Applicable Corps RegulatoryApplicable Corps Regulatory AuthoritiesAuthorities
Section 10 Rivers and Harbors Act of 1899• Structures in Navigable Waters and devices on
seabed of Outer Continental Shelfe.g. Wind turbine structures and transmission lines
Section 404 Clean Water Act• Discharges of Dredged or Fill Material into Waters of
the United Statese.g. Backfilling of trenches for transmission lines
Not applicable beyond three-mile limit of state waters
BUILDING STRONG®
Other Major Laws/AuthoritiesOther Major Laws/Authorities
Coastal Zone Management ActEndangered Species ActNational Historic Preservation ActFish & Wildlife Coordination ActOuter Continental Shelf Lands ActMarine Mammal Protection ActNational Environmental Policy ActMagnuson-Stevens Fishery Conservation & Management Act (Essential Fish Habitat)
3
BUILDING STRONG®
Corps Permit RequirementsCorps Permit RequirementsTitle 33 of the Code of Federal Regulations, Parts 320-332 prescribe the statutory authorities and general/special policies and procedures applicable to the review of applications for Department of the Army (DA) permitsSection 404(b)(1) of the Clean Water Act Guidelines (promulgated by USEPA) • Applicable to discharges of dredged/fill material into
waters of the United States• Rebuttable presumption that practicable alternatives
exist for proposed discharges into special aquatic sites for non-water dependent activities
BUILDING STRONG®
Public Interest Review FactorsPublic Interest Review FactorsBalancing process • Navigation• General environmental concerns• Conservation• Fish and wildlife values• Recreation• Economics• Energy Needs• Historic and cultural resources• Safety• Wetland values• Aesthetics• More listed at 33 CFR 320.4(a)(1)…
BUILDING STRONG®
Types of PermitsTypes of PermitsGeneral Permits• Nationwide Permits• Regional Permits• Programmatic Permits
Individual Permits• Standard Permits• Letters of Permission
6
BUILDING STRONG®
Standard Permits Standard Permits Public ParticipationPublic Participation
Public notices posted on districts’ websitesComments best in writing (letter or e-mail)Not a voteMay request e-mail notification when notices are publishedNotices sent to state and federal agencies, immediately adjoining properties, and interested parties as requested
7
BUILDING STRONG®
Interaction with BOEMREInteraction with BOEMREBOEMRE is Lead Federal Agency under the National Environmental Policy Act for projects on Outer Continental ShelfCorps is Cooperating AgencyWorking on Memorandum of Understanding to synchronize administrative processes for authorizing renewable energy projects on OCS
8
BUILDING STRONG®
Potential Windfarm IssuesPotential Windfarm IssuesNavigationMigratory Birds/BatsAcoustic/Vibration Disruption (fisheries and marine mammal impacts)AestheticsPublic Perception/OpinionOthers may arise on a case by case basisTie-ins to power transmission gridInterference with existing cables
9
BUILDING STRONG®
Potential Windfarm Projects Potential Windfarm Projects on Outer Continental Shelfon Outer Continental Shelf
Deepwater WindLong Island—NY City Offshore Wind ProjectBluewater Wind New JerseyGarden State Offshore Energy/PSEGOffshore MW LLCFisherman’s Energy of NJBluewater Wind Delaware
10
BUILDING STRONG®
RecommendationsRecommendations
Come to the Corps Early!Be Prepared to Engage Other AgenciesPublic OutreachBe FlexibleCommunication is Key
11
BUILDING STRONG®
Contact InformationContact InformationNortheast U.S. Region: James W. HaggertyRegulatory Program Manager, North Atlantic [email protected]: 347-370-4650New England District: Jennifer McCarthyRegulatory Division [email protected]: 978-318-8330New York District: MaryAnn MillerRegulatory Project [email protected]: 917-790-8516
12
BUILDING STRONG®
Contact InformationContact InformationPhiladelphia District: Larry SlavitterRegulatory Project [email protected]: 215-656-6734Baltimore District: Woody FrancisRegulatory Project ManagerWoody,[email protected]: 410-962-5689Norfolk District: John EvansRegulatory Project [email protected]: 757-201-7794
13
BUILDING STRONG®
Questions?
14