MASTER PLANNING UPDATE
APRIL 9, 2015
The Board of Education
HOENER ASSOCIATES, INC., ARCHITECTS
WARREN COUNTY R-III SCHOOL DISTRICT
Welcome to Warrior Nation
MASTER PLANNING SUMMARY SHEET WARREN COUNTY R-III SCHOOL DISTRICT
A. REBECCA BOONE E.S. $ 1,305,000 B. WARRIOR RIDGE E.S. $ 137,000 C. DANIEL BOONE E.S. $ 2,344,000 D. BLACK HAWK M.S. $ 2,346,000 E. WARRENTON H.S. $ 8,168,000 F. DATA CENTER $ 103,000 G. CENTRAL OFFICE and EARLY CHILDHOOD $ 300,000 H. MAINTENANCE FACILITY $ 137,000 I. BUS GARAGE $ 450,000
J. SUBTOTAL CONSTRUCTION COSTS (INCLUDES 20% CONTINGENCY) $ 15,290,000 K. A/E FEES, FIELD TESTING, PERMITS, SOFT COSTS, SCOPE, ETC. (10%) $ 1,529,000 L. CONCEPTUAL TOTAL $ 16,819,000
M. CONCEPTUAL TOTAL RANGE (+/- 5%) $15,979,000 to $17,659,000
10