legislation
LSA Pilot Objectives
To support the RSPP objective of efficient use of spectrum To test the CEPT and ETSI frameworks on spectrum sharing with
focus on 2.3-2.4 GHz band (ref: EC Mandate of March 2014) To validate the LSA sharing framework for the Italian NRA Applicability of LSA approach to other frequency bands ? Use cases: Fixed Service; PMSE; Telemetry
2 27 September 2016
System Architecture
3 27 September 2016
Summary of incumbent protection requirements
Parameters Fixed Service PMSE Telemetry
Comment
Boltzmann’s constant, k [Joule/°K] 1.38*10-23 1.38*10-23 1.38*10-23
Absolute receiver temperature, T [K°]
290 290 290
Frequency, f [MHz] 2340 2340 2340 Receiver bandwidth, B [MHz] 2 8 10 Receiver noise, NF [dB] 3.5 4 4
Noise power, N [dBm] -107.47 -100.95 -99.98
N = -174+10*log10(B[Hz])+NF*
Receiver antenna gain, G [dBi] 32 0 0
I/N [dB] -10 (1) -6 (2) -6 (3)
(1) Derived from ITU-R F.758-5 (2) CEPT Report 58 (3) ECC Report 172
Maximum allowable interference, power, Imax [dBm]
-117.47 -106.95 -105.98 Imax = I/N + N
E [dBμV/m] -4.87 37.65 38.62 E = 77.21 + Imax +
20*log10(f[MHz]) - G Measurement bandwidth [MHz] 2 8 10
Measurement height [m] At victim Rx
height 3 15
4 27 September 2016
Practical Aspects in Measurements
A: Testing the broadband functionality of the system in various locations on-site and around the site
B: Testing the LSA Protection Requirements Protection criteria imply the need to measure signals below the
noise floor Urban canyon around the deployment site meant that line of sight
was difficult to achieve to do functional tests in many outdoor locations
Accessibility of site / portability of equipment
5 27 September 2016
Types of Tests and Measurements
Scope Tests Functional tests Coverage (outdoor drive tests and indoor walk
tests) EIRP pattern Carrier power reduction Speed tests Hand-over Interoperability Evacuation time
Regulatory compliance
Compliance with the I/N protection criteria (PMSE/FS) Propagation model EMF exposure
Business context * Carrier aggregation
Various tests have been planned and executed within the LSA Pilot
* In progress
Instrumentation Network analyser R&S TSMW with software ROMES4 Spectrum analyzer Anritsu MS2720T Test receiver R&S ESMD with software ARGUS SwissQual Qualipoc handheld for walk tests
7 27 September 2016
Standard set ups and facility provided by MISE Purpose-built test equipment by JRC EM Exposure Measurements by FUB Post-measurement analysis (all) UE performance tests by MISE
8 27 September 2016
Field Measurements (Mobile Van of MISE)
9 27 September 2016
Field Measurements (Portable equipment from JRC)
Antenna Pattern Measurements
Antenna EIRP
Azi
mut
EIRP (dBm)
10
20
30
40
50
0 °15 °
30 °
45 °
60 °
75 °
90 °
105 °
120 °
135 °
150 °
165 °180 °195 °
210 °
225 °
240 °
255 °
270 °
285 °
300 °
315 °
330 °
345 ° V Pol.
H Pol.
Profile of measurement on MISE roof top
10 27 September 2016
LTE Signal measurements under different traffic conditions
11 27 September 2016
15:10 15:20 15:30 15:40 15:50 16:00 16:10 16:20 16:30 16:40
UTC time
30
40
50
60
70
80
90
100
Fiel
d st
reng
th (d
BV/
m)
Location: Via Groelandia (41.82620, 12.46688) - Date: 17.12.2015 - V Pol.
20 MHz
8 MHz
1 MHz
Base station off
Test mode
UL/DL traffic via iperf
Base station on
Drive Tests
Coverage Measurements
Outdoor walk tests (Opposite MISE)
15 27 September 2016
LTE Signal Measurements under different traffic conditions
16 27 September 2016
15:10 15:20 15:30 15:40 15:50 16:00 16:10 16:20 16:30 16:40
UTC time
30
40
50
60
70
80
90
100
Fiel
d st
reng
th (d
BV/
m)
Location: Via Groelandia (41.82620, 12.46688) - Date: 17.12.2015 - V Pol.
20 MHz
8 MHz
1 MHz
Base station off
Test mode
UL/DL iperf
Base station on
Base station off
Signal Analysis - OFDM Grid in idle mode
17 27 September 2016
Spectrogram in Test mode at 454 m
18 27 September 2016
Indoor BS at 7th floor
BS 1
≈ 120 m
≈ 9
5 m
Indoor BS @2.3 GHz
BS 2
Indoor BS @2.6 GHz
BS 4
BS FDD
BS 5
• BS properly located to allow coexistence with Wi-FI access points
• BS synchronisation and inter-cell hand-over required
Speed tests and handover measurements on 7th floor
≈ 120 m
≈ 9
5 m
Installed Indoor BS @2.3
A762
A741
A761
A760
A759 A758 A757 A756
A755
BAR
A742A743
A744
A739A740
BS 4
A714
BS 3
BS 1
BS 2
Measurements locations
A728
A734 A750
Handover BS1-BS3
Handover BS4-BS1
A702
B737 B735
A769
Handover BS3-BS2
Handover BS3-BS2
Handover BS2-BS1
Speed tests and handover measurements results: indoor base stations
Base Station
UE termina
l
Average Download
Maximun Download
Average Upload
Maximun Upload Room LEVEL
(dBm)
4 1 12.91 13.01 7.14 7.20 714 -73 4 2 14.13 15.06 6.63 6.85 714 -73 4 1 37.93 41.65 8.09 8.10 728 -51 4 2 37.48 37.60 8.48 9.34 728 -51 1 1 10.73 11.39 5.66 6.04 734 -63 1 2 9.57 10.70 7.23 7.62 734 -63 1 1 28.28 28.93 7.22 7.36 741 -51 1 2 38.91 40.43 7.04 7.15 741 -51 3 1 12.80 17.10 4.17 4.38 750 -73 3 2 19.82 20.76 6.56 6.99 750 -73 3 1 7.94 11.87 5.70 6.32 702 -59 3 2 9.27 15.58 7.18 7.66 702 -59 2 1 8.59 16.84 5.61 6.09 755 -81 2 2 9.45 12.68 7.39 7.87 755 -81 2 1 16.76 18.25 6.22 7.34 762 -54 2 2 6.56 13.01 8.51 9.29 762 -54 2 1 8.59 11.30 6.02 6.50 769 -78 2 2 8.42 14.84 6.57 6.67 769 -78 2 1 9.20 11.00 3.70 3.87 737 -72 2 2 7.74 8.12 2.45 2.81 737 -72 1 1 5.10 5.73 1.19 1.27 735 -85 1 2 1.63 1.94 0.53 0.57 735 -85
Key Features of the Pilot Integration of technologies, solutions and devices from various
companies An international test platform and distributed architecture: • eNodeB deployment and EPC in Italy • LTE network controller in Finland • LSA repository in France eNodeBs: Nokia Flexizone pico base stations indoor and outdoor 2.3GHz LTE-TDD (B40) and 2.6 GHz LTE-FDD (B7) User equipment: Off-the-shelf Smartphones Potential to test Carrier Aggregation
23 27 September 2016
Main Achievements
Regulatory level - Verification of sharing conditions - Feasibility of spectrum sharing - NRA insight into LSA process Industry level - System Integration - Interoperability of equipment and modules - Standardisation Innovations - Distributed Architecture - VMNO - 5G relevance
24 27 September 2016