+ All Categories
Transcript
Page 1: STARS OASIS TECH. CONT. L.L.C HVAC TESTING AND COMMISSIONINGstarsoasis.com/images/CompanyProfile.pdf · HVAC Commissioning method statement Coordination and witnessing of Testing

STARS OASIS TECH. CONT. L.L.C

HVAC TESTING AND COMMISSIONING

P.O.Box 47068 *Sharjah* United Arab Emirates* Tel. 06 5740350 * [email protected]

Page 2: STARS OASIS TECH. CONT. L.L.C HVAC TESTING AND COMMISSIONINGstarsoasis.com/images/CompanyProfile.pdf · HVAC Commissioning method statement Coordination and witnessing of Testing

Introduction

Company Introduction

Stars Oasis Tech. Cont. LLC (OTEC) is a leading independent Testing andBalancing company in the Middle East providing the following technicalservices to our Clients. The commissioning team comprises of fully qualified,experienced engineers and specialists dedicated to provide truly independentservices.

Testing and commissioning services are carried out in accordance with thefollowing Commissioning Codes of Practice:Chartered Institute of Building Services Engineers (C.I.B.S.E)

Building Services Research and Information Association (B.S.R.I.A)American Society of Heating, Refrigerating and Air Conditioning Engineers(A.S.H.R.A.E)Associated Air Balancing Council (A.A.B.C)Commissioning Specialist Association (C.S.A)

Our motto to provide top-notch tailor made quality solutions to our clientshelped us reach the pinnacle of success over the past .We take pride in thehistory of our success. The confidence our clients have on us motivates us tocontinue our journey with a passion to deliver the best without anycompromise.Every step forward is a challenge and we are sure that our drive to be thebest will help us deliver value added solutions to every challenge that we facewith integrity and perfection.

Introduction

Company Introduction

Stars Oasis Tech. Cont. LLC (OTEC) is a leading independent Testing andBalancing company in the Middle East providing the following technicalservices to our Clients. The commissioning team comprises of fully qualified,experienced engineers and specialists dedicated to provide truly independentservices.

Testing and commissioning services are carried out in accordance with thefollowing Commissioning Codes of Practice:Chartered Institute of Building Services Engineers (C.I.B.S.E)

Building Services Research and Information Association (B.S.R.I.A)American Society of Heating, Refrigerating and Air Conditioning Engineers(A.S.H.R.A.E)Associated Air Balancing Council (A.A.B.C)Commissioning Specialist Association (C.S.A)

Our motto to provide top-notch tailor made quality solutions to our clientshelped us reach the pinnacle of success over the past .We take pride in thehistory of our success. The confidence our clients have on us motivates us tocontinue our journey with a passion to deliver the best without anycompromise.Every step forward is a challenge and we are sure that our drive to be thebest will help us deliver value added solutions to every challenge that we facewith integrity and perfection.

Introduction

Company Introduction

Stars Oasis Tech. Cont. LLC (OTEC) is a leading independent Testing andBalancing company in the Middle East providing the following technicalservices to our Clients. The commissioning team comprises of fully qualified,experienced engineers and specialists dedicated to provide truly independentservices.

Testing and commissioning services are carried out in accordance with thefollowing Commissioning Codes of Practice:Chartered Institute of Building Services Engineers (C.I.B.S.E)

Building Services Research and Information Association (B.S.R.I.A)American Society of Heating, Refrigerating and Air Conditioning Engineers(A.S.H.R.A.E)Associated Air Balancing Council (A.A.B.C)Commissioning Specialist Association (C.S.A)

Our motto to provide top-notch tailor made quality solutions to our clientshelped us reach the pinnacle of success over the past .We take pride in thehistory of our success. The confidence our clients have on us motivates us tocontinue our journey with a passion to deliver the best without anycompromise.Every step forward is a challenge and we are sure that our drive to be thebest will help us deliver value added solutions to every challenge that we facewith integrity and perfection.

Page 3: STARS OASIS TECH. CONT. L.L.C HVAC TESTING AND COMMISSIONINGstarsoasis.com/images/CompanyProfile.pdf · HVAC Commissioning method statement Coordination and witnessing of Testing

CertificateCertificateCertificate

Page 4: STARS OASIS TECH. CONT. L.L.C HVAC TESTING AND COMMISSIONINGstarsoasis.com/images/CompanyProfile.pdf · HVAC Commissioning method statement Coordination and witnessing of Testing

CertificateCertificateCertificate

Page 5: STARS OASIS TECH. CONT. L.L.C HVAC TESTING AND COMMISSIONINGstarsoasis.com/images/CompanyProfile.pdf · HVAC Commissioning method statement Coordination and witnessing of Testing

CertificateCertificateCertificate

Page 6: STARS OASIS TECH. CONT. L.L.C HVAC TESTING AND COMMISSIONINGstarsoasis.com/images/CompanyProfile.pdf · HVAC Commissioning method statement Coordination and witnessing of Testing

Professional LicenseProfessional LicenseProfessional License

Page 7: STARS OASIS TECH. CONT. L.L.C HVAC TESTING AND COMMISSIONINGstarsoasis.com/images/CompanyProfile.pdf · HVAC Commissioning method statement Coordination and witnessing of Testing

STARS OASIS TECH. CONT. LLC - ORGANISATION CHART

HR &ADMINISTRATION

GENERAL MANAGER

OTEC

ACCOUNTSTECHNICALDOCUMENTATION

PROJECTS MANAGER

HR &ADMINISTRATION

TAB SUPERVISOR TAB SUPERVISOR TAB SUPERVISOR TAB SUPERVISOR TAB TECHNICIAN TAB TECHNICIAN

TAB ENGINEER

TAB TECHNICIAN TAB TECHNICIAN TAB TECHNICIANTAB TECHNICIANTAB TECHNICIANJUNIOR TAB

TECHNICIANS

TAB ENGINEERTAB TENGINEER TAB ENGINEER

TECHNICALDOCUMENTATION

Page 8: STARS OASIS TECH. CONT. L.L.C HVAC TESTING AND COMMISSIONINGstarsoasis.com/images/CompanyProfile.pdf · HVAC Commissioning method statement Coordination and witnessing of Testing

HVAC Testing & Commissioning

H.V.A.C. Testing & Balancing

Independent testing, adjusting and balancing of HVAC system components incompliance with international standards, to the design parameters and to theapproval of the client. OTEC offer a comprehensive service for all HVACsystem including Air Conditioning, Chilled Water and Domestic Hot and ColdWater services, for newly build and refurbishment. In addition, site surveysand troubleshooting can be undertaken, including acoustic and environmentaltesting.

HVAC Systems typically use sophisticated, automatic control to supply theproper amount of air for cooling, heating and ventilation in commercialbuildings. Problems encountered during installation, operation andmaintenance of servicing of the HVAC system could prevent it from operatingas designed. There for each system has to be tested to ensure its initial andcontinued performances.

In addition to provide optimal thermal conditions and balanced ventilation, aproperly adjusted and balanced system can also reduce operating cost andincrease equipment life.

Our Testing and Balancing report provides a complete record of the design,preliminary measurements and final test data. The report includes anydiscrepancies between the test data and the design specifications, along withreasons for those discrepancies.

HVAC Testing & Commissioning

H.V.A.C. Testing & Balancing

Independent testing, adjusting and balancing of HVAC system components incompliance with international standards, to the design parameters and to theapproval of the client. OTEC offer a comprehensive service for all HVACsystem including Air Conditioning, Chilled Water and Domestic Hot and ColdWater services, for newly build and refurbishment. In addition, site surveysand troubleshooting can be undertaken, including acoustic and environmentaltesting.

HVAC Systems typically use sophisticated, automatic control to supply theproper amount of air for cooling, heating and ventilation in commercialbuildings. Problems encountered during installation, operation andmaintenance of servicing of the HVAC system could prevent it from operatingas designed. There for each system has to be tested to ensure its initial andcontinued performances.

In addition to provide optimal thermal conditions and balanced ventilation, aproperly adjusted and balanced system can also reduce operating cost andincrease equipment life.

Our Testing and Balancing report provides a complete record of the design,preliminary measurements and final test data. The report includes anydiscrepancies between the test data and the design specifications, along withreasons for those discrepancies.

HVAC Testing & Commissioning

H.V.A.C. Testing & Balancing

Independent testing, adjusting and balancing of HVAC system components incompliance with international standards, to the design parameters and to theapproval of the client. OTEC offer a comprehensive service for all HVACsystem including Air Conditioning, Chilled Water and Domestic Hot and ColdWater services, for newly build and refurbishment. In addition, site surveysand troubleshooting can be undertaken, including acoustic and environmentaltesting.

HVAC Systems typically use sophisticated, automatic control to supply theproper amount of air for cooling, heating and ventilation in commercialbuildings. Problems encountered during installation, operation andmaintenance of servicing of the HVAC system could prevent it from operatingas designed. There for each system has to be tested to ensure its initial andcontinued performances.

In addition to provide optimal thermal conditions and balanced ventilation, aproperly adjusted and balanced system can also reduce operating cost andincrease equipment life.

Our Testing and Balancing report provides a complete record of the design,preliminary measurements and final test data. The report includes anydiscrepancies between the test data and the design specifications, along withreasons for those discrepancies.

Page 9: STARS OASIS TECH. CONT. L.L.C HVAC TESTING AND COMMISSIONINGstarsoasis.com/images/CompanyProfile.pdf · HVAC Commissioning method statement Coordination and witnessing of Testing

HVAC Testing & Commissioning

Commissioning Management

The commissioning company has a major role in any building as theirindependent input helps all concerned focus on the performance of eachsystem. The commissioning manager plays a vital part in bringing allconcerned parties to the table and ensure that the various systems arecoordinated ready for start up and commissioning. The commissioningmanager will schedule the trades so that upon initialization allinterconnections, integration or interfaces with other trades are consideredand incorporated within the start up process. The commissioning managercan be appointed at the design stage to review the commissionability of eachsystem, value engineering and hoe maintainable the actual design solutionwill be.

OTEC provide a fully independent Commissioning Management Serviceswhich offers the following:

HVAC Commissioning Design Assessment

System installation and commissioning-ability assessment and monito

HVAC Commissioning method statement

Coordination and witnessing of Testing and Balancing

Pre-commissioning and Commissioning Test witnessing

Verification of test documents

MEP site coordination

HVAC Testing & Commissioning

Commissioning Management

The commissioning company has a major role in any building as theirindependent input helps all concerned focus on the performance of eachsystem. The commissioning manager plays a vital part in bringing allconcerned parties to the table and ensure that the various systems arecoordinated ready for start up and commissioning. The commissioningmanager will schedule the trades so that upon initialization allinterconnections, integration or interfaces with other trades are consideredand incorporated within the start up process. The commissioning managercan be appointed at the design stage to review the commissionability of eachsystem, value engineering and hoe maintainable the actual design solutionwill be.

OTEC provide a fully independent Commissioning Management Serviceswhich offers the following:

HVAC Commissioning Design Assessment

System installation and commissioning-ability assessment and monito

HVAC Commissioning method statement

Coordination and witnessing of Testing and Balancing

Pre-commissioning and Commissioning Test witnessing

Verification of test documents

MEP site coordination

HVAC Testing & Commissioning

Commissioning Management

The commissioning company has a major role in any building as theirindependent input helps all concerned focus on the performance of eachsystem. The commissioning manager plays a vital part in bringing allconcerned parties to the table and ensure that the various systems arecoordinated ready for start up and commissioning. The commissioningmanager will schedule the trades so that upon initialization allinterconnections, integration or interfaces with other trades are consideredand incorporated within the start up process. The commissioning managercan be appointed at the design stage to review the commissionability of eachsystem, value engineering and hoe maintainable the actual design solutionwill be.

OTEC provide a fully independent Commissioning Management Serviceswhich offers the following:

HVAC Commissioning Design Assessment

System installation and commissioning-ability assessment and monito

HVAC Commissioning method statement

Coordination and witnessing of Testing and Balancing

Pre-commissioning and Commissioning Test witnessing

Verification of test documents

MEP site coordination

Page 10: STARS OASIS TECH. CONT. L.L.C HVAC TESTING AND COMMISSIONINGstarsoasis.com/images/CompanyProfile.pdf · HVAC Commissioning method statement Coordination and witnessing of Testing

HVAC Testing & Commissioning

Sound Level and Environmental Test

Upon completion of Testing and Balancing, we will provide Sound Level Testand Environmental condition monitoring. Sound Level testing comprises ofour engineers using state-of-the-art acoustic equipment that will measure thesound level in all spaces of the building. The study can only be conductedwhen commissioning is complete and all of the buildings fabrics and fittingshave been put in place. The study records all the sound within the space, withplant ON and OFF.

Environmental condition monitoring comprises if our engineers eitherphysically taking readings from each space or setting calibrated electronicdata loggers to record temperature and humidity. During this verification thebuilding management and controls system is modulated and each reading isverified. The data gathered is then provided to the controls specialist enablingexact offsets to be entered into the control system, if necessary. Theindividual space is then retested and signed off.

HVAC Testing & Commissioning

Sound Level and Environmental Test

Upon completion of Testing and Balancing, we will provide Sound Level Testand Environmental condition monitoring. Sound Level testing comprises ofour engineers using state-of-the-art acoustic equipment that will measure thesound level in all spaces of the building. The study can only be conductedwhen commissioning is complete and all of the buildings fabrics and fittingshave been put in place. The study records all the sound within the space, withplant ON and OFF.

Environmental condition monitoring comprises if our engineers eitherphysically taking readings from each space or setting calibrated electronicdata loggers to record temperature and humidity. During this verification thebuilding management and controls system is modulated and each reading isverified. The data gathered is then provided to the controls specialist enablingexact offsets to be entered into the control system, if necessary. Theindividual space is then retested and signed off.

HVAC Testing & Commissioning

Sound Level and Environmental Test

Upon completion of Testing and Balancing, we will provide Sound Level Testand Environmental condition monitoring. Sound Level testing comprises ofour engineers using state-of-the-art acoustic equipment that will measure thesound level in all spaces of the building. The study can only be conductedwhen commissioning is complete and all of the buildings fabrics and fittingshave been put in place. The study records all the sound within the space, withplant ON and OFF.

Environmental condition monitoring comprises if our engineers eitherphysically taking readings from each space or setting calibrated electronicdata loggers to record temperature and humidity. During this verification thebuilding management and controls system is modulated and each reading isverified. The data gathered is then provided to the controls specialist enablingexact offsets to be entered into the control system, if necessary. Theindividual space is then retested and signed off.

Page 11: STARS OASIS TECH. CONT. L.L.C HVAC TESTING AND COMMISSIONINGstarsoasis.com/images/CompanyProfile.pdf · HVAC Commissioning method statement Coordination and witnessing of Testing

HVAC Testing & Commissioning

Vibration Test

We provide vibration testing for both predictive maintenance and reactivemaintenance. With our predictive maintenance technique we utilize a vibrationmeasuring device that records a blue print of your piece of plant. Thismeasurement can be trended to ensure that each item of the plant is workingto its optimum performance. By utilizing this service as part of the regularmaintenance plant optimization can be guaranteed. The vibration test iscarried out on equipment suspected of excessive vibration and unusual noise.Any unusual noise should be dealt with immediately, this is often the tell tailsign that the plant is failing or working inefficiently. Vibration test can also becarried out on the plant with intermittent faults, often vibration can trace theroot of the problem quickly, accurately without any down time.

HVAC Testing & Commissioning

Vibration Test

We provide vibration testing for both predictive maintenance and reactivemaintenance. With our predictive maintenance technique we utilize a vibrationmeasuring device that records a blue print of your piece of plant. Thismeasurement can be trended to ensure that each item of the plant is workingto its optimum performance. By utilizing this service as part of the regularmaintenance plant optimization can be guaranteed. The vibration test iscarried out on equipment suspected of excessive vibration and unusual noise.Any unusual noise should be dealt with immediately, this is often the tell tailsign that the plant is failing or working inefficiently. Vibration test can also becarried out on the plant with intermittent faults, often vibration can trace theroot of the problem quickly, accurately without any down time.

HVAC Testing & Commissioning

Vibration Test

We provide vibration testing for both predictive maintenance and reactivemaintenance. With our predictive maintenance technique we utilize a vibrationmeasuring device that records a blue print of your piece of plant. Thismeasurement can be trended to ensure that each item of the plant is workingto its optimum performance. By utilizing this service as part of the regularmaintenance plant optimization can be guaranteed. The vibration test iscarried out on equipment suspected of excessive vibration and unusual noise.Any unusual noise should be dealt with immediately, this is often the tell tailsign that the plant is failing or working inefficiently. Vibration test can also becarried out on the plant with intermittent faults, often vibration can trace theroot of the problem quickly, accurately without any down time.

Page 12: STARS OASIS TECH. CONT. L.L.C HVAC TESTING AND COMMISSIONINGstarsoasis.com/images/CompanyProfile.pdf · HVAC Commissioning method statement Coordination and witnessing of Testing

HVAC Testing & Commissioning

Duct Leak / Pressure Test

A duct leakage tester is a diagnostic tool designed to measure the airtightness of forced air heating, ventilating and air-conditioning (HVAC)ductwork. A duct leakage tester consists of a calibrated fan for measuring anair flow rate and a pressure sensing device to measure the pressure createdby the fan flow. The combination of pressure and fan flow measurements areused to determine the ductwork air tightness.

During the construction process, when the duct is accessible before the grillesand equipment is installed, each intentional opening in the duct system issealed air tight with plastic and tape. The duct system is then placed underhigh pressure, and the airflow through the fan is measured. The fan airflow isinterpreted as duct leakage. If the level of leakage is out of spec, the leakyduct is repaired and then the test is repeated. The process continues untilacceptable results are achieved.

Higher pressure is critical to assure the pressure at the fan is equal to thepressure throughout the entire duct system. Only then can the pressure at thefan be interpreted to represent accurate airflow leakage throughout thesystem.

Since air is the fluid that carries the heating or cooling throughout the building,its flow, temperatures, velocities, losses, gains, and enthalpy must be verifiedat many points throughout the system so it can be effectively diagnosed andperformance rated.

Airflow is the life-blood of a system upon which all the other components andcircuits depend. Air is as essential to the system as power is to the fan.Without verification of airflow throughout the entire system, it’s impossible toeffectively test the heating and refrigeration performance.

HVAC Testing & Commissioning

Duct Leak / Pressure Test

A duct leakage tester is a diagnostic tool designed to measure the airtightness of forced air heating, ventilating and air-conditioning (HVAC)ductwork. A duct leakage tester consists of a calibrated fan for measuring anair flow rate and a pressure sensing device to measure the pressure createdby the fan flow. The combination of pressure and fan flow measurements areused to determine the ductwork air tightness.

During the construction process, when the duct is accessible before the grillesand equipment is installed, each intentional opening in the duct system issealed air tight with plastic and tape. The duct system is then placed underhigh pressure, and the airflow through the fan is measured. The fan airflow isinterpreted as duct leakage. If the level of leakage is out of spec, the leakyduct is repaired and then the test is repeated. The process continues untilacceptable results are achieved.

Higher pressure is critical to assure the pressure at the fan is equal to thepressure throughout the entire duct system. Only then can the pressure at thefan be interpreted to represent accurate airflow leakage throughout thesystem.

Since air is the fluid that carries the heating or cooling throughout the building,its flow, temperatures, velocities, losses, gains, and enthalpy must be verifiedat many points throughout the system so it can be effectively diagnosed andperformance rated.

Airflow is the life-blood of a system upon which all the other components andcircuits depend. Air is as essential to the system as power is to the fan.Without verification of airflow throughout the entire system, it’s impossible toeffectively test the heating and refrigeration performance.

HVAC Testing & Commissioning

Duct Leak / Pressure Test

A duct leakage tester is a diagnostic tool designed to measure the airtightness of forced air heating, ventilating and air-conditioning (HVAC)ductwork. A duct leakage tester consists of a calibrated fan for measuring anair flow rate and a pressure sensing device to measure the pressure createdby the fan flow. The combination of pressure and fan flow measurements areused to determine the ductwork air tightness.

During the construction process, when the duct is accessible before the grillesand equipment is installed, each intentional opening in the duct system issealed air tight with plastic and tape. The duct system is then placed underhigh pressure, and the airflow through the fan is measured. The fan airflow isinterpreted as duct leakage. If the level of leakage is out of spec, the leakyduct is repaired and then the test is repeated. The process continues untilacceptable results are achieved.

Higher pressure is critical to assure the pressure at the fan is equal to thepressure throughout the entire duct system. Only then can the pressure at thefan be interpreted to represent accurate airflow leakage throughout thesystem.

Since air is the fluid that carries the heating or cooling throughout the building,its flow, temperatures, velocities, losses, gains, and enthalpy must be verifiedat many points throughout the system so it can be effectively diagnosed andperformance rated.

Airflow is the life-blood of a system upon which all the other components andcircuits depend. Air is as essential to the system as power is to the fan.Without verification of airflow throughout the entire system, it’s impossible toeffectively test the heating and refrigeration performance.

Page 13: STARS OASIS TECH. CONT. L.L.C HVAC TESTING AND COMMISSIONINGstarsoasis.com/images/CompanyProfile.pdf · HVAC Commissioning method statement Coordination and witnessing of Testing

HVAC Testing & Commissioning

Plant Surveys

We provide a combination of observations and physical measurements in aconcise tabulated format to enable you to appreciate the condition andperformance against design. We also estimate the life expectancy of yourplant.

We record the physical details, design data and the dynamic measurement ofvolumetric flow rates, static pressures, speed and absorbed current. In orderto provide an extremely cost effective service, we focus on plant rooms andspecifically nominated areas. However, we would be happy to record andcompare air and water flow rates throughout the network. We can also inspectthe condition and operation of the HVAC system with regard to Life SafetyEquipments such as fire dampers and duct smoke detectors.

Our quality controlled documents record both static and dynamic plant data.Our team measures all relevant plant data with latest calibrated and certifiedtest equipment.

HVAC Testing & Commissioning

Plant Surveys

We provide a combination of observations and physical measurements in aconcise tabulated format to enable you to appreciate the condition andperformance against design. We also estimate the life expectancy of yourplant.

We record the physical details, design data and the dynamic measurement ofvolumetric flow rates, static pressures, speed and absorbed current. In orderto provide an extremely cost effective service, we focus on plant rooms andspecifically nominated areas. However, we would be happy to record andcompare air and water flow rates throughout the network. We can also inspectthe condition and operation of the HVAC system with regard to Life SafetyEquipments such as fire dampers and duct smoke detectors.

Our quality controlled documents record both static and dynamic plant data.Our team measures all relevant plant data with latest calibrated and certifiedtest equipment.

HVAC Testing & Commissioning

Plant Surveys

We provide a combination of observations and physical measurements in aconcise tabulated format to enable you to appreciate the condition andperformance against design. We also estimate the life expectancy of yourplant.

We record the physical details, design data and the dynamic measurement ofvolumetric flow rates, static pressures, speed and absorbed current. In orderto provide an extremely cost effective service, we focus on plant rooms andspecifically nominated areas. However, we would be happy to record andcompare air and water flow rates throughout the network. We can also inspectthe condition and operation of the HVAC system with regard to Life SafetyEquipments such as fire dampers and duct smoke detectors.

Our quality controlled documents record both static and dynamic plant data.Our team measures all relevant plant data with latest calibrated and certifiedtest equipment.

Page 14: STARS OASIS TECH. CONT. L.L.C HVAC TESTING AND COMMISSIONINGstarsoasis.com/images/CompanyProfile.pdf · HVAC Commissioning method statement Coordination and witnessing of Testing

HVAC Testing & Commissioning

Indoor Air Quality Test

The quality of air within our working environment is extremely importantASHRAE following an extensive survey concluded that productivity can beimproved by 10 - 25% by improving air quality. We provide air qualityinspections to determine whether the property is suffering from Sick BuildingSyndrome (SBS) or Building Related Illness (BRI).

A building's air duct network act as its respiratory system. Dirt, dust, debrisand microbial growth that accumulate inside of air ducts hidden from view andmake it difficult for the building to (breath) properly and function efficiently.

HVAC Testing & Commissioning

Indoor Air Quality Test

The quality of air within our working environment is extremely importantASHRAE following an extensive survey concluded that productivity can beimproved by 10 - 25% by improving air quality. We provide air qualityinspections to determine whether the property is suffering from Sick BuildingSyndrome (SBS) or Building Related Illness (BRI).

A building's air duct network act as its respiratory system. Dirt, dust, debrisand microbial growth that accumulate inside of air ducts hidden from view andmake it difficult for the building to (breath) properly and function efficiently.

HVAC Testing & Commissioning

Indoor Air Quality Test

The quality of air within our working environment is extremely importantASHRAE following an extensive survey concluded that productivity can beimproved by 10 - 25% by improving air quality. We provide air qualityinspections to determine whether the property is suffering from Sick BuildingSyndrome (SBS) or Building Related Illness (BRI).

A building's air duct network act as its respiratory system. Dirt, dust, debrisand microbial growth that accumulate inside of air ducts hidden from view andmake it difficult for the building to (breath) properly and function efficiently.

Page 15: STARS OASIS TECH. CONT. L.L.C HVAC TESTING AND COMMISSIONINGstarsoasis.com/images/CompanyProfile.pdf · HVAC Commissioning method statement Coordination and witnessing of Testing

HVAC Testing & Commissioning

Operating and Maintenance Manuals

We pride ourselves as one of the leading professionals in the preparation ofElectro-Mechanical Services Operating and Maintenance manuals, complyingwith BSRIA standards which has been widely accepted by the reputed Clients,Consultants and Contractors in the United Arab Emirates.

A well prepared Operating and maintenance manual is a handy tool of themaintenance staff to carry out effective maintenance on any plant orequipment installed at any facility.

Poor and unplanned maintenance affects the performance and life of theequipment resulting in untimely breakdown and increased costs affectingproductivity.

On the other hand effective maintenance carried out on any piece ofequipment complying with the manufacturers recommendations prolong thelife of the equipment and reduces down time and operational costs.

Our professional team work in line with the requirements of all parties involvedto prepare professional and tailor made manuals complying with the setstandards on each project.

HVAC Testing & Commissioning

Operating and Maintenance Manuals

We pride ourselves as one of the leading professionals in the preparation ofElectro-Mechanical Services Operating and Maintenance manuals, complyingwith BSRIA standards which has been widely accepted by the reputed Clients,Consultants and Contractors in the United Arab Emirates.

A well prepared Operating and maintenance manual is a handy tool of themaintenance staff to carry out effective maintenance on any plant orequipment installed at any facility.

Poor and unplanned maintenance affects the performance and life of theequipment resulting in untimely breakdown and increased costs affectingproductivity.

On the other hand effective maintenance carried out on any piece ofequipment complying with the manufacturers recommendations prolong thelife of the equipment and reduces down time and operational costs.

Our professional team work in line with the requirements of all parties involvedto prepare professional and tailor made manuals complying with the setstandards on each project.

HVAC Testing & Commissioning

Operating and Maintenance Manuals

We pride ourselves as one of the leading professionals in the preparation ofElectro-Mechanical Services Operating and Maintenance manuals, complyingwith BSRIA standards which has been widely accepted by the reputed Clients,Consultants and Contractors in the United Arab Emirates.

A well prepared Operating and maintenance manual is a handy tool of themaintenance staff to carry out effective maintenance on any plant orequipment installed at any facility.

Poor and unplanned maintenance affects the performance and life of theequipment resulting in untimely breakdown and increased costs affectingproductivity.

On the other hand effective maintenance carried out on any piece ofequipment complying with the manufacturers recommendations prolong thelife of the equipment and reduces down time and operational costs.

Our professional team work in line with the requirements of all parties involvedto prepare professional and tailor made manuals complying with the setstandards on each project.

Page 16: STARS OASIS TECH. CONT. L.L.C HVAC TESTING AND COMMISSIONINGstarsoasis.com/images/CompanyProfile.pdf · HVAC Commissioning method statement Coordination and witnessing of Testing

HVAC Testing & Commissioning

Witnessing, Verification and Inspection

For owners and operators of all electro-mechanical services, witnessing,inspection and verification of plant and equipment installed is a mandatoryprocess. Your facilities can benefit from our multi-disciplinary team of highlyqualified inspection engineers, who can provide mandatory inspectionservices as well as independent third party inspection, verification andendorsement.

Mandatory Witnessing & Inspection ServicesReview and verification of design drawings and technical data.Witnessing, inspection, verification and approval of new, used or in-service local or imported plant and equipmentWitnessing, verification and approval of installations.

Independent Third Party Inspection, Verification and EndorsementServicesInspection before, during and after InstallationCompliance Inspection on Imported and In-service Equipment andMachinery.Condition Monitoring and Plant Assessment;Non-Destructive Evaluation (Witness and Verification of Test Report);

and endorsement of Failure Investigation and Analysis Reports.

AdvantagesRespond to defects detected at an early stage to save costs.Improve safety and quality through our comprehensive and credibleinspections.Take advantage of business opportunities through compliance tovarious codes, standards, specifications and design requirements.Minimize the inspection time required for facilities that have been shutdown or are under construction, saving your costs.

HVAC Testing & Commissioning

Witnessing, Verification and Inspection

For owners and operators of all electro-mechanical services, witnessing,inspection and verification of plant and equipment installed is a mandatoryprocess. Your facilities can benefit from our multi-disciplinary team of highlyqualified inspection engineers, who can provide mandatory inspectionservices as well as independent third party inspection, verification andendorsement.

Mandatory Witnessing & Inspection ServicesReview and verification of design drawings and technical data.Witnessing, inspection, verification and approval of new, used or in-service local or imported plant and equipmentWitnessing, verification and approval of installations.

Independent Third Party Inspection, Verification and EndorsementServicesInspection before, during and after InstallationCompliance Inspection on Imported and In-service Equipment andMachinery.Condition Monitoring and Plant Assessment;Non-Destructive Evaluation (Witness and Verification of Test Report);

and endorsement of Failure Investigation and Analysis Reports.

AdvantagesRespond to defects detected at an early stage to save costs.Improve safety and quality through our comprehensive and credibleinspections.Take advantage of business opportunities through compliance tovarious codes, standards, specifications and design requirements.Minimize the inspection time required for facilities that have been shutdown or are under construction, saving your costs.

HVAC Testing & Commissioning

Witnessing, Verification and Inspection

For owners and operators of all electro-mechanical services, witnessing,inspection and verification of plant and equipment installed is a mandatoryprocess. Your facilities can benefit from our multi-disciplinary team of highlyqualified inspection engineers, who can provide mandatory inspectionservices as well as independent third party inspection, verification andendorsement.

Mandatory Witnessing & Inspection ServicesReview and verification of design drawings and technical data.Witnessing, inspection, verification and approval of new, used or in-service local or imported plant and equipmentWitnessing, verification and approval of installations.

Independent Third Party Inspection, Verification and EndorsementServicesInspection before, during and after InstallationCompliance Inspection on Imported and In-service Equipment andMachinery.Condition Monitoring and Plant Assessment;Non-Destructive Evaluation (Witness and Verification of Test Report);

and endorsement of Failure Investigation and Analysis Reports.

AdvantagesRespond to defects detected at an early stage to save costs.Improve safety and quality through our comprehensive and credibleinspections.Take advantage of business opportunities through compliance tovarious codes, standards, specifications and design requirements.Minimize the inspection time required for facilities that have been shutdown or are under construction, saving your costs.

Page 17: STARS OASIS TECH. CONT. L.L.C HVAC TESTING AND COMMISSIONINGstarsoasis.com/images/CompanyProfile.pdf · HVAC Commissioning method statement Coordination and witnessing of Testing

LIST OF PROJECTS

PROJECT NAME CONSULTANT / CLIENT

The One Tower @ TECOM DEWAN

The Abu Dhabi InternationalAirport Expansion -Catering South Side

ADAC

Souq Extra (Mall) - SiliconOasis, Dubai

JOHN R HARRIS

Asset Enhancement Worksin Burjman Centre - 1

SEED

Al Wasl Box Park EO

TAJ Downtown Hotel DAR / IBA

LULU Regional HQ - Dubai DAR / IBA

Bay Square @ Business Bay(12 Building & CommonBasement)

KHATIB ALAMI

G+3 GEMS WillingtonAcademy @ DSO

PJSI

Air College Al Ain - CMW-13019 - C002-02

CMW

Bawabat Al Sharq - Phase2A Buildings

AECOM

Construction of StableComplex @ Endurance Villa- Al Lissaili, Dubai

EO

Construction of ADNOCFilling Station - MotorWorld, Abu Dhabi

DORSCH

Al Falah Community - AbuDhabi (2080 Villas)

WS ATKINS

LIST OF PROJECTS

PROJECT NAME CONSULTANT / CLIENT

The One Tower @ TECOM DEWAN

The Abu Dhabi InternationalAirport Expansion -Catering South Side

ADAC

Souq Extra (Mall) - SiliconOasis, Dubai

JOHN R HARRIS

Asset Enhancement Worksin Burjman Centre - 1

SEED

Al Wasl Box Park EO

TAJ Downtown Hotel DAR / IBA

LULU Regional HQ - Dubai DAR / IBA

Bay Square @ Business Bay(12 Building & CommonBasement)

KHATIB ALAMI

G+3 GEMS WillingtonAcademy @ DSO

PJSI

Air College Al Ain - CMW-13019 - C002-02

CMW

Bawabat Al Sharq - Phase2A Buildings

AECOM

Construction of StableComplex @ Endurance Villa- Al Lissaili, Dubai

EO

Construction of ADNOCFilling Station - MotorWorld, Abu Dhabi

DORSCH

Al Falah Community - AbuDhabi (2080 Villas)

WS ATKINS

LIST OF PROJECTS

PROJECT NAME CONSULTANT / CLIENT

The One Tower @ TECOM DEWAN

The Abu Dhabi InternationalAirport Expansion -Catering South Side

ADAC

Souq Extra (Mall) - SiliconOasis, Dubai

JOHN R HARRIS

Asset Enhancement Worksin Burjman Centre - 1

SEED

Al Wasl Box Park EO

TAJ Downtown Hotel DAR / IBA

LULU Regional HQ - Dubai DAR / IBA

Bay Square @ Business Bay(12 Building & CommonBasement)

KHATIB ALAMI

G+3 GEMS WillingtonAcademy @ DSO

PJSI

Air College Al Ain - CMW-13019 - C002-02

CMW

Bawabat Al Sharq - Phase2A Buildings

AECOM

Construction of StableComplex @ Endurance Villa- Al Lissaili, Dubai

EO

Construction of ADNOCFilling Station - MotorWorld, Abu Dhabi

DORSCH

Al Falah Community - AbuDhabi (2080 Villas)

WS ATKINS

Page 18: STARS OASIS TECH. CONT. L.L.C HVAC TESTING AND COMMISSIONINGstarsoasis.com/images/CompanyProfile.pdf · HVAC Commissioning method statement Coordination and witnessing of Testing

LIST OF PROJECTS

PROJECT NAME CONSULTANT / CLIENT

Wild Flower - 33 VillaJumeirah Golf Estate -Dubai

Engineering ConsortiumConsulting Engineers /DAMAC

Al Raha Gardens GHD

Gourmet Tower @ MarinaMall

MEINHARDT

Zayed Military City -CMW-15069-C001

CMW

Zabeel Palace Main & WestGate

WSP

H.E.Juma Al Majid Villa @Khawaneej

Client

Construction of GYMBuilding and RelatedFacilities @ Jabel Ali Villa

Engineers Office

RAK Mall - LULU – Ras AlKhaimah

Eng.Adnan Saffrini

Zabeel II – Majlis forH.H.Sheikh Ahmed BinMohammed Al Maktoum

Engineers Office

Gulf Petrochen Project @Fujairah

Mott Mc Donald

Weatherford ManufacturingUnit – Abu Dhabi

SPEC

Fly Dubai Office @ AspionTower

Client

MBG Laboratory - Dubai Engineers Office

Lulu Hypermarket - Dibba Concept Design

LIST OF PROJECTS

PROJECT NAME CONSULTANT / CLIENT

Wild Flower - 33 VillaJumeirah Golf Estate -Dubai

Engineering ConsortiumConsulting Engineers /DAMAC

Al Raha Gardens GHD

Gourmet Tower @ MarinaMall

MEINHARDT

Zayed Military City -CMW-15069-C001

CMW

Zabeel Palace Main & WestGate

WSP

H.E.Juma Al Majid Villa @Khawaneej

Client

Construction of GYMBuilding and RelatedFacilities @ Jabel Ali Villa

Engineers Office

RAK Mall - LULU – Ras AlKhaimah

Eng.Adnan Saffrini

Zabeel II – Majlis forH.H.Sheikh Ahmed BinMohammed Al Maktoum

Engineers Office

Gulf Petrochen Project @Fujairah

Mott Mc Donald

Weatherford ManufacturingUnit – Abu Dhabi

SPEC

Fly Dubai Office @ AspionTower

Client

MBG Laboratory - Dubai Engineers Office

Lulu Hypermarket - Dibba Concept Design

LIST OF PROJECTS

PROJECT NAME CONSULTANT / CLIENT

Wild Flower - 33 VillaJumeirah Golf Estate -Dubai

Engineering ConsortiumConsulting Engineers /DAMAC

Al Raha Gardens GHD

Gourmet Tower @ MarinaMall

MEINHARDT

Zayed Military City -CMW-15069-C001

CMW

Zabeel Palace Main & WestGate

WSP

H.E.Juma Al Majid Villa @Khawaneej

Client

Construction of GYMBuilding and RelatedFacilities @ Jabel Ali Villa

Engineers Office

RAK Mall - LULU – Ras AlKhaimah

Eng.Adnan Saffrini

Zabeel II – Majlis forH.H.Sheikh Ahmed BinMohammed Al Maktoum

Engineers Office

Gulf Petrochen Project @Fujairah

Mott Mc Donald

Weatherford ManufacturingUnit – Abu Dhabi

SPEC

Fly Dubai Office @ AspionTower

Client

MBG Laboratory - Dubai Engineers Office

Lulu Hypermarket - Dibba Concept Design

Page 19: STARS OASIS TECH. CONT. L.L.C HVAC TESTING AND COMMISSIONINGstarsoasis.com/images/CompanyProfile.pdf · HVAC Commissioning method statement Coordination and witnessing of Testing

LIST OF PROJECTS

PROJECT NAME CONSULTANT / CLIENT

German Hospital – AbuDhabi

CLIENT

Gulf PharmaceuticalIndustries L.L.C

Gulf Pharmaceutical

Abu Dhabi Business Hub RAMAHI ENGG.

New Machinery &Component RepairWorkshop – ICAD-3

SPEC

ADMM F1 Driving SchoolRefurbishment Works

Clarke Samadhin

Mosque @ Jumeirah MERAAS

Commercial Development -Sector ME-9 / Plot No. 157

ADCP

Construction of HorseStable and Horse RacingTrack @ NAS

Engineers Office

Commercial Development -Salim Ahmed Ali Al Ghuss

ADCP

DADNA Farm Palace -Fujairah

Engineers Office

Beacon Education Schoolsat Al Raha Gardens

ATKINS

G + 3 GEMS WillongtonAcademy @ DSO

PJSI

Burj Dubai Development,Old Town

MACE

Commercial Development –Plot No. C-62, ME-10

ADCP

Rotana Hotel RefurbishmentWorks - SZR, Dubai

Al Manar

LIST OF PROJECTS

PROJECT NAME CONSULTANT / CLIENT

German Hospital – AbuDhabi

CLIENT

Gulf PharmaceuticalIndustries L.L.C

Gulf Pharmaceutical

Abu Dhabi Business Hub RAMAHI ENGG.

New Machinery &Component RepairWorkshop – ICAD-3

SPEC

ADMM F1 Driving SchoolRefurbishment Works

Clarke Samadhin

Mosque @ Jumeirah MERAAS

Commercial Development -Sector ME-9 / Plot No. 157

ADCP

Construction of HorseStable and Horse RacingTrack @ NAS

Engineers Office

Commercial Development -Salim Ahmed Ali Al Ghuss

ADCP

DADNA Farm Palace -Fujairah

Engineers Office

Beacon Education Schoolsat Al Raha Gardens

ATKINS

G + 3 GEMS WillongtonAcademy @ DSO

PJSI

Burj Dubai Development,Old Town

MACE

Commercial Development –Plot No. C-62, ME-10

ADCP

Rotana Hotel RefurbishmentWorks - SZR, Dubai

Al Manar

LIST OF PROJECTS

PROJECT NAME CONSULTANT / CLIENT

German Hospital – AbuDhabi

CLIENT

Gulf PharmaceuticalIndustries L.L.C

Gulf Pharmaceutical

Abu Dhabi Business Hub RAMAHI ENGG.

New Machinery &Component RepairWorkshop – ICAD-3

SPEC

ADMM F1 Driving SchoolRefurbishment Works

Clarke Samadhin

Mosque @ Jumeirah MERAAS

Commercial Development -Sector ME-9 / Plot No. 157

ADCP

Construction of HorseStable and Horse RacingTrack @ NAS

Engineers Office

Commercial Development -Salim Ahmed Ali Al Ghuss

ADCP

DADNA Farm Palace -Fujairah

Engineers Office

Beacon Education Schoolsat Al Raha Gardens

ATKINS

G + 3 GEMS WillongtonAcademy @ DSO

PJSI

Burj Dubai Development,Old Town

MACE

Commercial Development –Plot No. C-62, ME-10

ADCP

Rotana Hotel RefurbishmentWorks - SZR, Dubai

Al Manar

Page 20: STARS OASIS TECH. CONT. L.L.C HVAC TESTING AND COMMISSIONINGstarsoasis.com/images/CompanyProfile.pdf · HVAC Commissioning method statement Coordination and witnessing of Testing

LIST OF PROJECTS

PROJECT NAME CONSULTANT / CLIENT

Shamma School @ Al Ain UPA

G + 2 School @ Baniyas NEBPackage (01) Al QadisiyyaSchool - Type B

The Kindergarten Starters(G+2)

Arkiplan

Al Shafar Office @Business Bay

Holford Associates

Package (01) Al QadisiyyaSchool - Type B

UPA

Villa for Mr.Abdullah AlHabbai @ Al Khawaneej 1st

Engineers Office

Pullman Intl. Hotel – FirstFloor @ DCC - Dubai

WATERMAN

Hilton JBR Project - StairCase Pressurization System

Bureau Veritas

Villa for Mr.AhmadFalaknaz @ Al Saffa

Client

Safeer Mall - Fujairah Consultair

Mr.Hamad Al GhurairResidential Villa – AlKhawaneej

Client

Commercial Development –Plot No. C-62, ME-10

ADCP

Rasas Al Mansoory Bidg. –M10, Plot No. 54, Musaffah

GERMAN MERIT

Ericcson office @ Jabel AliDown Town

Client

LIST OF PROJECTS

PROJECT NAME CONSULTANT / CLIENT

Shamma School @ Al Ain UPA

G + 2 School @ Baniyas NEBPackage (01) Al QadisiyyaSchool - Type B

The Kindergarten Starters(G+2)

Arkiplan

Al Shafar Office @Business Bay

Holford Associates

Package (01) Al QadisiyyaSchool - Type B

UPA

Villa for Mr.Abdullah AlHabbai @ Al Khawaneej 1st

Engineers Office

Pullman Intl. Hotel – FirstFloor @ DCC - Dubai

WATERMAN

Hilton JBR Project - StairCase Pressurization System

Bureau Veritas

Villa for Mr.AhmadFalaknaz @ Al Saffa

Client

Safeer Mall - Fujairah Consultair

Mr.Hamad Al GhurairResidential Villa – AlKhawaneej

Client

Commercial Development –Plot No. C-62, ME-10

ADCP

Rasas Al Mansoory Bidg. –M10, Plot No. 54, Musaffah

GERMAN MERIT

Ericcson office @ Jabel AliDown Town

Client

LIST OF PROJECTS

PROJECT NAME CONSULTANT / CLIENT

Shamma School @ Al Ain UPA

G + 2 School @ Baniyas NEBPackage (01) Al QadisiyyaSchool - Type B

The Kindergarten Starters(G+2)

Arkiplan

Al Shafar Office @Business Bay

Holford Associates

Package (01) Al QadisiyyaSchool - Type B

UPA

Villa for Mr.Abdullah AlHabbai @ Al Khawaneej 1st

Engineers Office

Pullman Intl. Hotel – FirstFloor @ DCC - Dubai

WATERMAN

Hilton JBR Project - StairCase Pressurization System

Bureau Veritas

Villa for Mr.AhmadFalaknaz @ Al Saffa

Client

Safeer Mall - Fujairah Consultair

Mr.Hamad Al GhurairResidential Villa – AlKhawaneej

Client

Commercial Development –Plot No. C-62, ME-10

ADCP

Rasas Al Mansoory Bidg. –M10, Plot No. 54, Musaffah

GERMAN MERIT

Ericcson office @ Jabel AliDown Town

Client

Page 21: STARS OASIS TECH. CONT. L.L.C HVAC TESTING AND COMMISSIONINGstarsoasis.com/images/CompanyProfile.pdf · HVAC Commissioning method statement Coordination and witnessing of Testing

LIST OF PROJECTS

PROJECT NAME CONSULTANT / CLIENT

Bright Point Hospital - AbuDhabi

STH Society

B+G+2+R Commercial andResidential Building

LECASSA

Safa Hyper Market - Al Ain AEC

American College ofCreative Science - Phase 3

Consultair

Dubai Festival City Mall -CHW

Client

General Authority of IslamicAffairs & Endowment - AlAin

KEO / GRANADA

G +1 Villa @ Jumeirah Engineers Office

Byrne Office andWarehouse

Client

SAFA Villa Extension-2 @Al Safa

Engineers Office

Al Tayer Motors L.L.C -SZR

CLIENT

Vasan Eye Care CLIENT

Islamic Affairs Commercial,Administration Building -Al Ain

KEO / GRANADA

G+3 LabourAccommodation @ JebelAli Industrial Area

CLIENT

Princess Tower KEO

SAFA Villa Extension-2 @Al Safa

Engineers Office

LIST OF PROJECTS

PROJECT NAME CONSULTANT / CLIENT

Bright Point Hospital - AbuDhabi

STH Society

B+G+2+R Commercial andResidential Building

LECASSA

Safa Hyper Market - Al Ain AEC

American College ofCreative Science - Phase 3

Consultair

Dubai Festival City Mall -CHW

Client

General Authority of IslamicAffairs & Endowment - AlAin

KEO / GRANADA

G +1 Villa @ Jumeirah Engineers Office

Byrne Office andWarehouse

Client

SAFA Villa Extension-2 @Al Safa

Engineers Office

Al Tayer Motors L.L.C -SZR

CLIENT

Vasan Eye Care CLIENT

Islamic Affairs Commercial,Administration Building -Al Ain

KEO / GRANADA

G+3 LabourAccommodation @ JebelAli Industrial Area

CLIENT

Princess Tower KEO

SAFA Villa Extension-2 @Al Safa

Engineers Office

LIST OF PROJECTS

PROJECT NAME CONSULTANT / CLIENT

Bright Point Hospital - AbuDhabi

STH Society

B+G+2+R Commercial andResidential Building

LECASSA

Safa Hyper Market - Al Ain AEC

American College ofCreative Science - Phase 3

Consultair

Dubai Festival City Mall -CHW

Client

General Authority of IslamicAffairs & Endowment - AlAin

KEO / GRANADA

G +1 Villa @ Jumeirah Engineers Office

Byrne Office andWarehouse

Client

SAFA Villa Extension-2 @Al Safa

Engineers Office

Al Tayer Motors L.L.C -SZR

CLIENT

Vasan Eye Care CLIENT

Islamic Affairs Commercial,Administration Building -Al Ain

KEO / GRANADA

G+3 LabourAccommodation @ JebelAli Industrial Area

CLIENT

Princess Tower KEO

SAFA Villa Extension-2 @Al Safa

Engineers Office

Page 22: STARS OASIS TECH. CONT. L.L.C HVAC TESTING AND COMMISSIONINGstarsoasis.com/images/CompanyProfile.pdf · HVAC Commissioning method statement Coordination and witnessing of Testing

LIST OF PROJECTS

PROJECT NAME CONSULTANT / CLIENT

Princess Haya Office @Dubai Health Care City

Engineers Office

Pullman Hotel AdditionalWorks - Pullman Hotel,MOE

NOR

Carrefour Market @ AlGhurair Centre

J.M.REGNAULT &PARTNERS

Lakhani Villa @ EmiratesHills

Al Saraya

ENOC 104-2 ENOC

MAF Policlinic @ DeiraCity Centre

Client

Zoom @ Souk Al Bahar ENOC

Zoom @ Al Raffa - Dubai ENOC

Zoom Market @ BusinessBay

ENOC

Zoom Market @ JLT ENOC

Gems United Indian School,Block 1 @ Baniyas

NEB

Business Park Building -First Floor, Phase 2,3&4 -Dubai World Central

DWC

Business Park Building(A12) @ DWC

DWC

Halcrow Office – AbuDhabi

HALCROW

33/11 kV Substations atTaweelah (101-1& 101-2)

ADDC

LIST OF PROJECTS

PROJECT NAME CONSULTANT / CLIENT

Princess Haya Office @Dubai Health Care City

Engineers Office

Pullman Hotel AdditionalWorks - Pullman Hotel,MOE

NOR

Carrefour Market @ AlGhurair Centre

J.M.REGNAULT &PARTNERS

Lakhani Villa @ EmiratesHills

Al Saraya

ENOC 104-2 ENOC

MAF Policlinic @ DeiraCity Centre

Client

Zoom @ Souk Al Bahar ENOC

Zoom @ Al Raffa - Dubai ENOC

Zoom Market @ BusinessBay

ENOC

Zoom Market @ JLT ENOC

Gems United Indian School,Block 1 @ Baniyas

NEB

Business Park Building -First Floor, Phase 2,3&4 -Dubai World Central

DWC

Business Park Building(A12) @ DWC

DWC

Halcrow Office – AbuDhabi

HALCROW

33/11 kV Substations atTaweelah (101-1& 101-2)

ADDC

LIST OF PROJECTS

PROJECT NAME CONSULTANT / CLIENT

Princess Haya Office @Dubai Health Care City

Engineers Office

Pullman Hotel AdditionalWorks - Pullman Hotel,MOE

NOR

Carrefour Market @ AlGhurair Centre

J.M.REGNAULT &PARTNERS

Lakhani Villa @ EmiratesHills

Al Saraya

ENOC 104-2 ENOC

MAF Policlinic @ DeiraCity Centre

Client

Zoom @ Souk Al Bahar ENOC

Zoom @ Al Raffa - Dubai ENOC

Zoom Market @ BusinessBay

ENOC

Zoom Market @ JLT ENOC

Gems United Indian School,Block 1 @ Baniyas

NEB

Business Park Building -First Floor, Phase 2,3&4 -Dubai World Central

DWC

Business Park Building(A12) @ DWC

DWC

Halcrow Office – AbuDhabi

HALCROW

33/11 kV Substations atTaweelah (101-1& 101-2)

ADDC

Page 23: STARS OASIS TECH. CONT. L.L.C HVAC TESTING AND COMMISSIONINGstarsoasis.com/images/CompanyProfile.pdf · HVAC Commissioning method statement Coordination and witnessing of Testing

LIST OF PROJECTS

PROJECT NAME CONSULTANT / CLIENT

33/11 kV Substations atTaweelah (101-3)

ADDC

33/11 kV Substations atICAD Residential City

P..B.POWER / ADDC

33/11 kV Substations at AlAin (Contract no. A-39001)

ADDC

132/33 Kv DEWASubstation @ Mushrif,Dubai

DEWA

132/33 Kv DEWASubstation @ Campus,Dubai

DEWA

132/33 Kv DEWASubstation @ Perl Jumeira,Dubai

DEWA

DEWA Substation @Business Bay Creek Village,Dubai

DEWA

DEWA Substation @ Arjan,Dubai

DEWA

DEWA Substation @ CanalBridge, Dubai

DEWA

DEWA Substation@Wellness Village, Dubai

DEWA

DEWA Substation @ DohaRoad, Dubai

DEWA

DEWA Substation @Theme Park, Dubai

DEWA

LIST OF PROJECTS

PROJECT NAME CONSULTANT / CLIENT

33/11 kV Substations atTaweelah (101-3)

ADDC

33/11 kV Substations atICAD Residential City

P..B.POWER / ADDC

33/11 kV Substations at AlAin (Contract no. A-39001)

ADDC

132/33 Kv DEWASubstation @ Mushrif,Dubai

DEWA

132/33 Kv DEWASubstation @ Campus,Dubai

DEWA

132/33 Kv DEWASubstation @ Perl Jumeira,Dubai

DEWA

DEWA Substation @Business Bay Creek Village,Dubai

DEWA

DEWA Substation @ Arjan,Dubai

DEWA

DEWA Substation @ CanalBridge, Dubai

DEWA

DEWA Substation@Wellness Village, Dubai

DEWA

DEWA Substation @ DohaRoad, Dubai

DEWA

DEWA Substation @Theme Park, Dubai

DEWA

LIST OF PROJECTS

PROJECT NAME CONSULTANT / CLIENT

33/11 kV Substations atTaweelah (101-3)

ADDC

33/11 kV Substations atICAD Residential City

P..B.POWER / ADDC

33/11 kV Substations at AlAin (Contract no. A-39001)

ADDC

132/33 Kv DEWASubstation @ Mushrif,Dubai

DEWA

132/33 Kv DEWASubstation @ Campus,Dubai

DEWA

132/33 Kv DEWASubstation @ Perl Jumeira,Dubai

DEWA

DEWA Substation @Business Bay Creek Village,Dubai

DEWA

DEWA Substation @ Arjan,Dubai

DEWA

DEWA Substation @ CanalBridge, Dubai

DEWA

DEWA Substation@Wellness Village, Dubai

DEWA

DEWA Substation @ DohaRoad, Dubai

DEWA

DEWA Substation @Theme Park, Dubai

DEWA

Page 24: STARS OASIS TECH. CONT. L.L.C HVAC TESTING AND COMMISSIONINGstarsoasis.com/images/CompanyProfile.pdf · HVAC Commissioning method statement Coordination and witnessing of Testing

LIST OF PROJECTS

PROJECT NAME CONSULTANT / CLIENT

132/11 kV Substation @Culture Village - Dubai

DEWA

33/11 kV PrimarySubstation @ Sorouh AlGhadeer

P..B.POWER / ADDC

FEWA Substation - 33/11kV Dhaid Substation

FEWA

FEWA Substation - 33/11kV Hospital Substation inU.A.Q

FEWA

FEWA Substation - 33/11kV Waterfront Substation inUAQ

FEWA

FEWA Substation - 33/11kV Qidfa Substation inFujairah

FEWA

FEWA Substation - 33/11kV AASMAH Substation

FEWA Substation - 33/11kV Corniche Substation inFujairah

FEWA

FEWA

FEWA Substation - 33/11kV IDHEN Substation

FEWA

FEWA Substation - 33/11kV R.A.K Main Substation -

FEWA

Zayed Military City – AlMaqta Project (Sites 1559,1536 & 1649)

KN PARTNERS

CMW-11006-C002 - AlHamra, Western Region

CMW

LIST OF PROJECTS

PROJECT NAME CONSULTANT / CLIENT

132/11 kV Substation @Culture Village - Dubai

DEWA

33/11 kV PrimarySubstation @ Sorouh AlGhadeer

P..B.POWER / ADDC

FEWA Substation - 33/11kV Dhaid Substation

FEWA

FEWA Substation - 33/11kV Hospital Substation inU.A.Q

FEWA

FEWA Substation - 33/11kV Waterfront Substation inUAQ

FEWA

FEWA Substation - 33/11kV Qidfa Substation inFujairah

FEWA

FEWA Substation - 33/11kV AASMAH Substation

FEWA Substation - 33/11kV Corniche Substation inFujairah

FEWA

FEWA

FEWA Substation - 33/11kV IDHEN Substation

FEWA

FEWA Substation - 33/11kV R.A.K Main Substation -

FEWA

Zayed Military City – AlMaqta Project (Sites 1559,1536 & 1649)

KN PARTNERS

CMW-11006-C002 - AlHamra, Western Region

CMW

LIST OF PROJECTS

PROJECT NAME CONSULTANT / CLIENT

132/11 kV Substation @Culture Village - Dubai

DEWA

33/11 kV PrimarySubstation @ Sorouh AlGhadeer

P..B.POWER / ADDC

FEWA Substation - 33/11kV Dhaid Substation

FEWA

FEWA Substation - 33/11kV Hospital Substation inU.A.Q

FEWA

FEWA Substation - 33/11kV Waterfront Substation inUAQ

FEWA

FEWA Substation - 33/11kV Qidfa Substation inFujairah

FEWA

FEWA Substation - 33/11kV AASMAH Substation

FEWA Substation - 33/11kV Corniche Substation inFujairah

FEWA

FEWA

FEWA Substation - 33/11kV IDHEN Substation

FEWA

FEWA Substation - 33/11kV R.A.K Main Substation -

FEWA

Zayed Military City – AlMaqta Project (Sites 1559,1536 & 1649)

KN PARTNERS

CMW-11006-C002 - AlHamra, Western Region

CMW

Page 25: STARS OASIS TECH. CONT. L.L.C HVAC TESTING AND COMMISSIONINGstarsoasis.com/images/CompanyProfile.pdf · HVAC Commissioning method statement Coordination and witnessing of Testing

LIST OF PROJECTS

PROJECT NAME CONSULTANT / CLIENT

Military Works No.233/2010 – Al Ain

CMW

Zayed Military City – Camp51

CMW

Zayed Military City – JEWCBuilding

CMW

Zayed Military City – AlMaqta Project

KN PARTNERS

Military Facilities @Maleha, Sharjah J608

CMW

Constructions at Camp No.121516, CMW-13048-C001

CMW

Contract No. CMW-11041-C 004

CMW

Construction of SimulatorBuilding @ Mahawi

CMW

Construction of Car Storesand Car Wash Chamber @Mahawi

CMW

Construction of DifferentFacilities @ Sih HefairPhase

Al Torath

Maintenance Hanger &ATC Tower

CMW

Zayed II Military College,Building 1A&1B

CMW

Construction of Al QassimiADNOC Filling Station -Sharjah

Al Burj EngineeringConsultants

Construction of Al Kutbi Al Burj Engineering

LIST OF PROJECTS

PROJECT NAME CONSULTANT / CLIENT

Military Works No.233/2010 – Al Ain

CMW

Zayed Military City – Camp51

CMW

Zayed Military City – JEWCBuilding

CMW

Zayed Military City – AlMaqta Project

KN PARTNERS

Military Facilities @Maleha, Sharjah J608

CMW

Constructions at Camp No.121516, CMW-13048-C001

CMW

Contract No. CMW-11041-C 004

CMW

Construction of SimulatorBuilding @ Mahawi

CMW

Construction of Car Storesand Car Wash Chamber @Mahawi

CMW

Construction of DifferentFacilities @ Sih HefairPhase

Al Torath

Maintenance Hanger &ATC Tower

CMW

Zayed II Military College,Building 1A&1B

CMW

Construction of Al QassimiADNOC Filling Station -Sharjah

Al Burj EngineeringConsultants

Construction of Al Kutbi Al Burj Engineering

LIST OF PROJECTS

PROJECT NAME CONSULTANT / CLIENT

Military Works No.233/2010 – Al Ain

CMW

Zayed Military City – Camp51

CMW

Zayed Military City – JEWCBuilding

CMW

Zayed Military City – AlMaqta Project

KN PARTNERS

Military Facilities @Maleha, Sharjah J608

CMW

Constructions at Camp No.121516, CMW-13048-C001

CMW

Contract No. CMW-11041-C 004

CMW

Construction of SimulatorBuilding @ Mahawi

CMW

Construction of Car Storesand Car Wash Chamber @Mahawi

CMW

Construction of DifferentFacilities @ Sih HefairPhase

Al Torath

Maintenance Hanger &ATC Tower

CMW

Zayed II Military College,Building 1A&1B

CMW

Construction of Al QassimiADNOC Filling Station -Sharjah

Al Burj EngineeringConsultants

Construction of Al Kutbi Al Burj Engineering

Page 26: STARS OASIS TECH. CONT. L.L.C HVAC TESTING AND COMMISSIONINGstarsoasis.com/images/CompanyProfile.pdf · HVAC Commissioning method statement Coordination and witnessing of Testing

LIST OF PROJECTS

PROJECT NAME CONSULTANT / CLIENT

ADNOC Filling Station -Sharjah

Consultants

Construction of ADNOCService Station - Ajman

Al Burj EngineeringConsultants

Construction of ADNOCService Station - Mushrif,Abu Dhabi

Al Thorath EngineeringConsultants

LIST OF PROJECTS

PROJECT NAME CONSULTANT / CLIENT

ADNOC Filling Station -Sharjah

Consultants

Construction of ADNOCService Station - Ajman

Al Burj EngineeringConsultants

Construction of ADNOCService Station - Mushrif,Abu Dhabi

Al Thorath EngineeringConsultants

LIST OF PROJECTS

PROJECT NAME CONSULTANT / CLIENT

ADNOC Filling Station -Sharjah

Consultants

Construction of ADNOCService Station - Ajman

Al Burj EngineeringConsultants

Construction of ADNOCService Station - Mushrif,Abu Dhabi

Al Thorath EngineeringConsultants


Top Related