+ All Categories
Transcript
  • (RISK.03)Integrated Cost and Schedule Risk

    Analysis: A Draft AACE Recommended Practice

    Dr. David T. Hulett

  • 2

    Author Biography• David T. Hulett, Hulett & Associates, LLC• Degree:

    – Ph.D.

    • University:– Stanford University

    • Years of Experience:– 20+

    • Professional Field:– Project risk analysis and management, project scheduling

  • • The purpose of integrated analysis of schedule and cost risk to estimate the appropriate level of cost contingency reserve on projects

    • The main contribution is to include the impact of schedule risk on cost risk and hence on the need for cost contingency reserves

    • Additional benefits include the prioritizing of the risks to cost, some of which are risks to schedule so that cost risk mitigation may be conducted in a cost-effective way.

    Purpose

  • Linkage of Schedule and Cost Risk• Some resources such as labor, rented

    equipment and level-of-effort support by the project management team will cost more if they are engaged on the project longer than planned because activities take longer than expected

    • Risks to schedule will also be risks to the cost of these resources

  • Platform / Risk ModelResource-Loaded Schedule

    • The platform of this analysis is a resource-loaded project schedule– One may use a summary schedule or a

    detailed project schedule• The budget (without contingency) must be

    assigned to the activities – Using resources that may be summary in

    nature (e.g., construction, detailed engineering or procurement) or detailed

  • Monte Carlo Simulation• Monte Carlo simulation is the standard

    approach to discovering the impact of multiple risks on the overall project schedule or cost risk

    • Simulating a resource-loaded project schedule derives both schedule risk and the cost risk implication in the same simulation

    • The results also produce a list of risks that are prioritized through the risk model, for risk mitigation

  • Inputs• A best-practice project schedule, basically a

    schedule following recommended practice CPM scheduling. A schedule of 300 – 1,000 activities can summarize and represent a large project in this strategic analysis

    • A contingency-free cost estimate, meaning that line items do not have contingency padding built in and there is no below-the-line contingency included

    • Good-quality risk data – usually risks that have been identified during a qualitative risk analysis of the project leading to a list of prioritized risks are characterized by their probability and impact ranges

  • Outputs• How likely are the project plan’s cost and schedule

    targets to be met given the risk that may affect that plan?

    • How much contingency of time and cost needs to be provided to meet the risk threshold of the project management or other stakeholders?

    • Which risks are most important to the achievement of the project schedule and cost estimate?

    • A unique and useful result is the finding of joint time-cost risk result joint probability distribution, often shown as a scatter diagram of time-cost points showing the possibility of meeting both time and cost objectives jointly

  • Best Practice CPM Schedule 1• All work needed to complete the project must

    be represented in the schedule. The schedule should relate to the WBS

    • There should not be any “danglers.” This means that each activity needs a predecessor to its start date and a successor from its finish date

    Activity 101Predecessor Successor

    F-S or S-S F-S or F-F

  • • The schedule should not rely on date constraints or fixed lags between activities

    • The schedule should be recently statused• The schedule should have resources costed and

    assigned to activities– Summary resources are OK– The purpose of these resources is to get the costs on

    the right activities, not to level resources– Sometimes we create hammocks and apply summary

    resources to those

    10

    Best Practice CPM Schedule 2

  • Example of Resources Used

    11

  • Risk Data Inputs• Risk events may or may not happen, but if they

    do happen they will have a positive or negative impact on the cost or schedule or both– Risk events’ probabilities are < 100%– They have uncertain impacts as well

    • Uncertainties include ambiguities such as estimating error and uncertainties such as the level of labor productivity or the price of steel. – These uncertainties are 100% likely to occur but their

    impact on the project cost or schedule is uncertain

    12

  • Collecting Risk Data

    • The input risk data are usually collected in risk workshops or interviews. – In workshops the people may be influenced

    by strong personalities or people in higher positions in the organizations.

    – In individual interview sessions, usually protected by promises of confidentiality, people can discuss their concerns and make estimates without feeling the influence of others

    13

  • Risk Drivers (aka Risk Factors)

    • The risks’ impacts are specified by 3-point estimates– In Risk Drivers (Risk Factors) the impacts are ranges

    of multiplicative factors. The 3-point estimate of impact is converted to a triangular distribution

    • Risks are applied to activities– A schedule risk will multiply the duration of the activity

    that it is assigned to – For any iteration the software selects an impact at

    random from the distribution and uses that factor for that iteration

    14

  • Examples of Three Risk Types

    • Schedule duration estimate immaturity is an ambiguity. It has 100% probability of occurring and its impact range is both good and bad

    • Construction labor productivity is an uncertainty that, compared to the assumption, could be lower or higher

    • The possibility of quality, key personnel unavailability is a risk event– It may or may not occur– In this case its impact is never to the good

    15

  • Uncertainty and Ambiguity Risks Occur 100% of the time

    16

    Schedule inaccuracy operates 100% of the time (all iterations). On a construction activity of 100 days duration the results are triangularThe construction labor productivity risk would look similar to this figure

    95 100 105 110 115 120

    Distribution (start of interval)

    0

    20

    40

    60

    80

    100

    120

    140

    160

    180

    200

    220

    240

    Hits

    0% 95

    5% 99

    10% 100

    15% 101

    20% 102

    25% 103

    30% 104

    35% 104

    40% 105

    45% 106

    50% 106

    55% 107

    60% 108

    65% 109

    70% 109

    75% 110

    80% 111

    85% 113

    90% 114

    95% 116

    100% 120

    Cum

    ulat

    ive

    Freq

    uenc

    y

    0010 - Construction : Duration

  • Risk Events are Described by their Probability and Impact

    • If probability is < 100%, the risk will occur in that percentage of iterations, chosen at random

    • On an iteration if the risk occurs, a factor chosen at random from its impact range will multiply the duration of the activities to which it is assigned

    • If the risk does not occur the multiplicative factor is 100% with no effect on duration

    17

  • Risk Events occur with a Probability < 100%

    18

    100 102 104 106 108 110

    Distribution (start of interval)

    0

    100

    200

    300

    400

    500

    600

    700

    800

    900

    Hits

    0% 100

    5% 100

    10% 100

    15% 100

    20% 100

    25% 100

    30% 101

    35% 102

    40% 103

    45% 103

    50% 104

    55% 104

    60% 105

    65% 105

    70% 105

    75% 106

    80% 106

    85% 107

    90% 107

    95% 108

    100% 110

    Cum

    ulat

    ive

    Freq

    uenc

    y

    0010 - Construction : Duration Here a risk event, the possible unavailability of quality key staff, occurs 70% of the time. Hence, in 30% (900) of the 3,000 iterations the original duration of construction, 100 days, is correct. In 70% (2,100) of the iterations, the duration is longer than 100 days as a triangle

  • Risk Driver Strategy• Risks are usually higher-level strategic

    risks rather than tactical or technical risks• Data about risks is derived from in-depth

    interviews• A risk is usually assigned to several

    activities• An activity may have several risks

    assigned

    19

  • A Construction Activity withThree Risks Assigned

    2090 100 110 120 130 140

    Distribution (start of interval)

    0

    10

    20

    30

    40

    50

    60

    70

    80

    90

    100

    110

    120

    130

    140

    150

    160

    Hits

    0% 90

    5% 99

    10% 101

    15% 103

    20% 105

    25% 106

    30% 108

    35% 109

    40% 110

    45% 111

    50% 112

    55% 113

    60% 114

    65% 115

    70% 117

    75% 118

    80% 120

    85% 122

    90% 124

    95% 127

    100% 143

    Cum

    ulat

    ive

    Freq

    uenc

    y

    0010 - Construction : Duration

    The interaction of the three risks produces the expected histogram.In traditional 3-point risk estimating, the analyst and interviewees must approximate the result of three risks on duration. The Risk Driver analysis computes the distribution.

  • Risk Drivers Avoid the Need to Estimate the Correlation Coefficient

    © 2009 Hulett & Associates LLC

    21

    Activity A Activity B

    Activities A and B Correlation is Calculated to be 100%

    In the traditional approach to risk analysis, the correlation coefficient has to be estimated.

    Risk Drivers model how correlation occurs and the coefficient is a natural result of the model

    Risk #1P = 50%, Factors

    .95, 1.05, 1.15

  • Risk Factors Model How Correlation Occurs (2)

    © 2009 Hulett & Associates LLC

    22

    Risk #1P = 50%, Factors

    .95, 1.05, 1.15

    Activity A Activity B

    Activities A and B Correlation is Calculatedto be 48%

    Risk #2P = 25%, Factors

    .8, .95, 1.05

    Risk #3P = 45%, Factors

    1.0, 1.1, 1.2

    Risk Drivers model correlation as it is caused in the projectbased on the common (Risk # 1) and confounding (Risks # 2 and #3) risks

    affecting pairs of activitiesThe correlation coefficient is the result, not the assumption

  • Integrating Cost and Schedule Risk using Risk Drivers

    • The risks to activity durations will affect– Durations and completion dates– Costs of labor-type resources

    • For each iteration the cost as well as the finish date is calculated

    • Enhanced results include– Scatter diagrams (joint distributions) of time

    and cost– Probabilistic cash flows by month

    23

  • Schedule Risk applied to Activity with Labor Resource – Cost/Time Scatter

    Risk ID Risk Probability Minimum Most Likely Maximum

    1 Labor Productivity may be Uncertain 100% 95% 105% 120%

    24

    $600,000 $620,000 $640,000 $660,000

    Distribution (start of interval)

    0

    100

    200

    300

    400

    500

    600

    700

    Hits

    0% $585,000

    5% $596,000

    10% $600,000

    15% $603,000

    20% $606,000

    25% $609,000

    30% $611,000

    35% $613,000

    40% $615,000

    45% $617,000

    50% $619,000

    55% $621,000

    60% $623,000

    65% $626,000

    70% $628,000

    75% $631,000

    80% $634,000

    85% $638,000

    90% $642,000

    95% $647,000

    100% $660,000Cu

    mul

    ativ

    e Fr

    eque

    ncy

    RP one-pathEntire Plan : Cost

    0%

    0% 49%

    51%

    10/08/2012 20/08/2012 30/08/2012 09/09/2012 19/09/2012 29/09/2012 09/10/2012 19/10/2012

    Entire Plan: Finish

    51%

    $590,000

    $600,000

    $610,000

    $620,000

    $630,000

    $640,000

    $650,000

    $660,000

    Entir

    e P

    lan:

    Cos

    t

    51%

    RP one-path

    10/ 09/ 2012

    $619,000

    Deterministic Point Inside both limits Outside both limits

    Schedule Risk

  • Effect on Cost Risk of Adding Burn Rate Uncertainty

    25$580,000 $590,000 $600,000 $610,000 $620,000 $630,000 $640,000 $650,000 $660,000 $670,000 $680,000

    0%

    10%

    20%

    30%

    40%

    50%

    60%

    70%

    80%

    90%

    100%

    Cum

    ulat

    ive

    Prob

    abili

    ty

    Distribution AnalyzerRP one-path - Entire Plan - Cost RP one-path - Entire Plan - Cost

    8%

    9% 41%

    42%

    10/08/2012 20/08/2012 30/08/2012 09/09/2012 19/09/2012 29/09/2012 09/10/2012 19/10/2012

    Entire Plan: Finish

    51%

    $580,000

    $590,000

    $600,000

    $610,000

    $620,000

    $630,000

    $640,000

    $650,000

    $660,000

    $670,000

    $680,000

    Entir

    e Pl

    an: C

    ost

    50%

    RP one-path

    10/ 09/ 2012

    $624,453

    Deterministic Point Inside both limits Outside both limits

    Risk ID RiskDuration Impacts Cost Impacts

    Probability Minimum Most Likely Maximum MinimumMost Likely Maximum

    1 Labor Productivity may be Uncertain 100% 95% 105% 120% 95% 100% 110%

    Schedule, and Burn Rate Risk

    Schedule Risk Alone

  • Add Uncertainty in Procurement Costs

    • Equipment and material costs may be risky but not generally because their activities’ durations are uncertain

    • Putting risk factors on material-type resources causes the risk to be applied to the entire cost

    26

    Schedule Impact Factors Cost Impact Factors

    Risk ID Risk Probability Minimum Most Likely Maximum Minimum Most Likely Maximum

    1Labor Productivity may be Uncertain 100% 95% 105% 120% 95% 100% 110%

    2Suppliers may be busy 100% 100% 100% 100% 90% 105% 120%

  • Impact on Cost Risk of Adding Risk to Material Resources

    27$560,000 $570,000 $580,000 $590,000 $600,000 $610,000 $620,000 $630,000 $640,000 $650,000 $660,000 $670,000 $680,000 $690,000 $700,000 $710,000 $720,000 $730,0000%

    10%

    20%

    30%

    40%

    50%

    60%

    70%

    80%

    90%

    100%

    Cum

    ulat

    ive

    Prob

    abili

    ty

    Distribution AnalyzerRP one-path - Entire Plan - Cost RP one-path - Entire Plan - Cost RP one-path - Entire Plan - Cost

    16%

    16% 34%

    34%

    10/08/2012 20/08/2012 30/08/2012 09/09/2012 19/09/2012 29/09/2012 09/10/2012 19/10/2012 29/10/2012 08/11/2012

    Entire Plan: Finish

    50%

    $560,000

    $580,000

    $600,000

    $620,000

    $640,000

    $660,000

    $680,000

    $700,000

    $720,000

    Entir

    e Pl

    an: C

    ost

    50%

    RP one-path

    23/ 09/ 2012

    $640,372

    Deterministic Point Inside both limits Outside both limits

    Schedule, Burn Rate and Material Risk

    Schedule Risk Alone

    Schedule, and Burn Rate Risk

  • Simple Example: Construction Project

    28

    Cost Resources Risk Factors

  • We have Created and AssignedEight Risk Factors

    29

  • Basic Cost and Schedule Results

    30

    21-Dec-12 05-May-14

    Distribution (start of interval)

    0

    100

    200

    300

    400

    500

    600

    700

    Hits

    0% 19-Dec-12

    5% 27-Apr-13

    10% 25-May-13

    15% 13-Jun-13

    20% 03-Jul-13

    25% 18-Jul-13

    30% 01-Aug-13

    35% 14-Aug-13

    40% 28-Aug-13

    45% 08-Sep-13

    50% 20-Sep-13

    55% 02-Oct-13

    60% 16-Oct-13

    65% 29-Oct-13

    70% 14-Nov-13

    75% 30-Nov-13

    80% 16-Dec-13

    85% 06-Jan-14

    90% 03-Feb-14

    95% 23-Mar-14

    100% 02-Dec-14

    Cum

    ulat

    ive

    Freq

    uenc

    y

    AACEI Integrated Cost-Schedule RiskEntire Plan : Finish Date

    P-80 is 16 Dec 2013, a 7-month slip

    $600,000 $800,000 $1,000,000

    Distribution (start of interval)

    0

    200

    400

    600

    800

    Hits

    0% $537,199

    5% $619,334

    10% $636,168

    15% $648,572

    20% $658,705

    25% $667,247

    30% $675,521

    35% $683,271

    40% $692,139

    45% $699,319

    50% $706,146

    55% $713,313

    60% $721,955

    65% $730,838

    70% $740,066

    75% $749,866

    80% $760,750

    85% $775,498

    90% $792,533

    95% $819,295

    100% $1,008,966

    Cum

    ulat

    ive

    Freq

    uenc

    y

    AACEI Integrated Cost-Schedule RiskEntire Plan : Cost

    P80 is $760 million, a 22% reserve

  • Joint Cost-Schedule Distribution

    31

    7%

    6% 17%

    70%

    21-Dec-12 31-Mar-13 09-Jul-13 17-Oct-13 25-Jan-14 05-May-14 13-Aug-14 21-Nov-14

    Entire Plan: Finish

    76%

    $550,000

    $600,000

    $650,000

    $700,000

    $750,000

    $800,000

    $850,000

    $900,000

    $950,000

    $1,000,000

    Entir

    e Pl

    an: C

    ost

    77%

    AACEI Integrated Cost-Schedule Risk

    03-Dec-13

    $752,918

    Deterministic Point Inside both limits Outside both limits

    Joint C/S Distribution, Cross-hairs at 70% Joint Confidence Level

    Deterministic Plan

  • Probabilistic Cash Flow

    32

    Deterministic Cost: $624,220

    Det

    erm

    inis

    tic F

    inis

    h: 2

    9-Ap

    r-13

    21-Jan-11 01-May-11 09-Aug-11 17-Nov-11 25-Feb-12 04-Jun-12 12-Sep-12 21-Dec-12 31-Mar-13 09-Jul-13 17-Oct-13 25-Jan-14 05-May-14 13-Aug-14 21-Nov-14

    Time

    0

    200,000

    400,000

    600,000

    800,000

    1,000,000

    Cum

    ulat

    ive

    Deterministic Plan

    P-80

  • Prioritizing Risks To Cost

    33

    Risks to Cost in Priority Order at the P‐80P‐80

    ALL RISKS IN 760.8NO RISK 624.2Contingency Reserve at P‐80 136.6

    Risks Prioritized for Effect on CostActivity Duration Estimates are Inaccurate 39.2Site Conditions / Site Access may Slow Logistics 23.2Key Engineering Personnel may be Unavailable 18.4Cost Estimate is Inaccurate 14.9Capable Management may not be Assigned 13.4Equipment Suppliers may be busy 9.1Design Complexity may Challenge Engineers 3.4Environmental Agency may be Slow 0.1

    TOTAL Contingency Accounted For 121.6

    Some Interaction Effects are not Captured

    Prioritize risk mitigations using this table

  • QUESTIONS?

    David T. Hulett, Ph.D.Hulett & Associates, LLC

    Los Angeles, CA(310) 476-7699

    [email protected]

    34


Top Related