Appendix D: Project Listing preface D.0 2015 Plan Update
Transportation Outlook 2040 Project List
Transportation Outlook 2040 is the metropolitan transportation plan (MTP) for the greater Kansas City
region. A major component of the MTP is identifying a list of regionally important projects to improve the
transportation of people and goods (highway, transit, etc.). This federally required project listing is intended
to help the region identify and prioritize future transportation investments based on goals, strategies and
estimated financial resources. The projects in Transportation Outlook 2040 were developed, prioritized, and
ultimately selected through a comprehensive and coordinated process involving the general public, regional
transportation stakeholders and MARC planning committees.
Incorporation by Reference of the MARC Transportation Improvement Program
The Transportation Improvement Program (TIP) is a detailed list of projects to be implemented in the next
four to five years, and is developed for the metropolitan transportation planning process in accordance with
federal regulations (CFR §450.324). The TIP is incorporated into the MTP by reference, and therefore, upon
adoption by the MARC Board, the MTP shall include all projects in the most recently approved TIP as well as
any future TIP amendments approved before the next MTP update.
Financial Constraint
Federal planning regulations (CFR §450.322) state that “For the purpose of developing the metropolitan
transportation plan, the MPO, public transportation operator(s), and State shall cooperatively develop
estimates of funds that will be available to support metropolitan transportation plan implementation.”
The regulations also indicate “for illustrative purposes, the financial plan may (but is not required to)
include additional projects that would be included in the adopted transportation plan if additional
resources beyond those identified in the financial plan were to become available.”
Transportation Outlook 2040 includes “constrained” and “unconstrained” project lists. The financial plan
described in Appendix E: Financial Capacity demonstrates the availability of funding for projects in the
constrained list. The unconstrained list includes those projects that would be included in the plan if
additional resources beyond those identified in Appendix E become available.
To demonstrate financial
constraint in the plan, the
costs to operate, maintain
and preserve the
transportation system, in the
MARC MPO region, is
deducted from available
transportation revenues first,
and the remaining balance is
available for other
transportation investments.
The constrained project list
includes examples of
operations, management and
preservation projects in
addition to non-preservation
roadway and transit projects.
Category State Time Period Sponsor Project ID Facility/Program Location Description Capital Cost
Roadway KS 2015 to 2020
City of Bonner Springs
573 South 134th Street widening
Metropolitan to Kansas Avenue
Widening of South 134th Street. Improvements include curb and gutter, sidewalks, storm sewer, pavement markings, street lighting,
and replacement signage.
$4,050,000
Roadway KS 2015 to 2020
City of Bonner Springs
563 Metropolitan Avenue
Improvement Project
Between Nettleton Avenue and Western
City Limit line.
Widening of Metropolitan Avenue . Improvements include curb and gutter, sidewalks, grading improvements, storm sewer, pavement
markings, street lighting, and replacement signage.
$1,900,000
Roadway KS 2015 to 2020
City of Bonner Springs
744 Nettleton Avenue Extension
Nettleton Ave terminus NE side of K-
7 Interchange to Nettleton Ave
terminus south of Kansas Ave
This project includes the construction of a standard width three lane curb and gutter street. Improvements include curb and gutter,
sidewalks, storm sewer, pavement markings, street lighting, and replacement signage.
$2,500,000
Roadway KS 2015 to 2020
City of Bonner Springs
315 138th Street Improvements
between K-32 Highway and Kansas
Avenue
This project includes the widening of a narrow two lane ditched road to a standard width three lane curb and gutter street. Improvements include curb and gutter, sidewalks, storm sewer, pavement markings,
street lighting, and replacement signage.
$8,100,000
Roadway KS 2015 to 2020
City of Bonner Springs
576 Kansas Avenue Improvements
Between 134th Street and 138th Street
This project includes the widening of Kansas Avenue. Improvements include curb and gutter, sidewalks, storm sewer, pavement markings,
street lighting, and replacement signage.
$2,700,000
Roadway KS 2015 to 2020
City of Edgerton 2010 Waverly Road Reconstruction
Waverly Road US-56 to 199th Street
Reconstruction from US-56 to 199th Street; Project includes additional capacity and grade separation at BNSF rail crossing
$30,000,000
Roadway KS 2015 to 2020
City of Edwardsville 87 110th Street/Edwardsville Dr Reconstruction
I-70 to K-32 Reconstruct 110th Street/ Edwardsville Drive from I-70 south to K-32. Current road is a substandard 2 lane road section with a typical roadway width of 18 feet or less, numerous sight distance problems
and an ever increasing volume of traffic to be resolved.
$7,035,580
Roadway KS 2015 to 2020
City of Gardner 419 175th Street Improvements
I-35 to Clare Road The improvement will include 3250 lineal feet of divided arterial street with sidewalks, street lights, storm sewer and a traffic signal at
the Clare Road intersection.
$4,600,000
Roadway KS 2015 to 2020
City of Lansing 300 DeSoto Rd Reconstruction
Ida Street to Eisenhower Road
Reconstruct rural-type 2-lane road to current standard 4-lane facility to accommodate growing traffic demand. Construct RCB. Construct 10 ft. bicycle path and 5 ft. pedestrian sidewalk in accordance with
Trails Master Plan and city policy.
$7,219,000
Constrained Projects page 1 of 29Appendix D / Transportation Outlook 2040 2015 Plan Update
Category State Time Period Sponsor Project ID Facility/Program Location Description Capital Cost
Roadway KS 2015 to 2020
City of Leavenworth 539 Eisenhower Road Construction
155th Street west to (future) 30th Street
(County Road 29)
Construction Eisenhower Road as a four lane road west from K-5 to 155th Street in the last few years. It is proposed that a four lane
roadway would be extended west to County Road 5, and possibly an initial improved two lane roadway west to County Road 29.
$30,000,000
Roadway KS 2015 to 2020
City of Leawood 79 143rd Street Improvements
Nall to Kenneth Road The project will improve the current 2-lane ditch street to a 4-lane street with curb and gutter, streetlights, storm sewer, sidewalk,
bike/hike trail, and bicycle access. A traffic signal will be installed at the intersection of 143rd and Mission Road.
$23,400,000
Roadway KS 2015 to 2020
City of Lenexa 261 87th & I-435 Interchange
87th Street and I-435 interchange
Improvements to the existing interchange to provide capacity on the interchange ramps and on 87th Street to meet the projected traffic
demand.
$5,000,000
Roadway KS 2015 to 2020
City of Lenexa 263 95th Street Improvements
95th Street from Renner to I-35
Improve and widen to 4-lane divided roadway with sidewalks, street lights storm sewers, landscaping and storm water management
BMPs. This project will provide a mixed use trail as this is a MetroGreen Corridor.
$15,000,000
Roadway KS 2015 to 2020
City of Lenexa 256 K-10 & Ridgeview Interchange
K-10 Highway and Ridgeview Road
Improvements to the existing interchange to provide capacity on the interchange ramps and on Woodland Road under K-10 to meet the
projected traffic demand.
$12,000,000
Roadway KS 2015 to 2020
City of Lenexa 254 K-10 & Lone Elm Interchange
K-10 Highway and Lone Elm Road
New interchange including street lights, sidewalks, storm sewers, landscaping and storm water management, BMPs
$20,000,000
Roadway KS 2015 to 2020
City of Olathe 330 Lone Elm Improvements
Old 56 Hwy to 151st Street
Capacity improvement for future K-7 alignment, from a rural 2 lane to 4 lane divided arterial.
$22,100,000
Roadway KS 2015 to 2020
City of Olathe 329 Lone Elm Improvements
167th Street to 171st Street
Capacity improvement for future K-7 alignment, from a rural 2 lane to 4 lane divided arterial.
$8,000,000
Roadway KS 2015 to 2020
City of Olathe 328 Lone Elm Improvements
159th Street to 167th Street
Capacity improvement for future K-7 alignment, from a rural 2 lane to 4 lane divided arterial.
$8,000,000
Roadway KS 2015 to 2020
City of Olathe 325 119th Improvements
Lone Elm to Iowa Capacity improvements from 2 lane to 4 lane. $4,000,000
Roadway KS 2015 to 2020
City of Olathe 324 119th Improvements
Iowa to Woodland Capacity improvements from 2 lane to 4 lane. $4,000,000
Roadway KS 2015 to 2020
City of Olathe 323 K-7 Improvements 135th to Old 56 Hwy. Capacity improvement, widening from 4 to 5 lanes. $6,000,000
Constrained Projects page 2 of 29Appendix D / Transportation Outlook 2040 2015 Plan Update
Category State Time Period Sponsor Project ID Facility/Program Location Description Capital Cost
Roadway KS 2015 to 2020
City of Olathe 322 College Blvd and K-7 Interchange
College Blvd and K-7 Interchange
Interchange capacity improvement, installing Roundabouts at the ramp junctions. Extend life of bridge.
$2,000,000
Roadway KS 2015 to 2020
City of Olathe 320 135th St improvements
Clairborne to Mur-Len Capacity improvement, widening from 4 to 6 lanes. $8,000,000
Roadway KS 2015 to 2020
City of Olathe 332 Ridgeview and K-10 Interchange
Ridgeview and K-10 Interchange
Interchange capacity improvement, installing Roundabouts at the ramp junctions. Extend life of bridge.
$2,000,000
Roadway KS 2015 to 2020
City of Overland Park
308 Blue Valley Pkwy Widening
123rd St. to US-69 in Overland Park
The project includes widening Blue Valley Pkwy from a four-lane divided roadway to a six-lane divided thoroughfare with turn lanes,
storm sewers, a raised median, sidewalks, street lights, traffic signals, ADA compliant facilities, restoration and other items incidental to the
street construction.
$2,500,000
Roadway KS 2015 to 2020
City of Overland Park
287 159th Street reconstruction
Pflumm to Quivira in Overland Park
The project includes reconstruction of 159th Street from an unimproved two-lane roadway to a four-lane divided thoroughfare
with turn lanes, storm sewers, a raised median, sidewalks, street lights, traffic signals, ADA compliant facilities, restoration and other
items incidental to the street construction.
$6,000,000
Roadway KS 2015 to 2020
City of Overland Park
249 Quivira Road reconstruction and
widening
151st St. to 159th St. in Overland Park
The project includes reconstruction of Quivira Road from an unimproved two-lane roadway to a four-lane divided thoroughfare
with turn lanes, storm sewers, a raised median, sidewalks, street lights, traffic signals, ADA compliant facilities, restoration and other
items incidental to the street construction.
$6,000,000
Roadway KS 2015 to 2020
City of Overland Park
299 119th Street Widening
Pflumm to US-69 in Overland Park
The project includes widening 119th Street from a four-lane divided thoroughfare to a six-lane divided thoroughfare with turn lanes,
storm sewers, a raised median, sidewalks, street lights, traffic signals, ADA compliant facilities, restoration and other items incidental to the
street construction.
$8,000,000
Roadway KS 2015 to 2020
City of Overland Park
284 151st Street reconstruction
Chadwick to State Line in Overland Park
The project includes reconstruction of 151st Street from an unimproved two-lane roadway to a four-lane divided thoroughfare
with turn lanes, storm sewers, a raised median, sidewalks, street lights, traffic signals, ADA compliant facilities, restoration and other
items incidental to the street construction.
$5,000,000
Constrained Projects page 3 of 29Appendix D / Transportation Outlook 2040 2015 Plan Update
Category State Time Period Sponsor Project ID Facility/Program Location Description Capital Cost
Roadway KS 2015 to 2020
City of Overland Park
306 135th Street Widening
Pflumm to Switzer in Overland Park
The project includes widening 135th Street from a four-lane divided thoroughfare to a six-lane divided thoroughfare with turn lanes,
storm sewers, a raised median, sidewalks, street lights, traffic signals, ADA compliant facilities, restoration and other items incidental to the
street construction.
$8,000,000
Roadway KS 2015 to 2020
City of Overland Park
289 159th Street reconstruction
Metcalf to Kenneth in Overland Park
The project includes reconstruction of 159th Street from an unimproved two-lane roadway to a four-lane divided thoroughfare
with turn lanes, storm sewers, a raised median, sidewalks, street lights, traffic signals, ADA compliant facilities, restoration and other
items incidental to the street construction.
$15,000,000
Roadway KS 2015 to 2020
City of Overland Park
293 Quivira Road Widening
119th St. to 143rd St. in Overland Park
The project includes widening Quivira Road from a four-lane divided thoroughfare to a six-lane divided thoroughfare with turn lanes,
storm sewers, a raised median, sidewalks, street lights, traffic signals, ADA compliant facilities, restoration and other items incidental to the
street construction.
$12,000,000
Roadway KS 2015 to 2020
City of Overland Park
294 Antioch Road Widening
119th St. to 135th St. in Overland Park
The project includes widening Antioch Road from a four-lane divided thoroughfare to a six-lane divided thoroughfare with turn lanes,
storm sewers, a raised median, sidewalks, street lights, traffic signals, ADA compliant facilities, restoration and other items incidental to the
street construction.
$8,000,000
Roadway KS 2015 to 2020
City of Overland Park
296 Metcalf Avenue Widening
119th St. to 135th St. in Overland Park
The project includes widening Metcalf Avenue from a four-lane divided thoroughfare to a six-lane divided thoroughfare with turn
lanes, storm sewers, a raised median, sidewalks, street lights, traffic signals, ADA compliant facilities, restoration and other items
incidental to the street construction.
$8,000,000
Roadway KS 2015 to 2020
City of Overland Park
297 Metcalf Avenue Widening
135th St. to 159th St. in Overland Park
The project includes widening Metcalf Avenue from a four-lane divided thoroughfare to a six-lane divided thoroughfare with turn
lanes, storm sewers, a raised median, sidewalks, street lights, traffic signals, ADA compliant facilities, restoration and other items
incidental to the street construction.
$12,000,000
Roadway KS 2015 to 2020
City of Overland Park
305 119th Street Widening
Nall to Roe in Overland Park
The project includes widening east bound 119th Street to complete a six-lane divided thoroughfare with turn lanes, storm sewers, a raised
median, sidewalks, street lights, traffic signals, ADA compliant facilities, restoration and other items incidental to the street
construction.
$1,000,000
Constrained Projects page 4 of 29Appendix D / Transportation Outlook 2040 2015 Plan Update
Category State Time Period Sponsor Project ID Facility/Program Location Description Capital Cost
Roadway KS 2015 to 2020
City of Overland Park
280 Metcalf Avenue reconstruction
159th St. to 183rd St. in Overland Park
The project includes reconstruction of Metcalf Avenue from an unimproved two-lane roadway to a four-lane divided thoroughfare
with turn lanes, storm sewers, a raised median, sidewalks, street lights, traffic signals, ADA compliant facilities, restoration and other
items incidental to the street construction.
$15,000,000
Roadway KS 2015 to 2020
City of Shawnee 240 Johnson Drive and I-435 Interchange
improvements
Johnson Drive and I-435
This project will include signalization of the on/off ramps related to I-435 and Johnson Drive interchange. This project will also involve geometric improvements to prove exclusive right turn lanes at the
ramps along Johnson Drive.
$2,000,000
Roadway KS 2015 to 2020
City of Shawnee 238 Nieman Road Reconstruction
64th Street to Johnson Drive
This improvements to this segment of Nieman Road will include streetscape items such as paver brick sidewalks, benches, lighting,
and other enhancement features.
$5,000,000
Roadway KS 2015 to 2020
City of Shawnee 235 Quivira Road reconstruction and
widening
47th Street to 52nd Terrace
The project will provide reconstruction, widening, on-street bicycle lanes for a section of Quivira, and sidewalks on each side.
$1,800,000
Roadway KS 2015 to 2020
City of Tonganoxie 447 Laming Road Construction
Laming Road and Leavenworth County
Road to 4th Street.
This project will be built to comply with the planning done in the US 24/40 Corridor Access and Traffic Management Plan.
$2,540,000
Roadway KS 2015 to 2020
City of Tonganoxie 445 Woodfield Drive Extension
Woodfield Drive and Leavenworth County Road 5 thence east to
193rd Street
Comply with the planning provisions in the US 24/40 Corridor Access and Traffic Management Plan
$8,100,000
Roadway KS 2015 to 2020
City of Tonganoxie 446 1st Street Collector First and Ridge thence east to 206th Street
The project is built to comply with the planning goals in US 24/40 Corridor Access and Traffic Management Plan
$8,000,000
Roadway KS 2015 to 2020
Johnson County, Kansas - Public
Works
108 191st Street Improvements
Gardner Road to Four Corners
Construction of 191st Street will provide access to the Gardner Road Interchange on I-35 for the proposed BNSF Intermodal site and
logistics park. The majority of the existing roadway is gravel and will be upgraded to an asphalt roadway 40 feet in width with curb and
gutter.
$14,000,000
Roadway KS 2015 to 2020
KDOT 704 I-70/K-7 Interchange
phases 2, 5, 6, 7, 8 and 16
I-70/K-7 Reconstruction and capacity improvements of the I-70/K-7 Interchange. The interchange concept includes interchanges at I-70,
130th Street, and Kansas Avenue.
$31,800,000
Constrained Projects page 5 of 29Appendix D / Transportation Outlook 2040 2015 Plan Update
Category State Time Period Sponsor Project ID Facility/Program Location Description Capital Cost
Roadway KS 2015 to 2020
KDOT 3014 I-435/State Avenue DDI
I-435/State Avenue interchange
At I-435/State Avenue interchange in Wyandotte County, construction of a diverging diamond interchange to replace existing
configuration
$25,072,000
Roadway KS 2015 to 2020
Leavenworth County 684 Centennial Bridge Rehabilitation
K-92 Bridge Over Missouri River.
Rehabilitate the existing bridge structure, and widen the bridge from two (2) to four (4) lanes to increase capacity.
$42,000,000
Roadway KS 2015 to 2020
Leavenworth County 674 State Highway K-5 Realignment
From K-7 and McIntyre Road to I-
435 at Wolcott Road
Realign K-5 between K-7 and I-435 $39,500,000
Roadway KS 2021 to 2030
City of Gardner 697 175th Street Widening
West of Waverly Road to City Limits
This project includes the widening of 175th Street from a 2-lane ditch section to a 4-lane divided street section along with sidewalk, trail,
street lights, storm sewer, and additional appurtenant items.
$6,500,000
Roadway KS 2021 to 2030
City of Lansing 92 DeSoto Road Reconstruction
4-H Road to Ida Street, including
intersection approaches.
Reconstruct rural-type 2-lane road to current standard 4- lane facility to accommodate growing traffic demand. Replace functionally
obsolete bridge. Construct 10 ft. bicycle path and 5 ft. pedestrian sidewalk in accordance with Trails Master Plan and city policy.
$7,988,750
Roadway KS 2021 to 2030
City of Lansing 224 147th Street Reconstruction
McIntyre Road to 4-H Road
Reconstruct 2 1/2 miles of rural-type 2-lane road to current standard 4-lane facility to accommodate growing traffic demand. Replace
bridges. Construct 10 ft. bicycle path and 5 ft. pedestrian sidewalk in accordance with Trails Master Plan and city policy.
$16,967,500
Roadway KS 2021 to 2030
City of Leawood 65 Mission Road Improvements
135th to 151st Street. Improvement to a 4-lane undivided curb and gutter street with LED streetlights, storm sewer, sidewalks, bike/hike trail, and bike lanes.
$20,400,000
Roadway KS 2021 to 2030
City of Leawood 63 151st Street Improvements
Nall to east City Limit The improvements include widening 151st from a 2-lane ditch street to a 4-lane divided roadway with LED streetlights, traffic signal,
sidewalk, bike/hike trail, and on-street bike lanes.
$14,200,000
Roadway KS 2021 to 2030
City of Lenexa 268 College Boulevard Improvements
Renner Boulevard to Pflumm Road.
Improve and widen to 6-lane divided roadway with sidewalks, street lights storm sewers, landscaping and storm water management BMPs.
$12,000,000
Roadway KS 2021 to 2030
City of Lenexa 267 Lackman Rd Improvements
107th Street to Santa Fe Trail Drive
Improve and widen to 4-lane divided roadway with sidewalks, street lights storm sewers, landscaping and storm water management BMPs.
$6,000,000
Constrained Projects page 6 of 29Appendix D / Transportation Outlook 2040 2015 Plan Update
Category State Time Period Sponsor Project ID Facility/Program Location Description Capital Cost
Roadway KS 2021 to 2030
City of Lenexa 262 95th & I-435 Interchange
95th Street and I-435 interchange
Improvements to the existing interchange to provide capacity on the interchange ramps and on the bridge over I-435 to meet the
projected traffic demand. Including bike/ped trail connecting to the Prairie Star Parkway MetroGreen corridor.
$5,000,000
Roadway KS 2021 to 2030
City of Lenexa 260 87th St Improvements
K-7 Highway to Haven Improve and widen to 4-lane divided roadway with sidewalks, street lights storm sewers, landscaping and storm water management BMPs.
$26,000,000
Roadway KS 2021 to 2030
City of Lenexa 253 Lone Elm improvements
Prairie Star Parkway to K-10 Highway.
Improve and widen to 4-lane divided roadway with sidewalks, street lights storm sewers, landscaping and storm water management BMPs.
$5,000,000
Roadway KS 2021 to 2030
City of Lenexa 255 K-10 & Woodland Interchange
K-10 Highway and Woodland Road
Improvements to the existing interchange to provide capacity on the interchange ramps and on Woodland Road under K-10 to meet the
projected traffic demand.
$5,000,000
Roadway KS 2021 to 2030
City of Olathe 480 Ridgeview Improvements
KC Road to 135th Street.
Capacity improvement, widening from 4 to 6 lanes. $6,000,000
Roadway KS 2021 to 2030
City of Olathe 355 Ridgeview Improvements
119th Street to 127th Street
Capacity improvement, widening from 4 to 6 lanes. $6,000,000
Roadway KS 2021 to 2030
City of Olathe 354 Old 56 Improvements
K-7 Hwy to Bridge Capacity improvement from a rural 2 lane to 4 lane divided arterial. $6,000,000
Roadway KS 2021 to 2030
City of Olathe 520 135th St Improvements
Mur-Len to Black Bob Capacity improvement, widening from 4 to 6 lanes. $6,000,000
Roadway KS 2021 to 2030
City of Olathe 353 Old 56 Improvements
Bridge to 151st Capacity improvement from a rural 2 lane to 4 lane divided arterial. $6,000,000
Roadway KS 2021 to 2030
City of Olathe 352 KC Road Improvements
Renner to Ridgeview Capacity improvement, widening from 4 to 5 lanes. $11,000,000
Roadway KS 2021 to 2030
City of Olathe 351 College Blvd Improvements
Lone Elm to Woodland Capacity improvements from 2 lane to 4 lane. $13,000,000
Roadway KS 2021 to 2030
City of Olathe 347 119th St Improvements
Ridgeview to Renner Capacity improvement, widening from 4 to 6 lanes. $6,000,000
Roadway KS 2021 to 2030
City of Olathe 346 119th St Improvements
Renner to I-35. Capacity improvement, widening eastbound lanes from 2 to 3 lanes. $2,500,000
Constrained Projects page 7 of 29Appendix D / Transportation Outlook 2040 2015 Plan Update
Category State Time Period Sponsor Project ID Facility/Program Location Description Capital Cost
Roadway KS 2021 to 2030
City of Olathe 498 175th Improvements
K-7 Hwy to Ridgeview Capacity improvement from a rural 2 lane to 4 lane divided arterial. $13,000,000
Roadway KS 2021 to 2030
City of Olathe 490 Black Bob Improvements
135th Street to 139th Street
Capacity improvement, widening from 4 to 6 lanes. $2,000,000
Roadway KS 2021 to 2030
City of Olathe 491 Black Bob Improvements
151st Street to 159th Street
Capacity improvements from 2 lane to 4 lane. $13,000,000
Roadway KS 2021 to 2030
City of Olathe 492 College Blvd Improvements
West city limits to Clare
Capacity improvements from 2 lane to 4 lane. $20,000,000
Roadway KS 2021 to 2030
City of Olathe 493 Pflumm Improvements
143rd Street to 151st Street
Capacity improvements from 2 lane to 4 lane. $13,000,000
Roadway KS 2021 to 2030
City of Olathe 494 Woodland and K-10 Interchange
Woodland and K-10 Interchange
Interchange capacity improvement, installing Roundabouts at the ramp junctions.
$2,000,000
Roadway KS 2021 to 2030
City of Olathe 487 151st Construction Old 56 Hwy to Lone Elm
Construct missing link of 151st Street, including bridge over BNSF railroad and Cedar Creek. Construct 4 lane divided arterial.
$15,000,000
Roadway KS 2021 to 2030
City of Olathe 478 Ridgeview Improvements
College Blvd to 119th Street.
Capacity improvement, widening from 4 to 6 lanes. $6,000,000
Roadway KS 2021 to 2030
City of Olathe 484 127th Improvements
K-7 Hwy to Iowa. Capacity improvements from 2 lane to 4 lane. $7,000,000
Roadway KS 2021 to 2030
City of Olathe 511 Black Bob Improvements
127th Street to 135th Street
Capacity improvement, widening from 4 to 6 lanes. $6,000,000
Roadway KS 2021 to 2030
City of Olathe 482 K-7 Future Realignment
171st Street to 183rd Street.
Realignment of existing K-7 Hwy in compliance with the K-7 corridor plan.
$0
Roadway KS 2021 to 2030
City of Olathe 481 135th Bridge widening
135th Street bridge over I-35.
Bridge widening and geometric modifications to serve increased traffic demand.
$6,000,000
Roadway KS 2021 to 2030
City of Olathe 337 135th Improvements
Hedge Lane to K-7 Capacity improvement, widening from 4 to 6 lanes. $6,000,000
Roadway KS 2021 to 2030
City of Olathe 479 Ridgeview Improvements
K-10 to College Blvd. Capacity improvement, widening from 4 to 6 lanes. $6,000,000
Roadway KS 2021 to 2030
City of Olathe 489 159th Improvements
Ridgeview to Mur-Len Roadway project to improve capacity from 2 lanes to four lanes. $13,000,000
Constrained Projects page 8 of 29Appendix D / Transportation Outlook 2040 2015 Plan Update
Category State Time Period Sponsor Project ID Facility/Program Location Description Capital Cost
Roadway KS 2021 to 2030
City of Olathe 510 Black Bob Improvements
119th Street to 127th Street
Capacity improvement, widening from 4 to 6 lanes. $6,000,000
Roadway KS 2021 to 2030
City of Olathe 486 127th Improvements
Woodland to Ridgeview
Capacity improvements from 2 lane to 4 lane. $19,000,000
Roadway KS 2021 to 2030
City of Olathe 336 135th Improvements
Black Bob to Pflumm Capacity improvement, widening from 4 to 6 lanes. $6,000,000
Roadway KS 2021 to 2030
City of Olathe 335 127th and K-7 Interchange
127th and K-7 (future interchange)
New Roundabout Interchange replacing an at-grade intersection. $2,000,000
Roadway KS 2021 to 2030
City of Olathe 333 119th Improvements
Black Bob to Pflumm Capacity improvement, widening from 4 to 6 lanes. $6,000,000
Roadway KS 2021 to 2030
City of Olathe 136 119th and K-7 capacity
improvement
119th and K-7 interchange
Interchange capacity improvement, installing Roundabouts at the ramp junctions. Extend life of bridge.
$3,000,000
Roadway KS 2021 to 2030
City of Olathe 345 119th Improvements
K-7 to Lone Elm Increase from 2 lanes to 4 lanes $13,000,000
Roadway KS 2021 to 2030
City of Olathe 344 135th Improvements
Ridgeview to Clairborne
Capacity improvement, widening from 4 to 6 lanes. $8,000,000
Roadway KS 2021 to 2030
City of Overland Park
291 175th/179th St Widening
Lackman to Metcalf in Overland Park
The project includes widening 175th/179th Street from a two-lane roadway to a four-lane divided thoroughfare with turn lanes, storm sewers, a raised median, sidewalks, street lights, traffic signals, ADA
compliant facilities, restoration and other items incidental to the street construction.
$25,000,000
Roadway KS 2021 to 2030
City of Overland Park
269 Quivira Road reconstruction
179th St. to 191st St. in Overland Park
The project includes reconstruction of Quivira Road from an unimproved two-lane roadway to a four-lane divided thoroughfare
with turn lanes, storm sewers, a raised median, sidewalks, street lights, traffic signals, ADA compliant facilities, restoration and other
items incidental to the street construction.
$7,500,000
Roadway KS 2021 to 2030
City of Overland Park
276 Antioch Road reconstruction
167th St. to 179th St. in Overland Park
The project includes reconstruction of Antioch Road from an unimproved two-lane roadway to a four-lane divided thoroughfare
with turn lanes, storm sewers, a raised median, sidewalks, street lights, traffic signals, ADA compliant facilities, restoration and other
items incidental to the street construction.
$7,500,000
Constrained Projects page 9 of 29Appendix D / Transportation Outlook 2040 2015 Plan Update
Category State Time Period Sponsor Project ID Facility/Program Location Description Capital Cost
Roadway KS 2021 to 2030
City of Overland Park
278 Antioch Road reconstruction
179th St. to 199th St. in Overland Park
The project includes reconstruction of Antioch Road from an unimproved two-lane roadway to a four-lane divided thoroughfare
with turn lanes, storm sewers, a raised median, sidewalks, street lights, traffic signals, ADA compliant facilities, restoration and other
items incidental to the street construction.
$12,500,000
Roadway KS 2021 to 2030
City of Overland Park
706 US-69 Improvements
(Phase I)
151st Street to I-435 Reconstruct US-69 and add through lanes from 135th St. to I-435, construct northbound collector-distributor (C-D) road between 135th
& Blue Valley Pkwy, and construct auxiliary lanes from 151st St. to 135th St.
$210,000,000
Roadway KS 2021 to 2030
City of Overland Park
281 Kenneth Road reconstruction
143rd St. to 159th St. in Overland Park
The project includes reconstruction of Kenneth Road from an unimproved two-lane roadway to a four-lane divided thoroughfare
with turn lanes, storm sewers, a raised median, sidewalks, street lights, traffic signals, ADA compliant facilities, restoration and other
items incidental to the street construction.
$10,000,000
Roadway KS 2021 to 2030
City of Overland Park
3000 Quivira Road reconstruction
159th St. to 179th St. in Overland Park
The project includes reconstruction of Quivira Road from an unimproved two-lane roadway to a four-lane divided thoroughfare
with turn lanes, storm sewers, a raised median, sidewalks, street lights, traffic signals, ADA compliant facilities, restoration and other
items incidental to the street construction.
$15,000,000
Roadway KS 2021 to 2030
City of Overland Park
290 167th Street reconstruction
Antioch to Metcalf in Overland Park
The project includes reconstruction of the 167th Street interchange as a full access diamond, reconstruction of 167th Street from an
unimproved two-lane roadway to a four-lane divided thoroughfare with turn lanes, storm sewers, a raised median, sidewalks, street
lights, traffic signals, ADA compliant facilities, restoration and other items incidental to the street construction.
$22,000,000
Roadway KS 2021 to 2030
City of Overland Park
292 199th Street Widening
Antioch to US-69 in Overland Park
The project includes widening 199th Street from a two-lane roadway to a four-lane divided thoroughfare with turn lanes, storm sewers, a raised median, sidewalks, street lights, traffic signals, ADA compliant
facilities, restoration and other items incidental to the street construction.
$2,500,000
Roadway KS 2021 to 2030
City of Overland Park
309 135th Street Widening
Switzer to Nall in Overland Park
The project includes widening 135th Street from a six-lane divided thoroughfare to a eight-lane divided thoroughfare with turn lanes,
storm sewers, a raised median, sidewalks, street lights, traffic signals, ADA compliant facilities, restoration and other items incidental to the
street construction.
$12,000,000
Constrained Projects page 10 of 29Appendix D / Transportation Outlook 2040 2015 Plan Update
Category State Time Period Sponsor Project ID Facility/Program Location Description Capital Cost
Roadway KS 2021 to 2030
City of Overland Park
307 151st Street Widening
Rosehill to Nall in Overland Park
The project includes widening 151st Street from a four-lane divided thoroughfare to a six-lane divided thoroughfare with turn lanes,
storm sewers, a raised median, sidewalks, street lights, traffic signals, ADA compliant facilities, restoration and other items incidental to the
street construction. T
$18,000,000
Roadway KS 2021 to 2030
City of Overland Park
295 Antioch Road Widening
135th St. to 167th St. in Overland Park
The project includes widening Antioch Road from a four-lane divided thoroughfare to a six-lane divided thoroughfare with turn lanes,
storm sewers, a raised median, sidewalks, street lights, traffic signals, ADA compliant facilities, restoration and other items incidental to the
street construction.
$16,000,000
Roadway KS 2021 to 2030
City of Shawnee 67 Monticello Road widening
Midland Drive to 7900 Block
The project will provide reconstruction and widening of Monticello Road, from Midland Drive to the 7900 block. Monticello Road, from
71st Street south, will follow a new alignment. In addition to the road widening, this project includes on-street bicycle lanes, a recreational trail on the west side of Monticello and a sidewalk on the east side. A
roundabout will be installed at the new 75th and Monticello Road intersection.
$13,700,000
Roadway KS 2021 to 2030
City of Shawnee 233 Lackman Road Renner Road
75th Street to Johnson Drive
The project will provide reconstruction and widening of Lackman Road, from 75th Street to Johnson Drive. Lackman Road does not
currently exist between 63rd Street and Johnson Drive. In addition to the road widening, this project includes off-street recreational trail
facilities on one side and a standard sidewalk on the other.
$10,000,000
Roadway KS 2021 to 2030
City of Shawnee 228 Woodland Road reconstruction and
widening
71st Street to 7900 Block
The project will provide reconstruction and widening of Woodland Road, from the 7100 Block to the 7900 block. Woodland Road, from approximately the 7700 block north, will follow a new alignment. In addition to the road widening, a segment of Woodland will include
on-street bicycle lanes and sidewalks on each side.
$6,700,000
Roadway KS 2021 to 2030
City of Shawnee 236 Shawnee Mission Parkway Widening
Pflumm Road to I-435 This project would widen the existing roadway to 6 lanes, provide improved drainage, and provide better ramp access at Lackman and
Maurer.
$15,000,000
Roadway KS 2021 to 2030
City of Shawnee 229 75th Street reconstruction and
widening
Monticello Road to Mize Road
The project will provide reconstruction and widening of 75th Street, from Monticello Road to Mize Road. In addition to the road
widening, this project includes on-street bicycle lanes, and sidewalks on both sides of the street.
$13,700,000
Constrained Projects page 11 of 29Appendix D / Transportation Outlook 2040 2015 Plan Update
Category State Time Period Sponsor Project ID Facility/Program Location Description Capital Cost
Roadway KS 2021 to 2030
City of Shawnee 230 67th Street Construction
Gleason Road to Mize Road
The proposed 67th Street does not exist today but would extend 67th west of Gleason Road and connect to Mize Road. This project
includes pedestrian sidewalks on both sides.
$6,700,000
Roadway KS 2021 to 2030
City of Shawnee 241 K-7 Highway Interchanges
improvements
K-7 Intersections at 43rd Street, 47th
Street, 71st Street, 75th Street, Shawnee Mission Parkway and
83rd Street.
Convert all at-grade intersections along K-7 Highway to separated interchanges.
$75,000,000
Roadway KS 2021 to 2030
City of Shawnee 232 Renner Road reconstruction and
widening
79th Street to Holliday Drive
The project will provide reconstruction and widening of Renner Road, from Holliday Drive to the 7900 block. In addition to the road
widening, this project includes on-street bicycle lanes, and sidewalks on each side.
$22,000,000
Roadway KS 2021 to 2030
City of Shawnee 231 Shawnee Mission Parkway Widening
K-7 Highway to I-435 This project would widen the existing roadway to 6 lanes, provide improved drainage, and provide new bridge structures over I-435, K-7
Highway, and over mill creek Railroad.
$35,000,000
Roadway KS 2021 to 2030
City of Tonganoxie 431 206th Street Parkway Phase II
From US 24/40 south to future Honey Creek
Road alignment
comply with the planning in the US 24/40 Corridor Access and Traffic Management Plan
$10,625,000
Roadway KS 2021 to 2030
City of Tonganoxie 443 206th Street Parkway Phase III
206th Street and Honey Creek Road thence south and
west to the to Leavenworth County
Road 1 between Honey Creek Road and Hemphill Road
Comply with the Tonganoxie Comprehensive Plan $9,860,000
Roadway KS 2021 to 2030
City of Tonganoxie 458 14th Street Construction
14th Street and US 24/40 thence east to
214 Street
The construction of this route is planned in the US 24/40 Corridor Access and Traffic Management Plan
$2,188,000
Roadway KS 2021 to 2030
City of Tonganoxie 450 East Street Extension
4th Street and East Street, thence south
Honey Creek Road
This project is built to comply with the provisions of US 24/40 Corridor Access and Traffic Management Plan
$8,500,000
Constrained Projects page 12 of 29Appendix D / Transportation Outlook 2040 2015 Plan Update
Category State Time Period Sponsor Project ID Facility/Program Location Description Capital Cost
Roadway KS 2021 to 2030
City of Tonganoxie 411 206th Street Parkway Phase I
Leavenworth County Road 5 thence south
to US 24/40
Comply with the planning goals in US 24/40 Corridor Access and Traffic Management Plan
$459,000
Roadway KS 2021 to 2030
City of Tonganoxie 460 Washington Street Construction
Washington Street and US 24/40 going
east along Washington Street to
198th Street
The project includes a new street and a new bridge over Tonganoxie Creek. It also builds a pedestrian crossing onto the Tonganoxie Creek
Bridge as a part of the SRTS plan.
$12,750,000
Roadway KS 2021 to 2030
Johnson County, Kansas - Public
Works
120 199th Street Improvement
Stilwell Community area to Mission Road
Improvement of a rural standard roadway to a 40 wide street with curb and gutter. The project includes a railroad grade separation.
$7,500,000
Roadway KS 2021 to 2030
KDOT 3004 K-7 upgrade 175th Street to 215th Street
Modify K-7 to freeway design standards $60,500,000
Roadway KS 2021 to 2030
KDOT 3002 K-7 upgrade 43rd Street to K-10 Modify K-7 to freeway design standards $46,200,000
Roadway KS 2021 to 2030
KDOT 655 I-35 Reconstruction I-435 to 67th Street Reconstruct, widen, and implement operations strategies along approximately 5 miles of I-35 in order to meet the corridors needs
and future expected travel demand.
$140,000,000
Roadway KS 2021 to 2030
KDOT 3003 K-7 intersection enhancements
K-7 from Lansing to State Ave
Construct expressway intersection enhancements from the City of Lansing to State Avenue.
$21,000,000
Roadway KS 2021 to 2030
KDOT 3010 I-70/K-7 Interchange (phases 9-15)
I-70/K-7 Interchange Complete phases 9-15 of interchange improvements. The interchange concept includes interchanges at I-70, 130th Street, and Kansas Avenue. K-7 will have collector-distributor roads to separate through traffic from ramp traffic, and the project will extend from
Kansas Avenue on the south to 130th St. on the north.
$292,500,000
Roadway KS 2021 to 2030
KDOT 3015 I-70/I-435 Interchange
Flyover Ramp
I-70/I-435 Interchange At I-70/I-435 interchange in Wyandotte County, construction of a flyover ramp from I-435 NB to I-70 WB
$77,000,000
Roadway KS 2021 to 2030
KDOT 3001 K-7 Arterial street enhancements
125th Street to I-35 in Olathe
Construct arterial street enhancements along K-7 from the end of the 4 lane freeway at the signal at 127th south along Lone Elm to I-35.
$47,300,000
Constrained Projects page 13 of 29Appendix D / Transportation Outlook 2040 2015 Plan Update
Category State Time Period Sponsor Project ID Facility/Program Location Description Capital Cost
Roadway KS 2021 to 2030
Leavenworth County 698 West Leavenworth / Lansing K-7
Bypass
K-7 west of Fort Leavenworth, then south around the west city limits of Leavenworth and
Lansing to the intersection of K-7 and McIntyre Road
The West Leavenworth / Lansing K-7 Bypass will eliminate Numerous cross-streets, curb cuts, and traffic signals.
$62,000,000
Roadway KS 2021 to 2030
Unified Government of WYCO/KCK
407 I-70 and Turner Diagonal
Interchange Re-configuration
I-70 and Turner Diagonal
Re-configuration and reconstruction of existing interchange. New interchange would be more traditional configuration (probably a
diamond) and would eliminate several long circuitous ramps and a bridge, as well as restore acres of adjacent land for development.
$20,000,000
Roadway KS 2021 to 2030
Unified Government of WYCO/KCK
422 I-35 and Lamar Avenue
Interchange
I-35 and Lamar Avenue (24th St) in
Kansas City, KS
replacing and realigning all ramps, as well as widening and replacing the bridge. Also included is construction of a fly-over bridge on 24th
St. over the immediately adjacent BNSF Railroad main line.
$18,000,000
Roadway KS 2031 to 2040
City of Gardner 720 US-56 Improvements
Moonlight Road to I-35; interchange at
New Century Parkway
The project will consist of expanding US-56 to 6 lanes and will necessitate major modifications or reconstruction of the interchange
of US-56 and New Century Parkway.
$50,000,000
Roadway KS 2031 to 2040
City of Lansing 223 West Gilman Road Extension
Willow Street to DeSoto Road
Extend Gilman Road (new location) per Lansing Comprehensive Plan. Provide separate Bicycle path and pedestrian sidewalk per Lansing
Master Trails Plan and City Policy.
$3,148,800
Roadway KS 2031 to 2040
City of Lansing 198 4-H Road Reconstruction
DeSoto Road to K-7(US-73)(Main Street).
Reconstruct rural-type 2-lane road to current standard 4-lane facility to accommodate growing traffic demand. Construct 10 ft. bicycle path and 5 ft. pedestrian sidewalk in accordance with Trails Master
Plan and city policy.
$6,622,000
Roadway KS 2031 to 2040
City of Leawood 74 Kenneth Road Widening
138th to 143rd Street The project will widen the current 2-lane road to a 4-lane undivided roadway. The improvements will include relocating the existing
sidewalks along both sides. The existing streetlights will be relocated and replaced with LED lights. The road will be widening at specific locations to accommodate left turn movements and possible bike
lanes.
$3,200,000
Roadway KS 2031 to 2040
City of Lenexa 248 New Interchange at Clare and K-10
Clare Road and K-10 Highway
New interchange at Clare and K-10 Highway to provide access and connectivity.
$20,000,000
Constrained Projects page 14 of 29Appendix D / Transportation Outlook 2040 2015 Plan Update
Category State Time Period Sponsor Project ID Facility/Program Location Description Capital Cost
Roadway KS 2031 to 2040
City of Lenexa 203 83rd Street Improvements
Gleason to West city limits
Improve and widen to 4-lane divided roadway with sidewalks, street lights storm sewers, landscaping and storm water management BMPs.
$20,000,000
Roadway KS 2031 to 2040
City of Lenexa 247 Canyon Creek Blvd & K-10 Interchange
Canyon Creek Boulevard and K-10
Highway
Modify and improve the existing Canyon Creek Boulevard and K-10 interchange to provide the needed capacity to support the
anticipated development
$5,000,000
Roadway KS 2031 to 2040
City of Lenexa 246 Prairie Star Parkway & K-10
interchange
Prairie Star Parkway and K-10
Construction of a new interchange at Prairie Star Parkway and K-10 to provide access and connection to Prairie Star Parkway and areas in
western Lenexa.
$20,000,000
Roadway KS 2031 to 2040
City of Lenexa 244 Prairie Star Parkway
improvements
Mize Road to K-10 Highway.
4-lane divided roadway including sidewalks and a 10-foot wide bike/ped trail along one side. Also included are street lights, storm
sewers, landscaping and storm water management BMPs
$15,400,000
Roadway KS 2031 to 2040
City of Olathe 516 Ridgeview Improvements
159th Street to 167th Street
Capacity improvements from 2 lane to 4 lane. $13,000,000
Roadway KS 2031 to 2040
City of Olathe 517 Ridgeview Improvements
167th Street to 175th Street
Capacity improvements from 2 lane to 4 lane. $13,000,000
Roadway KS 2031 to 2040
City of Olathe 519 Moonlight Interchange at K-10
Moonlight at K-10 Hwy New interchange needed on K-10 Hwy to serve increase demand due to economic development.
$15,000,000
Roadway KS 2031 to 2040
City of Olathe 507 159th Improvements
Mur-Len to Black Bob Capacity improvements from 2 lane to 4 lane. $13,000,000
Roadway KS 2031 to 2040
City of Olathe 514 Pflumm Improvements
151st Street to 159th Street
Capacity improvements from 2 lane to 4 lane. $13,000,000
Roadway KS 2031 to 2040
City of Olathe 513 Black Bob Improvements
167th Street to 175th Street
Capacity improvements from 2 lane to 4 lane. $13,000,000
Roadway KS 2031 to 2040
City of Olathe 495 KC Road Improvements
North city limits to Renner Road
Capacity improvement, widening from 4 to 5 lanes. $5,000,000
Roadway KS 2031 to 2040
City of Olathe 512 Black Bob Improvements
159th Street to 167th Street
Capacity improvements from 2 lane to 4 lane. $13,000,000
Roadway KS 2031 to 2040
City of Olathe 509 159th Improvements
West city limits to Lone Elm
Capacity improvements from 2 lane to 4 lane. $26,000,000
Constrained Projects page 15 of 29Appendix D / Transportation Outlook 2040 2015 Plan Update
Category State Time Period Sponsor Project ID Facility/Program Location Description Capital Cost
Roadway KS 2031 to 2040
City of Olathe 515 Ridgeview Improvements
151st Street to 159th Street
Capacity improvements from 2 lane to 4 lane. $13,000,000
Roadway KS 2031 to 2040
City of Olathe 496 151st Bridge widening at I-35
151st Street and I-35 Interchange.
Capacity improvement, widening bridge between Interchange ramps from 4 to 6 lanes.
$15,000,000
Roadway KS 2031 to 2040
City of Olathe 497 175th Improvements
Hedge Lane to Lone Elm
Capacity improvement from a rural 2 lane to 4 lane divided arterial. $13,000,000
Roadway KS 2031 to 2040
City of Olathe 499 175th Improvements
Lone Elm to K-7 Hwy Capacity improvement from a rural 2 lane to 4 lane divided arterial. $13,000,000
Roadway KS 2031 to 2040
City of Olathe 506 159th Improvements
Lone Elm to K-7 Hwy Capacity improvements from 2 lane to 4 lane. $13,000,000
Roadway KS 2031 to 2040
City of Olathe 500 175th Improvements
Mur-Len to Black Bob Capacity improvement from a rural 2 lane to 4 lane divided arterial. $13,000,000
Roadway KS 2031 to 2040
City of Olathe 505 159th Improvements
Black Bob to Pflumm Capacity improvements from 2 lane to 4 lane. $13,000,000
Roadway KS 2031 to 2040
City of Olathe 504 151st Improvements
West city limits to Old 56 Hwy
Capacity improvements from 2 lane to 4 lane. $15,000,000
Roadway KS 2031 to 2040
City of Olathe 501 175th Improvements
Ridgeview to Mur-Len Capacity improvement from a rural 2 lane to 4 lane divided arterial. $13,000,000
Roadway KS 2031 to 2040
City of Olathe 502 175th Improvements
West City limits to Hedge Lane.
Capacity improvement from a rural 2 lane to 4 lane divided arterial. $13,000,000
Roadway KS 2031 to 2040
City of Olathe 503 135th Improvements
West city limits to Lakeshore Drive
Capacity improvements from 2 lane to 4 lane. $5,000,000
Roadway KS 2031 to 2040
City of Overland Park
282 Kenneth/State Line Road
reconstruction
159th St. to 199th St. in Overland Park
The project includes reconstruction of Kenneth Road and State Line Road from an unimproved two-lane roadway to a four-lane divided
thoroughfare with turn lanes, storm sewers, a raised median, sidewalks, street lights, traffic signals, ADA compliant facilities,
restoration and other items incidental to the street construction.
$25,000,000
Roadway KS 2031 to 2040
City of Tonganoxie 701 US Highway 24/40 Construction
Kansas Highway 16 south to Leavenworth
County Highway 1
Construct 4 lanes on US Highway 24/40 from Kansas Highway 16 south to Leavenworth County Highway 1
$6,290,000
Constrained Projects page 16 of 29Appendix D / Transportation Outlook 2040 2015 Plan Update
Category State Time Period Sponsor Project ID Facility/Program Location Description Capital Cost
Roadway KS 2031 to 2040
City of Tonganoxie 705 Leavenworth County Road 1
Upgrade
US Highway 24/40 to I-70
Upgrade Leavenworth County Highway 1 from a 2-lane county road to a 4-lane Parkway.
$12,750,000
Roadway KS 2031 to 2040
City of Tonganoxie 477 Hemphill Road Reconstruction
US 24/40 east to 206th Street
Reconstruct Hemphill Road starting at it intersection with US 24/40 thence east to 206th Street
$9,000,000
Roadway KS 2031 to 2040
City of Tonganoxie 476 Leavenworth County Road
Frontage Roads Build
US 24/40 to the Kansas Turnpike
Tonganoxie Interchange
Build reverse frontage roads on both sides of Leavenworth County Road 1 from US 24/40 to the Kansas Turnpike Tonganoxie Interchange
$18,000,000
Roadway KS 2031 to 2040
City of Tonganoxie 475 Honey Creek Parkway
between 222nd Street and 206th Street
This project is planned in the Tonganoxie Comprehensive Plan. $8,500,000
Roadway KS 2031 to 2040
City of Tonganoxie 473 East Side Collector East Side Collector and 14th Street thence south to Kansas Avenue
This road is planned in the Tonganoxie Comprehensive Plan $2,125,000
Roadway KS 2031 to 2040
City of Tonganoxie 472 West Side Collector 4th Street west of US 24/40 thence south and west along the
approximate horizontal alignment of US 24/40 to Honey
Creek Road.
This project is planned in the US 24/40 Corridor Access and Traffic Management Plan
$7,435,000
Roadway KS 2031 to 2040
City of Tonganoxie 466 4th Street Construction
Pleasant Street east to 198th Street
This project is being built to comply with the planning done in the US 24/40 Corridor Access and Traffic Management Plan.
$8,775,000
Roadway KS 2031 to 2040
KDOT 894 Johnson County Gateway Project -
Phase 2
Various Reconstruction and capacity improvements to the I-435/I-35/K-10 interchange in Johnson County, KS
$300,000,000
Roadway KS 2031 to 2040
Unified Government of WYCO/KCK
464 Leavenworth Road Improvements
K-7 to I-435 Widening and reconstructing existing 2-lane rural-type roadway into 4-lane urban street including lighting, and signalization as warranted.
$18,000,000
Roadway KS 2031 to 2040
Unified Government of WYCO/KCK
415 Donahoo Road Parkway
Improvements
K-7 to I-435 Replacement of existing two lane roadway with a four lane parkway with landscaped median, turn lanes, and other urban amenities.
$20,000,000
Constrained Projects page 17 of 29Appendix D / Transportation Outlook 2040 2015 Plan Update
Category State Time Period Sponsor Project ID Facility/Program Location Description Capital Cost
Roadway KS 2031 to 2040
Unified Government of WYCO/KCK
461 Leavenworth Road Improvements
between I-635 and 91st Street
Reconstruct and widen Leavenworth Road (K-5) to a 3-lane facility which would provide for dedicated left turn lanes at major
intersections, and a continuous center lane for left turns at other locations. Also, included would be a landscaped area and
bicycle/pedestrian path adjacent to the road.
$20,000,000
Roadway KS 2031 to 2040
Unified Government of WYCO/KCK
452 Polfer Road Construction
115th St to Hutton Road
Construct new 1 mile segment of Polfer Road, extending existing alignment east one mile to connect to Polfer Road.
$6,200,000
Roadway MO 2015 to 2020
City of Grandview 787 I-49/US 71 Outer Roads
Blue Ridge Boulevard to MO 150
This project will entail converting the Outer Roadways of I-49 from one way to two way traffic. It includes improvements to the existing
outer roads, existing City streets in the vicinity of the Main Street interchange, and construction of a new roadway between E 129th
Street and Highgrove Rd. It also adds roundabout interstate access on the north and southbound sections of I-49 near 140th Street. This
could require up to three phases of construction projects to complete.
$15,000,000
Roadway MO 2015 to 2020
City of Independence
202 39th Street Bridge Replacement
39th Street Bridge Over the Little Blue
River
This project will replace an obsolete two lane bridge on 39th Street over the Little Blue River. The new bridge will have four through
traffic lanes and sidewalks.
$3,000,000
Roadway MO 2015 to 2020
City of Kansas City, MO
646 Shoal Creek Pkwy Reconstruction
Platte Purchase Dr. to Holly St.
RECONSTRUCT EXISTING ROAD AND WIDEN TO 4 LANES AND PARKWAY STANDARDS
$4,846,600
Roadway MO 2015 to 2020
City of Kansas City, MO
577 Lees Summit Road Reconstruction
Phelps Road to US 40 RECONSTRUCT EXISTING ROAD AND WIDEN TO 3 LANES. $12,833,250
Roadway MO 2015 to 2020
City of Kansas City, MO
549 Cookingham Rd Reconstruction
Platte Purchase Dr to Oak Trwy
RECONSTRUCT EXISTING ROAD AND WIDEN TO 4 LANES. $14,910,000
Roadway MO 2015 to 2020
City of Kansas City, MO
339 135th Street Reconstruction
MO-150 to Oak RECONSTRUCT EXISTING ROAD AND WIDEN TO 3 LANES. $7,000,000
Roadway MO 2015 to 2020
City of Kansas City, MO
578 Lees Summit Road Reconstruction
Lakewood Blvd to Phelps Road
RECONSTRUCT EXISTING ROAD AND WIDEN TO 3 LANES. $11,498,095
Roadway MO 2015 to 2020
City of Kansas City, MO
689 Tiffany Springs Pkwy Improvement
Amity to I-29 NEW 4 LANE FACILITY AND INTERCHANGE IMPROVEMENT $15,336,000
Constrained Projects page 18 of 29Appendix D / Transportation Outlook 2040 2015 Plan Update
Category State Time Period Sponsor Project ID Facility/Program Location Description Capital Cost
Roadway MO 2015 to 2020
City of Kansas City, MO
729 NW 64th Street Improvements
Cosby to Roanridge CAPACITY IMPROVEMENTS TO ROUTE 45/NW 64TH STREET AND I-29 INTERCHANGE INCLUDING OUTER ROAD RELOCATION
$16,655,000
Roadway MO 2015 to 2020
City of Kansas City, MO
555 Englewood Rd Reconstruction
Waukomis Drive to US 169
RECONSTRUCT EXISTING ROAD AND WIDEN TO 4 LANES. $13,632,000
Roadway MO 2015 to 2020
City of Kansas City, MO
696 Tiffany Springs Road Construction
Congress Ave to Skyview Ave
NEW 4 LANE FACILITY ON NEW ALIGNMENT $9,230,000
Roadway MO 2015 to 2020
City of Kansas City, MO
562 Green Hills Reconstruction
NW 72nd Street to Barry Road
RECONSTRUCT EXISTING ROAD AND WIDEN TO 3 LANES. $8,660,500
Roadway MO 2015 to 2020
City of Kansas City, MO
543 Congress Ave Reconstruction
NW 112th Street to Cookingham Drive
RECONSTRUCT EXISTING ROAD AND WIDEN TO 4 LANES. $7,497,600
Roadway MO 2015 to 2020
City of Kansas City, MO
582 Lees Summit Road Reconstruction
85th Street to Gregory RECONSTRUCT EXISTING ROAD AND WIDEN TO 4 LANES. $13,216,650
Roadway MO 2015 to 2020
City of Kansas City, MO
392 22nd/23rd Street Reconstruction
Brooklyn to I-70 RECONSTRUCT EXISTING ROAD AND WIDEN TO 4 LANES. $10,738,220
Roadway MO 2015 to 2020
City of Kansas City, MO
618 Northwood Reconstruction
City Limits (Riverside) to Prairie View Drive
RECONSTRUCT EXISTING ROAD AND WIDEN TO 3 LANES. $7,668,000
Roadway MO 2015 to 2020
City of Kansas City, MO
546 Congress Ave Reconstruction
Ambassador Dr to NW 108th Street
RECONSTRUCT EXISTING ROAD AND WIDEN TO 4 LANES. $7,497,600
Roadway MO 2015 to 2020
City of Lees Summit 118 Blackwell Interchange
Improvements
Intersection of Blackwell Road
(Extension) and US 50 Highway
The extension of Blackwell Road from Shenandoah Drive to the extension of Oldham Parkway (approx. 1 mile) with a diamond
interchange at US 50 Highway and auxiliary highway lanes between the Blackwell interchange and Todd George Parkway interchange.
The project includes the extension of Oldham Parkway from Ransom Road/Todd George Parkway to Smart Road (approx. 2 miles) and the extension of Blue Parkway to Shenandoah Drive (approx. 0.5 mile).
The interchange will have roundabout intersections, as will the intersections of Blackwell Road at Shenandoah Drive and
Shenandoah Drive at Blue Parkway.
$23,700,000
Roadway MO 2015 to 2020
City of Lees Summit 208 Lees Summit Road Widening
Colbern Road to Lee’s Summit West City
Limits
Widen Lee’s Summit Road from a two-lane unimproved road to a four-lane urban standard with turn lanes and traffic signal
improvements between the existing intersection of Colbern Road and the Lee’s Summit West City Limit (approx. 1 mile).
$8,660,000
Constrained Projects page 19 of 29Appendix D / Transportation Outlook 2040 2015 Plan Update
Category State Time Period Sponsor Project ID Facility/Program Location Description Capital Cost
Roadway MO 2015 to 2020
City of Liberty 234 I-35 and Pleasant Valley Interchange
Interim Improvements
I-35 and Pleasant Valley Road/South
Liberty Parkway
The project area effects the Interstate 35 On- and Off-Ramps at US Highway 69 and Pleasant Valley Road, US Highway 69 between
proposed Flintlock Road and Pleasant Valley Road, Pleasant Valley Road (PVR) between Church Road and Swan Avenue, South Liberty Parkway (extension of PVR) between Swan Avenue and Plummer
Road, the extension of Flintlock Road from South Liberty Parkway to US Highway 69, and improvements along Garrison Road.
$0
Roadway MO 2015 to 2020
City of Pleasant Hill 600 Business 7 Highway
Improvements
7 Highway to 58 Highway
This project will resurface Business 7 Highway install bike lanes, and reconstruct sidewalks including ADA ramps.
$2,000,000
Roadway MO 2015 to 2020
City of Raytown 654 350 Highway & Blue Ridge Boulevard
Intersection Improvements
MO-350 and Blue Ridge Boulevard
Intersection, Raytown, Missouri.
Modification of a limited access intersection to provide full access in all directions to support activity center, transit interconnectivity and
metro green connection.
$20,000,000
Roadway MO 2015 to 2020
City of Raytown 604 350 Highway & Raytown Rd. Intersection
Alignment Study
350 Hwy from Sterling to Maple
This study calls for the divided 350 highway through Raytown to be combined within the eastbound 350 highway right-of-way. Walking
and Biking trails are also part of the project along 350 highway.
$36,988,517
Roadway MO 2015 to 2020
MoDOT 3009 I-435 N 48th Street to Missouri River
Add auxiliary lane to I-435 from Parvin Rd to MO river bridge; reconstruct I-435/MO 210 interchange as diverging diamond (project
157 is Phase 1)
$18,000,000
Roadway MO 2015 to 2020
MoDOT 3007 I-435 Phase 2 Improvements
Kansas state line to west of I-49
Phase 2 - Operational, capacity and safety improvements along corridor; project 160 is Phase 1
$21,000,000
Roadway MO 2015 to 2020
TDD - Transportation Development
District (Partners in Progress)
805 US 71 & Route 291 Interchange
Improvements
I-49/US-71 and MO 291 Interchange
This project includes modifications to the I-49/US-71 & MO 291 Interchange and modifications to MO 291 in Harrisonville
$23,200,000
Roadway MO 2021 to 2030
City of Gladstone 316 N. Broadway Street
Improvement
Englewood Road to NW 76th Street
The project will include improvements to N. Broadway from Englewood Road to NW 76th Street. Portions of the existing roadway
are 2 lane in each direction.
$7,000,000
Constrained Projects page 20 of 29Appendix D / Transportation Outlook 2040 2015 Plan Update
Category State Time Period Sponsor Project ID Facility/Program Location Description Capital Cost
Roadway MO 2021 to 2030
City of Independence
225 39th Street Improvements
from the West City limits east to Crysler
Avenue.
Project will improve the last section of 39th Street from two lanes to three lanes. The roadway will be widened on the existing alignment
with striping for a center turn lane. New curb and gutters will be installed and the storm sewers will be updated. Five foot sidewalks
will be placed on both sides of the road with new street lighting.
$4,000,000
Roadway MO 2021 to 2030
City of Independence
349 M-7 Highway Improvements
intersection with Pink Hill Road, north to
U.S. 24 Highway
The M-7 Highway Improvements, Pink Hill Road to U.S. 24 Highway, will improve approximately six miles of M-7 Highway into a four lane street with curbs and sidewalks between Pink Hill Road and U.S. 24
Highway.
$30,000,000
Roadway MO 2021 to 2030
City of Independence
361 M-78 Highway Improvements
Speck Road northeast to Truman Road
The M-78 Highway Improvements, Speck to Truman Road, will improve the existing M-78 Highway from two lanes to four lanes in Eastern Independence. The construction of curbs, sidewalks, and
storm sewers will be included with this project.
$12,500,000
Roadway MO 2021 to 2030
City of Independence
372 Winner Road Improvements
U.S. 24 Highway southeast to Sterling
Avenue
Project will improve the existing Winner Road from two lanes to three lanes in most areas. The roadway will be widened on the existing alignment with striping for a center turn lane except for
where the road must narrow for conflicts. New curb and gutters will be installed and the storm sewers will be updated. Five foot
sidewalks will be placed on both sides of the road with new street lighting.
$7,200,000
Roadway MO 2021 to 2030
City of Kansas City, MO
700 Woodland Reconstruction
Shoal Creek Pkwy to I-435
RECONSTRUCT EXISTING ROAD AND WIDEN TO 4 LANES. $16,188,000
Roadway MO 2021 to 2030
City of Kansas City, MO
522 Amity Rd Reconstruction
MO-152 to Tiffany Springs Pkwy
RECONSTRUCT EXISTING ROAD AND WIDEN TO 4 LANES. $13,206,000
Roadway MO 2021 to 2030
City of Kansas City, MO
521 85th Street Reconstruction
Troost to Prospect RECONSTRUCT EXISTING ROAD AND WIDEN TO 4 LANES. $10,576,160
Roadway MO 2021 to 2030
City of Kansas City, MO
541 North Brighton Avenue
Reconstruction
Pleasant Valley Road to NE 76th Street
RECONSTRUCT EXISTING ROAD AND WIDEN TO 4 LANES. $14,049,125
Roadway MO 2021 to 2030
City of Kansas City, MO
605 Little Blue Road Reconstruction
Woodson to Noland RECONSTRUCT EXISTING ROAD AND WIDEN TO 4 LANES. $14,995,200
Roadway MO 2021 to 2030
City of Kansas City, MO
570 Indiana Ave widening
Barry Road to Shoal Creek Pkwy
WIDEN IMPROVED FACILITY TO 4 LANES $7,313,000
Constrained Projects page 21 of 29Appendix D / Transportation Outlook 2040 2015 Plan Update
Category State Time Period Sponsor Project ID Facility/Program Location Description Capital Cost
Roadway MO 2021 to 2030
City of Kansas City, MO
608 Maplewoods Parkway
Reconstruction
NE 96th Street to Shoal Creek Pkwy
RECONSTRUCT EXISTING ROAD AND WIDEN TO 4 LANES AND PARKWAY STANDARDS
$24,360,000
Roadway MO 2021 to 2030
City of Kansas City, MO
609 Maplewoods Parkway
Reconstruction
M-1 to SPRUCE RECONSTRUCT EXISTING ROAD AND WIDEN TO 4 LANES AND PARKWAY STANDARDS
$6,688,600
Roadway MO 2021 to 2030
City of Kansas City, MO
2000 Shoal Creek Pkwy Enhancements
NE 108th to Woodland Ave
ADDITIONAL 2 LANES TO PARKWAY STANDARDS $6,400,000
Roadway MO 2021 to 2030
City of Kansas City, MO
2004 East Longview Pkwy Construction
MO-350 to E 82nd Street
NEW 4 LANE PARKWAY FACILITY $10,530,300
Roadway MO 2021 to 2030
City of Kansas City, MO
620 NW 108th Construction
Congress Ave to Skyview Ave
NEW 4 LANE FACILITY TO REPLACE UNIMPROVED ROAD $8,990,000
Roadway MO 2021 to 2030
City of Kansas City, MO
579 Lees Summit Road Reconstruction
Gregory to Lakewood Blvd
RECONSTRUCT EXISTING ROAD AND WIDEN TO 3 LANES. $16,614,000
Roadway MO 2021 to 2030
City of Kansas City, MO
420 Ambassador Rd Construction
NW Plaza Circle to NW 128th Street
NEW 4 LANE FACILITY $17,863,600
Roadway MO 2021 to 2030
City of Kansas City, MO
567 Holmes Rd Reconstruction
Martha Truman to 115th
RECONSTRUCT EXISTING ROAD AND WIDEN TO 4 LANES. $11,991,900
Roadway MO 2021 to 2030
City of Kansas City, MO
547 Cookingham Rd Reconstruction
Woodland Ave to I-435
RECONSTRUCT EXISTING ROAD AND WIDEN TO 4 LANES. $19,820,000
Roadway MO 2021 to 2030
City of Kansas City, MO
557 Front Street Reconstruction
I-35 to Chouteau RECONSTRUCT EXISTING ROAD AND WIDEN TO 3 LANES. $47,925,000
Roadway MO 2021 to 2030
City of Kansas City, MO
680 Tiffany Springs Pkwy Construction
N. Revere to Green Hills Road
NEW 4 LANE PARKWAY FACILITY $11,400,000
Roadway MO 2021 to 2030
City of Kansas City, MO
550 Cookingham Rd Reconstruction
Oak Trwy to Woodland Ave
RECONSTRUCT EXISTING ROAD AND WIDEN TO 4 LANES. $13,951,500
Roadway MO 2021 to 2030
City of Kansas City, MO
642 Red Bridge Reconstruction
Blue River to US 71 RECONSTRUCT EXISTING ROAD AND WIDEN TO 3 LANES. $23,004,000
Roadway MO 2021 to 2030
City of Kansas City, MO
673 Shoal Creek Pkwy Construction
I-435 to NE 108th NEW 4 LANE PARKWAY FACILITY TO REPLACE UNIMPROVED ROAD $49,940,000
Constrained Projects page 22 of 29Appendix D / Transportation Outlook 2040 2015 Plan Update
Category State Time Period Sponsor Project ID Facility/Program Location Description Capital Cost
Roadway MO 2021 to 2030
City of Kansas City, MO
637 Pleasant Valley Reconstruction
N Brighton to Searcy Creek Pkwy
RECONSTRUCT EXISTING ROAD AND WIDEN TO 3 LANES. $19,880,000
Roadway MO 2021 to 2030
City of Kansas City, MO
551 Cookingham Rd Reconstruction
I-435 to Skyview Ave RECONSTRUCT EXISTING ROAD AND WIDEN TO 4 LANES. $13,632,000
Roadway MO 2021 to 2030
City of Kansas City, MO
678 Skyview Reconstruction
NW 108th Street to Cookingham Drive
RECONSTRUCT EXISTING ROAD AND WIDEN TO 4 LANES. $14,200,000
Roadway MO 2021 to 2030
City of Lees Summit 122 Pryor Road Widening
Longview Road to M-150 Highway
Widen Pryor Road from a two-lane interim road standard to a four-lane urban standard with turn lanes and warranted traffic signals between Longview Road and M-150 Highway (approx. 3.5 miles).
$14,250,000
Roadway MO 2021 to 2030
City of Lees Summit 121 Todd George Interchange/US 50
Highway Reconstruction
Todd George Interchange at US 50
Highway
Reconstruct/widen the existing interchange at Todd George Parkway/Ranson Road and US 50 Highway. Capacity improvements
will upgrade the existing 4-lane arterial with single left-turn lanes to a 6-lane arterial with dual left-turn lanes and provide necessary
intersection separation.
$18,000,000
Roadway MO 2021 to 2030
City of Liberty 587 I-35/MO 152 Interchange
improvements
I-35/MO 152 Interchange improvements including: bridge widening to accommodate necessary lanes and the improvement of left turn movements exiting off I-35; improvements to the sidewalk and
pedestrian facilities
$10,000,000
Roadway MO 2021 to 2030
City of Liberty 585 I-35/M-291 Interchange
Improvements
I-35 / M-291 Interchange
Interchange modifications at I-35 and M-291. By replacing the aging bridge, eliminating traffic signals, coordinating signals and expanding
M291 with additional lanes.
$12,500,000
Roadway MO 2021 to 2030
City of Liberty 631 Pleasant Valley I-35 Interchange modifications
Pleasant Valley Road / I-35 / US-69 Interchange.
Interchange modifications at I-35 & Pleasant Valley Road & US-69 $0
Roadway MO 2021 to 2030
City of Peculiar 449 211th Street & I-49/U.S. 71 Highway
Interchange
I-49/U.S 71 Highway at future 211th Street
in northern Peculiar
The 211th Street & I-49/U.S. 71 Interchange project is proposed in conjunction with a new 5-mile segment of 211th Street extending
from State Route J to State Route Y.
$14,289,588
Roadway MO 2021 to 2030
City of Peculiar 601 211th Street Extension
State Route J to State Route Y in Cass County
The 211th Street project is proposed in conjunction with a new interchange at 211th Street and I-49/U.S. 71 Highway. The
interchange will be a separate Transportation Outlook 2040 project submission. 211th will be the primary traffic mover through this
center, and will also serve as one segment of a principal arterial road linking the City with cities and counties to the east and west.
$40,000,000
Constrained Projects page 23 of 29Appendix D / Transportation Outlook 2040 2015 Plan Update
Category State Time Period Sponsor Project ID Facility/Program Location Description Capital Cost
Roadway MO 2021 to 2030
City of Pleasant Hill 204 M-7 Highway Improvements
M-7 Highway from 50 Highway to 163rd
Street.
This project will continue improvements already made to M-7 Highway in south Blue Springs and in Pleasant Hill south of 163rd
Street. The project will expand the highway to 4 lanes, with center left turn lanes where needed, and install curbs, gutters, designated
bike lanes, and sidewalks on each side.
$20,000,000
Roadway MO 2021 to 2030
City of Pleasant Valley
3016 Pleasant Valley Road
Sobbie Rd to western city limit
Widen Pleasant Valley Road to 3‐lane cross section with sidewalks and add retaining walls where needed. Incorporate complete streets
elements such as sidewalks and/or multi-use paths as feasible.
$4,100,000
Roadway MO 2021 to 2030
Platte County 653 Improvements to MO 92 - Phase 1
Leavenworth to I-29 Safety Improvements, Widening to accommodate current capacity, Multi-modal shared use path, Park and Ride facility at MO-169.
$40,000,000
Roadway MO 2031 to 2040
City of Kansas City, MO
586 Lewis and Clark Expwy
Construction
I-435 to Sugar Creek NEW 2 LANE FACILITY $63,800,000
Roadway MO 2031 to 2040
City of Kansas City, MO
771 Red Bridge Reconstruction
State Line to Holmes RECONSTRUCT EXISTING ROAD AND WIDEN TO 3 LANES. $17,556,000
Roadway MO 2031 to 2040
City of Kansas City, MO
769 Raytown Road Reconstruction
87th Street to I-470 RECONSTRUCT EXISTING ROADWAY AND WIDEN TO 4 LANES $11,233,650
Roadway MO 2031 to 2040
City of Kansas City, MO
776 Wornall Road Reconstruction
Red Bridge Rd to 135th Street
RECONSTRUCT EXISTING ROADWAY AND WIDEN TO 3 LANES $33,655,050
Roadway MO 2031 to 2040
City of Kansas City, MO
2001 Line Creek Pkwy Construction
Tiffany Springs Pkwy to Shoal Creek
Parkway
NEW 4 LANE PARKWAY FACILITY $20,797,700
Roadway MO 2031 to 2040
City of Kansas City, MO
566 Green Hills Reconstruction
MO-152 to NW 108th Street
RECONSTRUCT EXISTING ROAD AND WIDEN TO 4 LANES. $17,750,000
Roadway MO 2031 to 2040
City of Kansas City, MO
2005 Line Creek Pkwy Construction
Stage Coach to Tiffany Springs Parkway
NEW 4 LANE PARKWAY FACILITY $16,477,300
Roadway MO 2031 to 2040
City of Kansas City, MO
2006 Wornall Road Reconstruction
Ward Parkway to Red Bridge Rd
RECONSTRUCT EXISTING ROAD TO PARKWAY STANDARDS $23,100,600
Roadway MO 2031 to 2040
City of Kansas City, MO
621 NW 108th Reconstruction
Skyview Ave to Platte Purchase Dr
RECONSTRUCT EXISTING ROAD AND WIDEN TO 4 LANES. $17,980,000
Constrained Projects page 24 of 29Appendix D / Transportation Outlook 2040 2015 Plan Update
Category State Time Period Sponsor Project ID Facility/Program Location Description Capital Cost
Roadway MO 2031 to 2040
City of Kansas City, MO
524 Barry Road Reconstruction
Union Chapel to Chariton
RECONSTRUCT EXISTING ROAD AND WIDEN TO 3 LANES. $13,667,500
Roadway MO 2031 to 2040
City of Kansas City, MO
526 Barry Road Reconstruction
Highland Ave to Indiana Ave
RECONSTRUCT EXISTING ROAD AND WIDEN TO 3 LANES. $6,390,000
Roadway MO 2031 to 2040
City of Kansas City, MO
545 North Brighton Avenue
Reconstruction
Barry Road TO Shoal Creek Pkwy
RECONSTRUCT EXISTING ROAD AND WIDEN TO 3 LANES. $11,715,000
Roadway MO 2031 to 2040
City of Kansas City, MO
548 Cookingham Rd Reconstruction
Skyview Ave to Platte Purchase Dr
RECONSTRUCT EXISTING ROAD AND WIDEN TO 6 LANES. $19,820,000
Roadway MO 2031 to 2040
City of Kansas City, MO
554 Eastern Rd Reconstruction
Cookingham Driveto City Limits
RECONSTRUCT EXISTING ROAD AND WIDEN TO 3 LANES. $12,141,000
Roadway MO 2031 to 2040
City of Kansas City, MO
624 NW 72nd Improvements
NW Prairie View to Roanridge
INTERSECTION AND INTERCHANGE IMPROVEMENTS $12,840,000
Roadway MO 2031 to 2040
City of Kansas City, MO
632 Parvin Road Extension
Kentucky Ave to Route 210
NEW 4 LANE FACILITY EXTENSION $51,758,000
Roadway MO 2031 to 2040
City of Kansas City, MO
633 Platte Purchase Reconstruction
NW 76th Street to Barry Road
RECONSTRUCT EXISTING ROAD AND WIDEN TO 3 LANES. $9,487,375
Roadway MO 2031 to 2040
City of Kansas City, MO
635 Platte Purchase Reconstruction
MO-152 to Tiffany Springs pkwy
RECONSTRUCT EXISTING ROAD AND WIDEN TO 4 LANES. $9,372,000
Roadway MO 2031 to 2040
City of Kansas City, MO
641 Raytown Road Reconstruction
I-435 to Blue Ridge Cut-Off
RECONSTRUCT EXISTING ROAD AND WIDEN TO 4 LANES AND PARKWAY STANDARDS
$16,600,000
Roadway MO 2031 to 2040
City of Kansas City, MO
558 Front Street Reconstruction
Chouteau to I-435 RECONSTRUCT EXISTING ROAD $30,615,200
Roadway MO 2031 to 2040
City of Kansas City, MO
725 Blue Ridge Blvd Reconstruction
St Andrews Drive to Grandview City Limits
RECONSTRUCT EXISTING ROADWAY AND WIDEN TO 3 LANES $21,132,000
Roadway MO 2031 to 2040
City of Kansas City, MO
568 Holmes Rd Reconstruction
Blue Ridge to Martha Truman
RECONSTRUCT EXISTING ROAD AND WIDEN TO 3 LANES. $13,781,100
Roadway MO 2031 to 2040
City of Kansas City, MO
569 Holmes Rd Reconstruction
135th to Blue Ridge RECONSTRUCT EXISTING ROAD AND WIDEN TO 3 LANES. $5,644,500
Roadway MO 2031 to 2040
City of Kansas City, MO
571 Interurban Rd Reconstruction
Cookingham to Route 92
RECONSTRUCT EXISTING ROAD AND WIDEN TO 3 LANES. $28,116,000
Constrained Projects page 25 of 29Appendix D / Transportation Outlook 2040 2015 Plan Update
Category State Time Period Sponsor Project ID Facility/Program Location Description Capital Cost
Roadway MO 2031 to 2040
City of Kansas City, MO
687 Tiffany Springs Pkwy Construction
I-435 to Amity Ave NEW 4 LANE FACILITY AND INTERCHANGE $59,640,000
Roadway MO 2031 to 2040
City of Kansas City, MO
591 Line Creek Pkwy Reconstruction
I-29 to Bell Street RECONSTRUCT EXISTING ROAD AND WIDEN TO 4 LANES. $17,466,000
Roadway MO 2031 to 2040
City of Kansas City, MO
594 Line Creek Pkwy Reconstruction
I-29 TO NW 68TH STREET
RECONSTRUCT EXISTING ROAD AND WIDEN TO 4 LANES. $24,600,000
Roadway MO 2031 to 2040
City of Kansas City, MO
617 NE 96th Reconstruction
North Oak to Maplewoods Pkwy
RECONSTRUCT EXISTING ROAD AND WIDEN TO 3 LANES. $9,372,000
Roadway MO 2031 to 2040
City of Kansas City, MO
723 107th Street Reconstruction
Hillcrest Rd to Raytown Rd
RECONSTRUCT EXISTING ROADWAY AND WIDEN TO 3 LANES $12,335,000
Roadway MO 2031 to 2040
City of Kansas City, MO
724 Bannister Road Reconstruction
James A Reed to Raytown Road
RECONSTRUCT EXISTING ROADWAY AND WIDEN TO 4 LANES $21,132,000
Transit KS 2015 to 2020
MARC 804 I-70 West Express Bus Enhancements
CBD to K-7 New express bus service along the I-70 corridor from the CBD to K-7 $10,927,000
Transit KS 2021 to 2030
Johnson County Transit
581 Metcalf/Shawnee Mission Parkway
transit service
Johnson County, Kansas
The project will provide enhanced transit service and support development and the redevelopment of Metcalf Avenue
$13,842,000
Transit KS 2021 to 2030
Johnson County Transit
588 Shawnee Mission Parkway transit
service
Metcalf to K-7 Enhance transit service on Shawnee Mission Pkwy from Metcalf to K-7
$38,463,000
Transit MO 2015 to 2020
KCATA 2011 Regional Fare Collection System
Regional Upgrade of fare collection system including new technologies that would be used across the entire system.
$6,556,000
Transit MO 2015 to 2020
KCATA 413 Prospect Bus Rapid Transit
Prospect Corridor from the downtown CBD to the vicinity of 85th Street in south
Kansas City
This Project will design, construct and implement a new bus rapid transit line in a corridor running from Downtown Kansas City,
Missouri south along Prospect Ave. to the vicinity of 95th St. with potential legs to the area of Bannister and Hillcrest Roads in south
Kansas City. It will include BRT vehicles with hybrid electric propulsion systems, enhanced transit stations, pavement
improvements, ITS improvements, passenger amenities and information displays, transit centers and park and ride facilities.
$46,987,000
Constrained Projects page 26 of 29Appendix D / Transportation Outlook 2040 2015 Plan Update
Category State Time Period Sponsor Project ID Facility/Program Location Description Capital Cost
Transit MO 2015 to 2020
KCATA 2012 Regional Vanpool Expansion Program
Regional Regional expansion of the vanpool program. $2,732,000
Transit MO 2015 to 2020
KCATA 2013 Regional Mobility Management
Regional Implementation of a regional one-call center, and expansion of Paratransit Services
$5,464,000
Transit MO 2015 to 2020
KCATA 803 I-70 East Express Bus Enhancements
CBD to eastern Jackson County
Enhanced express bus service along the I-70 corridor from the CBD to eastern Jackson County
$11,200,000
Transit MO 2015 to 2020
KCATA 433 State Avenue Corridor Bus Rapid
Transit
Wyandotte County, KS and Kansas City, MO
This project will implement Bus Rapid Transit in the State Avenue Corridor from Village West in western Wyandotte County to
Downtown Kansas City, Kansas and Downtown Kansas City, Missouri. This project will include design, construction, and acquisition of BRT
stations, transit centers, BRT vehicles, transit traffic signal priority, ITS improvements, passenger information and amenities, and paving,
and sidewalk improvements.
$13,113,000
Transit MO 2015 to 2020
KCATA 2018 I-435 Express Bus Between Johnson County and Kansas
City, MO
New express bus service along the I-435 corridor from Johnson County to Kansas City, MO
$36,060,000
Transit MO 2015 to 2020
KCATA 2019 Leavenworth County Express Bus
Kansas City, KS, Kansas City, MO, and
Leavenworth, KS
New express bus service to Leavenworth County serving locations in Kansas City, KS and Kansas City, MO
$2,185,000
Transit MO 2015 to 2020
KCATA 302 System Preservation
Kansas City, Missouri Purchase new revenue vehicles (buses). Vehicles will replace those vehicles (buses) that have met their useful life in accordance with FTA guidelines. Some vehicles will also be used to expand transit service
as funding permits.
$54,636,000
Transit MO 2015 to 2020
KCATA 428 North Oak Bus Rapid Transit Improvement
Downtown Kansas City, MO. through North Kansas City,
Gladstone and Kansas City north to
approximately Missouri Highway 152.
This Project will design, construct and implement a new bus rapid transit line in the North Oak corridor from Downtown Kansas City to
Missouri 152 in the Northland. It will include BRT vehicles with hybrid electric propulsion systems, enhanced stations, pavement improvements, ITS improvements, passenger amenities, transit
centers and park and ride facilities.
$27,318,000
Constrained Projects page 27 of 29Appendix D / Transportation Outlook 2040 2015 Plan Update
Category State Time Period Sponsor Project ID Facility/Program Location Description Capital Cost
Transit MO 2015 to 2020
KCATA 423 Independence Ave. transit service
CBD to E Jackson County
Enhance transit service along Independence Ave from CBD to Eastern Jackson County
$27,318,000
Transit MO 2015 to 2020
MARC 801 I-35 North Express Bus Enhancements
CBD to Northern Clay/Platte County
Enhanced express bus service along the I-35 north corridor from the CBD to northern Clay and Platte Counties
$13,842,000
Transit MO 2015 to 2020
MARC 800 I-29 Express Bus Enhancements
CBD to Airport and Platte County
Enhanced express bus service along the I-29 corridor from the CBD to Platte County, including Kansas City International Airport
$13,842,000
Transit MO 2021 to 2030
KCATA 435 Regional Park and Ride Lot
Development
Locations throughout the metropolitan
area.
This project will plan, design, and construct new park and ride lots in the Kansas City metropolitan area.
$6,921,000
Transit MO 2021 to 2030
KCATA 2023 System Preservation
Regional System preservation includes replacement of buses at the end of their useful life and preservation of other facilities and assets.
$138,423,000
Transit MO 2021 to 2030
KCATA 2020 St. Joseph Express Bus
Between Kansas City and St. Joseph, MO
New express bus service between St. Joseph and Kansas City, MO $6,921,000
Transit MO 2021 to 2030
KCATA 2021 US-169 Express Bus CBD to northern Clay County
New express bus along the US-169 corridor from the CBD to northern Clay County
$2,768,000
Transit MO 2021 to 2030
KCATA 2017 M-350 Express Bus CBD to eastern Jackson County
Enhanced express bus service along the MO-350 corridor from the CBD to eastern Jackson County
$10,036,000
Transit MO 2021 to 2030
KCATA 2016 US-40 Enhanced Transit Service
CBD to eastern Jackson County
Enhance transit service along the US-40 corridor from the CBD to eastern Jackson County
$6,921,000
Transit MO 2021 to 2030
KCATA 382 Radio Communications
System\ITS Upgrade &
Improvements
Greater KCATA Service area
Project is to upgrade and expand existing radio communication infrastructure and real-time passenger information systems. It will
include hardware upgrades required to meet FCC mandates, replacement of aging equipment, additional security cameras, and
dynamic passenger information systems.
$16,611,000
Transit MO 2021 to 2030
KCATA 2015 US-24 Enhanced Transit Service
CBD to eastern Jackson County
Enhance transit service along the US-24 corridor from the CBD to eastern Jackson County
$23,016,000
Transit MO 2021 to 2030
KCATA 2014 Regional/KCATA Downtown Transit Center and Super
stops
Regional Reorganization of downtown transit routing and construction of supper stops and related amenities.
$24,916,000
Constrained Projects page 28 of 29Appendix D / Transportation Outlook 2040 2015 Plan Update
Category State Time Period Sponsor Project ID Facility/Program Location Description Capital Cost
Transit MO 2021 to 2030
MARC 802 US-71/I-49 Bus Enhancements
CBD to Cass County Enhanced express bus service along the US-71/I-49 corridor from the CBD to Cass County
$12,112,000
Transit MO 2031 to 2040
KCATA 2024 System Preservation
Regional System preservation includes replacement of buses at the end of their useful life and preservation of other facilities and assets.
$183,300,000
Transit MO 2031 to 2040
KCATA 364 New Transit Maintenance and
Service Facility
TBD A new facility and/or facilities will be necessary due to the age of the facility and the need to provide for greater efficiencies.
$124,644,000
Constrained Projects page 29 of 29Appendix D / Transportation Outlook 2040 2015 Plan Update
Operations, management and preservation projects
Category State Time Period Sponsor Project ID Facility/Program Location Description Capital Cost
Management & Operations
MO 2015 to 2020 MARC 205 RideShare program
Greater Kansas City metropolitan area - Jackson, Clay and Platte counties
in MO; Johnson, Wyandotte and Leavenworth in KS
The RideShare program is a free service that assists individual commuters and employers with identifying and using alternatives to driving alone, including carpooling and
vanpooling, transit, bicycling, walking and telecommuting.
$0
Management & Operations
MO 2015 to 2020 MoDOT 215 Motorist Assist Operations -
Missouri
Various Counties, Various Corridors on the state highway system in Missouri.
This program allows for the continued operation of the Motorist Assist program on the Missouri side of the KC region. This
includes the staff time, fleet and materials required to manage traffic incidents on the state highway system.
$18,440,000
Management & Operations
MO 2015 to 2020 MoDOT 214 KCScout ITS Operations
Various Counties, Various Corridors including I-70, I-435, I-470, US 71, I-29
and I-35.
This project is to provide support needed to continue to operate and maintain the KC Scout system in the Kansas City
Region.
$45,580,000
Roadway KS 2015 to 2020 KDOT 1000 I-70 Bridge Replacements
I-70 (Lewis & Clark Viaduct) Construct Phase 1 of the selected alternative from the completed study of Project No. 70-105 KA-2130-01 (Westbound
I-70 River Truss over the Kansas River). This includes Units 1 through 7 of Bridge #030 and Unit 3 of Bridge #173.
$57,500,000
Roadway MO 2015 to 2020 MoDOT 227 I-70/I-435 Interchange
Bridge Replacements
I-70/I-435 Phase 1 - Replace 4 bridges $30,000,000
Roadway MO 2015 to 2020 MoDOT 160 I-435 Bridge Replacements
W of Kansas State Line to W of I-49 Phase 1 - Replace 4 existing bridges at Wornall and Holmes Rd and rehabilitate 4 existing bridges at 103rd St and Blue River
$49,000,000
Roadway MO 2021 to 2030 MoDOT 2025 Broadway Bridge Replacements
Broadway & US-169 Phase 1 - Broadway Bridge replacement $140,000,000
Roadway MO 2031 to 2040 MoDOT 191 I-70 Bridge Replacements
I-435 to I-470 Phase 1 - Replace bridges at Pittman Rd, Blue Ridge Blvd, Crysler Ave, Phelps Rd and UP railroad overpass
$25,000,000
Roadway MO 2031 to 2040 MoDOT 157 I-435 Bridge Rehab Missouri River Bridge Phase 1 - Replace/rehab Missouri River Bridge $80,500,000
O&M/Preservation Projects page 1 of 1Appendix D / Transportation Outlook 2040 2015 Plan Update
>>Operations,
Management and Preservation*
Non-Preservation
2015 to 2020 $ 200,520,000 $ 856,684,6122021 to 2030 $ 140,000,000 $ 2,398,096,2232031 to 2040 105,500,000$ 1,498,420,775$
Roadway Projects Summary *Operations, management and preservation projects include:1. Replacement/reconstruction projects greater than $30 million on the National Highway System(NHS);2. Interchange reconstruction projects requiring a break-in-access/access justification report; and3. Regional programs intended to improve operation and management of the transportationsystem.These projects are examples of the types of activities necessary to preserve and maintain thetransportation system. As explained in Appendix E Financial Capacity Analysis (page E-15), the costof system operations, maintenance and preservation is deducted first from future transportationrevenues, and the remaining balance is available for other types of projects.
2015 to 2020 272,180,000$ 2021 to 2030 300,950,000$ 2031 to 2040 307,944,000$
Transit Projects Summary