Project – RVPN Project Closure
End User Manual – Project System
2016-11-29 1
1.1. Project Closure A project has three stages of closure in SAP.:-
1. Techincally Complete (TECO) 2. Settlement – To be done by Accounts division 3. Capitalization - To be done by Accounts division
Prerequisites of Proejct Closure:-
1. All the WBS elements like T&C, CIVIL, PLCC etc., status must be in TECO (Technically Complete). 2. Remaining budget at Level 1 WBS element must be transferred to the lowest level Position-ID which
has a link to Level 1 WBS element. 3. All the financial entries must be closed.
Prerequisites for TECO (Technically Complete) A project is termed as Technically complete when no work is pending related to project. .It results in
1. No material procurement i.e. no material Purchase Requisition, Purchase Order can be raised. 2. No material can be transferred to project. 3. There should not be any open commitemts like PR (Purchase Requisition), PO (Purchase Orders)
against the WBS Elements like T&C, CIVIL, PLCC etc. 4. All the materials have to be issued against the project. There should not be any material left out at
each WBS Element like T&C, CIVIL, PLCC etc. This cab be checked by using T-Code: MBBS 5. Service entry sheet for external services must be completed. There should not be any open service
PO against the WBS Elements like T&C, CIVIL, PLCC etc. 6. We must have to set system status to TECO for each WBS Element like T&C, CIVIL, PLCC etc.
individually.Also it is pssoible to closed any of the WBS element individually. Please note that T&C,Civil,PLCC WBS element should be closed by respective wings only.
7. Once all the WBS has been closed by the respective wings then the complete project shall be closed by T&C.
Importance and Application of TECO status
1. After setting system status to TECO for each WBS Element like T&C, CIVIL, PLCC etc., costs can be booked against the WBS Elements but the system will give a warning message that means we can do financial entries / financial postings.
2. After setting system status to TECO for each WBS Element like T&C, CIVIL, PLCC etc., new commitments in the form of PR/PO cannot be made for that WBS element.
Following process steps need to be carried out for setting system status to TECO for each WBS Element like T&C, CIVIL, PLCC etc.
Project – RVPN Project Closure
End User Manual – Project System
2016-11-29 2
1.1.1. Project Builder: Project CGSS/15.04
Step Action
(1) Clicking the menu item executes it.
Project – RVPN Project Closure
End User Manual – Project System
2016-11-29 3
1.1.2. Project Builder: Project CGSS/15.04
Step Action
(1) Clicking the Set menu item executes it.
Project – RVPN Project Closure
End User Manual – Project System
2016-11-29 4
1.1.3. Project Builder: Project CGSS/15.04
Step Action
(1) Click
.
Project – RVPN Project Closure
End User Manual – Project System
2016-11-29 5
1.1.4. Performance Assistant
Step Action
(1) Click .
1.1.5. Project Builder: Project CGSS/15.04
Step Action
(1) Status for WBS Element was set TECO.
Project – RVPN Project Closure
End User Manual – Project System
2016-11-29 6
Step Action
.
1.1.6. Project Builder: Project CGSS/15.04
Step Action
(1) Click .
Project – RVPN Project Closure
End User Manual – Project System
2016-11-29 7
1.1.7. Project Builder
Project – RVPN Project Closure
End User Manual – Project System
2016-11-29 8
1.1.8. SAP Easy Access
Step Action
(1) Input Transaction Code CJ88 and Click OR Press Enter key
1.1.9. Set Controlling Area
Step Action
Input Controlling Area as 1000 always
(1) Click Continue OR Press Enter key
Project – RVPN Project Closure
End User Manual – Project System
2016-11-29 9
1.1.10. Actual Settlement: Project/WBS Element/Network
Step Action
Input WBS Element Check With hierarchy, With orders Input Settlement period, Posting period, Posting type Keep the default setting for Processing Type and check on Test Run (primarily execute with Test Run and after that disable check on Test Run) Check onDetail List, Check trans. data
(1) Click Execute .
Project – RVPN Project Closure
End User Manual – Project System
2016-11-29 10
1.1.11. Actual Settlement: Project/WBS Element/Network Basic list
Step Action
Settlement executed successfully with check on Test Run
Project – RVPN Project Closure
End User Manual – Project System
2016-11-29 11
Step Action
(1) Click on back button
1.1.12. Actual Settlement: Project/WBS Element/Network
Step Action
(1) Uncheck on Test Run
Project – RVPN Project Closure
End User Manual – Project System
2016-11-29 12
1.1.13. Actual Settlement: Project/WBS Element/Network
Step Action
(1) Click Execute .
Project – RVPN Project Closure
End User Manual – Project System
2016-11-29 13
1.1.14. Actual Settlement: Project/WBS Element/Network Basic list
Step Action
Settlement executed successfully without check on Test Run
(1) Click Detail lists .
Project – RVPN Project Closure
End User Manual – Project System
2016-11-29 14
1.1.15. Actual Settlement: Project/WBS Element/Network Detail list
Step Action
(1) Click on back button .
Project – RVPN Project Closure
End User Manual – Project System
2016-11-29 15
1.1.16. Actual Settlement: Project/WBS Element/Network Basic list
Step Action
(1) Click on back button .
Project – RVPN Project Closure
End User Manual – Project System
2016-11-29 16
1.1.17. Actual Settlement: Project/WBS Element/Network
Project – RVPN Project Closure
End User Manual – Project System
2016-11-29 17