Overview• Cost - $24.5 M• Schedule
– Let: June 2012– Construction: August 2012 – November 2013
• Major Features– Structures: 3 box culverts, 2 large culverts, 1 bridge– 3.5 miles STH 29– 3 miles local roads– Wetland Mitigation Site– Excavation: 400,000 CY Rock, 400,000 CY Common, 100,000 CY Borrow
• Staging– 4 stages– Counter directional traffic– ADT : 20,000