Page 1: zte mobilink bts swap

Introduction

Site Engineering Solution For MobilinkBY

Faran Ul Ghani/Du Erning

Page 2: zte mobilink bts swap

Purpose

• This ppt will describe in detail the site engineering swap solutions from existing BTS to new ZTE BTS/NodeB

Page 3: zte mobilink bts swap

Key Points

• Difference between Integrated Solution and Distributed Solution.

• Original BTS swapped with ZTE BS8700• BBU Installed in 8910A cabinet.

Page 4: zte mobilink bts swap

BTS Swap Scenarios

• Outdoor Macro Site swapped to Outdoor distributed site (IDU Installed in BC Cab)

• Outdoor Macro Site swapped to Outdoor distributed site (IDU Installed in Rectifier)

• Indoor Macro Site Swap to Outdoor Distributed Site

• Indoor Macro Site Swap to Outdoor Distributed Site (After New Rec Move ZTE BTS Outdoor

Page 5: zte mobilink bts swap

Outdoor Scenario Before Swap

Page 6: zte mobilink bts swap

After Swap

Page 7: zte mobilink bts swap

Outdoor to OutdoorScenario -2

Page 8: zte mobilink bts swap

After SwapNote: If IDU are less than 3, we will remain the IDU in REC

Page 9: zte mobilink bts swap

Indoor to OutdoorScenario -3

Page 10: zte mobilink bts swap

After SwapNote: Pre Install recti and ZTE BTS to prop location, IDU will remain in shelter

Page 11: zte mobilink bts swap

Indoor to OutdoorScenario -4

Page 12: zte mobilink bts swap

After Swap-1

Page 13: zte mobilink bts swap

After Swap-2Secondary Swap

Note: Secondary Swap need after new recti ready

Page 14: zte mobilink bts swap

Indoor to IndoorScenario -5

Page 15: zte mobilink bts swap

After Swap

Page 16: zte mobilink bts swap

RF System Swap Solution There are 6 RF system scenarios during the Site Swap RF Scenario 900M 1800M 1 Sector 2 or 3 Sectors • Single band S1-S4 R8881 R8863 • Single band S5-S8 R8881 x2 R8863 x2 • S1~S4 S1~S4 R8881 x2 R8863 x2 • S1~S4 S5~S8 R8881 x3 R8863 x3 • S5~S8 S1~S4 R8881 x3 R8863 x3 • S5~S8 S5~S8 R8881 x4 R8863 x4 • Any sector has a configure which is more than 8 TRXs, R8881 will be used

for all the sectors.

Page 17: zte mobilink bts swap

Scenario-1Single band 900M or 1800M sector

only.S1-S4

Page 18: zte mobilink bts swap

Scenario-2Single band 900M or 1800M S5-S8

Page 19: zte mobilink bts swap

Scenario-3Dual band 900M S1-S4 +1800M S1-S4

Page 20: zte mobilink bts swap

Scenario-4Dual band 900M S1-S4, 1800M S5-S8

Page 21: zte mobilink bts swap

Scenario-5Dual band 900M S5-8, 1800M S1-4

Page 22: zte mobilink bts swap

Scenario-5 CONT

Page 23: zte mobilink bts swap

Scenario-6Dual band 900M S5-S8 , 1800M S5-S8

Page 24: zte mobilink bts swap

Scenario-6 CONT

Page 25: zte mobilink bts swap

Scenario-7 UMTS swap

This scenario is showing the 3G swap • Distributed site: Original 3G RU is installed on

the tower. During the swap, dismantle the original RRU and install ZTE R8881/R8863 in the old location. Connect the jumpers from RRU to the 2100M port of the antenna.

• Macro site: Original 3G RU in the cabinet For some sharing site, there is no space on the tower to install RRU, The RRUs will be installed on the ground with a pole. During the swap, original feeders will be reused, connect the jumpers from RRU to original feeders.

Page 26: zte mobilink bts swap

FS- RRU Relations • R8881 connection

The connections between FS and R8881 should comply with the following rules:

• In case of using one FS board: The FS board is placed at slot3 of BBU, An additional FS board will be configured at slot 4 when there are more than 6 sectors.

• Each sector takes one FS port. The secondary R8881 for the same sector will be cascaded to the first R8881.

• The ports of FS board are numbered from 0 to 5 (from right to left).The RRU units are connected to the FS ports in the following order from port No. 0 to port No. 5:

• Not more than 6 sectors:

GSM 900 R8881 in order of cells (lower at first) takes 0, 1, and 2 DCS1800 R8881 in order of cells (lower at first) takes 3, 4, and 5

Page 27: zte mobilink bts swap

R8881 connection CONT• More than 6 sectors: GSM 900 R8881 in order of cells (lower at first) takes 0, 1, 2, 3…..(FS board in slot3) DCS1800 R8881 in order of cells (lower at first) takes 0, 1, 2, 3…..(FS board in slot4) UMTS2100 R8881 in order of cells (lower at first) takes 3,4,5 ports of the FS board in slot4.

Page 28: zte mobilink bts swap

R8863 connection The connections between FS and R8863 should comply with the following rules: • In case of using one FS board: The FS board is placed at slot3 of BBU. • Each R8863 takes one FS port. The secondary R8863 will directly connect to the FS

board instead of cascading. • The ports of FS board are numbered from 0 to 5 (from right to left).The RRU units

are connected to the FS ports in the following order from port No. 0 to port No. 5: • An additional FS board will be added in the 3G site. GSM 900 R8863 in order of cells (lower at first) takes 0, 1, and 2 DCS1800 R8863 in order of cells (lower at first) takes 3, 4, and 5 UMTS2100 R8863 in order of cells (lower at first) takes 0,1, and 2 of FS in slot4

Page 29: zte mobilink bts swap

RET connection

• R8881 The distance between RRU to Antenna is less than 6m ,One standard AISG cable for each sector.

Page 30: zte mobilink bts swap

R8881 CONTThe distance between RRU and Antenna is more than 6m ,NSBT and ASBT will be configured for each sector, connect RRU and NSBT with a AISG special cable (DB15 to AISG), and ASBT to the RCU with a AISG standard cable (AISG to AISG).

Page 31: zte mobilink bts swap

RET R8863

An AISG special cable connect the R8863 to the RCU for sector A, then cascade the RCU for sector B and C.

Page 32: zte mobilink bts swap

Power Supply Solution

All RRUs will be connected to the LLVD 25A breakers on existing rectifier. IF more than 6 RRUs are configured • R8881: parallel connect two RRUs to one breaker. • R8863: connect one RRU to one 25A breaker, add

additional breaker when there are more than 6 R8863.

DCPD7 will be used in the BC cabinet for the BBU&IDU power supply, which is connected to the BLVD breaker of the existing rectifier.

Page 33: zte mobilink bts swap

DCPD7

Page 34: zte mobilink bts swap

New power system swap.

As Mobilink planned, the new Rectifier will be installed.

Before new rectifier installed, an new ATS and DB will be installed outdoor which will provide the power to the new rectifier.

During the secondary swap, reconnect the power cable of original rectifier to the new built ATS and DB. After all equipments working normally, dismantle the original ATS and DB.

Page 35: zte mobilink bts swap

New Power System Swap

Page 36: zte mobilink bts swap

New Power System Swap

Page 37: zte mobilink bts swap

Transmission solution

In the phase 2, Ericson is using IP for the BTS transmission. All the phase 2 site will use an Ethernet cable connecting from IDU to CC board.

For the outdoor sites, a LPU will be configured for the Lightning protection Unit (LPU). All the signalling cables which is lying out of the BC cabinet, should be connected to the LPU first

Page 38: zte mobilink bts swap

Transmission Solution

Page 39: zte mobilink bts swap

External Alarm Solution

Page 40: zte mobilink bts swap

For Outdoor Sites

Page 41: zte mobilink bts swap

PIN and Colour definitionSA board

Page 42: zte mobilink bts swap

Labels Guideline

The following items should be abided when fix labels:

• Labels shall be affixed facing the same direction, and the side that indicates the cabling direction shall face upward or face the side of operation and maintenance for ease of reading.

• Both ends of each cable (power cable, grounding cable, transmission cable, jumper wire, and so on) shall be affixed with labels.

• Labels shall be affixed in a neat and workmanlike manner. • A label shall be affixed 200 mm from each end of a feeder, or 20 mm

from each end of a power cable, network cable, signal cable or fibre. • Affix labels on the cables distributed vertically and horizontally in the

way shown in the following figure.

Page 43: zte mobilink bts swap

Feeder and Jumper Labels Requirement

[Label Format] Sector ID- ANT1/2 [Labelling Conditions] • Sector ID: Ranges from S1 to S4 • ANT1 for TX/RX, ANT2 for RX

Page 44: zte mobilink bts swap

Optical Fibre Labels Requirement

[Label Format] Sector ID- OPB/OPR [Labelling Conditions] • Sector ID: Ranges from S1 to S4 • OPB: Used on BBU side; OPR: Used on RRU

side

Page 45: zte mobilink bts swap

Optical Fibre Labels Requirement CONT

When connect RRUs to BBU FS board with optical fibre, it’s very easy to make mistake. So ZTE require all the partners use temporary labels on the fibre's when lay them. The temporary label for fibres requirements are as follows: [Label Format] Fiber-SystemID-SectorID-1/2 [Labelling Conditions] • System ID:GSM900 DCS1800 • Sector ID: Ranges from S1 to S4 • 1/2 means the fiber quantity in one sector [Labelling Conditions]

Page 46: zte mobilink bts swap

Label of Main DC Cable

[Label Format] PWR [Labelling Conditions] • Main DC cable include DC power cable of

BS8800, ILP ,DCPD4 and so on.

Page 47: zte mobilink bts swap

Label of Outdoor LPB (OLP)

[Label Format] Sector ID-PWR [Labeling Conditions] • Sector ID: Ranges from S1 to S4 • PWR means power.

Page 48: zte mobilink bts swap

Label of GPS feeder

Page 49: zte mobilink bts swap

Label of Alarm Cable

Page 50: zte mobilink bts swap

Label of MW IF Cable [Label Format] MU1-ODU1 [Labelling Conditions] • If IDU more than one, A red remark used to

identify them

Page 51: zte mobilink bts swap

Label of Grounding Cable

Page 52: zte mobilink bts swap

THE ENDHave a Good DAY