VALIDATION OF MANUFACTURINGEXECUTION SYSTEMS (MES)
1A S Y S T E M S D E V E L O P M E N T L I F E C Y C L E ( S D L C ) A P P R O A C H
• The contents of this presentation represent the opinion of the speaker; and not necessarily that of his present or past employers.
2IVT MES ORLANDO (C) 2017 RAUL SOTO
ABOUT THE AUTHOR
• 20+ years of experience in the medical devices, pharmaceutical, biotechnology, and consumer electronic industries
• MS Biotechnology, emphasis in Biomedical Engineering• BS Mechanical Engineering• ASQ Certified Quality Engineer
• I have led validation / qualification efforts in many scenarios:• High-speed, high-volume manufacturing and packaging equipment• Enterprise resource planning applications (i.e. SAP)• IT network & infrastructure• Quality Systems Software (CAPA / NCs; pharmacovigilance; eDMS; eLMS; etc.)• Mobile applications• Laboratory : information systems and equipment / computerized analytical instruments• Product improvements, material changes, vendor changes
• Contact information:• Raul Soto [email protected]
3IVT MES ORLANDO (C) 2017 RAUL SOTO
4
http://camstar.industrysoftware.automation.siemens.com/user-groups/manufacturing-star-awards/#Johnson-Johnson
IVT MES ORLANDO (C) 2017 RAUL SOTO
OUTLINE
• Introduction• What is an MES
• Benefits
• ANSI / ISA – 95
• eDHR
• Scope: • What should be included in the
Validation project
• SDLC Approach• Description and deliverables
• Validation Deliverables• Planning and Strategy
• Requirements, Design, Trace Matrix
• Testing
• Reports, Procedures, and Governance
• Interfaces
• Going Live• Governance
• Hypercare
5IVT MES ORLANDO (C) 2017 RAUL SOTO
INTRODUCTION
IVT MES ORLANDO (C) 2017 RAUL SOTO
6M A N U F A C T U R I N G E X E C U T I O N S Y S T E M S
WHAT IS AN MES
• Manufacturing Execution System• Takes in vast quantities of data coming from the PLCs
and SCADA/HMI systems• Converts that into useful information about production
ops• Scheduling• Materials handling• Quality samples
7IVT MES ORLANDO (C) 2017 RAUL SOTO
ERP MES CONTROLS
8IVT MES ORLANDO (C) 2017 RAUL SOTO
ANSI / ISA – 95 CONTROL HIERARCHY LEVELS
• Level 0: Physical production process
• Level 1: Sensing/manipulation of production process
• Level 2: Monitoring, supervisory control and automated control of production process (i.e. SCADA HMI systems)
• Level 3: Workflow / recipe control to produce desired products, maintain records and optimize production process. Timeframe: shifts, hours, minutes, seconds (i.e. MES, LIMS)
• Level 4: Establish basic plant schedule – production, material use, delivery, shipping. Timeframe: month, weeks, days, shifts (i.e. ERP)
9IVT MES ORLANDO (C) 2017 RAUL SOTO
ANSI / ISA – 95 CONTROL HIERARCHY LEVELS
IVT December (c) 2017 Raul Soto 10
http://w
ww
.we
rum.c
om
/en/m
es/p
rod
ucts/p
as-x/isa
/isa.jsp
BENEFITS OF MES
• Provide complete history of manufactured lots/ batches/ units
• Electronic Device History Record / Batch Record
• Electronic approvals and audit trails
• Full traceability of product to raw materials and manufacturing process parameters at every stage
• Reduce use of paper
11IVT MES ORLANDO (C) 2017 RAUL SOTO
BENEFITS OF MES
• MES system is not just a piece of fancy technology
• The BUSINESS VALUE of an MES comes from the integration of data from multiple information sources: production data, quality data, business data, controls data, etc.
• Materials consumed, equipment used, parametric data, exceptions, date / time stamps
• Enforces as-designed process
• Ensures the right procedures, operators, equipment materials are used
• Enforces right sequence of operations
• Can track equipment usage and communicate with eCMMS
12IVT MES ORLANDO (C) 2017 RAUL SOTO
EDHR
• eDHR: Electronic Device History Records
• paperless, electronic systems within MES
• enforce production processes
• capture all information associated with as-built production records.
• provides the error-proofing and real-time visibility necessary to produce consistent product quality each and every time.
13IVT MES ORLANDO (C) 2017 RAUL SOTO
EDHR
• If product quality issues arise, eDHR can be used to contain suspect product, either in process or in the field, to take action to address the issue.
• The electronic records stored in eDHR yields information that can also help MD&D companies optimize production processes.
14IVT MES ORLANDO (C) 2017 RAUL SOTO
15IVT MES ORLANDO (C) 2017 RAUL SOTO
SCOPE : WHAT SHOULD BE INCLUDED INTHE VALIDATION PROJECT
16
IVT MES ORLANDO (C) 2017 RAUL SOTO
M A N U F A C T U R I N G E X E C U T I O N S Y S T E M S
SOFTWARE VALIDATION
• validation, software. (NBS) Determination of the correctness of the final program or software produced from a development project with respect to the user needs and requirements. Validation is usually accomplished by verifying each stage of the software development life cycle. See: verification, software.
• Source: FDA Glossary of Computer System Software Development Terminology http://www.fda.gov/iceci/inspections/inspectionguides/ucm074875.htm
17IVT MES ORLANDO (C) 2017 RAUL SOTO
SCOPE: SOFTWARE
• MES Application• Workflows
• Databases / Data warehouse • (i.e. Oracle)
• Middleware • (i.e. Archestra)
• Interfaces • (more on this later!)
• ETL tools• SQL scripts
• Reporting tools not part of the application • Reports created with tools like
Tableau, Cognos, BusinessObjects
• Other ancillary / support software
18IVT MES ORLANDO (C) 2017 RAUL SOTO
SCOPE: HARDWARE
• Servers (for all environments)
• Sandbox / Development / QA-Test /
Staging / Production
• Scanners
• Printers
• Bar code readers
• RFID systems
• others
19IVT MES ORLANDO (C) 2017 RAUL SOTO
SCOPE
• One or multiple sites?
• One or multiple manufacturing suites / lines (within each site)?
• Are you also decommissioning a legacy MES system?
• Data migration and /or archival
• GAMP 5: COTS vs Configuration vs Customization
• Medical Devices : eDHR • 21 CFR 820.184 - DEVICE HISTORY RECORD
20IVT MES ORLANDO (C) 2017 RAUL SOTO
SCOPE
• Define your project scope early on, document all changes
• Map your AS-IS business process workflows (pre-MES), vs your TO-BE
• Include in scope any configuration and/or customizations required (i.e. reports, interfaces)
• Recommendation: Minimize custom-coding, maximize the use of configuration alternatives provided by software.
21IVT MES ORLANDO (C) 2017 RAUL SOTO
PROJECT PLANNING
• Involve key stakeholders and end users from the start
• Testing, validation, user training and documentation require time and resources. Make sure you factor that into your project scope from the start.
22IVT MES ORLANDO (C) 2017 RAUL SOTO
SDLC APPROACH
23
IVT MES ORLANDO (C) 2017 RAUL SOTO
M A N U F A C T U R I N G E X E C U T I O N S Y S T E M S
WHAT IS AN SDLC
• SDLC : Systems Development Life Cycle
• Series of steps / phases that provide a model for development and lifecycle management of an application or piece of software.
• Software validation is NOT a one-shot deal.
• Validated software and its documentation require continuousupdates and improvements for the life of the system
• End-of-life has to be managed• Data migration or archival• Hardware decommissioning
24IVT MES ORLANDO (C) 2017 RAUL SOTO
SDLC APPROACH
IVT December (c) 2017 Raul Soto 25
TYPICAL VALIDATION DELIVERABLES
26IVT MES ORLANDO (C) 2017 RAUL SOTO
Validation Plan
Assessments
Requirements
Design
Development
SAT / FAT
IQ
OQ / System Testing
PQ / UAT
Traceability Matrix
Procedures
Validation Report
PURCHASING REQUIREMENTS
• NOT the same as your validation requirements
• Develop high level requirements to be used as part of the purchasing decision
• Vendor assessment should include compliance with these requirements
• Make sure you have a good idea of how much configuration and/or customization is needed to meet your main requirements• MINIMIZE the amount of customization / custom code
• These requirements will also be the basis for FAT / SAT
• SLA : Service Level Agreement
27IVT MES ORLANDO (C) 2017 RAUL SOTO
DEVELOPMENT / CONFIGURATION
• Development testing occurs before validation• COTS functionality + configuration
• Vendor or hired consultants
• Unit testing, test configuration, integration testing
• If custom coding is required, development testing should be more comprehensive
• Use bug tracking software (i.e. FogBugz, Redmine, Debbugs) to keep track of bug resolution
• Does not need to be formally documented, but IT HELPS
• Have Coding standards and follow them!
28IVT MES ORLANDO (C) 2017 RAUL SOTO
VALIDATION DELIVERABLES
29M A N U F A C T U R I N G E X E C U T I O N S Y S T E M S
IVT MES ORLANDO (C) 2017 RAUL SOTO
TYPICAL LIST OF VALIDATION DELIVERABLES
• Assessments • (Safety, 21CFR Part 11, Risk, Compliance,
Vendor etc.)
• Validation Plan
• Requirements (URS, FRS)
• Design (DS, FDS, TDS, DDS)
• Traceability Matrix
• Testing protocols and scripts• Development *
• Integration *
• FAT / SAT *
• Installation
• OQ / PQ or System Testing / UAT
• Testing Reports
• Training
• Procedures• Operational
• Administration
• Change Control
• Validation Report
IVT December (c) 2017 Raul Soto 30
* Do not fall strictly under validation
31
ASSESSMENTS
• Vendor Assessment
• Compliance Assessment (i.e. GxP, SOX, etc.)• 21 CFR Part 11 ER/ES (especially on Medical Devices)
• GAMP category
• Information Security
• Safety / EHS
• Risk Analysis / FMEA
• others
32IVT MES ORLANDO (C) 2017 RAUL SOTO
VALIDATION PLAN & REPORT
IVT December (c) 2017 Raul Soto 33
VALIDATION PLAN
• This is where you establish WHAT needs to be validated, and HOW it will be validated.
• Get everyone’s buy-in and commitment to the Validation Plan from the beginning
• Update as needed, following your organization’s formal change control process for documentation
• Define clear expectations for all roles
• Definitions of deliverables, author and approvers for each
34IVT MES ORLANDO (C) 2017 RAUL SOTO
VALIDATION PLAN
• System Overview
• Scope of Validation
• Roles and Responsibilities
• Assessments Required
• Validation Deliverables, author and approvers
• Validation and Testing Strategy
• Acceptance Criteria
• How to deal with• Testing defects and deviations
• changes in scope and strategy
35IVT MES ORLANDO (C) 2017 RAUL SOTO
VALIDATION REPORT
• Final scope
• List of Actual Deliverables• Document Numbers
• Date of Completion
• any additions or deviations from planned
• Summary of testing results per protocol; any additions or deviations
• Summary of defects and discrepancies, and resolution status
• Statement declaring the validated state of the system
• Release to Production
36IVT MES ORLANDO (C) 2017 RAUL SOTO
RESOURCES
• You will need resources from multiple disciplines (i.e. QA, IT, Engineering, Operations, technical writers, etc.)
• Plan which resources you need, when will you need them, and for how long
• This will help you budget for consultants, and borrow internal resources. “I need two validation resources, 25-30% of their time, during August and September” is a different conversation than “I need to borrow some of your people for the MES project”
• PM tools -such as MS Project- help
37IVT MES ORLANDO (C) 2017 RAUL SOTO
REQUIREMENTS
• Types:
• User Requirements
• Functional Requirements
• Regulatory Requirements
• Performance Requirements
• Security Requirements
• Classify by type and criticality
• Low criticality : nice to have
• Medium criticality: important but not critical
• High criticality: must have
• All regulatory requirements should be classified as HIGH criticality
38
• WHAT do you want your MES system to do?
IVT MES ORLANDO (C) 2017 RAUL SOTO
REQUIREMENTS
• Clear• Complete• Correct• Consistent• Concise• Prioritized
• Relevant• Feasible• Verifiable• Modifiable• Traceable• Unique
39
Requirements should be
IVT MES ORLANDO (C) 2017 RAUL SOTO
REQUIREMENTS
Written definition of the MES software functions:
• Proposed Workflows and Use Cases
• How users will interact with the system
• Functions that the MES software will perform
• Expected system inputs and outputs
• Reports the system is expected to generate, contents
• Interfaces (user, external)
• Required alarms and checks
• Performance: data throughput, reliability, timing
• Coding standards
40IVT MES ORLANDO (C) 2017 RAUL SOTO
REQUIREMENTS
• Required response times
• Intended operating environment (hardware platform, software operating system, middleware, database software, etc.)
• All ranges, limits, defaults, specific values that the MES software requires
• Mirroring & Replication of main and transactional databases
• Backup, restore, disaster recovery
• User Roles that need to be defined in the system
• Any safety-related specifications
• Part 11: Electronic Records & Signatures requirements
• Dates (Manufacturing, Expiration): based on local time or UTC?41IVT MES ORLANDO (C) 2017 RAUL SOTO
REQUIREMENTS: UDI
Unique Device Identification
• US Initiative to assign a unique identifier to all medical devices
• Signed into law on 2007, mandatory since 2013 FDA Final Rule
• Label of a medical device must have a unique identifier
• Unique identifier should ID device through distribution and use
• Unique identifier must include lot / serial number
• Typical elements:• Graphics and symbols
• Regular and 2D barcodes
• Lot / batch / serial number, expiration date, date of manufacture
42IVT MES ORLANDO (C) 2017 RAUL SOTO
43IVT MES ORLANDO (C) 2017 RAUL SOTO
DESIGN
• HOW does your MES as installed and configured, meet the Requirements?
• Design Specifications describe the actual software solution:
• Out-of-box / configured / custom-coded
• Address all requirements, individually or in groups
• Design documentation may include one or more of the following:
44
Design Specification
Detailed Design Specification
Technical Design Specification
Database Design Specification
Software Design Specification
Hardware Design Specification
Architecture Design
Security Design
InterfacesIVT MES ORLANDO (C) 2017 RAUL SOTO
DESIGN
Design documentation should include, at least:
• Actual workflows and use cases, as configured (or coded)
• System architecture
• Modules
• Screens
• Formulas, algorithms, and logic used
• Data structures, data flow diagrams
• Supporting software that is required for MES operation (i.e. Archestra)
• Hardware required
• Parameters that are measured or recorded
45IVT MES ORLANDO (C) 2017 RAUL SOTO
DESIGN
• Definition of control and data variables, where used
• Messages: Errors, alarms, warnings
• User roles, as configured
• Physical security
• Information security
• Actual reports as configured
• Interfaces, as configured
46IVT MES ORLANDO (C) 2017 RAUL SOTO
REQUIREMENTS TRACEABILITY MATRIX
• The RTM should enable us to trace:• From individual Requirements to their
specific Design Element(s) where the requirement is addressed
• From Design Elements to the specific Test Script(s) where they are being challenged.
47
We should be able to trace back and forwardRequirement Design elements Testing
IVT MES ORLANDO (C) 2017 RAUL SOTO
REQUIREMENTS TRACEABILITY MATRIX
• Requirements => start RTM draft
• Design documents => update RTM draft
• Test scripts => finalize RTM
• Final RTM should be approved before the system is released for production
• RTM should be updated as part of system change control every time requirements, design, or test scripts are changed, added, removed.
48IVT MES ORLANDO (C) 2017 RAUL SOTO
LIVING DOCUMENTS
• The following documents should be treated as “living documents” and maintained up to date throughout the life of the system
• Requirements • Design• Traceability Matrix• Risk Assessments (i.e. FMEA)
49IVT MES ORLANDO (C) 2017 RAUL SOTO
TESTING50M A N U FA C T U R I N G E X E C U T I O N S Y S T E M S
IVT MES ORLANDO (C) 2017 RAUL SOTO
TESTING
• Protocols, Test Scripts, Reports
• Pre- and post- approved
• Consistency in roles pre- and post- approving is important• Minimum: System Owner, Business Process Owner, QA
• Avoid conflicts of interest: Approvers cannot execute, testers can’t approve
• Dependencies and order of testing must be clear, evident, obvious
• Enforce Good Documentation Practices (GDP)
• Enforce the use of standard templates
• Keep evidence (printouts, screenshots, labels, etc.)
51IVT MES ORLANDO (C) 2017 RAUL SOTO
TESTING ENVIRONMENTS
• Development / Sandbox • For DEV testing• Qualification not required
• Test / Staging• For your formal validation (OQ, System Testing, UAT)• Qualified• Functionally equivalent to your PROD environment
• Production Environment• Live system• Performance testing• Qualified
52IVT MES ORLANDO (C) 2017 RAUL SOTO
INSTALLATION QUALIFICATION
• Installation Qualification• Document / verify the correct installation and configuration of
all software and hardware components, as per the Design Specification
• List actual software components and objects installed: name, version, location
• List actual hardware installed: name, model, quantity, S/N, location
• Turn-key test to ensure the system is ready for OQ / System testing
53IVT MES ORLANDO (C) 2017 RAUL SOTO
OPERATIONAL QUALIFICATION
Operational Qualification• Ensure system can perform under controlled conditions, non-
saleable product
• Document that system is installed and configured as per Design Specifications
• AND complies with requirements as per Requirements Specifications
• Testing will challenge all requirements, interfaces, reports, etc.
• Can test each subsystem individually
• Positive vs Negative testing
• Formal change control
54IVT MES ORLANDO (C) 2017 RAUL SOTO
OPERATIONAL QUALIFICATION
• System Testing• Test and verify that the system as integrated is functionally
complete
• Challenge compliance with functional and non-functional specifications
• Integration of MES with interfaces
• You can test individual functionalities, then end-end process workflows
55IVT MES ORLANDO (C) 2017 RAUL SOTO
OPERATIONAL QUALIFICATION
Risk-based testing:
1. COTS elements: • positive testing of all workflows, and alternate flows
2. Configured elements: • Positive testing• Negative testing• Boundary testing
3. Custom: • Same as Configured elements, PLUS
• Code reviews against coding standards
IVT December (c) 2017 Raul Soto 56
OPERATIONAL QUALIFICATION
• Tests functional requirements, configuration, security, ER/ES, compliance• May include positive testing, negative testing, boundary testing, interface
testing
• Positive Testing:• Ensures that system performs as intended, using normally expected inputs
• Negative Testing:• Ensures that system doesn’t accept invalid inputs
• Boundary Testing:• Challenges that performance is as expected when specific variables are set
to their max / min values.• Interface Testing:
• Tests that system components can pass data correctly to one another
57IVT MES ORLANDO (C) 2017 RAUL SOTO
PERFORMANCE QUALIFICATION
Performance Qualification / Production Qualification• Test that system is able to function under normal manufacturing
conditions
• End-to-End challenge of the complete process flow
• Normal mix of lots, products, operators, shifts, etc.
• Performance testing / load testing
• SOPs must be approved and effective
• Can use saleable product if company procedures allow for it
58IVT MES ORLANDO (C) 2017 RAUL SOTO
PERFORMANCE QUALIFICATION
• User Acceptance Testing• Testing focused on user-related requirements
• Challenge that the MES system is capable of supporting your normal business process
• Test cases should address ease of use from the standpoint of operators, QC technicians, etc.
59IVT MES ORLANDO (C) 2017 RAUL SOTO
PERFORMANCE QUALIFICATION
• Tests functional requirements, configuration, security, ER/ES, compliance• May include positive & negative testing, business process testing, end-to-end
testing, stress testing, performance testing
• Business Process Testing:• Verifies that the system works as intended following business process flows
• End – to – End Testing:• Verifies that the system is capable of supporting the intended process flows, from
beginning to end; ensure data integrity and that the correct data passes between components and interfaces.
• Performance Testing:• Verifies system stability, resource usage, and responsiveness under specific workloads.
• Stress Testing:• Tests system’s performance beyond the limits established in the specified requirements
60IVT MES ORLANDO (C) 2017 RAUL SOTO
TESTING EXECUTION
• Ensure test sets and scripts are executed in correct order
• GDP (Good Documentation Practices) are IMPORTANT
• Include evidence: screenshots, printouts, labels, etc.
• Changes to approved protocols / test scripts must follow formal documentation management (version up, re-approve, etc)
• Coordinate execution dates / times with owners of systems MES interfaces with
• Follow process for handling testing defects / deviations
• If you execute PQ / UAT with real product, QA must provide disposition of such product
61IVT MES ORLANDO (C) 2017 RAUL SOTO
TESTING TOOLS
• There are electronic testing tools that can be used in substitution of paper test scripts• Example: HP Applications Life Management (ALM), Valgenesys
• MUST validate these tools BEFORE you use them
• Pros: reduce GDP errors, standardize testing process, enforce use of correct templates, enforce approvers rules, manage test defects, can search for documents electronically
• Cons: administration, training, cost, less flexibility, maintenance, fixes / upgrades
• Tools become your official repository of validation documentation
• 21 CFR Part 11 full compliance may require additional wrap-around software solution
62IVT MES ORLANDO (C) 2017 RAUL SOTO
PROJECT CHANGE MANAGEMENT
• You must have a formal change control process while in the project, not just after go-live.
• Design freeze date – enforce it!• Any design changes requested after this date => after Go Live
• Except for critical (regulatory, business) changes
63IVT MES ORLANDO (C) 2017 RAUL SOTO
CHANGE CONTROL
• All changes should be assessed, documented, pre-approved, tested, post-approved
• Assessment
• Nature and scope of the change
• Risk assessment
• Documentation that needs to be updated (Requirements, Design, RTM, FMEA, etc.)
• Testing
• Functional tests
• Regression tests
64IVT MES ORLANDO (C) 2017 RAUL SOTO
INTERFACES
65M A N U FA C T U R I N G E X E C U T I O N S Y S T E M S
IVT MES ORLANDO (C) 2017 RAUL SOTO
INTERFACES
• Do NOT underestimate interfaces, especially to LIMS and your ERP.
• ALL interfaces must be part of the validation effort
• Define and document all your interfaces at the Design stage
• What data passes MES External system
• Test your interfaces configuration in Development testing
• Test your interfaces functionality explicitly in OQ / System Testing
66IVT MES ORLANDO (C) 2017 RAUL SOTO
SAMPLE INTERFACES DIAGRAM
67IVT MES ORLANDO (C) 2017 RAUL SOTO
ERPERPGlobal
Planning
SCADA / HMI
PLCs
Raw Materials Tracking
Distribution Control
Change ControlLIMS
MES
Lot production quantityand status
Audit DataData
Lot Info
POSSIBLE INTERFACES
• ERP (i.e. SAP, JD Edwards)
• Master production schedule
• Lot quantity and status
• Bill of materials
• LIMS (i.e. Labware, NuGenesis)• QC Audit data
• Manufacturing lines, SCADA / HMI (i.e. Wonderware, RSView)• Manufacturing orders
• Bill of materials
• Lot data
• Raw Materials Tracking software• Data exchange of r.m. lots used
• Documentation eDMS(i.e. Documentum)• Change control and procedures data
• Product hold information
• Distribution Control system• QC release data
• Lot data
68IVT MES ORLANDO (C) 2017 RAUL SOTO
GOING LIVE
69M A N U FA C T U R I N G E X E C U T I O N S Y S T E M S
IVT MES ORLANDO (C) 2017 RAUL SOTO
GOVERNANCE
• Procedures• System Administration
• Operation
• Change Control
• Maintenance
• Training
• Security and Access Control
• Configuration Management
• Backup / Restore / Disaster Recovery
• others
70IVT MES ORLANDO (C) 2017 RAUL SOTO
GOVERNANCE
• “Hypercare”
• SLA with vendors
• Change Control
• Support structure
• Periodic Review (and revalidation)
71IVT MES ORLANDO (C) 2017 RAUL SOTO
REFERENCES
72IVT MES ORLANDO (C) 2017 RAUL SOTO
https://www.fda.gov/RegulatoryInformation/Guidances/ucm085281.htm
REFERENCES
• http://ispe.org/gamp-good-practice-guide/manufacturing-execution-systems
IVT December (c) 2017 Raul Soto 73
REFERENCES
• General Principles of Software Validation; Final Guidance for Industry and FDA Staff, Jan 11 2002• http://www.fda.gov/downloads/RegulatoryInformation/Guidances/ucm126955.pdf
• ISPE GAMP5 Guide: Manufacturing Execution Systems• http://ispe.org/gamp-good-practice-guide/manufacturing-execution-systems
• Understanding Manufacturing Execution Systems (MES)• http://www.freedomcorp.com/solutions/qad/White%20Papers/MES%20White%20Paper.pdf
• Unique Device Identification (UDI)• http://www.fda.gov/MedicalDevices/DeviceRegulationandGuidance/UniqueDeviceIdentification/
• http://www.labelingnews.com/downloads/UDI_eBook.pdf
• Global Unique Device Identification Database (GUDID) Guidance for Industry and FDA Staff, June 27 2014• http://www.fda.gov/downloads/MedicalDevices/DeviceRegulationandGuidance/GuidanceDocuments/UCM369
248.pdf
74IVT MES ORLANDO (C) 2017 RAUL SOTO
REFERENCES
• US 21 CFR 820 Quality System Regulation• http://www.accessdata.fda.gov/scripts/cdrh/cfdocs/cfcfr/CFRSearch.cfm?CFRPart=820
• US 21 CFR 11 Electronic Records and Signatures• http://www.accessdata.fda.gov/scripts/cdrh/cfdocs/cfcfr/CFRSearch.cfm?CFRPart=11&showFR=1
• Annex 11 Computerised Systems. Jan 2011 updateEudraLex, Rules Governing Medicinal Products in the European UnionVol. 4 Good Manufacturing Practice, Medicinal Products for Human and Veterinary Use
• http://ec.europa.eu/health/files/eudralex/vol-4/annex11_01-2011_en.pdf
• ISO 13485 Medical devices -- Quality management systems -- Requirements for regulatory purposes• http://www.iso.org/iso/iso_catalogue/catalogue_tc/catalogue_detail.htm?csnumber=36786
• ANSI/ISA 95 and ANSI/ISA 88 Standards• https://www.isa.org/standards-and-publications/isa-standards/find-isa-standards-in-numerical-order/
75IVT MES ORLANDO (C) 2017 RAUL SOTO
QUESTIONS