SCHOOL OF ARCHITECTURE
New Architecture Bui lding, VIVA Campus,Shirgaon, Virar East , Dis t . Palghar,
Maharashtra 401 305Emai l : v ivaschoolofarch@gmail .com
Candidate’s Name : Shalaka R. Shinde
Academic Year : 2015-16
Training Period : 14TH December to 31ST March
LOG BOOKPROFESSIONAL PRACTICE TRAINING
FOURTH YEAR B. ARCH. SEMESTER - VIII
BRIEF DETAILS OF CANDIDATE
Candidate’s Name : Shalaka R. Shinde
Father’s Name : Rajendra S. Shinde
Mother’s Name : Rashmi R. Shinde
Residential Address : Plot no. 48, flat no. 7 Snehal CHS Chakala Tarun
Bharat. Behind Hotel Oriental Aster
Andheri (E) Mumbai-99
E-mail Address : [email protected]
Mobile No. : +91-9967022329
Term II Exam Seat No. :
Month & Year of Passing Fourth Year :
Period of Training : (14/12/2015) to (31/03/2016)
Duration of Training : 16 Weeks
Name of Firm / Organization : Around A Tree
If Firm then,
Name of Chief / Principal Architect : Suhani A. Shah
Council of Architecture Registration No. : CA/2016/74317 Valid Till: (31/12/2017)
Office Address : A-104, Sea shell apartments, Opposite
Nana Nani park, Seven bungalows; Versova
Andheri (W) Mumbai-61
E-mail Address : [email protected]
Mobile No. : +91-9833767013
Website (If any) :
Salary Drawn during Training Period : NIL
Candidate’s Signature :
BRIEF DETAILS OF PROJECT NO. – 1
Title of Project : RUSTOMJEE; MERIDIAN
Project Type : Residential Project.
Plot Area : 0.59 acres.
Site Address : Kandivali; Mumbai.
Stage of Project : Stage 3 (Construction drawings; CD Package) sent for execution.
Candidate’s involvement in the project during the Training Period
Design Development Drawings & Construction Drawings
(Stage 2 & 3)
1. Reference plan
2. Soil depth plan
3. Setting out plan
4. Grading plan
5. Material plan
6. Furnishing plan
7. Drainage plan
8. Irrigation plan
9. Lighting plan
10. Shrub planting plan
11. Tree planting plan
Specifications along with BOQ and Quantity estimation
Attending Meetings with client.
Contacting Vendors/Contractors for respective works and getting the
quotation for the same and approving it from the client to make the
final BOQ with revisions as per discussions with the client.
Plant list for the project for the record.
Certified that the above details/ information is true and correct to the best of my knowledge.
Signature of External Trainer: ________________________ Stamp:
BRIEF DETAILS OF PROJECT NO. – 2
Title of Project : ASNANI BUILDERS; VALENCIA.
Project Type : Residential + Commercial Project.
Plot Area : 9.28 acres.
Site Address : Bhopal, Madhya Pradesh.
Stage of Project : Stage 3 (CD Package) drawings of external 60 ft. and 80 ft. R.O.W.,
external rotary junction and Phase-1 of the project.
Candidate’s involvement in the project during the Training Period
Conceptual sketches and drawings; Conceptual presentation (Stage 1)
Design Development Drawings & Construction Drawings
(Stage 2 & 3) for Phase-1 of the project.
1. Reference plan
2. Soil depth plan
3. Setting out plan
4. Grading plan
5. Material plan
6. Furnishing plan
7. Drainage plan
8. Irrigation plan
9. Lighting plan
10. Shrub planting plan
11. Tree planting plan
Designing external 60 ft. and 80ft. R.O.W. and external and internal
rotary junctions. Contacting Vendors/Contractors for respective works
and getting the quotation for the same. (BOQ and Quantity estimation)
Plant list for the project for the record.
Certified that the above details/ information is true and correct to the best of my knowledge.
Signature of External Trainer: ________________________ Stamp:
BRIEF DETAILS OF PROJECT NO. – 3
Title of Project : RUSTOMJEE; PUNITDHAM TIRTH JAIN TEMPLE.
Project Type : Religious Project.
Plot Area : 2.62 acres.
Site Address : Gujarat; Ahmedabad.
Stage of Project : Stage 3 (Construction drawings; CD Package) sent for execution at the
Site.
Candidate’s involvement in the project during the Training Period
Design Development Drawings & Construction Drawings
(Stage 2 & 3).
1. Reference plan
2. Setting out plan
3. Grading plan
4. Material plan
5. Landscape sections
Designing external 60 ft. and 80ft. R.O.W.
Plant list for the project for the record.
Changes in the Final BOQ as per changes in the materials for flooring
patterns as per client’s feedback.
Brick paving flooring pattern detail drawings.
Specifications for Brickwork paving.
Contacting Vendors/Contractors for Road work for the internal
driveway and getting the quotation for the same.
(BOQ and Quantity estimation)
Certified that the above details/ information is true and correct to the best of my knowledge.
Signature of External Trainer: ________________________ Stamp:
BRIEF DETAILS OF PROJECT NO. – 4
Title of Project : WALLFORT; WOODS.
Project Type : Residential + Commercial Project
Plot Area : 35 acres.
Site Address : Raipur; Chhattisgarh.
Stage of Project : Stage 2 (Design Development drawings; DD Package) sent for
approval at the site by the client and the resp. consultants.
Candidate’s involvement in the project during the Training Period
Design Development Drawings & Construction Drawings
(Stage 2 & 3).
1. Reference plan
2. Soil depth plan
3. Setting out plan
4. Grading plan
5. Material plan
6. Furnishing plan
7. Drainage plan
8. Irrigation plan
9. Lighting plan
10. Landscape sections
Designing internal; 7.50, 9.00, 12.00, 18.00 & 24.00 mt. R.O.W.
Internal rotary junctions.
Contacting Vendors/Contractors for respective works and getting the
quotation for the same. (BOQ and Quantity estimation)
Plant list for the project for the record.
Certified that the above details/ information is true and correct to the best of my knowledge.
Signature of External Trainer: ________________________ Stamp:
LOG OF PROFESSIONAL TRAINING PERIOD
WEEK 1: (14 / 12/ 2015) Mon TO (20 / 12/ 2015) Sun
0614LA_Alancia-
Residential + Commercial project; understanding the project and revising the Master plan plotting for
the project.
0415LA_Meridian-
Residential project; understanding the conceptual drawings and working on Design Development
drawings package (Stage 2).
1. Reference plan-
2. Soil depth plan-
3. Setting out plan-
4. Grading plan-
5. Lighting plan-
6. Material plan-
7. Furnishing plan-
8. Drainage plan-
9. Irrigation plan-
RCC sections through Landscape (Stage 2).
Book reading- Forest for the trees, trees for the forest.
0515LA_Green acres-
Commercial project; understanding the conceptual drawings and working on the Design Development
drawings package (Stage 2).
1. Reference plan-
2. Soil depth plan-
3. Setting out plan-
4. Grading plan-
5. Lighting plan-
6. Material plan-
0715LA_Valencia-
Residential + Commercial project; understanding the project brief and working on conceptual
presentation drawings (Stage 1).
LOG OF PROFESSIONAL TRAINING PERIOD
WEEK 2: (21 / 12/ 2015) Mon TO (26 / 12/ 2015) Sat
0715LA_Valencia-
Residential + Commercial project;
Working on conceptual drawings for three gardens out of four proposed in the project as per Vastu
shastra (Stage 1).
Photoshop-Master plan for the conceptual presentation
0415LA_Meridian-
Residential project;
Revising the Design Development drawings package (Stage 2).
1. Reference plan
2. Soil depth plan
3. Setting out plan
4. Grading plan
5. Lighting plan
6. Material plan
7. Furnishing plan
8. Drainage plan
9. Irrigation plan
10. RCC sections
0515LA_Green acres-
Commercial project;
Internal road sections with respect to the landscaping proposed.
Revised Material plan (DD Package) as per discussions with the client.
0815LA_Punitdham Jain Temple-
Religious project;
Working drawing (Construction Drawing package; CD Stage 3) - Setting out plan for the entire site.
Brick flooring pattern revisions near the Gathering space around the temple.
0114LA_Wallace Fortuna-
Residential project;
Landscape maintenance monthly site visit.
Maintenance comments Presentation as per AAT given to the project handler to commence the same.
LOG OF PROFESSIONAL TRAINING PERIOD
WEEK 3: (28 / 12/ 2015) Mon TO (03 / 01/ 2016) Sun
0715LA_Valencia-
Residential + Commercial project;
Revised Conceptual Presentation as per client’s feedback on the same.
Design development drawings (Stage 2) commenced after the client’s approval on the same.
0415LA_Meridian-
Residential project;
Revising the Design Development drawings package (Stage 2).
1. Setting out plan
2. Grading plan
3. Material plan
4. Drainage plan (For approval from the respective consultant)
5. RCC sections through Landscape
Preliminary Stage BOQ and Quantity estimation for the Landscape proposed for the entire project.
0214LA_Wallfort Woods-
Residential + Commercial project;
Revising the Design Development drawings package (Stage 2).
1. Reference plan
2. Soil depth plan
3. Setting out plan
4. Grading plan
5. Lighting plan
6. Material plan
7. Furnishing plan
0815LA_Punitdham Jain Temple-
Religious project;
Specifications for Stone pavers and Revised BOQ and Quantity estimation as per the material change.
LOG OF PROFESSIONAL TRAINING PERIOD
WEEK 4: (04 / 01/ 2016) Mon TO (09 / 01/ 2016) Sat
0715LA_Valencia-
Residential + Commercial project;
Design development drawings (Stage 2) commenced after the client’s approval on the same.
1. Reference plan
2. Soil depth plan
3. Setting out plan
4. Grading plan
5. Lighting plan
6. Material plan
7. Furnishing plan
8. Drainage plan
9. Irrigation plan
0515LA_Green acres-
Commercial project;
Meeting with contractor for sample selection.
Finalized Material plan as per discussion with the contractor; Samples sent on site for execution.
0214LA_Wallfort Woods-
Residential + Commercial project;
Conceptual drawings for Compound wall for the project (Photoshop).
MEP drawings received from the respective consultants; approval by AAT given on the same.
0815LA_Punitdham Jain Temple-
Religious project;
Revised pattern for Stone pavers and Revised BOQ and Quantity estimation as per the change in
pattern.
LOG OF PROFESSIONAL TRAINING PERIOD
WEEK 5: (11 / 01/ 2016) Mon TO (16 / 01/ 2016) Sat
0715LA_Valencia-
Residential + Commercial project;
Project schedule to be finalized as per priority; GFC drawings to be sent for site execution as per the
schedule.
Rotary design for 80 ft. and 60 ft. road junction.
Two options for Road sections- 80 ft. road as per the Landscape proposed.
Two options for Road sections- 60 ft. road as per the Landscape proposed.
0114LA_Wallace Fortuna-
Residential project;
Monthly site visit for Landscape maintenance.
0214LA_Wallfort Woods-
Residential + Commercial project;
Revised MEP drawings; service layout for the manholes and services pipes for the entire site.
0415LA_Meridian-
Residential project;
Revising the Design Development drawings package (Stage 2) as per the respective consultant’s
feedback.
1. Setting out plan
2. Grading plan
3. Material plan
4. Drainage plan (For approval from the respective consultant)
5. RCC sections through Landscape
LOG OF PROFESSIONAL TRAINING PERIOD
WEEK 6: (18 / 01/ 2016) Mon TO (24 / 01/ 2016) Sun
0715LA_Valencia-
Residential + Commercial project;
Revised Design Development drawings for the following:
1. Rotary design for 80 ft. and 60 ft. road junction.
2. Finalized option for Road section- 80 ft. road as per the Landscape proposed.
3. Finalized option for Road section- 60 ft. road as per the Landscape proposed.
Design Development drawings (DD package; Stage 2) for Phase-1.
1. Reference plan
2. Facility plan
3. Setting out plan
4. Lighting plan
5. Material plan
6. Furnishing plan
7. Drainage plan
8. Shrub planting plan
9. Tree planting plan
0114LA_Wallace Fortuna-
Residential project;
Landscape maintenance comments presentation as per the site visit conducted.
0814LA_Boston House-
Commercial project;
Meeting with Landscape contractor, working on site execution drawings for the same.
Design Development drawings for Shrub planting plan (Stage 2) along with Quantity estimation.
Design Development drawings for Lighting plan (Stage 2) along with Quantity estimation.
0415LA_Meridian-
Residential project;
Approval on the Lighting plan from the MEP consultants.
LOG OF PROFESSIONAL TRAINING PERIOD
WEEK 7: (25 / 01/ 2016) Mon TO (30 / 01/ 2016) Sat
0715LA_Valencia-
Residential + Commercial project;
Design Development drawings (DD package; Stage 2) for Phase-1.
1. Reference plan
2. Facility plan
3. Setting out plan
4. Lighting plan
5. Material plan
6. Furnishing plan
7. Drainage plan
8. Shrub planting plan
9. Tree planting plan
0214LA_Wallfort Woods-
Residential + Commercial project;
Con-call with the client discussing issues in the Master plan. Revised Master plan as per the
discussion for approval.
0415LA_Meridian-
Residential project;
Approval on the following:
1. Lighting plan with electrical layout received from the MEP consultants.
2. Drainage plan received from the respective consultant.
Preliminary Landscape BOQ with Quantity estimation and Specifications
1. Hardscape
2. Soft scape
Design Development drawings package (Stage 2) for:
1. Tree planting plan
2. Shrub planting plan
LOG OF PROFESSIONAL TRAINING PERIOD
WEEK 8: (01 / 02/ 2016) Mon TO (06 / 02/ 2016) Sat
0715LA_Valencia-
Residential + Commercial project;
Revised Design Development drawings (DD package; Stage 2) for:
1. Compound wall design; two options.
2. 60 ft. R.O.W.
Reference images for Compound wall design as per client’s feedback.
0214LA_Wallfort Woods-
Residential + Commercial project;
Revised Compound wall design as per client’s feedback.
Plant List for the following Projects:
1. Wallace Fortuna
2. Boston House
3. Valencia
4. Wallfort Woods
0415LA_Meridian-
Residential project;
Revised Landscape BOQ with Quantity estimation and Specifications.
1. Hardscape
2. Soft scape
0814LA_Boston House-
Commercial Project;
BOQ and Quantity estimation for the Lighting fixtures along with installation and labour work.
Kanjurmarg-
Residential project;
Reference images research work for conceptual drawings presentation.
LOG OF PROFESSIONAL TRAINING PERIOD
WEEK 9: (08 / 02/ 2016) Mon TO (13 / 02/ 2016) Sat
0715LA_Valencia-
Residential + Commercial project;
Construction Drawings Planting package (CD package; Stage 3) for Phase-1.
1. Shrub planting plan
2. Tree planting plan
3. 60 ft. R.O.W. Planting Layout (CD package; Stage 3)
0116LA_Wallfort Indore-
Commercial project;
Design Development drawings (DD package; Stage 2) for:
1. Shrub Planting Layout for 9.00 mt. Road section.
2. Tree Planting Layout for 9.00 mt. Road section.
0415LA_Meridian-
Residential project;
Meeting with the client to discuss the issues concerning the project; like slab details at the edges of
peripheral planters due to changes in soil depths.
Revised Landscape BOQ with Quantity estimation and Specifications as per discussion with the
respective consultant
1. Hardscape- inclusive of supply and installation of materials with labor charges.
2. Soft scape- inclusive of supply and installation of materials with labor charges.
Civil work (Brickwork for planter walls); quantity added in the Revised BOQ.
Construction drawings (CD package; Stage 3) for following:
1. Setting out plan
2. Grading plan
3. Lighting plan
4. Material plan
5. Drainage plan
LOG OF PROFESSIONAL TRAINING PERIOD
WEEK 10: (15 / 02/ 2016) Mon TO (20 / 02/ 2016) Sat
0715LA_Valencia-
Residential + Commercial project;
Revised Construction Drawings package (CD package; Stage 3) for Phase-1.
1. Shrub planting plan
2. Tree planting plan
3. Setting out plan for Planting CD package
4. Revised Compound wall design- R4
Reference image selection by the client for:
1. Compound wall
2. Rotary landscape
Vendor selection for water feature requirement and green wall feature requirement for the project.
0814LA_Boston House-
Commercial project;
Revised Lighting layout as per client’s budget (CD package; Stage 3).
Revised BOQ and Quantity estimation as per changes in the Lighting layout.
0116LA_Wallfort Indore-
Commercial project;
Construction drawings (CD package; Stage 3) for:
1. Shrub Planting Layout for 9.00 mt. Road section.
2. Tree Planting Layout for 9.00 mt. Road section.
0415LA_Meridian-
Residential project;
Revised Landscape BOQ with Quantity estimation and Specifications as per changes in the
Landscape Master plan.
1. Hardscape- inclusive of supply and installation of materials with labor charges.
2. Soft scape- inclusive of supply and installation of materials with labor charges.
Civil work (Brickwork for planter walls); quantity revised in the BOQ.
Kanjurmarg-
Residential project;
Introduction to the project.
Reference images for conceptual presentation as per conceptual sketches and drawings.
Photoshop; Base plan for the conceptual presentation (Option 1)
0514LA_Wallfort Heights-
Residential project;
Approval drawings of RCC details.
Vendor requirement for Heritage plaster and discussion with the vendor for the same.
0815LA_Punitdham Jain Temple-
Religious project;
Preliminary BOQ inclusive of:
1. Materials used for Road work for the internal driveway.
2. Supply and installation rate of the materials.
3. Labor charges.
0214LA_Wallfort Woods-
Residential project;
Vendor requirement for ceramic embossed glazed tiles for flooring and cladding.
LOG OF PROFESSIONAL TRAINING PERIOD
WEEK 11: (22 / 02/ 2016) Mon TO (27 / 02/ 2016) Sat
0715LA_Valencia-
Residential + Commercial project;
Revised Design Development drawings package (DD package; Stage 2) for:
1. Revised Compound wall design- R5 & R6 & R7.
2. Green wall detail drawings.
Vendor selection for crazy cut paving for pedestrian walkway.
0214LA_Wallfort Woods-
Residential project;
Lighting layout for Row housing (Phase 1) and 12 meter R.O.W.
0116LA_Wallfort Indore-
Commercial project;
Revised Construction drawings (CD package; Stage 3) for:
3. Shrub Planting Layout for 9.00 mt. Road section.
4. Tree Planting Layout for 9.00 mt. Road section.
0415LA_Meridian-
Residential project;
Revised Landscape BOQ with Quantity estimation and Specifications as per changes in the rates for
granite given by contractor.
1. Hardscape- inclusive of supply and installation of materials with labor charges.
2. Soft scape- inclusive of supply and installation of materials with labor charges.
Section through peripheral planter to show the slab detail as per the soil depth; also revisions done in
the same as per the site observations.
Kanjurmarg-
Residential project;
Photoshop; Base plan for the conceptual presentation (Option 2)
Conceptual Presentation for the meeting scheduled with the client.
LOG OF PROFESSIONAL TRAINING PERIOD
WEEK 12: (29 / 02/ 2016) Mon TO (05 / 03/ 2016) Sat
0715LA_Valencia-
Residential + Commercial project;
Revised Design Development drawings package (DD package; Stage 2) for:
3. Revised Compound wall design- R8.
4. Green wall detail drawings.
Samples received from the vendor for ceramic embossed glazed tiles.
0214LA_Wallfort Woods-
Residential project;
Revised Lighting layout for Row housing (Phase 1) and 12 meter R.O.W.
0415LA_Meridian-
Residential project;
Revised Landscape BOQ with Quantity estimation and Specifications as per feedback from the client.
1. Hardscape- inclusive of supply and installation of materials with labor charges.
2. Soft scape- inclusive of supply and installation of materials with labor charges.
Revised Construction drawings for Podium level (CD package; Stage 3) for following:
1. Reference plan
2. Setting out plan
3. Grading plan
4. Lighting plan
5. Material plan
6. Drainage plan
7. Furnishing plan
8. Irrigation plan
9. RCC Sections as per changes in the Master plan and site observations.
Vendor list for Hardscape & Soft scape provided to the client.
LOG OF PROFESSIONAL TRAINING PERIOD
WEEK 13: (07/ 03/ 2016) Mon TO (12 / 03/ 2016) Sat
0715LA_Valencia-
Residential + Commercial project;
Entrance gate Elevation; Photoshop
Construction Drawings package (CD package; Stage 3) for:
1. Compound wall design- R7.
2. Green wall detail drawings.
3. Flooring details for the pedestrian walkway.
Samples received from the vendor for ceramic embossed glazed tiles.
0515LA_Green acres-
Commercial project;
Revised Construction drawings (CD package; Stage 3) for Peripheral Tree planting layout.
Preliminary Landscape BOQ with Quantity estimation and Specifications.
0415LA_Meridian-
Residential project;
Revised Final Construction drawings for Podium level (CD package; Stage 3) for following:
1. Reference plan
2. Setting out plan
3. Grading plan
4. Lighting plan
5. Material plan
6. Drainage plan
7. Furnishing plan
8. Irrigation plan
9. RCC Sections as per changes in the Master plan and site observations.
Finalized Vendor list for Hardscape & Soft scape provided to the client.
Ground floor Tree planting layout with revisions as per feedback from the client.
Play equipment BOQ with design received from the resp. contractor added in the Finalized BOQ
approved by the client.
LOG OF PROFESSIONAL TRAINING PERIOD
WEEK 14: (14 / 03/ 2016) Mon TO (19 / 03/ 2016) Sat
0715LA_Valencia-
Residential + Commercial project;
Revised Entrance gate Elevation; Photoshop
Preliminary Landscape BOQ with Quantity estimation and Specifications for Phase 1.
0515LA_Green acres-
Commercial project;
Revised Construction drawings (CD package; Stage 3) for Peripheral Tree planting layout.
Revised Landscape BOQ with Quantity estimation and Specifications as per NOC for Tree
plantation.
0415LA_Meridian-
Residential project;
Revised Final Construction drawings for Podium level (CD package; Stage 3) for:
1. Irrigation plan
Revised Ground floor Tree planting layout as per NOC requirement of trees- R2.
Revised Landscape BOQ with Quantity estimation and Specifications inclusive of Ground floor
Plantations.
1. Soft scape- inclusive of supply and installation of materials with labor charges.
0814LA_Boston House-
Commercial project;
Preliminary Landscape BOQ with Quantity estimation and Specifications for Phase 2.
0214LA_Wallfort Woods-
Residential project;
Construction Drawings package (CD package; Stage 3) for:
1. Grading plan for Phase 1.
LOG OF PROFESSIONAL TRAINING PERIOD
WEEK 15: (21 / 03/ 2016) Mon TO (26 / 03/ 2016) Sat
0715LA_Valencia-
Residential + Commercial project;
Construction drawings (CD package; Stage 3) for:
1. Finalized Compound wall design- R7.
2. Green wall detail.
0214LA_Wallfort Woods-
Residential project;
Construction drawings (CD package; Stage 3) for:
1. Reference plan
2. Setting out plan
3. Grading plan
4. Lighting plan
5. Material plan
6. Furnishing plan
7. Landscape sections
Kanjurmarg-
Residential project;
Photoshop; Base plan for the conceptual presentation (Option 3 & 4)
Conceptual Presentation for the same.
0114LA_Wallace Fortuna-
Residential project;
Status of Landscape maintenance comments till date presentation
LOG OF PROFESSIONAL TRAINING PERIOD
WEEK 16: (28 / 03/ 2016) Mon TO (31 / 03/ 2016) Thu
0214LA_Wallfort Woods-
Residential project;
Revised Construction drawings (CD package; Stage 3) for:
1. Reference plan
2. Setting out plan
3. Grading plan
4. Lighting plan
5. Material plan
6. Furnishing plan
7. Landscape sections
0515LA_Green acres-
Commercial project;
Construction drawings for Podium level (CD package; Stage 3) for:
1. Reference plan
2. Setting out plan
3. Grading plan
4. Lighting plan
5. Material plan
6. Furnishing plan
7. Landscape sections