Environmental IssuesDelay in completion of:
Dry ash evacuation system
Effluent Disposal SystemAmbient air Quality
Reasons:
Delay in material supply
Non performance by agency
8/12/2019 Risk Profile Redesigned
3/31
Environmental IssuesAction for mitigation of risk:
Direct procurement of critical material from Sub
vendors, Intervention to get the agency to get work done
through different working agencies at site,
Continuous monitoring and follow up with agencies.
8/12/2019 Risk Profile Redesigned
4/31
COAL SHORTAGEIssues with
Coal Tie up and availability
Coal UnloadingReasons
Delays in development of linked mines
Delay in Development of Indian Railway Network Delay in Development of Wagon Tippler
commissioning
8/12/2019 Risk Profile Redesigned
5/31
COAL SHORTAGEAction for mitigation of risk:
Getting coal through E-auction
Use of imported coal Outsourcing of mining operations
Issue taken up at CM(Bihar) level for environmentalclearance
8/12/2019 Risk Profile Redesigned
6/31
Water ShortageIssues with
Raw water availability
Reasons Delay in construction of Intake Well/Raw Water pump
house
Seasonal shortage of water
Excessive siltation and change in river course
8/12/2019 Risk Profile Redesigned
7/31
Water ShortageAction for mitigation of Risk
Intake well sinking completed
Raw water commissioning expected by June 15 Course of Ganga being controlled by Dredging
8/12/2019 Risk Profile Redesigned
8/31
SCHEDULE GENERATIONIssues with
Variable Charges, Merit Order
Reasons Unavailability of coal from linked coal mine
Site compelled to procure costly coal through e-auction
Large distance from mines
8/12/2019 Risk Profile Redesigned
9/31
SCHEDULE GENERATIONAction for mitigation of Risk
Regular follow up for expediting the development of
linked mines
Regular follow up with railways for early completion oforiginal rail transportation route envisaged in FR.
8/12/2019 Risk Profile Redesigned
10/31
Delay in execution by agenciesIssue
Delay w.r.t L2 network
Reasons
Financial problems of agencies Inadequate mobilization by agency
Shortage of skilled labor
Law and order issues
8/12/2019 Risk Profile Redesigned
11/31
Delay in execution by agencies
Action for mitigation of risk
Termination notice to be served to TPE
Enlistment of vendors with proven track recordsAward of erection contract is planned after
termination notice is served to TPE
Training and recruitment of ITI graduates is being
done.
8/12/2019 Risk Profile Redesigned
12/31
RISK PROFILE OF
NORTH KARANPURAPOWER PROJECT
8/12/2019 Risk Profile Redesigned
13/31
Problem in Land Availability
Reason Delay in finalization of R&R package
Delay in physical possession of land
Poor land record with state governmentAction for mitigation of risk
Physical possession started with disbursement of R&Rcompensation and barricading by Chain link fencing
of Main Plant
8/12/2019 Risk Profile Redesigned
14/31
Problem in transporting materials to the site
Reason Difficulty in receiving materials due to rail and road
connectivity problem
Action for mitigation of Risk
RCD, Govt. of Jharkhand is entrusted toconstruct/strengthen road of 110 km and Rs 250 crs
advance money deposited to RCD, GoJ.
8/12/2019 Risk Profile Redesigned
15/31
Water Shortage expected
Reason Delay in readiness of water system
Action taken for mitigation of risk
Govt. of Jharkhand is to construct the dam such thatwater is available by March 2017.
8/12/2019 Risk Profile Redesigned
16/31
Delay in availability of Construction
PowerSupply line to be constructed by DVC on deposit basis
Reason for Delay
Forest clearance is yet to be obtained by DVC Sub agency of DVC has raised certain claims due to
delay which is under negotiation.
8/12/2019 Risk Profile Redesigned
17/31
RISK PROFILE OFKAHALGAON
STATION
8/12/2019 Risk Profile Redesigned
18/31
Less efficiency w.r.t normative parameters
Reasons:
Frequent tripping due to backing down
Higher Heat Rate
Higher APC
Action for mitigation of Risk Reduce Specific Oil Consumption by start up time
reduction
Activities like Oxygen Optimization, BFP catridge
replacement, Flue gas duct repair and condenser waterbox cleaning being taken up to improve HR
8/12/2019 Risk Profile Redesigned
19/31
Less efficiency w.r.t normative parameters
Action for mitigation of Risk
Coal feeding to bunkers through reclamation to avoidbunker choking
Reduction of APC by improving utilization factor ofCHP, Stage I units Feed Regulating Stations.
Differential Pressure optimization and ID fan margin
improvement.
8/12/2019 Risk Profile Redesigned
20/31
Lower PLFReasons
High partial loading due to equipment problem
Coal shortage
Lower merit order
8/12/2019 Risk Profile Redesigned
21/31
Lower PLF
Action for mitigation of risk Preventive and predictive maintenance planning
More coal being lifted with proactive persuasion with
CIL Optimization of ECR by discouraging high specific
cost coal, use of MGR/RJ coal with restricted blending,raniganj coal of G6 grade to be preferred instead of
G5/G4/G3 coal as there is steep rise in price.
8/12/2019 Risk Profile Redesigned
22/31
Under recovery of O&M Charges
Reasons
Higher repair and maintenance cost
Higher employee cost excluding PRP
Higher CC expenses
8/12/2019 Risk Profile Redesigned
23/31
ANNEXURE II
DESCRIPTION2012-13 2013-14
MOU Actual MOU Actual Variation Reason for Deviation
EMPLOYEE COST 14519 16203 15423 19400 -3977
Increase in 44 No. of employees,resulting in increase in Sal
& wages by Rs. 4.6 crs. Increase in winter Liveries &
uniform exps by Rs. 1.78 crs, Contribution to Pension
Scheme Rs.28.41crs.Increase in medical exps Rs.1.27crs.
REPAIRS &
MAINT.12707 17089 14751 17943 -3192
1.BMD: Matls.Rs.1510 lakh:-
A). Higher consumption of mill spares due to poor quality
of coal- excess consm.Rs. 1420 Lakh. B). St-I APH tubes:
Excess consm: Rs.40 Lakh. C). Coal Feeder#6G: Rs.50Lakh.
2. CHP: Rs. 830 lakh :-
A). Excess Matls. Cost: Rs.718 Lakh mainly due to
conv.belts (Rs.550 Lakh, B). Increased services cost: Rs.
112 lakh.
3. O&M-CIVIL: Rs. 240 Lakh:- Excess Expenditure due to
A).Construction of peripheral road from gate no.1 to
Ekchari gate, B).Paving & Gravelling works for SWYD,C).Roller compacted road from Ekchari gate to Koa nala
bridge, D).Water-proofing treatment of Admn. Bldg.,
Canteen bldg., Auditorium roofs, E).FRP Lining in DM Plant,
F).Checking, testing and repairing of St-II coal bunkers,
G).Development of Dry ash silo area st-II.
Detail of BREAK up of O&M Cost
Detail of BREAK up of O&M Cost ANNEXURE II
8/12/2019 Risk Profile Redesigned
24/31
DESCRIPTION 2012-13 2013-14
MOU Actual MOU ACTUAL Variation
REPAIRS &
MAINT.12707 17089 14751 17943 -3192
4. MGR: Rs 258 Lakh:- i). Excess cost of Loco
overhauling Rs.125 Lakh, ii). PSC sleepers: Rs.54
Lakh, iii).Left & right turn out sets : Rs. 60 Lakh
returned to RITES against past loan, iv). Additional
job: Trip inspection for RJA rakes: Rs. 19 Lakh.
5. Ash Brick Manufacturing : Rs 140 Lakh
6. Dry Ash System Maint. : Rs 120 Lakh
7. Township : Rs 90 Lakh;- i). Ash /earth filling near
stadium-Rs.60Lakh, ii). Painting of schools & various
bldgs. Rs.30 Lakh.
STATION
OVERHEAD6509 6960 7215 6948 267
Total 33735 40252 37389 44292 -6903
Detail of BREAK up of O&M Cost ANNEXURE II
8/12/2019 Risk Profile Redesigned
25/31
Problem in Scheduling of Power
Reasons Lower merit order
Action for mitigation of risk
Efforts being made to reduce ECR by blending, andusing different coal bunkers at different TOD,improving HR/APC/SOC.
8/12/2019 Risk Profile Redesigned
26/31
Environmental Problems
Issues Emission high
Problem in Ash Utilization
Reasons
Design inadequacy of ESP/AGFC
Less Ash utilization due to location constraints
8/12/2019 Risk Profile Redesigned
27/31
Environmental Problems
Action for mitigation of risk
Permanent flue gas conditioning system has beeninstalled in U#1 & U#4. For U#2 & U#3 installationwork is under progress
ESP parameters recorded and corrective actions arebeing taken for deviations
Checks during O/H:
Action for mitigation of risk(Ash Utilization initiatives)
8/12/2019 Risk Profile Redesigned
28/31
Action for mitigation of risk(Ash Utilization initiatives)
Initiatives for Fly ash Brick Sector: Presently 25 parties lifting 18000 MT/month of f ly ash from ash silo in free of cost
for use in Fly ash brick manufacturing against only one party in last year. Fly ash is being issued within 14 days in every case after submission of application
with proper documents. 25 more parties/persons applied for fly ash in this regard are in pipeline in
different stage Application format and procedure is made available in BSPCB site for more
accessibility. Initiatives for Clay ash Brick Sector A Demonstration project for ash utilization in clay-ash brick manufacturing has
been organized to raise confidence among brick manufacturers for use of ash inbrick manufacturing and to popularise the clay ash brick in place of clay brick. Workshops for Brick kiln owners/ ash brick manufacturers for using ash in
brick manufacturing. 15000 MT pond Ash is being transported on free of cost to Brick klin.
Other Initiatives for Maximizing Ash Utilization Dedicated Road for ash transportation is constructed from NTPC gate to
Ekchari, bypassing Kahalgaon town from May-2013. Wind breaking wall has been constructed and water sprinkling is being done
on regular basis at Kahalgaon railway siding. Ash transportation in Jumbo bags directly by railway successfully done on
12.09.2013 on trial basis and now it is streamlined. It is being done by oneparty, Railway is being contacted for other parties. This process iseconomical and environment friendly
Ash Utilization through low land filling for public utility land, compilation is
in advance stage. First phase quantity will be 2.5LMT.
8/12/2019 Risk Profile Redesigned
29/31
Safety and Security problem
Reason
Problem in implementation of safety norms
Problem in security of installationsof stations
Action being taken for mitigation of risk Cases investigated, recommendations discussed in
daily meeting.
Awareness training programs
Site visits to check safety norms
8/12/2019 Risk Profile Redesigned
30/31
Availability of Ash DykeIssues
Availability of Land Space
Inadequate ash utilization
High Ash Content
ReasonsWork in Lagoon III D not started due to Local
Resistance
Capacity of Lagoon III A/B and C very low
High Ash Content in Lalmatia coal
8/12/2019 Risk Profile Redesigned
31/31
Availability of Ash DykeAction for mitigation of risk
Possibilities for buttressing is being explored forLagoon II
Matter of Local resistance taken with Local
Administration Dry ash extraction system for Unit# 3 & 4 to be
tendered. Cost estimation under revison.