+ All Categories
Transcript
  • 8/2/2019 Primavera P6 Portlets Index

    1/25

    Ten Six Consulting Presents

    Primavera P6 Portlet Index

    A Reference Guide to the P6 Dashboard Portlets

  • 8/2/2019 Primavera P6 Portlets Index

    2/25

    Primavera P6 Portlet Index

    2Copyright Ten Six Consulting LLC., 2012. All rights Reserved.

    Contents1.1 Available Portlets .......................................................................................................................... 3

    1.1.1 Schedule Performance Portlet .............................................................................................. 3

    1.1.2 Earned Value Performance Portlet ....................................................................................... 3

    1.1.3 Index Performance Portlet .................................................................................................... 4

    1.1.4 Project Statistics Portlet ........................................................................................................ 4

    1.1.5 Project Health Portlet ........................................................................................................... 5

    1.1.6 Project Notebooks Portlet .................................................................................................... 6

    1.1.7 Project Gantt Chart Portlet ................................................................................................... 6

    1.1.8 Resource Team Summary Portlet ......................................................................................... 7

    1.1.9 Open Requests for Resources Portlet ................................................................................... 8

    1.1.10 Resource Analysis Chart Portlet .......................................................................................... 10

    1.1.11 My Projects Portlet ............................................................................................................. 11

    1.1.12 My Activities Portlet ............................................................................................................ 12

    1.1.13 My Risks Portlet .................................................................................................................. 14

    1.1.14 My Issues Portlet ................................................................................................................. 16

    1.1.15 Communication Center Portlet ........................................................................................... 19

    1.1.16 My calendar ........................................................................................................................ 21

    1.1.17 Portfolio Views Portlets ...................................................................................................... 23

  • 8/2/2019 Primavera P6 Portlets Index

    3/25

    Primavera P6 Portlet Index

    3Copyright Ten Six Consulting LLC., 2012. All rights Reserved.

    1.1 Available Portlets1.1.1 Schedule Performance Portlet

    This portlet provides a shorthand project level view that shows symbols for To Date and Forecast at

    Completion summary metrics indicating a projects status based upon threshold values.

    1.1.1.1 Customization Settings for the Schedule Performance Portlet

    1.1.2 Earned Value Performance Portlet

    This portlet provides a shorthand project level view that shows symbols for To Date and Forecast at

    Completion summary metrics for Schedule and Labor Units indicating the earned value status of the

    projects.

  • 8/2/2019 Primavera P6 Portlets Index

    4/25

    Primavera P6 Portlet Index

    4Copyright Ten Six Consulting LLC., 2012. All rights Reserved.

    1.1.2.1 Customization Settings for the Earned Value Performance Portlet

    1.1.3 Index Performance Portlet

    This portlet provides a project level summary view of the Schedule Performance Index (SPI), Cost

    Performance Index (CPI) and To Complete Performance Index (TCPI).

    1.1.3.1 Customization Settings for the Index Performance Portlet

    1.1.4 Project Statistics Portlet

    This portlet provides a customizable set of data columns that can be used to show project level data of

    your choosing in the table area.

  • 8/2/2019 Primavera P6 Portlets Index

    5/25

    Primavera P6 Portlet Index

    5Copyright Ten Six Consulting LLC., 2012. All rights Reserved.

    1.1.4.1 Customization Settings for the Project Statistics Portlet

    1.1.5 Project Health Portlet

    This portlet provides a pre-compiled narrative of the projects health based upon various indicators in

    the projects current progress to date, actual units and other factors.

    1.1.5.1 Customization Settings for the Project Health Portlet

    Select only, no sub-options for Project Health portlet.

  • 8/2/2019 Primavera P6 Portlets Index

    6/25

    Primavera P6 Portlet Index

    6Copyright Ten Six Consulting LLC., 2012. All rights Reserved.

    1.1.6 Project Notebooks Portlet

    This portlet offers Notebook Topics grouped by project. Click on the twisty buttons to see the expanded

    text within the Notebook topic.

    1.1.6.1 Customization Settings for the Project Notebook Portlet

    Select only, no sub-options for Project Notebook portlet.

    1.1.7 Project Gantt Chart Portlet

    This portlet provides a view of the portfolio projects in the form of a simple Gantt chart. It includes a

    tool bar allowing you to open a selected project, filter the project list, modify the columns displayed,

    modify the time scale and print.

    Projects can be expanded using the + button in the ID column to reveal project milestones.

  • 8/2/2019 Primavera P6 Portlets Index

    7/25

    Primavera P6 Portlet Index

    7Copyright Ten Six Consulting LLC., 2012. All rights Reserved.

    1.1.7.1 Customization Settings for the Project Gantt Chart Portlet

    Select only, no sub-options for Project Gantt Chart portlet.

    1.1.8 Resource Team Summary Portlet

    This portlet provides a list of the people in the selected resource team. It also lists their role and the

    number of projects to which they are assigned. You can click on the resources name to switch to a

    Usage view and see a histogram or spreadsheet of utilization.

    1.1.8.1 Customization Settings for the Resource Team Summary Portlet

    Select only, no sub-options for Resource Team Summary portlet.

    The resources being displayed in this portlet are controlled by the selected Resource Team. To select

    the team you wish to view, click on the Select a resource team: fields select button.

  • 8/2/2019 Primavera P6 Portlets Index

    8/25

    Primavera P6 Portlet Index

    8Copyright Ten Six Consulting LLC., 2012. All rights Reserved.

    1.1.9 Open Requests for Resources Portlet

    This portlet provides a list of open requests for resources (generated by role assignments made within

    projects) that allows a functional manager to replace the request with an appropriately skilled person.

  • 8/2/2019 Primavera P6 Portlets Index

    9/25

    Primavera P6 Portlet Index

    9Copyright Ten Six Consulting LLC., 2012. All rights Reserved.

    Clicking on a name in the list will take you to the Resource Staffing page where a resource assignment

    can be made.

    1.1.9.1 Customization Settings for the Open Requests for Resources Portlet

    Select Open Requests for Resources to use this portlet.

    Display:

    All projects will display open requests for all projects in the system.

    Projects based on dashboard filter will use the portfolio or project selected in the dashboards Filter

    by field.

    Organize Options are Role by Project, Project by Role and Role by Project by Project Codes.

    Role Team select your Role Team in this field.

    Project Code select a project code for further grouping using the Role by Project by Project Codes

    option in the Organize field.

  • 8/2/2019 Primavera P6 Portlets Index

    10/25

    Primavera P6 Portlet Index

    10Copyright Ten Six Consulting LLC., 2012. All rights Reserved.

    1.1.10 Resource Analysis Chart Portlet

    This chart will display the allocation for the selected resource in the Resource field. Each shade in the

    histogram represents the resources usage on a particular project.

    1.1.10.1 Customization Settings for the Resource Analysis Chart Portlet

    Select Resource Analysis Chart option.

    Chart Type select from Histogram, Stacked Histogram, Area Chart and Pie Chart.

    Display Units or Costs

    Show Limit and/or Allocation Limit

    Display resource allocation: - set the fields with a value in weeks ahead and previous to current data

    date.

    Color Theme Pastel or Primary Colors

  • 8/2/2019 Primavera P6 Portlets Index

    11/25

    Primavera P6 Portlet Index

    11Copyright Ten Six Consulting LLC., 2012. All rights Reserved.

    1.1.11 My Projects Portlet

    This portlet displays a list of the projects that meet the criteria set in the customize page. Clicking on

    the projects name will open the project, close any other open projects and then switch the view over to

    the Projects tab.

    1.1.11.1 Customization Settings for the My Projects Portlet

    Select the My Projects portlet.

    Show project where I:

    Have access rights have view access or better to the project

    Am assigned as a resource the resource associated with your login has been assigned to one or more

    activities in the project.

    Am the Project Owner have been selected as the project owner in the Project Owner field of the EPSsGeneral Tab. See following figure:

  • 8/2/2019 Primavera P6 Portlets Index

    12/25

    Primavera P6 Portlet Index

    12Copyright Ten Six Consulting LLC., 2012. All rights Reserved.

    Above example: project owner has been set in the General tabs Project Owner field.

    1.1.12 My Activities Portlet

    This portlet displays a list of activities you are assigned to in the system; grouped by project. Click the

    twisty button to see the details below each project. Clicking on the Activity name link will switch you to

    the Projects tab in a page called Details of .

  • 8/2/2019 Primavera P6 Portlets Index

    13/25

    Primavera P6 Portlet Index

    13Copyright Ten Six Consulting LLC., 2012. All rights Reserved.

    1.1.12.1 Customization Settings for the My Activities Portlet

    Set the number of days ahead you wish to include for activities you are scheduled to work on. This is n

    days from the current data date.

  • 8/2/2019 Primavera P6 Portlets Index

    14/25

    Primavera P6 Portlet Index

    14Copyright Ten Six Consulting LLC., 2012. All rights Reserved.

    1.1.13 My Risks Portlet

    This portlet shows any risks in the project portfolio that you own or have other criteria selected for

    viewing it. Risks are grouped by project.

    Clicking on the risk name will open the Risks page of the Projects tab.

  • 8/2/2019 Primavera P6 Portlets Index

    15/25

    Primavera P6 Portlet Index

    15Copyright Ten Six Consulting LLC., 2012. All rights Reserved.

    1.1.13.1 Customization Settings for the My Risks Portlet

    Use the Customize link to access the Customize Risks dialog. Select from columns for the table and

    include risks based upon the selected criteria in the Filter tab.

  • 8/2/2019 Primavera P6 Portlets Index

    16/25

    Primavera P6 Portlet Index

    16Copyright Ten Six Consulting LLC., 2012. All rights Reserved.

    1.1.14 My Issues Portlet

    This portlet displays a list of the issues available to you based upon criteria set in the Customize page.

    The portlet is grouped by project. Clicking on the twisty button displays the issue name in the rows

    below.

    Clicking on the issue name link will open the Issues page of the Projects tab.

    1.1.14.1 Customization Settings for the My Issues PortletColumns choose the columns to display in the portlet.

  • 8/2/2019 Primavera P6 Portlets Index

    17/25

    Primavera P6 Portlet Index

    17Copyright Ten Six Consulting LLC., 2012. All rights Reserved.

  • 8/2/2019 Primavera P6 Portlets Index

    18/25

    Primavera P6 Portlet Index

    18Copyright Ten Six Consulting LLC., 2012. All rights Reserved.

    Filter

    Group

  • 8/2/2019 Primavera P6 Portlets Index

    19/25

    Primavera P6 Portlet Index

    19Copyright Ten Six Consulting LLC., 2012. All rights Reserved.

    Chart

    1.1.15 Communication Center Portlet

    This portlet shows you the resources that meet the criteria in the customization settings, and allows you

    e-mail people by selecting them in the Name list.

  • 8/2/2019 Primavera P6 Portlets Index

    20/25

    Primavera P6 Portlet Index

    20Copyright Ten Six Consulting LLC., 2012. All rights Reserved.

    Selecting the check box at the project level selects all the resources working on that project.

    1.1.15.1 Customization Settings for the Communication Center Portlet

  • 8/2/2019 Primavera P6 Portlets Index

    21/25

    Primavera P6 Portlet Index

    21Copyright Ten Six Consulting LLC., 2012. All rights Reserved.

    1.1.16 My calendar

    This portlet shows you a list of activities, grouped by projects, that you are assigned to work on during

    the period selected in the calendar area.

    Navigate the calendar weeks and months to see what projects and activities you have been scheduled to

    work on.

    Clicking on the twisty button on the project row will open the activity list below.

    Clicking on the activity name link will open the Details of page where you can examine

    the activity dates and other details.

  • 8/2/2019 Primavera P6 Portlets Index

    22/25

    Primavera P6 Portlet Index

    22Copyright Ten Six Consulting LLC., 2012. All rights Reserved.

    1.1.16.1 Customization Settings for the My Calendar Portlet

  • 8/2/2019 Primavera P6 Portlets Index

    23/25

    Primavera P6 Portlet Index

    23Copyright Ten Six Consulting LLC., 2012. All rights Reserved.

    1.1.17 Portfolio Views Portlets

    Portfolio Views portlets offer a wide range of options for the contents of each portlet you add to the

    dashboard.

    There are thirty existing Portfolio views to choose from with further sub-options for customizing the

    portlet. This means there are literally dozens of combinations of data you can display with these

    portlets. The categories for a portfolio view include Bubble Charts, Histograms, Pie Charts, Scorecards,

    Side-by-side Histograms and Stacked Histograms, each with a variety of sub-options.

    You can add or subtract portfolio views as needs demand.

    1.1.17.1 Customization Settings for the Portfolio Views Portlets

    Use the Add option to add new Portfolio View portlets to the list. Each one added is automatically

    placed in the list and given a number.

  • 8/2/2019 Primavera P6 Portlets Index

    24/25

    Primavera P6 Portlet Index

    24Copyright Ten Six Consulting LLC., 2012. All rights Reserved.

    Each Portfolio View added has a set of options to further configure the portlets content and appearance.

  • 8/2/2019 Primavera P6 Portlets Index

    25/25

    Primavera P6 Portlet Index

    25

    1.1.17.2 More Examples of Portfolio View PortletsBelow: Are we doing the right projects? bubble chart and Cost by Plan Pie Chart portlet examples

    Below: Spend by Location and Spend by Phase portlet examples.

    Below: Spend by Sponsor, by Location and Budgetary Scorecard portlet examples.