Water Plant #3Concentrate Pre-treatment
Project
Water Plant #3 Concentrate Pre-treatment
Project Regulatory Requirements: Wtp#3 has a discharge permit limit for iron of 0.3
mg/L Wtp#3 Concentrate is greater than 0.3 mg/L FLDEP AO 154NE provides a schedule to meet the iron discharge limitation Concentrate is permitted as a source water at Wtp#1 Color compliance at Wtp#1 is dependent on color
reduction treatment by ozone treatment at Wtp#3
Water Plant #3 Concentrate Pre-treatment
Project
Process Components:Primary Systemo Ozone system for color reduction o Recovers up to750,ooo gals/daySecondary Systemo Cartridge filtration system for iron reduction
Water Plant #3 Concentrate Pre-treatment Project
Funding: Total Project Cost - $1,580,000 Design & Permitting - $162,345 Construction Cost including contingency -
$1,407,680 Source of Funds: 5 Year CIP bond funds SJRWMD Cooperative Cost Share Grant - $494,800 Florida Legislative Funding Grant - $375,000
(waiting for Governor’s signature)o
Questions?