GULF DREDGING & GENERAL CONTRACTING Co.
Project Overview
RENOVATION AND EXPANSION OF SOUTH JETTY
Type of Contract
This contract is a lump sum contract
Scope of WorkScope of work of the project is to carryout dredging of the Al-Khafji
inner harbor and access channel and the renovation of the South Jetty and the construction of a new extension in order to enhance the daily operations. Also this Project will provide a larger materials yard adjacent to the loading and unloading area of heavy materials and safe berthing, metering, loading and unloading systems.
The dredging work includes widening of the existing navigable channel by 20 m in the inner part and 50 meters offshore, to a depth of (-6 m) CD, including final disposal of the quantity of about 800,000 m3 of soil.
1. The Scope of work for the project is divided into two parts.
.
PROJECT EXECUTION PLAN
GULF DREDGING & GENERAL CONTRACTING Co.
Project Overview
RENOVATION AND EXPANSION OF SOUTH JETTY
Part I is dealing with the Dredging of Al-Khafji Inner Harbor and Channel.
Part II is dealing with the work of Renovation and Expansion of South Jetty, Al-Khafji. The activities coming under Scope of Work (Part II) can be summarized as below.
Construction of Quay Wall for a length of 980 meters with Pre-cast Concrete Blocks
• Fixing of Fenders.• Fixing of 30 Ton capacity Bollards.• Backfilling and RCC Concrete Paving Works• Backfilling and Asphalt Paving Works• Re-location of existing Navigation Buoys.• Fixing of SSD Fencing • Construction of Control Room / Recreation Building• Construction of Guard House and Tide Gauge House• Construction of Public Toilets.• Construction of Septic Tanks.• Construction of Oil Collection Pits, Spill containment cover roof,
concrete trenchers, bulk and chemical mix foundation, concrete pipe supports, light poles foundations.
• Electrical, Mechanical and Instrumentation works.• Shifting of existing bulk and chemical mix from North to South Jetty.
PROJECT EXECUTION PLAN
GULF DREDGING & GENERAL CONTRACTING Co. RENOVATION AND EXPANSION OF SOUTH JETTY
DREDGING WORKS DREDGING PROCEDUREThe entire dredging area has been divided into 3 zones. Top priority has been allocated to dredging of zone-1 where quay wall construction activity will have to be progressed after completion of dredging work
Initially C.S.D Arefjan will be mobilized at cut – 1 in zone – 1 and continue dredging from cut1 to cut 3 and pump dredged material through shore connection-1 while Al-Kassar will be dredging area Al-Kassar 3 in zone 2. After completion of dredging of cut 3, Arefjan will commence dredging of cut 4 and pump dredged material through shore connection 2. Al-Kassar will shift position from area Al-Kassar-3 in zone 2 and commence dredging in area marked Al-Kassar-1 in zone 1 and continue dredging of trench and side slopes thereafter.
Pre-cast concrete block placing will commence after dredging equipment have moved at least 100 m away from construction site.
GULF DREDGING & GENERAL CONTRACTING Co. RENOVATION AND EXPANSION OF SOUTH JETTY
Quay Wall Construction
Geotechnical investigation
15 bore holes along the alignment of the quay wall to analyze the soil condition to determine suitability for the work
BH-1
BH-2
BH-3
BH-4
BH-5BH-6 BH-7
BH-8
BH-9
BH-10
BH-11
BH-12
BH-13
BH-14
BH-15
GULF DREDGING & GENERAL CONTRACTING Co. RENOVATION AND EXPANSION OF SOUTH JETTY
Quay Wall Construction
Trench excavationThe quay wall trench will be dredged to -8.00 CD for a width of 9.75 m throughout the alignment maintaining the required side slops
GULF DREDGING & GENERAL CONTRACTING Co. RENOVATION AND EXPANSION OF SOUTH JETTY
Quay Wall ConstructionPlacing Geotextile Divers will place Geotextile in trench bed as required
GULF DREDGING & GENERAL CONTRACTING Co. RENOVATION AND EXPANSION OF SOUTH JETTY
Quay Wall ConstructionPlacing Bed Material
•15 – 20 kg rubble bed to be placed for 1.40 M depth using crane and grab •10-30 CM crushed stone bed will be placed over the rubble bed for 300MM thickness using crane and grab and leveled by divers using leveling frames
(10-30 MM)CRUSHED STONES 0.3 M
Rubble 15-20 kg.GEOTEXTILE
SETT
ING
OU
T LI
NE
GULF DREDGING & GENERAL CONTRACTING Co. RENOVATION AND EXPANSION OF SOUTH JETTY
Quay Wall ConstructionPlacing of blocks
• Pre cast blocks will be lowered to the bed using 400 ton crane & placed in position by divers
• All the 4 layers will be placed in panel of 20.40 m
GULF DREDGING & GENERAL CONTRACTING Co. RENOVATION AND EXPANSION OF SOUTH JETTY
Quay Wall ConstructionPre load test Pre load test will be
conducted using special blocks panel by panel with a test load of 3 ton per m2
WeightsPre-loading
21
SETT
ING
OUT
LINE
GULF DREDGING & GENERAL CONTRACTING Co. RENOVATION AND EXPANSION OF SOUTH JETTY
Quay Wall ConstructionFilling behind quay wall
• Rubble fill• Granular material fill• Sand fill
Back FillRubble
15-20 kg
COMPACTED SANDFILL
GRANULAR FILL(2 LAYERS)
SETT
ING
OUT
LINE
GULF DREDGING & GENERAL CONTRACTING Co. RENOVATION AND EXPANSION OF SOUTH JETTY
Quay Wall ConstructionCasting Crown Beam
In situ casting of reinforced crown beam will be done using steel shutters
SETT
ING
OUT
LINE
GULF DREDGING & GENERAL CONTRACTING Co. RENOVATION AND EXPANSION OF SOUTH JETTY
Quay Wall ConstructionScour apron in front
• 30-50 Kg Rock will be placed in front of quay wall for scour protection using crane and grab
Rubble 30-50 kg.
SETT
ING
OUT
LINE
GULF DREDGING & GENERAL CONTRACTING Co. RENOVATION AND EXPANSION OF SOUTH JETTY
Quay Wall ConstructionQuay Furniture
• Fenders• Bollards• Ladders• Mooring Rings
SETT
ING
OUT
LINE
GULF DREDGING & GENERAL CONTRACTING Co. RENOVATION AND EXPANSION OF SOUTH JETTY
Quay Wall Construction