On-Site Strategies for Power Delivery
Reliability- Applications
UC Irvine
Advanced Power and
Energy Program
Presented at the
SoCal Chapter of AEE Annual Conference 2011 Energy Security: Keeping the Power On
September 22, 2011
Presented by
Richard Hack - PE, CEM
University of California, Irvine
© Advanced Power and Energy Program, 2011 2/29
Outline
• Energy Storage/carry-through
• On-Site Power Generation/CHP
• Example
• Concentration on “on-site” and end-use customer level systems (as opposed to grid scale).
© Advanced Power and Energy Program, 2011 3/29
Energy Storage
For short term outages, electric energy storage may suffice:
• Ultra-Capacitors: sags/surges • Flywheels:
© Advanced Power and Energy Program, 2011 4/29
Energy Storage
• With possible exception of hydrogen/fuel cell energy conversion, all have a finite duration
• Power delivery (kw) and energy capacity (kw-hr) both drive costs.
• Energy storage isn’t limited to power interruptions. • Great potential for demand response curtailment benefit
• Utilities can be/are supportive of large scale storage in system for demand reduction in critical periods.
• Financial rewards(?)
• Sandia Report1: • Characterizes 26 benefits of energy storage in
catagories of: 1) Electric Supply, 2) Ancillary Services,
3) Grid System, 4) End User/Utility Customer,
5) Renewables Integration, and 6) Incidental.
1: Energy Storage for the Electricity Grid:Benefits and Market Potential Assessment Guide: SAND2010-0815 Feb 2010
© Advanced Power and Energy Program, 2011 5/29
On-Site Power Generation
• Not diesel gen set back-up systems • On site power generation, grid parallel but capable
of switching to “islanding” mode in event of power
interruption.
• Can be combustion systems (reciprocating engines, gas turbines, boiler/steam turbine)
• Can be electrochemical based systems (fuel cells) • Can be of configured for high overall efficiency
operation through both generation of electricity
and capture of waste heat for use.
• In case of grid reliability, need waste stream to be available to support critical needs.
© Advanced Power and Energy Program, 2011 6/29
What is DG / C-CHP?
• Generation of electric power at or near the point of final use with some form of prime mover and the capture of waste heat to provide some additional beneficial use.
DG: Distributed Generation ( < 20 MW)
C-CHP: Combined Cooling, Heat and Power
• Opportunity to “get more bang for your buck” by getting two or maybe three uses for each unit of energy purchased and consumed on site.
© Advanced Power and Energy Program, 2011 7/29
Why DG / C-CHP?
• Why would I want to generate my own electricity? • Power Reliability
– Power Quality – Back-up Power
• Save $$$$ – Increased Efficiency of overall system
• Added capacity deferring system feed upgrade costs • Greenhouse Gas Emissions
– Environmental Stewardship – Value of Carbon Credits.
© Advanced Power and Energy Program, 2011 8/29
Opportunity for Heat Recovery
Thermodynamic Limitation
• Cannot transform energy at 100% efficiency.
Efficiency = η = (useful energy out) / (energy in)
• Generation of electricity from fossil energy resources will result in wasted energy.
– Efficiencies range from
© Advanced Power and Energy Program, 2011 9/29
Opportunity for Heat Recovery
Carbon In / Work = 154”C” / 75 Carbon In / Work = 100”C” / 75
Net Carbon Reduction: 35%
© Advanced Power and Energy Program, 2011 10/29
Reliable and Premium Power
Cost of Power Outages are exorbitant: EPRI/LBNL estimate from 2006: $79B annually (in 2002 dollars)1
• Commercial: $56.8B (72%) • Industrial: $20.4B (26%)
Individual Sectors2 (2000 $):
• Cellular Communications: $41K/hr • Credit Card: $2.6M/hr • Securities/Brokerage: $6.5 M/hr
DG can provide support
• Applications that require greater reliability than the grid alone. • In conjunction with the grid, “eight-9’s” or better reliability possible
• 0.31 sec / year
1: Cost of Power Interruptions to Electricity Customers in the United States: LBNL-58164; Feb 2006
2:Electric Power Interruption Cost Estimates for Individual Industries, Sectors, and US Economy: PNNL-13797; Feb 2002
© Advanced Power and Energy Program, 2011 11/29
Reliable and Premium Power
Premium Power:
• Could be considered the same as “reliable” power • IT-Grade Power • Applications where power quality is questionable
• Harmonics • Voltage sags/surges • End of line applications that require greater reliability
than the grid alone.
• Issues likely to get worse with increase renewables
• Computer intensive facilities likely most sensitive. • Some critical industries (semi-conductor/chips)
© Advanced Power and Energy Program, 2011 12/29
Energy Saving Opportunities
DG / C-CHP provides a means for locally generating
electric power and other beneficial products:
• Hot water/Steam • HVAC “Cooling” via absorption / adsorption
chillers
Plus:
• Opportunity to generate with grid outage • Store thermal energy for crucial heating/cooling
need
© Advanced Power and Energy Program, 2011 13/29
Waste Heat Recovery
• Recall that there is approximately 70-80% of the heat energy input to prime mover (in the form fuel input)
becomes wasted typically as heat:
• In the exhaust • Cooling water/oil system • Radiation to the atmosphere.
• Can not capture all of the heat in the exhaust; • Do not want to reduce exhaust temp too much • Exhaust condensation-corrosion issues • Exhaust dispersion – lofting
• Amount of waste heat available varies by prime mover. • For MTG, reasonable ROT is 50 - 60% of the exhaust heat can be
captured.
• e.g. Capstone C65; 400,000 btu/hr of heat; 550 F
© Advanced Power and Energy Program, 2011 14/29
Hot Water / Steam
• Hot Water • Amount of heat recovery and temperatures varies
depending upon inlet temperatures and flow rates
Figure courtesy Ingersoll-Rand
• Steam: • Nominal 15 psig steam possible with separate heat
recovery steam generator
• Higher pressure steam possible with auxiliary duct burners to increase exhaust energy/temperature
© Advanced Power and Energy Program, 2011 15/29
Desiccant Dehumidification
• Desiccant Dehumidification can provide substantial reductions in energy consumption:
• Reduced space conditioning loads – eliminates latent heat cooling requirements
• Desiccant dehumidifiers are most energy efficient methodology for moisture removal (ASHRAE 90.1 2004)
– For DG/CHP, regen-energy is “waste” energy – Discharge air @ approx 15% RH.
• Desiccant dehumidifiers located upstream of HVAC systems to dry air prior to cooling.
• Conventional refrigeration. • 80 F, 80 RH ambient make-up; 70 F, 40% RH supply air
– Enthalpy change:~15 btu/lb dry air cooling – @ 200 scfm, ~2 – 2.5 tons of cooling
•
© Advanced Power and Energy Program, 2011 16/29
Absorption Chilling for Cooling Needs
Heat Activated Cooling.
• Significantly reduced electric energy needs (pumping loads)
• Simplified Operating Principles • Refrigerant material (water for Li-Br, ammonia in other) is part of a
liquid binary mixture
• Easier/more efficient (less energy) to pump liquid to higher pressures than gas.
• Refrigerant/carrier pumped to “high” pressure • Heat (from prime mover) boils off high pressure refrigerant • “Expand” refrigerant to lower pressure = cooling • Refrigerant is reabsorbed, with captured heat • Liquid binary mixture is cooled via cooling tower
– Requires cooling towers with capacity of approx 2x the heat removed.
• Process repeats
© Advanced Power and Energy Program, 2011 17/29
Absorption Chilling for Cooling Needs
• Not as energy efficient as electric chillers in producing “cold” but does it with energy that
would otherwise not be utilized (exhaust waste
heat)
• In critical situations, does not compete for electric energy from generation system
Electric Chillers:
COP* 3 – 6 (EER = 10.5 – 21)
Absorption Chillers:
COP = 0.7 Single effect (EER = 2.5)
COP = 1.3 Double effect (EER = 4.5)
*COP = coefficient of performance = energy out/energy in
© Advanced Power and Energy Program, 2011 18/29
Absorption Chilling for Cooling Needs
Single Effect Chillers:
• Lower inlet temperatures: • 180 F water to approx 210 F (no need to consider steam
system headaches)
Double Effect Chillers:
• Higher inlet temperatures: • 250 F to 350 F hot water/steam • Direct firing from exhaust from prime mover.
Lithium Bromide – Water
• Temperatures limited to approx 40 F • HVAC • Medium Temp Cooling
© Advanced Power and Energy Program, 2011 19/29
Adsorption Chilling for Cooling Needs
Different principle than absorption chillers.
• Uses a benign adsorbent media (silica gel). • No safety hazard • Cooling occurs as a result of evaporation of
coolant from media.
Look to Power Partners (vendor, Table 7)
© Advanced Power and Energy Program, 2011 20/29
Data Center Cooling Needs
Air Temperature:
• ASHRAE standard: – 68F – 77 F, 40% - 55% RH
• ASHRAE Technical Committee TC9 2008 recommendation:
– 64.4F – 80.6F, 60% RH, Dew Point 41.9F – 59F
Chilled Water Temperature: – 50 – 55F discharge temp – 65 – 70 F return temps
• Very amenable to thermally activated chilling
© Advanced Power and Energy Program, 2011 21/29
Case Study Opportunity - Commercial Office
Multi-Tower Commercial Office Building
•1.11 million sq-ft
•Central Plant
•TES
Commercial Office Building Complex(average day, Aug 1 - Sept 30)
0
100
200
300
400
500
600
700
0:00 6:00 12:00 18:00 0:00
En
erg
y:
15
min
in
terv
al
2 MW demand
Total Electric
[kw-hr]
Chilling
[RT-hr]
Modified Electric / Heat Ratio(average day, Aug 1 - Sept 30)
0
0.2
0.4
0.6
0.8
1
1.2
1.4
1.6
1.8
2
0:00 6:00 12:00 18:00 0:00
Chilling Provided by double effect
absorption chillers: COP = 1.3
© Advanced Power and Energy Program, 2011 22/29
Typical Data - Commercial Office
Commercial Office Building Complex(average day, Aug 1 - Sept 30)
0
100
200
300
400
500
600
700
0:00 6:00 12:00 18:00 0:00
En
erg
y:
15
min
in
terv
al
2 MW demand
As Measured
Electric Energy [kw-hr]
Peak Demand: 2.53 MW
Daily Energy: 42,240 kw-hr
Modified Electric
Energy [kw-hr]
Net Grid Energy Input
1.5 MW GT, no net meter
Max turndown=70%
Peak Demand (6a-6p) = 0.33 MW
Daily Energy = 16,190 kw-hr
Application:
1.5 MW Turbine.
Assume max
turndown of 70%
No Export of
electricity to grid
Results:
-Mid-day peak
demand reduced 86%
-Daily Energy need
reduced 62%
-Vast Majority of
chilling load during
operation of turbine
met by absorption
chiller
© Advanced Power and Energy Program, 2011 23/29
Combined Heat and Power Installations in Data Center and Communications Facilities
Syracuse University Syracuse NY Microturbine 780 2009 Telecommunications Facility Burlingame CA Microturbine 120 2003
Chevron Accounting Center Concord CA Recip. Engine 3,000 1988
Guaranty Savings Building Fresno CA Fuel Cell 600 2004
Citibank West FSB Building La Jolla CA Microturbine 60 2005
QUALCOMM, Inc. San Diego CA Gas Turbine 11,450 1983/2006
WesCorp Federal Credit Union San Dimas CA Microturbine 120 2003
ChevronTexaco Corporate
Data Center San Ramon CA Fuel Cell 200 2002
Network Appliance Data
Center Sunnyvale CA Recip. Engine 825 2004
Zoot Enterprises Bozeman MT Recip. Engine 500 2003
First National Bank of Omaha Omaha NE Fuel Cell 800 1999
AT&T Basking Ridge NJ Recip. Engine 2,400 1995
Continental Insurance Data
Center Neptune NJ Recip. Engine 450 1995
Verizon Communications Garden City NY Fuel Cell 1,400 2005
Sources: Energy and Environmental Analysis, 2006;
The Role of Distributed Generation and Combined Heat and Power (CHP) Systems in Data Centers EPA/CHP Partnership, August 2007
Case Studies
© Advanced Power and Energy Program, 2011 24/29
Fuel Supply
What to do about fuel supply interruptions?
• In SoCAB, all generation will utilize natural gas. • Diesel gen sets restricted to 200 hours total per
year so not viable for general DG/CHP
applications.
• Natural gas supplies are generally not stressed with possible exception of high demand summer
when utility generators have priority
• However, what happens in the event of a disruption of natural gas supplies (earthquake,
fire)?
© Advanced Power and Energy Program, 2011 25/29
Fuel Supply
Alternative for combustion systems would be
“pseudo” natural gas
• Propane diluted with air to match Wobbe index of methane/natural gas.
• Propane is stored as liquid: • Large quantities of energy available in small volume • Vapor pressure at ambient is 80 – 150 psig. • suitable for use in many systems without the need for
gas compressors (and associated parasitic losses) in
crucial need periods.
• Long term storage on propane possible.
© Advanced Power and Energy Program, 2011 26/29
Fuel Supply
Alternative for combustion systems would be
“pseudo” natural gas
• Syracuse University Data Center uses such a system with Capstone Microturbines.
• Pierce College has similar system for microturbines as a designated emergency
response center.
• Camp Pendleton has (had) a similar system for base operations.
© Advanced Power and Energy Program, 2011 27/29
Fuel Supply
Application of diluted propane in fuel cells is more
complex.
• Questions of comparable reformation performance?
• Stored hydrogen works for PEM fuel cells but other systems (PAFC, MCFC, Solid Oxide) utilize
fuel reformation as an integral part of overall
system.
© Advanced Power and Energy Program, 2011 28/29
Grid Response
A DG/CHP system for power reliability must be
capable of operation in both grid parallel and
“island” modes.
• Not all DG systems can operate in both modes! • Speed of separation from the grid (< 1 cycle) • Stability of voltage control operation • Reconnection/synchronization with the grid upon
conclusion of outage: can take minutes
• Intelligence to determine if it is safe to reconnect.
© Advanced Power and Energy Program, 2011 29/29
Example
Syracuse University Data Center
• 12, 65 kW Capstone Microturbines • CCHP system (absorption chilling and heating) • Rear door cooling • DC Bus • “Hybrid” UPS configuration
• Generation when economically viable • Battery Back-up • Long term generation • Back-up fuel source (propane/air)
• Syracuse University Website: www.syr.edu/greendatacenter/GDC_facts.pdf
http://www.syr.edu/greendatacenter/GDC_facts.pdf
© Advanced Power and Energy Program, 2011 30/29
Example
Syracuse University Data Center (cont’d)
• Power delivery to facility Reliability: eight “9”s • 90% overall thermal efficiency possible • IT grade power
© Advanced Power and Energy Program, 2011 31/29
Questions?
Please feel free to contact us if you have any
questions:
Pacific Region Application Center /
UC Irvine Advanced Power and Energy Program:
Richard L. Hack – PE, CEM: 949-824-7302 x 122